singapore management university memorandum for … · 2021. 1. 23. · a. laytime commenced when...

28
19th Annual International Maritime Law Arbitration Moot In the matter of an arbitration under the LMAA Arbitration Rules SINGAPORE MANAGEMENT UNIVERSITY MEMORANDUM FOR RESPONDENT CLAIMANT RESPONDENT Cerulean Beans & Aromas Ltd v Dynamic Shipping LLC 945 Moccasin Road 23 Fuchsia Crescent Cerulean Cerulean TEAM 22 COUNSEL Berwin CHUA | FOUNG Han Peow | Isaiah ZHAO | Sean LEE | Terence YEO | Theodore TOH

Upload: others

Post on 29-Jan-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

  • 19th Annual International Maritime Law Arbitration Moot

    In the matter of an arbitration under the LMAA Arbitration Rules

    SINGAPORE MANAGEMENT UNIVERSITY

    MEMORANDUM FOR

    RESPONDENT

    CLAIMANT RESPONDENT

    Cerulean Beans & Aromas Ltd

    v

    Dynamic Shipping LLC

    945 Moccasin Road 23 Fuchsia Crescent

    Cerulean Cerulean

    TEAM 22

    COUNSEL

    Berwin CHUA | FOUNG Han Peow | Isaiah ZHAO | Sean LEE | Terence YEO | Theodore TOH

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    2 | P a g e

    TABLE OF CONTENTS

    LIST OF AUTHORITIES ....................................................................................................... 4

    I. Articles and Books ............................................................................................................ 4

    II. Cases ................................................................................................................................... 4

    III. Legislation.......................................................................................................................... 5

    STATEMENT OF FACTS ...................................................................................................... 7

    PRELIMINARY MATTERS .................................................................................................. 9

    I. The Tribunal has no jurisdiction to determine the Claimant’s claim for damages ... 9

    A. The damages sought by the Claimant falls within the ambit of “technical matters”

    9

    B. The opinion of an independent Master Mariner has not been sought ................... 10

    SUBMISSIONS ON THE ISSUE OF MARITIME LIEN ................................................. 11

    SUBMISSIONS ON THE CLAIMANT’S CLAIMS .......................................................... 12

    I. The Respondent is not liable for the Claimant’s claims as the Force Majeure

    (“FM”) clause applies ..................................................................................................... 12

    A. The Solar Flares were an “act of God” within the meaning of the FM clause ..... 12

    B. The Storm was an “unforeseen weather event” within the meaning of the FM

    clause ......................................................................................................................... 13

    C. The Respondent has complied with the procedural requirements of the FM clause

    13

    II. The Claimant is not entitled to claim the value of the damaged goods and the cost of

    replacement ..................................................................................................................... 14

    III. The Respondent's liability is limited by the Hague-Visby Rules ................................ 16

    A. Liability can be limited because the value and nature of the goods were not

    appropriately declared .............................................................................................. 16

    B. An unreasonable deviation does not preclude the limitation of liability ................ 16

    C. As the Hague-Visby Rules were incorporated into the Charterparty, the

    Respondent’s liability is limited to a sum less than the claims ............................... 17

    D. Even if the Hague Rules apply, the Respondent’s liability is limited to a sum less

    than the claims .......................................................................................................... 17

    SUBMISSIONS ON THE RESPONDENT’S COUNTERCLAIMS ................................. 19

    I. The Claimant is liable for freight of the delivered cargo ............................................ 19

    A. The Charterparty stipulates that 90% of freight is payable within two banking days

    of the delivery of cargo ............................................................................................. 19

    B. Freight is payable regardless if cargo was damaged ............................................... 19

    C. Freight is an exception to the general rule of set-off .............................................. 20

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    3 | P a g e

    II. The Claimant is liable for the agency fees at Spectre .................................................. 21

    A. The agency fees were reasonably incurred .............................................................. 21

    B. The Claimant could not have nominated its agents at Spectre ............................... 21

    III. The Claimant is liable for the agency fees at Dillamond ............................................. 22

    IV. The Claimant is liable for the cost of repairs to the Ship ............................................ 22

    A. The Claimant nominated an unsafe port ................................................................. 23

    B. The Respondent was not negligent either in anchoring the Ship or in the way it

    anchored .................................................................................................................... 24

    C. The damage was not caused by the Respondent’s negligence when cutting the

    anchor........................................................................................................................ 24

    V. The Claimant is liable for demurrage ........................................................................... 25

    A. Laytime commenced when the vessel arrived at waiting area ................................ 25

    B. The exceptions to laytime as stipulated in Clause 8(e) do not apply....................... 26

    C. Calculation of laytime and demurrage .................................................................... 27

    VI. The Claimant is liable for the use of electronic access systems at Dillamond ........... 27

    PRAYER FOR RELIEF........................................................................................................ 28

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    4 | P a g e

    LIST OF AUTHORITIES

    I. Articles and Books

    G.H. Treitel, Frustration and Force Majeure (Sweet & Maxwell, 3rd Ed, 2014)

    Harvey McGregor, McGregor on Damages (Sweet & Maxwell, 19th Ed, 2014)

    John Schofield, Laytime and Demurrage (6th Ed., 2011)

    Sir Bernard Eder, Howard Bennett, Steven Berry, David Foxton and Christopher F Smith,

    Scrutton on Charterparties (22nd Edition, Sweet & Maxwell, 2011)

    II. Cases

    Aldebaran Compania Maritima SA v Aussenhandel AG (The Darrah) [1977] AC 157

    Anglia Television v Reed [1972] 1 Q.B. 60

    Bim Kemi AB v Blackburn Chemicals [2001] 2 Lloyd’s Rep. 93

    Blanchet v Powell’s Llantivit Collieries [1874] L.R. 9 Ex. 74

    Brown Boveri (Australia) Pty Ltd v Baltic Shipping Co (The Nadezhda Krupskaya) [1989] 1

