slab evolution and status at alba synchrotron marta llonch1, fabien rey2, jon ladrera1 1...

1
www.cells.es www.cells.es Marta Llonch 1 , Fabien Rey 2 , Jon Ladrera 1 1 CELLSALBA, 08290 Cerdanyola del Vallès, Spain 2 European Spallation Source ESS AB, S221 00 Lund, Sweden Constructive solution Slab evolution and status at ALBA Synchrotron The 3GeV ALBA synchrotron light facility has currently seven operational stateoftheart phaseI beamlines, comprising soft and hard Xrays. Additionally, two phaseII beamlines are in construction. Since as early as 2012, ALBA Synchrotron has been hosting official users; however, the machine independent slab is being surveyed since 2009 (once the whole installation was finished). The ALBA critical floor slab has an outer radius of 60m and supports the Tunnel, the experimental lines and the service area as well. To achieve the expected accuracy in the subsequent alignment works is essential to have an updated accurate survey reference network installed in the critical slab. An important goal is to be able to track the movement of the slab and consider the components position. In this poster, we present you a report with general information about our slab constructive method, our survey network and an historical evolution report of the ALBA reference network from the very beginning. Abstract Our survey network has an amount of 564 alignment references, approximately. All the alignment points are placed in the ground and walls, along the whole slab. This tool enables us , in one hand, to align and install the Machine and beamlines components, in the other hand to track the movements and evolution of the slab and consider the components realignment. According to the geotechnical studies, the site is composed by a clayey soil with low plasticity, which ensures stability against small movements and traffic. However a proper design of the critical slab is needed. The taken solution for the critical slab floor area was 1 m of reinforced concrete slab resting on a base of 2 m thickness WATER TREATMENT INDEPENDENT SLAB AUXILIARY BUILDING LABORATORIES OFFICES PARKING TECHNICAL BUILDING BUNKER WORKSHOP External radius 60 m Internal radius 36.5 m Total surface 7200 m 2 Max. Floor differential displacements ˂ 2.5 mm/year Network composed of a gravel filling that was properly compacted and protected by two 15 cm poor concrete layers. The whole slab is divided in 16 sectors (about 450 m2 each one). Network evolution Current status The slab differential displacements from the beginning have been almost always within the required parameters. The last April campaign demonstrates the same. During the last two years 20122014, the maximum displacements have been near 3 mm in vertical direction in sector15. This can come from irregular water cycles or the proximity of a cellar in the area. The sector 15 area is where most movements have been recorded during all campaigns. Statistic dX dY dZ Mag Min -0.86 -0.66 -1.80 0.14 Max 0.66 0.69 3.27 3.29 Average -0.00 0.00 0.31 0.98 RMS 0.35 0.30 1.03 1.13 Statistic dX dY dZ Mag Min -0.48 -0.26 -3.33 0.06 Max 0.36 0.32 1.49 3.34 Average -0.02 0.05 -0.23 0.62 RMS 0.19 0.12 0.78 0.81 2012- 2014 2009 - 2010 2010 - 2012 EF 160 EF 203 EF 316 EF 94 Statistic dX dY dZ Mag Min -0.93 -0.62 -3.05 0.26 Max 1.14 0.84 3.70 3.71 Average -0.06 -0.06 -0.32 1.61 RMS 0.35 0.23 1.70 1.76 Front wall – EF 304 0.98 2.07 End station – EF 160 3.06 Distance between points 22572 2014 2012 ΔZ 160 EF 304 EF ΔZ BOREAS End Station BOREAS Front Wall BOREAS area slab tilting during the last two years. Slab tilting = 0.09 mrad* EF 304 EF 160 * Value corresponding to the slab tilting from July 2012 to April 2014 Extreme slab points height evolution. 2009 2010 2011 2012 2013 2014 EF160 0 0.24 2.00 3.77 5.30 6.83 EF316 0 -2.65 -2.93 -3.21 -2.65 -2.09 EF94 0 -0.72 -1.31 -1.90 -1.54 -1.17 EF203 0 -0.83 -0.54 -0.25 0.10 0.45 -4 -2 0 2 4 6 8 ∆Z Coordinate mm SLAB REFERENCE POINTS RELATIVE EVOLUTION THROUGH YARS

