smartmetertm steering committee update march 2011 · 2017-03-24 · steering committee march 2011...
TRANSCRIPT
SmartMeterTM
Steering Committee Update – March 2011
2 Steering Committee March 2011 Report
Agenda
► Monthly Updates
► Release Status Update
► Deployment Status Update
► Schedule Update
► Deployment Update
► Budget Status – Expenditures by Workstream
► Budget Status – Benefits
► Issues / Risks Summary
► Program Metrics
► Appendix
► Project Deployment Plan Progress
► Contingency Reconciliation
► SmartMeterTM Acronyms
3 Steering Committee March 2011 Report
Release Status Update
Overall Actions/Status
EAC Funded Budget* ITD Scope Schedule Resources Issues Risks
IT Releases, February 2011
Release I non-NEMS - Deploy
Release J TLM – Build/Deploy
Release J Outage – Plan/Analyze
Release K – Plan/Analyze
Release I - Migrate NEM and other ABS-billed
accounts from ABS to CC&B
Release J TLM - Integrate usage data into TLM
(Transformer Load Management) reporting to provide
actual customer peak load data
Release J Outage - Automate the outage detection
process to identify outages using SmartMeterTM data in
addition to customer calls.
Release K - Transition customers to interval billing to
support SmartMeterTM initiatives
Release I
▪ Non-NEMs Schedule assessing current ABS and CC&B rate components.
▪ The final Non-NEMs release will occur after completion of CC&B upgrade.
Release J TLM
▪ Transformer Load Management deployment date will move out to 04/22/11 due to incremental additional
change requests.
Release J Outage
• Outage plan/analyze has completed. Project forecast reviews are underway.
Release K
▪ Release K Phase 2 requirements definition is underway..
*Funded Budget represents the amount of funding that has been approved through the "gated" funding
process. Projects that are noted as "Plan/Analyze" or "Analyze" are only partially funded through those
initial phases. Upon completion of the Analyze phase, the release team will prepare a request to authorize
the remaining amount required to complete the Release.
4 Steering Committee March 2011 Report
Release Status Update (continued)
Application Upgrades – Upgrade Meter Data Management System (MDMS) and electric ‘head-end’ system.
Performance & Scalability - Ensure operation at necessary performance and scalability levels
HAN Enablement - Deployment of In Home Devices (IHD) to SMB & residential customers over the (AMI) network
Application Upgrades ▪ Successful deployment on 01/28. ▪ Electric ‘head-end’ system upgrade targeted for 4/1/2011.
Performance & Scalability ▪ Final MDMS Scale test is underway. ▪ Data Warehouse hardware improvement work is underway. Currently planning and creating initial
forecast for work completion. HAN Enablement ▪ Project dependency of SmartEnergy 2.0 standards will result in a renewed work effort in 2Q 2011.
Overall ▪ IT is working to realign all remaining IT work with remaining IT budget
Overall Actions/Status
EAC Funded Budget* ITD Scope Schedule Resources Issues Risks
IT Release, February 2011
Application Upgrades - Deploy
Performance & Scalability - Execute
HAN Enablement - Plan
*Funded Budget represents the amount of funding that has been approved through the "gated" funding
process. Projects that are noted as "Plan/Analyze" or "Analyze" are only partially funded through those
initial phases. Upon completion of the Analyze phase, the release team will prepare a request to authorize
the remaining amount required to complete the Release.
5 Steering Committee March 2011 Report
Deployment Status Update
Endpoints ▪ Increased rate of UTCs versus planned
Electric Network ▪ Supplemental network installation to support transition of meters to
Operations.
Gas Network ▪ Remediation of gas module transition issues.
