site logistics planning for high rise building ... · accommodating my presentation time. thank you...

115
Site Logistics Planning for High Rise Building Construction on Congested Downtown Sites by Hiba Mahboob Ali A thesis submitted in conformity with the requirements for the degree of Master of Applied Science Department of Civil & Mineral Engineering University of Toronto © Copyright by Hiba Mahboob Ali 2018

Upload: others

Post on 29-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

Site Logistics Planning for High Rise Building Construction on Congested Downtown Sites

by

Hiba Mahboob Ali

A thesis submitted in conformity with the requirements for the degree of Master of Applied Science

Department of Civil & Mineral Engineering University of Toronto

© Copyright by Hiba Mahboob Ali 2018

Page 2: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

ii

Site Logistics Planning for High Rise Building Construction on

Congested Downtown Sites

Hiba Mahboob Ali

Master of Applied Science

Department of Civil & Mineral Engineering

University of Toronto

2018

Abstract

Construction planning for tall buildings becomes more complex with small land parcels in urban

cores, fast-paced schedules and a growing number of domains involved in decision-making. This

research consists of evaluating the literature regarding construction planning techniques,

decision-making models, constraints in the current construction industry and holding interviews

with domain experts to summarize their implicit knowledge regarding construction site logistics

planning. It was found that there is no existing tool that adequately optimizes a construction site

plan as all research is carried out in isolation, only optimizing a certain piece of equipment or

operation. In this research, a multi-domain decision making tool was developed to assist project

planners in site planning on complex construction projects so multiple domain decisions and

impacts are simultaneously realized, and a framework for construction site planning that can be

applied to the industry was introduced.

Page 3: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

iii

Acknowledgments

During my bachelors at the University of Toronto, I was sure I would not pursue a masters’

degree. In 2nd year, I met Professor Brenda McCabe in the construction management course. Not

only did I love the course and identify her as a mentor for myself and all the females in the

program, I also knew I would only do a masters’ degree under her supervision. Time passed, and

my feelings towards research did not change. I was sure I couldn’t do it.

After graduating from my bachelor’s, Professor McCabe saw the potential in me to be passionate

about construction management and took me in as one of her research assistants. It is with deep

gratitude and utmost unbelief that I say my success is entirely due to Professor McCabe, her

unwavering belief in me, her patience, guidance and her passion for improving everything

around her. She has inspired me since 2nd year, during monument meetings, weekly drop-ins

from us whenever she was available to chat about life, and through the last 3 years of my time as

a research assistant. Thank you for being so sincere, always encouraging me and for guiding me

through the hardest times in my life without losing faith in me.

Thank you to Professor Pressnail for agreeing to be my second reader in such short notice, for

accommodating my presentation time. Thank you for enabling me to graduate and asking the

most interesting questions during my presentation. You have made me so excited to work in this

field of knowledge.

Thank you to my research group, some who I got to start my journey off with and some who I

barely got to spend enough time with and still had the opportunity to become friends with. Thank

you, Yuting Chen and Hesam Hamledari, for taking the time to talk with me, and teach about

their research, things at the university and life in general. Thank you, Patrick Marquis, for

partnering with me on literally everything and going through it all with me, from the very start.

Kamellia Shahi and Eric Li for motivating me and checking in on me. Pouya Zangeneh, for

being the best desk buddy and making everything just a bit lighter. Finally, thank you Arash

Shahi, for laying down the groundwork for so much of our success at conferences and for all the

feedback for me.

Thank you to my friends, who stood by me, as I put my life on hold to get it all back together,

encouraged me in ways I didn’t know I needed, and monthly glared me into getting it done—

Page 4: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

iv

whatever it might be. Thank you to my parents and my sister who have had the utmost patience

and understanding during my time in university and pushed me towards always striving for

better.

Thank you to Rescon, Daniels and Menkes for motivating this research and providing time and

resources for the information required to develop the framework developed in this research.

Finally, I want to thank Nelly Pietropaolo, who goes out of her way to make sure school is

running and my god is it running, but also makes sure her door is always open for anyone who

wants to talk. Thank you for all the times spent talking about events, volunteering, how to get

involved, camping, but most of all just life. Thank you for making my time at the University so

memorable.

Page 5: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

v

Table of Contents

Contents

Acknowledgments .......................................................................................................................... iii

Table of Contents ............................................................................................................................ v

List of Tables ................................................................................................................................. ix

List of Figures ................................................................................................................................. x

List of Appendices ........................................................................................................................ xii

Chapter 1 Introduction .................................................................................................................... 1

1 Introduction ................................................................................................................................ 1

1.1 Objectives ........................................................................................................................... 2

1.2 Methodology ....................................................................................................................... 2

1.3 Industry Partners ................................................................................................................. 3

1.4 Organization of Thesis ........................................................................................................ 3

Chapter 2 Challenges of Site Logistics for Tall Building Construction ......................................... 6

2 Challenges of Site Logistics for Tall Building Construction ..................................................... 6

2.1 Abstract ............................................................................................................................... 6

2.2 Introduction ......................................................................................................................... 6

2.3 Model Inputs ....................................................................................................................... 7

2.3.1 Object Storage Location Definitions ...................................................................... 8

2.3.2 Object Definition .................................................................................................... 9

2.3.3 Time Element ........................................................................................................ 10

2.3.4 Constraints ............................................................................................................ 12

2.4 Program Functions ............................................................................................................ 13

2.4.1 Model Logic .......................................................................................................... 13

2.4.2 Object Supply and Space Updating ...................................................................... 14

Page 6: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

vi

2.5 Model Output .................................................................................................................... 15

2.6 Shortcomings .................................................................................................................... 15

2.7 Future Developments ........................................................................................................ 16

2.7.1 Special Considerations for Tall Buildings ............................................................ 17

2.7.2 Proposed Model .................................................................................................... 18

2.8 Conclusion ........................................................................................................................ 20

Chapter 3 Interaction Diagrams for Multi-Domain Decision Making Processes ......................... 22

3 Interaction Diagrams for Multi-Domain Decision Making Processes ..................................... 22

3.1 Abstract ............................................................................................................................. 22

3.2 Introduction ....................................................................................................................... 22

3.3 Research Method .............................................................................................................. 23

3.4 Literature Review .............................................................................................................. 25

3.4.1 Information Exchange Models .............................................................................. 25

3.4.2 Equipment Management ....................................................................................... 26

3.4.3 Construction Logistics Planning ........................................................................... 27

3.4.4 Discussion ............................................................................................................. 29

3.5 Decision Making Tools ..................................................................................................... 30

3.5.1 Weighted Decision Matrix .................................................................................... 30

3.5.2 Decision Tree Diagram ......................................................................................... 30

3.5.3 Influence Diagrams ............................................................................................... 31

3.5.4 Bayesian Networks ............................................................................................... 33

3.5.5 Interaction Diagrams ............................................................................................. 34

3.5.6 Decision Making Tools Comparison .................................................................... 36

3.6 Interaction Diagrams ......................................................................................................... 37

3.6.1 Developing the Construction Site Logistic Interaction Diagram .......................... 38

3.6.2 Construction Site Logistics Interaction Diagram .................................................. 40

Page 7: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

vii

3.6.3 Case Study: 87 Peter Street, Toronto, ON ............................................................ 42

3.6.4 Improvements from Existing Models ................................................................... 46

3.7 Conclusion ........................................................................................................................ 48

Chapter 4 Site Logistics Planning with an Interaction Diagram ................................................... 51

4 Site Logistics Planning with an Interaction Diagram .............................................................. 51

4.1 Abstract ............................................................................................................................. 51

4.2 Introduction ....................................................................................................................... 51

4.3 Research Method .............................................................................................................. 52

4.4 Literature Review .............................................................................................................. 53

4.5 Planning Process ............................................................................................................... 54

4.5.1 Traffic Management Plan ..................................................................................... 55

4.5.2 Soil Remediation ................................................................................................... 56

4.5.3 Shoring Design ...................................................................................................... 57

4.5.4 Temporary Site Power .......................................................................................... 57

4.5.5 Crane Plan ............................................................................................................. 58

4.5.6 Hoist Plan .............................................................................................................. 58

4.5.7 Concrete Pump Plan .............................................................................................. 58

4.6 Interaction Diagram .......................................................................................................... 59

4.6.1 All Factors ............................................................................................................. 60

4.6.2 Traffic Management Factors ................................................................................. 62

4.6.3 Crane Factors ........................................................................................................ 63

4.6.4 Concrete Pump Factors ......................................................................................... 65

4.6.5 Hoist Factors ......................................................................................................... 66

4.7 Relationship Significance ................................................................................................. 69

4.8 Conclusion ........................................................................................................................ 70

Chapter 5 Conclusion .................................................................................................................... 71

Page 8: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

viii

5 Conclusion................................................................................................................................ 71

5.1 Research Contributions ..................................................................................................... 71

5.2 Limitations of Research .................................................................................................... 73

5.3 Future Research ................................................................................................................ 73

5.3.1 Programming from Tacit Knowledge ................................................................... 74

References ..................................................................................................................................... 86

Appendices .................................................................................................................................... 91

Page 9: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

ix

List of Tables

Table 1: Model Logic Summary ................................................................................................... 14

Table 2: Papers Modelling Types of Material Storage and Model Updating ............................... 28

Table 3: Weighted Decision Matrix Example .............................................................................. 30

Table 4: Traditional Nodes ........................................................................................................... 32

Table 5: Relationships ................................................................................................................... 33

Table 6: Interaction Diagram Features ......................................................................................... 35

Table 7: Benefits and Shortcomings of Decision Making Tools .................................................. 36

Table 8: Situation where Relationship Significance Varies ......................................................... 70

Table 9: Step 1 – Retrieve All Inputs ............................................................................................ 77

Table 10: Step 2 - User Inputs ...................................................................................................... 77

Table 11: Step 3 - Choose Equipment Combination .................................................................... 77

Table 12: Step 4 - Calculate Total Lift Times for 4 Scenarios for Each Equipment Combination

....................................................................................................................................................... 77

Table 13: Step 5 - Display Results ................................................................................................ 82

Page 10: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

x

List of Figures

Figure 1: Site Layouts with Different Time Dimensions.............................................................. 11

Figure 2: Model Comparison of Storage Type and Feedback ...................................................... 16

Figure 3: Proposed Model Framework ......................................................................................... 20

Figure 4: Decision Tree Example ................................................................................................. 31

Figure 5: Influence Diagram Example .......................................................................................... 32

Figure 6: Bayesian Network Example .......................................................................................... 34

Figure 7: Interaction Diagram Example ....................................................................................... 35

Figure 8: Relationship Significance Survey ................................................................................. 40

Figure 9: Construction Site Logistics Interaction Diagram .......................................................... 41

Figure 10: Site Plan ....................................................................................................................... 43

Figure 11: Proposed Site Plan Using Interaction Diagram ........................................................... 45

Figure 12: Actual Site Plan ........................................................................................................... 46

Figure 13: Actual vs Predicted Crane Cycle Lift Times ............................................................... 47

Figure 14: Site Interaction Diagram ............................................................................................. 60

Figure 15: Hoist Outrigged Platform ............................................................................................ 68

Figure 16: Relationship Rating Difference ................................................................................... 69

Figure 17: Crane and Concrete Pump Program Decision Flowchart ............................................ 75

Figure 18: Crane Database Summary ........................................................................................... 83

Figure 19: KNF 336i-16 Load Chart ............................................................................................ 83

Figure 20: Concrete Pump Database Summary ............................................................................ 84

Page 11: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

xi

Figure 21: Concrete Bucket Data Summary ................................................................................. 84

Figure 22: Radial and Tangent Movement of Hook ..................................................................... 92

Figure 23: Vertical Movement of Hook ........................................................................................ 93

Figure 24: All Building Factors Significance Ratings .................................................................. 94

Figure 25: Crane Factor Significance Ratings .............................................................................. 94

Figure 26: Hoist Factor Significance Ratings ............................................................................... 95

Figure 27: Traffic Management and Concrete Pump Factors Significance Ratings .................... 96

Figure 28: Crane 1 - KNF 336i-16 Load Chart ............................................................................. 97

Figure 29: Crane 2, 3 and 6 - Pecco PC 2000 ............................................................................... 97

Figure 30: Crane 4- Peiner SK315Figure 31: Condor FZ 001 ...................................................... 98

Figure 32: Crane 7 - Comedil CTL-250 ....................................................................................... 98

Figure 33: Crane 8 - AVRO LJK 160 ........................................................................................... 99

Figure 34: Crane 9 - Pecco PC 1400 ............................................................................................. 99

Figure 35: Crane 10 - Pecco PC 1200 ......................................................................................... 100

Figure 36: Crane 11 - Pecco PC 3600 ......................................................................................... 100

Figure 37: Crane 12 and 16 - Comedil CTT 331 ........................................................................ 101

Figure 38: Crane 13 - Peiner SK 415 .......................................................................................... 102

Figure 39: Crane 14 - Pecco Sn 406 ........................................................................................... 103

Figure 40: Crane 15 - Pecco PC 3000 ......................................................................................... 103

Page 12: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

xii

List of Appendices

Appendix A: Crane Cycle Equations ............................................................................................ 91

Appendix B: Charts Showing Significance Ratings for Relationships ......................................... 93

Appendix C: Crane Load Charts ................................................................................................... 96

Page 13: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

1

Chapter 1 Introduction

Introduction

Tall building construction is increasing around the world as urban center population grows and

densification is required. Tall buildings are defined subjectively according to their height relative

to the height of surrounding buildings, their footprint to height ratio, and the technologies being

used (Council of Tall Buildings and Urban Habitat, 2018). Although tall building construction

allows a more efficient use of the land parcels, many challenges are introduced during the

planning, construction and operation phases of the building.

Some of these challenges were recognized by the Building Tall research group and turned into

research initiatives, including the analysis of cladding systems, a benchmarking of the permitting

process for the construction of tall buildings in Toronto, and stack effect management. This

research focuses on the optimization of site logistics planning for the construction of tall

buildings in urbanized areas.

With congested construction sites and smaller land parcels, there is less area at the exterior of the

building footprint to store materials during construction. This was investigated through a review

of the literature. Through interviews with industry professionals, it was found that storage during

the construction phase of a building was only one logistic that needed to be improved. There was

no established industry method for site planning. Instead, each company and expert has their own

process that evolved over time and is passed from person to person informally. This research

focuses on evaluating the literature, interviewing industry professionals, and collecting site data

to create a tool for site logistics planning that streamlines the process across the industry.

Construction logistics consists of decisions across multiple stakeholders, domains and trades.

The project manager is tasked with coordinating the trades, clients, engineers and architects, and

the government. Every decision that is made in any domain has an impact on the options that are

available for other decisions in the project. As there is currently no standardized or documented

Page 14: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

2

way for site planning to occur, the best decisions for each project entirely rely on the experience

of the project manager.

1.1 Objectives

The purpose of this research is to produce a method for construction site logistics planning that

aids project managers to make decisions. This is to improve communication between

stakeholders in the early stages of the construction project, reduce costs by decreasing change

orders during the construction process, and ensure a project meets its goals.

The main goals are to:

1. Compare methods currently used for construction planning in literature and in the field

and summarize the findings

2. Observe site operations on various projects in Toronto and identify planning procedures

for high-rise construction in Toronto

3. Create a tool that visually shows the impact of decisions across multiple domains for any

decisions with multiple stakeholders, summarizes common site logistics planning steps

across sites and supports decision making

4. Apply the tool to construction logistics planning in Toronto

The scope of this research focuses on decision-making for construction logistics for high-rise

buildings in Toronto. The current trends for construction planning and material storage in urban

areas are explored. Further details about the scope can be found in chapter 3.3.

1.2 Methodology

This research sought to incorporate findings in the academic literature with the experience of

industry professionals to formulate a construction site logistics planning process. First, the

literature was reviewed to summarize the research that exists. Topics of interest included interior

storage, identifying model types and their features, equipment planning methods, project

Page 15: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

3

management techniques, and decision-making tools. The shortcomings and strengths of these

topics are outlined in the following chapters.

Industry professionals were interviewed to identify perceived areas of research. It was

established that there is no industry-wide process used by project managers to plan a project, and

that most decisions were made based on learned knowledge. Once this gap was identified,

decision-making tools were analyzed to apply a tool for logistics planning use. There were no

tools that achieved what was required for project planners, so an interaction diagram was created.

Factors impacting site logistics decisions for vertical transportation of materials were identified

through interviews and site visits. These were applied in the creation of the site logistics planning

interaction diagram. The interaction diagram was reviewed by industry professionals and

revisions were made for ease of use and specificity. The diagram was then validated through

surveys and feedback from planners.

The final interaction diagram for construction site logistics is presented and applied to a case

study. Decisions made without the interaction diagram are compared to show how it simplifies

decision making for project managers, supplies reasoning for decisions, and summarizes the

impact of a decision on other domains. Future research is identified at the end of this thesis.

1.3 Industry Partners

The Residential Construction Council of Ontario (RESCON) is a board of directors that

represents builders, developers, and its other members on construction issues and purses research

to improve construction efficiency. In this research, RESCON is the industry partner, along with

its members The Daniels Corporation and Menkes Developments. Site logistics planning in

urban areas was identified as requiring a more efficient process as tall building construction

introduces new challenges in planning.

1.4 Organization of Thesis

This document is a paper-based thesis comprising three independent paper chapters, an

introductory chapter that explains the overall research, a chapter that provides guidance in the

Page 16: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

4

form of pseudocode for the development of a software to support the automation of planning for

vertical transportation, and a conclusions chapter that summarizes the findings and contributions.

Due to the paper-based format, there exists some repetition but efforts have been made to

minimize it.

Chapter 2 comprises a paper entitled Challenges of Site Logistics for Tall Building Construction,

which was presented at and published in the 2016 CSCE Conference proceedings. It summarizes

the limitations found in storage research and practices on construction sites currently, identifies

existing model features in the literature, analyzes their uses, and presents a proposed framework

for a model to automate site planning.

Chapter 3, entitled Interaction Diagrams for Multi-Domain Decision Making Processes, presents

a method for multi-domain decision making in planning, construction and operations. This is the

interaction diagram, a graphical model that shows the impacts of a decision in one domain on

decisions or factors within the same and other domains. An interaction diagram is constructed for

construction site logistics planning with a focus on vertical transportation and a case study is

presented to compare decisions made by using the interaction diagram to decisions that were

carried out during the project. This paper is expected to be submitted to Journal of Engineering

Education.

Chapter 4, Site Logistics Planning with an Interaction Diagram, details the construction logistics

planning interaction diagram developed in Chapter 3 with a focus on the vertical transportation

of materials and personnel. It explains situations for each factor and the impact it can have on the

rest of the project, as well as presenting steps to take when planning a construction project. It

will be submitted to CSCE 2019 Conference.

