slow down check point - sarooj · majis industrial services company was ... cast-in situ concrete...
TRANSCRIPT
SAROOJ CONSTRUCTION COMPANYQuarterly Newsletter Volume 8, Issue 4 OCT - NOV - DEC 2016
IN THIS ISSUE : SC 111 & 112 - THE PROJECT - THE CHALLENGES - EARTHWORKS
CONCRETE AND CBM - ASPHALT WORKS - BUILDINGS & SHEDS
STEELWORKS - MEP WORKS - HSE AND QUALITY - THE TEAM - PROJECT
GENERAL FEATURES - SAROOJ NEWS - THE GROUP IN MEDIA
SLOW DOWN...CHECK POINT
2
THE GROUP IN THE MEDIA
SAROOJ NEWS
THE TEAM
HSE AND QUALITY
STEEL WORKS
BUILDING AND SHEDS
ASPHALT WORKS
CONCRETE AND CBM
EARTHWORKS
THE CHALLENGES
THE PROJECT
CONTENTS
Dear Colleagues,
Two decades ago, precisely in 1995, the Sultanate of Oman published its vision 2020. Several 5- year plans were inspired by it and aimed at achieving its national objectives. A pillar of the infrastructure strategy was the construction of the Sohar Industrial Port (SIP). Since then this port kept growing in capacity, efficiency, and quality of its services. Very quickly it attracted many industries to its zones. Steel smelters, refineries petrochemical complexes, aluminum smelters, fabrication yards, power and desalination plants. Majis Industrial Services Company was formed to supply customers with utilities – Oman International Container Terminal Company built their first container yard inside the port.
What further enhanced the growth of SIP is the Royal Decree that restricted commercial activities in port Sultan Qaboos in Muttrah to tourism and leisure and move all other activities to Port Sohar, particularly container handling. The operators of the port and their service providers had to accommodate this sudden surge in the demand.
OICT embarked on Phase II of their yard. SCC were invited to participate to this Tender and were selected by the owner as the preferred bidder. Delivery on time and to specification was of essence.
This contract is another manifestation of our strategy to become the preferred local and regional partner for many international companies.
Simon KaramDirector
Message from the...
PROJECT GENERAL FEATURES
MEP WORKS
3
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
OVERVIEW:
The Project: Container Yard and Main Gate at Sohar Port The Client: Oman International Container Company (OICT)
The Consultant: Tebodin
The Contractor:Sarooj Construction Company
The Location:Sohar Industrial Port
The Duration:18 Months
Project Manager:V.C.Pandian
The Contract Value:34 Million US Dollars
Container Yard
Reefer Gantry
Pouring Concrete
Cantilever Cranes
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
4
The ProjectOICT are a specialized company that build and operate container yards in various ports. Containers are constantly off-loaded from ships, transported by traveling cranes and stacked in a yard before they are transported to final destinations by road transport. The scope consisted of major earthworks and soil improvement, of casting reinforced concrete sleepers taking the containers’ loads, of asphalt access tracks capable of taking heavy loads, of roads for trailers, and of spreading aggregate between sleepers.Furthermore, the construction of a main gate housing security and control activities under shaded area was part of the scope of works. Provision of reefer gantries, external lighting, and the building of several sub-stations were to be included. Several ancillary activities such as fencing, provision of weighbridges, parking areas for trailers were also carried out.
Cantilever Cranes
Container Yard
Ready to Operate
Reefer Gantries
Traveling Cranes
Closer Look
5
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
Whilst technical problems were relatively easy to solve considering the repetitive nature of the works, the real challenge was to complete the works on time and achieve the various milestones when working in a restricted and busy environment. This necessitated sustained efforts to obtain approvals, permits, no objection certificates (NOC), and gate passes. Existing services had to be located, exposed, protected, and reinstated.The management of the procurement of local materials proved challenging. In order to ensure constant supply of aggregate sub-base materials, hot mix asphalt, ready mix concrete, single size aggregates for spreading and cement bound materials (CBM), we had to mobilize our own resources to the area. Several long lead imported items had to be procured from abroad on time requiring thus constant monitoring and follow-up.