Endpoints
▪ Executing urban customer access, non-standard installation and customer
outreach processes
▪ In progress
▪ In progress
Actions/Status Challenges
EAC 2011 Forecast
(2011 EAC / CPI)
Scope Schedule Resources Issues Risks
Deployment: February, 2011
Endpoints (2011 YTD)
Gas Network (2011 YTD)
Electric Network (2011 YTD)
6 Steering Committee March 2011 Report
11M Meters Scalability
Legend
Office Closures (ITD)
Alpha I Pilot
Schedule Update 2010
Jul Sep Oct Nov Dec Feb Jan May Aug Apr
Jun
Benefits
Apr Jun May Mar IT Release Deployment
Release H
Field Delivery
Remaining Engineering Solutions for MLPP Scenarios
3.0M Meter/Module Installations, 2010
Release I
Approved Milestone (delay)
Release J
Plan/Analyze complete
MLPP Cost/Benefit Analysis
Initial Network Deployed
350 Positions Captured
6 Phase-I Office
Closures, cumulative 2011 Office Closures
2011
Meter Reading Reductions (ITD) 450 Positions Captured
550 Positions Captured
Meter Power Status Check (MPSC)
- Call Center and IVR
Remote Connect
Disconnect 2
Q3 Deploy
Check Point-
Enhanced Outage Notification (EON)
Restoration (OR) / Transformer Loading
Management (TLM)
2 Phase 1 Office
Closures Complete, 2010
TLM deploy TLM Plan
TLM Analyze
OR Deploy
SE2.0 finalized
ABS non-NEMS
Deploy
ABS/CC&B Synchronization Reports
SM Operations Center SMOC Phase 1.0 Deploy
As of 2/31/11
EON
Forecasted Milestone (delay)
Milestone Met
Baseline Milestone
Forecasted Milestone (early)
Oct Sep Aug Jul Nov Dec
NEMS Migration Phase I
2.0M Meter/Module Installations, 2011
Milestone TBD
Release O
Performance & Scalability
HAN Alpha I & II Alpha II complete
HAN Enablement
Q2 Deploy
‘Head-end’ system upgrade (electric)
Release K Rel K Phase 1 Analyze
Rel K Phase 2 Analyze
HAN restart
7 Steering Committee March 2011 Report
As of March 11, 2011 Deployment Update
Through
Friday,
3/11
2011 Install Rate vs. Plan - Weekly Meter Totals
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
7-J
an
21-J
an
4-F
eb
18-F
eb
4-M
ar
18-M
ar
1-A
pr
15-A
pr
29-A
pr
13-M
ay
27-M
ay
10-J
un
24-J
un
8-J
ul
22-J
ul
Week Ending (Friday) Dates
We
ek
ly I
ns
talls
.0M
.4M
.8M
1.2M
1.6M
2.0M
Weekly installs
2011 Cumulative Installs
2011 Target
2011 Weekly target
2011 target (Rev. 14 prelim) : 2.0MTotal SM Inception to
date meters in
service: 7,736,089
8 Steering Committee March 2011 Report
2011 Budget Status – Expenditures by Workstream
Year-to-Date Variance Explanations:
Favorable YTD capital variance ($7.5M) due to timing; includes favorable variances due to: 1) fewer meter/module installations of $4.8M (#5), 2) less IT spending of $1.2M
(#11), and 3) other miscellaneous favorable variances ($1.5M).