In the concluding chapter 6, the findings and limitations of this research are summarized.

Contributions to the body of knowledge are listed and future research to follow the findings is

mentioned. A pseudocode for optimizing concrete pump and crane operations using the factors

from the site logistics framework in Chapter 4 and equations from literature is introduced.

Page 17: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

5

Databases for concrete pump and the construction crane, summarized from manufacturer data,

are presented.

The appendices comprise collected data and references. Appendix A shows the comparison of

real crane lift times compared with predicted crane lift times using equations from the literature.

Appendix B summarizes the ratings for the significance of relationships for the construction site

logistics interaction diagram from surveys with experts. Appendix C shows crane load charts that

were used to build the crane database to be used in the program.

Page 18: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

6

Chapter 2 Challenges of Site Logistics for Tall Building Construction

The entirety of Chapter 2 is an article published in the proceedings from CSCE 2016: London

conference titled Challenges of Site Logistics for Tall Building Construction. Although there are

many authors, the work was primarily the undertaken by the first author.

Ali, H., Marquis, P., McCabe, B., Shahi, A., Lyall, R., and Francavilla, J. “Challenges of Site

Logistics for Tall Building Construction”. CSCE Conference. London, Ontario, June 1-4, 2016.

Challenges of Site Logistics for Tall Building Construction

2.1 Abstract

The construction of tall buildings has become a necessity in crowded urban cores, such as the

Greater Toronto Area. The result of denser population and shifting construction guidelines,

however, is the decrease of available space for building processes. For this reason, challenges in

planning and storage during construction phases occur. Reducing the cost of storage and the

distance of materials and equipment from the work area, while increasing site productivity

through scheduling and planning, is known as site logistics. This paper examines the existing site

logistics processes as well as site layout and optimization models that can be used for

construction of tall buildings. Advantages and shortcomings of each site logistics planning

strategy are noted and a set of recommendations are provided for better utilization of site area

during the construction of tall buildings. Finally, this paper outlines the use of interior storage

spaces as a viable solution for reducing the construction footprint of tall buildings. Factors that

need to be considered for including interior storage in existing site layout and optimization

models are also examined.

2.2 Introduction

The basis of site logistic planning for the materials and equipment (objects) that need to be

located on-site is a compromise between object size and shape, duration of storage, location of

Page 19: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

7

use, and available space on the site. Many models have been created for construction site logistic

planning to increase productivity and reduce costs and project duration. These models aim to

create layouts for construction projects that aid in placing objects close to the area of use,

ensuring an adequate supply of objects is available as needed to stay on schedule (Cheng and

Kumar, 2015). The models consider site space, schedule, and constraints as the basis of their

logic.

Early models used a simple framework where objects were placed outside the building footprint

on a first-come, first-served basis (Sadeghpour et al., 2004). Because space was readily available

and therefore not a constraint, the objective was to minimize travel time to bring the objects to

the work areas where they were needed (Tommelein and Zouein, 1993). While very useful in

some circumstances, the constructors of tall buildings in urban areas typically have to deal with

very restricted space, and congestion quickly becomes a serious problem (Jung et al., 2014).

Hence, more recent models have added features that are better equipped to address congested

conditions.

Although several models exist, they are often made for specific situations and cannot be used

seamlessly across all building projects. It is even more difficult to create such a model with the

continuous changes that the construction industry faces, ranging from policy modifications to

varying building environments and new construction methods.

The objective of this paper is to review existing models in the literature, analyze their

shortcomings, and provide recommendations for future models with a focus on tall building

construction in the Greater Toronto Area (GTA). The existing models are further compared

according to their inputs, program functions, and model outputs so a systematic analysis can be

presented.

2.3 Model Inputs

Every model needs inputs to define the situation. Every construction site, however, is unique due

to its location, project details, subsurface conditions, regulatory constraints, labour and material

Page 20: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

8

practices, and so forth. Fortunately, there are also some similarities across inputs used in many

models. The following section outlines and compares inputs used in existing models.

2.3.1 Object Storage Location Definitions

There are several factors involved in defining layout locations in a construction site. First, the

unique project details, such as site plans and schedules, have to be uploaded to the model. These

are obtained from various forms of documentation including drawings, spreadsheets and reports

(Sadeghpour et al., 2004). Once details of each construction project have been defined, a location

must also be represented.

There are generally three ways that locations are represented. First, predetermined locations can

be used to represent on-site storage areas (Wang et al., 2014). These blocks have a predefined

size and are used to store objects of one type at any point in time (Cheng and Kumar, 2015). This

means that a large space used to store a small amount of material is not available for other

materials as the block is used and therefore unavailable. Second, available space is described

using a grid. Objects can be located across multiple grids depending on their size, shape, and

other parameters (Sadeghpour et al., 2004). Again, once a grid is used, it is unavailable for other

materials. The final approach is to treat the construction site as a continuous space, allowing the

placement of objects anywhere there is space available. In this case, the model is able to

represent the actual area used, thereby making better use of the available space.

These various representations of space allow different levels of granularity for placing objects,

however, each comes with advantages and drawbacks. Models using predetermined locations are

computationally light as there are a limited number of areas where objects can be placed. The

biggest shortcoming is that it permits wasted space if objects are smaller than the predefined

locations. The grid system allows the user to define the size of the grid, thereby providing a finer

locating system if smaller grids are selected. However, no locations between the grids can be

used (Sadeghpour and Andayesh, 2015). A more accurate method for placement lies with the

continuous representation of space as it allows objects to be located anywhere on the site to get

Page 21: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

9

the optimal location with exact shapes. As expected, this method proves to be the most time-

consuming and computationally intensive to carry out (Zouein et al., 2002).

While many models use only space exterior to the building footprint, some also incorporate

interior space, adjacent space, and temporary off-site locations (Cheng and Kumar, 2015). The

use of exterior space is common, however, the congestion found in urban construction areas has

decreased available storage space exterior to the building footprint. For example, Toronto now

requires all new projects in the downtown area to extend the building footprint to the property

boundaries, leaving no space on the lot for material staging. This has prompted construction

managers in dense urban areas to look for storage space within the building. To date, models

have only used interior storage space as a secondary location in cases of over-ordering (Cheng

and Kumar, 2015). The use of adjacent land, such as roads and sidewalks, extends the site parcel

for easy storage, but requires permits and has associated rental costs. Finally, the use of off-site

temporary locations has also only been used as a last resort where there is no space available on

site and the objects have already been shipped (Cheng and Kumar, 2015). The use of these

secondary locations creates a need for two or three iterations of object handling, which decreases

the efficiency of the site logistics model as time and resources are allocated towards the

relocation.

2.3.2 Object Definition

After defining the location type, the definition of on-site objects is undertaken. Some parameters

that characterize objects include their shape, mobility and typology (Sadeghpour and Andayesh,

2015).

The shape of an object includes defining the object as a point, an orthogonal box or as its actual

shape. The point location only works for very simple sites with sufficient space, or where

predefined blocks are used. In this case, the predefined location must be able to accommodate

the largest object (Li and Love, 1998). The orthogonal geometry models objects as rectangles

and ensures no overlap on limited sites. They lead to suboptimal layouts because only two

orientations are possible, resulting in wasted space (Zouein et al., 2002). Finally, the

Page 22: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

10

representation of the objects as their actual shape leads to the creation of complex algorithms, but

is necessary for congested sites (Sadeghpour and Andayesh, 2015).

An object’s mobility ranges from stationary to self-propelled objects. The modelling of

stationary objects, like cranes, is relatively straightforward, however, their location cannot be

changed once in place. On the other hand, moving objects like trucks requires programs to model

trajectories of the objects at various times throughout the project, ensuring that no clashes occur

(Tommelein and Zouein, 1993). In between the two, lie objects that can be relocated, such as

building materials. Finally, the object type classifications include construction equipment,

temporary facilities, construction materials, workspace, and access paths. These are necessary for

specifying handling procedures.

2.3.3 Time Element

There are three types of time breakdowns, namely, static, staged, and dynamic (Sadeghpour and

Andayesh, 2015). The static time representation allows the model to only create one layout for

the entire duration of the project, assuming objects remain at their locations for the entire

duration of construction. The staged representation allows users to breakdown the project into

times representing major changes with respect to site storage. The dynamic breakdown allows

the project to be modelled in real-time, showing continuous changes over the project duration.

The most efficient breakdown happens to be the dynamic approach. It incorporates the

consumption of objects as activities proceed, allowing the reuse of available space for future

storage (Tommelein and Zouein, 1993). Figure 1 shows the differences in site layouts using the

various approaches. Figure 1a shows the size and shape of each object, as well as the start and

end date. For instance, object A requires six grid boxes and arrives on day zero. Object A is

consumed by day four. Figure 1b, 1c, and 1d show the static, staged and dynamic time

breakdown approach, respectively. The staged approach is split at day 3, allowing 2 stages

during the construction project. By incorporating the dynamic approach, the space allocated to

object A during days 0-4, can be used to store other objects once A is completed.

Page 23: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

11

Figure 1: Site Layouts with Different Time Dimensions

As can be seen by the maximum number of boxes required in each time breakdown in Figure 1b,

1c and 1d, the static approach requires the most area to accommodate all site objects at 17 grid

boxes, while the dynamic approach, with a maximum of 11 grids occupied, requires the least.

The static time representation is not sufficient to create the object layout for complex projects

with limited space since they require the reuse of space. The staged procedure creates solutions

at predefined times of the project stages. It lengthens object on-site duration across the entirety of

a stage, but provides a better solution than the static approach. Finally, though the dynamic

model is the best solution as it changes layout whenever any object is consumed, it requires

Page 24: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

12

significant computing efforts (Jung et al., 2014). To minimize these efforts, a discrete event

model can be used to model every change instead of every moment of a project (Tommelein and

Zouein, 1993).

2.3.4 Constraints

The limiting factors of site logistics that allow the optimization within the model are known as

constraints. These constraints are project and object specific, acting as the interaction between

objects and available locations. Although the main objective of a site logistics model is to

increase productivity by decreasing travel times, other objectives such as, providing work areas,

and increasing security also exist (Li and Love, 1998). Due to this, constraints can be set up as

decreasing travel distance, providing buffer zones around objects or areas, creating visibility of

certain objects for security reasons and storing objects inside spaces (Huang and Wong, 2015).

Consequently, the qualitative constraints defined above are translated into optimization formulas

in the form of utility functions. The utility functions add a weight to each constraint representing

their importance in the project. An example of a utility function is shown in Equation 1

(Sadeghpour and Andayesh, 2015). The representation of constraints in the utility function is a

numerical way to analyze trade-offs.

+ Pkw ijij

Equation 1

where w is the weight given to closeness between objects and k is the numerical representation

of a constraint being fulfilled. P is the penalty and ij refer to objects i and j.

In multi-objective problems with more than one constraint, violations are likely to occur as it is

harder to satisfy all constraints (Marler and Arora, 2004; Zolfagharian and Irizarry, 2014). Under

these circumstances, an unconstrained solution with penalties may be preferred (Smith and Coit,

1997; Wang et al., 2014). An example of a penalty may be in the form of object relocation which

may be necessary if objects cannot be placed close to their immediate work area due to existing

on-site objects. Hence, the penalties can be added to the utility function, shown as P in Equation

Page 25: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

13

1 (Sadeghpour and Andayesh, 2015). Unfortunately, the difficulty of creating efficient penalty

equations due to optimal solutions being almost infeasible is noted (Smith and Coit, 1997).

The constraints are vital in tall buildings as productivity greatly decreases as buildings get taller.

This is due in part to the longer vertical transportation times for site personnel and objects from

the ground to the construction floor. The objects that limit vertical movement are cranes and

hoists. There are additional restrictions, such as limited work hours in accordance with local

noise by-laws, the need to acquire air rights for crane swings over neighboring properties, and

scheduling deliveries around rush hour traffic. Hence, there is a need to not only optimize the

location of these objects, but also their operations to ensure that objects are moved to required

location in time for use in on-going activities (Heikkilä et al., 2013). The operations can be

optimized using penalty functions as well (Wang et al., 2014).

2.4 Program Functions

Once users have input project specific details, the solution is dependent on the inner workings of

the program. The form of logic used by the model has a direct effect on the solution and the time

it takes a computer to solve the problem. Additionally, the object handling module has an impact

on the amount of space required on a site. The details of these mechanisms are discussed next.

2.4.1 Model Logic

The type of logic used is heavily dependent on the required level of detail, as well as the inputs

of the model. The simplest form of modelling is on an order basis, locating objects at optimal

available locations based on the order in which they are input to the program. This is a first-

come, first-served method, which can cause conflicts in complex projects in terms of the

ordering method actually used. Some proposed ordering methods for the objects include

chronological arrival, size, and on-site duration (Sadeghpour et al., 2004). Unfortunately, as this

is a step-by-step process, larger amounts of objects slows down the program.

A second approach is the incremental optimization technique, usually carried out with genetic

algorithms (GA) (Marler and Arora, 2004). The program creates a solution satisfying some of the

Page 26: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

14

constraints. After this, it creates more solutions in increments, replacing the prior solution if the

posterior one is found to be better. The program stops creating solutions when it reaches a

threshold. This method allows the program to obtain a local optimized solution and is suitable for

sites with many objects as added data does not have a significant time effect on the program.

Finally, the program can also be designed to find the absolute optimal solution. Although this is

the best method, it requires the most amount of time, effort and computational power, sometimes

producing results that are only marginally better than the incremental optimization approach. The

approaches used for optimization in some existing models are summarized in Table 1.

Table 1: Model Logic Summary

Source Logic Type Visual Representation

Tommelein and Zouein, 1993 Order basis ✓

Li and Love, 1998 Incremental approach (GA)

Zouein et al., 2002 Incremental approach (GA)

Sadeghpour et al., 2004 Order basis (fuzzy logic) ✓

Sadeghpour et al., 2006 Order basis ✓

Said and El-Rayes, 2010 Incremental approach (GA)

Said and El-Rayes, 2012 Incremental approach (GA)

Heikkilä et al., 2013 Order basis ✓

Jung et al., 2014 Order basis (agent-based method)

Cheng and Kumar, 2015 Order basis

2.4.2 Object Supply and Space Updating

As sites cannot accommodate nor need to store their total objects throughout the entirety of the

project, a staggered ordering method is preferred. An approach that has been extensively used is

the just in time (JIT) ordering method, often associated with lean construction (Issa, 2013;

Marhani et al., 2012). This method allows sites to order only required objects for each phase,

decreasing the stock of objects on-site and thus the need for on-site storage space (Bertelsen and

Nielsen, 1997). This method has been reported to decrease schedule delays and overall project

costs.

In conjunction with the JIT method, space updating can be used. The space updating can be

automatic or manual, allowing the model to recognize available space for future ordering

Page 27: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

15

(Heikkilä et al., 2013). A limited number of current models have built-in updating. The updating

allows re-optimization of the remaining site area as changes from the initial plan occur over the

duration of the construction project (Tommelein and Zouein, 1993).

2.5 Model Output

The pre-existing models have had two substantial ways of representing results. Firstly, the results

can be formatted as a spreadsheet, assigning a certain amount of objects to predetermined

locations on certain days. Although the spreadsheet summarizes the results very clearly, it does

not create a visual representation of the site.

A more recent method is a 3-dimensional (3D) model with built-in information, known as

building information models (BIM) (Cheng and Kumar, 2015). BIM can graphically show

locations of objects over the course of the project and allow the user to identify any assignments

they may want to change, as well as locations where objects can be moved to (Wang et al.,

2014). The 3D model is easier to use in presenting the site and analyzing the 3D changes for a

dynamic model, however, it has been found that 2-dimensional (2D) models are easier for users

to understand (Heikkilä et al., 2013). In recent years, the movement away from computer-

assisted drawings (CAD) into BIM software, which allows 3D and 2D imaging from the same

model, has been observed (Cheng and Kumar, 2015). Table 1 summarizes the existing models

that have incorporated visual output.

2.6 Shortcomings

Even with the considerable model mechanisms described, there are limitations in the field of site

logistic modelling. Firstly, there is no industry accepted standard procedure (Sadeghpour et al.,

2004). This is mainly due to the varying programs and techniques used by site planners. The

introduction of an industry accepted model would increase the ease of sharing data between

trades, planners and other relevant personnel.

There is also a lack of real-time updating to the models, which would simulate changing layouts

that take into account the as-built conditions. Furthermore, there is very little use of interior

Page 28: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

16

space as storage for modelling. The range of existing model abilities with respect to storage type

and updating are shown in Figure 2 . As shown, there is currently no model among these papers

that uses interior space as primary storage and incorporates updating, which is needed due to the

impacts of any variances between the original plan and the as-built conditions.

Figure 2: Model Comparison of Storage Type and Feedback

2.7 Future Developments

It is proposed that future models incorporate a 4D approach, with automatic updating. The

updating can be carried out using a photo modelling technique. This technique uses 2D

photographs to create 3D models of a construction site (Gore et al., 2012). Updating the model

so as-built conditions are incorporated into the site logistic plan can result in the re-optimization

of site logistics since the as-built conditions may differ from the as-planned ones. This is

important since any changes can result in the initial plan becoming inapplicable without

updating. The use of a drone capturing 2D pictures can meet update requirements without

additional manual labour (Gaich and Pötsch, 2015).

Page 29: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

17

Furthermore, manual changes to the simulations must be possible to ensure that expert

knowledge can improve computer generated solutions. This can be aided if the model shows a

few different options including optimal and sub-optimal solutions for the user to choose from.

Finally, the consideration for policies can be integrated to ensure that utilized space is permitted

for use. For instance, some areas on the site may not be usable in the footprint due to a need to

have an offset from surrounding pedestrian walkways. This step will help in the early planning

stages while the building footprint is designed.

2.7.1 Special Considerations for Tall Buildings

Apart from the logistic plan used, there are many factors to consider for the construction of tall

buildings. Some of these factors are presented in this section.

• Complexities of tall building construction introduce new constraints, such as:

o changes to storage space as the construction process progresses, including shifts

in the building footprint due to a podium to tower structure, and accounting for

the time needed for a slab to gain sufficient strength to be used to store materials

(Jung et al., 2014; Cheng and Kumar, 2015); and,

o the delay of interior construction due to the space being used for storage while

maintaining schedule criticality (Said and El-Rayes, 2012).

• Challenges with respect to cranes and hoists, such as:

o Vertical movement of objects, such as windows, precast concrete panels, steel

column and beams, where crane and hoists are limiting resources (Jung et al.,

2014) For example, if the crane is being used to move concrete, it cannot be used

for anything else. The use of a concrete pump frees up the crane for other

activities;

o Assembly and dismantling of cranes in congested urban setting and at great

heights;

Page 30: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

18

o Decreased line of sight if the crane is placed too far from the building edge on the

side of a pick-up point; and,

o Increased wind forces as height increases.

