Simplified Configuration Management and Qualification Testing for

CubeSats

Keith Mashburn

Space Science and Engineering LaboratoryMontana State University

August 11, 2008

1

Page 2: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Agenda

• Overview of Configuration Management

• Example Configuration Management System

• Overview of CubeSat Qualification Testing

• Example CubeSat Qualification Program

Page 3: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Overview of Configuration Management

• Configuration Management (CM) is the process of organizing and maintaining engineering data

• Components of a simple Configuration Management System (CMS)

Document Control

Inventory Management

Manufacturing Control

Flight Assurance

• Dedicated staff members devoted to CMS activities is a must

Page 4: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

CMS Implementation

CMS

DOCUMENT CONTROL

PARTS INVENTORYCONTROL

MANUFACTURINGCONTROL

FLIGHT ASSURANCE

Page 5: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Document Control

• Each engineering document issued a sequential number

• All documents undergo a peer review process to ensure quality

• Each document contains a coverpage for review signatures and a revision log to track changes

• After all approval signatures are obtained the document is formally released

• Changes to released documents tracked using Engineering Change Order (ECO)

Page 6: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

SSEL Document Control

• Released documents can be accessed using an online database • All document originals are locked in a secure filing cabinet

Page 7: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Parts Inventory Control

• Verify parts meet outgassing requirements

• All parts purchased from commercial vendors

• Maintain detailed records of all flight parts in stock

• All electrical parts stored in ESD safe containers

• All flight parts stored in locked cabinets

Page 8: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

SSEL Parts Inventory Control

Page 9: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Manufacturing Control

• Manufacturing Planning should start early in the design phase of the mission

• Inspection and other hold points should be identified early in planning stage

• Identify the necessary fabrication, assembly, and testing procedures for all flight hardware and related ground support equipment (GSE)

• Personnel involved in flight fabrication and testing should be trained in the application area (ESD, Soldering, Polymerics, etc.)

• At least two persons are required during all flight hardware operations

Page 10: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

SSEL Manufacturing ControlMANUFACTURING

CONTROL

MPS Acceptance

Review

Prepare MPS Package

Obtain parts kit from

inventory control

Nonconformances that occur during testing will be tracked with Nonconformance Reports (NCR)

Manufacture assembly per

MPS

Workmanship Inspection

Perform Performance

Testing

10

Page 11: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Flight Assurance

• Provide oversight during all phases of the integration and testprogram to ensure the work is performed according to specifications

• Perform workmanship inspections during fabrication and assembly activities

• Certify equipment/GSE setup prior to execution of all qualification tests

• Maintain detailed records of all non-conformances that occur during I&T

• Verify test records and data are adequate to meet test requirements

Page 12: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

SSEL Flight Assurance

Page 13: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

CubeSat Qualification Testing

Page 14: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Overview of CubeSat Qualification Testing

• Qualification testing ensures that design is acceptable and that the satellite will function in the expected environments

• Qualification begins with the completion of the flight hardware and software and ends with the satellite ready for shipment to CalPoly for acceptance testing

• Qualification testing consists of a series of functional and performance tests, followed by a sequence of environmental exposures

• The requirements for qualification testing are derived from a variety of sources including the individual mission requirements, the CubeSat

program requirements, and the designated launch vehicle requirements

Page 15: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Example of CubeSat Qualification Program (1 of 3)

Page 16: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Example of CubeSat Qualification Program (2 of 3)

SpacecraftBus

Integration

Payload and Flight Battery

IntegrationCPT #1

CPT #2(Pre-

Environmental)

S/C BusBake-Out

EMITesting

VibrationTesting

Thermal/VacuumTesting

FSW 1.0

FSW 1.1

Environmental Testing

Software Development/Validation on EDU Hardware

CPT #3(Post-

Environmental)

Mission OpsTesting

Deliver toCalPoly forAcceptance

Testing

FSW 1.2

Stake and Coat

Page 17: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Example of CubeSat Qualification Program (3 of 3)

Page 18: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

CubeSat Environmental Testing (1 of 2)

Vibration Test• Perform low-level sine test to confirm modes

• Perform random vibration to qualification levels

• Perform low frequency sine vibe, only if required

Thermal/Vacuum Test• Operate in thermal/vacuum environment to verify system performance

• Calibrate on-board temperature sensors

• Perform mission simulations

EMI • Operate system on nominal RF link and verify operational integrity (Self-Compatibility)

• Perform conductive/radiated emissions and susceptibility measurements, only if required

Post-Environmental Performance

Testing

Page 19: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

CubeSat Environmental Testing(2 of 2)

Page 20: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Pack and Ship• Securely pack satellite and GSE for shipment to CalPoly

• Transport CubeSat via commercial air carrier

CubeSat

Structural Requirements Confirmation

• Cal-Poly to verify conformance to CubeSat Standard

CubeSat Delivery and Acceptance (1of 2)

Delivery • Post-shipment inspection of CubeSat and GSE

• Post-shipment performance test

Acceptance Testing

• Cal-Poly to perform vibration testing to acceptance levels on integrated P-POD

Final Flight Preparation

• Cal-Poly perform final battery charging

• Cal-Poly pull Remove Before Flight (RBF) Pin

P-POD Integration• Cal-Poly to integrate CubeSats into P-POD

Page 21: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

CubeSat Delivery and Acceptance (2 of 2)

Page 22: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Acknowledgements I would like to thank Ms. Celena Byers

for all of her hard work on the implementation and maintenance of the

SSEL Configuration Management System.

Page 23: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Contact Info

Keith Mashburn – I&T Team Lead:

[email protected]

Celena Byers – SSEL Configuration Management Specialist:[email protected]

Page 24: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Backup Slides

Page 25: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Processor

Software

Storage

PeripheralI/F

CDH PCB Integration and Test

Perform PCB Assembly

Perform workmanship inspection

Electrical interface testing

Initial Power-up

Oscillator measurement or calibration

Watch dog functional check

Memory read/write verification tests

Verify S/W loading capability

Perform initial checks of the peripheral I/F

CDH

Page 26: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

BCR

Solar Array

VoltageRegulators

Digital I/FBoard

EPS PCB Integration and Test

Perform PCB Assembly

Perform Workmanship Inspection

Electrical interface testing

Initial Power-up

Voltage regulator functional testing

Safety inhibit functional testing

EPS

SafetyInhibits

Page 27: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Magnet

DampeningRod

ACS PCB Integration/Verification

Perform PCB Assembly

Perform Workmanship Inspection

Electrical interface testing

Battery charge/discharge testing

ACS

Page 28: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Receiver

Amplifier

COMM PCB Integration/Verification

Perform PCB Assembly

Perform Workmanship Inspection

Electrical interface testing

Initial Power-up

Transmitter/Amplifier functional testing

Receiver functional testing

RF link test and power measurements

Watchdog functional testing

COMM

Transmitter

TNC

Receiver

Amplifier

Transmitter

Antennas

Page 29: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Particle Detector

Payload PCB Integration and Test

Perform PCB Assembly

Perform Workmanship Inspection

Electrical interface testing

Initial Power-up

Preamp noise measurements

I2C Interface functional

Payload Plateau Curves

Payload

Page 30: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Backup Slide: System CPT Plan

Page 31: Simplified Configuration Management and Qualification ...mstl.atl.calpoly.edu/~workshop/archive/2008/Summer... · Manufacturing Control •Manufacturing Planning should start early

Backup Slide: System Environmental Test Plan