sip report amiruzaki 13517.pdf

45
STUDENT INDUSTRIAL TRAINING PROJECT REPORT Application Engineering Flow and Return to Stock Process SEPTEMBER 2013 DISEMBER 2013 Cohu Semiconductor Equipment Group Mohamad Amiruzaki Sanip 13517

Upload: hakeym-larh

Post on 04-Oct-2015

54 views

Category:

Documents


2 download

TRANSCRIPT

  • STUDENT INDUSTRIAL

    TRAINING PROJECT

    REPORT

    Application Engineering Flow and

    Return to Stock Process

    SEPTEMBER 2013 DISEMBER 2013

    Cohu Semiconductor Equipment Group

    Mohamad Amiruzaki Sanip

    13517

  • Mechanical Engineering

  • ACKNOWLEDGEMENTS

    In completion of this Industrial Project for four (4) months, I would like to express

    my deepest gratitude to all parties that involve in making my internship program very

    interesting and meaningful. Throughout the internship period, I have learned a lot of

    new things and gain many experiences that will be valuable for my future career

    path.

    First and foremost, I would like to thank UTPs Centre for Student Internship,

    Mobility and Adjunct Lectureship (CSIMAL) for helping me in seeking the best

    placement for my industrial training program.

    I would also like to express my gratitude following person for their profesionalism

    and contributing to the program

    Mr Cheng Kian Aik, Mechanical Design Team Leader (Host Company

    Supervisor)

    Dr Suhaimi B Hasan (UTP Supervisor)

    Miss Mei Ling (HR department)

    All staff in Ismeca Malaysia Sdn Bhd

    Last but not least, thanks to my family and friends for their support and

    encouragement throughout this internship. I really hope that I could apply all of the

    skills and knowledge that I have gained during my internship for my future career.

  • TABLE OF CONTENTS

    HOST COMPANY VERIFICATION STATEMENT .............................................

    ACKNOWLEDGEMENT ........................................................................................ #

    LIST OF FIGURES .................................................................................................. #

    LIST OF TABLES .................................................................................................... #

    INDUSTRIAL PROJECT REPORT ...................................................................... #

    CHAPTER 1 :ABSTRACT AND INTRODUCTION ............................................ #

    SECTION 1.1:OBJECTIVES .......................................................................................... #

    SECTION 1.2 SCOPE OF STUDY ................................................................................... #

    SECTION 1.3 PROBLEM STATEMENT ........................................................................... #

    SECTION 1.4 THE RELEVANCY OF THE PROJECT ......................................................... #

    CHAPTER 2 : BACKGROUND AND LITERATURE REVIEW ........................ #

    SECTION 2.1 FEASIBILITY OF THE PROJECT WITHIN SCOPE OF TIME ............................ #

    SECTION 2.2 CRITICAL ANALYSIS LITERATURE & CITATION & CROSS REFERENCE ..... #

    Subsection 2.2.a. Toyota Production System ........................................................ #

    Subsection 2.2.b Identify 7Muda(Waste) ........................................................... # Subsection 2.2.c Lean Manufacturing .................................................................. #

    Subsection 2.2.c Excess Part Management .......................................................... #

    SECTION 2.3 RELEVANCY AND RECENTNESS OF LITERATURE ..................................... #

    CHAPTER 3 : METHODOLOGY ........................................................................... #

    SECTION 3.1 RESEARCH METHODOLOGY ................................................................... #

    Subsection 3.1.a Project Activity .......................................................................... #

    SECTION 3.2 KEY MILESTONE ................................................................................... #

    SECTION 3.3 GANTT CHART ....................................................................................... #

    SECTION 3.4 TOOLS REQUIRED .................................................................................. #

    CHAPTER 4 : RESULTS AND DISCUSSION ...................................................... #

    SECTION 4.1 FINDINGS ............................................................................................... #

    SECTION 4.2 DATA GATHERING ................................................................................. #

    Subsection 4.2.a. Percentage of Items VS Project................................................ #

    Subsection 4.2.b Percentage of RTS VS Module .................................................. #

    Subsection 4.2.c Project VS Bulk items ................................................................. #

    Subsection 4.2.d Number of parts VS Time taken ................................................. #

    SECTION 4.3 PROJECT DELIVERABLES. ..................................................................... #

  • CHAPTER 5 : CONCLUSION AND RECOMMENDATIONS ........................... #

    SECTION 5.1 IMPACT .................................................................................................. #

    SECTION 5.2 RELEVANCY TO THE OBJECTIVES .......................................................... #

    SECTION 5.3 SUGGESTED FUTURE WORK FOR EXPANSION AND CONTINUATION ......... #

    Subsection 5.3.a. Drawings .................................................................................. #

    Subsection 5.3.b Radio Frequency Identification(RFID) ..................................... #

    REFERENCES .......................................................................................................... #

  • Introduction and Abstract

    Manufacturing is one of the branches of engineering that involves the process

    of making goods from raw materials like metal and copper into useful products that

    can be used to ease our everydays life. Some countries like China uses manufacturing

    as their main economic activity which helps their economic to grow rapidly. As a

    result, nowadays, China is the famous country for manufacturing and most of the

    products used by us are made in china.

    Since the basic principles of manufacturing engineering are applied in all

    industries, they work in numerous sectors including food and drink, oil, plastics, and

    pharmaceuticals. Big companies play the role during the industrial revolution, where

    the manufacturing sector becomes essential in all countries. Toyota motors is one of

    them. Toyota has practiced so called Toyota Production System. It introduces the

    management philosophy about organizing manufacturing and logistics for the

    automobile manufacture. One of its key principles is 7 'Muda',the Japanese term used

    by Toyota to signify a non-value adding process or waste.

    Figure 1.0- 7 wastes by Toyota Production System

  • Cohu Semiconductor Equipment Group (COHUSEG) is also one of the manufacturer

    which contributes to the economic growth in Malaysia. COHUSEG also facing the

    problem with the several waste that stated in the Figure 1.0. Over production,

    Inventory and Rework is kind of the waste that COHUSEG encounter. All these

    problem can be seen during the Return to Stock process.