    Lloyd's Rep. 518

    Bunge SA v Kyla Shipping Co. Ltd [2013] EWCA Civ 734 at [70];

    Daewoo Heavy Industries v Klipriver Shipping (The Kapitan Petko Voivoda) [2003] 2 Lloyd’s

    Rep. 1

    Elena Shipping v Aidenfield Ltd [1986] 1 Lloyd's Rep. 425

    Freedom Maritime Corporation v International Bulk Carriers SA and another (The Khian

    Captain) [1985] 2 Lloyd’s Rep 212

    ISS Machinery Services v Aeolian Shipping [2001] 2 Lloyd’s Rep. 641

    Kodros Shipping Inc. v Empresa Cubana de Fletes (No. 2) [1983] 1 A.C. 736

    Mediterranean Salvage & Towage Ltd v Seamar Trading & Commerce Inc [2009] EWCA Civ

    531

    Merchant Shipping v Armitage [1873] L.R. 9 Q.B. 99

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    5 | P a g e

    Nugent v Smith [1876] 1 C.P.D. 421

    Oldendorff (EL) & Co GmbH v Tradax Export SA (The Johanna Oldendorff) [1973] 2 Lloyd’s

    Rep 285

    Pust v Dowie [1864] 5 B. & S. 20

    Rankin v The Ship, Eliza Fisher [1895] 4 Ex CR 461

    Reardon Smith Line Ltd v Ministry of Agriculture, Fisheries and Food [1963] 1 Lloyd’s Rep.

    12

    Ships “Hako Endeavour”, “Hako Excel”, “Hako Esteem” and “Hako Fortress” v

    Programmed Total Marine Services Pty Ltd [2013] FCAFC 21

    The Berostar [1970] 2 Lloyd’s Rep 403

    The Elena [1986] 1 Lloyd’s Rep 425

    The Mogileff [1921] P 236

    The Owners of the Norway v Ashburner (The Norway) (No. 2) (1865) 3 Moo. P.C. 254

    The Rosa S [1989] Q.B. 419

    The Superior Pescadores Syemgas Fzco and others v Superior Pescadores SA [2016] EWCA

    Civ 101

    The Thekos SMA 2405 [1987]

    The Vasilia [1972] 1 Lloyd’s Rep 51

    The World Star [1987] 1 Lloyd’s Rep 452

    III. Legislation

    Carriage of Goods by Sea Act 1991 (Act No. 160/1991) (Australia)

    Coinage Act (Cap 10, 1870)

    Coinage Act (Cap 24, 1971)

    International Convention for the Unification of Certain Rules of Law relating to Bills of Lading

    (“The Hague Rules”) (1924)

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    6 | P a g e

    Protocol to Amend the International Convention for the Unification of Certain Rules of Law

    Relating to Bills of Lading (“The Hague-Visby Rules”) (1968)

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    7 | P a g e

    STATEMENT OF FACTS

    1. On 22 July 2017, Cerulean Beans and Aromas Ltd (the “Claimant”) entered into a voyage

    charterparty (the “Charterparty”) with Dynamic Shipping LLC (the “Respondent”),

    owners of the Madam Dragonfly (“the Ship”). The cargo to be shipped was 1000 bags of

    high-grade coffee each weighing 70kg, placed in four large containers. It was agreed that

    the cargo is to be discharged by 7pm on Friday, 28 July 2017.

    2. On or around 22 July 2017, the Claimant paid the amount of US$100,000 on account of

    wages which would become payable to the crew of the Ship following the voyage into a

    special Bank account of the Respondent established for that purpose. The Respondent has

    not paid the crew of the Madam Dragonfly wages due for the voyage and has not repaid

    the US$100,000 to the Claimant.

    3. On 26 July 2017, the Respondent informed the Claimant that the Ship’s communication

    and satellite systems were knocked out by solar flares (“Solar Flares”) for 17 hours. The

    Solar Flare was reported to be an “unprecedented international emergency” which

    knocked out radio and satellite communications systems “around the world”. During the

    period where its systems were down, the Ship made a detour to the port of Spectre

    (“Spectre”) as it only had the charts to Spectre.

    4. The Ship arrived at the waiting area outside Dillamond at 7am on 29 July 2017. The Ship

    could not enter the port as a “once in a lifetime” storm (“Storm”) caused delays in the port.

    The Ship berthed in Dillamond at approximately 5pm on 29 July 2017. The cargo was then

    discharged and placed in a warehouse at Dillamond at 12.02am on 30 July 2017. The

    Claimant took delivery of the cargo at 1.17pm on 31 July 2017.

    5. Three of the containers were completely water damaged. The value of the damaged cargo

    was US$15,750,000 (“the Damaged Cargo Claim”).

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    8 | P a g e

    6. On 1 August 2017, the Claimant entered into a settlement agreement with Coffees of the

    World Ltd, whom the former was contractually obliged to supply coffee. The Claimant

    and Coffees of the World agreed that the Claimant would source for replacement coffee at

    a price of US$9,450,000 (“the Replacement Coffee Payment”) in addition to a settlement

    payment of US$5,000,000 (“the Settlement Payment”).

    7. The Claimant served notices of arbitration to the Respondent on 11 August 2017 in

    accordance with Clause 27 of the Charterparty. The Respondent’s counter-claims include

    freight, agency fees at Spectre and Dillamond, cost of repairs to the Ship, demurrage and

    use of electronic access systems at Dillamond.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    9 | P a g e

    PRELIMINARY MATTERS

    I. The Tribunal has no jurisdiction to determine the Claimant’s claim for damages

    8. The Tribunal has no jurisdiction to determine the Claimant’s claim for damages as the

    claims arise from “technical matters” which the Charterparty provides should be

    determined by an “independent Master Mariner”.1 Clause 27(e) states that arbitral

    proceedings cannot be commenced unless disputes relating to technical matters have been

    referred to expert determination by an independent Master Mariner.2 The Respondent

    submits that (A) the damages sought by the Claimant falls under the ambit of “technical

    matters” as defined in Clause 27(g) and (B) the opinion of an independent Master Mariner

    has not been sought.

