SHIMLA JAL PRABANDHAN NIGAM LTD.
DETAILED PROJECT REPORT
BULK WATER SUPPLY FROM SUTLEJ RIVER
SEPTEMBER 26, 2019
AURANGABAD, MAHARASHTRA, INDIA
Areas
Water and Waste Water
Solid Waste Management
Roads and highways
Urban infrastructure
Project management
Services
Feasibility Studies
Detailed Project Report
Design & Detail Engineering
Hydraulic Modelling
Water Audit and Leak Detection Studies
Construction Supervision
Head Office “Sai Complex”
Plot No. 72, Flat No. 05, New SBH Colony, Shahanoorwadi,
Aurangabad – 431005.
SHIMLA JAL PRABANDHAN NIGAM LIMITED DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP,
Aurangabad (Maharashtra) Client Circulation P a g e | i
Contents
1. EXECUTIVE SUMMARY ........................................................................................ i
1.1 PREAMBLE: .................................................................................................................. 1
1.2 OBJECTIVE ................................................................................................................... 1
1.3 BACK GROUND OF PROJECT ..................................................................................... 2
1.4 PROJECT NEED ........................................................................................................... 2
1.5 CURRENT STATUS OF THE EXISTING WATER SUPPLY: ......................................... 3
1.6 DESIGN CONSIDERATIONS: ....................................................................................... 3
1.7 PROPOSED PROJECT IN BRIEF: ................................................................................ 4
1.8 MAIN FEATURES OF THE PROPOSED PROJECT ..................................................... 4
1.9 LOCATIONS OF SOURCE ............................................................................................ 6
1.10 LOCATIONS OF PROPOSED ALIGNMENT, SUMP AND PUMP HOUSES ................ 7
1.11 PROJECT COST ......................................................................................................... 9
2. INFORMATION OF SHIMLA CITY ...................................................................... 11
2.1 LOCATION OF SHIMLA CITY ..................................................................................... 11
2.2 LOCATION, CONNECTIVITY & DETAILS: .................................................................. 11
2.3 CLIMATE & RAINFALL: ............................................................................................... 12
2.4 DEMOGRAPHY ........................................................................................................... 12
2.5 HISTORY OF THE CITY .............................................................................................. 12
2.6 SOCIO-ECONOMIC FEATURES ................................................................................. 13
2.7 MAP OF SHIMLA PLANNING AREA ........................................................................... 13
3. POPULATION FORECASTING & WATER DEMAND......................................... 14
3.1 POPULATION .............................................................................................................. 14
3.2 LAND USE PLAN ......................................................................................................... 16
3.3 WATER DEMAND CALCULATION .............................................................................. 18
4. EXISTING WATER SUPPLY STATUS ................................................................ 21
4.1 HISTORY ..................................................................................................................... 21
4.2 EXISTING SOURCES ......................................................................................... 21
4.3 GUMMA SOURCE ............................................................................................... 22
4.4 DHALLI CATCHMENT ......................................................................................... 24
4.5 CHEROT & JAGROTI .......................................................................................... 24
4.6 CHAIR NLLAH ..................................................................................................... 24
4.7 ASHWANI KHAD ................................................................................................. 24
4.8 RIVER GIRI ......................................................................................................... 24
5. DESIGN CRITERIA ............................................................................................. 25
5.1 INTRODUCTION ......................................................................................................... 25
SHIMLA JAL PRABANDHAN NIGAM LIMITED DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP,
Aurangabad (Maharashtra) Client Circulation P a g e | ii
5.2 DESIGN PERIOD ........................................................................................................ 25
5.3 WATER DEMAND ....................................................................................................... 25
5.4 SYSTEM LOSSES ....................................................................................................... 25
5.5 PUMPING SYSTEM .................................................................................................... 26
5.6 HOURS OF SUPPLY ................................................................................................... 26
5.7 MINIMUM DIAMETER OF PIPELINE FOR RISING MAIN ........................................... 26
5.8 STORAGE ................................................................................................................... 26
i. Capacity ....................................................................................................................... 26
ii. Staging Height ............................................................................................................. 27
5.9 SURGE PROTECTION ................................................................................................ 27
5.10 METERING ................................................................................................................ 27
i. Bulk Meter:................................................................................................................... 27
ii. Domestic Water Meter ................................................................................................. 27
5.11 SYSTEM SAFETY ..................................................................................................... 28
5.12 PIPES ........................................................................................................................ 28
5.13 WATER TREATMENT PLANT ................................................................................... 28
5.14 WATER QUALITY ..................................................................................................... 29
6. PROPOSED PROJECT ....................................................................................... 30
6.1 GENERAL.................................................................................................................... 30
6.2 SOURCE CONSIDERATION: ...................................................................................... 30
6.3 GEOTECHNICAL INVESTIGATIONS: ......................................................................... 30
6.4 PRELIMINARY LAND ACQUISITION / TRANSFER REQUIREMENTS ....................... 31
6.5 AVAILABILITY OF WATER AND WATER RESERVATION ......................................... 31
6.6 HEAD WORKS: - ......................................................................................................... 32
6.7 RAW WATER RISING MAIN: - .................................................................................... 32
6.8 RAW WATER PUMPING MACHINERY: - .................................................................... 33
6.9 WATER TREATMENT PLANT: - .................................................................................. 33
6.10 PURE WATER STAGES I, II and III ........................................................................... 33
6.11 AUTOMATION ........................................................................................................... 36
6.12 EXPRESS HT FEEDER AND 20 MVA SUBSTAION ................................................. 36
6.13 200 KW SOLAR PLANT ............................................................................................ 36
6.14 COMPOUND WALL ................................................................................................... 37
7. PROJECT COST ................................................................................................. 38
7.1 RECAPITULATION SHEET ......................................................................................... 38
8. OPERATION AND MAINTENANCE .................................................................... 39
8.1 NECESSITY OF MAINTENANCE ................................................................................ 39
8.2 MAINTENANCE SCHEDULE....................................................................................... 40
SHIMLA JAL PRABANDHAN NIGAM LIMITED DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP,
Aurangabad (Maharashtra) Client Circulation P a g e | iii
8.3 ACTIVITIES IN MAINTENANCE SCHEDULE .............................................................. 40
8.4 O&M FOR THE WATER SUPPLY PROJECT .............................................................. 40
8.5 O&M FOR PUMPING STATION .................................................................................. 40
8.6 PROBLEMS IN TRANSMISSION MAINS .................................................................... 41
8.7 MAINTENANCE OF PIPELINES .................................................................................. 42
8.8 RECORDS AND REPORTS ........................................................................................ 42
8.9 REPORTS ................................................................................................................... 44
9. ENVIRONMENTAL IMPACT ASSESSMENT ...................................................... 45
9.1 NEED FOR THE EIA ................................................................................................... 45
9.2 SCOPE OF THE EIA STUDY....................................................................................... 45
9.3 ENVIRONMENTAL IMPACTS OF THE PROJECT ...................................................... 45
9.4 SITE CLEARANCE ...................................................................................................... 45
9.5 PUBLIC SAFETY ......................................................................................................... 45
9.6 ACCESS MANAGEMENT ............................................................................................ 46
9.7 STORAGE OF CONSTRUCTION MATERIALS ........................................................... 46
9.8 GOOD HOUSEKEEPING AT CONSTRUCTION SITES .............................................. 46
9.9 WATER POLLUTION ................................................................................................... 47
9.10 NOISE POLLUTION .................................................................................................. 47
9.11 AIR POLLUTION ....................................................................................................... 47
9.12 OCCUPATION SAFETY AND HEALTH ASPECTS ................................................... 48
9.13 IMPACTS FROM CONSTRUCTION CAMPS ............................................................ 48
9.14 OTHER IMPACTS ..................................................................................................... 48
10. PROJECT BENEFITS ......................................................................................... 50
SHIMLA JAL PRABANDHAN NIGAM LIMITED DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP,
Aurangabad (Maharashtra) Client Circulation P a g e | iv
List of Tables
TABLE 1.8-1 ................................................................................................................................ 4
TABLE 1.11-1 - RECAPITULATION SHEET ................................................................................ 9
TABLE 3.1-1 - POPULATION FOR LAST FIVE DECADES ....................................................... 14
TABLE 5.2-1- DESIGN STAGES ............................................................................................... 25
TABLE 5.2-2- DESIGN PERIOD ................................................................................................ 25
TABLE 5.4-1 - BRAKE UP OF LOSSES .................................................................................... 25
TABLE 5.14-1 - DESIGN PARAMETERS. ................................................................................. 29
TABLE 6.4-1 - LAND AVAILABILITY ......................................................................................... 31
TABLE 6.5-1 - WATER AVAILABILITY ...................................................................................... 31
TABLE 6.7-1- RAW WATER RISING MAIN ............................................................................... 32
TABLE 6.8-1- RAW WATER PUMPING MACHINERY .............................................................. 33
TABLE 6.9-1- WATER TREATMENT PLANT ............................................................................ 33
TABLE 6.10-1- PURE WATER RISING MAIN STAGE I ............................................................. 34
TABLE 6.10-2- PURE WATER RISING MAIN STAGE II ............................................................ 34
TABLE 6.10-3- PURE WATER RISING MAIN STAGE III ........................................................... 34
TABLE 6.10-4- PURE WATER PURE WATER PUMPING MACHINERY STAGE I.................... 35
TABLE 6.10-5- PURE WATER PURE WATER PUMPING MACHINERY STAGE II ................... 35
TABLE 6.10-6- PURE WATER PURE WATER PUMPING MACHINERY STAGE II ................... 35
TABLE 7.1-1 RECAPITULATION SHEET ................................................................................ 38
List of Figures
FIGURE 1.9-1 – LOCATION OF PROPOSED INTAKE ............................................................... 6
FIGURE 1.9-2 – LOCATION OF PROPOSED INTAKE WITH ADJACENT VILLAGE .................. 6
FIGURE 1.10-1 – ALIGNMENT FROM INTAKE TO WTP TO DEVIDHAR ................................... 7
FIGURE 1.10-2 – ALIGNMENT FROM DEVIDHAR TO DUMMI .................................................. 7
FIGURE 1.10-3 – ALIGNMENT FROM DUMMI TO SANJAULI.................................................... 8
FIGURE 2.1-1 - LOCATION OF SHIMLA CITY .......................................................................... 11
FIGURE 2.7-1 – MAP OF SHIMLA PLANNING AREA ............................................................... 13
FIGURE 4.1-1 - HISTORY OF DEVELOPMENT OF WATER SUPPLY SYSTEM ...................... 21
FIGURE 4.1-2 - DETAILS OF GUMMA PUMPING STATION .................................................... 23
FIGURE 4.1-3 - KEY PLAN OF WATER SUPPLY SYSTEM FROM GUMMA IS AS SHOWN IN
FIGURE BELOW. ............................................................................................................... 23
FIGURE 5.8-1 – ELEVATED STORAGE RESERVOIR .............................................................. 26
FIGURE 5.10-1 FLOW METERS ............................................................................................... 27
FIGURE 5.11-1- SAFETY VALVES ........................................................................................... 28
FIGURE 5.12-1- API PIPES ....................................................................................................... 28
SHIMLA JAL PRABANDHAN NIGAM LIMITED DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP,
Aurangabad (Maharashtra) Client Circulation P a g e | v
Annexure Content
Design Statement ..................................................................................................................... 51
Financial statement ................................................................................................................... 92
Cost Estimates
................................................................................................................................. 265
........................................................................................................................ 103
Rate Analysis .......................................................................................................................... 185
Drawings
GENERAL
REPORT
SHIMLA JAL PRABANDHAN NIGAM LIMITED DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP,
Aurangabad (Maharashtra) Client Circulation P a g e | 1
1. EXECUTIVE SUMMARY
1.1 PREAMBLE:
To manage water supply and wastewater management in Greater Shimla Planning Area a
government undertaking company has been formed by Govt. of Himachal Pradesh and
Shimla Municipal Corporation and named it as Shimla Jal Prabandhan Nigam Limited
(SJPNL). Company decided to take the program for improvement of water supply and
sewerage infrastructure in hand. As a part of this a detailed project report for Bulk water
supply system from Sutlej River is to be prepared. SJPNL called a tender for appointment
of independent consultant for Providing Development Services for Water Supply Scheme
project from Sutlej River.
SJPNL has planned to propose the Water supply project under different phases and under
different schemes of GoI, as well as get financial assistance from External Funding
Agencies like World Bank. Govt. of Himachal Pradesh may also provide part financial
assistance through State Plan for implementation of proposed projects.
Government has laid the norm for designing water supply scheme with 135 LPCD rate of
water supply in the City where underground drainage project is either contemplated or
completed. As the Shimla is the state capital and one of the top-most tourist locations in
the country, drinking water conforming to prescribed standards of purity is of prime concern
for the city from the overall development as well as health point of view.
Sameer Joshi of Yash Innovative Solutions LLP, Aurangabad (Maharashtra) has been
awarded the work for Providing Development Services for Water Supply Scheme in Shimla
City.
