Software Project Management

Manage Unavoidable Complexity

Avoid Unmanageable Complexity

Page 2: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Project Management: Some Statements

• If you fail to plan, you plan to fail

• Planning seems to increase luck

• Planning and estimating is a key competence for all software engineers

• If you don’t ask for risk information, you are asking for trouble

• Uncertainty must certainly not be stated in uncertain terms

• If you don’t actively attack risks, they will actively attack you

• Insanity: doing the same thing over and over again and expecting a different result

• The most important customer of the project plan is the project team itself

Page 3: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Content

• Project Management Basics

• Requirements Management

• Estimation

• Risk Management

• Project Tracking

– Milestone Trend Analysis

– Earned Value Chart

• Intergroup Co-ordination

• Peer Reviews

• Problem Report Tracking

Page 4: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Project Management Basics

Schedule - lead time - process - planning

Performance - specifications - derivatives - quality - etc.

Cost - human resources - equipment - etc.

If they are all fixed - Don’t appoint a project manager - Keep your fingers crossed

If they can be adjusted - Appoint a project manager - Set priorities

Page 5: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Project Management Processes

Monitor

Schedule

Cost

Performance

Control

PlanPlan

Project Data

Technology Skills Resources

PlanMeasured Data

ProductProject

Project Management

Project Implementation

ReadjustmentDeviations

Project Data

Page 6: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Two main phases in a software project

CommercialReq. Spec.

Functional Requirements Spec.Architecture / Top-Level Design

Software Development Plan

CS CRCD

Concept Confirmation Product Implementation

CS: Concept StartCD: Commitment Date (commitment to cost, schedule, performance)CR: Commercial Release

Page 7: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Content of a Software Development Plan

• Objectives, Scope (with reference to specification/architecture)• Deliverables• Activities (work breakdown structure with activities of max. 2 - 3

weeks)• Assumptions, Dependencies, Constraints (e.g., required hardware

models, intergroup dependencies)• Estimates (size, effort, schedule, computer resources, + justification)• Project Organization and Resource Allocation• Schedule of Activities (including project milestones)• Risk Management (identification, resolution, monitoring of risks)• If applicable, Subcontract Management Plan(s)• Progress reporting and communication structure• Software Development Environment (methods/tools/standards)• Project Quality Plan (inc. (intermediate) release acceptance criteria)• Software Configuration Management Plan

Page 8: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Requirements Management

• At the beginning of the project:– Collect commercial requirements as input

– Write Requirements Specification

– Review with all stakeholders

– Formally approve the specification and use it as baseline for the project activities

• What goes wrong?– Stakeholders don’t know what they want

– Not all stakeholders identified (e.g., service, factory) Many change requests during the project

• Possible solutions:– Work on requirements in a pre-project phase

– Rapid prototyping / incremental deliveries

– Formal change control

Page 9: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Estimation

• The only unforgivable failure is to not learn from past failures

• Project failures are mostly caused by inflated and unreasonable expectations

• Definitions of Estimate:Default

Prediction that meets the enforced deadline

AlternativeMost optimistic prediction that has a non-zero

probability of coming true

ProposedEqually likely to be above or below actual result

Page 10: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Causes of inaccurate estimates

• Frequent requests for changes

• Overlooked tasks

• User’s lack of understanding of their own requirements

• Insufficient communication and understanding between users and analysts

• Poor or imprecise problem definition

• Insufficient analysis when developing estimate

• Lack of co-ordination between involved disciplines

• Lack of an adequate methodology or guidelines for estimating (lack of historical data)

From:Nine Management Guidelines for Better Cost EstimatingAlbert L. Lederer and Jayesh PrasadCommunications of the ACM, Vol. 35, Nr. 2, Febr. 1992

Page 11: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

How to develop estimates? - 1• Immature (lack of) process: estimated date = target date• First improvement step: Size/effort estimates are made based on

expert opinions and the project team’s own historical data using Wide Band Delphi techniques

• Wide Band Delphi:– A facilitator is assigned, who organises an estimation meeting and

presents each expert with an estimation form.– The participants discuss estimation issues using their knowledge of the

requirements and the software architecture.– Each participant fills out the estimation form anonymously and hands it

over to the facilitator. The participants should not share their estimates.– The facilitator prepares and distributes a summary of the estimates with

the averages and standard deviations of all estimates.– The facilitator initiates a discussion between the experts focussing on

those points where their estimates varied widely.– After the discussion, the experts fill out the estimation forms, again

anonymously, and hand them over to the facilitator.The last 3 steps are repeated until consensus is reached.

