(some) mdi engineering aspects at ilc & clic...the first important measure will be to choose a...

67
(Some) MDI Engineering Aspects at ILC & CLIC A. Hervé / ETH-Zürich Together with ILC and CLIC MDI Groups CLIC Meeting-14 January 2011

Upload: others

Post on 13-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

(Some) MDI Engineering Aspects

at ILC & CLIC

A. Hervé / ETH-ZürichTogether with ILC and CLIC MDI Groups

CLIC Meeting-14 January 2011

Alain Hervé, CLIC-Meeting, 14 January 2011 2

This is a slightly updated version

of the talk presented at

IWLC10

on Friday 22 Oct. 2010

3

Content of the talk

I will not try to cover all aspects of MDI, please refer

to talks of the working group chairmen:

• Andrei Seryi (John Adams Institute) for ILC.

• Lau Gatignon (CERN) for CLIC

I will introduce:

• the main features of MDI for ILC,

• then look at CLIC, pointing out what is different

and why,

• not forgetting at the end the challenges of the

Push-Pull.

Alain Hervé, CLIC-Meeting, 14 January 2011

4

MDI at a LC is governed by

• A small L* (3.5 m) to maximize luminosity, and thus

the last machine elements penetrate inside the

detector.

• A small size of the beams (nm level), requiring

extreme stability of the BDS.

• An active pre-alignment system is needed to

correct for slow drifts

• A beam fast Feed Back system is also mandatory

to correct movements at higher frequencies.

Alain Hervé, CLIC-Meeting, 14 January 2011

5

MDI @ ILC

Alain Hervé, CLIC-Meeting, 14 January 2011

6

SiD: QD0 penetrates inside the experiments

QD0QF

2 concepts

SiD and ILC

Retained after LoIs

7

• Position of the BDS elements and QD0 aligned at ± 10 μm rms

w.r.t ideal straight line.

For the last 500 meters on each side of IP

Pre-alignment system,

example of CLIC (H. Maynaud et al. /CERN)

Alain Hervé, CLIC-Meeting, 14 January 2011

(active) prealignment

system is mandatory

Philip Burrows

CLIC MDI Meeting 6/11/09

8

Intra-train feedback system

• Last line of defence against relative beam misalignment

• BPM measures vertical deviation of outgoing beam

• Fast kicker correct vertical position of beam incoming to IR

(JAI/Oxford, Valencia, CERN, DESY, KEK, SLAC)

QD0 in ILC (Bret Parker / BNL)Very involved coil package at 1.8 K

⇐ Field on axis

is reduced and

luminosity is

recovered

DiD and anti DiD at ILC(Dipole Integrated Detector)

➽ not adopted at CLIC

Alain Hervé, CLIC08 Workshop, 16 October 2008 10

DiD on-axis field

ILC typical beam line components

IP

1st conical tube

DN150CF flange

Ion pump integrated

in beam pipe

Pre-pumping port

+ gauges

Special gate valve

BPM

QD0 Cryostat, Coils at 1.8K

Kicker

Valves for

Push-Pull

Common break point at

9m from IP

Bellows(ILD)

Alain Hervé, CLIC-Meeting, 14 January 2011

QF

QD0 @ 1.8 K

Cam/support

SiD supports the QD0 from the endcap door

using a cam/support system

BPM

Kicker

IP

This is based on SLD Experience

Alain Hervé, CLIC-Meeting, 14 January 2011

QD0 support

ILD: QDO supported from the tunnel wall(Matthieu Joré / LLR)

• Using 2 square tubes :

– Internal QD0 support tube

• Attached to machine tunnel

• Good coherency with machine vibrations and high natural frequency

– External FCals support tube

• Could be supported from pillar and tension rods

5 mm gap between

both supports

Machine concrete

Pillar

Tension rods

(from an idea of Hiroshi Yamaoka at KEK,

idea also used by CLIC detectors)

Alain Hervé, CLIC-Meeting, 14 January 2011

14

Vibration consideration for ILC

and influence of beam Feed-Back system(P. Burrows et al. / JAI)

• For ILC, the fast beam Feed Back system

developed at JAI is very efficient and can have a

reach of 300 nm.