1.2 OBJECTIVE
Objectives of Water Supply Plan for any region should be conceived and conceptualized
consistent with broader perceptions related to socio- economic structure of the inhabitants,
their needs and requirement of adequate potable water and involvement of capital
investment as well. The strategy of planning should therefore aim at formulation of general
programs directed to specific results and conceptual frame work for action.
Provision of drinking water to communities is not only the basic amenity but it should be
viewed as an integral part of the major public health program aimed at prevention of water
borne diseases which will result in better health, happiness and wellbeing of the community.
It has been proved by epidemiological studies that all fatal enteric diseases like cholera;
Diarrhea, typhoid etc. are caused due to intake of contaminated water. hence the planning
and design of water supply projects should address not only the technical features but the
SHIMLA JAL PRABANDHAN NIGAM LIMITED DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP,
Aurangabad (Maharashtra) Client Circulation P a g e | 2
public health aspect too. The planned strategy shall take into account the identification of
source of supply, collection, transmission, distribution and other related aspects
The program includes;
Identification and development of source (surface source).
Provision of treatment units
Provision of storage facility
Preparing detailed designs, drawings and cost estimates for planning and
implementation of prioritized capital investment plan
1.3 BACK GROUND OF PROJECT
Shimla is the state capital of Himachal Pradesh with the population of 2,05,260 souls as
per 2011 census. Government of Himachal Pradesh (GoHP) constituted Shimla Planning
(SPA) Area through notification in November 1977, which comprises as below:
(1) Shimla Municipal Corporation (SMC)
(2) Recently merged Special Areas of Dhalli, New Shimla, and Totu
(3) Special Areas of Kufri, Shoghi and Ghanahatti
The proposed project is to be designed for the Whole Shimla Planning Area instead of only
Shimla Municipal Corporation.
Presently water supply to the City is mainly from the Gumma and Giri sources. After time
to time augmentation of existing sources, City receives about 40 MLD water from existing
sources. Insufficient supply of water from existing system and old and irreparable
distribution system leads to scarcity in water supply. Further increased commercial,
educational and tourism activities in the City causes the growth in the population and rapid
urbanization of area in the vicinity.
1.4 PROJECT NEED
Existing source is capable of catering only 40 MLD of water against the ultimate stage
demand of the 107.63 MLD. It is of prime importance to have the source capable of catering
the difference of 67.63 MLD. Bulk water supply project for the Shimla City is needed to
raise the service level at the 135 LPCD rate of water supply as per the guideline of Service
Level Benchmark (SLB).
After studying all the nearby sources, it is found that no other source except Sutlej River is
feasible for supplying the 67.63 MLD of water to the SPA. No any project was executed
from this source in past and hence all new components up to and excluding the Sanjauli
and Ridge reservoirs has to be include under the said project. Delay in preparation and
execution of new comprehensive bulk water supply scheme for the City will lead to more
crucial situation of water supply system in future.
SHIMLA JAL PRABANDHAN NIGAM LIMITED DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP,
Aurangabad (Maharashtra) Client Circulation P a g e | 3
1.5 CURRENT STATUS OF THE EXISTING WATER SUPPLY:
Presently in all there are seven sources of raw water for the SPA. Out of all these sources
only two sources are capable to supply considerable quantum of water. These two sources
are at Gumma and Giri. Out of these the source of water at Gumma was initially
commissioned in 1921-1922 and later on augmented thrice. After last augmentation the
source is now capable to provide 20 MLD of water to SPA. This source is proposed to
utilize completely with proposed project. Again, there is second major source located on
Giri River which is capable of supplying about 20 MLD of water. Remaining five sources
are of negligible capacity and not useful for further utilization. Hence the proposed project
has to be designed for the balance capacity considering the capacity of above two sources.
1.6 DESIGN CONSIDERATIONS:
Design of Bulk water supply project will be complying to following
CPHEEO’s “Manual of Water Supply and Treatment – 1999 “, issued by Ministry of Urban
Development, Govt. of India.
Guidelines for Preparation of Project Reports under National River Conservation Plan and
National Ganga River Basin Authority – Dec 2010 issued by Ministry of Ministry of
Environment & Forest, Govt. of India
Environmental and Social Management Framework (ESMF) issued by Ministry of Ministry
of Environment & Forest, Govt. of India
Any other Guideline issued by GoI and GoHP for planning and design of projects likely to
be proposed for funding under various funding agencies like World Bank, etc.
Guidelines of World Bank
Design Considerations are summarized as follow.
1. Design Year : 2018
2. Project approval and Construction Period : 2 Years
3. Base Year : 2020
4. Intermediate Stage : 2035
5. Ultimate Stage : 2050
6. Rate of Water Supply : 135 LPCD
7. Institutional Demand : Data provided by SMC
8. Pumping Hours : 24 Hrs
9. Source (Surface) : Sutlej River (Near Shikrodi village)
10. Pipe Material for Rising main : API 5L X 65
11. Storage Capacity of sump : 4 Hrs
12. Supply Hours for WTP : 24 Hrs
13. Soil Strata : As per Trial pits
SHIMLA JAL PRABANDHAN NIGAM LIMITED DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP,
Aurangabad (Maharashtra) Client Circulation P a g e | 4
14. Losses in the System : 15 %
1.7 PROPOSED PROJECT IN BRIEF:
The detailed project report has been prepared with reference to the existing water supply
facilities available with the SPA. The total demand of the town for the ultimate year 2050 is
worked out about 107.63 MLD. The quantity of water available from the existing two
sources equals to 40 MLD is deducted from the demand for proposed source. And hence
proposed project is planned to design for the demand of 67.63 MLD.
The project has been planned to receive adequate water supply to the City. Project Is
planned to minimize unnecessary pumping. In Proposed project, following major
components are proposed.
1. Headwork is proposed to construct on the bank of Sutlej River near Shikrodi Village.
The location of the headwork is near the motored road. Jack well, Pump house and
Approach bridge are the main components to be executed under the Headwork.
2. Water Treatment plant of capacity 42 MLD with pre-sedimentation treatment including
solar power plant for area lighting.
3. Sump of 4 hr storage capacity at Devidhar and Dummi
4. Raw and Pure Water Pumping machinery with allied works.
5. Raw and Pure Water rising pipelines with allied works
6. Electric substation with HT lines.
7. Construction of pump house and attendant quarter at Devidhar and Dummi .
8. Construction of Metaled roads.
9. Automation. Etc.
1.8 MAIN FEATURES OF THE PROPOSED PROJECT
Table 1.8-1
Name of Implementing Agency Shimla Jal Prabandhan Nigam Limited
Area to Served Shimla Planning Area
State Himachal Pradesh
Source of supply Sutlej River
Population as per 2011 census. 2,05,260 souls
Details Present
Stage 2020 Intermediate Stage 2035
Ultimate Stage 2050
Projected Population (souls) 243250 318467 413674
Rate of water supply (lpcd) 135 135 135
Daily Domestic water demand in MLD 32.84 42.99 55.85
Daily Institutional, Floating and commercial water demand in MLD
19.71 26.43 35.64
Daily demand with losses in MLD 61.82 81.67 107.63
SHIMLA JAL PRABANDHAN NIGAM LIMITED DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP,
Aurangabad (Maharashtra) Client Circulation P a g e | 5
Rate of Raw Water pumping (litres per hours)
1944730 1944730 3156229
Daily Pumping Hours 11.50 24.00 24.00
Cost of the scheme in Rs. 3225351762
Per capita cost of the scheme (Ultimate stage)
13259 10128 9540
Cost of water per 1000 liters in Rs. 45.3 84.8 176.71
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 6
1.9 LOCATIONS OF SOURCE
Figure 1.9-1 – Location of Proposed Intake
Figure 1.9-2 – Location of proposed intake with Adjacent village
Name of Source:
Sutlej River, Shikrodi Village.
Proposed
Intake
Proposed
Head Work
Sunni
Shikrodi
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 7
1.10 LOCATIONS OF PROPOSED ALIGNMENT, SUMP AND PUMP HOUSES
Figure 1.10-1 – Alignment from Intake to WTP to Devidhar
Figure 1.10-2 – Alignment from Devidhar to Dummi
Proposed
Head Work
Proposed
WTP 42 MLD
Proposed
Sump & PH 11.27 ML
@ Devidhar
Proposed
Sump & PH 11.27 ML
@ Devidhar
Proposed
Sump & PH 11.27 ML
@ Dummi
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 8
Figure 1.10-3 – Alignment from Dummi to Sanjauli
Proposed
Sump & PH 11.27 ML
@ Dummi
Existing reservoir
@ sanjauli
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 9
1.11 PROJECT COST
Table 1.11-1 - Recapitulation Sheet
Sr. No.
Item of work Amount
(Rs in Lac)
1 Detail survey and investigation including consultancy services and site development etc.
L.S 53.00
2 Acquisition of Land for various structures Annexure-A 1970.61
3 Road Restoration and Plantation Annexure-B 540.00
4 Raw water stages at Shikrodi
Annexure-C 253.76
Annexure-D 1055.23
Annexure-E 204.72
4 Water Treatment Plant (42 MLD) at Shikrodi Annexure-F 2520.00
5 Desilting Tank at Shikrodi Capacity: - 10.50 ML Annexure-G 525.00
6 RCC sump well of 11.27 ML capacity each at Devidhar and Dummi
Annexure-H 1127.22
7 Earthwork for Rising Main Annexure-I 1318.59
8 Providing & laying of various rising mains Annexure-J 12010.84
9 HT Lines from Himachal Pradesh State Electricity Board Limited
Annexure-K 5791.19
10 Providing Erecting Substations at Shikrodi, Devidhar and Dummi
Annexure-L 1355.08
Annexure-M 1096.21
Annexure-N 1027.00
13 Pumping Machinery for Raw water and Pure Water Stages
Annexure-O 5017.50
16 Automation to Raw Water Pumping Machinery, Pure Water Pumping Machinery and WTP
Annexure-P 320.18
10 Construction of pump house cum attendant quarter 2 Nos. of 600 Sqm. Each at Devidhar and Dummi .
Annexure-Q
366.54
11 Construction of staff quarters Type-I,II & III. 610.90
12 Construction of bridges at various points. 291.00
14 Construction of 12 Km.5/7m wide Katcha road. 675.00
15 Solar Power Plant 500 Kwp Annexure-R 380.00
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 10
Sr. No.
Item of work Amount
(Rs in Lac)
16 Environmental Impact Assessment & Environmental Management Plan.(L.S)
L..S. 100.00
Net Total Rs. In Lac. 38609.57
Consultancy fees for detailed design, tender
documents, bid management and construction & supervision @2 % of cost
772.19
Add 3% contingency 1158.29
Gross Total Rs. In Lac. 40540.04
Gross Total Rs in Crore 405.40
The project is viable and planned to be completed in 36 months of time period.
YASH INNOVATIVE SOLUTIONS
LLP, AURANGABAD,
MAHARASHTRA
EXECUTIVE ENGINEER
SJPNL
MD CUM CEO
SJPNL
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 11
2. INFORMATION OF SHIMLA CITY
2.1 LOCATION OF SHIMLA CITY
Figure 2.1-1 - Location of Shimla City
2.2 LOCATION, CONNECTIVITY & DETAILS:
This town is situated south of river Sutlej in the east, traverse spur of Central Himalyas at
31o4΄ to 31o10΄ North and 77o5΄ to 77o15΄ East longitude. Shimla is also a district which
is bounded by Mandi and Kullu in the north, Kinnaur in the east, the state
of Uttarakhand in the south-east, and Solan and Sirmaur. The average height of the city
above mean sea level is 2130.0 m. The general topography of Shimla is hilly with
elevations varying between 2454 m above MSL. at Jakhoo hill to 1507 m above MSL in
Lal Pani area. The city is like an irregular crescent and situated at about 88 km from
Kalka. It covers an area of 9950 ha interspersed with exquisite scenic landscapes. The
city spreads over a unique combination of hills, spurs and valleys. The mountains of Kullu
and Spiti are in the north and the central range of eastern Himalayas stretches east and
southeast.
The city has congested built-up areas. Cutting of terrain in natural profile of land for
construction, haphazard development, traffic congestion, over concentration in central
area, unauthorized constructions, encroachment on road and public land have generally
affected the natural setting as well as the scenic beauty of the city.
City is connected to National capital Delhi by domestic airport situated at 23 km distance.
It is also connected by train. Nearest broad-gauge station is at Kalka 70 km from the
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 12
Shimla and connected by narrow gauge to Shimla. Shimla is well connected by the other
important cities by road transport.
Shimla was first constituted as Municipal Committee and subsequently converted into
Corporation with effect from 29th June 1969. At present Municipal Corporation of Shimla
consist of 25 wards having population of 171640 souls as recorded during 2011 census
operation. The geographical area coverage of MC, Shimla is approximately 22.07 Sq.
Km. The DPR has been planned taking into consideration of the water demand of Shimla
Planning Area.
2.3 CLIMATE & RAINFALL:
Shimla is on the map of international tourist centers on account of its being hill station
with salubrious climate and extraordinary natural and scenic landscapes. It maintains a
pleasant climate during summer month from April to mid-June followed by monsoon up
to end of September. The city experiences winter from September to March and cold
spells between the month of December and February when temperature ranges between
-4oC to 17oC. The temperature in summer month varies between 18oC and 32oC. Average
annual rainfall is recorded as 1179.8mm. The maximum and minimum annual rainfall
recorded so far is 1897mm in the 1995 and 456.37mm in the year 1987. Most of the
rainfall occurs in the month of June, July, August and September, which accounts for 70%
of annual rainfall.