The Challenges
Congested Worksite
Live Site
High Structures
Existing and New Services
Confined Areas
Complexity of Finishings
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
6
Unsuitable Soil
Encouraging SMEs
Disposal
Soil Improvement
Sub-Base Materials
Manholes and Chambers
EarthworksThe site is on the sandy beach. It has to be leveled and then reduced by 600mm to remove the sand and replace it with granular fill materials as a general improvement of ground performance. The real loads come from the stack of containers that rest on ground beams. Special treatment was applied for areas under the beams. Additional layer of aggregate base course is applied before the concrete is poured. Interstices are filled with clean aggregates. The movement of vehicles bringing materials from outside sources was organized in such a way that no truck/trailer would travel without being loaded. Coming in they would carry imported materials, going out they would carry unsuitable materials and sand. This opportunity was explored not only to optimize resources and improve efficiency, but also it proved suited to award large parts of the scope to local small and medium size enterprises (SMEs).
7
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
Cast-In Situ Concrete Sleepers
Casting Roof Slab
Concrete Ducts
Steel Reinforcement
Finishing Top of Concrete
Sleeper Beams
Concrete WorksConsistent with our commitment to encourage small and medium size enterprises, we have decided to procure our ready-mix concrete from a local supplier in Sohar. However, in order to ensure continuous delivery when needed on site, we preferred to use our own concrete transit mixers and concrete pump. The major concrete works were to be done on ground beams (sleepers) carrying containers and on traveling-crane lanes. Considering the repetitive nature of the works, it was decided to use steel moulds and panels to form the beams and hold the concrete when it is still wet. Reinforcing steel was cut and bent on site. Several other places and structures required concrete on the project: service ducts, surface drainage channels, hardstandings, pole foundations.
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
8
Fresh Concrete
Steel Reinforcement
Concrete Blinding
Steel Shuttering
The specifications called for the use of a layer of cement bound materials (CBM) to be placed under the asphalt in areas of heavy loads such as the mobile traveling cranes. This technique requires the use of a special wet mix plant to mix granular materials with controlled gradation together with cement in a defined ratio. These materials had to be placed by aggregate spreader to achieve exact gradient and thickness. The layers would be compacted by vibratory rollers. The surface would eventually be cleaned to receive bituminous prime coat which seals its surface.
Concrete and CBM (Cont’d)
9
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
Rubber Tyred Roller
Laying of CBM
New Area Ready for CBM
Aggregate Spreader Machine
Compacting Around Structures
Compaction
Finished Product
Steel Roller
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
10
Traffic Arrows
Bird’s View
Compaction On-Going
Thermoplastic Paint
Intermediate Lane
Asphalt Finisher
Asphalt Works
In the container yard, circulation areas for trailers, vehicles, maintenance pick-ups, and trucks had to be provided between the stacking zones. Two challenges: the supply of hot mix asphalt and the discontinuity in laying. We decided to obtain the asphalt from our plant in Suwaiq despite the distance (about 100 km) and to plan laying of bituminous base course and wearing course in such a manner as to reduce the number of mobilizations of resources. A well-engineered road marking system was implemented giving direction to users and ensuring safety of operations.
11
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
Prime Access
Numbering of Zones
Interlock Pavement
Road Marking
Driving Lanes
Working around Structures
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
12
Isolated Footings
Concrete Frame
Floor Ducts
Curing Stud Columns
Roof Slab
Scaffolding
Building and ShedsThese are specialized buildings: three booths, substation sheds, and shaded areas. The project included the construction of a main gate controlling access to and from the port. Security personnel at the check point work from gate houses and inspect vehicles stopping under shaded areas. Trucks enter, go through buildings to be inspected by Royal Oman Police. The majority of these structures consist of steel frame and insulated cladding. Sub-station buildings, on the other hand, are designed as concrete structures that are air-conditioned to protect equipment from excessive heat which many jeopardize their performance.