• Requirements of different labels for each floor. An example of this is rebar_basement,

rebar_1, rebar_2 and so on. As different amounts of objects of each type are needed for

each floor, the ordering and locating of the objects in batches is necessary; and,

• Considerations to weather and height as duration of construction processes may vary. For

instance, pumping concrete at heights requires a thinner mix or expensive admixtures,

resulting in concrete needing more time to cure.

• Differences between the construction methods and materials used for tall residential

buildings compared to commercial buildings.

With the additional considerations regarding tall building construction and updated model

mechanisms, it is believed that a superior logistic planning model may be created. There is a

need for industry follow-up to gain further information about considerations to building factors.

This information creates cohesion between methods of carrying out on-site activities and the

planning of the application of activities as models can always be lacking without the inclusion of

industry experience. The inclusion of this data would ensure that the logistic model is feasible for

real-life conditions. The use of a database to store expert knowledge and apply it to future

projects is recommended.

2.7.2 Proposed Model

A flowchart of a proposed model can be seen in Figure 3. The steps of the model are outlined.

1. Users input documentation to generate a BIM site model and incorporate the schedule to

assess possible delays of non-critical activities. Any new expert knowledge or urban

policies can be stored in a database so they may be used for current and future projects.

Page 31: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

19

2. The material supply schedule should be generated to minimize on-site objects.

3. The numbers of cranes and hoists and their location should be optimized. (Wang et al.,

2014).

4. Constraints can be input by the user at this point.

5. The locations of objects over the course of the construction project should be optimized

through discrete-event modelling and an incremental approach.

6. A 3D model of the optimized layout, as well as the option to display sub-optimal layouts

should be available to the user. This enables visualization and validation of the logistic

plan.

7. At this step, project updating can be input, so the model can optimize the remaining areas

returning back to step 4. This is to incorporate the placement of objects in locations other

than those specified in the initial plan.

8. If the building structure changes after construction has commenced, the updating returns

to step 1. It can skip step 3 if it is indicated in the model that cranes and hoists have

already been placed. This allows the re-optimization of the remaining objects. This

process is shown with the dashed arrows in Figure 3.

Page 32: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

20

Figure 3: Proposed Model Framework

2.8 Conclusion

This paper identified mechanisms and approaches that are used in several models in site logistic

planning. The lack of interior space as an available storage solution in most models is identified

as a significant capability gap as it would limit the optimization of logistic plans for congested

tall building construction projects in dense urban areas, where exterior storage is limited.

Furthermore, the lack of updating capabilities was identified as another area of major

shortcoming of existing models, as the plans generated at the start of project would not be

applicable to the site for the most of the duration of the project. The combination of the preferred

mechanisms outlined in the paper, and addressing these shortcomings in existing models can lead

to the creation of a model that is efficient, comprehensive and adaptable.

Page 33: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

21

With respect to the congested conditions occurring in dense urban areas and the complexities of

tall building construction, it is concluded that the use of an incremental approach for

optimization alongside the abovementioned considerations will create a model that can

efficiently and reliably optimize site logistics. A sample framework for a proposed model has

been outlined in the paper, which uses 3D analysis instead of 2D analysis so space-time conflicts

do not occur as vertical construction commences. This is especially important in tall buildings

since their structure changes over their height. Furthermore, the proposed model includes a

database to store expert knowledge and urban policies to guarantee all operations are permitted

and efficient. The next steps for this research is to gain knowledge in urban policies that heavily

affect construction site logistics, and to gain deeper understanding in vertical transportation

systems, such as hoists and cranes, and to build a site logistic model that is geared towards tall

building construction in congested urban areas, such as the GTA.

Page 34: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

22

Chapter 3 Interaction Diagrams for Multi-Domain Decision Making

Processes

Chapter 3 introduces interaction diagrams as a tool for multi-domain decision making and

describes the process of creating an interaction diagram.

Interaction Diagrams for Multi-Domain Decision Making Processes

3.1 Abstract

Site planning in urban centres has become increasingly complicated as construction sites become

smaller, buildings are taller, new equipment is introduced into operations, and construction

schedules are condensed. However, the most complex factor that has been introduced to site

planning are the decisions that are made across several domains and impact the construction

schedule. It has become important to use a multi-discipline decision-making tool so the best

decisions for the overall project are incorporated. This paper reviews current literature and site

operations for planning techniques to establish how construction site planning is carried out.

Decision making tools are reviewed to analyze their benefits and shortcomings in terms of

construction site logistics planning. Since decisions are not made in a strict order, or several

decisions occur simultaneously across domains in construction, a multi-domain decision-making

tool, the interaction diagram, is developed. An example site logistic interaction diagram focusing

on vertical delivery systems on construction sites is outlined in the paper and applied to a

construction site for a case study. The interaction diagram illustrates various decisions across

domains visually for project managers and shows the impact a decision has across multiple

domains and can be applied to unique scenarios for users.

3.2 Introduction

Over the years, construction-site planning in North America’s largest cities has become more

complex due to locational constraints to rising labour and land costs, changes in regulations to

accommodate surrounding activities, and limited availability of large land parcels. Several

Page 35: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

23

approaches have been undertaken to improve decision making for construction site planning.

However, a method in which all constraints are considered together does not exist.

There is also a growing need for decision-making to be multi-disciplinary to increase

communication in the early stages of the planning process. Better communication can ensure

comprehensive design and planning and decrease change orders in the project. A linear planning

process often results in clashes of electrical, mechanical, and plumbing services with structural

or architectural building components. These lead to change orders and addendums, which are

costly.

The objective of this paper is to present a decision-making process that can combine several

disciplines and represent relationships in multi-factor decision-making optimization. Decision-

making approaches are explored, including information exchange models, construction site

logistics planning programs, and equipment management programs. These approaches can be

employed together to create a generalized planning method that spans the lifetime of a

construction project.

The research questions are two-fold.

1. How is decision making currently carried out to ensure the best design or construction

across multiple domains?

2. How can considerations from multiple domains be integrated to decrease changes and

inefficiencies between planning and application?

3.3 Research Method

In this paper, several techniques for planning and construction-site planning were explored

through the literature. The scope of the research focuses on determining current trends in

planning processes for the construction of high-rise buildings in Toronto—specifically for the

vertical transportation of materials and personnel—identifying their limitations and analyzing

various decision-making tools for application in construction project planning.

Page 36: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

24

For the literature review, a set of queries was used to find papers relating to construction

planning including: construction management, logistics planning, site planning, decision making,

construction design, and resource management. Papers on planning techniques were also

explored using queries including: mind maps, interaction diagrams and multi-domain decision

making techniques. The papers were filtered using a set of inclusion and exclusion categories for

the construction planning papers.

Papers that were included had techniques that were used in construction, planning, or design

stages and improved communication, or operation efficiency in projects. Papers that were

excluded had methods that could not be used in North America, could not be applied to tall

buildings, or did not contribute to methods being used in the last two decades.

The literature review established the techniques which had been introduced in theory. After this,

interviews with experienced project managers were held to collect information about the

planning procedures that were currently being used in the field, their shortcomings, and areas

which require improvement. The example introduced in this paper is specific to construction site

logistics planning reflecting the domain the experts were interviewed for but can be extended to

other applications that require complex systems with multiple factors and decisions.

Data collection from site can be carried out to gain more information about inputs required for

decisions once the decision-making tool is created. In this case, site data for tower crane lift

times were observed and recorded. Finally, the various methods used in literature were compared

to identify their benefits and shortcomings to create a model that site managers and project

planners can implement for construction planning during the design and planning phases of

construction. The model is used to encourage early communication in the design and

construction phase across domains by visually showing stakeholders how their decisions may

impact other domains, and increase conversation with other domain stakeholders to optimize

decisions for the whole project. Although the model shows the decision factors and relationships

for users to make educated decisions, the project manager still needs to make decisions, and

understand the project and the decision-making tool.

Page 37: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

25

3.4 Literature Review

Currently, there are no standardized, industry-accepted procedures for site planning that focus on

the complexity of modern projects with complicated design and limited site storage space. This

literature review explores the methods used in the design and construction process over the past

20 years. The review seeks to summarize current planning techniques and find ways in which

the isolated methods can be brought together to result in a comprehensive construction planning

method. These are categorized as information exchange models, equipment management,

construction site logistic planning, and feedback models.

3.4.1 Information Exchange Models

Information exchange models focus on complete data exchange between various models, by

creating a standard for data exchange. This can be seen in industry foundation classes (IFC),

which is a universal language that has been developed to enable interoperability between various

programs by creating libraries of elements from several programs used in architecture,

construction and engineering. Using this language, various users can export their data to the IFC

language and import it into other programs used by other users.

A typical use of the IFC has been seen in building information models (BIM). BIM is a 3D

model that is collaboratively between users, so separate sets of drawings are not required. It can

display the model, information about the model and also update changes to the design in real

time. BIM software uses the IFC language to export building elements from programs in

different domains to one program.

The BIM objects have rules and a library to help translate one type of data format into another

(Lee et al., 2018). BIM uses clash detection to ensure no overlapping elements are introduced to

a project or to allow users to leave notes for communicating required changes in other domains.

It has been used in construction logistics planning as it is an up to date building model, however

its use requires daily model updates, and ongoing communication with suppliers to maintain an

accurate schedule. (Cheng and Kumar, 2015; Kumar and Cheng, 2015).

Page 38: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

26

Although data exchange models aim to ensure a complete migration of data to one program, in

the design phase of a construction project, they do not improve decision making due to domain

conflicts and only focus on physical conflicts represented in the models. An example of this is

seen when a building design creates a passive ventilation system as part of the envelope of a

building, which uses opening windows through the building strategically to allow ventilation in

the summer. However, introducing an air conditioning unit to the building or creating window

openings for aesthetics can cause interference with the passive ventilation design. Although this

creates a design that is not working efficiently in practice, in the BIM there are no physical

clashes of building elements overlapping. Thus, data exchange models leave it to the users to

identify operation clashes and only focus on complete data exchange, while having limitations in

identifying an efficient design for the overall project.

3.4.2 Equipment Management

In this context, construction site equipment management refers to the scheduling and operations

of high-cost equipment that impact site activities. The focus is on major equipment used during

construction, including the hoist, tower crane, and concrete pumps. Crane planning in the

literature focuses on minimizing the distance from the site pick up point to the installation

location, decreasing delivery time, creating an efficient crane radius to allow all materials to be

delivered as easily as possible, and minimizing cost (Rodriquez-Ramos and Francis, 1983;

Hosseini et al., 2017). The literature has examined single and multiple cranes on site, various

control methods for operating the crane, lift visualization, and crane operation efficiency to aid in

planning and providing feedback on sites (Zhang et al., 1999; Irrizary and Karan, 2012; Kang et

al., 2009; Lee et al., 2011; Shapira and Elbaz, 2014; Wang et al., 2014).

Hoist management planning deals with on-site productivity since taller buildings result in longer

delivery times (Wei et al., 2015). The factors that affect productivity are hoist velocity, distance

between stops, number of stops, and the load carried by the hoist (Cho et al., 2010). Finally,

concrete pump optimization is restricted to improving concrete mix design to ensure it can be

pumped long distances without strength or slump loss, choosing an adequate pump and hose, and

the experience of the operator (Wei et al., 2015; Ba et al., 2009; Liu et al, 2009).

Page 39: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

27

Unfortunately, research into the planning of these resources is typically simplified with

assumptions to allow detailed modeling. This is not always representative of the planning needs

of site managers in real-life applications. For instance, there is often no indication of cost or time

savings that result in a project when multiple vertical-lifting equipment are introduced.

Furthermore, the equations found in literature are not universally representative of the time an

activity may require in real-life applications since site-condition factors are not incorporated (Ali

et al., 2016).

3.4.3 Construction Logistics Planning

Some construction sites have sufficient space for staging materials and are able to use a first-

come, first-served method for material storage. Planners focus on minimizing material handling

time on large construction sites by storing materials at the time of delivery as close as possible to

the area of final use (Sadeghpour et al., 2004; Tommelein and Zouein, 1993). In congested urban

centers, however, construction sites are often constrained in parcel size, limiting the material

storage space exterior to the building footprint.

Alternatives explored in the literature include interior material storage inside the building

footprint and model updating as construction progresses (Ali et al., 2016), as can be seen in

Table 2. Types of storage used on construction site typically include: off-site storage (typically

by using street occupancy or renting land close to the construction site); exterior storage outside

of the building footprint inside the site parcel if adequate space is available; or interior storage,

which is located at the lower storeys of buildings as construction progresses and concrete floors

reach strength (Jung et al., 2014; Said and El- Rayes, 2009; Said and El- Rayes, 2012;

Sadeghpour et al., 2004; Sadeghpour et al., 2006).

Site specific and user specified factors are inputs for material storage planning. These inputs

include defining the storage locations as grid blocks or points; defining material objects by the

shape, size, and quantity of materials to be stored; and, model updating. This last input is the

most complex and can range from a static site plan with only one storage layout for the duration

of the entire project to a dynamic plan reflecting the continuous changes in material needs and

Page 40: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

28

space availability as the construction progresses and materials are consumed. (Sadeghpour et al.,

2004; Cheng and Kumar, 2015; Li and Love, 1998; Tommelein and Zouein, 1993, Sadeghpour

and Andayesh, 2015; Gore et al., 2012).

Table 2: Papers Modelling Types of Material Storage and Model Updating

Material Storage Type Model Updating

Static Dynamic

None Gore et al., 2012

Offsite

Exterior Only Said and El-Rayes, 2009;

Sadeghpour et al., 2004;

Sadeghpour et al., 2006

Interior (Secondary) Said and El-Rayes, 2012 Cheng and Kumar, 2015

Interior (Primary) Jung et al., 2014

User-defined constraints between objects and locations include minimizing the distance between

material storage and area of use, providing work preparation areas, maintaining a sight-line of

the materials for security purposes, and specifying types of storage needed for different materials

(Li and Love, 1998; Huang and Wong, 2015). Other constraints can include material supply to

introduce lean methods of construction to the plan and just-in-time material delivery (Issa, 2013;

Marhani et al., 2012, Bertelsen and Nielsen, 1997). This reduces the amount of materials and

congestion on site. However, this increases management challenges and the risk of materials

shortages for a task if there are delivery delays.

Models with feedback involve updating the building model to track construction progress, and

compare as-built conditions to design drawings and the project schedule. This has been carried

out by using pictures from cameras to create photo-based point clouds with GPS coordinates

(Gore et al., 2012). The photos are stitched together to illustrate the building process. A similar

process is carried out by drones to decrease required manpower and create an automated method

for updating. Furthermore, updating BIMs have been used to create crane lift simulations to aid

the crane operator during blind lifts (Heikkilä et al., 2013). The addition of feedback models to

planning and site management aids in viewing site conditions during the project, and timely

changes to the schedule.

Page 41: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

29

The site logistics plan is typically a site plan or 3D model with equipment locations shown at

various times during the project based on schedule and material supply (Cheng and Kumar,

2015; Wang et al., 2014). Unfortunately, there is a lack of literature that employs interior storage

as a primary storage location, as required in the current congested sites, and models with material

updating based on material supply (Ali et al., 2016). Furthermore, there are few industry-

accepted models that perform material storage optimization and resource scheduling.

3.4.4 Discussion

The above three areas of planning focus on various construction project phases, ranging from the

early design process to construction progress tracking. The information exchange models seek to

use programming to automate data exchange between domains and identify clashes. The

equipment management and construction site logistic planning methods use the information

exchange models to create simulations on BIMs for a construction project. These can include

crane swing or hoist lift simulations carried out on a building project. Simulations are typically

based on optimization equations developed in the literature through site observations and

practices, such as crane swing time equations.

Over the last two decades, each area has been expanded to increase the knowledge and improve

the planning methods in each domain. The above methods focus on delivering results to users to

show the optimal solution based only on factors that can be represented quantitatively in

equations for a small part of a construction project, which can be applied to the overall site plan

by the user. However, the complex interactions within and between domains, and different parts

of planning and construction are disregarded in place of simplifying the problem to manageable

units. Regrettably, this means that there is a lack of an industry-wide procedure for construction

project planning. With this in mind, this paper explores existing decision-making tools and

outlines a method for creating interaction diagrams that take into account industry experience

and findings in the literature to create a decision-making tool that incorporates several domains.

Page 42: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

30

3.5 Decision Making Tools

Decision-making tools have been used in a variety of decisions. In their simplest form, they

weight out the pros and cons of various choices, so the user can make the best decision with the

information they have. As problems have become more complex and it has become obvious that

not every factor in a decision-making problem hold the same priority as others, decision-making

tools have developed to take into account these changes. Five decision tools that focus on the

factors affecting a situations are discussed in this section, namely, weight decision matrix,

decision tree diagrams, influence diagrams, Bayesian networks, and interaction diagrams. These

diagram have specialized purposes and advantages, as discussed.

3.5.1 Weighted Decision Matrix

A weighted decision matrix breaks down various options into factors that a user requires in a

solution. As each factor may hold different importance for a successful solution, weights are

assigned to each factor by the user so that the sum of all factors is 100% as seen in Table 3.

Finally, each factor for each option is rated on a scale by the user. The ratings can be multiplied

by the weights and all the weighted ratings can be summed to show the best solution. Weighted

decision matrices are a simple way to rate different options as they assume that the factors are

independent.

Table 3: Weighted Decision Matrix Example

Criteria Weight Mobile Crane Interior Tower Crane Exterior Tower Crane

Rating Weighted

Score

Rating Weighted

Score

Rating Weighted

Score

Cost 0.35 -0.25 -0.0875 -0.5 -0.175 -1 -0.35

Product Quality 0.40 0.5 0.20 1 0.40 1 0.40

Reliability 0.25 1 0.25 0.5 0.125 0.7 0.175

TOTAL 0.3625 0.35 0.225

Rank 1 2 3

3.5.2 Decision Tree Diagram

Decision tree diagrams illustrate paths a user can take to reach a decision, showing at each node

the various choices the user has. These diagrams become very large for complicated optimization

Page 43: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

31

problems since each path must be shown. They also inherently indicate a linear decision-making

problem, which may not be the case in complex problems. An example of a decision tree

diagram can be seen in Figure 4, where the building footprint size and height impact the crane

type used for construction.

Figure 4: Decision Tree Example

3.5.3 Influence Diagrams

The decision matrix and decision tree methods are relatively simple and are used to model

problems with independent factors. However, this may not be true for complex problems.