2.4 DEMOGRAPHY
As of 2011 India census Shimla Planning Area had a population of 205260.The average
growth rate of population in last five decades is 28.70 %. There are many historical,
religious and tourist locations situated around the Shimla City. It is state capital and well
connected by national capital Delhi and nearby state capitals like Chadigarg, Jaipur.
Tourist from all over world visit Shimla due to well connectivity and vicinity of important
historical, religious and tourist points. Due to this commercial activities in the City are
significantly increased. Increased commercial activities lead to increase in population.
Considering all above facts and analyzing present scenario in the City it makes necessary
to take the average of all three methods for population forecasting. Accordingly, average
of Arithmetical increase, Incremental increase, and Geometric progression method is
taken for population forecasting.
2.5 HISTORY OF THE CITY
Its history goes back to the British days when it was first discovered as a beautiful scenic
location for summer resort. Its importance grew when it was declared summer capital of
Govt. of India in 1864 AD. The city further attained the status of capital of Himachal
Pradesh in the year 1966 AD after reorganization of the state’s boundaries.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 13
2.6 SOCIO-ECONOMIC FEATURES
Natural resources play a key role in economic survival of the town as tourism and
agriculture are the main stay of the economy. The shift from agriculture to horticulture has
changed the economic pattern of the region as the city has become major centre for
collection and distribution. Per capita income is estimated to be Rs. 27486.0 per annum.
The key drivers of economic sectors for MC, Shimla are tourism, health area, education,
agri processing, trading hub etc.
The traditional small-scale industries like wool spinning, weaving, basket making and
metal work that use local resources are making tardy progress. There are about 450 small
scale and service industries operating in SPA.
Tourism is an important revenue earner to the state Govt. It employs nearly 4049 numbers
of workers. Shimla is an attractive destination for tourist from all over the world through
out the year. Topography of the town is characterized by interlocking spurs, narrow and
deep valley with high peaks and thick forest. Its salubrious climate and beautiful scenic
location attract large number of foreign tourists. It is easily accessible through
Chandigarh-Shimla National Highway No 22, Kalka-Shimla narrow gauge toy train and
by air from Delhi, Chandigarh and Kullu. Tourist population grew from 9,12,528 in 1998
to 21,97,795 in 2007.
2.7 MAP OF SHIMLA PLANNING AREA
Figure 2.7-1 – Map of Shimla Planning Area
CITY DEVELOPMENT PLAN - SHIMLA
Special Area Ghanahatti
Municipal Corporation Area Dhalli
Special Area Shoghi
Special Area Kufri
New Shimla
Tutu
ADMINISTRATIVE BOUNDARIES - SHIMLA PLANNING AREA
Cantonment Area
0 1 2 3 4 5 6 kms1
Special Area Shoghi
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 14
3. POPULATION FORECASTING & WATER DEMAND
3.1 POPULATION
Based on the historical population data, considering the infrastructure development in the
region population projections have been worked out with the Arithmetic Growth method,
Geometric Growth method and Incremental increase method. The details of the
forecasted population are as under.
The population data for the Shimla Planning Area is as below.
Table 3.1-1 - Population for last five decades
Stages considered for the design of the project are as follow.
Base Stage Year – 2020
Intermediate Stage Year – 2035
Ultimate Stage Year – 2050
Details of each method are as stated below
Arithmetical Increase Method
The Method is based on the assumption that population is increasing at a constant
rate. The rate of change of population with time is constant. This method gives low
value and is suitable for well settled and established communities.
Pn = P1 + n X
Where,
Pn = Population in nth decade
P1 = Population in latest decade
n = no of decades
X = Average increase per decade
Incremental Increase Method
In this method, in addition to arithmetical increase, incremental increase is added
once for each decade.
Pn = P1 + nX + n(n+1) Y/2
Where,
Pn = Population in nth decade
Sr. No. Year Population
1 1971 72870
2 1981 95851
3 1991 129827
4 2001 174789
5 2011 205260
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 15
P1 = Population in latest decade
n = no of decades
X = Ave. increase per decade
Y = Ave. Incremental Increase
Geometric Progression Method
This method based on assumption that future growth follows the geometric mean. This
method gives much higher value and mostly applicable for growing Citys and cities
having vast scope for expansion.
Pn = P1 x (1 + Geometric Mean ) n
Where,
Pn = Population in nth decade
P1 = Population in latest decade
n = no of decades
Population of the SPA as per 2011 census is 2,05,260. The decadal population growth of
the SPA and the projected population made by various methods is shown in following
Table. The population projection calculations are as below.
Table 3.1.2 Population of last five decades and decadal growth
Year Population Increase in
Decade
Incremental increase in
Decade
Rate of Growth per Decade
1971 72870
22981 0.3154
1981 95851 10995
33976 0.3545
1991 129827 10986
44962 0.3463
2001 174789 -14491
30471 0.1743
2011 205260
Total 678597 132390 7490 Rg =
Average 135719 33098 2497 0.2870
City shows low, medium and high rate of growth in various areas hence Population
forecast, made by the average of three methods- Arithmetic method, Incremental
increase method and Geometric progression method, seems to be rational. Hence, the
forecast, as made by the average of Arithmetic method, Incremental increase method
and Geometric progression method, is adopted
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 16
Table 3.1.3 Population Projection by various methods
Year
Arithmetical
Increase
Method
Incremental
Increase
Method
Geometric
Progression
Method
Average of AI,
II and GP
Methods
2020 235048 237183 257588 243273
2035 284695 294882 376091 318556
2050 334342 358198 549112 413884
Floating Population: The decadal growth of the Floating Population of SPA is shown in
Table 3.1.4. The projected floating population of the city is shown in Table 3.1.5.
Table 3.1.4: Decadal growth of the Floating Population*
Sr. No.
Year Population*
Increase in
Decade (X)
Incremental increase
(Y)
Rate of growth
per decade
Decadal growth
in %
1 1971 20000
2 1981 40000 20000 1.000 100.00
3 1991 60000 20000 0 0.500 50.00
4 2001 80635 20635 635 0.344 34.39
5 2011 140500 59865 39230 0.742 74.24
Total 120500 39865
Average 24100 30125 13288 0.598
*Ref.: WAPCOS Revised DPR, p.15
Table 3.1.5 Projected floating population of the SPA.
Sr. No.
Year n Arithmetic method
Incremental increase method
Geometric progression
method
Average of Incremental
increase method
and Geometric
progression method.
Graphical Method*
1 2020 0.9 193864 191735 204944 198340 187000
2 2035 2.4 230903 220747 275422 248084 215000
3 2050 3.9 267943 244157 370135 307146 225000
*Finally adopted
3.2 LAND USE PLAN
City Development Plan (CDP) of Town and Country Planning Department has recorded
Land use areas of the city for the year of 2004 and predicted land use areas for the year
2021 as shown in Tables 3.2.1 and 3.2.2 respectively.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 17
Table 3.2.1: Land use areas for the year of 2004
SN Land Use Area (in Hectare)
% of urban area
% of Planning
Area
1 Residential 903.13 61.19 9.07
2 Commercial 25.22 1.71 0.25
3 Industrial 9 0.62 0.09
4 Tourism 21.7 1.47 0.22
5 Public & semi- public 138.78 9.4 1.39
6 Parks & open spaces 6 0.41 0.06
7 Traffic and Transportation 371.93 25.2 3.75
Total 1475.76 100
8 Agriculture, 2174.75 21.85
9 Forest 6080.15 61.12
10 Water bodies and undevelopable
land 219.34 2.2
Total 8474.24 85.17
Grand Total 9950 100
Table 3.2.2: Land use areas for the year of 2021
SN Land use Area in Hectare
% of Urban Area
% of Planning
area
1 Residential 2124 68 21.35
2 Commercial 51.2 2 0.51
3 Industry 17 1 0.17
4 Tourism 98 3 0.98
5 Public & Semi Public 274.28 9 2.76
6 Parks & Open Spaces 32 1 0.33
7 Traffic & Transportation 484.93 16 4.87
Total 3081.41 100
8 Agriculture 620.63 6.24
9 Forest 6028.62 60.59
10 Water bodies &
Undevelopable slopes 219.34 2.2
Total 6868.59
Grand Total 9950 100
From the Tables 3.2.1 and 3.2.2, it is to be noted that the land use areas in the year 2021
have been increased by reducing the Agriculture area. So, the total planning area of
1475.76 Ha which was considered in the year 2004 has been increased to 3081.41 Ha
for the prospective year of 2021.Land use areas as suggested by the Town and Country
Planning Department for the year 2021are considered as the base year is 2020.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 18
As mentioned in other DPRs, the measured area of SPA is 11,199 Ha rather than earlier
reported 9950 Ha. Hence, land use percentages are computed for the year 2021 for the
measured areas and are shown in Column 5 of the Table 3.2.3
Table 3.2.3: Land use areas
S.N. Land Use
Area in Hectare % of
Urban Area
% of Planning
area 2001 2021 Measured
Area (2021)
1 2 3 4 5 6 7
1 Residential 903.13 2124 2391 68.93 21.35
2 Commercial 25.22 51.2 58 1.66 0.51
3 Industrial 9 17 19 0.55 0.17
4 Tourism 21.7 98 110 3.18 0.98
5 Public & semi- public 138.78 274.28 309 8.90 2.76
6 Parks & open spaces 6 32 36 1.04 0.32
7 Traffic and Transportation
371.93 484.93 546 15.74 4.87
Total 1475.76 3081.41 3468 100 30.97
8 Agriculture, 2174.75 620.63 699 6.24
9 Forest 6080.15 6028.62 6785 60.59
10 Water bodies and undevelopable land
219.34 219.34 247 2.20
Total 8474.24 6868.59 7731 69.03
Grand Total 9950 9950 11199 100.00
3.3 WATER DEMAND CALCULATION
As per CPHEEO, recommended water supply levels for cities with piped water supply
where sewerage system exists or being contemplated is 135 LPCD. Hence domestic
demand of water at the rate of 135 LPCD for the period of 30 years is calculated. All the
following data regarding demand calculation and design demand from the proposed
source on Sutlej River is finalized and approved by SJPNL.
Table 3.3.1: Domestic Water Demand
S.N. Design Stage
Year Population
Domestic Demand without Losses
Domestic Demand with 15% System
losses
1 2020 243250 Souls 32.84 MLD 38.63 MLD
2 2035 318467 Souls 42.99 MLD 50.58 MLD
3 2050 413674 Souls 55.85 MLD 65.70 MLD
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 19
As the Shimla is famous tourist location the floating population also contribute major part
of the total water demand. Demand for day tourist and overnight trippers is worked out at
the 45 LPCD and 135 LPCD rate of supply respectively.
Table 3.3.2: Floating Water Demand
S.N.
Design
Stage
Year
Day Tourist Overnight
Trippers
Floating
Demand
without
losses
Floating
Demand with
15% System
losses
1 2020 45333 Souls 23347 Souls 6.24 MLD 7.34 MLD
2 2035 52630 Souls 31421 Souls 8.02 MLD 9.44 MLD
3 2050 61102 Souls 42289 Souls 10.36 MLD 12.19 MLD
Also, other demands such as institutional, commercial, industrial, cantonment, satellite
town demand of water is worked on the basis of data provided by municipal Corporation.
Details of other demand are summarized as below.
Table 3.3.3 Other Demand
S.N. Details 2020 2035 2050
1 Institutional 7.89 MLD 10.62 MLD 14.29 MLD
2 Industrial 0.10 MLD 0.10 MLD 0.10 MLD
3 Cantonment 0.54 MLD 0.54 MLD 0.54 MLD
4 Additional Shimla
Planning Area 4.93 MLD 7.14 MLD 10.35 MLD
Demand without Losses
13.46 MLD 18.40 MLD 25.28 MLD
Demand with 15 %
System Losses 15.84 MLD 21.65 MLD 29.74 MLD
Presently two main sources supply around 40 MLD of water to the SPA. Hence the
demand for the design purpose of the project from Sutlej River is calculated by deducting
the capacity of current sources from total demand.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 20
Table 3.3.4 Design Demand
S.N. Design Stage
Year
Total
Demand of
the SPA
Water Available
from Existing
Sources
Demand proposed
to be cater from
Sutlej River
1 2020 61.82 MLD 40.00 MLD 21.82 MLD
2 2035 81.67 MLD 40.00 MLD 41.67 MLD
3 2050 107.63 MLD 40.00 MLD 67.63 MLD
Proposed Source on Sutlej River near Shikrodi Village is hence being designed for the
demand shown in above table.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 21
4. EXISTING WATER SUPPLY STATUS
4.1 HISTORY
Water supply for Shimla was originally executed in the year 1875 by bringing water
through gravity main from Dhalli catchment area for a population of 16000 persons. The
city grew over the years increasing its boundary as well as population with subsequent
augmentation of water supply to match the needs of the growing population. Though the
capacity after commissioning of augmentation schemes of water supply i.e. Nauti Khad
& Giri, is 54.54 MLD, presently only two sources are feasible for further utilization i.e. Giri
And Gumma. Both of these are presently supplying 40 MLD of water to SPA.