• Thus the needed stability of the QD0 support is

around 50 nm or better.

• First vibration measurements in the CMS area have

shown that this is possible.

Alain Hervé, CLIC-Meeting, 14 January 2011

15

Vibration consideration from CMS

Geophones

Top 100 nm

Ground 5 nm

Measurements at KEK

on BELLE (Hiroshi

Yamaoka) have also

shown a degradation

of performances when

moving up along the

yoke.

➽ 50 nm at beam

level look reasonable.

Vibrations on ground and top of CMS

central barrel YB0 in ‘Quiet

experimental area’ end of 2009

(Artoos, Guinchard et al.)

Alain Hervé, CLIC-Meeting, 14 January 2011

16

MDI @ CLIC

Alain Hervé, CLIC-Meeting, 14 January 2011

17

Introduction - II

• CLIC MDI studies have benefitted of a jump-start

due to the studies done for ILC.

• However two parameters are really different and

make the problem more difficult:

• The vertical size of the beam is smaller, typically

1 nm compared to 5 nm in ILC

• The beam time structure is unfavorable and the

reach of the beam Feed-Back system is reduced.

Alain Hervé, CLIC-Meeting, 14 January 2011

IP-Feed-Back Systems (Phil Burrows and J. Resta-Lopez / JAI)

ILC (500 GeV)

• Beam time structure: – Train repetition rate: 5 Hz

– Bunch separation: 369.2 ns

– Train length: 969.15 µs

• Intra-train (allows bunch-to-bunch correction)

• Digital FB processor (allows FPGA programming)

CLIC (3 TeV)

• Beam time structure:– Train repetition rate: 50 Hz

– Bunch separation: 0.5 ns

– Train length: 0.156 µs

• Intra-train (but not bunch-to-bunch)

• All-analogue FB processor

For CLIC, intra-train FB corrections at the IP are especially

challenging

• bunch separation about 740 times smaller than for the ILC

• bunch train length about 6200 times shorter than for the ILC

Alain Hervé, CLIC-Meeting, 14 January 2011

19

Stability of the QD0 mechanical support

• If we move backward in the CLIC stabilization budget:

• Ultimate stabilization to obtained the luminosity is

0.15 nm @ 4Hz at IP.

• Thus, before the intra-train Fast Feed-Back

system, a stability of 0.5 nm is needed.

• Thus, before the active stabilization system,

5 nm or less are needed for the stability of the QD0

mechanical support.

This is a factor 10 w.r.t. ILC!

Alain Hervé, CLIC-Meeting, 14 January 2011

20

To obtain the utmost beam stability

for CLIC additional efforts are needed.

(In addition to the active pre-alignment and

intra-train Fast Feed-Back systems)

Alain Hervé, CLIC-Meeting, 14 January 2011

1-Use a permanent magnet QD0(Michele Modena et al. / CERN)

21

This is to suppress vibrations due to cooling and thin

suspensions of the cold mass. The use of Permendur

imposes to have H ≈ 0.

Thus a non negligible anti-

solenoid coil, fixed on the

endcap, has to be foreseen

outside the support tube.

This will also reduce the field

seen by the beam and recover

luminosity loss

⇐ (Barbara Dalena).

Alain Hervé, CLIC-Meeting, 14 January 2011

22

2-Decouple the QD0 support

from the experiment

This has been shown previously: the most stable

element is the tunnel floor and not the yoke of the

experiment.

Top 100 nm

Ground 5 nm

⇐Measurements in

CMS area

end of 2009.

Alain Hervé, CLIC-Meeting, 14 January 2011

23

3-Minimize the length of the support tube

• It is clear that the length of the support tube must

be minimized as flexion is involved.

• This can be obtained by abandoning the opening

on IP.

• Anyway not much maintenance can be done on IP,

and if the Push-Pull operation is working well, it is

more efficient to repair in the garage area.