Therefore, the influence diagrams were developed. Influence diagrams are graphical ways to

represent expert knowledge for decision-making problems. They can be transformed into rule-

based programs by applying probabilistic distributions to the factors involved in a decision

(Howard and Matheson, 2005). Moreover, they can represent the visual logic in an optimization

problem without the restriction of applying mathematical proof by accounting for unknown

Page 44: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

32

variables and aid in the gathering of empirical data for factors that have not yet been studied (Pearl,

2005). Traditional influence diagrams simplify the tree diagrams by assigning distributions to

nodes. They are acyclic, having no loops in them. A simple influence diagram is shown in Figure

5.

Figure 5: Influence Diagram Example

There are three types of nodes in the traditional influence diagram and two types of influence

relationships. The nodes represent different types of variables, whereas the relationships identify

how information from predecessor nodes impact target nodes. The nodes and relationships are

summarized in Table 4 and

Table 5, respectively (Howard and Matheson, 2005; Bielza et. al, 2010).

Table 4: Traditional Nodes

Node Function Mathematical Logic Shape in

Analytica

Decision

Node

Represents decisions that the user will

make, given all incoming variables are

known

Indicates the optimal

alternative

Rectangle (Nodes

A and C in Figure

5)

Chance

Node

These are factors that cannot be

controlled by the user and are usually

unknown until the time of the decision

Probabilistic

distribution of an

unknown variable

Oval Node B in

Figure 5)

Objective

Node

This is the goal of the influence

diagram, to optimize this variable for

Utility function of the

problem based on

Irregular hexagon

(Node D in

Page 45: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

33

the decision-making problem. incoming factors Figure 5)

Table 5: Relationships

Relationship Type Target Node Function

Informational (arrow A to C

in Figure 5)

Decision Node Indicates a linear, causal relationship. Indicates

variables that must be known at the time user has to

make a decision.

Conditional (arrow A to B

in Figure 5)

Chance Node Does not indicate a casual relationship. Indicates that

the probabilistic distribution of a chance node will be

influenced by the variables leading to it.

Conditional (arrow B to D

and C to D in Figure 5)

Objective Node Function dependency for the utility function

This model is useful for the incomplete representation of optimization problems in real-life

application as it takes into account experiential knowledge from industry professionals and

allows them to make decisions in their fields, following a linear path (Shachter, 1986). Experts

often have a better estimate of the results of a situation than can be easily represented by

equations, especially with the lack of empirical data. Creating equations also leads to a broad

generalization, resulting in models which do not apply for a variety of conditions or are too

broad to be accurate for real-life applications.

3.5.4 Bayesian Networks

Bayesian networks, which are mathematical models based on conditional probabilities, require

complete data for optimization problem representation. They are used to determine the probability

of an outcome given the probability distribution of factors leading to the final outcome. Each node

in a Bayesian network is quantified with a priori or conditional probabilities, which can be

determined from empirical data or from experts. While Bayesian networks are capable of handling

uncertainty, the outputs are probabilistic, which does not always help the decision maker when

quantitative optimization is needed for the decision-making process.

An example of a Bayesian network can be seen in Figure 6, where two nodes show factors for

building footprint size and building height, and how they impact the type of crane. Each node has

a probability, and the state of the nodes impact the probability of the state of the final node. The

Page 46: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

34

associated probabilities for each node is shown beside the node in the form of a table. As can be

seen, the probability for each type of crane is not 1/3rd, but depends on each scenario. The data for

the scenarios can be collected empirically.

Figure 6: Bayesian Network Example

3.5.5 Interaction Diagrams

Interaction diagrams minimize decision paths by representing nodes for each decision with each

node representing only the impact it can have on other nodes through relationship arrows. It is a

visual representation of qualitative information usually only known to domain experts as they

cannot be represented through equations. In this way, the interaction diagram is a comprehensive

overview of all decisions that need to be made in the planning phase. It can be used in

conjunction with influence diagrams and Bayesian networks to summarize probabilistic

distributions of factors involved, as well as descriptions about decisions that cannot be

represented through equations. Hence, the interaction diagram acts as a model to summarize

expert knowledge in a domain that is accessible to a variety of users. The nodes and relationships

are summarized in Table 6. The interaction diagram nodes have varying colors corresponding to

the domain they belong to. An example of this can be seen in the sample interaction diagram in

Figure 7.

Page 47: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

35

Table 6: Interaction Diagram Features

Feature Shape Function

Factor Category Node Rectangle Represents large groups of

factors in one domain

Factor Node Oval Represents factors in each

domain

Significance Relationship

Arrows

High Significance

Medium Significance

Low Significance

Not Rated/ Disagreed

These arrows show relationships

between factors. The factor at

the beginning of the arrow

impacts the factor at the end of

the arrow. The type of arrow

indicates the significance of the

relationship (the impact a factor

has on another factor)

determined from surveys from

experts in the field.

Figure 7: Interaction Diagram Example

Page 48: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

36

The interaction diagram also allows for loops and does not define a path as decisions can be

made simultaneously and do not need to be made only in one order. For instance, a user can

decide to place a hoist in the building before placing a tower crane in the building. The location

of these pieces of equipment have an impact on where the other equipment can be located as they

cannot occupy the same space, however, there is no reason why a user has to locate one before

the other for every site. Finally, the interaction diagram allows for incomplete data for domain

factors and details about the decisions as it is not a path network, relationships and nodes can

always be added as required by the user.

3.5.6 Decision Making Tools Comparison

In Table 7, a summary of the benefits and limitations for the five discussed decision-making

tools is presented. Overall, the weighted decision matrix and tree diagram are models that are too

simple to represent complex planning problems, whereas the influence diagram and Bayesian

networks don’t adequately represent real-life decisions made in the construction field currently

as there are factors without collected empirical data and unknown variables in each decision-

making problem and offer no loops for decision-makers.

Table 7: Benefits and Shortcomings of Decision Making Tools

Decision

Making Tool

Benefits Shortcomings

Weighted

Decision

Matrix

Easy to make

Allows qualitative evaluation of

alternatives

Depends on user criteria weights

Must be updated as ratings or solutions

change

Assumes independence between factors

Tree Diagram Allows for incomplete data Becomes complicated and large due to

illustration of all steps along a path

Does not change qualitative decisions into

quantitative evaluation

Influence

Diagram

Allows representation of different

paths in probabilistic equations for

each node

Can have incomplete data

Must have a path for the user to make

decisions

No feedback loops

Bayesian

Network

Shows path for a decision and

evaluates various options on

probabilistic distributions

Cannot have incomplete data

No loop

Influence Allows for feedback loops No strict path for decision making – user

Page 49: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

37

Diagram Can have incomplete data

Decisions can be made

simultaneously

Visual overview of multiple domain

factors

must be aware of project

Must be updated for new technology or

domains

Specific to standard or process

The program Analytica added nodes and functionality to extend the usability of the traditional

influence diagram (Lumina, 2018). These include modules that help simplify the major influence

diagrams, by creating sub-diagrams for nodes to illustrate the factors impacting each node, and

feedback loops as long as a lagged time interval is introduced between nodes. The program

allows the user to build an influence diagram using nodes and relationship arrows, and then add

mathematical distributions to the nodes based on their influencing factors. The arrows in the

diagram will change based on the equations that are input, so this allows the users to build the

diagram as more data become available without deeming the entire model outdated or

inapplicable.

Unfortunately, influence diagrams inherently require the modeler to create a path for decision-

making. This is not always an accurate representation of the decision-making progress in real-life

application. As an alternative, an interaction diagram is proposed to be applied with an influence

diagram. The influence diagram can show probabilities and dependence of relationships for

certain paths in an optimization problem, whereas the interaction diagram is a summary of all

factors and the impacts a user decision has on various fields, without restricting the user to a

certain decision path. This is much more realistic as many decisions are made simultaneously or

may be carried out in a different order than the one path identified in an influence diagram.

3.6 Interaction Diagrams

The development of an interaction diagram depends on translating expert knowledge into a

visual model. This requires interviews with industry professionals and a literature review

regarding planning processes used in current domains, followed by a survey to rate the

significance of relationships and eliminate factors that are not agreed upon by the industry.

An interaction diagram uses rectangles to represent large decisions for the user and circles for the

factors that influence each major decision. The relationships between variables is based on

Page 50: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

38

literature and expert knowledge, with different weights applied to the arrows to represent

significance ratings of relationships as determined by a survey among experienced individuals in

the field.

The overall goal of the interaction diagram is to show major decisions on a project in one

diagram and to reduce isolation in decisions, and to support experienced individuals in making

decisions systematically. Influence diagrams can be used as modules for major decisions or to

show the inputs of a factor, however, the overall project should be using interaction diagrams for

decision-making as there is no absolute decision or domain that is always most important in

decision-making and requires the flexibility of an interaction diagram to be applicable across a

variety of projects.

3.6.1 Developing the Construction Site Logistic Interaction Diagram

An interaction diagram communicates decision-making factors that are typically only known to

industry experts and trained individuals. Due to this, it is important to hold interviews with

experienced professionals to understand their decision-making process. For the development of

the construction site logistics diagram with a focus on vertical transportation on the site, project

managers and site planners were interviewed several times regarding the process of site layout

planning, including material supply processes, permitting procedures, and equipment logistics. It

was crucial to collect the planning processes on different construction sites as each site had

differing factors that were special to each case.

After identifying the factors from the interviews, any checklists that were already in place and

the most expensive decisions were distinguished. Furthermore, any problems that could occur

were pinpointed and typical resolutions were gathered. These included surrounding

environmental factors, such as construction crane radii being restricted by surrounding buildings,

permitting restrictions due to neighbor agreements, and traffic by-laws that impacted delivery

times and types to the site. At the end of the interviews, the common factors for all sites were

used in the creation of the site logistics interaction diagram since this allows the diagram to be

applied to a variety of construction sites.

Page 51: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

39

All the various relationships and their impacts on different parts of site logistics were

summarized in the interaction diagram by illustrating factors in bubbles and showing

relationships between factors via connecting arrows. The details of each factor and any impacts

that it might have was researched in the literature and the by-laws of Toronto. These can be seen

in the references in the interaction diagram and the supplementary notes that accompany the

interaction diagram.

In the development of the interaction diagram, it was identified that each module of the planning

process needed to be represented visually in the interaction diagram to illustrate decisions of

each domain and easily see where interactions between domains occurred. This was carried out

by creating boxes around each domain in the interaction diagram and using different colors for

each domain. This will be seen in the case study below of the construction site logistics planning

interaction diagram.

For the purpose of validation, the interaction diagram was reviewed by expert individuals and the

significance level of each relationships was rated on a scale from 0 (minimal impact between

factors) to 5 (a very high impact between factors). Comments from the individuals were recorded

to determine any discrepancies between the ratings of the relationships. A sample of the rating

survey can be seen in Figure 8.

Page 52: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

40

Figure 8: Relationship Significance Survey

For all significance ratings that had a difference between expert opinions greater than 2, experts

were interviewed again and clarifications for their ratings were collected. At this point, experts

could also rerate the significance if necessary. Any significance rating of 0 for relationships

indicated that experts did not believe there was typically an impact from one factor to the other.

These arrows were then removed from the interaction diagram and a description of the special

cases where the relationship would be applicable was summarized for the reader. The

significance level for the remaining relationships were illustrated by using different types of

arrows. The legend for the arrows can found at the bottom of Figure 9. Finally, all relationships

and factors were explained in text format to supplement the visual decision-making process

shown in the interaction diagram.

3.6.2 Construction Site Logistics Interaction Diagram

The construction site logistics interaction diagram summarizes factors that influence decisions

regarding high-cost resources on site, as seen in Figure 9. This includes the crane, hoist and

concrete pump. The operations of all these pieces of equipment is influenced by construction site

factors and a traffic management plan. The decisions that are required to be made by a site

planner for the use of the equipment, such as the location or type of equipment impact the

operation of other pieces of equipment in this planning process, however, there is no preference

as to which piece of equipment should be planned for first. The arrows that are the most heavily

weighted have the greatest impact for decisions and should be determined as early as possible in

the design or planning process.

Page 53: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

41

Figure 9: Construction Site Logistics Interaction Diagram

The all factor category in the site logistics interaction diagram covers factors that do not belong

to any other category, are building-specific and have an impact of the all other parts of the

construction project. For instance, the avoid CP (critical path) activities impacts the location of

the crane and hoist to ensure the pieces of equipment are not located in areas required for the

building to be inhabitable like the mechanical room or lobby area. A single factor may impact

many other factors in the same or other domains. An example of this can be seen with the noise

by-law factor, which impacts the operation times of the hoist and crane, the type of concrete

pump used, and the delivery schedule. The crane, concrete pump and hoist have their factors

broken into factor categories of location, operation and type of equipment, where factors

influencing each category are identified. Finally, the traffic management category identifies

factors that may impact the deliveries to the construction site.

Page 54: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

42

The interaction diagram identifies areas in which empirical data should be collected to automate

decision making that is currently based on experience or theoretical knowledge. An example of

this is the time it takes a crane to perform a lift. Although equations exist in the literature, their

results vary from the real-life application as many factors found in the interaction diagram are

not considered in the theoretical equations. This includes wind speed and crane-operator delay.

By identifying factors that are not commonly included in theoretical processes by using the

factors identified by domain experts, a user can follow a decision-making process that is more

accurate to the results of a construction site.

Currently, the models that exist focus on isolated domain optimization. This was seen in the

equipment management and construction site logistics planning models. The equipment

management models take a few factors that come from the equipment and the building to be

constructed to optimize the location or operation of the tower crane or hoist. The construction

site logistics planning models focus on optimizing material storage alone. However, these have

an impact on the operation of the tower crane and hoist since the locations of material storage are

the drop off locations for the tower crane and hoist. Decision making tools that exist are either

too simple as seen by the weighted tree matrix and tree diagram, assuming independence or paths

for decisions, or requiring complete information and mathematical representation of problems as

seen by the influence diagram and Bayesian networks. Interaction diagrams summarize

qualitative data and allow for mathematical optimization models in each domain to show factor

influences on other domains.

3.6.3 Case Study: 87 Peter Street, Toronto, ON

The main purpose of this section is to illustrate the application of the construction site logistics

interaction diagram to a construction site located in Toronto that was observed during site visits

for logistic planning. A comparison of the real-life applied decisions that were carried out by

experience project managers and the decisions that are recommended with the use of the

interaction diagram by a novice is included.

Page 55: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

43

The building that is to be analyzed is 87 Peter Street, Toronto, ON. It is a 157m tall building with

49 storeys. A sketch of the site and its location is shown in Figure 10. Each decision that is

outlined below follows the format: the decision is introduced, the proposed option for each

decision, its reason and impact are detailed. Finally, the carried-out decision and its reasons for

the site. The final layouts for the proposed and carried out decisions are shown in Figure 11 and

Figure 12, respectively.

Figure 10: Site Plan

The first decision that will be looked at is the crane type. There are two crane types (B3) that can

typically be used; a flathead crane or a luffing crane. The proposed option for this site was the

luffing crane. At the location of this project, there are several neighboring buildings (B13),

which minimize the radius a crane can weathervane (B11) (swing freely). Due to this, a luffing

crane is chosen so a large radius (B10) for lifts can be covered, while the jib can be maneuvered

to avoid neighboring buildings. The impact of the proposed decision is the increase in lift time

relative a flathead crane. As the luffing crane must perform two actions during each lift (pulling

up the load, then straightening the jib so the load can reach its destination), each lift takes a

longer time than a flathead crane would. The crane used was a luffing crane since the initial

erection of the crane was not higher than the neighboring building on the North side of the

Page 56: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

44

construction area and a hammerhead crane would not be able to clear the neighboring building

even though the contractor has air rights. The city and neighbors were contacted to receive air

rights so crane swings over the adjacent land could occur. Due to this decision, the lift times

were increased.

After deciding on the crane type, the location for the crane (B2) must be decided. It was

proposed that the crane should be located external to the building, as close to center of this

building as possible, since it is not likely for the crane and hoist to share an apartment suite (A1).

However, it must be noted that elevator shafts and stairwells must be avoided (A3&A5). Since

the building is so small, the tower crane was located external to the building (B3). The impact of

this decision is the decrease between the distance of the crane, pick-up points and drop-off

points, resulting in an overall decrease in crane lift times. The tower crane being located

externally reduced finishing time of required areas for the building. On the other hand, there was

increased time to finish the façade where the exterior crane was anchored. The location for the

crane was the same as the proposed location. This was to minimize finishing time to the slab and

interior of the building.

The next decision is the inclusion of a concrete pump (C). It was proposed that a concrete pump

should be included, since the luffing crane (B3) decreases the productivity of the construction

site, a concrete pump (C) is introduced to the project to deliver concrete and decrease the

payload on the crane (B2). It is also useful as the concrete pump typically minimizes the delivery

time for concrete over the crane as the building gets taller. This would impact the payload on the

crane, decreasing it and maintaining a faster schedule for the site. At the site, a tower crane and

concrete bucket were used for concrete delivery between P3 and the 5th floor. After the 5th floor,

a concrete pump was introduced to maintain the schedule required by the owner for construction.

The final decisions that will be discussed are the inclusion and location of a construction hoist

(D). It is proposed to include a construction hoist. As this is a tall building and a luffing crane

should be used, a construction hoist should be included to decrease the payload on the crane

(B2). It is optimal to locate the hoist on the centre of the long side of the building (D4) to

minimize the distance of deliveries to either side of the building, however, due to site space

Page 57: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

45

restrictions, there is no space for a construction hoist to be located at the exterior of the building

without imposing on neighboring properties. Due to this, the construction hoist can be located at

the short sides of the building. The impact of this decision is to decrease the payload on the

crane. There is a need for a traffic route for deliveries to the hoist (E1). Since the crane is already

located at the back of the building, the hoist can only be placed on the street side of the building,

requiring traffic closures to occur during delivery times (E4 & E5). At 87 Peter Street, the hoist

was located on the north side of the building. Neighbors were contacted and an agreement was

made with them to encroach on their property for the duration of the project. Due to this

decision, the hoist did not have to be accessed from the road and, therefore, no occupancy permit

was required to occupy sidewalk or road area. The doors of the hoist were positioned on the

shorter sides of the hoist to reduce encroachment on the neighboring property. The location of

the hoist is the only decision that differs greatly from the proposed decision.

Figure 11: Proposed Site Plan Using Interaction Diagram

Page 58: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

46

Figure 12: Actual Site Plan

The decisions made using the interaction diagram are very similar to the decisions made in the

actual project during construction. The real-life decisions that differ from the proposed decisions

were due to additional information that a user could not have while using the interaction

diagram, however, the issues were identified during the planning as seen in the location of the

hoist. By using the interaction diagram, a user was able to make decisions and identify

challenges that may require creative solutions. It is recommended that each company tweak this

interaction diagram to reflect their planning process and apply it to new construction projects for

consistency in planning, and programmers include impacts from the factors in construction site

logistics planning models.

