4/13/2017
2
Agenda Item 8A
Wastewater Conveyance System and Treatment Plant Reliability Project
Final Environmental Impact Report
Project Overview Map
4/13/2017
3
SVCW EIR Process
Public scoping and NOP (30 days, Feb 19‐March 23)
Complete technical analyses Prepare Administrative Draft EIR
Draft EIR Public Review (45 Days, Nov 29‐Jan 13)
Comments received from public
Respond to Comments/Prepare Final EIR
FEIR circulated (10 days, Mar 31‐Apr10)
Public Comment/Certify EIR/Approve Project April 13, 2017
File Notice of Determination
Main Purposes of CEQA
• Provide information to decision makers and the public regarding environmental impacts of projects
• Identify ways to mitigate or reduce those impacts
• Evaluate project alternatives to avoid impacts
• Facilitate public participation
• Foster public agency coordination
4/13/2017
4
General Contents of an EIR
• Project Description (What, Where, When, How, Why)
• Environmental Setting (on and around the project area)
• Significant Environmental Effects
• Mitigation Measures
• Unavoidable Significant Adverse Effects
• Alternatives (design, construction, operation, location, etc.)
Environmental Analysis
• Hazards/Hazardous Materials
• Visual/Aesthetics
• Utilities/Services
• Cultural Resources
• Growth‐Inducing Impacts
• Cumulative Impacts
• Global Climate Change
• Land Use
• Geology and Soils
• Drainage and WQ
• Biological Resources
• Traffic/Circulation
• Noise and Vibration
• Air Quality
Resource Categories Analyzed:
4/13/2017
5
EIR Alternatives
• SVCW considered 140 potential design alternatives
• 15 alternatives were fully vetted, preferred project selected
• EIR Alternatives:
– avoid or reduce impacts while achieving project objectives
• No Project Alternative is mandatory
• Location Alternatives
• Design Alternative
• Reduced Scale/Components Alternative
EIR Findings
• The proposed project would not result in any significant and unavoidable impacts.
• Construction would result in short‐term significant impacts able to be mitigated to a less than significant level.
• Ongoing operations at WWTP and the pump stations would have noise impacts requiring mitigation
4/13/2017
6
Anticipated Construction Periods
Gravity Pipeline 2018 to 2023
Front of Plant Facilities 2017 to 2022
Pump Stations 2021 to 2023
Future Nutrient Removal 2025+
Requested Action Items
i. Certify Final EIR–Commission certifies that the EIR was prepared in accordance with CEQA requirements
ii. Adopt Resolution:– Findings of Fact
–Mitigation Monitoring and Reporting Program
–Approving the Project
4/13/2017
7
Next Steps
File Notice of Determination w/County– Begins 30‐day statute of limitations on challenges
Consider Approving 2 Components of Project– Agenda Item 8B (to follow)
Agenda Item 8ARecommendation
i) Certify Final EIR
ii) Adopt Resolution:
Findings of Fact
MMRP
Approve Project
4/13/2017
8
Agenda Item 8BGravity Pipeline & Front‐of‐Plant
Progressive Design Build Request for Qualifications
Gravity Pipeline Project Component
4/13/2017
9
Front‐of‐Plant Project Component
Flow Chart for Progressive Design‐Build
Engineering Owner’s Advisor