Figure 4.1-1 - History of Development of Water Supply System
4.2 EXISTING SOURCES
Presently there are seven sources of water for SPA as listed below.
1. Dhalli Catchment
2. Cherotand Jagroti
3. CheirNallah
4. Source Gumma at Nauti Khad to Carignano
5. Source at Gumma at Nauti Khad near Bridge
6. Ashwani Khed to Kasumpti
7. River Giri
Following table shows the details of existing sources, their capacities and area served.
Table. 4.2.1: Details of Existing Sources
SN
Source Existing Capacity (MLD)
Proposed
Capacity (MLD)
Name WTP/ Tank
Area served/ Reservoir Type Mode
of supply
1 Dhalli
Catchment Spring Gravity 0.45 0.00
1875 1884 1992
No systematic
potable water
supply till.
Presently city
gets 54.5
MLD water 1st reservoir of
9 ML capacity
was constructed
at Sanjauli
Last
augmentation
scheme29.5
MLD
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 22
SN
Source Existing Capacity (MLD)
Proposed
Capacity (MLD)
Name WTP/ Tank
Area served/ Reservoir Type Mode
of supply
2 Churat Nallah
Dalli filter
Dhalli Zone balance and sent to Sanjauli reservoir
3.5 0.00
3 Chair Nallah
Lambidhar
Kufri Surface 1.7 0.00
4 Gumma at Nauti Khad
Carignano
(a) Reservoirs: Sanjauli, Ridge, Mansfield,
Surface Gravity 16.75 21.77 (b) sectoral tanks:
Engine Ghar, North Oak, Bharari, Advace Study,
Sandal Chakkar and Totu
Gumma at Nauti Khad
near Bridge
Carignano
(a) Reservoirs: Sanjauli, Ridge, Mansfield,
Surface Gravity 4.54 (b) sectoral tanks: Engine Ghar, North Oak, Bharari, Advace Study,
Sandal Chakkar and Totu Pump
5 Ashwani
Khad Kasumpti
(1) Adjoining area and sectoral tanks located at
sector-1, 3 & 4 New Shimla, (2) Mans field
and then adjoining area and sectoral tank at
Knolls and Tuti Kandi and sump well of Kamna Devi Pump house wood
Surface Pumpi
ng 7.6 0.00
6 River Giri Dhalli
Adjoining area of Dhalli Zone and balance is received at Sanjauli
reservoir
Surface
Pumping
upto WTP and then by
gravity
20 18.23
Total 54.54 40.00
4.3 GUMMA SOURCE
Gumma Pumping Station (PH) gets water from two sources, namely, (i) Gumma source
and (ii) Nauti Khad intake
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 23
There are three sets of pumping machinery at Gumma which pumps the water to
Carignano Reservoir. Further reservoirs at Mashobara, Sanjauli, Ridge and Mansfield
lodge are feed by gravity from Carignano Reservoir.
Details of pumping machinery, discharge, head with year of commissioning is as shown in
following figure.
Figure 4.1-2 - Details of Gumma Pumping Station
Figure 4.1-3 - Key plan of water supply system from Gumma is as shown in figure below.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 24
4.4 DHALLI CATCHMENT
An average of 0.45 MLD water is received from this source under gravity condition at
Dhalli filter. This is the source based on spring sources of the dense protected forest
known as Dhalli catchment. Due to shrinkage in spring water this source is not capable
to supply the considerable quantum of water hence supply from this source is not
considered for proposed project.
4.5 CHEROT & JAGROTI
From this source an average of 3.50 MLD of water is received which is collected at Dhalli
Filter. Part of this water is distributed in the adjoining area of Dhalli Zone and balance is
received at Sanjauli reservoir through gravity main from Dhalli filter. Due to shrinkage in
spring water this source is not capable to supply the considerable quantum of water hence
supply from this source is not considered for proposed project.
4.6 CHAIR NLLAH
From the source, an average of 1.70 MLD water is received which is pumped from Chair
source to storage tank at Lambidhar from where water is distributed to Kufri under SPA
Shimla. Due to shrinkage in spring water this source is not capable to supply the
considerable quantum of water hence supply from this source is not considered for
proposed project.
4.7 ASHWANI KHAD
From this source, about 7.60 MLD of water is pumped through two stages and received
at Kasumpti reservoir from where part of the water is distributed in the adjoining area and
sectoral tanks located at sector-1, 3 & 4 New Shimla are filled-up. The balance water is
again pumped from this reservoir to Mans field tank. From Mans field tank the water is
distributed in the adjoining area and sectoral tank at Knolls wood is also connected with
this water tank. In addition to this the sectoral tank at Tuti Kandi and sump well of Kamna
Devi Pump house is also fed. Due to shrinkage and contamination in spring water this
source is not capable to supply the considerable quantum of water hence supply from
this source is not considered for proposed project.
4.8 RIVER GIRI
From this source, about 20.00 MLD of water is pumped into Dhalli Treatment Plant and
further water is distributed in the adjoining area of Dhalli Zone and balance is received at
Sanjauli reservoir through gravity main from Dhalli filter. This source is proposed to utilize
for proposed project.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 25
5. DESIGN CRITERIA
5.1 INTRODUCTION
The designs confirm to Manual of Water Supply & Treatments Third Addition of May, 1999
(CPHEEO Manual) with few modifications necessary for specific project needs. The
design parameters proposed shall be finalized after discussion with SPA. Also, recent
remarks raised by CPHEEO regarding the water supply projects are taken into
consideration for design of distribution system.
5.2 DESIGN PERIOD
The proposed scheme will be designed considering stages as follow.
Table 5.2-1- Design Stages
Base Year 2020
Intermediate Year 2035
Ultimate Year 2050
Component wise design period is considered as follow.
Table 5.2-2- Design Period
WTP, Reservoirs and Pumping Machinery
15 years after execution period
Head Work, Raw Water & Pure Water Leading Mains and Distribution Network
30 Years after execution period
5.3 WATER DEMAND
Water domestic demand will be calculated at 135 lpcd rate of water supply for the
projected population in the year 2020, 2035 and 2050 with necessary provision for
miscellaneous demand and the system losses at 15%. In addition to domestic demand,
institutional demand, other demands in each ward of the City are worked out and
projected for each design stage appropriately. Institutional demands are calculated at rate
of supply specified as per CPHEEO.
5.4 SYSTEM LOSSES
Total system losses from source to consumer end shall be considered as 15%.
Table 5.4-1 - Brake up of Losses
Stage Losses
Distribution System 10%
Pure Water Conveying mains 3%
Water Treatment Plant 1%
Pure Water Conveying mains 1%
Total 15%
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 26
5.5 PUMPING SYSTEM
There will be provision of 50% standby for the pumping machinery more than 1000 HP
and 100% for the pumping machinery less than 1000 HP in proposed Water Supply
project.
5.6 HOURS OF SUPPLY
The pumping system if required will be planned based on the analysis of the distribution
system. Generally whole system is to be designed for 24 hours of supply.
5.7 MINIMUM DIAMETER OF PIPELINE FOR RISING MAIN
The minimum size as calculated by the computerized analysis for “Economic size of rising
main” will be adopted for the rising main. Also, diameter will be checked for water hammer
calculations and maximum permissible velocity. According to all above checks diameter
will be adopted.
5.8 STORAGE
Figure 5.8-1 – Elevated Storage Reservoir
i. Capacity
For zones where new reservoirs, are to be proposed, capacity will be kept at 8 hours
requirement of that zone for Intermediate stage (year 2035).
For zones where there are existing reservoirs, no new reservoir will be proposed if
existing reservoir is having capacity to fulfill at least 6 hour demand of that zone.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 27
For zones where there are existing reservoirs having capacities less than 6 hours, new
additional reservoirs will be proposed of capacity such that storage capacity of existing &
new reservoir proposed will together be of 8 hrs of Intermediate stage requirement of that
zone.
ii. Staging Height
As per recommendation of CPHEEO manual, Para 10.3.6, staging height of new
reservoirs will be kept between 15 m to 20 m. However, due consideration will be given
to maintain at least 12 m terminal pressure is the system as per CPHEEO manual para
10.3.3 and also, economic analysis of feeder mains (existing as well as to be proposed)
in order to avoid boosting in system as for as possible.
5.9 SURGE PROTECTION
Water hammer analysis will be carried out for rising main and appropriate surge protection
device will be provided.
5.10 METERING
Figure 5.10-1 Flow Meters
i. Bulk Meter:
Bulk Meter shall be provided at the reservoirs inlet and outlet as well as bifurcation
points in the zone to correctly assess the quantity of the water supplied.
ii. Domestic Water Meter
The domestic meters used for the residential/house connections will help in creating
awareness in the people about the usage of water. Metering will be useful to accurately
quantify the consumption made by the individual house connections and will also increase
the revenue of the municipal Corporation. Metering will limit the excessive usage of the
water, as more usage means more billing to the consumer. This will also help to change
the mindset of people that water is not free.
Proper implementation of metering will help in quantifying in the Unaccounted-for Water
(UFW) and may eliminate the Non-Revenue Water (NRW).
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 28
Provision of domestic and bulk meters will increase the revenue of the Municipal
Corporation.
The metering is also necessary for implementation of 24x7 water supplies.
5.11 SYSTEM SAFETY
Figure 5.11-1- Safety Valves
Various appurtenances such as Air Valves, sluice valves
/ Butterfly valves, scour valves, pressure relief valves with
anchor blocks, thrust blocks etc. will be provided on the
pipe lines.
5.12 PIPES
Figure 5.12-1- API Pipes
The American Petroleum Institute
specification API 5L covers seamless and welded
steel line pipe. This is steel pipe for pipeline
transportation systems in the petroleum and
natural gas industries. API 5L is suitable for
conveying gas, water, and oil. Size range is limited
only by manufacturer's capabilities. The C value
of the theses pipes is taken as 140.00. Apart from
that the jointing of the pipeline is also simple and
there is no issue of availability of pipes and
specials.
5.13 WATER TREATMENT PLANT
The aim of water treatment is to produce and maintain water that is hygienically safe,
aesthetically attractive and palatable, in an economic manner. Method of water
treatment to be employed depends on the nature of raw water constituents and
desired standards of water quality. Raw water quality at source, which may be ground
water or surface water, has considerable effect on the water treatment method. The
plant will be completely automated with SCADA and PLC and having a connectivity
to the centre command centre based at Shimla. As the Source contains lot of silt it is
necessary to provide pre-sedimentation process.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 29
5.14 WATER QUALITY
The safe water supply to consumers is to ensure that the water supplied is free from
pathogenic organisms, clear, palatable and free from undesirable taste and odour, of
reasonable temperature. The establishment of minimum standards of quality for
public water supply is very much essential to achieve safe drinking water. The
physical and chemical quality of drinking water in accordance to BIS code IS: 10500-
1991 guidelines presented in below Table
Summary of Design Parameters
Table 5.14-1 - Design Parameters.
1. Design Approach 24 x 7 water supply with metering
2. Design Period 30-year period starting 2020
i.e. year 2050
3. Design Population (Ultimate
stage) 413674
4. Per Capita Supply 135 lpcd for domestic supply
5. Peak Factor 1.0 (24 hrs supply)
6. Minimum pipe diameter As per economical dia
7. Velocity Head 4.00 m
8. Pipe Materials API 5L X65 grade
9. ‘C’ Value 140
10. Reservoir Capacity For detention period of 4 hrs
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 30
6. PROPOSED PROJECT
6.1 GENERAL
The detailed project report has been prepared with reference to the existing water supply
facilities available with the SPA. This DPR is prepared for the project of Bulk Water supply
from the Sutlej River.
The project has been planned to receive equitable water supply to the City. Planning also
involves to minimize the unnecessary pumping.
6.2 SOURCE CONSIDERATION:
Shimla City is located at an altitude of 2276 m above MSL. After calculating the total water
demand of the City, it founds that a strong source of water which will be able to cater the
water demand throughout the year is most important factor. Accordingly, study of all
possible sources nearby the City is conducted. Some of the existing sources are
proposed to utilize. But city’s design stage demand is around 107 MLD against the
present supply of 40 MLD. There is deficit of about 67 MLD. No assured source is found
nearby the town capable to cater the demand of 67 MLD. The only assured source is the
River Sutlej flowing at around 20 Km distance from the town. There are three major
irrigation projects at distance more than 50 km.
In proposed project LSL at source is 600 m and Final discharge point RL at Sanjauli
reservoir is around 2260. Hence there is huge static difference 1660 m in head. Also,
quantity of water to be lifted is much more. Therefore, it is necessary to provide the
pumping in stages.