    Returning to Stock process is important for the company because if the parts are not

    properly returned to the warehouse, it would be disposed and it will cost a big lost for

    the company which is not beneficial. Other than that if the process is not carried out

    properly, for example wrong part numbers for the parts, it would result in the

    dissatisfaction of customers. It is because, when the part number put by the respective

    engineers is wrong, the parts would be put into the wrong storage. In future, when the

    customer order the parts for their project, the person in charge would take out wrong

    part from the wrong storage. Thus, it would cause a big problem for the future projects.

    In conclusion, this project is about how we can improve the Return to Stock process

    so that it would be more efficient in terms of saving cost, time and its effectiveness.

    Other than that, in this project, it also would analyse the engineering flow which means

    the process started after the customer made and order until the product or the machine

    is tested before it being sent to the customers.

  • 1.5.9.1 Objectives

    SIP Objectives

    Purpose of the Student Industrial Project (SIP) is to expose students to the real working

    environment so that they can relate theoretical knowledge with application in the

    industry. SIP also let the students to develop their skills in safety environment, work

    ethics and communication management. SIP will provide opportunity to UTPs

    students to build solid understanding of the fundamentals of business and organization

    performance such as economic models of business, competitive positioning and

    strategy execution. With this real life experience, students can develop their ability in

    assessing performance, interpreting trends, exploring the sequences of change and

    making better decisions. Briefly students should be able to:

    I) Investigate theoretical knowledge in industry

    II) Analyse complex engineering/technical projects in industry

    III) Evaluate and propose solution for given complex project or problem

    IV) Communicate effectively on complex engineering /technical activities

    Project Objectives

    Based on the objectives of the Student Industrial Project (SIP), the best project is the

    project that can fulfil the objective of SIP project regarding Engineering Flow and the

    process of Return to Stock which is part of the engineering flow. The current process

    of Return to Stock might time consuming especially when it is gave to the Engineering

    department since the process to find the part number is time consuming. Thus it is best

    if that process can be improved so that the process would be well-organized. Thus, to

    sum up at the end of the project, student should be able to:

    i) Analyse the engineering flow from the order until the machine is sent to

    customer relate it with Toyota Production System and Lean manufacturing.

    ii) Define Return to Stock (RTS) and importance of it to the engineering flow.

    iii) Analyse the current process flow of the current RTS and state the

    advantages and disadvantages of the flow.

  • iv) Propose the solution to improve the RTS process so that it becomes more

    easier, save time and efficient

    v) Reflect the relevancy of the new solution to the current engineering world.

    1.1.5.9.2. Scope of study

    Scope for the projects refers to the boundary or limits within which the study needs to

    be kept. It is essential for the study to keep the projects stay in focus and exhausive.

    So, for the projects , basically the students were asked to analyse the application of

    enginnering flow. So that the students understand and learn something from the

    process of product making. Students should suggest some improvement to the

    engineering flow. Basically, engineering flow start with the order from the customer

    who intrested in the product. Then they would present what kind of semiconductor that

    they created with the detailed specification of what kind of turret-based testing

    machine that they want. Then Centre of Excellence (COE) of mechanical would make

    the layout to pass to the Hardware ,vision and T & C can start work after machine

    layout was complete. Then they would make the Bill of Materials (BOM) which list

    all parts needed for the project. The process would undergone several other process

    and then before it is send to the customer the project would be fine tune by us so that

    it really meets customers specification.

    After the products were completed and being tested for its capability, the excess spare

    parts would be collected in a box according to the projects. All these excess spare parts

    either need to be scrapped because the part was specially design for that particular

    project or need to be return to the stock. Others would be listed according to part

    number and bill of material before the list being analyse by the other department. All

    these processes were referred as Return to Stock (RTS) process. The students were

    required to ensure that the process of RTS is improved with the new method that is

    more time saving. The students also should consider either the method is practical for

    every department or not.

  • 1.5.9.3 Problem Statement

    Return to Stock (RTS) plays important role in the application flow at ISMECA

    Semiconductor. It determines how much the loss that need to be recoup by the

    company. The more excess parts in the project the more loss we need to recoup.

    Therefore, RTS should be taken seriously so that we can analyse carefully the reasons

    of the parts return to be avoided in the future. Besides, we should ensure the part is

    return to the right place with the right part number as it is important if the parts are

    needed to be reuse for the next time. Following figures was the current brief RTS flow

    that practiced by ISMECA.

    As an engineer, it is important for the student to look at any process positively and

    negatively. So that, the student can improve any negative sides of the process to

    become positive element and maximise the positive side of the process so that it would

    become more reliable and effective. The advantage of this process, it separate between

    Start

    Gather all parts in a box

    Identify the part that need to scrap

    Record all the part that already has part number

    Find the missing part number in SAP or BOM list

    Record the new part in the RTS List.

    Attach the list with the box

    Send to the Person in Charge of Warehouse

    End

    Figure 1.3- Process

    flow of RTS

    according to the

    student

  • the usable part and unusable part. Not all the excess part can be reuse or resell to the

    customer because some of them are custom made for only certain project. Once the

    project is completed, means the unusable parts become completely useless. Besides,

    in the process flow the spare parts was completely taken care of. This is to ensure that

    the spare parts free from cosmetic and labelling defect. Thus the part would be as good

    as new spare part when it is brought out back to be reuse or resell.

    However the disadvantages of the process of the flow is the real problem. One of the

    disadvantages is, the part that without the part number. In the process, we just need to

    find the part in the BOM list or SAP which contains thousands of parts. Thus,

    sometimes, the engineer faces a problem like where to find the product number for this

    part. Based on the students opinion, this is the most time consuming process in RTS

    because the process is really complicated. The student needs to open the drawing,

    module by module, part by part, which sometimes take about a day or two.

