solutions for consolidation 2 - corrected
DESCRIPTION
Soil Mechanics, ConsolidationTRANSCRIPT
-
NATIONAL UNIVERSITY OF SINGAPORE
DEPARTMENT OF CIVIL ENGINEERING
CE2112 SOLUTIONS FOR CONSOLIDATION II
1. An oil tank, 10 m high and 50 m diameter, is to be constructed on a site where 1 m of gravel
overlies 4 m of soft clay. Below the clay is dense sand. In the initial filling and proof-loading
of the tank, water is to be used. Filling will progress in weekly increments, and the
increments must be of such a magnitude to ensure that the mean excess pore water pressures
in the soft clay does not exceed 60 kPa. Superposition may be assumed valid. Given that cv =
52 m2/year, calculate the sequence of weekly water levels for the test loading. What factors
could limit the validity of the analysis?
Solution:
Soft clay layer has 2-way drainage, drainage path H = 2m.
Cv = 52m2/year = 1m2/week
Assuming unit weight of water w = 10kN/m3
Oil tank
Permeable Gravel
Soft Clay
Permeable dense sand
Cv = 52m2/yr 4m
1m
-
Since allowable excess pore pressure = 60kPa, initial allowable loading = 60kPa => 6m of water.
After the 1st week, T = 2H
tcv = 22
1*1= 0.25 => T = 0.5
Initial excess pore pressure profile is rectangular. Hence use central curve,
U = 0.56 or 56% => 1 - U = 0.44 or 44%
i.e. 44% of the initial excess pore pressure still remains, on average.
=> uave = 0.44 * 60 = 26.4kPa
Thus, on average, we can add another 60 26.4 = 33.6kPa 3.36m of water.
Just after the 2nd loading of 33.6kPa, we expect the resultant excess pore pressure profile to look
something like this:
33.6kPa
Initial
excess pore
pressure
Excess pore
pressure
just before
2nd
loading
Excess pore
pressure
just before
2nd
loading
Excess pore
pressure
due to 2nd
loading
60kPa
A B
After the 2nd week: There is no solution for the initial excess pore pressure shown in B above.
Hence, we need to split the excess pore pressure up into 2 portion, one arising from the initial
-
loading of 60kPa (i.e. the area under the curved portion) and the other arising from the 2nd
loading (after 1st week) (i.e. the area under the rectangular portion).
Excess pore pressure from the 1st loading: T = 2H
tcv = 22
2*1= 0.5 => T = 0.7071
=> U = 0.76 or 76% => 1 - U = 0.24 or 24%
i.e. 24% of the excess pore pressure from the first loading still remains.
uaveA = 0.24 * 60kPa = 14.4kPa
Excess pore pressure from the 2nd loading: T = 2H
tcv = 22
1*1= 0.25 => T = 0.5
U = 0.56 or 56% => 1 - U = 0.44 or 44%
=> uaveB = 0.44 * 33.6 = 14.8kPa
Total average excess pore pressure still remaining = 14.4 + 14.8kPa = 29.2kPa
Hence, we can add another 60 29.2 = 30.8kPa or 3.08m of water => up to 10m.
2. The diagram below shows a 6 m deep excavation which is to be made in a 20 m thick layer of
residual soil overlying sand which in turn overlies bedrock. The permeabilities are (i) residual
soil: 10-8 m/s and (ii) sand: 10-4 m/s. The compression index Cc for the residual soil is 0.05
and its unit weight is 19 kN/m3. The excavation is to be made over a relatively short duration
of about 20 days but it is to be left open for another 120 days. The excavation was effectively
dewatered. Taking the elevation datum to be at the bottom of the excavation, the hydraulic
head at the base of the excavation is 0m. During the excavation, groundwater recharge was
undertaken via shallow sub-soil drains near the ground surface which has the effect of
maintaining the phreatic surface virtually at the ground surface, thus maintaining a hydraulic
head of 6m at the retained soil surface. Seepage analysis shows that, in the long-term, after
steady-state seepage has established itself, the streamlines in the vicinity of the retaining wall
(both in the retained soil and in the excavation) are approximately vertical straight lines (i.e.
one-dimensional seepage flow) and that the hydraulic head within the sand layer is 2.5m.
-
20
m
6m
6m
Residual soil:
= 19kN/m3
k = 10-8
m/sResidual
soil
Sand Layer (highly permeable)
Hydraulic head h = 0m
Hydraulic head h = 6m
Hydraulic head h = 2.5m
(a) Discuss qualitatively the transient ground response arising from the construction work,
with appropriate sketches of the initial, short-term, long-term and transient (i.e. interim)
profiles of total and effective vertical stresses as well as pore pressures.