    A. The damages sought by the Claimant falls within the ambit of “technical matters”

    9. The claim for damages falls within the definition of “technical matters” under Clause

    27(g).3 Clause 27(g) states that “technical matters” refer to matters surrounding technical

    aspects of the performance of the Charterparty, such as the vessel's route, storage

    conditions and matters which can reasonably be considered within the expert technical

    knowledge of a Master Mariner.4 Here, the dispute arose over a breach in the Charterparty,

    triggered by the route taken by the Ship and its seaworthiness. The route taken by the Ship

    falls squarely within the ambit of the clause and seaworthiness is a technical matter which

    can reasonably be considered within the expert technical knowledge of a Master Mariner.

    Hence, the clause applies to the damages claimed sought by the Claimant, and the Claimant

    cannot validly commence arbitration until the dispute on technical matters underlying the

    damages has been determined by an independent Master Mariner.

    1 The Charterparty, Cl 27(d). 2 The Charterparty, Cl 27(e). 3 The Charterparty, Cl 27(g). 4 The Charterparty, Cl 27(g).

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    10 | P a g e

    B. The opinion of an independent Master Mariner has not been sought

    10. Clause 27(d) requires disputes on “technical matters” to be referred to expert

    determination by an independent Master Mariner.5 As the damages claimed are being

    disputed on technical matters, the Claimant’s claim for damages falls within Clause 27(d).

    The expert report that was referred to was from a maritime engineer, not an “independent

    Master Mariner”. Hence, Clause 27(d) has not been satisfied.6

    11. Given the above, the Respondent submits that Clause 27(e) applies to bar arbitral

    proceedings and hence the Tribunal has no jurisdiction to determine the Claimant’s claim

    for damages.

    5 Moot Scenario, p 12. 6 Moot Scenario, p 43.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    11 | P a g e

    SUBMISSIONS ON THE ISSUE OF MARITIME LIEN

    12. The Claimant’s claim to a maritime lien over the Ship can only arise by way of subrogation

    to the crew’s wage lien. However, in the present case, the requirements for the Claimant

    to be subrogated to the rights under the wage lien have not been satisfied.

    13. The UK admiralty courts have consistently insisted on the requirement of prior court

    approval. Strict enforcement of this particular requirement has been observed in various

    cases such as The Mogileff,7 The Berostar,8 The Vasilia9 and The Worldstar10. This

    requirement should similarly be strictly enforced under Australian law.11

    14. Requirement of prior court approval provides an essential safeguard for the seamen’s

    interests and ensures that they are not taken advantage of by lower ranking creditors whose

    only interest is the protection of their own commercial interest which may be at the expense

    of the ship’s crew.12 Thus, judicial scrutiny acts as an important balance between the

    commercial interests of other creditors and the protection of seafarer’s wages.

    15. In the present case, the Claimant had not obtained prior leave of court for the payment of

    crew’s wages or its subrogation to the crew’s maritime lien. Hence, the wage lien was

    effectively extinguished when the US$100,000 was used to satisfy the crew’s wages.

    16. Therefore, the Claimant is not entitled to any kind of maritime lien over the Ship.

    7 The Mogileff [1921] P 236. 8 The Berostar [1970] 2 Lloyd’s Rep 403. 9 The Vasilia [1972] 1 Lloyd’s Rep 51. 10 The World Star [1987] 1 Lloyd’s Rep 452. 11 Ships “Hako Endeavour”, “Hako Excel”, “Hako Esteem” and “Hako Fortress” v Programmed Total Marine

    Services Pty Ltd [2013] FCAFC 21 at [99]. 12 Rankin v The Ship, Eliza Fisher [1895] 4 Ex CR 461 at 469.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    12 | P a g e

    SUBMISSIONS ON THE CLAIMANT’S CLAIMS

    I. The Respondent is not liable for the Claimant’s claims as the Force Majeure (“FM”)

    clause applies

    17. FM would serve as a defence to what would have otherwise been a breach of the

    Charterparty. This would concurrently defeat the Claimant’s claim for the Replacement

    Coffee Payment, the Damaged Cargo Claim and the Settlement Payment which are losses

    flowing from the alleged breach of the Charterparty. In this regard, the Respondent submits

    that: (A) the Solar Flares which disrupted the communication systems on 25 July 2017

    constituted an “act of God” event;13 (B) the Storm occurring on 28 July 2017 was an

    “unforeseen weather event” within the meaning of the FM clause and;14 (C) the

    Respondent has complied with the procedural requirements of the FM clause.

    A. The Solar Flares were an “act of God” within the meaning of the FM clause

    18. In determining whether an event falls within the ambit of an FM clause, the inquiry is

    “whether on its true construction, the contract under consideration provides for the

    event … [that] has occurred”.15 This requires a careful consideration of the terms within

    the Charterparty.