Construction Manager (CM)
SVCW (Owner)
SVCW issues solicitations for design-
build team
SVCW selects design-build team
Design-build team completes design and
constructs project
• Qualifications Step:• SVCW Issues Request for Qualifications (Procurement Documents)
• Shortlists D‐B Teams, then
• Proposal Step:• Issues Request for Proposals (includes drawings, specifications, technical memoranda, contract language, etc)
*From January 2017 Commission Meeting Presentation
*
4/13/2017
10
i. Approve Request for Qualifications Procurement Documents
ii. Authorize Manager to issue Request for Qualifications from Design‐Build Entities
Agenda Item 8BRecommendation
Agenda Item 8CGravity Pipeline & Front‐of‐Plant
Task Order Authorizations
4/13/2017
11
Flow Chart for Progressive Design‐Build
Engineering Owner’s Advisor
Construction Manager (CM)
SVCW (Owner)
SVCW issues solicitations for design-
build team
SVCW selects design-build team
Design-build team completes design and
constructs project
Flow Chart for Progressive Design‐Build
Engineering Owner’s Advisor
Construction Manager (CM)
SVCW issues solicitations for design-
build team
SVCW selects design-build team
Design-build team completes design and
constructs project
SVCW (Owner)
4/13/2017
12
Owner’s Project Team
Engineering Owner’s Advisor
Construction Manager (CM)
SVCW Authority Engineer
Construction Law–Hanson Bridgett
O&M – WET
Finance – SVCW CFO
Design-Builder
SVCW Commission
SVCW Manager
SVCW Project Manager
Policy Level
Project Level
Owner’s Team
SCADA – Tech Edge
Legal – SVCW Counsel
Owner’s Project Team
Engineering Owner’s Advisor
Construction Manager (CM)
SVCW Authority Engineer
Construction Law –Hanson Bridgett
O&M – WET
Finance – SVCW CFO
Design-Builder
SVCW Commission
SVCW Manager
SVCW Project Manager
Policy Level
Project Level
Owner’s Team
SCADA – Tech Edge
Legal – SVCW Counsel
4/13/2017
13
Agenda Item 8COwner’s Design‐Build Team
• Successful Projects have Excellent Project Teams
• Previous Actions:
– Engineering Owner’s Advisors
– Re‐assigning SVCW Staff
– Dedication of SVCW Authority Engineer & CFO
• Today’s Actions:
– Operations Focus via Water Environmental Technical
– Automation Focus via Technical Edge
– Legal Focus via Hanson Bridgett
i. Approve Task Order for Operational Consulting Services – WET ‐ $2.16M
ii. Approve Task Order for Automation Consulting Services – Technical Edge ‐$2.16M
iii. Approve Task Order for Legal Design‐Build Services – Hanson Bridgett ‐ $460k
Agenda Item 8CRecommendation
4/13/2017
14
Agenda Item 8DFront‐of‐Plant
Geotechnical and Site Civil ServicesTask Order Amendment
Front‐of‐Plant Construction & Staging Area
4/13/2017
15
Front‐of‐Plant Soil Stabilization
SOIL STABILIZATION
• 7% Lime Treatment to Upper 18” of Existing Soil across Entire 10 Acre Area
• Ready for Design‐Builder Mobilization
4/13/2017
16
Front‐of‐Plant Site Civil
POTENTIAL SOUNDWALLALONG RADIO ROAD
NEW ROADWAY
NEW STAFF PARKING
NEW STAFF ENTRANCE
• Relocates Staff Entrance and Parking
• Provides Site Drainage
• Lighting, Electrical & Signal Conduits
• Soundwall, if needed
Agenda Item 8DFront‐of‐Plant Site Work