3.6.4 Improvements from Existing Models

The interaction diagram seeks to aid project managers in decision making. It visually shows that

the productivity of a site or a piece of equipment is a function of various factors across domains,

as per Equation 2, and that several decisions impact each other. Furthermore, the interaction

diagram takes into account that decisions across several domains are oftentimes made

simultaneously and does not impose a step-by-step order on the user.

Productivity = f (x1, x2, x3, …)

Equation 2: Site Productivity

Page 59: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

47

Although, the mathematical representation of the factors implies that equations can be used to

represent site operations and optimize productivity and site logistics, it must be noted that an

experienced estimator or site superintendent outweigh mathematical models with their implicit

knowledge. This becomes obvious when a mathematical equation or model is compared to real

life data, as seen in a small summary in Figure 13. The recorded data was gathered from site

observations at various construction sites in Toronto, including 169 Fork York Blvd., 110 River

Street, 130 Queens Quay East and 2560 Eglinton Avenue West. Although, the same object, the

concrete bucket, is observed in the table below, the lift times vary in predicated and actual cycle

times. The predicted cycle times are impacted by the mass of the object being lifted and the

vertical and horizontal distances between the pick-up point and drop-off point of the object and

the crane itself, as per Appendix A: Crane Cycle Equations (Wang et al., 2014).

Figure 13: Actual vs Predicted Crane Cycle Lift Times

Most of the recorded data is within 50% of the predicted cycles times with four recordings as

outliers. Due to these observed differences between recorded data and predicted cycle times, the

interaction diagram relies on experienced decision-makers with mathematical models as a

supporting aid if required rather than a critical part of the decision-making process.

Page 60: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

48

The interaction diagram can be customized to each company so an agreed overall decision-

making process can be developed for construction site planning, while users still have the

flexibility to apply their experience to the decisions using the framework-like interaction

diagram. It also enables experts in each domain to represent their tacit knowledge into a method

that can be learned by others. Finally, as new technology is developed, the interaction diagram

must also be revised to reflect the new domains.

3.7 Conclusion

Site planning has become more complicated in recent years in Toronto as construction projects

become more complex and require coordination between multiple fields. There is currently no

existing, industry-wide planning process, however, many companies and experts carry out

planning in systematic ways that have not been documented. The processes found in the

literature are often isolated in domains.

As established in this paper, there are currently processes to improve communication between

disciplines in the design process through the development of seamless integration between

programs using BIMs for clash detection. Planning methods for decision making on construction

projects include equipment management and site logistics planning, however, there is no model

that addresses the relationship site logistics planning can have on equipment operation or any

other domains. Hence, decision-making models were explored to create a system that can

represent the impacts of decisions across the several domains involved in a construction project.

Potential decision-making models include the weighted matrix, tree diagram, influence diagrams

and Bayesian networks. The weighted matrix and tree diagram are helpful with small, isolated

decisions since they assume independence, and a strict path to follow for a decision, respectively.

The influence diagram and Bayesian networks are a good representation of the probability of a

decision outcome given that mathematical models are known for each and the model is complete.

Modelling using influence diagrams is heavily based on a deep understanding of factors that are

involved in an optimization problem, the collection of expert knowledge in the domain and the

modelling of unknown information (Bielza et. Al, 2011; Howard and Matheson, 2005). The

Page 61: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

49

shortcomings found in these decision-making tools, namely, the inability to have loops,

incomplete models and a representation of qualitative data, led to the development of the

interaction diagram to illustrate the various decisions involved in a complex project across

domains.

The interaction diagram summarizes all factors and the relationships between decisions across

various fields, which allows for decisions that are carried out simultaneously and not always

carried out in the same order as there is no restricted path. This can be seen in the example of the

site logistics planning model and case study above, where the decisions for tower cranes, hoists

and concrete pumps can be made simultaneously while the user is able to see the impacts a

specific site or traffic plan will have on these decisions, as well as how making decisions in one

domain or for one piece of equipment will impact the rest of the construction site.

Influence diagrams can be used as modules for major decisions or to show the inputs of a factor,

however, the overall project should be using interaction diagrams for decision-making as there is

no absolute decision or domain that is always most important in decision making and requires

the flexibility of an interaction diagram to be applicable across a variety of projects. These

interaction models can be used in the construction industry to illustrate design and planning

optimization problems in building construction, oil refineries, mining jobs, and transport lines by

splitting job types into factors that are typical across similar projects and displaying the inputs

necessary for the user to make decisions. This is a useful way to represent the problem since the

various decision domains can be viewed together and relationships between domains identified,

thus reducing isolation in decision-making. Communication in the early stages of planning can

be increased as users are able to see many domain impacts and no longer have to make only

decisions in their domains without any information on impacts to other domains, resulting in

project decisions that are optimal for the project as a whole. Since these diagrams make use of

domain knowledge and illustrate the decision-making process visually so the decision-making

process is communicated with individuals in other fields, the interaction diagrams serve as an

intelligent system to streamline decision-making processes in projects and justify decisions. They

summarize all the factors impacting a decision and are a better representation of decision-making

Page 62: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

50

that does not follow a specific path since multi-domain decisions are not linear than influence

diagrams and Bayesian networks.

Interaction diagrams can be created in each company, field or placed as a policy in decision-

making at a city planning level to create industry-accepted, decision-making systems in each

field. Furthermore, several influence diagrams can be turned into modules to represent influences

of decisions across various domains and used as input in larger programs for planning and

design, as seen in the construction site logistics model above, while the interaction diagrams can

provide a detailed view of factors impacting decisions given different starting points for the user.

Page 63: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

51

Chapter 4 Site Logistics Planning with an Interaction Diagram

Chapter 4 details the site logistics interaction diagram presented in chapter 3 and outlines a

construction site logistics planning process.

Site Logistics Planning with an Interaction Diagram

4.1 Abstract

Building construction in urban centres, such as Toronto, has become more complex due to

densification and taller buildings, as well as increasing logistics and interactions between

multiple domains and trades during the design and construction phases of a construction project.

There is currently no industry-wide method for site planning and this results in each individual

project manager, each company and each trade making decisions with their own processes,

creating optimization in isolation and not for the project as a whole. This paper presents an

outline of construction site planning and a framework to aid project managers in decision-

making with multiple domain factors and impacts. The developed framework in this paper

focuses on vertical transportation of materials and personnel, and can be modified to include

more domains and new equipment as required by site managers. By using the framework, every

company can have a basis for decisions and create standards for project planning.

4.2 Introduction

Tall building construction in congested urban areas, such as Toronto, has become more

challenging with increased land and labour costs, and changing regulations. To reduce the cost

and time required in the overall construction of a building, improvements in site logistics

planning are necessary. Site planning for construction sites in Toronto, as well as for the most

expensive pieces of construction equipment like cranes and hoists, is typically performed

manually by experienced project managers. There are no existing guidelines that novices can

follow to perform these duties as they usually familiarize themselves with the concepts through

experience and learning from other site managers. Currently, in literature, site logistics

Page 64: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

52

optimization is carried out in isolation for each piece of equipment, not considering the impacts

one decision may have on the overall site plan.

The objective of this paper is to present a framework for the decision making that is required in

site logistics planning in Toronto, and to create a model that can support the decision-making

process in future projects and be used in construction education. Although the details of this

framework are specific to Toronto, it can be modified to meet the needs of any location. This

framework includes logistics covering the tower crane, construction hoist, concrete pump and the

traffic management plan. Some steps for planning are introduced in the paper, followed by an

interaction diagram of factors affecting site logistic decisions and the significance of their

relationships.

4.3 Research Method

For the research of this project, the decision-making processes of construction sites in Toronto

were modelled. This involved observing sites with logistics planned by industry professionals

and finding common methods used across all construction sites. The sites observed included 169

Fort York Blvd., Toronto, which consists of three residential towers of 8, 18 and 30 storeys; 110

River St., Toronto, consisting of two residential building tower of 10 and 29 storeys, and 130

Queens Quay East, Toronto, to be built to 35 storeys. The first two sites used construction hoists,

cranes and concrete buckets for vertical transportation, whereas the last site used a concrete

pump for concrete delivery. In total, over 12 hours were spent observing the sites and 24.5 hours

dedicated to obtaining model information from studying site logistics plans. Apart from site

observations, a review of the literature and city and provincial by-laws pertaining to site logistics

planning was completed. The findings are discussed in the following sections.

Expert A is the director of high rise construction at Daniels Corporation. He has been working in

this field for 10 years, with a previous background as a superintendent at Tridel and currently

oversees the operations of 10 sites located in Toronto and Mississauga. Expert B is a senior

project manager at Menkes, and currently manages two residential towers being built at One

York St., Toronto. Expert B has previous experience in the construction industry in Calgary as a

Page 65: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

53

general contractor and carpenter. Due to the difference in their experience and current roles,

there are discrepancies seen in their interviews for factor significance rating. This will be further

outlined in the next section. Apart from these two experts, professionals in the field of concrete

finishing and formwork engineering, as well as an additional project manager, were interviewed.

4.4 Literature Review

Project management for a construction site requires planning for several site activities, ranging

from scheduling day to day tasks to making decisions about large pieces of equipment, and

balancing the budget of the project. The Project Management Body of Knowledge outlines

management techniques for scheduling, assigning resources, identifying risk and communicating

with stakeholders for general management (Project Management Institute, 2013). The literature

currently focuses on safety and risk of a construction site (Perrenoud et al., 2017; Pirzadeh and

Lingard, 2017; McCabe et al., 2017). There is also a trend towards simulation for construction

management education focusing on cost and scheduling (Rokooei et al., 2017). Research into the

transferring of construction management knowledge has been undertaken to identify

shortcomings in translating construction experience into shared information (Tatum, 1993).

However, all of these methods do not take into account policies for pieces of large equipment or

the interaction decisions for one piece of equipment have on the rest of the site plan, as they rely

on industry professionals to be aware of the changing policies and intuitively create site

management plans based on experience.

Currently, equipment optimization is often carried out in isolation in the literature. Crane

operations are typically optimized by minimizing the distance to the material lift locations on the

site (Rodriguez-Ramos and Francis, 1983). Sites with multiple tower cranes can be similarly

optimized by minimizing the number of conflicts between the cranes and the distances of all

anticipated lifts (Zhang et al., 1999; Irrizary and Karan, 2012), which can also be assessed

visually (Kang et al., 2009). The crane costs may be used as a proxy for operations and

minimized (Hosseini et al., 2017). Although these methods have considered the cost and lifting

time for the tower crane using site specific building layouts, they did not consider the effect of

Page 66: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

54

local policies on the operation of the tower crane or the advantage of including other vertical

lifting equipment, such as a construction hoist, to reduce the work required by the crane.

Construction hoist planning typically uses computer simulation to model how hoist productivity

is affected by increased heights and longer wait times for personnel (Wei et al., 2015). Some

programs for construction hoist planning focus on modifying hoist operations based on changing

building envelopes by using inclined hoists (Kim et al., 2016). Hoist operating plans have been

developed based on hoist velocity, distances between stops, the number of stops, and the weight

of materials or personnel to be carried (Cho et al., 2010). Simulations for peak vertical

transportation periods, such as the morning rush for workers have been created to optimize trip

breakdowns (Kamleh, 2014; Park et al., 2001). For these studies, assumptions focus on

optimizing the operation of the hoist without looking at the impacts of choosing the location or

the type of hoist.

Finally, research in concrete pumps are limited to improving concrete mix for pumping and

strength purposes and the characteristics of the pump (Wei et al., 2015). Some studies look at

applications of the concrete pump in tall buildings and some considerations such as the pump

and hose type, and experienced operators to optimize concrete delivery (Ba et al., 2009). There

have also been studies to determine the difference between the actual delivery rate of concrete

pumps compared to the manufacturer’s data (Liu et al., 2009).

All of these optimization efforts are carried out in isolation either in the piece of equipment or

have general planning procedures that must be applied to the construction industry. There is a

need to draw on elements of these categories to create a framework for site planning. The

framework seeks to summarize the effects of the decisions since optimization in one category

may result in a loss of productivity or increased costs for the construction site. Furthermore, a

planning process is outlined to show phases of a site plan that should be considered.

4.5 Planning Process

The planning process of a construction site involves making a site plan of all deliveries and

activities to occur on the site. The site plan documents are submitted to the governing body to

Page 67: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

55

obtain permits so construction can begin. The planning process typically includes the following

six to seven major steps:

• Traffic Management Plan

o Phase 1: Excavation Plan

o Phase 2: Construction Plan

o Phase 3: Construction Plan 2 (optional)

• Crane Plan

• Soil Remediation

• Shoring Design

• Hoist Plan

• Site Power

• Concrete Pump Plan

4.5.1 Traffic Management Plan

The traffic management plans fall under the construction management plan for the planning

checklist provided by the City of Toronto (City of Toronto, 2017b). It seeks to communicate the

requirements of each site to the city and is approved on a project-by-project basis to avoid

conflicts between the local traffic and other construction sites in the area. Furthermore, the goal

of the construction management plan is to reduce impacts to local traffic and negative impacts to

public safety. For construction sites located in areas with heavy traffic, a traffic study may have

to be conducted to analyze the effects on the neighborhood (City of Toronto, 2006). Due to the

complexity of traffic in Toronto, the City is in the process of mandating that traffic management

plans must be designed by traffic consultants as opposed to project managers (City of Toronto,

2013). The traffic management plans can have two to three phases.

The first phase of the plan is the excavation plan. Since deliveries and traffic are comparatively

simpler in the excavation phase of the construction project, this is a simpler traffic plan

indicating the excavation area, entry and exit ramp locations, site gates for access to the

construction site, temporary construction fence locations, and signage. This plan typically gets

Page 68: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

56

approved by the City of Toronto over a shorter time than the construction plan. The excavation

plan is submitted for approval and must be approved before site work can begin.

The construction plan can be submitted for approval at the start of construction for the project,

while excavation occurs. It is usually approved within six to eight months in the City of Toronto.

It is considered the permanent traffic plan for the site since it typically remains in place for the

rest of the duration of construction. This plan identifies truck maneuvers on site and on the road

for deliveries, road closures, site entry and exit gates, staging and material storage plans, and

required signage.

Finally, a phase 3 construction plan can be submitted for approval if the phase 2 plan becomes

inadequate for the construction site. This is usually due to policy or cost changes during

construction. An example of this is a change in street occupancy costs in the City of Toronto

from a flat rate fee of $5.77 + HST /m2/ month to permit fees from $27.67 to $110.68 + HST

/m2/month for roads based on the area being occupied and $6.06 + HST /m2/month for sidewalks

(City of Toronto, 2015; City of Toronto, 2017a). This type of change can drive construction site

managers to implement new traffic management plans on the construction site to reduce areas

that are being rented from the City and reduce site costs.

4.5.2 Soil Remediation

A geotechnical study must be performed on a construction site by a professional geotechnical

engineer, as required by the City of Toronto in the planning application checklist (City of

Toronto, 2010; City of Toronto, 2017b). This study identifies the soil composition and can also

indicate if soil remediation must occur at the location. In Toronto, there are two land

classifications for development: greenfield and brownfield. Greenfield refers to land that has had

no previous development on it. While this typically means that remediation is unlikely, there

have been instances where remediation was required due to salt in the soil. Brownfield land

refers to land that has had previous development, which indicates a strong potential for

contaminants in the soil (Government of Ontario, 2012). Soil risk assessment must be carried out

on the first 1.5 metres (depth) of soil on a site (City of Toronto, 2014b). Depending on the results

Page 69: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

57

from the risk assessment, remediation must be carried out on the soil, sometimes requiring a

higher standard of soil to be imported to the site (City of Toronto, 2014b).

4.5.3 Shoring Design

Shoring systems are temporary structures that hold soil in place so construction can occur in the

excavated opening on a site, and must be designed by engineers (City of Toronto, 2014a). The

two most common shoring systems used in Toronto are secant (also known as caisson) pile

walls, and soldier pile and lagging.

A secant pile wall is a system in which holes are drilled into the ground and concrete is filled in

the holes to create a rigid perimeter before excavation begins (Macnab, 2002). These piles are

drilled into each other to create a continuous wall and can have reinforcement in them. The

soldier pile and lagging system consist of wide flange steel columns hammered into the earth

(Macnab, 2002). As excavation occurs, timbers are installed between the steel piles.

Both these shoring systems can use tiebacks, which angle down into the earth and use tension to

hold the lagging systems against the excavated walls (Macnab, 2002). A tieback agreement must

be obtained from the adjacent property owners identifying where the tiebacks will be located, the

de-tensioning procedure of the tiebacks, and protection of adjacent properties in case of damage.

If a tieback agreement cannot be made with neighboring properties or utilities, alternate systems

like rakers must be used. Rakers are steel members that angle to the floor of the excavation to

support the walls of the excavation. Although these are cheaper than tiebacks and require no

agreements with neighbors, they obstruct the area of construction.

4.5.4 Temporary Site Power

Preparing the site for construction requires electrical service for the equipment and natural gas

for winter heat during construction. In Toronto, this requires consulting with Toronto Hydro and

Enbridge (Toronto Hydro, 2018; Enbridge, 2016). The consulting includes planning the

relocation of cables, utilities and fire hydrants to ensure a clear area for construction and fire

safety, and to provide temporary water supply and power for construction (OHSA, 1997). In

some cases, adequate power supply is not available, and diesel-powered equipment must be used.

Page 70: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

58

4.5.5 Crane Plan

The crane is the largest piece of equipment on a building construction site and impacts its

surrounding area. Deciding which crane will be used depends on the formwork contractor, since

the formwork contractors in Toronto usually own the cranes. The radius and capacity of the

crane is based material loads for the project and the crane load charts; the dismantling procedure

will also influence the crane location and operations. The location of the tower crane and its

boom swing must be identified when obtaining a permit from the City of Toronto (City of

Toronto, 2017a).

4.5.6 Hoist Plan

As a building gets taller, the vertical transportation of materials and personnel becomes the

activity most limiting construction. A construction hoist, which is a tower mounted elevator cage

typically mounted on the outside face of a building, can support the vertical lifting needs of the

site (Wei et al., 2015). It is important to ensure that a hoist is located at a continuous vertical face

where it can climb the building. This may be against the envelope or at a line of balconies, but, in

Toronto, occupancy of a building cannot occur until all openings in the building are closed

(Government of Ontario, 1992). Due to this, locating hoist access on a balcony, which can be

closed off with sliding doors, allows for faster finishing of the building envelope.

4.5.7 Concrete Pump Plan

Another piece of equipment that can be used to decrease the payload on a tower crane and speed

vertical transportation is the concrete pump. The decision to include a concrete pump depends on

an adequate power supply and available space for its installation and operation. It is becoming

more common for concrete pumps to be used to provide concrete delivery at a constant rate, have

a workable slump, and maintain the required concrete strength (Wei et al., 2015).