13
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
Concrete Protection
Superstructure for Sub-Station
Sub-Station
Main Gate Filter
Booth
Inspection Shed
Sub-Station Building
Simple Architecture
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
14
Several steel structures had to be manufactured and assembled on site. This task was assigned to our sister company Synergy Petroleum International (SPI). A prominent part was the building of reefer gantries. These structures carry containers that act as cold stores. Therefore, they have to be provided with power and give access to operators. Other structures such as canopies, provided shaded areas at the new entrance gate to the Port.
Steel Works
Steel Erection
Access Stairs
Ready to Receive Cold Stores
Connecting Power
15
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
Men at Work
Reefer Gantries
Steel Shell
Balustrades
Canopy
A Row of Reefers
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
16Generators
Sub-Main Distribution Boards
High Mast MV Cable Lighting Poles Cable Drum
Medium Voltage Switch Gear
Industrial Sockets
MEP Work
A new 11kv sub-station fed from the Sohar Industrial Port (SIP) network was built in order to provide power to the traveling cranes as well as to feed the reefer gantries with necessary electrical supply. Three new security booths were serviced with HVAC, power, firefighting system and domestic lighting. The container yard is lit with a series of high masts (25m) carrying flood lights and aviation lights. Special connections and power outlets were provided to the reefer gantries as these carry cold stores containers. An external firefighting system consisting of pipes and hydrants was integrated with the overall system available in the Port. All installations were properly earthed using copper bars, cables, and rods placed in earth pits. Weighbridges were installed at each gatehouse.
17
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
Reefer Gantries at Night
Transformers
Power Engine
Indoor Transformers
Reefer Gantry Lit
Terminations
Cable Trays
Cold Store Containers
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
18
Our client, OICT, put the management of HSE matters high on their agenda which coincides with Sarooj’s commitment to conduct their business without causing any harm to people, their health, and the environment they work and live in. Of particular importance was the management of hazards deriving from (i) the existing services and their protection (ii) the fact of working near live operations. Permit to work system and clear interfacing mitigated the risks. Consequence management scheme in parallel with a recognition and reward programme, enhanced safety performance.
HSE and Quality
HSE Meeting
Tool Box Meeting
Team Ready to Work
Barricade
19
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
In-Situ Test
Concrete Cubes
Gradation Test
Inside the Laboratory
Testing Compaction
Concrete Slump Test
Testing Joints
Reading Temperature
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
20
A solid HSE plan was drawn and implemented considering the heavy loads to be handled and stored. A strict quality control plan had be adhered to in order to ensure good performance of foundation layers, CBM layer, and asphaltic courses. Furthermore, special attention was given to the concrete sleeper beams.