Favorable YTD expense variance ($5.9M) due to timing associated with: 1) underruns in Customer of $5.9M (#16) and four other workstreams totaling $1.0M (#13, #15,
#24 and #25), partially offset by additional early meter retirements of -$1.0M (#23)
# Work Stream Budget Actual Variance Budget Actual Variance #
Capital (000s)
1 PMO $293 $220 $74 $617 $520 $97 $3,833 $46,849 1
2 SM OPERATIONS $0 $5 ($5) $0 $45 ($45) $0 $11,350 2
4 SM FIELD DELIVERY - EXECUTION NETWORK $407 $254 $153 $811 $738 $74 $4,436 $28,992 4
5 SM FIELD DELIVERY EXECUTION ENDPOINTS $8,778 $5,188 $3,589 $15,194 $10,428 $4,765 $106,706 $254,742 5
6 SM FIELD DELIVERY OFFICE $1,244 $1,007 $237 $2,550 $2,232 $318 $10,738 $40,921 6
7 SM SOLUTIONS OFFICE $800 $386 $414 $1,889 $1,319 $570 $6,773 $11,269 7
8 SM SOLUTIONS - ENGINEERING $645 $261 $384 $1,414 $626 $788 $3,000 $11,445 8
9 SM SOLUTIONS - G&E METERING SERVICES $6,435 ($853) $7,288 $10,900 $11,206 ($307) $62,241 $921,194 9
10 Field Delivery / Solutions Total: $18,308 $6,244 $12,064 $32,758 $26,550 $6,208 $193,894 $1,268,564 10
11 IT (Including Technology Monitoring) Total: $2,951 $1,796 $1,156 $5,317 $4,110 $1,207 $27,038 $348,646 11
12 Capital Total: $21,553 $8,265 $13,288 $38,693 $31,225 $7,467 $224,765 $1,675,409 12
Expense (000s)
13 PMO $362 $92 $270 $708 $367 $342 $3,138 $25,183 13
14 SM OPERATIONS $368 $533 ($165) $713 $1,446 ($734) $2,730 $57,073 14
15 SM CHANGE MANAGEMENT $483 $189 $294 $959 $767 $192 $5,032 $13,345 15
16 CUSTOMER $5,443 $1,404 $4,039 $8,746 $2,894 $5,852 $36,766 $71,561 16
0
17 SM FIELD DELIVERY - EXECUTION NETWORK $67 $0 $67 $133 $0 $133 $800 $0 17
18 SM FIELD DELIVERY - EXECUTION ENDPOINTS $0 $1 ($1) $0 ($0) $0 $2,370 $103 18
19 SM FIELD DELIVERY OFFICE $329 ($16) $345 $592 $28 $565 $0 $15,169 19
21 SM SOLUTIONS OFFICE $334 $80 $255 $1,392 $897 $495 $2,283 $2,637 21
22 SM SOLUTIONS - ENGINEERING $31 $3 $28 $55 $12 $44 $127 $1,573 22
23 SM SOLUTIONS - G&E METERING SERVICES $2,024 $5,057 ($3,033) $4,048 $5,057 ($1,008) $6,571 $53,525 23
24 Field Delivery / Solutions Total: $2,786 $5,124 ($2,339) $6,221 $5,993 $229 $12,151 $73,006 24
25 IT (Including Technology Monitoring) Total: $319 ($38) $357 $500 $484 $16 $5,946 $131,329 25
26 Expense Total: $9,761 $7,304 $2,457 $17,846 $11,951 $5,895 $65,763 $371,497 26
27 Capital + Expense Total: $31,314 $15,569 $15,745 $56,539 $43,176 $13,363 $290,528 $2,046,906 27
Year-to-Date - FebruaryInception to
Date Spend
Current Month - February2011 Annual
Budget
9 Steering Committee March 2011 Report
2011 Budget Status – Benefits
2007 2008 2009 2010 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec ITD Actual#
1 Activated Meter Benefits: 111$ 4,705$ 26,055$ 56,313$ 6,181$ 6,334$ 6,485$ 6,698$ 6,996$ 7,313$ 7,720$ 8,116$ 8,558$ 9,007$ 9,436$ 10,093$ 99,698$ 1
2 Mainframe License Benefits: 1,250$ 5,000$ 5,000$ 5,000$ 417$ 417$ 417$ 417$ 417$ 417$ 417$ 417$ 417$ 417$ 417$ 417$ 17,083$ 2
3 Total: 1,361$ 9,705$ 31,055$ 61,313$ 6,598$ 6,751$ 6,902$ 7,115$ 7,412$ 7,730$ 8,137$ 8,533$ 8,975$ 9,424$ 9,853$ 10,510$ 116,782$ 3
4 2011 Cumulative Actual + Forecast: 6,598$ 13,349$ 20,250$ 27,365$ 34,778$ 42,507$ 50,644$ 59,177$ 68,151$ 77,575$ 87,428$ 97,938$ 4
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Budgeted Benefits:
5 Monthly 3,914$ 3,914$ 4,047$ 4,186$ 4,278$ 4,350$ 4,432$ 4,507$ 4,593$ 4,683$ 4,763$ 4,850$ 5