The above are some steps that are outlined in a construction site plan to indicate the operation of

the construction site. There may be additional steps required based on site details and the city

process for each location. The interaction diagram in the following section details some factors

that may influence decisions for the steps found in this planning process.

Page 71: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

59

4.6 Interaction Diagram

The interaction diagram is to be used as a guide and checklist of factors that affect decision

making. This can be used by new and experience project managers in the industry, as well as be

a teaching tool for students to illustrate the impacts of decisions in site planning. The relationship

of factors is explained, as well as some observed scenarios where their impact is discussed in

terms of other site planning decisions and the variety in applications. The interaction diagram

includes significance ratings of the relationships to illustrate the importance of decision

relationships.

As each construction site is unique in its geographical and physical features, it is first necessary

to generalize equipment and operation interactions that occur across all sites. Routine

interactions that influence site logistics are summarized in Figure 14. Some categories interact

with each other, and some all factors, shown at the top, have an impact on multiple categories.

For example, the traffic management plan and concrete pump affect the crane and hoist, whereas

noise by-laws affect multiple equipment operations. The diagram has been organized by

grouping categories of factors together by equipment or process. The factors in squares are big

decision points for equipment, whereas the factors in circles contribute towards those decisions.

All categories have letters and each factor is numbered. For instance, the factor shared suites

under category all factors is factor A1. The factors are bolded throughout the following sections.

All factors are outlined in section 4.6.1, while sections 4.6.2 to 4.6.5 discuss category-specific

factors. Finally, section 4.7 explains some factors that cannot be rated due to their impact being

site specific, the varying examples observed at sites, and some procedures to be used in the

situations.

Page 72: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

60

Figure 14: Site Interaction Diagram

4.6.1 All Factors

All factors do not fit into any of the other equipment or logistics categories and impact several

decisions on the site. They are directly influenced by the individual building. Currently,

residential building construction is funded through the sale and occupancy of units, whereas

commercial buildings are financed by the owners (Hendrickson and Au, 1989). Since the income

for each residential unit is not released to the developer until the unit is occupied, completing the

construction of residential buildings on time is important to reduce borrowing costs. In large

projects with multiple or very tall towers, the developer may wish to stage the transfer of units to

owners rather than wait until the entire project is complete. In order for units to be occupied

before the construction of the entire building is complete, units that are sold must be prioritized

for finishing at the start of site planning so they can meet occupancy standards (Government of

Ontario, 1992). This is represented as the occupancy factor (A4) on the interaction diagram. The

Page 73: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

61

influence of this factor includes locating the crane and hoist away from the early occupancy

units.

Fortunately, unit finishing is not a critical activity if planned correctly. A critical activity is an

activity on the critical path, so if the duration of the critical activity changes, the overall duration

of the project will also change. A critical path is defined as “a sequence of critical activities that

form the longest sequence in a project…the sum of the activity durations, taking into account

leads and lags, determines the overall project duration” (Baldwin and Bordoli, 2014). In contrast

to unit finishing, lobby finishing and mechanical equipment installation, under the building

finishes factor (A5), are vital to the operation and occupation of the building. These are activities

that may fall under the avoid critical path task factor (A3), therefore, crane and hoist locations

must be chosen to avoid interfering with these areas of the building. The interference caused by

the hoist and crane can be minimized by placing both pieces of equipment in the same suite,

represented by the shared suite factor (A1). However, special care must be taken to ensure there

is enough area in the units for the crane to be located inside, and deliveries from the hoist to

easily maneuver to other parts of the building.

Another factor that impacts the placement of the crane is the building height (A2). As a building

gets taller, the crane operator’s sight line to the pick-up point becomes obstructed by the building

slab edges. Although, this can slow down lifts due to the requirement of radio communication

with the crane operator to perform lifts, crane operators usually learn the flight paths of each lifts

and can perform them without being able to see them due to repetition. Taller buildings may

interfere with aircraft flight paths depending on their location. This consideration requires

including Aviation Canada during planning to check flight paths and the approved maximum

height for construction in the area to obtain air rights (B7) for the crane. It is also important to

note that the tower crane extends higher than the building and so the allowed height for clearance

should be the maximum height of the tower crane and not the building itself.

The above factors largely influence the location of equipment, however, there are also factors

that affect the equipment and site operation. The first of these factors is impacted by the local

noise by-laws (A8). For Toronto, the noisy by-law restricts site operations on weekdays to be

Page 74: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

62

between 7 a.m. to 7 p.m. (City of Toronto, 2009) to ensure neighbors are not disturbed. Beyond

site operations, the noise by-laws impact equipment operation and delivery schedules. Deliveries

can only occur outside the allowed time if they do not produce noise and are from a non-

unionized trade.

Another factor that effects the equipment operation is wind speeds (A7) as the crane and hoist

can only operate when the wind speed is below 50 km/h (Infrastructure Health and Safety

Association, 1995). High wind speeds above 50 km/h, sometimes observed in Toronto between

October and May, cause site operations to shut down and delay the schedule (Metoblue, 2006).

As such, the local wind patterns often dictate the location of the hoist. Toronto has prevailing

westerly winds, which means if the hoist was located on the north or south face the winds would

shear the hoist and impede its operation (Metoblue, 2006).

Finally, several pieces of equipment and processes on the construction site require energy and

heating to operate, as addressed by the site power factor (A6). These can be either through

diesel-powered generators or an electricity service connection. It is important to note that

generators produce high levels of noise that can be avoided with a serviced site.

4.6.2 Traffic Management Factors

A traffic management plan is required to outline the safety and logistics procedures of the site

(City of Toronto, 2017b). The street layout around the site and the building layout in context to

the site influence the locations of site entrance and exit gates (E1). These gates seek to separate

the site vehicular traffic from the public and provide safety for pedestrians and public vehicular

traffic in the area. Under the pedestrian and vehicular protection factor (E2), the site must

have a temporary fence around its perimeter and overhead protection or rerouting of pedestrians,

both of which influence where the gates can be located (OHSA, 1997). The available space (E3)

on the site also dictates the traffic management plan as it outlines the traffic route for deliveries

at the site. Inadequate space on a site may result in the need to obtain additional space from the

city around the construction site in the form of sidewalks, roads, or adjacent parking lots, which

involve an additional cost to the project.

Page 75: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

63

In addition to these costs, road permits (E4) and police escorts may be required for delivery of

loads wider than 1.5m, dictating the delivery schedule (E5) and project cost (Ministry of

Transportation, 2017). Finally, to ensure a smooth flow of traffic and delivery to the construction

project, the traffic management plan must outline the locations of loading docks and pumping

areas for the hoist, crane, and concrete pump. Spacing out the loading areas for these pieces of

equipment will aid in avoiding delivery conflicts.

4.6.3 Crane Factors

As buildings get taller, vertical delivery of materials becomes a crucial part of the planning

process as the longer times to move material over the increased distances causes a decrease in

productivity of the crane. To optimize crane operations on site, crane logistics must be carefully

planned in the early stages. The crane logistics can be described in terms of three categories:

location, operation, and crane type.

4.6.3.1 Crane Location

The crane location (B1) is influenced by a number of factors, as seen in the interaction diagram

in Figure 14. A consideration for choosing the crane is to ensure that the crane’s radius (B10)

and capacity (B18) is able to pick up the heaviest loads on site and deliver them to the materials’

required drop off location (Hosseini et al., 2017). Typically, locating the crane at the centre of

the building footprint can achieve this, however, the crane must not hit any surrounding

buildings (B13) when it is left to weathervane (B11) and must avoid being located in any areas

that might delay the building finishing because they are critical path tasks (A3) (Bodéré and

Grillaug, 2005). Air rights (B7) have to be obtained for crane swings over surrounding land for

the boom and lifted loads to fly over neighbor and city property. For larger sites, more than one

crane may be necessary, as represented by the number of cranes factor (B15). In this case, the

crane locations and erection plan must ensure that cranes can service the entire site without the

jibs and masts of the cranes interfering with one another, as per the crane interaction factor

(B14) (Zhang et al., 1999). Single cranes may also be chosen to be located near the building

footprint’s edge if possible, so the slab does not obstruct the crane operator’s sight line (B5) to

the pick-up point. The sight line (B5) to the material pick-up point (B6) is influenced by the

Page 76: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

64

traffic management plan as the delivery routes and loading areas are part of this plan. It is

important to note that in Ontario, cranes are typically owned by formwork contractors, and so the

location of formwork storage (B8) should be accessible for lifts.

Finally, the dismantling (B4) procedure must be considered when the crane location is chosen.

A mobile crane may not be able to reach the tower crane for removal if the tower crane is too far

from the road or too high. In buildings that are less than 40 storeys high, large mobile crane can

be used for the dismantling process. The typical dismantling procedure for a tall building

requires the use of a derrick crane located on the roof. The tower crane erects the derrick crane,

then the derrick crane is used to dismantle the tower crane and transport it down the building.

The derrick crane is dismantled and transported down the building using the construction hoist.

Since the dismantling procedure can vary depending on tower crane location and height, a

consultant will typically outline the dismantling procedure at the beginning of the project to

guarantee the crane can be removed. The crane location effects the excavation (B9) procedure

since the foundation has to be poured at the crane location so the crane can be erected as early as

possible.

4.6.3.2 Crane Type

Although the type (B3) of crane is influenced by the construction site requirements in terms of

the loads that it must carry, the availability of the tower crane from the supplier dictates what can

be used on the site. In Toronto, cranes are typically rented from formwork contractors for the

duration of the project. The two choices that must be made when picking a crane is if the crane

will be an internal or external crane, and if it will be a hammerhead or a luffing crane.

An external crane is anchored at the envelope of the building and creates holes in the envelope

that remain open until all construction is completed. An interior climbing crane, on the other

hand, is wedged into openings in the slab and moves up the inside of the building. The climbing

crane requires reshoring for 7-8 floors below it, but frees up the lower floor slabs for finishing

purposes. The external cranes are easier to erect and dismantle than the climbing cranes as the

building structure does not impede them, but have a higher cost than climbing cranes. For some

Page 77: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

65

buildings, where finishing the slab is more important and the budget allows, the external crane

may be a better choice.

Depending on the neighboring buildings, a luffing crane may be chosen if the radius of a

hammerhead crane would interfere with surrounding structures. The hammerhead crane has a flat

jib, whereas the luffing crane has a jib which can be lowered to reach large radii and lift to avoid

neighboring structures during a swing or weather-vaning. Since the luffing crane is typically

slower than the hammerhead crane, hammerhead cranes are preferred where possible. In some

special cases, the project manager may choose to switch to a hammerhead crane from a luffing

crane once the crane’s boom clears the height of neighboring buildings to save operation time

and cost. It is important to keep in mind that this will result in additional erection and

dismantling costs, and that the decision of type of crane will impact the speed (B17) of each lift.

4.6.3.3 Crane Operation

The type (B3) and location (B1) of the crane impact its operation (B2). If a location is picked

for the crane which requires a larger radius for material lifts, the time required to complete each

lift increases. Inversely, the lifting capacity of the crane decreases as the load is further from the

center and results in the jib deflecting due to heavy loads. In addition to this deflection, lifted

materials can sway if they encounter strong winds. Since there is a risk of hitting surrounding

buildings with erratically swinging loads, crane lifts may not be performed or be performed at a

slower speed (Infrastructure Health and Safety Association,1995). Finally, the ambient

temperature (B16) has an impact on whether a tower crane can be operable or not, as they are

typically operable only above -20°C. It is important to note that the presence of a concrete pump,

hoist and other cranes reduce the overall payload of the crane, dividing tasks over many

resources.

4.6.4 Concrete Pump Factors

The presence and operation (C2) of a concrete pump is one method to reduce the payload of the

tower crane as it dedicates one piece of equipment to concrete transportation and ensures that the

crane is not a limiting piece of equipment on the construction schedule (Wei et al., 2015).

Page 78: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

66

The concrete is pumped up the building through a pipe connected to the pump. The boom of the

pump is moved with the crane or hydraulically with the use of a remote control. It is very rare for

the pipe to be moved by hand for concrete pumping. As concrete is being moved over greater

distances, superplasticizers are added to the mix so the concrete is flowable, but maintains the

required strength (Kosmatka and Panarese,1994).

The location (C1) of the concrete pump is dictated by the available space on the site. Usually,

the concrete pump is placed at the ground floor of the building. If there is no space for concrete

truck to deliver the concrete on site, or for the pump to be placed, the concrete pump can be

located across the street or on adjacent properties with pipes run underground if necessary to

allow vehicular traffic. Another consideration for the location (C1) factor of the concrete pump

is the placement of the hose and boom, since they can impact the finishing process in a project. It

is preferable for the hose to be run through a stairwell or an adjacent opening beside the elevator

shaft, since running the hose through suites can delay the finishing of the suite.

Finally, the location of the site affects the type (C3) of concrete pump that can be used, mainly

due to the noise by-law (City of Toronto, 2009). If the building is in a residential area, an electric

pump is preferred to limit the noise caused by the construction site. In industrial areas, a gas-

fueled pump can be used.

4.6.5 Hoist Factors

In tall residential buildings, construction hoists are used to move material and personnel up the

building, since the building elevator is typically not operational and cannot be used by site

personnel. From site observations, it was concluded that hoists are typically installed when the

concrete formwork reaches the 10th floor.

4.6.5.1 Hoist Locations

The main consideration when planning the location (D1) of the hoist is to minimize the openings

in the building without requiring additional landing platforms. This is represented by the

balcony/window line factor (D5) on the interaction diagram, typically accomplishing this by

locating the hoist at balconies or where the envelope is consistent, and to reshore the slab to

Page 79: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

67

provide adequate strength. The location of the hoist is influenced by the available space (D7)on

the construction site, as a building close to the perimeter of the plot may result in the hoist or the

loading dock (D6) encroaching on neighboring property and require special permission. The

location of the hoist should also minimize the distance materials and personnel have to travel on

the floor from the hoist. This can be done by locating the hoist at the centre of the long side of

building (D4). Finally, it is necessary to obtain recommendations from the site superintendent

since they understand the site and the effect the location of the hoist will have on daily tasks.

4.6.5.2 Hoist Type

The type (D3) of hoist that is chosen has an effect on the productivity of the trips. First, the size

(D16) of the hoist car depends on the largest window units that have to be transported up the

building, as hoists typically transport window wall system panels. In addition to size, the door

access (D12) should be able to receive deliveries from the loading dock and deliver loads to the

openings on the building. Sometimes there is only one door if the loading dock can be placed in

the same location as access to the upper floors, however, due to available space, sometimes doors

are required on both sides of the hoist. The type of hoist impacts the speed (D14) with which

deliveries are made, as a self-leveling hoist may be chosen. A self-leveling hoist aligns the floor

of the hoist with the floor slab of the building so the operator does not have to adjust the cab,

thus increasing the productivity.

Another way to increase productivity is to use a hoist with a larger capacity (D13), since this

will decrease the number of trips necessary for transporting materials and personnel. The

capacity of the hoist can also be augmented by increasing the number of hoist cars (D15). The

number of cars will depend on the height and footprint of the building, as a larger building

indicates more materials and personnel that need to be moved. Unfortunately, the increase in

hoist cars results in an increase in openings in the building. A solution that has been observed is

the addition of an outrigged landing platforms for the hoists on all floors to service 6 car hoists,

with 3 masts, as can be seen in Figure 15. This results in only needing one opening in the

building while substantially increasing the number of hoists.

Page 80: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

68

Figure 15: Hoist Outrigged Platform

4.6.5.3 Hoist Operation

As with all activities for each project, the operation (D2) of the hoist revolves around a

schedule. Outside of the morning rush up and end of day rush down for personnel, the hoist is

used to move materials up the building. Due to this, a booking system (D9) must be developed

so trades can ensure their materials are shipped to their required locations when needed.

Furthermore, a skilled operator (D8) is able to intuitively decide how the hoist lift cycles will be

carried out, since the hoist is not automatic and the hoist operator can change the direction of the

hoist based on requests for pick up (Hwang, 2009). As with all equipment, the reliability (D11)

of the hoist is dictated by the age and maintenance procedure of the hoist. Project managers tend

to rent hoists that are under five years old, as seen on the observed sites, at a slightly higher cost

to avoid hoist breakdowns.

Part of planning the hoist lift plan is to include days when hoist cars are not operational due to

performing a hoist jump (D10). The hoist mast is extended every three to seven floors as seen

on site. This process consists of attaching the cab to the mast using cables and disengaging the

cable that allows the cab to move up and down the mast. Sections of the mast are lowered by the

crane and hoist carpenters attach the section to the existing mast to extend it using clamps while

standing in the hoist cab. When the extension of the mast is completed, the cable upon which the

cab rides is run up the extended mast, and the tension is restored so it carries the hoist car once

Page 81: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

69

again. After this process is complete, an inspection must be carried out to ensure the hoist is

anchored and operating correctly. The extension can take up to a day, which means every three

to seven floors, one hoist tower with one or two cars attached to it becomes unavailable. These

are some factors that are not seen in the simulations that are developed in literature, depending

on experienced project managers to plan accordingly.

4.7 Relationship Significance

After all the factors and relationships were modelled in the interaction diagram, their significance

was identified based on trends observed at the construction sites and after reviewing their

construction management plans. The relationships were rated on a scale of 1 to 5, very low to

very high importance, respectively. Any relationships that could not be rated due to large

variations in their importance based on the situation or management techniques were left unrated

on the interaction diagram. The differences in ratings are shown in Figure 16. The figure aims to

graphically show the ratings, as well as the differences in agreement between the two

individuals. Some situations that can alter the importance of a relationship are outlines in Table

8. A chart of all ratings can be found in Appendix B.

Figure 16: Relationship Rating Difference

Page 82: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

70

Table 8: Situation where Relationship Significance Varies

Relationship Reasoning

Shared suites

(A1) to crane

location (B1).

Sharing suites for the crane and hoist location is ideal to decrease the areas that

cannot be finished until the equipment is removed. Unfortunately, this is dependent

on the unit layout and the available space in each unit since the crane may block

deliveries from the hoist if there is not enough space in the unit. The relationship

significance will vary since this method may only be carried out when possible, and

in other situations may have a high impact on the location decision for both the

crane and the hoist.

Shared suites

(A1) to hoist

location (D1).

Formwork

storage (B8) to

crane location

(B1).

There is a variation in the relationship significance for the location of the formwork

for project managers, as formwork engineers are typically responsible for the

operation of the crane, as well as the formwork storage. Due to this, the project

managers may have to modify their decisions based on the formwork engineer’s

requirements.

Road permit

(E4) to delivery

schedule (E5).

