simplifiying cost and schedule risk analysis with acumen risk
DESCRIPTION
Schedule risk analysis doesn’t have to be complicated. In this webinar learn how Acumen Risk™ uses a more intuitive approach to evaluating risk to achieve truly integrated cost and schedule risk analysis.TRANSCRIPT
![Page 1: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/1.jpg)
Dr. Dan Patterson PMP, Acumen CEO Simplifying Risk Analysis with
Acumen Risk
![Page 2: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/2.jpg)
//
// Acumen
! Project Management Software ◦ Providing insight into project challenges
◦ Improving planning accuracy & reliability
! Core Concepts: ◦ Project success requires a sound plan
◦ Forecast accuracy requires risk consideration
! Recognition: ◦ Planning Innovation of the Year 2012
◦ Inc. 500 Fastest Growing Company
! Legacy ◦ 25 years of thought-leadership
◦ Trusted by Fortune 500 & Industry Leaders
Anadarko
CH2M Hill
Chevron
ConocoPhillips
Constellation Energy
DCMA
DTE Energy
Duke Energy
Enbridge
Fluor
General Dynamics
Hess
Hill International
Jacobs
KBR
Marathon
NASA
Newmont Mining
Repsol
SAIC
Shaw
Shell
URS
Proven Project Analytics
October 11, 2012 2
![Page 3: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/3.jpg)
//
//
Build Schedule Basis
Acumen Fuse®: Project Diagnostics
Acumen Risk™: Risk Analysis & Register
Acumen 360™: Project Optimization
Team Validation and Buy In
S1 // Schedule Basis
S2 // Critiqued
S3 // Risk-Adjusted
S4 // Optimized
S5 // Team Approved
Acumen Fuse Diagnostics ! Improved Schedule Quality
Acumen 360 Scenario Generation ! Acceleration/Deceleration
Acumen Risk Risk Analysis ! Simplified Cost/Schedule
Acumen Software Summary
October 11, 2012 3
![Page 4: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/4.jpg)
//
//
Why Perform Risk Analysis?
! Scheduling ◦ Science behind forecasting project completion
◦ Doesn’t account for scope uncertainty, unknowns
! Risk Analysis ◦ Gain true insight into schedule achievability
◦ Pinpoints risk hotspots that will cause delay
◦ Structured approach to reducing risk exposure
October 11, 2012 4
![Page 5: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/5.jpg)
//
//
! Manual summary schedule
! Complex data loading
! Abstract & highly statistical
! Error-prone/misleading reporting
Legacy Risk Tools Shortcomings
October 11, 2012 5
Requires a statistician
![Page 6: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/6.jpg)
//
//
! Graphical data loading ! Uses native schedule
! Meaningful context
! Very fast analysis
! Intuitive reporting
! Insightful metrics
The Acumen Risk™ Approach Risk Reengineered…
October 11, 2012 6
Designed for collaborative project risk workshops
![Page 7: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/7.jpg)
// Schedule Impact on Cost Risk Cost Risk Distribution
$90K $130K $100K
Uncertainty
Schedule Risk Distribution
P0 280d (93%)
P100 360d (120%)
Schedule Impact on Cost Risk Distribution
$90K $130K $100K
Uncertainty
Deterministic: 300d
$84K $156K
![Page 8: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/8.jpg)
//
//
! Create new or Import
! Cost & Schedule Risks
! Pre & Post Mitigated
! Custom Templates ◦ Auto-Calibrate matrix
◦ Absolute/relative impacts
! Map to Schedule ◦ Activity-based mapping
Project Risk Register Tracking Risk Events
October 11, 2012 8
![Page 9: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/9.jpg)
//
//
! P-Dates ◦ “I’m 50% confident I will
finish on…”
! Contingency ◦ “How much more/less
time do I need to finish by…?”
! Deterministic Confidence Level ◦ “How realistic is my
planned finish date?”
Risk Exposure Histogram
October 11, 2012 9
P- Dates
Contingency
Deterministic
![Page 10: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/10.jpg)
//
//
! Risk Drivers: ◦ High-risk activities
◦ Most impactful events
! Contribution Factor™ ◦ Uncertainty contribution
◦ Logic contribution
◦ Risk Event contribution
Risk Drivers Tornados
October 11, 2012 10
Total Contribution
Uncertainty/Logic/ Risk Event
Contribution
Differentiate Between Risk Events
![Page 11: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/11.jpg)
//
//
! Compare scenarios in a single workbook: ◦ Turn on or off risks
◦ Benefit of mitigation
◦ Uncertainty vs. Risk Events
◦ Schedule A vs. Schedule B
◦ Impact of schedule delay on cost risk
Risk Comparison Distribution Curves
October 11, 2012 11
Benefit of Mitigation
![Page 12: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/12.jpg)
Acumen Risk™ Demonstration
![Page 13: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/13.jpg)
//
//
Top of bar: Sanctioned Target Completion Date
Vertical Line: Forecasted Date Range
Diamond: Actual/Final Completion Date
Acumen Forecast Accuracy
October 11, 2012 13
5 – May -12
23–Dec-11
6-Jun-11
18-Nov-10
2-May-10
14-Oct-09
28-Mar-09
![Page 14: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/14.jpg)
//
//
Integration ! Primavera:
◦ P6 (XER, XML, Web Services/P6 R8)
◦ P3
◦ Risk Analysis
! Microsoft: ◦ Project
◦ Project Server
◦ Excel
Licensing: ! Stand alone / Named user
! Concurrent / Multi user
! Citrix based
Training ! Risk 101 & Acumen Risk
! Online and Private on-site
Additional Information
October 11, 2012 14
![Page 15: Simplifiying cost and schedule risk analysis with acumen risk](https://reader034.vdocuments.site/reader034/viewer/2022051412/5487b27d5906b5c90c8b4616/html5/thumbnails/15.jpg)
More information: White papers: www.projectacumen.com Software Trial: www.projectacumen.com/trial Twitter: @projectacumen Email: [email protected]