    Besides, the other disadvantages of the flow is the number of spare parts high or too

    many. According to the students supervisor, a great RTS is when RTS with less parts

    in it. Thus we need to add some new process in the RTS so that it would lessen the

    number of spare parts in the box.

    Last but not least, the problem can be seen in current RTS is sometimes the part from

    the other project was thrown in a box. This result in when we key in the part number,

    the BOM or SAP shown that the part is not belong to that particular project. This

    problem can be taken by ensure the Standard Operating Procedure (SOP) of the RTS

    was followed after any project or machine has been shipped.

  • 1.5.9.4 Relevancy of the project

    This project would help the manufacturing company especially the company that tried

    to improve on their inventory management system which facing similar problem with

    ISMECA Semiconductor. Since nowadays technology keep on improving thus many

    new manufacturers company start their operation. Thus this excess spare part

    management is important for them to know or to do proper ways to recycle the spare

    parts not just blindly scrap them which might cause big loss to the company.

  • Background and Literature Review

    Feasibility of the Project within Scope and Time frame

    This project is considered feasible to the project within the scope of the

    study because most of the information for the project is kept inside the company. Thus

    the student just needs to think about the great solution that can solve the problem.

    The project also can be said feasible in term of the time frame since the

    time given to complete the project is more than enough. The project has been suggested

    to the student during the second month of Industrial Training (IBB 3037). Thus it gives

    the student a lot of time to think about the title though the problem statement has been

    given during first day of Industrial Project (IBB 3047). In conclusion, the time frame

    given should be sufficient to complete the whole project.

    Critical Literature Review,Citation andCross-Referencing

    Toyota Production System

    Toyota Production System (TPS) is perhaps the most publicized collection of visual

    systems. According to the Khanna and Shankar (2008), ideas of TPS generated by Mr

    Kicchiro Toyota, founder of Toyota Automotive Industries and his staff , Mr Taichi

    Ohno based on the showcase and the automatic machine invented my Mr. Sakichi

    Toyoda, automatically stops functioning when the thread on the machine happens to

    be cut off. Braiden and Herron (2007) claimed that reasonable response about what is

    the goal regarding manufacturing proposed by Taiichi Ohno All we are doing is

    looking at the time from the moment the customer gives us an order to the point where

    we collect the cash. And reducing the time line by removing the non-value-added-

    wastes. This response means that the manufacturing company should know the most

    important objective is the input where customer placed order and the output where we

    collect the cash. Other process which not added any value to the product considered as

    waste.

  • It is important for any company who practices TPS to understand how to identify

    waste, so that it can be eliminated. After the waste has been eliminated, the output will

    help to increase profitability in manufacturing and distribution business. Hubbard

    (2010) stated that a process adds value by producing goods or providing a service will

    pay for. Thus any other process which the customer would not pay for it consider a

    waste. When the great Italian sculptor Michelangelowas asked what he was sculpting,

    he responded he was not sculpting but releasing the figure (value) inside by removing

    the unnecessary rocks (wastes). Like Michelangelo, we should

    eliminate all forms of wastes in any process or product until only what is valuable

    remains. The key is to spot waste and then stop the waste.

    Toyota Production System (TPS) key concepts consists of three Japanese words with

    prefix mu- which every Japanese know, as product improvement program or

    campaign. The first one was called Muri which means overload or overburden and

    the second one was Mura means unevenness. Muri refers more specifically to

    overloading an equipment, facility or human resource beyond it capacity. This undue

    stress may cause downtime, defects, delays and even disasters to the company. An

    operator or a machine load is over capacity might harm them. Working for 110 % for

    an operator or a machine or a firm is truly heavy. The operator would get sick while

    the machine would get broken after a while. With this sick operator or broken down

    machine, it would make the production become slower unless the machine is fix or the

    operator becomes healthy. Mura refers to unevenness in production volume which is

    the extreme difference highs (peaks) and low (valleys) in production schedule. For

    example a workload for Monday is 8 hours while the workload on Tuesday is 16 hours.

    This inconsistency causes the cause periods of overload and long idle time. It is a must

    to prevent Mura and Muri completely in order to eliminate the next waste which is

    Muda.

  • Identify 7 Muda(Waste)

    Muda () is a Japanese term for an activity that is does not add any value or is

    unproductive or un-useful(). Once the Mura and Muri have been sorted out, it will

    be time to identify Muda in all the operations, material usage and defects. It is

    important to keep in mind that anything that does not add value is Muda or Waste.

    Muda consist of 7 waste which are overproduction, waiting-time, conveyance or

    transport, processing, inventory, motion and correction or rework. Overproduction

    happens when customer produces more than their needs. For example the customer

    order only 3 parts but the operator made 10 parts with hope that the part can be usde

    for the other machine. Overproduction was the worst waste because it would cause

    the other waste to happen. The next waste is called defects or errors. It means any

    activity that causes the product to rework, unnecessary adjustments or returns. Bad

    quality or defects does not only result in customer dissatisfactionand damage to

    company image, but also in wastes due to additional costs and time to recall, rework,

    repair, and replace the defective items. The rest of the other waste was shown in the

    next figure.

  • Figure 2.2.b Examples of Several Waste in a picture

    1. Muda of waiting: a waiting employee does not create added value.

    2. Muda of transport: products transported from one place to another in the plant do

    not create any added value.

    3. Muda of inventory: capital unnecessarily tied up, value destroyed.

    4. Muda of processing: stress of the work.

    5. Muda of motion: no value is created during motion.

  • Lean Manufacturing

    Henry Ford comes out with the concept of lean manufacturing which helps to eliminate

    most of the waste. Lean manufacturing is define by Abu Shaaban (2012) as ssa

    philosophy based on the Toyota production system to shorten the time line between

    customer order and shipment of final product by elimination of waste. Other definition

    was made by Liker (2004) who defined lean manufacturing as process which adding

    value to eliminating waste which responsive to the change, focus on the quality, and

    enhancing the effectiveness of work force. Trying to Imagine, a factory which only

    produces only enough materials to produce just that which has no excess inventories,

    no scrap, non-value added functions. All orders are shipped on time to the customer.