Accordingly, Pumping is proposed in following stages
1. Raw Water Stage – From Jack well to WTP
2. Pure Water Stage 1 – From WTP to Devidhar
3. Pure Water Stage 2 – From Devidhar to Dummi
4. Pure Water Stage 3 – From Dummi to Sanjauli
6.3 GEOTECHNICAL INVESTIGATIONS:
Geology of Shimla indicates sub Himalayan characteristics. The rock found in the project
area have undergone three distinct generations of deformations resulting in variation of
altitude of formation. Carbonaceous, Phyllite, local bands of quartzite and lime stone
forming Jutog group of rocks occupy main Shimla area and extends from Annadele–
Chura Bazar-prospect hill-Jakhoo-U.S. club and high land area whereas shales, slate,
greywacke quartzite, local conglomerates and dolomites forming Shimla group of rocks
are found in Sanjaulli and Dhalli area.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 31
6.4 PRELIMINARY LAND ACQUISITION / TRANSFER REQUIREMENTS
IPH department had issued the certificate regarding land availability. Photocopy of the
same is attached herewith.
Table 6.4-1 - Land Availability
6.5 AVAILABILITY OF WATER AND WATER RESERVATION
IPH department had issued the certificate regarding water availability. Photocopy of the
same is attached herewith.
Table 6.5-1 - Water Availability
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 32
6.6 HEAD WORKS: -
6.6.1) Jack well and Pump House:
Jack well for the proposed water supply project is proposed near the Shikrodi village on
the bank of Sutlej River. Construction will be RCC M-300 with over headed pump house
in RCC and brickwork. Size of Jack well and Pump house is proposed to keep as per
space requirement for pumps. Rose pieces of appropriate sizes are proposed at specified
levels so as to make provision for required inflow of water into Jack well. Separate room
is proposed for installation of electrical equipment beside the approach bridge.
6.6.2) Approach Bridge:
Approach Bridge of width 7.50 m width and required length is proposed for the access to
Jack well and pump house. Raw water rising main will be laid on one side of Bridge resting
on the chairs from the maintenance point of view. A panel room of appropriate size is
proposed adjoining to approach bridge. Provision for street lighting is also made.
6.6.3) Approach Channel
Approach channel of required 50.0 m length is proposed to access the inflow of water into
Jack well. Bottom level of channel is proposed to kept so that water below the minimum
draw down level can be taken. Approach Channel is designed for the twice the value of
ultimate demand of the City.
6.7 RAW WATER RISING MAIN: -
Raw water rising main is of API 5L X 65 grade pipe designed for the ultimate demand of
the City. Supply for the 24 hours is considered. Design is based on computerized analysis
for economical diameter. Diameter is also checked for water hammer calculations and
maximum permissible velocity. Accordingly, diameter is proposed. Air valves are
proposed of cast steel material as total working pressure is exceeding the value of 250
N/mm2
Table 6.7-1- Raw Water Rising Main
Name of Sub work Raw Water Rising Main
Alignment From Jack well to WTP (Near Shikrodi)
Length 0.2 Km
Outer Diameter 762 mm
Material API 5L X 65
Design Discharge 67.63 MLD
Supply Hours 24
Floor level at PH 636.00 m
Discharge Point RL 664.18 m
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 33
6.8 RAW WATER PUMPING MACHINERY: -
Proposed raw water pump is now designed for the demand of intermediate stage 2035.
Pumping will be done for 24 Hrs to fulfill the demand of City. A separate HT express
feeder is proposed from the nearest substation.
Table 6.8-1- Raw Water Pumping Machinery
Name of Sub work Raw Water Pumping Machinery
Location Jack well on Sutlej River
Type Vertical Turbine
HP 365 ( 2 working + 2 stand by)
Stand By 100%
LSL in Jack well 600.20 m
Discharge Point RL 664.18 m
Discharge 540.20 LPS
Total Head 69 m
Hours of pumping 24
6.9 WATER TREATMENT PLANT: -
Conventional WTP of 42.00 MLD is proposed near the jack well. It is near the village
Shikrodi accessible by road. Capacity of WTP is worked out for the demand of the City at
intermediate stage 2035. As the raw water contains high amount of silt, desilting treatment
is necessary. Desilting tank for 6 hrs detention period is proposed. Also, post treatment
for prevention of viral contamination is necessary as there is history of contamination
occurs due to various organisms.
Table 6.9-1- Water Treatment Plant
Name of Component Water Treatment Plant
Location Near jack well at Shikrodi
Type Conventional
FSL of Desilting tank 664.18
Capacity 42.00 MLD
Hours of Pumping 24 Hours
LSL of pure water sump 654.18.00
Pre-treatment Desilting and pre-chlorination
Post-treatment Disinfection
6.10 PURE WATER STAGES I, II and III
6.10.1) PURE WATER RISING MAIN
Pure water rising main is of API 5L X 65 grade pipe designed for the ultimate demand of
the City. Supply for the 24 hours is considered. Design is based on computerized analysis
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 34
for economical diameter. Diameter is also checked for water hammer calculations and
maximum permissible velocity. Accordingly, diameter is proposed. Air valves are
proposed of cast steel material as total working pressure is exceeding the value of 250
N/mm2. For taking care of fluctuating pressure due to highly undulated topography, water
hammer control devices are proposed depending upon the surge analysis.
Table 6.10-1- Pure Water Rising Main Stage I
Stage I
Alignment From WTP to Devidhar
Length 2.294 Km
Outer Diameter 762 mm
Thickness 7.92 mm
Material API 5L X 65
Design Discharge 67.63 MLD
Supply Hours 24
Floor level at PH 654.18 m
Discharge Point RL 1312.26
Table 6.10-2- Pure Water Rising Main Stage II
Stage II
Alignment From Devidhar to Dummi
Length 8.312 Km
Outer Diameter 762 mm
Thickness 7.92 mm to 12.70 mm
Material API 5L X 65
Design Discharge 67.63 MLD
Supply Hours 24
Floor level at PH 1312.26 m
Discharge Point RL 1817.64 m
Table 6.10-3- Pure Water Rising Main Stage III
Stage III
Alignment From Dummi to Sanjauli
Length 10.065 Km
Outer Diameter 762 mm
Thickness 7.92 mm to 9.53 mm
Material API 5L X 65
Design Discharge 67.63 MLD
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 35
Stage III
Supply Hours 24
Floor level at PH 1817.64 m
Discharge Point RL 2256.30 m
6.10.2) PURE WATER PUMPING MACHINERY: -
Proposed pure water pump is now designed for the demand of intermediate stage 2035.
Pumping will be done for 24 Hrs to fulfill the demand of City. A separate HT express
feeder is proposed from the nearest substation.
Table 6.10-4- Pure Water Pure Water Pumping Machinery stage I
Stage I
Location Sump at Devidhar
Type Horizontal Multistage Pump
HP 1175 (6 working + 3 stand by)
Stand By 50%
LSL in Sump 654.18 m
Discharge Point RL 1312.26 m
Discharge 540.20 LPS
Total Head 667 m
Hours of pumping 24
Table 6.10-5- Pure Water Pure Water Pumping Machinery stage II
Stage II
Location Devidhar to Dummi
Type Horizontal Multistage Pump
HP 935 (6 working + 3 stand by)
Stand By 50%
LSL in Sump 1308.26 m
Discharge Point RL 1817.64 m
Discharge 540.20 LPS
Total Head 530 m
Hours of pumping 24
Table 6.10-6- Pure Water Pure Water Pumping Machinery stage II
Stage III
Location Dummi to Sanjauli
Type Horizontal Multistage Pump
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 36
Stage III
HP 825 (6 working + 3 stand by)
Stand By 50%
LSL in Sump 1813.64 m
Discharge Point RL 2256.30 m
Discharge 540.20 LPS
Total Head 466 m
Hours of pumping 24
6.10.3) PURE WATER SUMP, PUMP HOUSE AND STAFF QUARTER: -
Pure Water Sumps are proposed at Devidhar and Dummi. The detention period for the
sump is proposed to keep for 4 hrs. Accordingly, capacity of sump comes to 11.27 ML.
Pump house of 600 Sqm is proposed to accommodate pumping machinery with all allied
equipment. Provision of quarters for attendant as well as other supporting staff is
proposed for the convenience to staff and better monitoring of the system near each
pumping station.
6.11 AUTOMATION
In order to have better control on operation of WTP and optimize the man power, chemical
and electricity expenses as well as for daily water quality report generation, automation
of WTP is proposed in this project. Ultrasonic level transmitter, turbidity, PH, Residual
Chlorine sensors, PLC based control monitoring and communication system, butterfly
valves with electric actuators are the components of this sub work. In addition to this
pressure transmitter and residual chlorine analyzer are provided for each zone in
distribution system.
6.12 EXPRESS HT FEEDER AND SUBSTAION
For one raw water and three pure water pumping stages, three electric substations are
required of capacity around 10, 7 and 6 MVA at Shikrodi, Devidhar and Dummi
respectively. Express HT feeder main shall also require to laid from nearest power station.
Quotation from the state electricity department has been taken and provision is made
accordingly.
6.13 500 KW SOLAR PLANT
A solar power plant of 500 KW is proposed at the WTP premises. It will help for plant
electrification and reduction of electricity expenses. Roof top of all buildings in WTP
premises are proposed to utilize for the erection of solar power plant. Hence no additional
land is required.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 37
6.14 COMPOUND WALL
In order to safeguard the automized WTP campus and sump and pump house located at
Devidhar and Dummi, compound wall with RCC framed structure and brickwork, plaster,
panting is proposed.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 38
7. PROJECT COST
7.1 RECAPITULATION SHEET
The detailed cost estimates have been prepared on the basis of the detailed design
based on local conditions with due consideration to parameters likes it preparation,
civil works and equipment. The rates considered for estimation are based on rate
analysis done within the department and where rate analysis not done used quotation
from the market.
Table 7.1-1 Recapitulation Sheet
Sr. No.
Item of work Amount
(Rs in Lac)
1 Detail survey and investigation including consultancy services and site development etc.
L.S 53.00
2 Acquisition of Land for various structures Annexure-A 1970.61
3 Road Restoration and Plantation Annexure-B 540.00
4 Raw water stages at Shikrodi
Annexure-C 253.76
Annexure-D 1055.23
Annexure-E 204.72
4 Water Treatment Plant (42 MLD) at Shikrodi Annexure-F 2520.00
5 Desilting Tank at Shikrodi Capacity: - 10.50 ML Annexure-G 525.00
6 RCC sump well of 11.27 ML capacity each at Devidhar and Dummi
Annexure-H 1127.22
7 Earthwork for Rising Main Annexure-I 1318.59
8 Providing & laying of various rising mains Annexure-J 12010.84
9 HT Lines from Himachal Pradesh State Electricity Board Limited
Annexure-K 5791.19
10 Providing Erecting Substations at Shikrodi, Devidhar and Dummi
Annexure-L 1355.08
Annexure-M 1096.21
Annexure-N 1027.00
13 Pumping Machinery for Raw water and Pure Water Stages
Annexure-O 5017.50
16 Automation to Raw Water Pumping Machinery, Pure Water Pumping Machinery and WTP
Annexure-P 320.18
10 Construction of pump house cum attendant quarter 2 Nos. of 600 Sqm. Each at Devidhar and Dummi .
Annexure-Q
366.54
16 Environmental Impact Assessment & Environmental Management Plan.(L.S)
L..S. 100.00
Net Total Rs. In Lac. 38609.57
Consultancy fees for detailed design, tender documents,
bid management and construction & supervision @2 % of cost
772.19
Add 3% contingency 1158.29
Gross Total Rs. In Lac. 40540.04
Gross Total Rs in Crore 405.40
11 Construction of staff quarters Type-I,II & III. 610.90
12 Construction of bridges at various points. 291.00
14 Construction of 12 Km.5/7m wide Katcha road. 675.00
15 Solar Power Plant 500 Kwp Annexure-R 380.00
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 39
8. OPERATION AND MAINTENANCE
The objective of an efficient operation and maintenance of a water supply system is
to provide safe drinking water as per designed quality and quantity, with adequate
pressure at convenient location and time at competitive cost on a sustainable basis
“Operation refers to timely and daily operation of the components of a Water Supply
system such as headwork’s, treatment plant, machinery and equipment, conveying
mains, service reservoirs and distribution system etc., effectively by various technical
personnel, as a routine function.”
“Maintenance is defined as the act of keeping the structures, plants, machinery and
equipment and other facilities in an optimum working order. Maintenance includes
preventive / routine maintenance and also breakdown maintenance. However,
replacements, correction of defects etc. are considered as actions excluded from
preventive maintenance. Operation and maintenance requirements described in
following sections are in lined with Manual on Operation and Maintenance of Water
Supply Systems, CPHEEO, Ministry of Urban Development, 2005 and Operation and
Maintenance Manual for Rural Water Supplies, Ministry of Drinking Water and
Sanitation, Go I, New Delhi, 2013
8.1 NECESSITY OF MAINTENANCE
The large investments will be required to construct utilities intended to provide
facilities for water supply will become unproductive in the sense that the objective for
which they have been installed is not achieved mainly on account of poor
Maintenance. Often the investments become unproductive, and a larger amount of
money is required to replace and rebuild the system components. Interruptions in
service occur owing to the breakdown of equipment as a result of poor
maintenance.
