Site and Highway Staking with Trimble SCS900
![Page 2: Site and Highway Staking with Trimble SCS900. Benefits of doing your own stakeout Stakeout has historically been labor intensive –Multiple person crews](https://reader033.vdocuments.site/reader033/viewer/2022051316/56649cd95503460f949a371c/html5/thumbnails/2.jpg)
Benefits of doing your own stakeout
Stakeout has historically been labor intensive– Multiple person crews
Using Trimble technology reduces labor– Allows single person crews for
GPS (SPSx81) Robotic Total Station (SPSx30)
Reduces cost– Reduces need for subcontracted layout
Reduces downtime– No need to schedule or wait for crews to arrive
Puts the power of data in your hands– Documentation of stake positions and accuracy
![Page 3: Site and Highway Staking with Trimble SCS900. Benefits of doing your own stakeout Stakeout has historically been labor intensive –Multiple person crews](https://reader033.vdocuments.site/reader033/viewer/2022051316/56649cd95503460f949a371c/html5/thumbnails/3.jpg)
SCS900 Stakeout Menu
Option 3 – Stakeout Menu Different menu depending on design loaded– Surface design (TTM)– Road design (PRO)
Stakeout Settings
![Page 4: Site and Highway Staking with Trimble SCS900. Benefits of doing your own stakeout Stakeout has historically been labor intensive –Multiple person crews](https://reader033.vdocuments.site/reader033/viewer/2022051316/56649cd95503460f949a371c/html5/thumbnails/4.jpg)
Staking Points
Stake to coordinates (NEZ)– Structures, utilities, radii,
corners
Picking Options– Pick from plan view– Pick from list– Create new
![Page 5: Site and Highway Staking with Trimble SCS900. Benefits of doing your own stakeout Stakeout has historically been labor intensive –Multiple person crews](https://reader033.vdocuments.site/reader033/viewer/2022051316/56649cd95503460f949a371c/html5/thumbnails/5.jpg)
Staking Lines
Stake EP, curb, pads, lots, utilities, contours Picking Options– Pick from plan view– Create New
Other Options– Reverse– Station / offset– Tangent / corner points– Staking Interval
Trimble Menu
![Page 6: Site and Highway Staking with Trimble SCS900. Benefits of doing your own stakeout Stakeout has historically been labor intensive –Multiple person crews](https://reader033.vdocuments.site/reader033/viewer/2022051316/56649cd95503460f949a371c/html5/thumbnails/6.jpg)
Staking Side Slopes & Catch Points
Project any line at any slope Dynamic daylight / catch points– Intersection updated using current ground
elevation– Useful when model doesn’t daylight correctly,
slopes are not complete, or slopes need to be modified
![Page 7: Site and Highway Staking with Trimble SCS900. Benefits of doing your own stakeout Stakeout has historically been labor intensive –Multiple person crews](https://reader033.vdocuments.site/reader033/viewer/2022051316/56649cd95503460f949a371c/html5/thumbnails/7.jpg)
Staking Planes
Simple slopes or pads– Good for temporary work that is not in design
3 Types– Level Plane– Sloping Plane– Three Point Plane
![Page 8: Site and Highway Staking with Trimble SCS900. Benefits of doing your own stakeout Stakeout has historically been labor intensive –Multiple person crews](https://reader033.vdocuments.site/reader033/viewer/2022051316/56649cd95503460f949a371c/html5/thumbnails/8.jpg)
Staking Surfaces
Live Cut / Fill to current design Good for supervisors or inexperienced users
![Page 9: Site and Highway Staking with Trimble SCS900. Benefits of doing your own stakeout Stakeout has historically been labor intensive –Multiple person crews](https://reader033.vdocuments.site/reader033/viewer/2022051316/56649cd95503460f949a371c/html5/thumbnails/9.jpg)
Staking Roads – Option 1
Roadway Feature– Pavement
CL, EP, Curb, Shoulder
– Dirt SG, Ditches, Benches
![Page 10: Site and Highway Staking with Trimble SCS900. Benefits of doing your own stakeout Stakeout has historically been labor intensive –Multiple person crews](https://reader033.vdocuments.site/reader033/viewer/2022051316/56649cd95503460f949a371c/html5/thumbnails/10.jpg)
Staking Roads – Option 2
Catch Point– Stake design tie slopes– Stake user defined slopes
![Page 11: Site and Highway Staking with Trimble SCS900. Benefits of doing your own stakeout Stakeout has historically been labor intensive –Multiple person crews](https://reader033.vdocuments.site/reader033/viewer/2022051316/56649cd95503460f949a371c/html5/thumbnails/11.jpg)
Staking Roads – Option 3
Location on Surface– Cut / Fill on the road at
Specific Station / Offset Any random location
![Page 12: Site and Highway Staking with Trimble SCS900. Benefits of doing your own stakeout Stakeout has historically been labor intensive –Multiple person crews](https://reader033.vdocuments.site/reader033/viewer/2022051316/56649cd95503460f949a371c/html5/thumbnails/12.jpg)
Report Utility
What data is recorded during stakeout?– Measured NEZ– Raw data (LLH or HA/VA/SD)– Precision – Design NEZ– Cut / Fill– Horizontal deviation from staked point– Station / Offset (lines or roads)– In / Out of tolerance– Rod height– Date and time