Alain Hervé, CLIC-Meeting, 14 January 2011

24

Minimize the length of the support tube

Platform

Pacman -> Pacrings

End of

TunnelEnd of

Tunnel

Alain Hervé, CLIC-Meeting, 14 January 2011

View of the shielding Packring arrangement

Alain Hervé, CLIC08 Workshop, 16 October 2008 25

Clearly CLIC experiments

must have the same length!

Alain Hervé, CLIC08 Workshop, 16 October 2008 26

This has been achieved for CLIC_SiD

and CLIC_ILD at the cost of some active

coils in CLIC_ILD pacrings

7 May 2010 H. Gerwig - 13th MDI 27

HallExperiment 1

HallExperiment 2

Transfer tunnel with IP

AlignmentTunnel

Discussed withJ. Osborne & M. Gastal

Excavated volume is less than for a standard hall

Flat walls on tunnel sides

19/10/2010 27

This governs the proposal

for CLIC Experimental Area(H. Gerwig / CERN)

28

• The idea is to decouple and stabilize the support of

QD0 and QF1.

• It must be connected to the active pre-alignment

system to correct or low freq. (< 1 Hz) movements.

4-Support the QD0 and QF1

from a Pre-Isolator(Andrea Gaddi et al. / CERN)

Alain Hervé, CLIC-Meeting, 14 January 2011

Pre-isolator @ CLIC

QD0 QF1

Pre-isolator slab

(can be extracted as one

complete unit) through the

experimental area

Accelerator

tunnel

IP

Alain Hervé, CLIC-Meeting, 14 January 2011

Pre-isolator @ CLIC

Alain Hervé, CLIC08 Workshop, 16 October 2008 30

Low freq. air

springs

5-Adopt the solution of a double tube

Thank You !

31Alain Hervé, CLIC-Meeting, 14 January 2011

(Timing!)

The outer support-tube allows access

Alain Hervé, CLIC08 Workshop, 16 October 2008 32

Double support-Tube and anti-Solenoid

Alain Hervé, CLIC08 Workshop, 16 October 2008 33

Detail supporting of double Support-Tube

Alain Hervé, CLIC08 Workshop, 16 October 2008 34

35

➽ It has to be implemented inside the limited space and

environment of the support tube, more integration effort is

needed.

(Andrea Jeremie et al. Annecy)

Proof of principle has been obtained in the lab.

6-Use a sophisticated active

Stabilization System

Alain Hervé, CLIC-Meeting, 14 January 2011

Present cross section of Support-Tube

Alain Hervé, CLIC08 Workshop, 16 October 2008 36

Active stabilization system

Clearly more integration work

will be needed inside the support

tube.

Support QD0 coils from

outer Support-Tube

Outer

Support-

Tube Criscrossed inner Support-

Tube

QD0

37

Obtaining the utmost beam stability

All these efforts will pay but it

must not be forgotten that:

➽ The first important measure will be to choose a

‘quiet’ site with respect to cultural noise and

design a ‘quiet’ area with respect to technical

noise.

Alain Hervé, CLIC-Meeting, 14 January 2011

38

Push-Pull Considerations

Alain Hervé, CLIC-Meeting, 14 January 2011

39

Reminder

• The push-pull project, to exchange quickly two

experiments on IP, is a very ambitious one.

• In size of loads to be moved > 10’000 tons, number

of movements, 6 per year ➽ 180 over 15 years.

• It is demanding considering: environment, final

precision, and time constraints, (full exchange in less

than three or four days) including precise

realignment.

• But, one must always be able to extract sideway an

experiment for maintenance every year (like Opal,

Delphi, Aleph… on LEP).

• Thus the Push-Pull project is just a more

demanding normal maintenance displacement

scenario!Alain Hervé, CLIC-Meeting, 14 January 2011

detector

B

may be

accessible

during run

accessible

during run Platform for electronic

and services. Shielded.

Moves with detector.

Isolate vibrations.

Starting point (~2006) push-pull for ILC

Proposal by A. SeryiProposal by A. Seryi

first Power Pointfirst Power Point

Proposal by A. SeryiProposal by A. Seryi

first Power Pointfirst Power Point

detector

A

Alain Hervé, CLIC08 Workshop, 16 October 2008 41

SiD and ILD with or without a platform ?

