solar and wind sector development strategy solar … · solar and wind sector development strategy...
TRANSCRIPT
Solar and Wind Sector Development StrategySolar and Wind Sector Development StrategySolar Energy Technology Roadmap 18 June 2012Solar Energy Technology Roadmap 18 June 2012
Green Industries, Department of Trade and Industry
Content
• Challenges
• Solar and wind strategy
• Local Content Requirements
• Window 2 Bid Summary• Window 2 Bid Summary
• Way forward
South Africa is in a difficult position
Electricity demand may reach 78 000 MW with economic growth
86% of power generation capacity from coal87% of primary energy supply from fossil fuels
2006 data, Source: DoE 2011 data, Source: Eskom
95% of crude oil requirement is imported
Source: Eskom
Demand @ 4% if GDP @ 6%
Demand @ 2.3 % if GDP @ 4%
Manufacturing employment and manufacturing share of GDP
1,100,000
1,150,000
1,200,000
1,250,000
1,300,000
1,350,000
13.5
14.0
14.5
15.0
15.5
16.0
16.5
17.0
17.5
44
1,050,000
Sour
13.5
So
urc
e
A large renewable energy programme can put electricity on the
grid, support industrialisation and jobs and address South Africa’s climate
commitments
Motivating Factors
• Addressing the country’s energy needs.
• Meeting GHG emission reduction commitments (climate
change).
• Very good solar and wind resources.
• Existing industrial capabilities in a range of relevant areas, e.g.
engineering, metal fabrication, composites, etc.engineering, metal fabrication, composites, etc.
• Growing number of component suppliers into renewable
energy value chains.
• Job creation.
2011 Renewable Energy Year
• Early balanced scenario had no solar commitment.
• Revised balanced scenario had 400 MW solar commitment - 11,4 GW renewables.
• Policy adjusted Integrated Resource Plan (IRP) 8 400 MW solar PV and 1 000 MW CSP and 8 400 MW wind.
• December 2011 announcement of 1st 28 projects• December 2011 announcement of 1st 28 projects
(1 415 MW).
• May 2012 – another 19 projects (1 044 MW).
• August 2012 – round 3.
KEY ACTION PROGRAMMES
• Market creation and Independent Power Producer (IPP) facilitation – ensures investor certainty. • IRP and Renewable Energy Independent Power Producer Procurement
Programme (REIPPP).
• Local manufacturing and industry upgrading incentives: Secure economic opportunities across value chains and develop and maintain local skills.• Manufacturing Incentives – Manufacturing Competiveness • Manufacturing Incentives – Manufacturing Competiveness
Enhancement Program (MCEP), etc.
• http://www.thedti.gov.za/financial_assistance/financial_assistance.jsp
• Renewable energy finance.• IDC, SARi and NT.
KEY ACTION PROGRAMMES
• Development and upgrading of technical and physical infrastructure: • Standards for wind turbines developed.
• Testing facilities investigation.
• Possible standards for solar to be investigated.
• Trade and investment support and facilitation:• ITAC tariff reviews. • ITAC tariff reviews.
• TISA investment facilitation and export promotion.
• Research, demonstration and skills development: Support focused and coherent approach to Research and Development and skills development.• Support DST and DHE initiatives.
KEY ACTION PROGRAMMES
• Minimum levels and targets for local content
required to participate in the REIPPP.
• Review annually and increase targets to optimum
levels.
Local Content RequirementsLocal Content
Technology First Bid
Submission Date
Second Bid
Submission Date
Third Bid
Submission Date
Current
Threshold
Current Target
Threshold
Target Threshold Target
Onshore Wind
25% 45% 25% 60% 40% 65%
Solar Photovoltaic
35% 50% 35% 60% 45% 65%
Solar CSP Without Storage
35% 50% 35% 60% 45% 65%
Storage
CSP with
storage
25% 45% 25% 60% 40% 65%
Biomass 25% 45% 25% 60% 40% 65%
Biogas 25% 45% 25% 60% 40% 65%
Landfill gas 25% 45% 25% 60% 40% 65%
Small scale
hydro
25% 45% 25% 60% 40% 65%
25% 45% 25% 60% 40% 65%
Emerging issues
• Request for Proposals (RFP) for round 3 will be amended to incorporate briefing notes, etc.
• Other issues:
• Clarification of local content issues (definition and its application).• SABS standard – SATS 1286:2011.