Inside Site Laboratory
Weighing the Cube
Personal Protective Equipement
Site Laboratory Unit
Column of Sieves
Crushing Concrete Cubes
HSE and Quality (Cont’d)
21
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
V.C. Pandian (Project Manager)
Nayef El Akouri (Electrical Manager) Joseph Bouty (Site Engineer - Civil)
Jad Fadel (Site Engineer - Electrical)
Charbel Ayoub (Electrical Supervisor) Bakhos Maatouk (Civil Supervisor)
Assem El Haj Diab (Site Engineer - Civil)
Asif Mohammed (Site Manager)Jean Pierre Feghali (Site Engineer - Mechanical)
Sandeepa W.K. (QS)
The Team
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
22
Farhan Hamid Ansari(HSE Lead)
Adnan (Assistant Surveyor)
Chockalingham Velu (Site Accountant)
Fadi Ayoub (Concrete Foreman)
Said Mohammad Al Maamari (HSE Officer)
Midhun E.M.(Draftman)
Ramachandran Kaliyath (Earthwork Foreman)
Muhammad Yousaf(Steel Foreman)
Anvarbhi Mansuri(Earthwork Foreman)
Waseem Tariq(Surveyor)
Parvinder Singh(Lab Technician)
Bhumaiyya(Building Foreman)
David Dibb(Plumbing Foreman)
Chandrika Sharma (Carpenter Foreman)
Ragunath Persiyasamy(Project HSE Team Lead)
Sajesh Sadananthan(Surveyor)
Sajid Raza(Lab Technician)
Anbu Kaliyaperumal (Concrete Foreman)
Amjad Hussain (Supervisor)
Georges Chahine (Supervisor)
23
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
Praveen(Time Keeper)
Shaju Veluthedath(Camp Boss)
SC 111 & 112 - SLOW DOWN! ... CHECK POINT
24
Project General Features:
Volume of Cut : 285,000 m3
Volume of Granular Fill : 146,000 m3
Concrete Sleeper Beams : 593 No
Concrete Pavement : 6,153 m3
Reinforced Concrete : 22,000 m3
Cement Bound Materials : 28,000 m3
Asphalt Pavement : 72,000 m3
Interlock Pavement : 23,000 m3
Reefer Gantries : 16 No
Sub-Station Buildings : 3 No
Electrical Cables : 44 Km
Security Booth Buildings : 5 No
25
SAROOJ NEWS
• Majid Al Futtaim Corporation has awarded package one of the prestigious ‘Mall of Oman’. Although the project is
very challenging, our construction team, led by Mr. Mansour El Akouri have decided to embark on it with confidence.
• P hase II of the Oman International Container Terminal (OICT) in Sohar Industrial Port (SIP) has been successfully
completed and commissioned by VC Pandian and his team.
• Final Discussion with Petroleum Development Oman have led to signing Service Contract C311622. Elyas Rouhban
already has started mobilization in terms of training personnel, upgrading equipment, planning and putting the team together.
• Elie Nammour has successfully completed his project in Sur. The Reverse Osmosis Plant has been commissioned
and the production of desalinated water started. In this respect Elie has added SIDEM to the long list of Sarooj satisfied customers. The project was completed without any lost time injury (LTI).
• Wassim Karam, a Senior Project Manager with SNE of Lebanon with whom we worked closely on marine
works in ‘The Wave’ Waterfront Project, has joined our team to work as a Project Manager on the ‘Mall of Oman’. He is welcome to Sarooj family.
• Masirah International continue progressing on their revetment works in the port of Khassab. They are also
renovating the floating pontoons. It is a major contract which they have secured directly with the Ministry of Transport and Communications.
• Sarooj CEO, Mr. Jad Karam and his charming wife Deema were blessed with a new girl in their young family. Lea is
her given name. We congratulate her parents and her sister Danni for this happy arrival.
26
THE GROUP IN MEDIA
27
THE GROUP IN MEDIA
28
Sarooj Construction Company LLC
Oman - Main OfficeP.O.Box 1413 , Postal Code 112 - Ruwi - Sulatante Of Oman
Telephone : (+968) 24 59 60 01 / 02 / 03 - Fax : (+968) 24 59 60 11
Dubai - UAE OfficeJumeirah Lake Towers - Gold (AU) Tower, Office 16B
P.O.Box 625789 - United Arab EmiratesTelephone : +971 4 431 1723 - Fax : +971 4 431 1543
Abu Dhabi - UAE OfficeDana Offices Suites - United Arab Emirates
Telephone : +971 50 3969755 - Fax : +971 4 431 1543
Doha - Qatar OfficePalm Tower, B Wing - 15th Floor, West Bay - Qatar
Tel : +974 403 42044 - Fax : +974 403 42020
www.sarooj.com
CONSTRUCTINGEXCELLENCE
CGRcretivity.com