6 Cumulative 3,914$ 7,829$ 11,875$ 16,061$ 20,339$ 24,690$ 29,121$ 33,629$ 38,222$ 42,904$ 47,667$ 52,518$ 6
Actual / Current Forecast:
7 Monthly 2,193$ 2,314$ 2,371$ 2,454$ 2,481$ 2,513$ 2,567$ 2,614$ 2,671$ 2,723$ 2,767$ 2,871$ 7
8 Cumulative 2,193$ 4,507$ 6,878$ 9,332$ 11,814$ 14,326$ 16,893$ 19,507$ 22,177$ 24,900$ 27,668$ 30,539$ 8
9 YTD Variance (1,722)$ (3,321)$ (4,997)$ (6,728)$ (8,526)$ (10,363)$ (12,229)$ (14,122)$ (16,044)$ (18,004)$ (20,000)$ (21,979)$ 9
*
**
SmartMeter Balancing Account (SBA) Credits *
#
($ in thousands)
2011 SmartMeter Balancing Account (SBA) actual and forecast credits assumes the continuation of the $1.95 electric / $1.04 gas activated meter-month savings and $5 million per year mainframe
license savings.
2011 benefits, budget versus actual and forecast, do not include meter reading costs and benefits which are being recorded in the Meter Reading Memorandum Account beginning on January 1,
2011.
Preliminary ForecastActual
2011 Benefits, Budget vs. Actual and Forecast **
($ in thousands)
10 Steering Committee March 2011 Report
Issues Summary
Target Resolution
Date
Issues Impact Status Summary
3/15/2011
Volume of deployed
untransitioned meters
to SM Read status
higher than expected
under 2010 base plan
Increased costs and negative
customer impact
Significant business process enhancements have been implemented and
have contributed to a 33% reduction in untransitioned meters. Finalizing
transition targets consistent with 2011 deployment goals (Revision 14,
Deployment Schedule).
Ongoing
Increasing number of
installations affected by
access refusals
Increased costs, increase in
unable to complete (UTC) back-
log, customer change
management
Working plan to engage customers across multiple communication
channels to enhance customer understanding of SmartMeter journey and
benefits.
11 Steering Committee March 2011 Report
Risks Summary
# Created
On P I Score
Prev.
Score Risks Impact Status Summary
Assoc.
Issue
1 5/15/2009 3 3 9 25 Non-standard Installations may
impact deployment cost and
schedule
Key drivers: Need customer
access to reach meter, meter
with space limitations and
customer overbuilds
Schedule and additional
costs
Cost impact estimate included within approved reforecast
Estimate-at-Complete. Installations and resource planning
being adjusted to mitigate schedule impacts. Customer
outreach strategies being incorporated into field pilots and
deployment strategies prior to starting full scale deployment
to minimize customer impact
2 3/22/2010 4 4 16 16 Vendor SmartMeter products
cannot be delivered to meet the
deployment schedule.
Key drivers: Remaining vendor
development activities and
resources to complete
solutions, insufficient lead time
for procurement due to design
changes/schedule decisions.
Deployment slow/stand
down, resource planning
ability, and additional costs
Vendor solutions for non-standard deployment under
development, testing and review. Management of vendor
delivery timelines subject to ongoing joint project and vendor
leadership review. Focus on remaining deployment
dependencies being used to validate integration of vendor
product deliveries.
Finalization of network design/equipment mix to complete
network deployment in process with vendors.
3 4/4/2008 3 5 15 15 Business processes enabled by
new technology may not
perform as intended.