    Such are the desired outcome of lean manufacturing. One of the important steps to

    implement lean manufacturing is Just-In-Time (JIT) concept. Monden (1998) and

    Levy (1997) are both agree that JIT production is the back bone of the lean

    manufacturing. JIT is defined as producing and/or delivering only the necessary parts,

    within the necessary time in the necessary quantity using minimum resources.

    Therefore, no need for inventory since the appropriate number of parts are produced

    and shipped immediately when the customer order is received. However, it is

    impossible in practical sense, thus the key to the efficiency to this system is by

    decreasing the quantity in the system.

    Cohu SEG also practiced the lean manufacturing system. This system is appropriate

    to be used in the company since one machine costs around half million. Thus if the

    company used the old traditional mass production system, it would cost millions of

    loss. That is why the company uses the lean manufacturing system. Initially, the

    company would receive an order from the customers which is from the manufacturing

    semiconductor company. Then the customers would specify about the machine that

    they want with the engineer of the company. If the engineer has a problem with the

    specification from the customer, they will discuss the problem together until both sides

    are satisfied. Then Centre of Excelence (COE) mechanical would create a machine

    layout and pass to other department (Hardware and Vision). After that, Bill of Material

    (BOM) would be created after technical drawing and schematic drawing has been

  • drawn. COE mechanical would validate mechanical BOM to prevent any missing or

    additional part creation before the parts can be fabricated by respective manufacturer.

    After the parts are created, the machine would be assembly by the fine tuner. After the

    machine is completed and shipped, all the excess spare part would be collected in a

    box to undergo return to stock process.

    Excess spare part Management

    Excess parts Management start after the project or machine has been completed and

    shipped to the customers. It is comprised in the inventory management. Inventory

    according to Investopedia refer to the raw materials, work-in-process goods and

    completely finished goods that are categorized to be partial of businesss assets that

    are ready or will be ready for sale. It is the most important assets that most business

    possess, because the turnover of inventory represents one of the primary sources of

    revenue generation and subsequent earnings for the companys shareholders. In this

    project, inventory refers to completely finish goods. Jianfeng,Jingying and Xiaodong

    (2011) stated that effective inventory management of spare parts is important for

    support maintenance operations and protect against failures. For example if a machine

    is broken and needed to be replace some of the parts , the fine tuner for the machine

    could easily request it from the inventories.

    However, having these inventories left idle in the warehouse would cost the company

    large amount of money. It is because the greater amount of parts in inventories the

    larger space needed to store them. The space that is used to store them considered a

    waste since the parts does not add value. Besides the space can be used for other

    activities which more profitable like adding the space for assembly process.

    Furthermore, the inventories need maintenance so that they stay valuable and does not

    broken. For example, the metals in the inventories need to be avoided from water and

    air to prevent oxidation which would cause the metals to rust. Rusting would cost the

    metals lost in value which is a loss to the company. MPWANYA (2005) stated that

    having these inventories on hand can cost around 20 to 40 percent of their actual value

    every year. He added that for some company that have poor inventory management

    can seriously damage the business

  • Relevancy and the recentness of the literature

    Most of the literature taken was about not less than 10 years. Thus it is still relevant

    to the the world of manufacturing. Furthermore, the lean manufacturing is a long-

    term discussion started after Mr Kicchiro Toyoda, the founder of Toyota introduce

    Toyota Production System in Japanese and influence to the whole Asia. At the same

    time, Henry Ford introduce lean manufacturing that influences the whole West

    countries. The literature used in the literature review mostly a paper explaining about

    the TPS and lean manufacturing in modern view. Thus it is still relevance to apply in

    this new era.

    Methodology

    Research Methodology

    Identify the research problem

    Extensive literature review on the problem

    Collecting the data

    Analysis and interpretation of Data

    Design the solution for the problem

    Discussion and Conclusion

    Figure 3.1- Process

    flow of Research

    Methodology

  • Project Activities

    Identify the research problem

    Research problem that chosen for the project is on how to improve on Return to Stock.

    Return to Stock is one of the process in the excess part management. After the product

    is completed and all the parts were collected in the box, the engineer and fine tuner

    will work together in order to find the part number of all the parts in the box. Without

    the part number, the warehouse would face a problem in placing the right parts at the

    right place. In order to find the part number, engineer should revise the overall drawing

    of the project. After they found the similar part, the engineer should double check the

    part with the dimension to ensure that the parts number and its revision are correct.

    Other than finding the part number, the engineer in charge also should determine why

    the products is return. There are several reasons why the product is return:

    i) Purchase Order cancellation The customer cancel the project

    ii) Customer Request Change the customer want to change the part for their

    machine with the other part

    iii) Engineering Change design change by engineering /wrong revision

    iv) Wrong Order the part is not found in BOM thus it is not belong to the project

    v) Bulk item screw , nuts , pins , washer and fitting

    vi) Canevas item Additional items that the customer does not want.

    Supervisor of the author found out that this process takes a lot of time. Thus the author

    needs to improve the process or suggest new process, so that RTS can be done in a

    short amount of time.

    Extensive literature review on the problem

    Literature review is important in any research in order to compare the problem with

    the common problem faced by other manufacturing company. For this project, the

    author found out the similar problem about taking too many time in the process that

    does not add any value or known as muda or waste. The author compared the project

    between Toyota Production System. The solution to eliminate the waste is by practiced

    lean manufacturing. The author did some cross referencing so that the information is

  • more reliable. Literature review also important to ensure that the problem is relevance

    to nowadays world.

    Collecting the data

    Data Collection involves checking or logging the data in; checking the data for

    accuracy; entering the data into the computer; transforming the data; and developing

    and documenting a database structure that integrates the various measures. In this

    study, data is gathered from observation and recorded data that had been done earlier.

    Observation data is done by analysing the return product sample given to the author

    by the operator. Data also had been collected by the author using the RTS product list

    for every project.