    19. Clause 17 explicitly defines FM events as including an “act of God”.16 An “act of God”

    refers to an irresistible event which the shipowner can neither avoid nor guard against.17

    The Respondents would thus have to show that there was no reasonable precaution under

    all circumstances that could have prevented the delay.18 The Respondent respectfully

    13 The Charterparty, Cl 17. 14 The Charterparty, Cl 17. 15 Bunge SA v Kyla Shipping Co. Ltd [2013] EWCA Civ 734 at [70]; Sir Bernard Eder, Howard Bennett, Steven

    Berry, David Foxton and Christopher F Smith, Scrutton on Charterparties (22nd Edition, Sweet & Maxwell,

    2011) at 1-089. 16 The Charterparty, Cl 17. 17 Nugent v Smith [1876] 1 C.P.D. 421, at 437. 18 Nugent v Smith [1876] 1 C.P.D. 421, at 437.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    13 | P a g e

    submits that no precaution could have been taken since it was not aware of the impending

    Solar Flares. There is no indication as to the Respondent’s awareness of Cerulean news

    reports on the impending Solar Flares.19

    20. Therefore, the Respondent can rely on the FM clause.

    B. The Storm was an “unforeseen weather event” within the meaning of the FM clause

    21. The Charterparty makes express provision for “unforeseen weather events”.20 The

    Respondent submits that the Storm which occurred on 28 July 2017 falls within the

    aforementioned definition. In its email correspondence with the Claimant, the Respondent

    has described it as “roll[ing] in very suddenly” and that the crew “…[did not] see it on

    the radar until about 30 min[utes] ago”.21 Furthermore, the Storm was described by a

    news agency as a “once in a lifetime” storm event.22 Cumulatively, these facts lead to the

    conclusion that the Storm was unforeseen.

    22. Therefore, the Storm falls within the ambit of the FM clause and the Respondent is entitled

    to rely on Clause 17 to excuse its delayed performance.

    C. The Respondent has complied with the procedural requirements of the FM clause

    23. The central issue here is whether the procedural requirements in the FM clause have been

    breached by the Respondent, thereby precluding the Respondent from relying on the FM

    clause.23 To this end, the Respondent submits that prompt written notice was given by the

    Respondent

    24. In the Charterparty, the word “prompt” is used to denote the prescribed notice period.24

    19 Procedural Order No. 2, Cl 7 & 8. 20 The Charterparty, Cl 17. 21 Moot Scenario, p 19. 22 Moot Scenario, p 21. 23 G.H. Treitel, Frustration and Force Majeure (Sweet & Maxwell, 3rd Ed, 2014) at 12-048. 24 The Charterparty, Cl 17.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    14 | P a g e

    25. With respect to the Solar Flares incident, the Respondent submits that such notice has been

    given since the Claimant was informed of the delay as soon as the communications with

    the Ship have been restored.25 The Respondent has given such notice as practicably as it

    could in the circumstances, after it has established the status and whereabouts of the Ship.26

    In the same vein, the Respondent was not aware that a delay has resulted from the Solar

    Flares.27

    26. With respect to the Storm, the Respondent has notified the Claimant within 30 minutes of

    the crew detecting the Storm. This, it is submitted, constitutes prompt written notice.

    27. Therefore, the Respondent has not breached this requirement of the FM clause in respect

    of both FM events.

    II. The Claimant is not entitled to claim the value of the damaged goods and the cost of

    replacement

    28. Even if the Respondent is found by the Tribunal to be liable to the Claimant for the breach

    of the Charterparty, the Respondent submits the Claimant would be barred from recovering

    all heads of claims. This is due to the issue of double recovery.

    29. It is trite law that a plaintiff claiming damages for breach of contract has to elect between

    claiming for loss of profits or for incurred expenditures.28 Loss of profits is defined as the

    pecuniary loss suffered by a contracting party due to non-delivery of property.29 Such loss

    of profits may be due to a loss of a specific sale to a third party.30 Here, the value of the

    damaged cargo includes the margin of profits that the Claimant would have received by

    selling the cargo to Coffees of the World. On the other hand, incurred expenditures refer

    25 Moot Scenario, p 17. 26 Moot Scenario, p 17. 27 Moot Scenario, p 17. 28 Anglia Television v Reed [1972] 1 Q.B. 60. 29 Harvey McGregor, McGregor on Damages (Sweet & Maxwell, 19th Ed, 2014) at 4-018. 30 Harvey McGregor, McGregor on Damages (Sweet & Maxwell, 19th Ed, 2014) at 4-018.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    15 | P a g e

    to the expenses incurred by a plaintiff in searching for replacement goods due to non-

    delivery under a contract of carriage.31 Expenses incurred by way of settlement with a third

    party are also considered as incurred expenditure.32 Applying these principles to the

    present case, the Replacement Coffee Payment and Settlement Payment can be classified

    as incurred expenditures.

    30. An allowance for both loss of profits and incurred expenditure would result in double

    recovery.33 This is because a claim for loss of profits also encompasses expenses which

    were necessarily incurred to fulfil contractual obligations.34 Applying this to the present

    case, the coffee cargo and the replacement coffee are alternative ways in which the

    Claimant could fulfil its contractual obligations with Coffees of the World. Since the

    purpose of contractual damages is to put a plaintiff in the position as he would have been

    in had the contract been performed,35 the Claimant should only be allowed to claim either

    the value of the damaged cargo or a combination of the Replacement Coffee Payment and

    the Settlement Payment, but not both.

    31. In light of the foregoing, the Respondent submits that even if the Tribunal finds that

    liability is established, the Claimant is only entitled to either the damaged cargo claim or

    the combination of the Replacement Coffee Payment and the Settlement Payment.

    However, given that the Respondent’s liability is limited by the Hague-Visby Rules, the

    Claimant’s claims should not be allowed in full.