Upload: others

Post on 18-Sep-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Slab evolution and status at ALBA Synchrotron Marta Llonch1, Fabien Rey2, Jon Ladrera1 1 CELLSˆALBA, 08290 Cerdanyoladel Vallès, Spain 2 European Spallation Source ESS …

www.cells.eswww.cells.es

Marta Llonch1, Fabien Rey2, Jon Ladrera1

1 CELLS�ALBA, 08290 Cerdanyola del Vallès, Spain2 European Spallation Source ESS AB, S�221 00 Lund, Sweden

Constructive solution

Slab evolution and status at ALBA Synchrotron

The 3GeV ALBA synchrotron light facility has currently seven operationalstate�of�the�art phase�I beamlines, comprising soft and hard X�rays.Additionally, two phase�II beamlines are in construction. Since as earlyas 2012, ALBA Synchrotron has been hosting official users; however, themachine independent slab is being surveyed since 2009 (once the wholeinstallation was finished). The ALBA critical floor slab has an outerradius of 60m and supports the Tunnel, the experimental lines and theservice area as well.To achieve the expected accuracy in the subsequent alignment works isessential to have an updated accurate survey reference networkinstalled in the critical slab. An important goal is to be able to track themovement of the slab and consider the components position. In thisposter, we present you a report with general information about our slabconstructive method, our survey network and an historical evolutionreport of the ALBA reference network from the very beginning.

Abstract

Our survey network has an amount of 564 alignment references,approximately. All the alignment points are placed in the ground and walls,along the whole slab. This tool enables us , in one hand, to align and installthe Machine and beamlines components, in the other hand to track themovements and evolution of the slab and consider the componentsrealignment.

According to the geotechnical studies, the site iscomposed by a clayey soil with low plasticity,which ensures stability against small movementsand traffic. However a proper design of thecritical slab is needed. The taken solution for thecritical slab floor area was 1 m of reinforcedconcrete slab resting on a base of 2 m thickness

WATER TREATMENT

INDEPENDENT SLAB

AUXILIARY BUILDING

LABORATORIES

OFFICES

PARKING

TECHNICAL

BUILDING

BUNKER

WORKSHOP

External radius 60 m

Internal radius 36.5 m

Total surface 7200 m2

Max. Floor differential displacements ˂ 2.5 mm/year

Network

composed of a gravel filling that was properly compacted and protected bytwo 15 cm poor concrete layers. The whole slab is divided in 16 sectors(about 450 m2 each one).

Network evolution Current statusThe slab differential displacements from the beginninghave been almost always within the required parameters.The last April campaign demonstrates the same. Duringthe last two years 2012�2014, the maximum displacementshave been near 3 mm in vertical direction in sector15. Thiscan come from irregular water cycles or the proximity of acellar in the area. The sector 15 area is where mostmovements have been recorded during all campaigns.

Statistic dX dY dZ Mag

Min -0.86 -0.66 -1.80 0.14

Max 0.66 0.69 3.27 3.29

Average -0.00 0.00 0.31 0.98

RMS 0.35 0.30 1.03 1.13

Statistic dX dY dZ Mag

Min -0.48 -0.26 -3.33 0.06

Max 0.36 0.32 1.49 3.34

Average -0.02 0.05 -0.23 0.62

RMS 0.19 0.12 0.78 0.81

2012

-20

1420

09 -

2010

2010

-20

12

EF 160EF 203

EF 316EF 94

Statistic dX dY dZ Mag

Min -0.93 -0.62 -3.05 0.26

Max 1.14 0.84 3.70 3.71

Average -0.06 -0.06 -0.32 1.61

RMS 0.35 0.23 1.70 1.76

Front wall – EF 304 0.982.07

End station – EF 160 3.06

Distance between points 22572

2014

2012ΔZ

160 EF

304 EFΔZ

BOREAS End Station

BOREAS Front Wall BOREAS area slabtilting during the lasttwo years.

Slab tilting = 0.09 mrad*

EF 304EF 160

* Value corresponding to the slab tilting from July 2012 to April 2014

Extreme slab points height evolution.

2009 2010 2011 2012 2013 2014

EF160 0 0.24 2.00 3.77 5.30 6.83

EF316 0 -2.65 -2.93 -3.21 -2.65 -2.09

EF94 0 -0.72 -1.31 -1.90 -1.54 -1.17

EF203 0 -0.83 -0.54 -0.25 0.10 0.45

-4-202468

∆Z

Coo

rdin

ate

mm

SLAB REFERENCE POINTS RELATIVE EVOLUTION THROUGH YARS