( M. Oriunno / SLAC )

As the idea of push-pull has been

introduced during the LoI process, ILD

has adopted a platform, however SiD

has chosen to move directly on the

ground.

Presently the two solutions are not

compatible, and discussion are going on

and a work plan has been adopted to

converge fairly quickly.

With

Without

Alain Hervé, CLIC-Meeting, 14 January 2011

42

Push-Pull for CLIC detectors

H. Gerwig / A Gaddi19/10/2010 42

CLIC has chosen to use

platforms from the start

This governs the geometry of exp area

Alain Hervé, CLIC08 Workshop, 16 October 2008 43

First concept of experimental area

Alain Hervé, CLIC08 Workshop, 16 October 2008 44

45

Platform/ Airpad consideration

• The platform solution shows all its advantages

when used in conjunction with airpads (as opposed

to rollers), because airpads:

• have no preferred direction of movement.

• allow an easy repair of the rail / support system,

removing the high risk of staying blocked.

• allow a fast and safe positioning of the

experiment on beam.

Alain Hervé, CLIC-Meeting, 14 January 2011

Alain Hervé, CLIC08 Workshop, 16 October 2008 46

Load will arrive off-center and off-axis

Alain Hervé, CLIC-Meeting, 14 January 2011

Alain Hervé, CLIC08 Workshop, 16 October 2008 47

2D movement and a rotation are needed

this is very difficult with rollers

Alain Hervé, CLIC-Meeting, 14 January 2011

Alain Hervé, CLIC08 Workshop, 16 October 2008 48

With Airpads a simple positive indexing

mechanism is possible giving ≈mm precision

Alain Hervé, CLIC-Meeting, 14 January 2011

Alain Hervé, CLIC08 Workshop, 16 October 2008 49

The final precision could be +-1 mm

and +-0.1 mrad.

Alain Hervé, CLIC-Meeting, 14 January 2011

50

Vertical adjustment

• Exchanging 10’000 ton experiments will induce a

settlement of the whole experimental zone and

adjacent machine tunnels.

• One can expect vertical movements in the

millimeter range that can take one month to recover.

• This kind of slow drift must also be taken care of by

the active pre-alignment system.

Alain Hervé, CLIC-Meeting, 14 January 2011

51

Moving towards a common solution

for the Push-Pull system

• ILD is making studies to justify that it cannot move

without a platform.

• At the same time, it must be shown that the use of

a platform is not detrimental to SiD that has chosen

to support the QD0s from the endcap doors.

•CLIC must also demonstrate that the lay-out of the

experimental area will allow to meet the

specification.

Alain Hervé, CLIC-Meeting, 14 January 2011

52

Vibration consideration at ILC

moving towards a common solution

• The priority is to develop credible simulation tools,

and Marco Oriunno at SLAC for SiD and Hitoshi

Yamaoka at KEK for ILD have started extensive

studies.

• However, one must make sure that the results of

simulations are in agreement with reality and

extensive benchmarking is required.

Alain Hervé, CLIC-Meeting, 14 January 2011

53

1st Mode, 2.38 Hz 2nd Mode, 5.15 Hz 3rd Mode, 5.45 Hz

4th Mode, 6.53 Hz 5th Mode, 10.42 Hz 6th Mode, 13.7 Hz

Vertical motion

SiD Free Vibration Mode (example)

M. Oriunno / SLAC

54

Response amplitude (Comparison of computations and measurements)

QCS-t

QCS-s

Coil-t

Coil-s

Measurements@QCS-sCalculation: damp=0.5%

MeasurementCalculation:

H. Yamaoka / KEK

55

Vibration considerations

connected to the platform

• The CMS plug is a good example of what can be a

Push-Pull platform, it has the necessary rigidity.

• It can be used to benchmark the simulation

programs.

• First vibration measurements have been carried out

end of 2009.

• End Oct. a new measurement campaign has been

performed (K. Artoos, M. Guinchard et al.) for SiD.