Key driver: Increased data
volume and validation,
underlying business processes.
Billing errors, customer
complaints, inability to meet
endpoint deployment goals.
Continuing to monitor technology performance and
identifying mitigations to resolve any identified technology
performance issues. Meter transition process checks
updated to include new integrated standards with Vendor for
validating Network design, meter connectivity and read
performance. Planning for Full –Deployment/Interval Billing
via functionality deployments and additional process
capability initiatives through 2011 underway.
12 Steering Committee March 2011 Report
Program Metrics
Feb '11 Variance Analysis
Metric Key Performance Indicator Actual Target Var Actual Target Var Actual Target Var Forecast Target Var
P1SM Earnings Contribution ($M -
estimated)5.7$ 5.7$ 0.0% 5.8$ 5.7$ 1.8% 11.5 11.4 0.9% 70.0$ 66.2$ 5.7%
P2 OSHA Recordable Rate (YTD) - 0.37 - 0.42 - 0.51
P3 MVI Recordable Rate (YTD) - 0.95 3.56 0.98 ` 0.98 0.98 1 MVI reported in February
C1Customers enrolled in SmartRate
(net)24,043 (track only) 23,803 (track only)
C2# of CPUC escalated Customer
Complaints55 (track only) 84 139.0 (track only)
C10Customer Complaint Rate
(escalated to CPUC)0.035% (track only) 0.060% (track only) 0.047% (track only)
D1Meters/Modules Installed -
Electric & Gas157,291 127,028 23.8% 139,423 120,783 15.4% 296,714 287,460 3.2% 2,000,000 2,000,000 0.0%
D2 Gas Network - DCUs Installed 20 27 -25.9% 8 46 -82.6% 28 73 -61.6% 617 617 0.0% Fewer Network installations initiated than planned; Network
units at completion under review
D3 Electric Network - Nodes Installed 253 160 58.1% 194 445 -56.4% 447 605 -26.1% 4,417 4,417 0.0% Fewer Network installations initiated than planned; Network
units at completion under review
D5 UTC Rate 6.3% 5.0% 25.7% 4.5% 6.0% -25.0% 5.5% 6.0% -8.3% 5.5% 6.0% -8.3%
D7 UTCs open beyond 90 days 145,673 (track only) 150,696 (track only)
D8 CPI - Endpoints $31.41 $44.46 -29.4% $39.48 $44.17 -10.6% $35.20 $44.17 -20.3% $44.17 $44.17 0.0%
D12 CPI Gas Network $773 $2,222 -65.2% $9,375 $1,505 522.9% 3,286.0 1,505 118.3% $1,505 $1,505 0.0% Fewer Network installations initiated than planned; Network
units at completion under review
D13 CPI Electric Network $1,883 $2,130 -11.6% $1,526 $1,371 11.3% $1,707 $1,371 24.5% $1,371 $1,371 0.0%Increase in complex Network installations, location alternatives
in progress
D14Total Weeks of Inventory on Hand
- Electric Meters19 6 216.0% 16 8 100.0%
D15Total Weeks of Inventory on Hand
- Gas Modules18 6 205.8% 19 8 137.5%
O4 Transition Aging - Average Days 143 (track only) 118 (track only) 128 (track only)
O5 SM Billing accuracy % (SA) 99.88% 99.88% 0.0% 99.88% 99.88% 0.0% 99.88% 99.88% 0.0% 99.88% 99.88% 0.0%
O6 SM Billing timeliness % (SA) 99.82% 99.79% 0.0% 99.87% 99.79% 0.1% 99.85% 99.79% 0.1% 99.79% 99.79% 0.0%
O7SM % Bills not estimated
(BSEGs)99.90% 99.90% 0.00% 99.86% 99.90% -0.04% 99.88% 99.90% 0.0% 99.90% 99.90% 0.0% Analysis in progress
B2Meters Activated - Electric & Gas
(end of month)62,940 (track only) 87,197 (track only) 150,137 (track only)
B3Remote Disconnect & Reconnect
Transactions26,500 (track only) 25,597 (track only) 52,097 (track only)
B5 ITD Meter Reading HC reductions 470 (track only) 487 (track only)