Page 12: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

How to develop estimates? - 2

• What can go wrong with Wide Band Delphi?– No consensus has been reached when the plan must be presented

to management– Average of the individual estimates is taken as the final estimate– But: when the deviation remains high, you only know that you

have insufficient insight

• Next improvement step: Size/effort estimates are made using historical data from the Organization’s Software Process Database (with an explicit effort to use data from “similar” projects)– Use expert opinion to determine the “project type”– Use historical data from the same type of projects for productivity

figures (from “size” to “effort”)

Page 13: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Project type classification

Large-scale simulation

DOD management information system

Enterprise information systems

Telecom switch

DOD weapon system

National Air Traffic Control System

Commercial compiler

Embedded automotive application

Small scientific simulation

Business spreadsheet

Enterprise application (such as order entry)

Higher Technical Complexity Embedded, real-time, distributed, fault-tolerant High-performance, portable Unprecedented, architecture re-engineering

Lower Technical Complexity Straightforward automation, single thread Interactive performance, single platform Many precedent systems, application re-engineering

Higher Managerial Complexity Large scale (multi-site) Contractual Many stakeholders “Projects”

Lower Managerial Complexity Smaller scale Informal Few stakeholders “Products”

Average software project 5 to 10 people 10 to 12 months 3 to 5 external interfaces some unknowns, risks

From: Software Project Managementby Walker Royce, Addison-Wesley,1998, ISBN 81-7808-013-3

Page 14: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Risk Management

• List top-x of risks

• Add actions to prevent the risk from occurring• Add contingency plans (what to do when the risk materializes)

• Plan capacity for a certain percentage of the total effort required for contingency plans

Risk Probability P (1-5)

Effect Seriousness S (1-5)

Exposure P * S (1-25)

Risk Probability P (1-5)

Effect Seriousness S (1-5)

Exposure P * S (1-25)

Aversion action

Action holder

Contingency

Page 15: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Project Tracking

Dilbert by Scott Adams

Page 16: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Content of a Software Progress Report - 1

• Management Summary and Attention Points– short status overview– issues requiring immediate management action

• Project Dashboard– Milestone Trend Analysis– Earned Value Chart

• Project Status– major results achieved during the reporting period– major expectations for the coming period– complete list of deliverables/results– project definition changes (planned vs. actual number of change

requests)– main problems and issues

• Risk Management– identification of risks + probability + effects + seriousness– actions + action holders + action status

Page 17: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Content of a Software Progress Report - 2

• Project Staffing– planned versus actual staffing

• Budget– budgeted versus actual costs

• Problem Reports– % of test cases passed / failed / not yet executed– expected versus actual numbers– status of CR/PRs (entered, analyzed, solved, tested, closed,

rejected)

• Performance Tracking– actual size figures (versus estimates)– actual usage of critical computer resources (versus estimates)

• Inter-group Deliverables and Issues– identification of all inter-group deliverables and issues– actions + action holders + action status

• Other Issues

Page 18: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Milestone Trend Analysis

jan

feb

mar

may

june

july

aug

sep

oct

nov

dec

apr

jan feb mar apr may june july aug sep oct nov dec

Actual time

Page 19: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

jan

feb

mar

may

june

july

aug

sep

oct

nov

dec

apr

jan feb mar apr may june july aug sep oct nov dec

Actual time

jan

feb

mar

may

june

july

aug

sep

oct

nov

dec

apr

jan feb mar apr may june july aug sep oct nov dec

Actual time

Commercial Release

Design Release

Product Range Start

Commercial Release

Design Release

Product Range Start

Example Milestone Trend Analysis

What can you learn of these MTA’s?