    Analysis and interpretation of Data

    Data gathered consist of

    - Project number

    - Product description with quantity

    - Product module

    Several graph are generated from the data collected. The data will be analyse from the

    graph to suggest the suitable solution.

    Design the solution for the problem

    Several solutions would be suggested. The flow for the solution would be drawn so

    that it is more understandable. The advantages and disadvantages for each solution

    would be determine. The best solution would be chosen for the conclusion.

    Discussion and Conclusion

    The best solution will be explained and the author would verify why the solution is

    given. The solution also would be reflected to the objective of the project and would

    be define the relevancy solution to the company.

  • Key Milestone

    Figure 3.2-Key

    Milestone

  • Gantt chart G

    antt C

    ha

    rt

    Descrip

    tion o

    f pla

    nnin

    g

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    21

    22

    23

    24

    25

    26

    27

    28

    Pro

    po

    sed p

    roje

    ct topic

    Pro

    ject to

    pic

    confirm

    atio

    n

    Identify

    pro

    ble

    m

    Co

    llectin

    g d

    ata

    Dra

    fting

    repo

    rt

    Discu

    ssion o

    f pro

    ble

    ms

    enco

    unte

    r

    Asse

    ssment a

    nd

    corre

    ction o

    n d

    raft

    Discu

    ssion w

    ith

    superv

    isor

    Ana

    lyze

    the d

    ata

    Resu

    lt and fin

    al

    findin

    gs

    pro

    po

    sed a

    solu

    tion

    Fin

    al re

    po

    rt

    pre

    pa

    ratio

    n

    Subm

    ission o

    f fina

    l

    repo

    rt to su

    perv

    isor

    Subm

    ission o

    f fi na

    l

    repo

    rt to U

    TP

    superv

    isor

    Perio

    d p

    lannin

    g (W

    eek

    ly)

    Table 3.3.- Gantt chart

  • Tools required

    Hardware

    - Portable Laptop To write the Student Industrial Project Report

    - Pendrive To transfer RTS data from office.

    - Personal Computer To key in parts in RTS and compare the drawing with

    the part.

    - Stationaries- Pencil to write draft of report and long ruler to measure the long

    parts that cannot be measured by using vernier caliper

    - Measuring tools electronic vernier caliper to measure the parts accurately to

    ensure the parts is the same with the drawings in server

    Software

    - System, Application, Product (SAP) system to retrieve the Bill of Materials

    (BOM) and compare with the order by customers

    - Excel to key in the part number to RTS list ; to create Gantt chart, Key

    milestone and graph to analyse data from RTS list.

    - Word To write the Student Indsutrial Project Report.

    - Gmail To communicate with other colleques regarding the project.

  • Result and Discussion

    Findings

  • For the graph 2.1-2.3, author analyse which module are the most returnable for

    3 random project. As a result for Project 1 (Graph 2.1), total parts available was 389

    with the number of parts return are 20. This gave the percentage of 5% . In this 5% of

    return product, 35% of it are from Platform module, 30% are from Feeding module,

    10% are from Orientator module, 10% are from Taping module and the balance 15%

    are from Table module.

    With 365 total parts invovled in Project 2 (Graph 2.2), 26 parts or 7%

    of it were return to stock. 42% of the return parts in this Project are from Platform

    module, 30% are from Adaptation module, 19% are from Tapping module, and 4%

    are from Maintenance, Table and Feeding module.

    During Project 3 (Graph2.3), total parts that had been returned were 43

    parts from 556 parts that give the percentage up to 8%. Platform module produce the

    highest returned parts with 44% followed by Tapping module with 33%. For

    Adaptation module, Table module, and Test module they covered 5% of the returned

    parts each. Vision module with 7% and the lowest are from Maintenance module with

    only 2%.

    0

    5

    10

    15

    20

    25

    2

    22

    14

    0 0 02

    0 0 0

    Project 3

    Value

  • Data analysis

    From the Figure XX , the project with highest percentage of return parts or items was

    Project 3 with 15.63% of total items in the project. The lowest percentage was from

    project 7 with 1.94% of total items. For the high percentage, it might because of poor

    management of the project or the return parts might mainly made up of canevas or

    bulk items. In the other hand for the project with the low number of items can be said

    well handed project.

    However, from the graph we can see the different project has different number of

    parts. The graph does not show any pattern that we can forecast for the next project.

    This due to various manipulated variable or reasons which cause the quantity of parts

    in a project high or low. The reasons are wrong bookings ,engineering related ,

    canevas item , bulk item , request from project manager, typing error of project

    manager, the item is not belong to the project , and the parts are belong to supplier.

    Reflecting the objective of the project,we should reduce all these errors in order to

    lessen the quantity of RTS in future. Techniques of reduce the errors would be

    discussed on the next section.

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    20

    5.14

    7.2

    15.68

    7.2

    2.5 2.5 1.943.19 2.84

    7.9

    Project VS Percentage of Return Item

    Percentage

  • For the total 10 projects that had been analyzed, 3673 parts were involved with 196

    parts were submitted to the engineer to be store at the warehouse. This shows that for

    10 projects that haad been done, 5.34% of the parts were returned to the stock.Though

    the percentage is around 5% which looks like it is not significance , each of the parts

    that return has high value. Assume that one part has a price around RM 3 , with 196

    parts the price for the total parts return are RM 588. Moreover , note that , the price of

    part is various from one to another. One might have really high value and another one

    might be really cheap. According to last year report , averangely the total price for

    return parts for one project is around RM 300 to RM 400. This shown that the return

    parts was somehow a loss or a waste to the company if it was not properly manage.

    From this 5.34% returned parts, Platform module gave the highest percentage

    with 42.86% of the returned parts are from this module. Following is Adaptation

    module with the percentage of 14.80% and Tapping module 13.78%. All these three

    modules are the critical modules as they are the highest of three by producing return

    parts.From 10 projects that were done, some of the module gave the same percentages.