Some of the key issues contributing to the poor Operation & Maintenance have
been identified as follows:
i) Lack of finance, inadequate data on Operation & Maintenance
ii) Inappropriate system design; and inadequate workmanship
iii) Multiplicity of agencies, overlapping responsibilities
iv) Inadequate training of personnel
v) Lesser attraction of maintenance jobs in career planning
vi) Lack of performance evaluation and regular monitoring
vii) Inadequate emphasis on preventive maintenance
viii) Lack of Operation Manual
ix) Lack of appreciation of the importance of facilities by the community
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 40
x) Lack of real time field information etc.
8.2 MAINTENANCE SCHEDULE
A maintenance schedule is required to be prepared to improve the level of
maintenance of water distribution networks and house connections through
improved co-ordination and planning of administrative and field work and through
the use of adequate techniques, equipment and materials for field maintenance.
The schedule has to be flexible so that it can achieve team action with the
available vehicles and tools.
Co-ordination of activities is required for spares and fittings, quality control of
materials used and services rendered.
Training of maintenance staff shall include training to achieve better public
relations with consumers apart from the technical skills.
8.3 ACTIVITIES IN MAINTENANCE SCHEDULE
Following activities are to be included in the schedule
Establishment of procedures for setting up maintenance schedules and obtaining
and processing the information provided by the public and the maintenance
teams.
Formation of maintenance teams for each type of service with provision for
continuous training.
Establishment of repair procedures for standard services.
Specification of appropriate tools.
Allocation of suitable transport, tools and equipment to each team Establishment
of time, labor and material requirement and output expected; time required and
other standards for each maintenance task, and
Monitoring the productivity of each team.
8.4 O&M FOR THE WATER SUPPLY PROJECT
The following aspects on O&M of water supply system shall be implemented in the
project town.
8.5 O&M FOR PUMPING STATION
According to available data the specific capacity of pumps should be measured at
regular intervals either monthly or bi-monthly and it should be compared with the
original specific capacity. As soon as 10 to 15% decrease in specific capacity is
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 41
observed steps should be taken to determine the cause and accordingly corrective
measures should be taken. Rehabilitation procedures should be initiated before the
specific capacity has declined by 25%. A check list given below can be used to
evaluate the performance of a well:
(I) Static water level in the intake well,
(II) Pumping rate after a specific period of continuous pumping,
(III) Specific capacity after a specified period of continuous pumping,
(IV) Sand content in a water sample after a specified period of continuous
pumping,
(V) Total depth of the well,
(VI) Efficiency of the well,
(VII) Normal pumping rate and hours per day of operation,
(VIII) General trend in water levels in wells in the area,
(IX) Draw down created in the production well because of pumping of nearby
wells.
(X) A significant change in any of the first seven conditions listed above indicates
that a well or pumping rate needs attention.
8.6 PROBLEMS IN TRANSMISSION MAINS
The followings are the main problems occurred in distribution system:
1. Leakage
2. Air Entrapment
3. Water Hammer
4. Lack of Records/ Maps etc.
A maintenance schedule is required to be prepared to improve the level of
maintenance of water supply Transmission system through improved co-ordination
and planning of administrative and fieldwork and through the use of adequate
techniques, equipment and materials for field maintenance. The schedule has to be
flexible so that it can achieve team action with the available vehicles and tools. Co-
ordination of activities is required for spares and fittings, quality control of materials
used and services rendered. Training of maintenance staff shall, apart from the
technical skills, include training to achieve better public relations with consumers.
Fol lowing act iv i t ies are to be inc luded in the schedule:
1. Develop and conduct a surveillance program for leaks in pipelines, pipe joints
and valves,
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 42
2. Develop and conduct a water quality surveillance program,
3. Develop and conduct a program for locating and repairing leaks including
rectifying cross connections if any, arrange for flushing, cleaning and
disinfecting the mains,
4. Establish procedures for setting up maintenance schedules and obtain and
process the information provided by the public and the maintenance teams
about the pipeline leaks,
5. Establish repair procedures for standard services and with provision for
continuous training of the team members,
6. Procure appropriate machinery, equipment and tools for repair of leaks and
replacement of pipes and valves,
7. Allocate suitable transport, tools and equipment to each maintenance team,
8. Establish time, labor and material requirement and output expected, time
required and other standards for each maintenance task, and
9. Arrange for monitoring the productivity of each team.
8.7 MAINTENANCE OF PIPELINES
Pipeline bursts/main breaks can occur at any time and the O & M agencies shall
have a plan for attending to such events. This plan must be written down,
disseminated to all concerned and the agency must always be in readiness to
implement the plan immediately after the pipe breaks reported.
After a pipe break is located, determine which valve is to be closed to isolate the
section where the break has occurred. Some important consumers may be on the
transmission system and having an industrial process dependent on water supply
which cannot be shut down as fast as the water supply lines are cut off and should
be notified about the break down. These consumers have to be informed about the
probable interruption in water supply and also the estimated time of resumption of
water supply. After the closure of the valve the dewatering/mud pumps are used to
drain the pipe break points. The sides of trenches have to be properly protected
before the workers enter the pit. The damaged pipe is removed, and the
accumulated silt is removed from inside the pipe and the damaged pipe is replaced
and the line is disinfected before bringing into use. A report shall be prepared
following every pipe break about the cause of such break, the resource required.
8.8 RECORDS AND REPORTS
A record system has to be developed which should be realistic and apply to the
operating problems involved in the distribution system. Management must be clear as
to why the data/information is collected, as to who will review the data and who will
respond to the results of review. The most efficient way to keep records is to plan what
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 43
data is essential and then prepare the formats followed by the persons concerned for
filling of the data, frequency and to whom the record is to be sent for review and report.
Sample records to be maintained are given below for guidance:
Updated system map.
Pressure and flow readings at selected monitoring points.
Persistent low pressure or negative pressure areas.
Age of pipes/quality of pipes Pipelines to be replaced. Presence of corrosive
water in the system.
Water budget for each zone served by one SR.
Number of Connection Given,
Number of meters out of order.
Status of fire hydrants and public taps.
Quantity measured at outlet of reservoir.
Quantity distributed/measured or billed.
Source of leaks and persistent leak points.
Status of bulk meters - function or not.
Status of consumer meters.
Facilities for repairs of consumer meters.
Number of unauthorized connections.
Residual chlorine levels at the pre-selected monitoring points.
Bacteriological quality of the water sampling points.
Persistent areas where residual chlorine is absent/where bacteriological samples are unwholesome.
Record on carrying out repairs on the following works and its cost:
i. The pipe line leaks or replacement of pipes.
ii. Change of gland ropes of the valves in distribution system.
iii. Replacement of parts.
iv. Replacement of manhole covers
Record on man hours spent on routine operations in the distribution system in the previous year and the cost thereof.
Record on total cost of repairs and replacements in previous year along with breakup of material cost and labor cost with amount spent on outside agencies for repairs and replacements.
Record on when the exposed piping was last painted and the cost of materials and labor cost thereof.
Record on the un-served areas - extension of pipelines- need for interconnections.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 44
8.9 REPORTS
With the accumulation of all essential data a report can be prepared evaluating the
O&M of the facility. The report can identify the deficiencies in the system and its
appurtenances and then plan future repairs to the network or valves and other
equipment or for replacement of defective valves or other equipment or additions and
extensions to the distribution network.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 45
9. ENVIRONMENTAL IMPACT ASSESSMENT
9.1 NEED FOR THE EIA
The objective of the project is to provide an efficient operation and maintenance of a
water supply system with safe drinking water. The EIA study aims to provide
sustainable development of the project and to address the impacts caused due to
project development and provide the following:
• Minimize potential adverse impacts on environment
• Provide mitigation measures for construction and operation phase
9.2 SCOPE OF THE EIA STUDY
The scope of EIA study includes the following
• Baseline environmental status of the project area.
• Assess Environmental impacts of the project
• Provide Mitigation Measures due to project activities
• Prepare Environmental Management Plan
9.3 ENVIRONMENTAL IMPACTS OF THE PROJECT
Although the project will have the above mentioned beneficial impacts on the
community, but there will some negative impacts during construction and operation
phases. The intensity of potential impacts may be reduced by adopting mitigation
measures as follows:
9.4 SITE CLEARANCE
The site clearance is required to setting up the construction activities of the project.
The activity involves the clearance of shrubs and bushes from the construction site.
Mitigation Measures
No illegal felling of trees
Debris shall be stored properly and disposed to the low-lying areas as identified
by Municipal Council.
9.5 PUBLIC SAFETY
The proposed project activities shall be carried out in the residential areas and
contractor has to give utmost care to minimize inconvenience to the public.
Mitigation Measures
Excavated pits shall be kept open for the minimum possible time.
Temporary fences shall be provided near construction sites especially around
deep excavated areas, located in the vicinity of schools, temple/ mosque, places
of public concentrations
Use and movement of heavy and mobile equipment shall be monitored. All the
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 46
drivers and operators should have valid license for operating such equipment.
Warning signs boards and signals in appropriate locations preferably 50m from
the construction sites shall be place. The warning sign boards shall be in Hindi.
9.6 ACCESS MANAGEMENT
During construction, especially in residential areas, contractor shall plan their work in
such a way that vehicular and human movement is not disturbed.
Mitigation Measures
Special safety measures in case of temple / mosque and public places for access
Special safety measures for access for children to schools;
Special safety measures for access of patients to hospitals;
9.7 STORAGE OF CONSTRUCTION MATERIALS
The requirement for storing the construction materials during execution phase for
different activities has to be confined appropriately inside the premises/storage yard.
In any case, waste materials should not be allowed to dump in haphazard way inside
the construction sites.
Mitigation Measures
However, temporary storage facility may be permitted under the following conditions:
Minimum period of temporary storage should be minimum in public place;
No disturbance to existing access;
No residual material shall be allowed to be left at site after consuming the same
9.8 GOOD HOUSEKEEPING AT CONSTRUCTION SITES
The contractor has to maintain good housekeeping at construction sites. Some of the
mitigation measures are as follows:
Mitigation Measures
Construction sites shall be kept free of clutter and debris.
Limited quantity of material shall be stored at construction sites
Place trash and debris in the proper receptacles located conveniently throughout
the job site.
Remove combustible materials such as wood and paper from the site promptly.
Keep form and scrap lumber with protruding nails cleared away from work areas,
passageways
Remove or bend over protruding nails prior to disposal and storage.
Keep storage, staging, and work areas, along with walkways on the construction
site, free of obstructions and debris.
Store tools and materials neatly and out of the way in storage bins or lockers and
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 47
keep flammable or hazardous wastes, if any, in covered, segregated waste
containers.
Disposal of debris and loose materials to identified sites.
Place protective guards across areas where workers may could fall or could face
an impalement hazard.
Construction sites shall be kept free of water logging or stagnation of water
Construction sites in built-up areas, adjacent to a public way, shall be suitably and
sufficiently fenced off and provided with controlled access points to prevent the
entry of unauthorized persons.
First aid box and firefighting equipment shall be provided at site.
Proper drinking and sanitation facilities shall be provided at site.
9.9 WATER POLLUTION
Dumping of construction debris or solid waste in the water body and improper
drainage in and around the construction sites may be one of the sources of the water
pollution during implementation phase.
Mitigation Measures
No washing of vehicles or equipment shall be permitted near the water source.
Construction debris shall not be disposed to the water sources.
9.10 NOISE POLLUTION
Various construction activities at generate high noise levels and will be a source of
noise pollution especially in rural residential areas.
Mitigation Measures
Machineries as well as equipment shall be maintained properly.
No noise generating equipment shall be allowed at construction sites.
Generator etc. shall be properly enclosed, and proper padding shall be placed below
such machinery to reduce vibration.
Special care must be taken near religious structures, schools, hospitals etc.
Machineries/equipment/vehicles shall meet the noise emission requirement of the
state pollution control board, HP.
9.11 AIR POLLUTION
The source of air pollution at sites may be vehicle movement, fugitive dust emission
from the construction sites, and loading and unloading of construction material.
Mitigation Measures
Properly maintained vehicles and equipment shall be used
Construction debris shall not be allowed to remain unattended at construction sites
Workers working in dusty areas such as concrete mixing equipment shall use
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 48
stringently nose masks.
Machineries/ equipment/ vehicles shall meet the emission standards as stipulated by
the State Pollution Control Board, HP
9.12 OCCUPATION SAFETY AND HEALTH ASPECTS
The contractor has to ensure occupation safety and health aspects by taking the
following mitigation measures:
Personal protection equipment (PPE) such as safety helmets, safety shoes, nose
masks, and ear plugs shall be provided to the workers and shall be used stringently
by the construction workers.
Contractor has to provide a first aid box at site offices and is to maintain update
information of nearest dispensary where the emergency may be dealt.
9.13 IMPACTS FROM CONSTRUCTION CAMPS
Generation of sewage and domestic waste will be the main source of pollution from
construction camps. Such wastes shall be properly disposed of in the
approved/designated landfill sites. Improper management of such waste may have
the following adverse impacts in the neighboring areas by providing:
A breeding ground for mosquitoes,
An unaesthetic view of the area,
Health and hygiene-related problems
9.14 OTHER IMPACTS
Some short-term impacts may take place during the construction phase, - the locations
and contexts of such impacts are:
a) Site Office
Temporary impacts may occur due to construction of site offices and labor camps.