Page 20: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Simple WBS Example

Deliverable Effort Human Resources Start & End Dates Relations Cum Eff

D1 2 Adam, Betty 9901.1 - 9901.5 - 2

D2 1 Adam 9902.1 - 9902.5 D1

D3 1 Betty 9902.1 - 9902.5 D1

D4 1 Adam 9903.1 - 9903.5 D1

D5 1 Betty 9903.1 - 9903.5 D1

R1 1 Adam 9904.1 - 9904.5 D2

R2 2 Betty, Carol 9904.1 - 9904.5 D1

R3 3 Adam, Betty, Carol 9905.1 - 9905.5 D3 12

R4 1 Betty 9906.1 - 9906.5 D5

R5 2 Adam, Carol 9906.1 - 9906.5 D4

R6 2 Adam, Carol 9907.1 - 9907.5 D4

R7 2 Betty, Dave 9907.1 - 9907.5 D5

R8 4 Adam, Betty, Carol, Dave 9908.1 - 9908.5 D1 23

R9 1 Adam 9909.1 - 9909.5 D2

R10 2 Betty, Dave 9909.1 - 9909.5 D3

R11 1 Carol 9909.1 - 9909.5 D4

T1 3 Betty, Carol, Dave 9910.1 - 9910.5 R1 - R2 - R8 - R9 30

T2 1 Betty 9911.1 - 9911.5 R4 - R5 - R6 - R7 -R 11

T3 1 Carol 9911.1 - 9911.5 R3 - R10

T4 2 Betty, Carol 9912.1 - 9912.5 T1 -T2 -T3 34

E1 1 Betty 9913.1 - 9913.5 T4 35

19

27

32

4

6

9

15

Page 21: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Schedule Example

9901 9902 9903 9904 9905 9906 9907 9908 9909 9910 9911 9912 9913

D1

R2

R8

D2R1

R9

T1

D3

R3

R10

T3

D4

R5

R6

R11

D5

R4

R7

T2

T4

E1

Page 22: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Earned Value Chart (incomplete)

0

5

10

15

20

25

30

35

40

1 2 3 4 5 6 7 8 9 10 11 12 13

Weeks

Eff

ort Planned Effort and

Value

Page 23: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Schedule Example

9901 9902 9903 9904 9905 9906 9907 9908 9909 9910 9911 9912 9913

D1

R2

R8

D2R1

R9

T1

D3

R3

R10

T3

D4

R5

R6

R11

D5

R4

R7

T2

T4

E1

Page 24: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Earned Value

Planned Effort and Value

Tangible Deliverables - Earned Value

Time Cards - Effort Spent

Deliverable Effort Human Resources Start & End Dates Relations Cum Eff

D1 2 Adam, Betty 9901.1 - 9901.5 - 2

D2 1 Adam 9902.1 - 9902.5 D1

D3 1 Betty 9902.1 - 9902.5 D1

D4 1 Adam 9903.1 - 9903.5 D1

D5 1 Betty 9903.1 - 9903.5 D1

R1 1 Adam 9904.1 - 9904.5 D2

R2 2 Betty, Carol 9904.1 - 9904.5 D1

R3 3 Adam, Betty, Carol 9905.1 - 9905.5 D3 12

R4 1 Betty 9906.1 - 9906.5 D5

R5 2 Adam, Carol 9906.1 - 9906.5 D4

R6 2 Adam, Carol 9907.1 - 9907.5 D4

R7 2 Betty, Dave 9907.1 - 9907.5 D5

R8 4 Adam, Betty, Carol, Dave 9908.1 - 9908.5 D1 23

R9 1 Adam 9909.1 - 9909.5 D2

R10 2 Betty, Dave 9909.1 - 9909.5 D3

R11 1 Carol 9909.1 - 9909.5 D4

T1 3 Betty, Carol, Dave 9910.1 - 9910.5 R1 - R2 - R8 - R9 30

T2 1 Betty 9911.1 - 9911.5 R4 - R5 - R6 - R7 -R 11

T3 1 Carol 9911.1 - 9911.5 R3 - R10

T4 2 Betty, Carol 9912.1 - 9912.5 T1 -T2 -T3 34

E1 1 Betty 9913.1 - 9913.5 T4 35

19

27

32

4

6

9

15

Page 25: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Earned Value Chart

Earned Value

0

5

10

15

20

25

30

35

40

1 2 3 4 5 6 7 8 9 10 11 12 13

Weeks

Eff

ort

Effort Spent

Planned Effort and Value

Slip of 3 weeks, 50% delay20 % under budget, 50 % effort overrunCarol still at other project, lower productivity than estimatedDepending on priority setting: less functionality and/or more budget

and/or delayed release

Schedule :Budget :Analysis :Mitigation :

Page 26: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Maturity of project tracking process

• Lack of process: Constant crisis and re-actions

• First improvement: Corrective actions are taken when the actual results deviate significantly (based on team judgment) from the plan