(b) By making appropriate simplifying assumptions, estimate
(i) the final settlement at the ground surface if the excavation is left open for a long time,
(ii) the ground settlement after 120 days.
Solution:
(a) Initial state, before excavation: Groundwater is in hydrostatic equilibrium.
-
s u s 0 0 0 gwt
380kPa 200kPa 180kPa
At ground surface: = 0 & u = 0 => = 0
At the base of the residual soil layer:
= 20 * 19 kPa = 380kPa
u = 20 * 10 kPa = 200kPa
= 380 200 = 180kPa
Short-term i.e. just after excavation:
Inside the excavation, at the excavation level:
= 0, = 20
180*6= 54kPa (Effective stress cannot changed in the short-term; hence
we can just use the initial effective stress at 6m depth)
u = 0 54 = -54kPa
At the base of the residual soil layer:
= 14 * 19 kPa = 266kPa
and = 180kPa (i.e. unchanged)
u = = 266 180 = 86kPa
Inside the retained soil, , and therefore u remain unchanged.
Hydraulic head h = 2.5m in the sand layer and the base of the residual soil layer
Elevation z = -14m
In the long term, in the sand layer and base of the residual soil,
-
u = w(h z) = 10*(2.5 (-14)) = 165kPa
Inside the excavation, at the base of the residual soil,
= 266kPa (same as short-term)
= 266 165 = 101kPa
-
s u s
380 164.7 200 180 215.3
s u s
266 86 64.7 101.3 180
165 165
-
In the retained soil, at the ground surface, , u and remain unchanged.
At the base of the residual soil layer,
= 380kPa (no change in total stress since there is no loading)
u = 165kPa
= 380 165 = 215kPa
Notice that there is
(i) a general increase in effective stress in the retained soil in the long-term; this will lead to
settlement.
(ii) a general decrease in effective stress in the excavation area in the long-term, leading to heave
(or swelling) of the soil.
(c) Since the coefficient of volume change is not known, we need to use the compression index:
e = Cc
'
'lg
1
0
s
s
At the mid-depth of the retained soil,
0 = 90kPa (i.e. short-term)
1 = 107.5kPa (i.e. long-term)
e = 0.05
5.107
90lg = -3.858x10-3
Since no other information is given to allow us to find the in-situ value of void ratio, we need to use
the bulk weight to give an estimate
=
e
eGsw
1
Assuming Gs = 2.65,
1.9 = e
e
1
65.2 => in-situ e = 0.833
mv = '1 s
e
e=
905.107*833.110858.3 3
x= 1.203x10-4 /kPa or 120.3strains/kPa
cv = vwm
k
=
4
8
10203.1*10
10
xm2/s = 8.313x10-6m2/s
or 0.718m2/day
Caution! This is not an accurate way of determining cv. Wherever possible, cv should be measured.
Directly measured values are often more representative and reliable! We only do this because no
other information is available.
-
(i) = D
v udzm = mv*(area under excess pwp profile)
The initial excess pore pressure u can be obtained by considering the difference in the short-
and long-term pore pressure profiles, i.e.
u u
165 200 (200-165)
= 35kPa
Hence, excess pwp profile is triangular with maximum of 35kPa at the base of the soil layer.
Hence,
= 1.203x10-4* *35 * 20kPa = 0.042m or 42mm.
(ii) This is a double-drainage consolidation problem, so we should use the centre curve.
Drainage path D = 10m
t = 120days.
T = 210
120*718.0= 0.862 => T = 0.928
U = 0.91 from chart.
Alternatively, use the approximate formula 3T) - exp( -1 U41
32
= 0.862)*3 - exp( -1 41
32 = 0.936
120 = 0.936*42mm = 39.3mm
-
3. A seabed soil profile consists 5 m of soft, normally consolidated marine clay underlain by dense
sand. The seabed is at a depth of 4 m below mean sea level (msl). It is required to reclaim this site
to a height of 2m above msl with sand (also known as hydraulic fill). The properties of the soil
are as follows:
Marine clay: compression index = 0.7
swelling index = 0.2
coefficient of consolidation = 2 m2/year
in-situ water content at 4 m below seabed level = 70%
bulk unit weight = 16 kN/m3
Gs = 2.68
Hydraulic fill: bulk unit weight = 18 kN/m3 (below waterline)
15 kN/m3 (above waterline)
(a) Estimate the final settlement of the reclaimed land arising from consolidation of the soft clay.
(b) How long will it take for 90% of this settlement to occur?