    Table module and Test module both have the same percentage which each module

    represent 6.12% of the total returned parts, same goes with Equipment module and

  • Orientator module which also showing the same percentage of 2.04%. Feeding module

    produce 7.14% of the total 5.34% of the returned parts while Vision module produce

    4.59% from the total parts. Maintenance module is the lowest percentage from all 10

    modules that had been analyzes with only 1.02% of product returns.

    Altough most of the parts come from Platform module , we can not simply blame the

    person in charge for the module. Platform was the big module which consists of many

    simple module like Support for PC , Turret or Frame mounted. Platform is the module

    which consist the largest number of parts in every module. Other than that , Platform

    basically the frame for the other module and it is not assemble by the company. Some

    parts like wheel and the stand which commonly return back to the stock because it

    might be too old. For the other module , some of the part might need change because

    of not fit to the module or need engineering change or the customer himself would like

    the part to be change. As a conclusion , the engineer should take note on which kind

    of module have the highest amount to be given extra attention when doing the order to

    avoid excess parts on that module again.

  • Graph 1.1 showed the bulk and normal parts that are submitted to the engineer

    to be stored at the warehouse for every project. As referred to the graph, the author

    determined that the bulk parts made up around 9 to 65% of the return items. This shows

    only 20% of the total project have a bulk parts more than normal parts to be sent for

    Return to Stock.

    The bulk parts consist of fittings, screw, nuts and other small parts of the

    component. Mostly, the bulk parts can be reused for other projects. This make keeping

    the bulk parts in the warehouse are not economic. Other than that, by reused the bulk

    parts, the warehouse space can be reduced. The cost to upgrade the warehouse as the

    storage of items or part keep increased day by day can also be cut as the minimal usage

    of bulk parts space.

    From the data analysis, ISMECA Semiconductor can reused about 20% to 30%

    of the parts that are submitted to the engineer to be store at the warehouse. By reused

    this items, ISMECA semiconductor can reduce the cost of buying new parts. It also

    can reduce the production time as if they buy a new sets of parts, they need to order it

    50%

    65%

    44%

    19%

    45%

    9%

    57%

    22%25%

    32%

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    1 2 3 4 5 6 7 8 9 10

    Par

    t/It

    em

    Nu

    mb

    ers

    Project

    Total Parts

    Bulk Items

    Bulk Item Percentage

  • and wait for several days before the parts deliver at production line. Different with

    reused, the parts can be used on the spot as the parts are already on the production line.

    Therefore, in the author point of view, this type of return should be stored at a section

    which contains whole set of bulk items to be use. Further clarification about the storage

    of bulk items would be explained at the next section.

  • Graph show that the number of parts versus time taken to complete the listing of

    RTS. The more items in the RTS, the more time taken to complete listing the parts in

    the RTS list. For Project 4 and 5, we can see that though the items in the project is

    many but the author can finish listing the parts with short amount of time. This is due

    to most of the parts already has their part number attached at the package or written

    on the part with the tape. Thats why the author only need to key in the number

    which save a lot of time.

    This graph conclude that the loss of the part number consume lots of time for the

    author to complete his job. When the author receive a box with a part which did not

    have part number, the author needs to go through the drawing by module one by one.

    Some of the drawing of module has too many parts which made the user to disable

    some of parts visibility in order to see the inside parts. After the author found the

    similar part in the assembly drawings, the author needs to see its technical drawing

    and measure the actual part and compare it with the drawings. Some drawing looks

    like the same but the dimension is different. This process was the process that the

    author needs to improve in order to ensure the process of RTS became much faster

    and easier.

    74

    14

    21

    2 3

    5

    0

    2

    4

    6

    8

    10

    12

    0

    10

    20

    30

    40

    50

    60

    70

    1 2 3 4 5 6 7 8 9 10

    Tim

    e T

    ake

    n

    Nu

    mb

    er

    of

    Par

    ts

    Project

    Parts with no part number

    Total parts

    Time taken to completeRTS

  • Project Deliverables or Suggestion of Solutions.

    After the analysis of all the form the Return to Stock list, several problems were

    identified. These problems happen because of several reasons stated above. From all

    the reason, Canevas and bulk items are the error that cannot be avoided since this

    items were compulsory to be ordered but the customer does not want it and the bulk

    items cannot be predicted thus it is normal to order the bulk items more than

    required. Moreover, reasons like wrong bookings or the typing error were kind of

    error which is categorized as human error. Human is not machine thus human are not

    perfect. We cannot vanished human error at once but we can minimize the error.

    Other types of error considered as technical error that can be avoided with practiced

    the right Standard of Procedure (SOP) or improve the process or the system.

    Thus , after several weeks of thinking to make the process of RTS easier and lessen

    the time taken and number of items for each project , I suggest several ideas.Firstly I

    am thinking of using of RFID for each manufactured parts. RFID is the new

    technology which has been widely use in many products like vehicles, airline

    passangers , Alzheimers patiens and pets. It is kind of tags which attached to the

    product and the tracker can easily track it by using special devices. However, after

    discussion with the supervisor, this kind of devices is too expensive. Furthermore , in

    order to buy the RFID tags and applied it as a part of Industrial Project , it taking too

    much time as the author needs to help the supervisor and project manager to finish

    the project. Thus for this Industrial Project the author think it is not suitable.

    Nevertheless, the tagging of the parts is a good of idea. Previous method practiced by

    was by using the labelled and barcode system but then in order to assemble become a

    big module the packaging is ripped and thrown away. When the assembler found out

    that the part is not fit or not suitable to be assemble or the assembler found out that it

    is not belong to that project , the package already been disposed. Along with the

    disposed package was the barcode and the number of parts.Thats where the problem

    of lost part number started.

