Page 2: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

LNG Projects in Denmark

Port of Skagen

Port of Hirtshals

Samsø Island ferry

Port of Aarhus

Copenhagen Malmö Port

5 ports:

2

Page 4: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

Why LNG?

4

Page 5: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

Main Challenges for LNG

5

Page 6: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

6

Page 7: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

Stockholm-Turku

7

Viking Grace – daily service from Stockholm to Turku - Daily bunkering in Stockholm

Page 8: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

Gothenburg

8

New LNG terminal – production, storage, ship bunkering, truck loading rail loading and regasification (injection to national grid)

Page 9: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

Rotterdam

9

• LNG carrier/bunker vessel = normal

tanker carrying dangerous goods • LNG fuelled ship = normal ship, no extra

port regulations

• Shore- to- Ship bunkering: 1st July 2013 • Ship-to Ship bunkering: 2014

Page 10: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

LNG Chain: Rotterdam-Gothenburg

10

Page 11: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

Similar projects

11

Port of Zeebrugge and Port of Antwerp: • LNG procedures • LNG supply chains • LNG security • Bunker vessels – ship2ship • Share the risk – port and operators in common investment setup

Page 12: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

Hamburg

12

Page 13: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

Tallinn

13

Terminal Project

Page 14: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

Conclusions

14

• LNG is at the present the most complete medium term viable solution – still not a “silver bullet”

• Several ongoing port projects in North Europe – but still small demand

• Significant remaining challenges – demand and insecurity concerning sulphur rules 2015 and other solutions e.g. scrubber, electricity, dual fuel

• Pressing timetables, complementarity of compliance strategies and solutions

• Ongoing policy initiatives from European Commission • An opportunity for South European ports too??

Page 15: SMALL SCALE LNG INFRASTRUCTURE SOLUTIONS · 2013. 10. 30. · Tallinn 13 Terminal Project . Conclusions 14 • LNG is at the present the most complete medium term viable solution

Thank you for your attention

Tom Elmer Christensen - sekretariatschef Danske Havne – Danish Ports