Small Modular Reactors: Progress Towards Deployment

2 © 2013 Generation mPower, LLC. All rights reserved.

• Accelerate transition to cleaner energy industry

Balance intermittent sources with nuclear … load following

Repower aging fossil sites … 45GW < 500 MWe

Replace retiring nuclear plants … economics

• Expand practical opportunities for nuclear power

Access for deregulated, merchant, and smaller utilities

More flexible siting

Incremental power additions

The Nuclear Industry Challenge

3 © 2013 Generation mPower, LLC. All rights reserved.

• Smaller plant, smaller investment

• Integrated reactor system

• Simpler, safer, architecture

• Factory built

• Lower risk

B&W mPower™ Integral Reactor

Traditional 2 Loop PWR NSSS

Same proven technology – better architecture

Reactor Coolant Pumps (4)

Reactor Vessel

Pressurizer

Once Through Steam Generators (2)

What is a Small Modular Reactor (SMR)?

4 © 2013 Generation mPower, LLC. All rights reserved.

B&W mPower Nuclear Island Features

• 2 x 180MWe units

• Fully underground reactor systems

• Optimized for minimum staff and O&M

• Enhanced spent fuel pool cooling

180MW mPower SMR

• Compact <40-acre site footprint

• Integral, rail-shippable reactor module

• Passively safe design philosophy

• 4-Year extended operating cycle

mPower “twin-pack” Site Layout

Simple and robust architecture lowers cost / risk, enhances licensing

5 © 2013 Generation mPower, LLC. All rights reserved.

Breakthrough Safety Performance …

Core Damage

Frequency Target

(per reactor year)

Lowest Reactor

Break Location

(Feet above core)

Severe Accident

Coping Time

(days)

Emergency

Zone

Reduction

(REM at 1000 Feet)

7

14

~75

~10 -5

~10 -6

10 -8

~ 5

~ 5

1 REM at 1000 Feet Gen II PWR

Gen III PWR

B&W mPower Safety is enhanced by integrated design features and defense in depth

8 Hours

25 REM at 25 Miles

25 REM at 25 Miles

6 © 2013 Generation mPower, LLC. All rights reserved.

From this…

To this…

Existing Large Reactor 10 mi. Emergency Planning Zone

Shrinking the Emergency Planning Zone …

Enables EPZ “inside the fence”

• Core protected for all postulated accidents

• Two weeks before any fuel damage after most severe hypothetical accidents

7 © 2013 Generation mPower, LLC. All rights reserved.

Testing is foundation for low risk, high reliability mPower design

More than a Design … A Complete Testing Program

Nuclear Island Test Facility Bedford, VA

$100M USD Investment

• Establish design

• Support licensing

• Prepare for operation

• Confirm performance

• Demonstrate reliability

Fuel Technology Center Lynchburg, VA

Production Prototype Main Control Room

Lynchburg, VA

8 © 2013 Generation mPower, LLC. All rights reserved.

• Cooperative Agreement signed

$101M Cost-share funds obligated

• Starting Construction Permit Application

Site borings completed

Geo-Tech validating seismic design

Working toward mid-2015 CPA submittal

• Fall, 2014 Design Certification Application

Design Certification Approval expected Fall 2017

Significant milestones achieved

DOE Funding and Clinch River Project Update

9 © 2013 Generation mPower, LLC. All rights reserved.

Active NRC Pre-Application Engagement

Monthly meetings, weekly interaction

20 + Topical (LTR) and Technical Reports

Technical approach to Security, Source Term

No regulatory changes required

2021 2022 2012 2013 2014 2015 2016 2017 2018 2019 2020

Prep CPA

Prep DCD

Design Cert

NRC Review/Rule

Prep OLA NRC Review/Hrng

CP

OL

NRC Review/Hrng

Coordinated Part 50/Part 52 Process: One Design, One Review

Licensing Process Supporting 2014 DCA, 2015 CPA Schedules

10 © 2013 Generation mPower, LLC. All rights reserved.

Developing a Stable and Sustainable Supply Chain

• Revitalizing entire nuclear supply chain

• Working with more than 200 suppliers across 33 states

• Suppliers selected for major equipment

• B&W only US manufacturer capable of producing entire reactor

Robust supply chain will create skilled, and desirable jobs in engineering, manufacturing and construction

Trademarks, service marks and logos featured or referred to within this document are the property of their respective owners the use of which herein does not imply an affiliation with Generation mPower LLC or an endorsement or sponsorship of these materials unless otherwise stated.

11 © 2013 Generation mPower, LLC. All rights reserved.

SMR Impact on Job Creation

SMRs can have a significant impact on job creation

Phase Direct Jobs* Design & Licensing (2008-2017) 400 Mfging, Constr., Launch 2 unit Clinch River Plant 1,600 Annual Operation of 2 unit Clinch River Plant 300-350 Mfging, Constr., Launch of each 2 unit NOAK Plant 1,360 Annual Operation of each 2 unit NOAK Plant 300-350 *Estimates do not include significant supplier base job creation.

NOAK = Nth of a kind

12 © 2013 Generation mPower, LLC. All rights reserved.

• Extend RPS / Clean Energy technology policies to SMRs

Only practical, near-term carbon-free base-load energy source

Lower total cost of electricity than wind or solar technology

• Enhanced PPA and PTC regulatory framework

Creates opportunity for Municipals and Cooperatives

Acknowledges long service life of investment (60-80 years)

• “Early adopter” incentives

Energy independence

Portfolio balancing

SMR Legislative and Policy Enablers

SMR will compete on a “level playing field”

13 © 2013 Generation mPower, LLC. All rights reserved.

Changing the game … mPower’s Vision

• A “differentiated” nuclear solution

• Changing traditional rules of the game

True modular construction

Right-sized Emergency Planning Zone

Design for optimum security staffing

Extended 4-year operating cycle

Load following opposite wind/solar

Improve the economics .. .reduce the investment risk