• Next improvement: Corrective actions when the actual results deviate significantly (more than pre-defined thresholds (based on experience)) from the plan

• Final improvement: Corrective actions when the actual results deviate significantly (i.e. outside the Upper and Lower Control Limits (obtained from Statistical Process Control)) from the plan

Page 27: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Inter-group co-ordination

• Required deliverables from other groups (internal and/or external) are listed under “Dependencies” in the project plan: it is assumed that these deliveries will be on time and with the right quality

• Improvement step: all (intermediate) deliverables from/to other groups are explicitly listed with delivery date and person responsible, and quality criteria are defined and agreed upon for all deliverables from/to other groups

• Next improvement step: – pro-active checking of the status of the expected

deliverables – in case of problems, a joint effort is started to solve

the issue– in case of disagreement, the issue is escalated via

pre-defined and agreed upon channels

Page 28: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Peer Reviews

• 2 types of review:– To improve quality through detection of defects by

peers as early as possible – To formally approve a deliverable by e.g., project

leader, system architect, management• Lack of process: document quickly read by reviewers• First improvements (to establish stable process):

– Review meetings and preparation time planned– Checklists (per type of documented) used and

maintained– Metrics collected (preparation time, review meeting

time, number of major/minor defects found, etc.)• Next improvements (to improve yield):

– Ensure right persons are involved in review– Measure and ensure effectiveness of reviews

Page 29: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Problem Report Handling: Maturity Grid

Severity of problem:• S: Safety, the product causes a dangerous

situation• A: Product cannot be shipped, most

customers will return it– Errors in basic functionality– Major errors in advanced functions– Non-compliance to standards– Errors that are irritating for every customer

• B: Product can be sold, but critical customers will return it– Minor errors in the basic functions – Major errors in the functions difficult to reach

(>2 levels deep in the menus) – Major errors in stress tests

• C: Customers tolerate the defect or do not see it– Minor errors in the functions difficult to reach – Minor errors in stress tests

• D: The defect is accepted for the product

Evolution of problem• 4: Problem entered, cause

not yet known • 3: Problem analyzed,

cause known, problem assigned to engineer

• 2: Solution implemented and tested by engineer

• 1: Solution tested by tester, included in formal release, and declared solved

• 0: Solution verified by submitter and declared closed

Page 30: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Problem Report Handling: Example Maturity Grid

S A B C D

4 0 1 3 12 0

3 0 3 3 8 0

2 0 3 11 24 0

1 0 5 31 56 0

0 1 26 79 125 7

Page 31: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Problem Report Handling

• All tests done and Maturity Grid shows:

• Can we start releasing the product?

• It depends !

S A B C D

4 0 0 0 0 0

3 0 0 0 0 0

2 0 1 2 7 0

1 0 5 17 12 0

0 0 164 206 343 53

0

20

40

60

80

100

120

140

320 321 322 323 324 325 326 327 328 329 330 331 332 333 334 335 336 337 338

PRs entered PRs solved PRs still open

0

20

40

60

80

100

120

140

160

320 321 322 323 324 325 326 327 328 329 330 331 332 333 334 335 336 337 338

PRs entered PRs solved PRs still open

Page 32: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

Final Project Stage - PR Curve

FW-R33/55, CDR 800/820 set software: open A+B+C PRs

0

50

100

150

200

250

300

wk107

wk109

wk111

wk113

wk115

wk117

wk119

wk121

wk123

wk125

wk127

wk129

wk131

wk133

wk135

wk137

Asymptotic

Page 33: Software Project Management Manage Unavoidable Complexity Avoid Unmanageable Complexity

The Asymptotic Period

How to limit the “asymptotic” period for maturing the software?Find as many defects as possible as early as possible!

Measures to be taken:• Ensure (plan + track) that all required testing is done on time

– Integration, functional, system, electrical, torture room, field, factory, service, conformance, stress/stability

• Ensure multiple rounds of testing are done on time– After fixing an “A” problem (e.g. certain functionality does not work

at all) found in the first round, multiple “B” and “C” problems will probably be found in the next round

• Prioritize PRs and ensure PRs are closed when they have been solved

Longer term improvements:• Reuse test cases (increasing test coverage)

– Random testing often results in PRs and should result in new test cases

– Measure test coverage, track % of test cases executed and passed