(c) It is desired to enforce this 90% settlement within a period of 2 years by placing an additional
surcharge consisting of hydraulic fill on top of the final reclamation level. Estimate what
height of surcharge will be required to achieve this?
Solution:
(a) Additional overburden stress from landfill = 2*15 + 4*(18-10) kPa = 62kPa
Coefficient of volume change is not given, so we need to use the compression index.
4m
5m
2m
Fill surface after reclamation
Sea level
Sand fill
Soft clay
Dense sand (highly permeable)
-
Consider mid-depth of soft clay layer:
Initially, 0 = 2.5 * (16 10) = 15kPa
Finally, after a long-term (after consolidation),
= 15 + 62 = 77kPa
Hence, change in void ratio e = Cc log
15
77 = 0.7 * 0.71 = 0.497
We do not know the initial void ratio, so we need to deduce it from indirectly,
= 16 = e
e
1
)68.2(*10 => e ~1.8
We can also deduce e from water content assuming fully saturation,
e = Gsw = 2.68 * 0.7 = 1.876
Hence, the two estimates agree reasonably well and we can adopt e = 1.876 (usually more reliable
to estimate e from water content than bulk unit weight).
Equivalent mv = '1 s
e
e=
62*876.2
497.0/kPa = 2.787x10-3/kPa
Initial excess pore pressure profile is rectangular, hence
= udzmv = 2.787x10-3* 62 * 5m = 0.86m or 86cm.
(b) U = 0.9 => T = 0.92 => T = 0.846
2H
tcv = 0.846 => t = 2
5.2*846.0 2years = 2.65years
(c) Absolute settlement corresponding to 90% consolidation = 0.9 * 86cm = 77.4cm
For t = 2years, T = 2H
tcv = 25.2
2*2 = 0.64 = T = 0.8 => U = 0.83 or 83%.
If 83% consolidation under surcharge corresponds to 77.486cm,
then full settlement under surcharge = 83.0
8677.4/0.83 = 0.931.036m or 9301036mm
Let be the required effective overburden stress of the surcharge.
Then 2.787x10-3 * 5 = 0.931.036 => = 66.7kPa74.3kPa ~ 75kPa
Hence, additional surcharge on top of the landfill is 66.775 62 = 413kPa
or 413/15m = 0.2687m of sand i.e. 2687cm of sand.
4. The figure below shows a site underlain by two layers of soft clay. In order to enforce early
settlement of the ground, a 5 m thick layer of loose sand (unit weight = 14 kN/m3 ) is placed on
-
top of the ground. Estimate how long it will take for the ground surface to settle 50 mm. The
groundwater table is at the ground surface.
Properties:
upper soft soil layer: cv = 0.5 m2/year
k = 10-9 m/s
= 15 kN/m3
sand seam: k = 10-3 m/s
= 17 kN/m3
lower soft soil layer: cv = 1.5 m2/year
k = 10-9 m/s
= 17 kN/m3
Solution:
mv = vwc
k
=
5.0*10
24*365*3600*10 9m2/kN = 6.31x10-3m2/kN
Surcharge = 14 * 5 = 70kPa
Final compression = 70 * 8 * 6.31x10-3m = 3.534m
Lower soil layer,
mv = vwc
k
=
5.1*10
24*365*3600*10 9m2/kN = 2.10x10-3m2/kN
Final compression = 70 * 8 * 2.1x10-3m = 1.176
Estimate settlement after 1 week: t = 7days
Ground surface
Upper soft soil layer 8 m
Sand seam 1 m
Lower soft soil layer 8 m
Bedrock (impermeable)
-
Upper soil layer: T = 2H
tcv = 16*365
7*5.0= 5.993x10-4
T = 0.02448 which is too small to read from the graph.
Using the approximate formula instead:
4T
U =
-45.993x10*4 = 0.0276
Compression after 7 days = 0.0276*3.534m = 97.6mm > 50mm
Hence, 50mm is likely to represent very small degree of consolidation. Hence we can use the
approximate relation to solve for the real time.
For the upper soil layer:
4T U =
16*365*
0.5t*4
= 0.0104t =
u
tu
Where the subscript u refers to the upper soil layer.
Hence, tu = 0.0104ut
Where u = 3.534m.
tu = 0.0369t
For the lower soil layer:
4T U =
64*365*
1.5t*4
= 9.253x10-3 t =
l
tl
Where the subscript l refers to the lower soil layer.
Hence, tl = 9.253x10-3lt
Where l = 1.176m.
Hence, tl = 0.01088t
Hence, total settlement at time t = t = tu + tl = (0.0369+0.01088) t
=0.0478t
For t = 0.05m, => t ~1.1days i.e. it takes ~1.1days to reach 50mm settlement.