sidewalk and bus stop design presented by: dan feinblum 5/9/01 ence 667

15
Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Upload: buddy-anderson

Post on 04-Jan-2016

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Sidewalk and Bus Stop Design

Presented by: Dan Feinblum

5/9/01

ENCE 667

Page 2: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Project Overview

• Consultants Working For Delaware Department of Transportation (DelDOT)

• Work in Churchmans Crossing Area

• 3-5 Years for All Design and Construction

• Design New Sidewalks and Bus Stops

• Improve Existing Conditions

Page 3: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Project Objectives

• Improve Pedestrian Mobility

• Promote a Multi-modal Transportation System

• Improve Traffic Conditions

• Complete and Connect Existing Networks

• Improve Drainage

• Satisfy Americans With Disabilities Act (ADA)

Page 4: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Performance Measures

• Critical Path Method (CPM)

• Project Crashing

• Subcritical Path Analysis

• Lead-Lag (Precedence) Relationships

Page 5: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Develop Base Schedule

• Determine Activities and Their Characteristics

• Create Activity on Arrow Diagram

• Complete Forward and Backward Pass

• Input into Primavera Scheduling Software

• Determine Critical Path and Overall Project Duration

Page 6: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Base Schedule

Sheet 1 of 1

Weeks-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54

Determine sidewalk locations/type/curb

Establish sidewalk alignements/baselines

Right of Way CADD and coordination

Locate drainage structures

CADD initial sidewalk locations/create plan shee

Field verification of existing conditions

Prepare survey/mapping requests

Request/coordinate utility info

Determine existing drainage conditions

Prepare stormwater management waiver

CADD drainage

Drainage pipe computations

Process utility info

Submit Preliminary Plans

Develop typical sections

Finalize sidewalk alignment/locations

Signing and striping

Finalize drainage

Proposed lighting

Process Survey and Utility Information

Earthwork/quantities

Semi-Final Quantities

Submit Semi-Final Plans

Finalize Typical Section

Stakeout and construction information

Final quantities

Finalize construction cost estimate

Submit Final Plans

Check and verify quantities

Review and Address DelDOT comments

Complete all CADD work

Submit PS&E plans

Page 7: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Critical Path of Base Schedule

• Activities on Critical Path: 10, 20, 110, 270, 130, 120, 280, 290, 220, 200, 240, 300, 230, 320, 210, and 250

• Verified Project Duration of 256 Days and Critical Path in Linear Program

Page 8: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Network Diagram for Base Schedule

1 2 3

4 5

10

6

7 8

12

9

11

13

14

15

24

16

17

18

19

20

21

23

22

25

180

40 50

270

2606030

90

310

130

230

320

250

170

120

280 220

160

200

290 190 300

2402010 110

10070

80

START

END

Page 9: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Project Crashing

• Modified Linear Program of Base Schedule

• Allowed for 11 Activities to be Crashed

• Could Not Crash an Activity To Less Than 1 Day

• Used Linear Programming to Generate Cost VS. Project Duration Graph

• Minimum Duration of Project = 57 Days

Page 10: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

y = 0.5506x2 - 415.5x + 70228

R2 = 0.9984

0

10000

20000

30000

40000

50000

60000

0 50 100 150 200 250 300

Duration of Project (Days)

Co

st

($)

Cost VS. Project Duration

• 220 Days Costs $5600• 210 Days Costs $7225

Difference = $1625

Page 11: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Subcritical Path• 20% of Activities Generate 80% of Delays

• Paerto (1848-1923) Analysis

• Quantifies the Criticality of All Project Paths

• Utilizes the Following Equations:

%)100(12

2

09.01'

1 = the minimum total slack (or lag) in a network

2 = the maximum total slack in the network

= total slack for the path whose criticality is to be calculated.

Page 12: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Path Number Activities on Path TS G (%) G' (%)1 * 0 100.00 10.002 80, 70, 100 6 96.23 9.663 50, 40 12 92.45 9.324 170 20 87.42 8.875 160 33 79.25 8.136 190 103 35.22 4.177 60, 310, 260 130 18.24 2.648 180, 140 145 8.81 1.799 150 146 8.18 1.74

* Path 1 includes the following activities : 320, 300, 290, 280, 270,250, 240, 230,220, 210, 200, 20, 130, 120, 110, 10

Subcritical Path Analysis

Page 13: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Lead- Lag (Precedence) Relationships

• Utilizes CPM

• Shortens Project Duration by Allowing Activities to be Completed Simultaneously

• Implement Where Activities Could be Completed Simultaneously

• Shortened Project Duration from 256 to 224 Days (Saves 32 Days)

Example :Activity 110 can begin 5 days after activity 20 starts. Allows adequate time for initial SW & BS locations to be developed so that Right of Way can begin working

Page 14: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Modified Schedule With Lead- Lag Relationships

Sheet 1 of 1

Weeks-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53

Determine sidewalk locations/type/curb

Establish sidewalk alignements/baselines

Right of Way CADD and coordination

Locate drainage structures

CADD initial sidewalk locations/plan sheets

Field verification of existing conditions

Prepare survey/mapping requests

Request/coordinate utility info

Determine existing drainage conditions

CADD drainage

Submit Preliminary Plans

Drainage pipe computations

Finalize sidewalk alignment/locations

Develop typical sections

Signing and striping

Proposed lighting

Prepare stormwater management waiver

Earthwork/quantities

Finalize drainage

Process utility info

Semi-Final Quantities

Process Survey and Utility Information

Submit Semi-Final Plans

Finalize Typical Section

Stakeout and construction information

Final quantities

Finalize construction cost estimate

Submit Final Plans

Check and verify quantities

Review and Address DelDOT comments

Complete all CADD work

Submit PS&E plans

Page 15: Sidewalk and Bus Stop Design Presented by: Dan Feinblum 5/9/01 ENCE 667

Future Work

• More Detailed Version of Schedule

• Implement Multi-Project Scheduling

• Resource Allocation

• Probability Analysis of Activity/Project Durations

Any Questions?