These impacts are likely to be marginal and can be mitigated by sensitizing and
educating the workers
b) Equipment Storage and Machinery Maintenance
The site area should have a proper maintenance shed for regular maintenance of the
construction vehicles. The waste emanating from the maintenance shed should not be
allowed to spread over the construction site. Oil and grease change of equipment and
vehicles should be carried out in the service areas designated for vehicles. Wastes
should be collected and disposed of properly and expeditiously.
c) Employment Opportunities
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 49
Construction activities can provide employment opportunities to the local population
and residents of the neighboring area. People may come to provide labor or service
the construction camps. It is necessary to ensure that after completion of construction
work, such temporary establishments are removed promptly and not used for setting
up squatter colonies.
d) Property Access
Access to buildings in sites where construction activities are going on will be
affected, leading to minor economic loss. Such minor impacts will be restricted to the
construction phase only. However, temporary access to such premises should be
provided and such areas should be restored at the earliest.
SHIMLA JAL PRABANDHAN NIGAM LIMITD DPR FOR BULK WATER SUPPLY FROM SUTLEJ RIVER
Yash Innovative Solutions LLP
Aurangabad Maharashtra Client Circulation P a g e | 50
10. PROJECT BENEFITS
Economic, industrial and commercial growth of any area is primarily depending upon
availability and utilization of the natural resources. SHIMLA city will get tremendous
benefits from the 24x7 water supply scheme. Some of the beneficiaries of the 24x7 water
supply scheme for SHIMLA are focused below.
A. Citizens will get better urban services and eventually leads to improvement/ upliftment
of lifestyle
B. Positive positioning of Shimla city
C. Improvement in hygiene
D. Investment in and around Shimla City
E. Restrict the migration of Shimla to other urban centers
F. Will create employment opportunities through new investments by large industrial
players
G. Shimla will be positioned as sustainable city in Country
DESIGN
STATEMENT
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
2017 2020 2035 2050 2017 2020 2035 2050 2017 2020 2035 2050
A Domestic Demand
Population Census of India 2001-2011 225119 235048 284694 334340 226317 237182 294880 358196 230068 243250 318467 413674
Domestic Demand 135lpcd 30.4 31.7 38.4 45.1 30.6 32.0 39.8 48.4 31.1 32.84 42.99 55.85
B Floating population demand 45 lpcd per day 44000 45333 52630 61102 44000 45333 52630 61102 44000 45333 52630 61102
Over night tripers 135 lpcd per overnight stay 22000 22667 26315 30551 22000 22667 26315 30551 22000 23347 31421 42289
5.9 6.1 7.1 8.2 5.9 6.1 7.1 8.2 5.9 6.24 8.02 10.36
C Institutional 7.4 7.7 9.4 11.4 7.4 7.8 9.7 12.2 7.4 7.89 10.62 14.29
Schools
Statistic Abstract,Government
of Himachal Pradesh 2015-
2016
103548 107639 130651 158582 103548 108278 135373 169248 103548 109886 147893 199044
OfficesStastical and Economical
Survey 2016-201745547 47347 57468 69754 45547 47628 59545 74446 45547 48335 65052 87552
Hospitals(<100) 631 656 796 966 631 660 825 1031 631 670 901 1213
Hospitals(>100) 1125 1169 1419 1723 1125 1176 1471 1839 1125 1194 1607 2163
Schools 45 lpcd per school enrollment 4.7 4.8 5.9 7.1 4.7 4.9 6.1 7.6 4.7 4.9 6.7 9.0
Offices 45 lpcd per office employee 2.0 2.1 2.6 3.1 2.0 2.1 2.7 3.4 2.0 2.2 2.9 3.9
Hospitals(<100) 350 lpcd per hospital bed 0.2 0.2 0.3 0.3 0.2 0.2 0.3 0.4 0.2 0.2 0.3 0.4
Hospitals(>100) 450 lpcd per hospital bed 0.5 0.5 0.6 0.8 0.5 0.5 0.7 0.8 0.5 0.5 0.7 1.0
D IndustrialDemand data from SMC
website0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1
E CantonmentDemand data from SMC
website0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54
FAdditional Shimla Planning
Area
Population Data from TCP Office,Shimla 33928 35530 43542 51553 33928 35714 45347 56154 33928 36537 52916 76638
135 lpcd 4.6 4.8 5.9 7.0 4.6 4.8 6.1 7.6 4.6 4.93 7.14 10.35
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Water Demand Calculations
Moderate Growth High Growth
Directory obn Medical and
Public Health Institutions in
Himachal
Sr.No Demand type SourceLow Growth
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.51
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
2017 2020 2035 2050 2017 2020 2035 2050 2017 2020 2035 2050
Moderate Growth High GrowthSr.No Demand type Source
Low Growth
Total 49.0 51.0 61.4 72.4 49.1 51.4 63.4 77.0 49.7 52.5 69.4 91.5
G 15% Water Lossess 57.6 60.0 72.3 85.1 57.8 60.4 74.6 90.6 58.4 61.82 81.67 107.63
H Fire 1.5 1.6 1.8 2 1.5 1.6 1.8 2 1.5 1.6 1.8 2
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.52
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
YearProjected
Population
Domestic
Demand
@135 LPCD
floating
Demand
Institutional
DemandIndustrial
Cantonment
Board
Demand
Upcoming satellite
town Demand
Deamnd at
Consumer
end in MLD
Demand at
Source (with
15% losses)
in MLD
Fire
Demand
Water
Available
from
Existing
Source
Demand from
Sutlej
Full Demand
from Sutlej
for design of
Single pipe
system
2020 243250 32838750 6242445 7891745 100000 540000 4932495 52.55 61.82 1.60 40.00 21.82 21.82
2021 248264 33515703 6361224 8073697 100000 540000 5079906 53.67 63.14 1.61 40.00 23.14 23.14
2022 253279 34192656 6480003 8255649 100000 540000 5227317 54.80 64.47 1.63 40.00 24.47 24.47
2023 258293 34869609 6598782 8437601 100000 540000 5374728 55.92 65.79 1.64 40.00 25.79 25.79
2024 263308 35546562 6717561 8619553 100000 540000 5522139 57.05 67.11 1.65 40.00 27.11 27.11
2025 268322 36223515 6836340 8801505 100000 540000 5669550 58.17 68.44 1.67 40.00 28.44 28.44
2026 273337 36900468 6955119 8983457 100000 540000 5816961 59.30 69.76 1.68 40.00 29.76 29.76
2027 278351 37577421 7073898 9165409 100000 540000 5964372 60.42 71.08 1.69 40.00 31.08 31.08
2028 283366 38254374 7192677 9347361 100000 540000 6111783 61.55 72.41 1.71 40.00 32.41 32.41
2029 288380 38931327 7311456 9529313 100000 540000 6259194 62.67 73.73 1.72 40.00 33.73 33.73
2030 293395 39608280 7430235 9711265 100000 540000 6406605 63.80 75.05 1.73 40.00 35.05 35.05
2031 298409 40285233 7549014 9893217 100000 540000 6554016 64.92 76.38 1.75 40.00 36.38 36.38
2032 303424 40962186 7667793 10075169 100000 540000 6701427 66.05 77.70 1.76 40.00 37.70 37.70
2033 308438 41639139 7786572 10257121 100000 540000 6848838 67.17 79.03 1.77 40.00 39.03 39.03
2034 313453 42316092 7905351 10439073 100000 540000 6996249 68.30 80.35 1.79 40.00 40.35 40.35
2035 318467 42993045 8024130 10621025 100000 540000 7143660 69.42 81.67 1.80 40.00 41.67 41.67
2036 324814 43849908 8179962 10865938 100000 540000 7357158 70.89 83.40 1.81 40.00 43.40 43.40
2037 331161 44706771 8335794 11110851 100000 540000 7570656 72.36 85.13 1.83 40.00 45.13 45.13
2038 337508 45563634 8491626 11355764 100000 540000 7784154 73.84 86.86 1.84 40.00 46.86 46.86
2039 343856 46420497 8647458 11600677 100000 540000 7997652 75.31 88.60 1.85 40.00 48.60 48.60
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Water Demand Calculations
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.53
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
YearProjected
Population
Domestic
Demand
@135 LPCD
floating
Demand
Institutional
DemandIndustrial
Cantonment
Board
Demand
Upcoming satellite
town Demand
Deamnd at
Consumer
end in MLD
Demand at
Source (with
15% losses)
in MLD
Fire
Demand
Water
Available
from
Existing
Source
Demand from
Sutlej
Full Demand
from Sutlej
for design of
Single pipe
system
2040 350203 47277360 8803290 11845590 100000 540000 8211150 76.78 90.33 1.87 40.00 50.33 50.33
2041 356550 48134223 8959122 12090503 100000 540000 8424648 78.25 92.06 1.88 40.00 52.06 52.06
2042 362897 48991086 9114954 12335416 100000 540000 8638146 79.72 93.79 1.89 40.00 53.79 53.79
2043 369244 49847949 9270786 12580329 100000 540000 8851644 81.19 95.52 1.91 40.00 55.52 55.52
2044 375591 50704812 9426618 12825242 100000 540000 9065142 82.66 97.25 1.92 40.00 57.25 57.25
2045 381938 51561675 9582450 13070155 100000 540000 9278640 84.13 98.98 1.93 40.00 58.98 58.98
2046 388285 52418538 9738282 13315068 100000 540000 9492138 85.60 100.71 1.95 40.00 60.71 60.71
2047 394633 53275401 9894114 13559981 100000 540000 9705636 87.08 102.44 1.96 40.00 62.44 62.44
2048 400980 54132264 10049946 13804894 100000 540000 9919134 88.55 104.17 1.97 40.00 64.17 64.17
2049 407327 54989127 10205778 14049807 100000 540000 10132632 90.02 105.90 1.99 40.00 65.90 65.90
2050 413674 55845990 10361610 14294720 100000 540000 10346130 91.49 107.63 2.00 40.00 67.63 67.63
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.54
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
1 Population of Intermediate Stage (Year 2035) 318467 Souls
2 Requirement of Town 41.67 MLD
3 Hours of Pumping 24 Hours
4 Capacity Required 41.67 MLD
5 Deduct capacity of Existing WTP 0 MLD
6 Proposed WTP capacity 41.67 MLD
42.00 MLD
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Statement Showing capacity calculations for WTP
Hence provide WTP of capcity
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.55
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Sr no DetailsLSL at
Start Point
FSL at
Discharge
Point
Static
HeadLength
Atmospheric
pressure
Average
Vapour
Pressure
1Rising Main from Intake to
Desilting Tank600.2 664.18 63.98 139 99.12 2.60
2Rising Main from WTP to
Devidhar654.18 1312.26 658.08 2294 98.92 2.60
3Rising Main from Devidhar to
Dummi1308.26 1817.64 509.38 8312 96.57 2.60
4Rising Main from Dummi to
Ridge1813.64 2208.46 394.82 8143 94.83 2.60
5Rising Main from Dummi to
Sanjauli1813.64 2256.3 442.66 10065 94.83 2.60
e =
Patm = Atmosphere pressure
Pv = Vapour pressure of liquid
inside pipe
Sf = Safety factor 4
e = Wall(Shell) thickness
C = 345000000 kpa
Atmospheric pressure
at Altitude 0 101.33 Kpa 14.70 psi
at Altitude 500 99.49 Kpa 14.43 psi
at Altitude 1000 97.63 Kpa 14.16 psi
at Altitude 1500 95.91 Kpa 13.91 psi
at Altitude 2000 94.19 Kpa 13.66 psi
at Altitude 2500 92.46 Kpa 13.41 psi
Vapour Pressure
At 10oC 1.23 Kpa 0.18 psi
At 20oC 2.33 Kpa 0.34 psi
At 30oC 4.24 Kpa 0.61 psi
Rising Main
from Intake
to Desilting
Tank
Rising Main
from WTP
to Devidhar
Rising Main
from
Devidhar to
Dummi
Rising Main
from
Dummi to
Ridge
Rising Main
from Dummi to
Sanjauli
Hence Wall thickness
Constant=0.010387 0.010380 0.010295 0.010231 0.010231
1 508.00 5.28 5.27 5.23 5.2 5.2
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Design for Collapsing Pressure
Minimum Thickness(e) For Collapsing Pressure is given by,
Required Wall thickness
Wall thickness for collapsing pressure for different diamteres without internal mortor lining are worked
out as follow
Outside Diameter in mm as
per IS 3589S.N.
RAW WATER RISING MAIN
3S F
D P a tm P vC
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNL
Page No.56
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Rising Main
from Intake
to Desilting
Tank
Rising Main
from WTP
to Devidhar
Rising Main
from
Devidhar to
Dummi
Rising Main
from
Dummi to
Ridge
Rising Main
from Dummi to
Sanjauli
Required Wall thickness
Outside Diameter in mm as
per IS 3589S.N.