    31 Harvey McGregor, McGregor on Damages (Sweet & Maxwell, 19th Ed, 2014) at 4-022. 32 Harvey McGregor, McGregor on Damages (Sweet & Maxwell, 19th Ed, 2014) at 4-023. 33 Harvey McGregor, McGregor on Damages (Sweet & Maxwell, 19th Ed, 2014) at 4-024. 34 Harvey McGregor, McGregor on Damages (Sweet & Maxwell, 19th Ed, 2014) at 4-024. 35 Harvey McGregor, McGregor on Damages (Sweet & Maxwell, 19th Ed, 2014) at 2-003.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    16 | P a g e

    III. The Respondent's liability is limited by the Hague-Visby Rules

    32. The Claimant submits that the Hague-Visby Rules were incorporated into the Charterparty

    instead of the Hague Rules (“HR”). Whether the Clause Paramount36 incorporates the

    HVR or the HR depends on the applicable law. Where the specific state has already

    incorporated the HVR, the Clause Paramount will also incorporate the particular

    legislation.37 Since the Charterparty is governed by the laws of New South Wales, and

    Australia’s Carriage of Goods by Sea Act 199138 enacts the HVR, the HVR were

    incorporated into the Charterparty and provide the relevant limitation of the Respondent’s

    liability in this case.

    A. Liability can be limited because the value and nature of the goods were not appropriately

    declared

    33. Unless the Claimant has appropriately declared the value and nature of the goods shipped,

    the Respondent can limit its liability under both the HVR and the HR.39 The declaration

    of value by the Claimant in this case was not included in the Charterparty itself40 and

    therefore is not binding on the Respondent. The Claimant is not entitled to recover in

    excess of the limit provided by the HR through a declaration of value before shipment.

    Accordingly, the Respondent is entitled to limit its liability under the HVR.

    B. An unreasonable deviation does not preclude the limitation of liability

    34. The Claimant cannot argue that an unreasonable deviation disentitles the Respondent from

    limiting its liability under the HVR and the HR. Article IV rule 5 of both the HVR and the

    HR, which uses the term “in any event”, may still provide the carrier with a defence of

    package limitation even in the case of an unreasonable deviation.41 Therefore, the Claimant

    36 The Charterparty, Cl 28. 37 The Superior Pescadores Syemgas Fzco and others v Superior Pescadores SA [2016] EWCA Civ 101. 38 Carriage of Goods by Sea Act 1991 (Act No. 160/1991) (Australia). 39 Article IV Rule 5 of the Hague Rules and Hague-Visby Rules. 40 Moot Scenario, p 2. 41 Daewoo Heavy Industries v. Klipriver Shipping (The Kapitan Petko Voivoda) [2003] 2 Lloyd’s Rep. 1.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    17 | P a g e

    cannot argue that an unreasonable deviation renders the defence of package limitation

    irrelevant.

    C. As the Hague-Visby Rules were incorporated into the Charterparty, the Respondent’s

    liability is limited to a sum less than the claims

    35. Pursuant to the HVR, the Respondent is not liable for any damage or loss exceeding the

    equivalent of 666.67 units of account per package or unit or 2 units of account per kilo of

    gross weight of the goods lost or damaged, whichever is the higher.

    36. The Respondent submits that the relevant packages were the “four containers” as this was

    what was listed in the dock receipt. Even though this was amended by the Respondent,

    the Claimant raised no objections to that, signifying their agreement to contract on the

    amended terms. The higher limit would thus be based on the gross weight of the goods

    damaged and the Respondent’s liability is limited at only 140,000 SDR (1,000 x 70 x 2).

    37. If the Tribunal finds that the relevant package or unit is each bag of coffee, the higher limit

    would be 666, 670 SDR (1000 x 666.67). This amount is still less than what is sought by

    the Claimant.

    D. Even if the Hague Rules apply, the Respondent’s liability is limited to a sum less than

    the claims

    38. If the Tribunal finds that the Clause Paramount42 had the effect of incorporating the HR

    and not the HVR, the applicable limitation of liability is £100 sterling gold value per

    package or unit. The value of £100 sterling would be considered by reference to the

    quantity of gold equivalent to £100 sterling in 1924.43 The gold content of £100 sterling

    was in 1924 defined as a matter of English law by the Coinage Act 1870,44 and was at the

    date of the Charterparty, defined by the Coinage Act 1971,45 as being 798.805 grammes

    42 The Charterparty, Cl 28. 43 The Rosa S [1989] Q.B. 419. 44 Coinage Act (Cap 10, 1870). 45 Coinage Act (Cap 24, 1971).

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    18 | P a g e

    of gold at a millesimal fineness 916.66, which is the same as 732.238 grammes of fine

    gold. Taking the relevant date of the assessment of the Respondent’s liability as being the

    date of delivery of the goods,46 which is 31 July 2017, this gives a gold value of £100

    sterling as US$32,790.57.47 The Respondent submits that the relevant packages were the

    “four containers” as this was what was listed in the dock receipt. Even though this was

    amended by the Respondent, the Claimant raised no objections to that, signifying their

    agreement to contract on the amended terms. The Respondent would thus not be liable for

    an amount exceeding US$131,162.28 (32,790.57 x 4), which is significantly less than what

    was sought by the Claimant.

    39. If the Tribunal finds that the “packages” were the 1000 bags, the limit of liability would

    be US$32,790,570 (32,790.57 x 1000).

    46 The Rosa S [1989] Q.B. 419. Endorsed in Brown Boveri (Australia) Pty Ltd v Baltic Shipping Co (The

    Nadezhda Krupskaya) [1989] 1 Lloyd's Rep. 518. 47 The price per ounce of fine gold on 31 July 2017 is estimated at USD 1269.55.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    19 | P a g e

    SUBMISSIONS ON THE RESPONDENT’S COUNTERCLAIMS

    I. The Claimant is liable for freight of the delivered cargo

    40. The Respondent is claiming for the freight of US$500,000 for the following reasons: (A)

    Clause 22 of the Charterparty states that 90% of the freight is payable within two banking

    days of the delivery of cargo; (B) freight is payable regardless if the cargo was damaged

    and (C) freight is a general exception to set-off.