Alain Hervé, CLIC-Meeting, 14 January 2011

A. Hervé - 12 July 2007 ILC-IRENG07-0712-4345 56

The 2000-ton CMS Plug has been used for

the Heavy Lifting operation

Plug

1

CMS plugCMS plug

Alain Hervé, CLIC08 Workshop, 16 October 2008 57

The CMS Plug finished looks neat!

20 m

Alain Hervé, CLIC08 Workshop, 16 October 2008 58

Steel reinforcement of CMS Plug

➽ Clearly models need benchmarking to evaluate

damping coefficient and Young’s modulus

59

Vibration consideration

connected to the platform

• The study of the CMS plug is a good example of

work that is in interest of both ILC and CLIC

(ILC is interested in the platform solution and CLIC

has directly engaged on using two platforms for the

Push-Pull operation.)

Alain Hervé, CLIC-Meeting, 14 January 2011

60

Vibration and movements

connected to civil engineering

• LHC experimental areas for ATLAS and CMS are a

good example of how such systems behave in the

CERN geology.

• However, the level of the requirements for CLIC

necessitates to re-examine the situation of general

movements, ground vibration and micro-seisms.

• A first discussion with tunneling experts has been

organized by J. Osborne mid February.

Alain Hervé, CLIC-Meeting, 14 January 2011

61John Osborne : GS-SE

•At the Linear Collider Workshop in Oct 2009 in Geneva, it was agreed in

the MDI subgroup that further in-depth civil engineering studies should be

undertaken to study the feasibility of the proposed detector movement

system and experimental area layout

•As such, a one day workshop is being set-up at CERN to see how best

this issue can be tackled on 16th February 2011

•An expert tunneling firm from London (ARUP) are participating in this first

meeting

•Goals of the meeting :

• Review the experience learnt from LHC detector assembly,

installation and operational movements

• Review existing data on ground movements / stability / vibration

issues

• Plan how best to verify the feasibility of the concrete platform

concept and potential ground movements that could be induced by

detector exchange with push-pull operation

• Share knowledge with ILC

Civil Engineering Studies for CLIC Experimental

Layout

62

Conclusions

Alain Hervé, CLIC-Meeting, 14 January 2011

63

Conclusions-I

• To maximize LC luminosity the last focusing element

must penetrate inside the experiment to achieve a low L*.

• The small size of the beams imposes to use an active

pre-alignment system against slow drifts.

• In addition a beam Fast Feed Back system is needed to

correct for movements at higher frequencies.

• This is sufficient for ILC that benefits from a favorable

beam time structure.

• For CLIC that has smaller beam size and an unfavorable

beam time structure, supplementary efforts are needed.

Alain Hervé, CLIC-Meeting, 14 January 2011

64

Conclusions-II

• The Push-Pull system is a very demanding project and

there is no example to refer to.

• CLIC has adopted a platform to move each experiment.

• ILC concepts are in discussion to adopt a common

solution and a working plan has been drafted.

• It is important to make sure that the platform solution

does not worsen the stability of the QD0s that, in SiD, are

supported from the endcap doors.

Alain Hervé, CLIC-Meeting, 14 January 2011

65

Conclusions-III

• The CMS plug is a good example of what a platform

could be.

• It can be used to benchmark simulation models.

• Further vibration measurements on the CMS plug will be

needed.

• These measurements are also in the interest of the

CLIC project.

• The studies of platform and associated vibrations could

be part of the ILC/CLIC Collaboration.

Alain Hervé, CLIC-Meeting, 14 January 2011

66

Conclusions-IV

• The MDI studies are now mature for both ILC and CLIC.

• More detailed studies and tests are needed for CLIC due

to the level of stability required for the QD0.

• More studies are needed from the civil engineering point

of view to ascertain slow movements and vibrations (starts

with meeting mid-Feb.).

• The requirements are different enough that (apart maybe

the Push-Pull system proper) solutions adopted by ILC

and CLIC, although similar, are fairly different and are

likely to stay different.

Alain Hervé, CLIC-Meeting, 14 January 2011

Thank You !

67Alain Hervé, CLIC-Meeting, 14 January 2011