Depending on the location of a construction site and the surrounding roads and

traffic, obtaining road permits may range in difficulty from obtaining road permits

with an associated expense to rerouting site traffic and deliveries outside the area or

work times to accommodate local traffic.

Crane type (E3)

to crane speed

(E17).

The major influence that the crane type has on the crane speed is choosing between

a hammerhead and a luffing crane, as luffing cranes require more time to complete

swings due to needing to fold up the jib.

4.8 Conclusion

This paper outlines a general planning process used in construction site logistic planning at the

start of a project and discusses factors that affect planning decisions in detail. It presents an

interaction diagram that shows relationships between decision factors and planning categories and

indicates their significance in a variety of scenarios.

This paper aims to be used as a teaching tool for in-class learning, an introduction to new personnel

in the industry, and a support tool for decision making by experienced professionals by presenting

situations and nuances of the factors included in the interaction diagram. Since there is no existing

site logistics manual due to geological and site-specific differences, this paper presents a

framework for general decisions that can be observed on all sites, with details specific to the City

of Toronto. The proposal for future work in the field consists of developing a phone based

application that can be used to carry out logistic planning decisions seen in section 4, and provide

resources for planners including links to permits, and reminders of application deadlines to aid in

completing the required tasks during the initial phases of site planning.

Page 83: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

71

Chapter 5 Conclusion

The entirety of chapter 5 summarizes findings through the research, the contributions to the body

of literature, and paths for future research to follow the development of the interaction diagram

as a decision-making tool and the site logistics interaction diagram to be applied to construction

site planning in Toronto for tall buildings.

Conclusion

The three papers included in this dissertation establish the current procedures used in

construction site logistics planning and use features of existing decision-making tools to create

an interaction diagram for decision-making in construction projects of tall building projects.

In chapter 2, programs for storage on construction sites were reviewed and a proposed

framework for construction planning was introduced. With the framework in mind, it was

necessary to revisit the planning process at an earlier stage. From this, planning processes for the

whole of the construction site were observed on sites and decision-making tools were reviewed

in chapter 3. The interaction diagram was introduced as a tool for decision-making where each

decision had an impact on several domains. An interaction diagram for vertical transportation

equipment for tall buildings in Toronto was developed and applied to a construction site in

Toronto. This interaction diagram and the construction process were described in chapter 4.

5.1 Research Contributions

The interaction diagram was developed as a decision-making tool for multi-domain decisions to

support users in complex planning problems, allow them flexibility in planning and apply their

knowledge for each decision, and encourage communication between trades and stakeholders

early in the planning process by visually showing users all the domains that are impacted by a

decision. This aim of this tool is to be comprehensive and adaptable for users.

The interaction diagram was applied to construction logistics planning with a focus on vertical

transportation for tall buildings in Toronto to summarize the implicit knowledge from interviews

Page 84: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

72

with industry professionals. Several interaction diagrams can be made for various domains and

joined together to create a larger decision-making model that encompasses all domains of a

construction site. The four goals of this research were addressed throughout the chapters. These

are listed below:

1. The methods for construction planning and storage were summarized in chapters 2, 3.4

and 4.4. These chapters looked at storage methods, logistic planning models, equipment

management, information exchange models and decision-making tools. A typical

construction planning procedure used in industry was outlined in chapter 4.5. This

information was gathered through interviews with planners and review of the procedure

with experts.

2. Site operations were observed on a variety of construction sites in the GTA and expert

planners in the industry were interviewed. These site visits led to gathering concrete lift

time data for lifts of varying materials and weights, at different sites, during different

weather conditions. The sites were observed from fall throughout winter to include

impacts of wind and cold weather in Toronto.

3. The interaction diagram was developed as a method for decision-making across multiple

domains. The method for creating the interaction diagram was presented in chapter 3.6.

The interaction diagram separates factors for each domain and shows impacts of a

decision on factors within and outside of the domain, thus enabling users to view impacts

of a decision for an entire project at a glance.

4. The interaction diagram was applied to vertical transportation domains on tall

construction buildings in Toronto. The factors were collected through site visits and

surveys with professionals. The vertical transportation interaction diagram is introduced

in chapter 3.6 and applied to a building in Toronto in chapter 3.6.3, where decisions using

the interaction diagram are compared to decisions that were carried out on the actual

construction site. This interaction diagram is explained in detail, where each factor, its

impact and the reason for each decision is described in chapter 4.6.

Page 85: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

73

5.2 Limitations of Research

Although the interaction diagram allows users the freedom to make decisions suitable to their

needs, it is a tool that requires updating. This can be in the form of adding sections for new

technologies that would make construction more efficient or gathering additional factors for new

domains of impact. The use of the interaction diagram is dependent on the industry professional

using it and on their understanding of each construction project.

As a way to address these limitations, it is recommended that the interaction diagram is updated

on a set time frame for each company or when a new construction method or technology is

developed. The interaction diagram is built to allow users to make decisions with a glance on the

impacts on the overall project and draw on their own experience, however, creating an automated

program to aid in the use of the interaction diagram would add structure to the decision-making

process. This option is explored in the following section.

5.3 Future Research

Through site visits and interviews with industry experts, areas of further research have been

identified. As previously mentioned, a program should be created to automate parts of the

logistics process for construction logistics planning and add structure to planning process. This is

discussed in section 5.3.1. In this section, the framework for a program for a tower crane and

concrete pump is introduced, as well as databases for tower cranes, concrete buckets and

concrete pumps. A database for construction hoists should be developed by collecting

manufacturer data for construction hoists available in Toronto.

Furthermore, a program for hoist scheduling should be created that allows different trades to

request times for lifting their materials and site managers to review all requests. Currently, the

construction hoist schedules are typically booked on a first-come, first-serve basis. This does not

allow a schedule for the hoist that is always beneficial for the site, and trades are required to use

the hoist within their allotted time or risk losing their spot. In addition to the hoist scheduling

program, a web-based application available to project planners should be developed that can run

through the construction planning process outlined in section 4.5, alerting site planners of any

Page 86: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

74

documentation and permits they need to file, and ensuring all procedures are addressed. All of

these developments should draw on the factors outlined in the interaction diagram to ensure the

impacts are accounted for in the programs. Finally, more interaction diagrams covering all

domains of design, planning and construction should be created through interviews with industry

professionals to create an overview of the entire building process in Toronto.

5.3.1 Programming from Tacit Knowledge

Each domain of the interaction diagram introduced in the interaction diagram identifies areas

where programs can be created to work together to aid in construction site logistics planning.

One such area is to expand on existing programs of finding the best location for a crane using

purely mathematical calculations to create a program that finds the best location for the crane,

using building and equipment properties, combinations of pick-up and drop-off points and

adjusted equations from empirical data collection; and the improved site productivity when using

a concrete pump. A flowchart for the process is shown in Figure 17. More details can be found

throughout Table 9 to

Table 13, with references to which factors from the interaction diagram are included in the

program.

Page 87: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

75

Figure 17: Crane and Concrete Pump Program Decision Flowchart

Page 88: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

76

The first step of the program is to retrieve all relevant information of building characteristics,

equipment and weather data for the project at hand. This gives the program context as to what

problem is being solved so solutions are specific to the building and location. The user is then

asked to provide restrictions for pick-up points, number of pours and areas to avoid for the

placement of the crane. These are factors that the user can choose and is not restricted to the site

plans.

After this, equipment is chosen from crane and concrete pump databases. Combinations of the

pieces of equipment are run through the simulation to calculate the most efficient vertical

transportation time for the site using different types of equipment and locations for the

equipment. In these scenarios, materials to be lifted are assigned to specific pieces of equipment.

The concrete is assigned to the concrete pump if the scenario includes the concrete pump, and all

materials to be lifted are assigned to the tower crane.

The four scenarios for each simulation consist of: interior crane and concrete pump, exterior and

concrete pump, interior crane only, and exterior crane only. For each run, lift times for all

materials to be lifted are calculated and stored. The best 3 total lift times are stored in an array. If

the current run is better than the previous runs, the new time and crane coordinates are replaced.

Once all the points of the building are checked for coordinates of the crane, new combinations of

equipment are run through the program again.

Finally, after all equipment combinations have been checked, the program displays the results of

the best run time, the most efficient equipment combination, the predicted downtime for

equipment forecasted from historical weather data and the recommended dismantling procedure

for the crane based on the location of the crane. Table 9 to

Table 13 break down a pseudocode for a program to minimize the time of lifts for materials with

four scenarios consisting of cranes and concrete pumps on a construction site. Each step from the

flowchart in Figure 17 is represented by one of the following tables.

Page 89: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

77

Table 9: Step 1 – Retrieve All Inputs

Factor Code Comments

B13

B16

READ building coordinates and neighboring buildings to avoid

(starting from SW, going clockwise)

READ number of building floors and elevations of each

READ lift object information (type; x,y,z coordinates for pick-up and

drop-off points; weight)

READ crane database (crane radius, capacity, lift time)

READ concrete pump database (flow rate)

READ schedule breakdown procedure (day to day activities)

READ material breakdown based on schedule (day to day)**

READ weather data for temperature and rain/ snow patterns

ASSIGN a = total number of items to be lifted

Input from

database or

building model

**Create activity

(i) dependencies

Table 10: Step 2 - User Inputs

Factor Code Comments

B6

A3, A5

B4

ASK USER FOR:

Number of pours/ floor (pour layout)

3 pick-up point locations

Areas to avoid placing crane*

Acceptable closeness of crane to edge of slab*

Maximum distance of crane from road for removal of crane*

*automate if

possible

Avoid shear walls,

elevator shaft,

stairs and

mechanical room

for crane

placement

Table 11: Step 3 - Choose Equipment Combination

Factor Code Comments

CHOOSE crane from database and acceptable radius depending on

maximum lift weight and surrounding buildings distance

CHOOSE concrete bucket from database

CHOOSE concrete pump from database

Table 12: Step 4 - Calculate Total Lift Times for 4 Scenarios for Each Equipment

Combination

Factor Code Comments

Scenario 1: Interior Crane and Concrete Pump

Set Crane Coordinates: x = 0, y = 0

For y<= north coordinate of building

If x<=east coordinate of building

For (objecti = 1, i<a, i = +1)

Starts crane at SW

corner

Page 90: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

78

If obecti type ≠ concrete

CraneTimei = vertical lift time as a

function of object weight + horizontal

movement of boom and tangent movement of

hook time as function of distance from pick-

up point to drop-off point + lowering object as a

function of height of drop-off point + time to return

crane to pick-up point

Else

ConcretePumpTimei = Concrete

Pump flowrate * (zdist + √(xdist2 +

ydist2)) * area covered in pour (m2)

End if

Activity Time Duration Function

If i type = concrete

If day time = day time + activity

duration > 8

Activity start = next day at 0

hour

Activity end = activity

duration / 8

If day time = day time + activity

duration < 8

Activity start = day time

Activity end = day time +

activity duration

Elseif i type ≠ concrete

Activity start = activity end of

activityi-1

Activity end = activity start + activity

duration

End if

Store activity start and activity end in array j

End loop

Total Lift Time Function

If j total time = array k1

If crane location of j closer to the middle of

the building than crane location of k1

Array k3 = array k2

Array k2 = array k1

Array k1 = array j

End if

Else if j total time < array k1

Array k3 = array k2

Array k2 = array k1

Array k1 = array j

Calculates object

lift time for all

objects except

concrete

Calculates

concrete lift time

using concrete

pump

Stores activity

duration, day start

and day end in

array j (temporary

table for each run).

These are based on

8 hour work days.

Repeats loop for

next object

If current run is

better than stored

run, the top 3

results are replaced

so minimum time

and closest crane

location to the

center of the

building is stored.

This stores total

time of all lifts for

the construction of

the building,

schedule of lifts

and crane location

in the arrays.

Page 91: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

79

Else if j total time = array k2

If crane location of j closer to the middle of

the building than crane location of k2

Array k3 = array k2

Array k2 = array j

End if

Else if j total time < array k2

Array k3 = array k2

Array k2 = array j

Else if j total time = array k3

If crane location of j closer to the middle of

the building than crane location of k3

Array k3 = array j

End if

Else if j total time < array k3

Array k3 = array j

End if

x = x + ½ crane pad width

Else

x = 0

y = y + ½ crane pad width

End if

End loop

Moves crane x

direction

Moves crane y

direction

Scenario 2: Exterior Crane and Concrete Pump

x = -1/2 crane pad width

y = -1/2 crane pad width

For y <= N coordinate of building + ½ crane pad width

For (objecti = 1, i<a, i = +1)

If objecti type ≠ concrete

CraneTimei

Else

ConcretePumpTimei

Endif

End loop

Activity Time Duration Function

Total Lift Time Function

y = y + ½ crane pad width

End loop

For x <= E coordinate of budilnig + ½ crane pad width

For (objecti = 1, i<a, i = +1)

If objecti type ≠ concrete

CraneTimei

Else

ConcretePumpTimei

Endif

Starts outside

building at SW

corner

Moves coordinate

in positive y

direction

Page 92: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

80

End loop

Activity Time Duration Function

Total Lift Time Function

x = x + ½ crane pad width

End loop

For y >= S coordinate of building - ½ crane pad width

For (objecti = 1, i<a, i = +1)

If objecti type ≠ concrete

CraneTimei

Else

ConcretePumpTimei

Endif

End loop

Activity Time Duration Function

Total Lift Time Function

y = y - ½ crane pad width

End loop

For x >= W coordinate of budilnig + ½ crane pad width

For (objecti = 1, i<a, i = +1)

If objecti type ≠ concrete

CraneTimei

Else

ConcretePumpTimei

Endif

End loop

Activity Time Duration Function

Total Lift Time Function

x = x - ½ crane pad width

End loop

Moves coordinate

in positive x

direction

Moves coordinate

in negative y

direction

Moves coordinate

in negative x

direction

Scenario 3: Interior Crane Only

Set Crane Coordinates: x = 0, y = 0

For y<= north coordinate of building

If x<=east coordinate of building

For (objecti = 1, i<a, i = +1)

CraneTimei

End loop

Activity Time Duration Function

Total Lift Time Function

x = x + ½ crane pad width

Else

x = 0

y = y + ½ crane pad width

End if

End loop

Starts crane at SW

corner

Moves crane x

direction

Moves crane y

direction

Page 93: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

81

Scenario 4: Exterior Crane Only

x = -1/2 crane pad width

y = -1/2 crane pad width

For y <= N coordinate of building + ½ crane pad width

For objecti

CraneTimei

i = i + 1

End loop

Activity Time Duration Function

Total Lift Time Function

y = y + ½ crane pad width

End loop

For x <= E coordinate of budilnig + ½ crane pad width

For objecti

CraneTimei

i = i + 1

End loop

Activity Time Duration Function

Total Lift Time Function

x = x + ½ crane pad width

End loop

For y >= S coordinate of building - ½ crane pad width

For objecti

CraneTimei

i = i + 1

End loop

Activity Time Duration Function

Total Lift Time Function

y = y - ½ crane pad width

End loop

For x >= W coordinate of budilnig + ½ crane pad width

For objecti

CraneTimei

i = i + 1

End loop

Activity Time Duration Function

Total Lift Time Function

x = x - ½ crane pad width

End loop

Starts outside

building at SW

corner

Moves coordinate

in positive y

direction

Moves coordinate

in positive x

direction

Moves coordinate

in negative y

direction

Moves coordinate

in negative x

direction

REPEAT all scenarios for different combinations of tower crane and

Page 94: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

82

concrete pump to determine best lift times

Table 13: Step 5 - Display Results

Factor Code Comments

DISPLAY best time for each scenario, equipment used and location of

tower crane

DISPLAY time hoist and tower crane are estimated to be inoperable

from forecasting from historical weather data

RECOMMEND dismantling procedure applicable based on each crane

location

The program uses equipment database to retrieve information relevant to calculations. A crane

database and concrete pump database were created. The crane database, shown in Figure 18,

summarizes crane type, capacity, height, and other characteristics of cranes available in Toronto.

A crane load chart can be seen in Figure 19, showing that as crane boom length and radius

increases, the capacity of the crane decreases. The information for the crane database is retrieved

from individual crane load charts included in Appendix C. Cranes are owned by various

formwork companies, and therefore the stock may differ between companies. For this reason, a

variety of cranes were included in the database so a company could choose the crane they owned

after the program optimizes the crane for the particular site. Concrete pump and concrete bucket

data are retrieved from manufacturer data for equipment in Toronto. These can be seen in Figure

20 and Figure 21, respectively.

Page 95: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

83

Figure 18: Crane Database Summary

Figure 19: KNF 336i-16 Load Chart

Page 96: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

84

Figure 20: Concrete Pump Database Summary

Figure 21: Concrete Bucket Data Summary

Adding to this program, the construction hoist operation can be added to determine material

handling and delivery times by the hoist and the improved productivity of the construction site as

the overall payload of the crane is decreased. Finally, interaction diagrams for the planning

phases and other domains of construction or the lifetime of a building can be developed and used

Page 97: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

85

with the construction site logistics interaction diagram to increase the scope of decision-making.

In this manner, the interaction diagram can be used to visually view the impacts of factors and

their decisions on multiple domains, and act as an input for the creation of programming for

construction site logistics planning.

Page 98: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

86

References

Ali, H., Marquis, P., McCabe, B., Shahi, A. Lyall, R., and Francavilla, J. 2016. Challenges of

Site Logistics for Tall Building Construction. Canadian Society of Civil Engineering

Conference, London, Ontario, p. 155-165.

Ba, L., Yang, Y., Liang, S., Mo, H., Cao, H., Lie, T., and Chen, J. 2009. Progress in Study of

Concrete Pumping Construction Techniques in Super High-Rise Building. Key

Engineering Materials Vols 405-406, p. 110-116.

Baldwin, A, and Bordoli, D. 2014. A Handbook for Construction Planning and Scheduling. John

Wiley & Sons Ltd. West Sussex, UK.

Bertelsen, S., and Nielsen, J. 1997. Just-in-time Logistics in the Supply of Building Materials.

1st International Conference on Construction Industry Development: Building the Future

Together, Singapore: p. 9-11.

Bielza, C., Gomez, M., and Shenoy, P. P. 2010. Modelling Challenges with Influence Diagrams:

Constructing Probability and Utility Models. Decision Support Systems 49, p. 354-364.

Bodéré, S., and Grillaug, G. 2005. Wind effects on out-of-service tower cranes. European and

African Conference on Wind Engineering (4), p. 44-45.

Cheng, J. and Kumar, S. 2015. A BIM-based Framework for Material Logistics Planning. 23rd

Annual Conference of the International Group for Lean Construction: Global Knowledge

- Global Solutions, Production Planning and Control, Perth, Australia 34, p. 33-42.