    A. The Charterparty stipulates that 90% of freight is payable within two banking days of

    the delivery of cargo

    41. Freight is the remuneration payable for carriage of the cargo. The freight rate is contracted

    to be a lumpsum of US$500,000 for four containers of coffee beans.48 Clauses 11 and 22

    of the Charterparty stipulates that 90% of the freight has to be paid within two banking

    days of cargo delivery.49 Therefore, since the Claimant has acknowledged delivery,50 it is

    liable for the payment of freight.

    B. Freight is payable regardless if cargo was damaged

    42. The Respondent submits that the Claimant is liable for the payment of freight as long as

    the cargo was delivered. This is so even if the cargo was damaged.

    43. Where the charterparty provides for a lump sum freight, payable on delivery, the entire

    freight is payable even if part of the cargo is lost by excepted perils.51 Applying this

    principle to the present case, the Claimant is liable for the payment of freight even if it

    contends that the cargo was damaged. Therefore, since the Claimant has acknowledged

    delivery,52 it is liable for the payment of freight regardless of the damage to the cargo.

    48 Moot Scenario, p 3. 49 Moot Scenario, p 7 & 11. 50 Moot Scenario, p 24. 51 The Owners of the Norway v Ashburner (The Norway) (No. 2) [1865] 3 Moo. P.C. 254. See also Merchant

    Shipping v Armitage [1873] L.R. 9 Q.B. 99. 52 Moot Scenario, p 24.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    20 | P a g e

    C. Freight is an exception to the general rule of set-off

    44. Even though the cargo delivered was damaged, the Claimant is not entitled to set-off the

    claim for breach of contract against the freight.

    45. Freight is an exception to the general rule that claims for breach of contract can be set off

    in diminution or extinction of a different claim for a sum due under the same contract.53 It

    is also trite law that where freight is due and payable under the terms of the charter, and a

    claim under a possible breach of contract for damages arises, both the owner and the

    charterer are required to pursue their claims independently as they cannot be set off against

    each other.54 Applying these principles to the present case, the Claimant cannot set off

    freight against the claims it is pursuing for the damaged cargo. Freight is payable by the

    Claimant independent of the claims it seeks to recover from the losses arising from the

    damaged cargo.

    46. Furthermore, the Respondent submits that there is no basis for apportioning lump sum

    freight even when part of the cargo is not delivered. This is due to the rule that freight is

    either fully recoverable or non-recoverable.55 In the present case, all four containers of

    coffee beans were delivered.56 As such, it is unreasonable for the Claimant to contend that

    it is not liable for freight.

    47. Given the above, the Respondent respectfully submits that the full lump sum freight is still

    payable by the Claimant, and a claim for damages can be raised independently of the

    freight by the Claimant instead.57

    53 Bim Kemi AB v Blackburn Chemicals [2001] 2 Lloyd’s Rep. 93; ISS Machinery Services v Aeolian Shipping

    [2001] 2 Lloyd’s Rep. 641. 54 Elena Shipping v Aidenfield Ltd [1986] 1 Lloyd's Rep. 425. 55 Merchant Shipping v Armitage [1873] L.R. 9 Q.B. 99 at 110 – 111. As to the non-apportionability of

    lumpsum freight see also Pust v. Dowie [1864] 5 B. & S. 20; Blanchet v. Powell’s Llantivit Collieries [1874]

    L.R. 9 Ex. 74. 56 Moot Scenario, p 24. 57 The Elena [1986] 1 Lloyd’s Rep 425.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    21 | P a g e

    II. The Claimant is liable for the agency fees at Spectre

    48. The Respondent is claiming US$75,000 for the agency fees at Spectre as (A) these fees

    were reasonably incurred and (B) the Claimant could not have nominated its agents.

    A. The agency fees were reasonably incurred

    49. The Respondent submits that the agency fees were reasonably incurred. This is because

    the Respondent did not breach its obligation to ensure the seaworthiness of the Ship.

    50. It is submitted that the failure of the Ship’s communication and navigation systems was

    not due to any fault in the equipment, but the severity of the Solar Flares. It was reported

    in the Cerulean newspaper that the Solar Flare was an “unprecedented international

    emergency” and that satellites systems “around the world” were knocked out.58 The report

    also suggests that only delays of 20 hours or more in reconnection could be attributed to

    old or faulty equipment.59

    51. The Ship’s communications systems were up within a short time frame of 17 hours.60 The

    Respondent submits that this time frame is acceptable and does not indicate

    unseaworthiness because it was consistent with other systems based on a report published

    in the Cerulean newspaper dated 25 July 2017.61 As such, the Ship was forced to detour to

    Spectre due to the severity of the Solar Flares, and not due to a breach of the Respondent’s

    obligation to ensure the seaworthiness of the Ship. It is therefore reasonable for the

    Claimant to reimburse the Respondent for the agency fees incurred at Spectre.

    B. The Claimant could not have nominated its agents at Spectre

    52. The Respondent further submits that the Claimant could not have possibly nominated its

    agents at Spectre. This is because the Ship’s navigation and communication systems were

    58 Moot Scenario, p 35. 59 Moot Scenario, p 35. 60 Moot Scenario, p 17. 61 Moot Scenario, p 35.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    22 | P a g e

    down due to the Solar Flares.62 As such, it was impossible for the Ship to have contacted

    the Claimant for the latter to nominate its agents at Spectre. Furthermore, there was no

    obligation on the Respondent to communicate this deviation to the Claimant beforehand,

    since such an obligation only arises if the Ship calls at a port for cargo purposes.63

    Therefore, it was reasonable for the Respondent to have nominated its own agents at

    Spectre. The Claimant should thus reimburse the Respondent for these fees.

    III. The Claimant is liable for the agency fees at Dillamond

    53. The Respondent is claiming US$50,000 as the agency fees at Dillamond since the

    Charterparty specifies that this cost is to be borne by the Claimant.