Jan '11 - Month Results Month Results 2011 Year End ForecastYTD
13 Steering Committee March 2011 Report
Appendix
► Combined Plan / Target / Actual Progress
► Contingency Reconciliation
► SmartMeter™ Acronyms
14 Steering Committee March 2011 Report
Project Deployment Plan Progress
#s as of 02/28/11
Combined Gas and Electric Plan, Target, and Actuals
(Cumulative)
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
11,000
EOY
2007
Q108 Q208 Q308 EOY
2008
Q109 Q209 Q309 EOY
2009
Q110 Q210 Q310 EOY
2010
Q111 Q211 Q311 EOY
2011
Q112 Q212 EOY
2012
TargetBus Case PlanActual
# in Thousands
15 Steering Committee March 2011 Report
Contingency Reconciliation
SmartMeter Contingency Reconciliation $000s
Business Case Approved Contingency 177,753
Total Project Decsision Requests Approved and Adopted by Steering Committee 177,753
Remaining Contingency -
Approved Project Decision Requests, by Approval Date
2007 106,329$
2008 $32,240
2009 $20,313
2010 $18,871
$177,753
16 Steering Committee March 2011 Report
SmartMeterTM Acronyms
Acronym Definition Acronym Definition
ABS Advanced Billing System MARA My Account Re-Architecture
AFCI Arc Fault Circuit Interrupter MDMS Meter Data Management System
AMI Advanced Metering Infrastructure MLPP Meter Location Problem Project
AP Access Point MPSC Meter Power Status Check
Apps Applications MV-90 Multi Vendor - 90
ASM Automated Storage Management MVI Motor Vehicle Incidents
BDG Business Development Group NEMS Net Energy Metering Services
CC&B Customer Care and Billing NIC Network Interface Card
CEDSA Centralized Electric Distribution System Assets OIR Order Instituting Rulemaking
CoE Center of Excellence OIS Outage Information System
CPI Cost Per Install OMT Outage Management Tools
CPUC California Public Utilities Commission Ops Operations
DART Distribution Asset Reconciliation Tool OSHA Occupational Safety and Health Administration
DC Data Center PCR Project Change Request
DCU Data Collector Unit PCT Programmable Communicating Thermostat
DR Disaster Recovery PDP Peak Day Pricing
DRA Division of Ratepayer Advocates PDR Project Decision Request
DSCI Distribution Control Systems, Inc. PE Perfomance Engineering Company
EA Ecologic Analytics PMO Project Management Office
EAC Estimate at Completion PTR Peak Time Rebate
ED Energy Division QBR Quarterly Business Review
EMR Electric Meter Reader RCDC2 Remote Disconnect Phase 2
EMT Electric Meter Technician Rev. Revision
EOM End-of-Month RF Radio Frequency
EON Emergency Outage Notification RFA Request For Authorization
EOY End Of Year RV Restoration Validation
FA Functional Area SBA SmartMeter Balancing Accounts
FD Field Delivery SM SmartMeter
GE General Electric Co. SM Apps SmartMeter Applications
GFI Ground Fault Interrupter SMU SmartMeter Upgrade
HAN Home Area Network SR Service Request
HC Head Count TBD To Be Determined
IHD In-Home Devices TechArch Technical Architechture
ISTS Information Systems and Technology Services TIC Technology Innovation Center
IT Information Technology TLM Transformer Load Management
ITD Inception To Date TOU Time Of Use
IVR Interactive Voice Response UIQ Utility IQ - SSN software
KC Knowledge Center UTC Unable To Complete (meter installation)
KVAR Kilo-Volts-Amps Reactive YTD Year-To-Date
LOB Line of Business
SmartMeter Acronyms