• Investigate “deeming” of certain components.
• Split between natural localisation and new industries – equipment.
Local content measurement and verification.Local content measurement and verification.
– Clear commitment required for long term plan; will DoE stick to IRP? Pace of roll out?
– Determine optimum level of local content: • Wind Industry Roadmap.
• Economic impact of localisation.
• Capacity and competitiveness of local suppliers.
Technology: Onshore Wind
Component Project
Component
Cost
Percentage of
total project
cost
Local Content Committed
Equipment Balance of Plant
Wind turbine blades R15 000,00 15% 5%
Nacelle R30 000,00 30% 0%
Towers R10 000,00 10% 5%
Transport R8 000,00 8% 5%
Civil works R12 000,00 12% 5%
Electrical R6 000,00 6% 6%
Erection costs R5 000,00 5% 5%
Spares and tools R2 000,00 2% 2%
Total EPC Costs R88 000,00 88% 10% 23%
Project development:
Consultants
R3 000,00 3% 3%
Project development:
Operating assets
R2 000,00 2% 2%
Project development:
Administration
R1 000,00 1% 1%
Other costs: Contingencies R3 000,00 3% 3%
Other costs: Initial working
capital
R3 000,00 3% 3%
Total Non-EPC Costs R12 000,00 12% 12%
R100 000,00 100% 10% 35%
REIPPP Window 2 Bid Summary
Bids received Approved
bids
Value of
approved
projects
Value of
local;
content
committed
MW
Approv-
ed
Job creation
potential
79 (3 200
MW)
19
(due to
R28,1bn R11,8bn 1 044 7 059
construction
Only 51 met
the
requirements
capacity
limitation)
jobs and 328
operation jobs
Zooming in on solar photovoltaics(PV)
• 1450 MW total allocation for Solar photovoltaics (PV).
• 631,53 MW awarded in window 1.
• 818,.47 remained to be allocated in subsequent windows.
• 450 MW was allocated for window 2.
• 417,10MW was awarded in window 2 (9 projects).• 417,10MW was awarded in window 2 (9 projects).
• Total remaining allocation 401,37 MW for subsequent
windows.
• Average price in Window 1 – 275 c/KWh.
• Average price in Window 2 – 165c/KWh.
Zooming in on concentrated solar power (CSP)
• 200 MW total allocation for Solar PV.
• 150 MW awarded in window 1.
• 50 MW remained to be allocated in subsequent windows.
• 50 MW was allocated for window 2.
• 50 MW was awarded in window 2 (1 project).• 50 MW was awarded in window 2 (1 project).
• Total remaining allocation 0 MW, for subsequent windows.
• Average price in Window 1 – 268 c/KWh.
• Average price in Window 2 – 251 c/KWh.
Zooming in on the Wind Sector
• 1 850 MW total allocation for wind.
• 633,99 MW awarded in window 1.
• 1216.01 remained to be allocated in subsequent windows
• 650 MW was allocated for window 2.
• 562,60MW was awarded in window 2 (7 projects).• 562,60MW was awarded in window 2 (7 projects).
1. Total remaining allocation 653,41 MW for subsequent windows.
• Average price in Window 1 – 114 c/KWh.
• Average price in Window 2 – 89c/KWh.
Summary of MW allocation within the REIPPP
Technology MW
allocation
per
determin-
ation
MW
allocated in
the 1st bid
submission
round
MW
allocated in
the 2nd bid
submission
round
MW
awarded in
2nd
submission
round
Remaining
MW to be
allocated in
the next
rounds
Onshore
wind
1 850 633,99 650 562,60 653,41
Solar PV 1 450 631,53 450 417,10 401,37Solar PV 1 450 631,53 450 417,10 401,37
CSP 200 150 50 50 0
Biomass 12,5 0 12,5 0 12,5
Biogas 12,5 0 12,5 0 12,5
Landfill gas 25 0 25 0 25
Small hydro 75 0 75 14,3 607
Totals 3 625 1 415,52 1 275 1 044 1 165,48
Way Forward
• Incorporation of the SABS standard (SATS
1286:2011) in the revised RFP.
• Finalising the decisions on the deemed levels
of local content.
• Communication of the ‘clarified local content • Communication of the ‘clarified local content
rules’.
Thank you
Ntombifuthi Ntuli
Director: Renewable Energy
Department of Trade and IndustryDepartment of Trade and Industry
(012) 394 5699