Freyer & Laureta Design Original – Lime Stabilization onlyAmendment – Prep for Future Construction
Anticipated Bid Date:May 2017
Anticipated Project Award:June Commission meeting
4/13/2017
17
Approve Task Order Amendment for Front‐of‐Plant Soil Stabilization and Site Civil – Freyer & Laureta ‐ $46,740
Agenda Item 8DRecommendation
Agenda Item 8EProposed 2017‐18 Budget
Workshop #2
4/13/2017
18
Budget Changes Since March
Description
Proposed
2017‐18
Budget
MARCH
Revised
2017‐18
Budget
APRIL
$
Increase/
(Decrease) Comments
Gross Operating Expenses 23,868,381$ 23,912,933$ 44,552$ Incorporated compensation study
Less Miscellaneous Revenue (621,608) (621,608) ‐
Net Operating Expenses 23,246,773$ 23,291,325$ 44,552$
Revenue‐Funded Capital 1,222,576 1,546,000 323,424 Updated cost of valves at pump stations and FEF
Reserve Designations 2,130,895 2,030,298 (100,597) Recognized investment earnings on Operating Reserve
Total before Debt Service 26,600,244$ 26,867,623$ 267,379$
Debt Service Payments 12,347,586$ 12,347,586$ ‐$
Total Member Contributions 38,947,831$ 39,215,209$ 267,379$
Budget‐to‐Budget Overview• $742 thousand (3.3%) increase in Net Oper. Expense
• $16 thousand increase in revenue‐funded capital
• $245 thousand increase in Cash Reserve designations
• $917 thousand decrease in Debt Service PaymentsYear‐over‐year Budgeted Member Entity Contributions
Description
2016‐17
Adopted
Budget
2017‐18
Proposed
Budget
$
Increase/
(Decrease)
%
Increase/
(Decrease)
Gross Operating Expenses 22,975,931$ 23,912,933$ 937,002$ 4.1%
Less Miscellaneous Revenue (426,829) (621,608) 194,779 45.6%
Net Operating Expenses 22,549,103$ 23,291,325$ 742,222$ 3.3%
Revenue‐Funded Capital 1,530,039 1,546,000 15,961 1.0%
Reserve Designations 1,785,302 2,030,298 244,995 13.7%
Total Contributions before Debt Service 25,864,444$ 26,867,623$ 1,003,179$ 3.9%
Debt Service, Participating members 13,265,210$ 12,347,586$ (917,624)$ (6.9%)
Total Member Contributions 39,129,654$ 39,215,209$ 85,555$ 0.2%
4/13/2017
19
Revenue‐Funded CapitalProposed 2017‐18 Revenue‐Funded Capital Expenditures
Description
One‐time
Cost
Force Main Valves
V3 and V4 ‐ Valves on 48" FM 300,000$
Treatment Plant Equipment
Front Loader for Sludge Beds 185,000$
Sludge Bed Covers for stockpile & Equipment 125,000
Biosolids Transfer Truck 110,000
Fleet Replacement 50,000
Digester Sensors & Flowmeters on mix pumps 30,000
Electric cart 21,000
Forklift Replacement, Operations 35,000
Subtotal 556,000$
Pump Station Valves & Equipment
Menlo Park Pump Station Inlet Gate Replacement 110,000$
Pump Station Valves ‐ San Carlos PS 270,000
Valves for Belmont Pump Station 92,000
Menlo Park Pump Station Nitrate dosing system 45,000
FEF Control Valve 50,000
Subtotal 567,000$
Technology
I.T. Data Storage Equipment 73,000$
Blades for VM servers and Controller Cards 50,000
Subtotal 123,000$
GRAND TOTAL, REVENUE‐FUNDED CAPITAL 1,546,000$
Operating Budget Contributions
38
2017‐18 Budget Revenue Allocation to Member Agencies ‐ Proposed
Description Belmont
Redwood
City San Carlos
West Bay
San District TOTAL
Allocation Factors
