  • SITE EXPLANATION(MECHANICAL WORK)

    O Mon Thermal Power Plant Unit No.2

  • 1. Project overview

    Description

    Project Name O Mon Thermal Power Plant Unit No.2 Construction Project

    OwnerOwner : EVNGENCO 2

    Consultant : TEPSCO(Tokyo Electric Power Service Company)

    LocationO Mon Disctrict, Cantho City, Vietnam(About 200km away from HCMC)

    Contract period July 1, 2013 ~ Oct. 31, 2015

    Warrant period Warranty Period : 730 days

    Advance payment 10%

    Selecting Subcontractor

    June 15, 2013

    1.1 General

  • 1. Project overview

    1.2 Site location

    150kmCan Tho City 18km

  • 1. Project overview

    1.3 Overall Site photo

    Unit No. 1Power Plant

    Unit No. 2Location

  • 1. Project overview

    850m

    590m

    Cooling Water Piping

    Power Block

    *See the next slide

    Switchyard

    1.4 Overall Plot Plan

  • 1. Project overview

    Power(STG) House

    Main Transformer

    Boiler

    ESP

    CCB

    FGD

    1.5 Plot Plan (Power Block)208m

    85m

  • 1. Project overview

    208m

    1.6 Section View (Power Block)

  • 2. Inquiry package

    2.1 Composition of Inquiry package

  • 2. Inquiry package

    2.2 Letter of Tender

    Subcontractor to input is

    1. Tender cost

    2. Expiry date of the Tender

    3. Signature and address

    4. Subcontractor name and address

    5. Percentage for overhead charges and profit

    6. Initials of signatory of Tender

  • 2. Inquiry package

    2.3 Schedule

    Subcontractor to input is

    1. Bill of Quantities

    2. Daywork Schedule

    3. Break down of Price

    Adjustments to Final Amount of Subcontract Work

  • 2. Inquiry package

    2.3 Schedule

    Price schedule

    1. Unit rate in Bill of Quantity shall include indirect cost and O&P

    2. Total cost from BILL OF QUANTITY(SUMMARY), Break down of

    Price (Summary 1) and Break down of Price (Summary 2) shall

    be same

  • 2. Inquiry package

    2.3 Schedule

    Optional price 3 sets of field erection tank (PKG B)

    Material, pre-fabrication and primer coating

  • 2. Inquiry package

    2.3 Schedule

    Optional price for NDE (Will be included in Addendum for PKG A)

    RT, PT, UT and MT

    Description QtyUnit Rate

    (USD)

    Amount

    (USD)

    RT 7,000 films

    PT 25,000 m

    UT 20 m

    MT 30 m

  • 2. Inquiry package

    2.4 Condition of Subcontract

    Condition of Subcontract is general condition, and referred by Letter of

    Tender

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Content

    1. General

    2. Scope of Works and Measurement

    3. Free-Issue Materials

    4. Technical Specification

    5. Other condition

    Annex

    1. Detail scope of Work

    2. Conceptual Drawing for Definition of Package A and B

    3. Measurement Formula for Piping Works

    4. Preliminary Construction Schedule

    5. Special tools and consumables to be provided by Contractor

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Scope of Works and Measurement

    1. Mechanical work is divided into 2 packages

    2. Package A : Power Block (T/G and BLR, up to GAH outlet)

    3. Package B : Non Power Block (EP, FGD and others, from GAH outlet)

    4. Mechanical work includes piping, equipment installation, painting and

    commissioning assistance

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Piping work

    1. Installation of pipe, fitting, flanges, valves, bolts/nuts, inline

    instruments and other piping components

    2. Installation of support, performing NDE and heat treatment

    3. Flushing, blowing and any other pre-commissioning activities.

    4. Detail scope as per Specification and Annex 1 (In case any conflicts

    arise between Specification and Annex 1, Specification will prevail)

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Equipment erection

    1. Installation of equipment including piping

    2. Delivery condition of pipe, condenser, steam turbine and other

    equipment, if available, is stated in Contractor-furnished data

    3. Erection of procedure based on Unit No. 1, if available, is stated in

    Contractor-furnished data

    4. Preparation, temporary structure and any pre-commissioning activities

    are Subcontractor scope of work

    5. Detail scope as per Specification and Annex 1 (In case any conflicts

    arise between Specification and Annex 1, Specification will prevail)

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Equipment delivery condition

    Piping for Boiler and Steam turbine

    Condenser

    Steam turbine

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Equipment erection procedure for Unit No. 1

    Generator, steam turbine, condenser, steam drum, heater and etc.