  • Engineering department start to play their role on RTS after the excess part has been

    collected in a box. Then , we would take out the parts that cannot be reused to be sent

    to scrapped. The remaining parts in the box would be sent to engineering department

    be keyed into the RTS list. Before the parts can be key in, the author needs to ensure

    that all parts in the box has their part number. If not, the author need to refer back to

    the drawings. For the author point of view, this step is the most hardest and time

    consuming step in the RTS process. The step might be easier for the engineer who

    design the machine or project, but for the author, he needs to randomly check the

    drawings. After the author did several projects for RTS , the author realized that the

    name of the parts describe the part itself. For example in the return box , there is a

    rod which does not have part numbers. Thus the author simply use the find command

    in Microsoft Excel to find the word rod in the Bill of Materials. The results varies

    from 30 up to 100++ . Next, the author would go through the parts one by one and

    compare its features with the drawing in the server.

    So, in order to improve this steps, the author suggest to strengthen the engraved

    method. Actually, the engraved method has been put into practice on some of the big

    parts like blocks and the nest. The disadvantages of the engrave method was it is not

    applicable to the small parts or parts which has small flat surface areas like long rod.

    The author would like to improvise the engraved method by combine it with tagging

    method which is using small coloured sticker like shown in the Figure below.

  • It is advisable to use this sticker at the module which has many returns part like

    Platform and Taping. Platform or Taping is considered as big module or mother

    which consist of several small module or children. So we assign the children with

    the number while reasons of RTS with an alphabet.

    Other than that, author thought that in the description of material in the BOM list is

    too little. The author suggested to improvise the database by adding the description

    of the item like its weight or the number of holes and types of hole for each items or

    material used for the parts. Besides , for the simple parts like block which has

    dimension of 20x60x3 and has two holes with diameter., we might can add the

    dimension beside the name of parts. This solution needs a lot of work and involved

    other department since the database needs to be altered.The alternative for this

    solutions is the company should consider making other database other than Bill of

    Material which consists of complete description of every product. In order to do this

    engineering department should work together with software department to produce

    new program to search the parts based on its descriptions. It is tiring and time

    consuming but once the part missing its numbers it is much easier to find its number.

    13

    C

    Children Number (for example) 12 - Frame 15 Turret 13 PC kit

    Reasons of RTS (for example) A Bulk items C Wrong Bookings D Canevas

  • Morever, the customer can always refer to this program if they would like to have

    part change or module change.

    After the analysis of the parts , the author found out that the return items mostly

    made up of bulk items or canevas. Bulk items are the items which included fittings,

    washer , various types of screw (countersunk, headless), nuts or bolt. Canevas are the

    items which included 1.5m 3pin plug or safety cover which is the extra items which

    supplied to the customer but they dont want. The analogy for Canevas items is like

    the medical kit , jumper , kit to change tyre to the new car. Without all these items ,

    the car can still function well but they are important in case of emergency. Bulk

    items and canevas made up almost half or more of total of number of parts return.

    So , from the analysis the author think we should separate bulk items with the other

    parts as soon as it received by the engineer in charge. As stated earlier, the

    percentage for this kind of parts to be reuse is high rather than other parts. Thus it

    cannot considered waste to the company if it is managed well. In this company bin to

    placed all the standard bulk items from BOSSARD and ADAX already provided at

    the production site. The author think in order to improvise the system , the company

    should provide more bin for non-standard items but they always appear in the Return

    to Stock like fittings , amplifier and spacer. So that , the amount of items return

    would be less and the common items can be reused for the other projects.

  • Combining all three solution the author comes out with the new flow of system. This

    new flow of system can be said the final solution or the product of this project. With

    this solutions , the author hope the Return to Stock process can become easier and

    the parts for the RTS would become lesser and lesser day by day.

    Start

    All the excess part are collected in the box.

    Identify the part that need to scrap

    Seperate the bulk items or canevas items with normal item

    The colour stiker was applied by the fine tuner with the

    numbering and alphabet

    The labelled part according to the module was sent to the

    engineer.

    The engineer search the similar looking part in the new program made for lost part number items.

    The engineer check the dimension for lost part number

    items

    Record the new part in the RTS List.

    Send to the Person in Charge for next process

    End

  • Conclusion and Recommendation

    Impact

    Since the method or new flow still did not applied to the system, thus the results still

    undetermined. Nevertheless, according to 28 weeks of working in this company , the

    author think this system will be effective to the system .Implementation of the

    separation of bulk items with normal items reduce the number of parts that need to be

    return and might reduce the number of loss part number items. With the additional of

    adding new description which describe each parts in the new program, the user

    would easily found the part number for the loss part. Thus , the RTS list might only

    taken around 2 or 3 hours. On the other hand , the implementation of the sticker will

    reduce the number of parts in module which has large number of return items . In

    addition , the engineer or project manager can track the reasons of return item by

    simply looking at the sticker. So , process of analysis of RTS reasons can be done

    easily in the future. The author hope if the process is chosen to be implement in this

    company , the person who involved with RTS can follow the Standard Operating

    Procedure (SOP) which is made based on the solution , accordingly so that the

    process of RTS become easier and faster.

    The impact of the project to the author was the author learnt lots of new things that is

    important in future life. The author learnt how to manage time properly so that the

    project will be sent on time. This project also teach the author to organize the report

    so that it is easier to be interpreted and understand.

    Relevancy to the objectives

    Before the author discuss the relevancy of the solution to the objective , the author

    would like to recap the objective of the project which are :

    i) Analyse the engineering flow from the order until the machine is sent to

    customer relate it with Toyota Production System and Lean manufacturing.

    ii) Define Return to Stock (RTS) and importance of it to the engineering flow.

    iii) Analyse the current process flow of the current RTS and state the

    advantages and disadvantages of the flow.

    iv) Propose the solution to improve the RTS process so that it becomes more

    easier, save time and efficient

  • v) Reflect the relevancy of the new solution to the current engineering world.

    The first and second objective has been achieved when the author write literature

    review which reflected the engineering flow and RTS .RTS and its importance has

    been during the problem statement along with the flow. After the author analyse the

    data from the RTS list , the author found out the solution for RTS which is further

    explain during the project deliverable.