Flow 13.18% 46.53% 13.55% 26.74% 100%
Biochemical Oxygen Demand (BOD) 12.42% 46.31% 12.36% 28.91% 100%
Suspended Solids (SS) 12.57% 46.22% 12.13% 29.08% 100%
Weightings
Operating Expenditures Flow BOD SS
Operations 26.5% 33.5% 40.0% 1,113,646$ 4,068,775$ 1,105,035$ 2,494,269$ 8,781,725$
Maintenance 26.5% 33.5% 40.0% 772,429 2,822,120 766,457 1,730,036 6,091,043
Laboratory 26.5% 33.5% 40.0% 218,344 797,732 216,655 489,031 1,721,762
Environmental Services 26.5% 33.5% 40.0% 138,975 507,754 137,900 311,267 1,095,896
Engineering 26.5% 33.5% 40.0% 70,303 256,857 69,760 157,460 554,380
Safety 100.0% 0.0% 0.0% 50,277 177,495 51,688 102,003 381,463
Information Services 26.5% 33.5% 40.0% 215,216 786,306 213,552 482,027 1,697,101
Administrative Services 100.0% 0.0% 0.0% 473,104 1,670,223 486,386 959,849 3,589,562
Subtotal 3,052,294$ 11,087,263$ 3,047,434$ 6,725,942$ 23,912,933$
Subtract Miscellaneous Income 26.5% 33.5% 40.0% 78,829$ 288,005$ 78,219$ 176,555$ 621,608$
2017‐18 Net Operating Revenue Required 2,973,466$ 10,799,257$ 2,969,215$ 6,549,387$ 23,291,325$
2016‐17 Net Operating Revenue Required 3,014,719 10,019,055 3,289,247 6,226,082 22,549,103
$ Increase / (Decrease) (41,253) 780,202 (320,032) 323,305 742,222
% Increase / (Decrease) (1.4%) 7.8% (9.7%) 5.2% 3.3%
4/13/2017
20
Flow and Loading Trends
Description Belmont
Redwood
City
San
Carlos
West
Bay Total
Flow
2012 thru 2014 13.61% 44.77% 16.26% 25.36% 100.00%
2013 thru 2015 13.48% 45.64% 14.31% 26.57% 100.00%
2014 thru 2016 13.18% 46.53% 13.55% 26.74% 100.00%
Biochemical Oxygen Demand
2012 thru 2014 13.51% 42.77% 16.53% 27.19% 100.00%
2013 thru 2015 12.81% 44.79% 14.49% 27.91% 100.00%
2014 thru 2016 12.42% 46.31% 12.36% 28.91% 100.00%
Suspended Solids
2012 thru 2014 14.83% 40.17% 17.47% 27.53% 100.00%
2013 thru 2015 13.71% 42.73% 14.99% 28.57% 100.00%
2014 thru 2016 12.57% 46.22% 12.13% 29.08% 100.00%
Flow & Loading Sensitivity
$3.2
$9.9
$3.9
$6.2
$3.1
$10.4
$3.4
$6.4
$3.0
$10.8
$3.0
$6.5
$‐
$2.0
$4.0
$6.0
$8.0
$10.0
$12.0
Belmont RedwoodCity
San Carlos West BaySan District
Allocated 2017‐18 Operating Budget ‐ Flow & Loading Sensitivity($ Millions)
2014 Factors (three year avg) 2015 Factors (three year avg) 2016 Factors (three year avg)
4/13/2017
21
Budget vs. Long Range Financial Plan
• Only significant difference from LRFP is the reimbursement of reserves due to emergency repairs
Year‐over‐year Budgeted Member Entity Contributions
Description
Jan 2017
Long Range
Fin. Plan
2017‐18
Proposed
Budget
$
Increase/
(Decrease)
%
Increase/
(Decrease)
Gross Operating Expenses 23,806,537$ 23,912,933$ 106,396$ 0.4%
Less Miscellaneous Revenue (435,427) (621,608) 186,181 42.8%
Net Operating Expenses 23,371,110$ 23,291,325$ (79,785)$ (0.3%)
Revenue‐Funded Capital 1,500,000 1,546,000 46,000 3.1%
Reserve Designations 1,148,947 2,030,298 881,351 76.7%
Total Contributions before Debt Service 26,020,057$ 26,867,623$ 847,566$ 3.3%
Debt Service, Participating members 12,347,586$ 12,347,586$ ‐$ 0.0%
Total Member Contributions 38,367,643$ 39,215,209$ 847,566$ 2.2%
Calendar
• March 23rd – Review and Direction
• April 13th – Adoption