    For condenser installation, some tools and consumables as stated in 2.2.5 Special

    tools and consumables to be provided by Contractor will be supplied by

    Contractor

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Preparation for erection of main equipment

    Jack-up system for Generator and Steam drum

    Temporary structure for Generator, steam drum, condenser and etc.

    Temporary rail for turbine, heater, deaerator and etc.

    Note: For transportation of Generator of Unit No. 1, conventional transporter used,

    while SPMT will be used for transportation of Generator and other critical

    equipment. Thus, quantity of temporary steel structure will be reduced.

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Generator Installation

    This rail will not be

    needed

    SPMT

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Route of SPMT for Generator Installation

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Equipment erection

    Adjustments to tonnage of Equipment

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Painting work

    1. Surface preparation, preservation and coating

    2. Painting and blasting material

    3. Color coding, line marking and touch-up

    4. Transportation of Materials/Pipe spools/Equipment from/to painting

    shop

    5. Detail scope as per Specification and Annex 1 (In case any conflicts

    arise between Specification and Annex 1, Specification will prevail)

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Free issue materials

    As per Specification

    Technical Specification

    As per Specification

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Other conditions

    Acquisition of permit by Subcontractor

    Temporary facility and utility for Work by Subcontractor

    (including sufficient number of portable toilets at Site)

    Office area by Contractor

    (Subcontractor shall carry out back-filling, compaction and gravelling if required)

    Shop area by Contractor

    (Subcontractor shall carry out glass cutting, grubbing and moving existing material to

    Contractor designated place)

    Material handling, transportation and storage by Subcontractor

    Preservation of Equipment and material by Subcontractor including periodic manual shaft

    rotation of Rotating equipment.

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Other conditions Location for Subcontractor office and shop

    Shop area

    Shop area

  • 2. Inquiry package

    2.5 Specification (Special condition of Subcontract)

    Construction schedule

    Critical Path (will be included in Addendum) Power receiving: October 1, 2014 Initial Firing: February 15, 2015 Steam Admission: May 23, 2015 Synchronization: June 10, 2015 Take over: October 31, 2015

    Preliminary construction schedule

  • 2. Inquiry package

    2.6 Drawing, Clauses of Contract

    Drawings

    Bid drawings for reference

    Clauses of Contract

    1) General Condition of Contract

    2) Special Condition of Contract

    3) General Technical Provisions

    4) Technical provision for Civil and Architectural works

    5) Technical provision for Turbine generator and Auxiliaries

    6) Technical provision for Boiler and Auxiliaries

    7) Technical provision for FGD system

  • 2. Inquiry package

    2.7 Contractor-Furnished data

    Package A

    1) General inspection requirement with inspection and test plan

    2) Turbine generator and Boiler vendor piping delivery condition

    3) Steam turbine delivery condition

    4) Condenser delivery condition

    5) FDF and GRF delivery condition

    6) GAH delivery condition

    7) Deaerator delivery condition

    8) Turbine generator and Boiler area vendor piping information

    9) Preliminary heavy bulky cargo list for turbine generator and boiler

    10) Boiler air & GR duct division instruction

    11) Boiler erection procedure

    12) Boiler gas duct & structure division instruction

  • 2. Inquiry package

    2.7 Contractor-Furnished data

    Package A

    13) Boiler leaving out steel structure division instruction

    14) Boiler pressure parts division instruction

    15) Boiler steel structure before pressure parts division instruction

    16) Condenser supply division instruction

    17) Erection procedure for Boiler steel structure

    18) Installation procedure for condenser

    19) Opening plan for power house & CCB

    20) Turbine erection procedure

    21) Installation plan for generator, steam drum, heater and etc.

  • 2. Inquiry package

    2.7 Contractor-Furnished data

    Package B

    1) General inspection requirement with inspection and test plan

    2) ESP preliminary packing list

    3) Field fabrication tank reference drawing

    Additional data from Unit No.1 (to be included in Addendum)

    1) Silencer drawing for blowing out piping

    2) Target plate drawing

  • 2. Inquiry package

    2.8 Clarification (will be included in Addendum)