    54. Clause 12(a) of the Charterparty stipulates that the Ship shall be consigned to the

    charterer’s agents at the discharge port.64 The clause also states that the charterer shall pay

    all customary fees at the discharge port.65 On a plain reading of the clause, this means that

    the Ship is consigned to the Claimant at Dillamond, and the Claimant is to pay all

    customary fees at Dillamond. Since agency fees can be considered as a form of customary

    fees, the Respondent submits that it is fair and reasonable for the Claimant to be liable for

    this head of claim.

    IV. The Claimant is liable for the cost of repairs to the Ship

    55. The Respondent is claiming USD$875,000 for the cost of repairs to the Ship. This is

    because the damage to the Ship was suffered due to (A) the nomination of an unsafe port

    by the Claimant. The Respondent also submits that (B) it was not negligent either in

    anchoring the Ship or in the way it anchored, and (C) the damage was not caused by the

    62 Moot Scenario, p 17. 63 The Charterparty, Cl 12(b). 64 The Charterparty, Cl 12(a). 65 The Charterparty, Cl 12(a).

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    23 | P a g e

    Respondent’s negligence when cutting the anchor after it was tangled in the coral bed

    outside Dillamond.66

    A. The Claimant nominated an unsafe port

    56. The Claimant breached the implied warranty of port safety when it nominated an unsafe

    port. The Respondent submits that this was the proximate cause of the damage to the Ship.

    The Claimant is liable for the cost of repairs as there is no break in the chain of causation

    resulting from any negligence on the part of the Respondent's as the safety of a port must

    be warranted throughout the entire voyage.

    57. It is trite law that where a charterparty provides for the nomination of a port, but is silent

    as to its safety, a warranty that the port is safe will be implied.67 The obligation to nominate

    a safe port extends from the time of nomination to the period of the vessel's likely visit,

    hence prospective safety of the port must be taken into consideration.68 Applying these

    principles to the present case, although there is no express warranty by the Claimant as to

    the safety of Dillamond, such a warranty must necessarily be implied into the Charterparty.

    Such implication is necessary from the terms of the Charterparty as the Claimant did not

    offer the Respondent any alternative port of discharge. The Claimant by requiring the

    cargo to be delivered directly and only to Dillamond,69 must have implied that the port is

    safe for the Ship to berth and for the cargo to be unloaded.

    58. A storm which passes through a port after nomination can render it unsafe, and this is a

    breach of the safe port warranty by the charterer.70 The shipowner will be entitled to

    recover the cost of repairs to the vessel from the charterer.71 In present case, the Storm

    66 Moot Scenario, p 20. 67 Mediterranean Salvage & Towage Ltd v Seamar Trading & Commerce Inc [2009] EWCA Civ 531. 68 Kodros Shipping Inc. v Empresa Cubana de Fletes (No. 2) [1983] 1 A.C. 736. 69 The Charterparty, Cl 1. 70 The Thekos SMA 2405 (1987) (van Gelder, Boulalas, Mavriks, Nelson, Nichols). 71 The Thekos SMA 2405 (1987) (van Gelder, Boulalas, Mavriks, Nelson, Nichols).

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    24 | P a g e

    rendered Dillamond unsafe,72 resulting in the eventual damage suffered by the Ship when

    it had to anchor outside Dillamond. As such, the Respondent submits that the Claimant

    breached its implied warranty to nominate a safe port.

    59. Given that safety includes the prospective safety of the port, and not just during the period

    of nomination, the Claimant breached its implied warranty to nominate a safe port, and is

    thus liable for the damage suffered by the Ship.

    B. The Respondent was not negligent either in anchoring the Ship or in the way it anchored

    60. The Respondent was not negligent in anchoring the Ship when waiting, or in the way it

    anchored. The chain of causation was not broken, and the Claimant's breach in nominating

    an unsafe port remains the proximate cause of the damage suffered by the Ship.

    61. The Respondent was instructed to wait at the area outside the port, along with other ships,

    while Dillamond was closed due to the Storm.73 It was reasonable for the Respondent to

    anchor the ship to avoid the Storm as the crew did not expect the Storm to reach them

    where they anchored.74 Therefore, the facts and sequence of events suggested that the

    Respondent has exercised all reasonable care in the circumstances, and was not negligent

    in anchoring the Ship. The act and place of anchoring were well considered by the

    Respondent to be safe.

    62. Therefore, the Respondent was not negligent in anchoring the Ship, and it did not break

    the chain of causation.

    C. The damage was not caused by the Respondent’s negligence when cutting the anchor

    63. The Respondent also submits that the eventual damage suffered by the ship was not due to

    the negligence of the Respondent when removing the anchor.

    72 Moot Scenario, p 21. 73 Moot Scenario, p 20. 74 Moot Scenario, p 20.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    25 | P a g e

    64. The Storm reached the Ship while it was anchored, and the Storm was much heavier than

    it was at land.75 The crew had to cut the anchor to minimise damage to the hull. The facts

    strongly indicated that the crew were constrained to act the way they did due to the Storm

    and conditions that were unexpected and beyond their control. Therefore, the damage to

    the Ship was not due to any inadvertence or negligence of the Respondent.

    65. Given the above, the Respondent is not liable for the damage to the Ship. The damage

    suffered by the Ship was due to the necessary act of anchoring outside the unsafe port

    nominated by the Claimant. The Respondent was not negligent either in anchoring the Ship

    or in the way it anchored. The Claimant is thus liable for the damage to the Ship as the

    nomination of the unsafe port was the proximate cause of damage to the Ship.

    V. The Claimant is liable for demurrage

    66. The Respondent is claiming US$100,000 in demurrage as (A) the laytime commenced

    when the vessel arrived at the waiting area and (B) laytime exceptions as stipulated in

    Clause 8(e) do not apply.