    For the last objective , for the author point of view , this solution Is relevance since

    the method use is simple and can be implement to other factory of manufacturing

    company who overcome the same problem. But , the author think there is better way

    to solve the problems if the author given more time . The author would discuss more

    about this better way in the next section. In conclusion , most of the objectives is

    relevant and the project meet its objective.

    Suggested Future Work for Expansion and Continuation

    Drawings

    From the author opinion , this kind of drawings is much easier to be refer for the

    engineer to do RTS . This kind of drawings was called exploded drawings.

  • Compared to current type of drawings which gather all the parts together in the

    drawings , this kind of drawing is gave more wide vision on the parts. With this kind

    of drawings , each of the part can be trace and be located. It is better if the drawings

    is made according to the module and documented for reference of engineers and the

    customers.

    Radio-frequency identification (RFID)

    Radio frequency identification (RFID) is an automatic identification method, relying

    on storing and remotely retrieving data using devices called RFID tags or

    transponders. An RFID tag is an object that can be applied to anything including

    animal, any product or person for the purpose of identification using radio waves.

    Some tags can be read from several meters away and beyond the line of sight of the

    reader. For passive RFID tags, it have no internal power supply while and active

    RFID tags have their own internal power source which is used the power of

    Integrated Circuit(IC) to broadcast the signal to reader.

    RFID is the most suitable methods to solve this problems. This RFID tag contains

    tiny semiconductor chips, miniaturized antennas and sometimes a battery. The tag

    can be in many forms depend on the type of object that the user want to track. The

    author ideas was to attached every parts with the passive tags of RFID which is

    cheaper, smaller and thinner . This kind of RFID do not have internal power source

    thus they rely on the signals by RFID reader.

  • In order to use the RFID tags in the warehouse and make the process of RTS more

    easier, my suggestion is we used the strip type of RFID and we attached it on every

    manufactured product. However to save cost , the author suggest to act according to

    the analysis of RTS which means we only attached the RFID to the module which

    have highest amount of items. After that , after we scan it for Return to Stock , and

    the parts safely placed in the warehouse , the RFID tags can be detach and attached it

    to the new project. This kind of method might have chance of RFID broken during

    the transportation of parts of during the assembly. Therefore to avoid this situation

    from happen it is advisable for the handler of the parts from the fabrication of parts

    until the person in charge for warehouse.

    Recommendation for UTP

    Industrial Project (IP) is the course that is compulsory for each student of UTP to

    take this course in order to graduate .It is the new version of normal Student

    Industrial Training which the previous batch enrolled a semester before. Thus the

    author would like to suggest a few recommendation for improvement of this course.

    First of all, the author would like to suggest for student who would like to intern in a

    company to ask about the training that he or she might undergo. The student should

    ask the detail of the training and what kind of work that he or she would do. Some

    company take for granted that the UTP student has long period of training and they

    just ask them to help them doing simple things which is not worth to be done by real

    engineer. CSIMAL should provide a guideline that needed to be undergone by the

    trainee before they finish the training.

    Next, for the Log book, the author think it is too burdensome to do the Logbook

    every day. Some of the trainee might undergone similar routine for several days.

    Thus the author thing the Logbook should only be written every week.

  • Lastly , before the student going for industrial training , CSIMAL should organize a

    short course or workshop on how to do proper technical report. It is true that during

    first year every student is compulsory to take academic writing course but in that

    course does not included on how to write technical project report . For example , how

    to write great methodology, impact or discussion.It is important for the student to

    learnt about all these to produce great report.

    Other than that ,the Industrial Project is a good platform for every student

    experienced to handle a project as a preparation for his or her Final Year Project

    during Final year. The period of 7 months is just great which enables the author to

    experience a lot during industrial training.

  • Safety Training and value for practical experience

    Lesson Learnt and Experienced Gained

    During the industrial internship, there are many things that the author learnt and

    experience new knowledge especially during the completing the task given by Host

    Company and completing the industrial project. The surrounding of the workplace also

    teaches the author about the work environment. Industrial internship program is made

    to help students in exposing themselves to the real working environment. It acts as a

    bridging to connect the knowledge that has been taught in UTP with the reality of the

    working. From here, the author was able to acquiring vest of knowledge that related to

    manufacturing industry to build the knowledge and be able to get sense of what its

    like working in a particular career field. During the internship, most of the time, the

    author did the office works. Thus it is important for the author to learnt about time

    management.

    Time management

    Industrial Project teach the author to manage the time really well compared to the

    Industrial Training , the first part of the Internship. For Industrial Project , the student

    needs to come out with a project and a report which solve problems face by engineering

    world . It is count as additional work which the author needs to do after office hour.

    This project considered as university project and the author was told that the student

    cannot mixed the university project and work task that given during office hour. The

    author has been paid to complete the work task during the office hour and the company

    disallow the student to do the project during office hour. For the author this is a big

    challenged since he needs to manage time after office hour to do the project.It is

    challenging since the author cannot staying up to late as tomorrow he needs to wake

    up early for work. Sometimes the author need to wake up in the middle of the night to

    work on the project.

  • Besides, sometimes the author has been given the two works in a time. For example

    when the author finding the part number in the drawings the project manager asked to

    help him design a cover for the machine. The author learnt that in this kind of situation

    the author needs to know the level of urgency which mean which one is more

    important.In the working field , work task were given constantly. It is a common when

    the first task was not done yet but the second task was received. Thats why the level

    of urgency is important.

    Lastly it is important for the author to learn that in the working field , last minute

    working is a really bad ideas. Working life is really different in university life. In the

    university life if you given an assignment which needed to be sent on Friday , the

    student always start working a day before. Then if the assignment is bad , the biggest

    punishment that the student will get is low of marks for that assignment.on. Despite of

    working field , if any of the work done badly , the company would face a loss or the

    customer might get angry. If it keeps on happening the risk of the worker fired from

    the work Is really high. Thats why in working field we need to work every project

    starting from the first day task was given to retain the quality of the work.

    Self discipline

  • References