Cho, C., Cho, M., Kim, Y., Kim, J., Lee, J., and Kwon, S. 2010. Simulation Method of

Construction Hoist Operating Plan for High Rise Buildings Considering Lifting Heights

and Loads. International Symposium on Automation and Robotics in Construction 2, p.

22- 28.

City of Toronto. 2006. Traffic Operations Assessment: Terms of Reference.

http://www1.toronto.ca/static_files/CityPlanning/PDF/traffic.pdf

City of Toronto. 2009. Toronto Municipal Code. Chapter 591: Noise.

http://www.toronto.ca/legdocs/municode/1184_591.pdf

City of Toronto. 2010. Geotechnical Study/ Hydrogeological Review.

http://www1.toronto.ca/static_files/CityPlanning/PDF/geotechnical.pdf

City of Toronto. 2013. Guidelines for the Preparation of Transportation Impact Studies.

http://www1.toronto.ca/City%20Of%20Toronto/Transportation%20Services/Files/pdf/TI

S_InternetSecured_20130708.pdf

City of Toronto. 2014a. Toronto Municipal Code. Chapter 363.

http://www.toronto.ca/legdocs/municode/1184_363.pdf

City of Toronto. 2014b. Policy for Accepting Potentially Contaminated Lands to be Conveyed to

the City under the Planning Act.

http://www.toronto.ca/legdocs/mmis/2015/pw/bgrd/backgroundfile-74422.pdf

Page 99: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

87

City of Toronto. 2015. Street Occupation Permit Fee Revisions.

http://www.toronto.ca/legdocs/mmis/2015/pw/bgrd/backgroundfile-80114.pdf

City of Toronto. 2017a. Construction Permit Information: Street Occupation.

http://www1.toronto.ca/wps/portal/contentonly?vgnextoid=efe5a84c9f6e1410VgnVCM1

0000071d60f89RCRD&vgnextchannel=2bdb4074781e1410VgnVCM10000071d60f89R

CRD

City of Toronto. 2017b. Planning Application Checklist.

https://wx.toronto.ca/intra/it/pubformrep.nsf/57a82d5a76decda785257460004a171a/0a03

cb5478ceaf7a852574730067b08d/$FILE/11-0008-Development-Approval-Planning-

Checklist.pdf

Council of Tall Buildings and Urban Habitat. 2018. CTBUH Height Criteria.

http://www.ctbuh.org/TallBuildings/HeightStatistics/Criteria/tabid/446/language/en-

US/Default.aspx

Enbridge. 2016. Natural Gas for Residential Construction Heat.

https://www.enbridgegas.com/businesses/builders-contractors/for-builders/natural-gas-

residential-construction-heat/

Gaich, A., and Pötsch M. 2015. 3D Images for Data Collection in Tunneling-Applications and

Latest Developments. Geomechanics and Tunneling 8 (6), p. 581-588.

Gore, S., Song, L., and Eldin, N. 2012. Photo-modeling for Construction Site Space Planning.

Construction Challenges in a Flat World, Construction Research Congress, West

Lafayette, Indiana, p. 1350-1359.

Government of Ontario. 1992. Ontario Building Code. Division C, Part 1, Subsection 1.3.3.5.

https://www.ontario.ca/laws/regulation/120332

Government of Ontario. 2016. Proposed Growth Plan for the Greater Golden Horseshoe.

https://placestogrow.ca/index.php?option=com_content&task=view&id=420&Itemid=12

Government of Ontario. 2012. https://www.ontario.ca/page/guide-site-assessment-cleanup-

brownfields-filing-records-site-condition

Heikkilä, R., Malaska, M., Törmänen, P., and Keyack. C. 2013. Integration of BIM and

Automation in High-rise Building Construction. 30th International Symposium on

Automation and Robotics in Construction and Mining, ISARC, Montreal, Quebec,

Canada 23, p. 1171-1176.

Hendrickson, C and Au, T. 1989. Project Management for Construction. Chapter 1: The Owner’s

Perspective. Prentice Hall.

Hoesseni, M., Beiranvand, P., Dadgar, M.R., and Olfati, A. 2017. A mathematical model for

optimal tower crane layout planning. Decision Science Letters 6, p. 377-386.

Howard, R.A., and Matheson, J.E. 2005. Influence Diagrams. Decision Analysis 2(3), p. 127-

143.

Page 100: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

88

Huang, C., and Wong, C.K. 2015. Optimisation of Site Layout Planning for Multiple

Construction Stages with Safety Considerations and Requirements. Automation in

Construction 53(1), p.58-68.

Hwang, S. 2009. Planning Temporary Hoists for Building Construction. Construction Research

Congress 1, p. 1300-1307.

Infrastructure Health and Safety Association. 1995. Hoisting and Rigging Safety Manual.

Irizarry, J., & Karan, E. P. 2012. Optimizing location of tower cranes on construction sites

through GIS and BIM integration. Journal of Information Technology in Construction

(ITcon) 17(23), p. 351-366.

Issa, U.H. 2013. Implementation of Lean Construction Techniques for Minimizing the Risks

Effect on Project Construction Time. Alexandria Engineering Journal 52(4), p. 697-704.

Jung, M., Park, M., Lee, H., and Lee, B. 2014. Resource-based Multi-method Simulation Model

for Super-tall Building Construction. Computing in Civil and Building Engineering,

ASCE, Orlando, Florida, USA, p. 1045-1052.

Kamleh, M. 2014. Improving Hoist Performance during the Up-Peak of Tall Building

Construction. University of Toronto thesis.

Kang, S., Chi, H., and Miranda, E. 2009. Three-Dimensional Simulation and Visualization of

Crane Assisted Construction Erection Processes. Journal of Computing in Civil

Engineering 23(6), p. 363-371.

Kim, T., Lim, H., Kim, S., Cho, H. and Kang, K. 2016. Inclined construction hoist for efficient

resource transportation in irregularly shaped tall buildings. Automation in Construction

62, p. 124-132.

Kosmatka, S., and Panarese, W. 1994. Design and Control of Concrete Mixtures. 13th Edition.

Portland Cement Association.

Kumar, S.S., and Cheng, J.C.P. 2105. A BIM-based Automated Site Layout Planning

Framework for Congested Construction Sites. Automation in Construction 59, p. 24-37.

Lee, D., Son, K., and Kim, S. 2011. Analysis of Operation Efficiency of Tower Crane in Form

Work Construction for Multi-family Housing. Proceedings of the 28th ISARC, Seoul,

Korea.

Lee, Y., Eastman, C.M., and Solihin, W. 2018. Logic for Ensuring the Data Exchange Integrity

of Building Information Models. Automation in Construction 85, p. 249-262.

Li, H., and Love, P. 1998. Site-level Facilities Layout Using Genetic Algorithms. Journal of

Computing in Civil Engineering 12(4), p. 227-231.

Linstone, H.A., and Turoff, M. 1975. The Delphi method: Techniques and applications. Reading,

Mass: Addison-Wesley Publishing Company.

Liu, H., Li, W., and Zhao, Q. 2009. Measuring method of concrete pump discharge based on

pressure. IEEE International Conference on Robotics and Biomimetics, p. 1527-1531.

Page 101: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

89

Lumina. 2018. Why Analytica? http://www.lumina.com/why-analytica

Macnab, A. 2002. Earth Retention Systems Handbook. New York: McGraw Hill Professional.

Marhani, M.A., Jaapar, A., Bari, N.A.A. 2012. Lean Construction: Towards Enhancing

Sustainable Construction in Malaysia. Procedia Social and Behavioural Sciences 68, p.

87-98.

Marler, R.T., and Arora, J.S. 2004. Survey of Multi-objective Optimization Methods for

Engineering. Structural and Multidisciplinary Optimization 26 (6), p. 369-395.

McCabe, B., Alderman, E., Chen, Y., Hyatt, D.E., and Shahi, A. 2017. Safety Performance in the

Construction Industry: Quasi-Longitudinal Study. Journal of Construction Engineering

and Management 143(4), art. 04016113.

Metoblue. 2006. Climate Data: Toronto.

https://www.meteoblue.com/en/weather/forecast/modelclimate/toronto_canada_6167865

Ministry of Transportation. 2009. A Guide to Oversize/Overweight Vehicles and Loads in

Ontario. http://www.mto.gov.on.ca/english/trucks/oversize-overweight-manual.shtml

Nav Canada. 2017a. Land Use Program. http://www.navcanada.ca/EN/products-and-

services/Pages/land-use-program.aspx

Nav Canada. 2017b. Land Use Processing Times and Assessment Procedures.

http://www.navcanada.ca/EN/products-and-

services/Forms/Land%20Use%20Processing%20Times%20and%20Assessment%20Proc

edures.pdf

OHSA. 1997. Occupational Health and Safety. https://www.worksafebc.com/en/law-

policy/occupational-health-safety/searchable-ohs-regulation/ohs-regulation/part-14-

cranes-and-hoists#SectionNumber:14.92

Park, K., Jang, M., and Lee, H. 2001. An Analysis of the Optimal Planning of Material Lifting in

the High-Rise Building Construction. Conference Proceeding of AIK 21(2), p. 515-519.

Perrenoud, A., Lines, B.C., Savicky, J., and Sullivan, K.T. 2017. Using Best-Value Procurement

to Measure the Impact of Initial Risk-Management Capability on Qualitative

Construction Performance. Journal of Management in Engineering 33(5), art. 04017019.

Pirzadeh, P., and Lingard, H. 2017. Understanding the Dynamics of Construction Decision

Making and the Impact on Work Health and Safety. Journal of Management in

Engineering 33(5), art. 05017003.

Rodriguez-Ramos, W.E. and Francis, R.L. 1983. Single Crane Location Optimization. Journal of

Construction Engineering and Management 190(4), p. 387-397.

Rokooei, S., Goedert, J.D., and Najjar, L. 2017. Journal of Professional Issues in Engineering

Education and Practice 143(4), p. 04017003-1-9.

Sadeghpour, Farnaz, and Mohsen Andayesh. 2015. The Constructs of Site Layout Modeling: An

Overview. Canadian Journal of Civil Engineering 42 (3), p. 199-212.

Page 102: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

90

Sadeghpour, Farnaz, Osama Moselhi, and Sabah Alkass. 2004. A CAD-based Model for Site

Planning. Automation in Construction 13 (6), p. 701-15.

Said, H. and El-Rayes, K. 2010. Optimizing Material Logistics Planning in Construction

Projects. Construction Research Congress, ASCE, Banff, Alberta, Canada, p. 1194-1203.

Said, H. and El-Rayes, K. 2012. Optimal Material Logistics Planning in Congested Construction

Sites. Automation in Construction 31 (1), p. 1580-1589.

Shachter, R.D. 1986. Evaluating Influence Diagrams. Operations Research 34 (6), p. 871-882.

Shapira, A. and Elbaz, A. 2014. Tower Crane Cycle Times: Case Study of Remote-Control

versus Cab-Control Operation. Journal of Construction Engineering and Management

140(12), p. 05014010-1 -12.

Smith, A.E., and Coit, D.W. 1997. Handbook of Evolutionary Computation. Institute of Physics

Publishing and Oxford University Press. Bristol, England, U.K

Tatum, C.B. 1993. Structure and Characteristics of Knowledge from Construction Experience.

Stanford University, Technical Report Number 81.

Tommelein, I., and Zouein, P. 1993. Interactive Dynamic Layout Planning. Journal of

Construction Engineering and Management 119 (2), p. 266-287.

Toronto Hydro. 2018. Requesting New or Upgraded Commercial Service.

http://www.torontohydro.com/sites/electricsystem/business/connections/Pages/newlarges

ervice.aspx

Toronto Pearson. 2017. Crane Permit Requests.

https://www.torontopearson.com/en/businesspartners/forms/crane-requests/#

United States Environmental Protection Agency. 2012. Small Business Liability Relief and

Brownfields Revitalization Act. https://www.congress.gov/107/plaws/publ118/PLAW-

107publ118.pdf

Wang, J., Liu, J., Shou, W., Wang, X., Hou, L. 2014. Integrating Building Information

Modelling and Firefly Algorithm to Optimize Tower Crane Layout. 31st International

Symposium on Automation and Robotics in Construction and Mining, Sydney, Australia,

ISARC, p. 321-328.

Wei, Y., Pinheiro, A., Pedraza, D., Wu, B., and McCabe, B. 2015. Vertical Delivery Challenges

for High-Rise Building Construction.

Zhang, P., Harris, F.C., Olomolaiye, P.O., and Holt, G.D. 1999. Location Optimization for a

Group of Tower Cranes. Journal of Construction Engineering and Management 125(2), p.

115-122.

Zolfagharian, S., and J. Irizarry. 2014. Current Trends in Construction Site Layout Planning.

Construction Research Congress 2014, ASCE, Atlanta, GA, USA, p. 1723-1732.

Zouein, P., Harmanani, H., and Hajar, A. 2002. Genetic Algorithm for Solving Site Layout

Problem with Unequal-Size and Constrained Facilities. Journal of Computing in Civil

Engineering 16 (2), p. 143-151.

Page 103: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

91

Appendices

Appendix A: Crane Cycle Equations

Equations from the literature were applied to the lifts to predict cycle times (Huang et al., 2011).

It was noticed that there were great variations between the actual time to perform a lift and the

estimated time for a lift as calculated from equations from the literature as the equations did not

account for environmental or situational factors, such as wind, operator experience, and repair

time.

Equation 3 to Equation 5 calculate the distances of the crane center (Crk) to the object destination

(Dj) and source (Si), and the distance between the object source and destination coordinate,

respectively. Equation 6 calculates the radial movement of the hook, whereas Equation 7

calculates the tangent movement of the hook.

Finally, Equation 8 and Equation 9 calculate the horizontal and vertical movement of the crane,

respectively. Equation 10 adds the results of Equation 8 and Equation 9 with coefficients relating

to simultaneous vertical and horizontal movement of the hook and operator experience to

calculate the total cycle time for a lift. Diagrams showing the horizontal and vertical movements

of a crane can be seen in Figure 22 and Figure 23.

𝜌(𝐷𝐽𝑥, 𝐶𝑟𝑘

𝑥) = √(𝐷𝑗𝑥 − 𝐶𝑟𝑘

𝑥)2 + (𝐷𝑗𝑦

− 𝐶𝑟𝑘𝑦

)2

Equation 3: Distance between Destination (drop-off) Point and Crane Coordinates

𝜌(𝑆𝑖𝑥, 𝐶𝑟𝑘

𝑥) = √(𝑆𝑖𝑥 − 𝐶𝑟𝑘

𝑥)2 + (𝑆𝑖𝑦

− 𝐶𝑟𝑘𝑦

)2

Equation 4: Distance between Source (pick-up) Point and Crane Coordinates

𝐼𝑖,𝑗 = √(𝐷𝑗𝑥 − 𝑆𝑖

𝑥)2

+ (𝐷𝑗𝑦 − 𝑆𝑖

𝑦)

2

Equation 5: Distance between Destination (drop-off) Point and Source (pick-up) Point

𝑇𝑟(𝑖,𝑗)𝑘 =

|𝜌 (𝐷𝑗𝑥,𝐶𝑟𝑘

𝑥) − 𝜌 (𝑆𝑖

𝑥,𝐶𝑟𝑘𝑥

)

𝑉𝑟

Page 104: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

92

Equation 6: Time for Radial Movement of Hook

𝑇𝜔(𝑖,𝑗)𝑘 =

1

𝑉𝜔arccos(

(𝑙𝑖,𝑗)2 − 𝜌(𝐷𝑗𝑥,𝐶𝑟𝑘

𝑥)

2− 𝜌(𝑆𝑖

𝑥,𝐶𝑟𝑘𝑥

)2

2𝜌(𝐷𝑗𝑥,𝐶𝑟𝑘

𝑥)𝜌(𝑆𝑖𝑥,𝐶𝑟𝑘

𝑥)), (0 ≤ arccos(𝜃) ≤ 𝜋)

Equation 7: Time for Tangent Movement of Hook

𝑇ℎ(𝑖,𝑗)𝑘 = max (𝑇𝑟(𝑖,𝑗)

𝑘 , 𝑇𝜔(𝑖,𝑗)𝑘 )+ ∝ min (𝑇𝑟(𝑖,𝑗)

𝑘 , 𝑇𝜔(𝑖,𝑗)𝑘 )

Equation 8: Total Time for Horizontal Movement of Hook

𝑇𝑣(𝑖,𝑗)=

|𝑆𝑗𝑧− 𝐷𝑗

𝑧|𝑉ℎ

Equation 9: Total Time for Vertical Movement of Hook

𝑇𝑖,𝑗𝑘 = 𝛾𝑘 { 𝑚𝑎𝑥 (𝑇ℎ(𝑖,𝑗)

𝑘 , 𝑇𝑣(𝑖,𝑗)) + 𝛽 𝑚𝑖𝑛 (𝑇ℎ(𝑖,𝑗)𝑘 , 𝑇𝑣(𝑖,𝑗)) }

Equation 10: Total Time for Each Lift

Figure 22: Radial and Tangent Movement of Hook

Page 105: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

93

Figure 23: Vertical Movement of Hook

Appendix B: Charts Showing Significance Ratings for Relationships

In Figure 24, Figure 25, Figure 26, and Figure 27 below, significance ratings for all factors from

the two experts are shown.

Page 106: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

94

Figure 24: All Building Factors Significance Ratings

Figure 25: Crane Factor Significance Ratings

Page 107: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

95

Figure 26: Hoist Factor Significance Ratings

Page 108: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

96

Figure 27: Traffic Management and Concrete Pump Factors Significance Ratings

Appendix C: Crane Load Charts

The following figures, from Figure 28 to Figure 40, are load charts from manufacturer’s for

cranes included in the database.

Page 109: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

97

Figure 28: Crane 1 - KNF 336i-16 Load Chart

Figure 29: Crane 2, 3 and 6 - Pecco PC 2000

Page 110: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

98

Figure 30: Crane 4- Peiner SK315Figure 31: Condor FZ 001

Figure 32: Crane 7 - Comedil CTL-250

Page 111: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

99

Figure 33: Crane 8 - AVRO LJK 160

Figure 34: Crane 9 - Pecco PC 1400

Page 112: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

100

Figure 35: Crane 10 - Pecco PC 1200

Figure 36: Crane 11 - Pecco PC 3600

Page 113: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

101

Figure 37: Crane 12 and 16 - Comedil CTT 331

Page 114: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

102

Figure 38: Crane 13 - Peiner SK 415

Page 115: Site Logistics Planning for High Rise Building ... · accommodating my presentation time. Thank you for enabling me to graduate and asking the most interesting questions during my

103

Figure 39: Crane 14 - Pecco Sn 406

Figure 40: Crane 15 - Pecco PC 3000