    A. Laytime commenced when the vessel arrived at waiting area

    (1) Vessel arrived at writing area at 7am on 29 July 2017

    67. Clause 8(c)(ii) of Charterparty states that laytime is calculated from when the Ship arrives

    at the discharge port until all cargo has been discharged.76 The Ship arrived at the waiting

    area at 7am on 29 July 2017.77 It is trite law that the waiting area is considered as part of

    the port. It is trite law that the port area includes the usual places where ships wait for their

    turn to berth.78 In the present case, the Ship was instructed by the port to wait at the waiting

    75 Moot Scenario, p 20. 76 The Charterparty, Cl 8(c)(ii). 77 Moot Scenario, p 20. 78 Oldendorff (EL) & Co GmbH v. Tradax Export SA (The Johanna Oldendorff) [1973] 2 Lloyd’s Rep 285, at p

    291. See also Charterparty Laytime Definitions 1980 in John Schofield, Laytime and Demurrage (6th Ed.,

    2011).

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    26 | P a g e

    area, along with the other ships waiting for a berth.79 As such, the Ship should be

    considered as an “arrived ship” when it reached the waiting area.

    (2) “WWD” includes Saturdays

    68. A WWD is defined as a type of working day which the weather allows the particular ship

    in question to load or discharge the cargo.80 Although 29 July 2017 is a Saturday, it is well-

    established that WWD includes Saturdays provided that the weather permits work.81 In the

    present case, the storm only lasted throughout Friday night and the weather was clear on

    Saturday.82 This is obvious from the fact that (i) the discharging operation occurred on

    Saturday and (ii) many other vessels conducted their operations at the port as well.83 29

    July 2017 should thus be considered as a WWD under clause 8(c)(ii) of the Charterparty.

    B. The exceptions to laytime as stipulated in Clause 8(e) do not apply

    69. The Respondent submits that the exceptions to laytime as stated in Clause 8(e) do not apply

    to the facts of the present case. This is because, on a literal interpretation of the clause, it

    is only applicable to exempt “time occupied in shifting ports or berths” from being

    calculated within laytime.84 In the present case, the laytime ran whilst the Ship was waiting

    for its turn outside the port, which does not fall within the exception. As such, Clause 8(e)

    cannot be invoked in the present case.

    70. Furthermore, Clause 8(e) only exempts the period of delay caused by the Storm from being

    counted as laytime.85 The Ship’s travelling time from the waiting area to the berth is thus

    not exempted by Clause 8(e). In the present case, the Ship started to make its way into the

    79 Moot Scenario, p 20. 80 Aldebaran Compania Maritima SA v Aussenhandel AG (The Darrah) [1977] AC 157 (HL). See also Freedom

    Maritime Corporation v International Bulk Carriers SA and another (The Khian Captain) [1985] 2 Lloyd’s Rep

    212. 81 Reardon Smith Line Ltd v Ministry of Agriculture, Fisheries and Food [1963] 1 Lloyd’s Rep. 12, at p. 32. 82 Moot Scenario, p 21. 83 Moot Scenario, p 25. 84 The Charterparty, Cl 8(e). 85 The Charterparty, Cl 8(e).

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    27 | P a g e

    berth at around 7am on 29 July 2017.86 Laytime should have thus started to accrue from

    that moment onwards.

    C. Calculation of laytime and demurrage

    71. Clause 8(c)(ii) of the Charterparty provided for the laytime to be 0.5 WWD.87 Since

    laytime commenced at 7am on 29 July 2017, laytime would expire 12 hours later, at 7pm

    on 29 July 2017. The cargo was only discharged at 12.02am on 30 July 2017.88 As such,

    laytime was exceeded by 5 hours. Since the agreed demurrage rate was US$20,000/hour89,

    the total demurrage is US$100,000.

    VI. The Claimant is liable for the use of electronic access systems at Dillamond

    72. The Claimant is liable to compensate the Respondent USD$10,000 for the use of electronic

    access systems (“EAS”) at Dillamond because the Claimant failed to take delivery of the

    cargo upon discharge.90 Clause 11 of the Charterparty allows the Respondent to discharge

    at a usual berth in Dillamond should the Claimant’s agents fail to take delivery.91 Since

    the Claimant’s agents were not available, the only reasonable cause of action for the

    Respondent was to offload the cargo and store it in the port’s warehouses. As the port uses

    an EAS for its warehouses, the incurrence of such a cost was inevitable and hence

    reasonable.92

    86 Moot Scenario, p 20. 87 The Charterparty, Cl 8(c)(ii). 88 Moot Scenario, p 23. 89 The Charterparty, Cl 9. 90 Moot Scenario, p 24. 91 The Charterparty, Cl 11. 92 Moot Scenario, p 23.

  • Team 22 Memorandum for Respondent

    ___________________________________________________________________________

    28 | P a g e

    PRAYER FOR RELIEF

    For the reasons set out above, the Respondent seeks the following orders and declarations:

    a. A declaration that the Tribunal has no jurisdiction to determine the Claimant’s claim

    for damages;

    b. A declaration that the Claimant is not entitled to any maritime lien over the Ship

    c. A declaration that the Respondent is not liable for the Claimant’s claims due to the

    application of the Force Majeure clause;

    d. An order that the Claimant pays the Respondent freight in the amount of USD$500,000;

    e. An order that the Claimant pays the Respondent the agency fees at Spectre in the

    amount of USD$75,000;

    f. An order that the Claimant pays the Respondent the agency fees at Dillamond in the

    amount of USD$50,000;

    g. An order that the Claimant pays the Respondent the cost of repairs to the Ship in the

    amount of USD$875,000;

    h. An order that the Claimant pays the Respondent demurrage in the amount of

    USD$100,000;

    i. An order that the Claimant pays the Respondent the fees for the use of electronic access

    systems in Dillamond in the amount of USD$10,000; and

    j. An order for costs.