2 558.80 5.8 5.8 5.75 5.72 5.72
3 609.60 6.33 6.33 6.28 6.24 6.24
4 660.40 6.86 6.85 6.8 6.76 6.76
5 711.20 7.39 7.38 7.32 7.28 7.28
6 762.00 7.91 7.91 7.84 7.8 7.8
7 812.80 8.44 8.44 8.37 8.32 8.32
8 863.60 8.97 8.96 8.89 8.84 8.84
9 914.40 9.5 9.49 9.41 9.35 9.35
10 965.20 10.03 10.02 9.94 9.87 9.87
11 1016.00 10.55 10.55 10.46 10.39 10.39
12 1066.80 11.08 11.07 10.98 10.91 10.91
13 1117.60 11.61 11.6 11.51 11.43 11.43
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNL
Page No.57
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
SrNo Description SI Unit FPS Unit
1 Shell Diameter 762 mm 30.000 inches
2 Plate thickness 7.92 mm 0.312 inches
3 Mortar Lining thickness 0 mm 0.000 inches
4 Coating thickness 0 mm 0.000 inches
5 Minimum Earth cover H 500 mm 19.685 inches
6 Grade of Steel used API X 65
7 Density of Earth fill w 1800 kg/cum 112.320 lb/cuft
8 Modulus of Elasticity steel E 2000000 kg/sqcm 28440000 lb/sqin
9 Modulus of Soil Reaction E' 28.12 kg/sqcm 400 lb/sqin
10 Yield Strength 450 N/sqmm 65264 lb/sqin
11 Tensile Strength 535 N/sqmm 77591 lb/sqin
A) Check Against Deflection
1 Dead Load on the Conduit (Pb)
Unit load due to backfill ( Pb ) 18 kN/m2
2 Superimposed Load ,Wc
Wheel load ( IRC class AA ) = 6.25 T
Impact factor
As per IS 783-85 Clause No. 11.2 Impact factor for cover >0.9 m
a= 1
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
RAW WATER RISING MAIN
MS Pipe Design and Checks
C
C
bD
DHP
l
PCW PC
SDHl 215.1
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.58
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
l= 2.099 m
l/(2*H)= 2.099
D/(2*H)= 0.762
From IS 783-85 Figure 3 , for l/2H= 2.099 & D/2H= 0.762 Cp = 0.81
WC= 2.41 T/m
= 23.64 kN/m
Unit load due to traffic load (Ps) = 31.02 kN/m2
Deflection determination
Iowa- Sprangler Deflection Equation
rx = Horizantal deflection of pipe
DL = Deflection lag factor = 1
DR = Rerounding factor = 1
K = Bedding constant = 0.1
D = Outer Diameter (mm)
E = Modulus of elasticity of steel = 2.1x105 N/m
2
I = Transverse moment of inertia per unit
length of individual pipe wall components ( = t3/12) mm3
E' = Modulus of soil reaction, kPa
Pipe wall Stiffness =
= 19309.54 N/m2
= 19.30954 kPa
rx/D = 0.01453
'
3061.08 E
D
EI
PPDKD
D
x sbL
R
3D
IE
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.59
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
= 1.45255 %
Which is within permissible limits (2% - for cement mortar lined &coated pipe)
B) Check against Buckling
Allowable buckling pressure (qa) is given by Maximum buckling pressure is given by
where
qa = allowable buckling pressure ,in psi where
FS = Design factor (3.0) hw = Height of water surface above top
D = Outer Diameter (in) of pipe (in)
RW = water buoyancy factor γw = specific weight of water = 0.0361 lb/cu.in
= 1-0.33(hw/h), 0<=hw<=h Wc = vertical soil load on pipe per unit length, lb/in
hw = Height of water surface above top WL = Live load on pipe per unit length, lb/in
of pipe (in)
h= Height of soil surface above top
of pipe (in)
B' = empirical coefficient of elastic support
=
EI = Pipe wall stiffness
Stiffness of pipe 71849.33 Specific weight of water 0.0361 lb/cu in
Factor H/D 0.656168 ht.Of Water 3.281 feet
Design factor 3 FS Water Buonvy factor 0.3400013 Rw
Height of water above pipe 39.37 in soil Load (Wc) 460.62992 lb/inch
2
1
3
''32
1
D
EIEBR
FSq Wa
He 065.041
1
D
W
D
WRh LC
Www
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.60
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Water buoyancy factor 0.340001 Rw Live Load ( WL) 135.14246 lb/inch
Elastic support coefficient 0.217607 B' (From IS 783)
Allowable buckling pressure 16.73082 psi Max. Buckling Pressure 2.231766 psi
C) Check for Vacuum Condition:
Stewart formula for collapsing pressure
Pc = 58.160 psi
Maximum Vacuum which can be created = Atm. Pressure - Vapour Pressure at 36oC
Factor of safety against Vacuum condition =
= 14.0 psi
Thus the pipeline is safe against
collapsing under full vaccum
condition = 4.150 > 4 OK
Factor of safety Condition Fulfilled
D ) Thickness Required For Handling
For pipe size greater than1350 mm
Thickness = inches
Diameter 746.16 mm
Thickness required for handling 3.1354 mm
As Max. buckling pressure is less than allowable buckling pressure……safe
Reference AWWA Manual, M11
400
20D
3
250200000
d
tPc
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.61
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Daily Demand 67.63
Supply Hrs 24
Design Discharge 67.63
C 140.00
Yeild Stress 450.00
Welding Efficiency 0.80
Design Factor for Working Pressure
excluding Surge0.9
Design Factor for Working Pressure
including Surge0.9
Outer Diameter 711.20 762.00 812.80 863.60 914.40 965.20 1016.00 1066.80 1117.60
Internal Diameter 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
Thickness req. for Collapsing
pressure7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
Rate of Friction 4.22 2.99 2.19 1.64 1.23 0.95 0.74 0.58 0.46
Normal Velocity 2.06 1.79 1.58 1.40 1.24 1.12 1.01 0.91 0.83
Velocity of Wave Pressure 1043.34 1026.09 1034.63 1041.08 1026.78 1032.96 1039.26 1027.05 1032.38
Water Hammer 219.23 187.25 166.18 148.30 130.13 117.62 106.92 95.64 87.67
Velocity Head 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-139 63.98 0.139 0.65 0.46 0.34 0.25 0.19 0.15 0.11 0.09 0.07
Working Pressure excluding Surge 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-139 68.63 68.44 68.32 68.23 68.17 68.13 68.09 68.07 68.05
Working Pressure including Surge 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-139 287.85 255.68 234.50 216.53 198.30 185.75 175.02 163.71 155.72
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Raw Water Rising Main from Jakwell to WTP
Chainage Static Head LengthFrictional Head for Diameter
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.62
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Thickness req. for Working Pressure
excluding Surge as per Barlow's
equation
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-139 0.87 0.93 0.99 1.05 1.11 1.17 1.23 1.29 1.35
Thickness req. for Working Pressure
including Surge Barlow's equation695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-139 3.63 3.46 3.39 3.32 3.22 3.19 3.16 3.11 3.09
Thickness req. for Working Pressure
excluding Surge as per IS-5822695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-139 2.24 2.29 2.34 2.39 2.44 2.49 2.55 2.60 2.65
Thickness req. for Working Pressure
including Surge as per IS-5822695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-139 4.58 4.44 4.37 4.32 4.24 4.21 4.18 4.14 4.13
Required Thickness Length 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-139 139 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.63
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Daily Demand 67.63
Supply Hrs 24
Design Discharge 67.63
C 140.00
Yeild Stress 450.00
Welding Efficiency 0.80
Design Factor for Working Pressure
excluding Surge0.9
Design Factor for Working Pressure
including Surge0.9
Outer Diameter 711.2 762 812.8 863.6 914.4 965.2 1016 1066.8 1117.6
Internal Diameter 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
Thickness req. for Collapsing
pressure7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
Rate of Friction 4.22 2.99 2.19 1.64 1.23 0.95 0.74 0.58 0.46
Normal Velocity 2.06 1.79 1.58 1.40 1.24 1.12 1.01 0.91 0.83
Velocity of Wave Pressure 1043.34 1026.09 1034.63 1041.08 1026.78 1032.96 1039.26 1027.05 1032.38
Water Hammer 219.23 187.25 166.18 148.30 130.13 117.62 106.92 95.64 87.67
Velocity Head 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
139-349 642.86 0.21 0.97 0.69 0.51 0.38 0.28 0.22 0.17 0.13 0.11
349-439 596.92 0.09 0.42 0.30 0.22 0.16 0.12 0.09 0.07 0.06 0.05
439-499 536.64 0.06 0.28 0.20 0.14 0.11 0.08 0.06 0.05 0.04 0.03
499-559 469.93 0.06 0.28 0.20 0.14 0.11 0.08 0.06 0.05 0.04 0.03
559-619 421.57 0.06 0.28 0.20 0.14 0.11 0.08 0.06 0.05 0.04 0.03
619-679 357.9 0.06 0.28 0.20 0.14 0.11 0.08 0.06 0.05 0.04 0.03
679-739 265.05 0.06 0.28 0.20 0.14 0.11 0.08 0.06 0.05 0.04 0.03
739-1219 205.47 0.48 2.23 1.58 1.16 0.86 0.65 0.50 0.39 0.31 0.25
1219-1579 153.53 0.36 1.67 1.19 0.87 0.65 0.49 0.38 0.29 0.23 0.18
1579-2269 95.71 0.69 3.20 2.27 1.67 1.24 0.94 0.72 0.56 0.44 0.35
2269-2433 41.76 0.164 0.76 0.54 0.40 0.30 0.22 0.17 0.13 0.10 0.08
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Frictional Head for Diameter
Raw Water Rising Main from WTP to Devidhar
Chainage Static Head Length
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.64
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Working Pressure excluding Surge 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
139-349 647.83 647.55 647.37 647.24 647.14 647.08 647.03 646.99 646.97
349-439 601.34 601.22 601.14 601.08 601.04 601.01 600.99 600.98 600.97
439-499 540.92 540.84 540.78 540.75 540.72 540.70 540.69 540.68 540.67
499-559 474.21 474.13 474.07 474.04 474.01 473.99 473.98 473.97 473.96
559-619 425.85 425.77 425.71 425.68 425.65 425.63 425.62 425.61 425.60
619-679 362.18 362.10 362.04 362.01 361.98 361.96 361.95 361.94 361.93
679-739 269.33 269.25 269.19 269.16 269.13 269.11 269.10 269.09 269.08
739-1219 211.70 211.05 210.63 210.33 210.12 209.97 209.86 209.78 209.72
1219-1579 159.20 158.72 158.40 158.18 158.02 157.91 157.82 157.76 157.71
1579-2269 102.91 101.98 101.38 100.95 100.65 100.43 100.27 100.15 100.06
2269-2433 46.52 46.30 46.16 46.06 45.98 45.93 45.89 45.86 45.84
Working Pressure including Surge 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
139-349 867.06 834.80 813.55 795.54 777.28 764.70 753.95 742.63 734.64
349-439 820.56 788.46 767.32 749.38 731.18 718.64 707.92 696.62 688.64
439-499 760.15 728.08 706.97 689.05 670.86 658.33 647.61 636.32 628.34
499-559 693.44 661.37 640.26 622.34 604.15 591.62 580.90 569.61 561.63
559-619 645.08 613.01 591.90 573.98 555.79 543.26 532.54 521.25 513.27
619-679 581.41 549.34 528.23 510.31 492.12 479.59 468.87 457.58 449.60
679-739 488.56 456.49 435.38 417.46 399.27 386.74 376.02 364.73 356.75
739-1219 430.93 398.30 376.81 358.63 340.25 327.60 316.78 305.41 297.39
1219-1579 378.43 345.96 324.58 306.48 288.15 275.53 264.75 253.40 245.39
1579-2269 322.14 289.23 267.56 249.25 230.78 218.05 207.20 195.79 187.74
2269-2433 265.75 233.55 212.34 194.35 176.12 163.56 152.82 141.50 133.52
Thickness req. for Working Pressure
excluding Surge Barlow's equation695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
139-349 8.18 8.77 9.35 9.93 10.52 11.10 11.68 12.27 12.85
349-439 7.59 8.15 8.68 9.22 9.77 10.31 10.85 11.40 11.94
439-499 6.83 7.33 7.81 8.29 8.79 9.27 9.76 10.26 10.74
499-559 5.99 6.42 6.85 7.27 7.71 8.13 8.55 8.99 9.41
559-619 5.38 5.77 6.15 6.53 6.92 7.30 7.68 8.07 8.45
619-679 4.57 4.91 5.23 5.55 5.89 6.21 6.53 6.87 7.19
679-739 3.40 3.65 3.89 4.13 4.38 4.62 4.86 5.10 5.34
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.65
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
739-1219 2.67 2.86 3.04 3.23 3.42 3.60 3.79 3.98 4.17
1219-1579 2.01 2.15 2.29 2.43 2.57 2.71 2.85 2.99 3.13
1579-2269 1.30 1.38 1.46 1.55 1.64 1.72 1.81 1.90 1.99
2269-2433 0.59 0.63 0.67 0.71 0.75 0.79 0.83 0.87 0.91
Thickness req. for Working Pressure
including Surge Barlow's equation695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
139-349 10.95 11.31 11.75 12.20 12.64 13.12 13.61 14.09 14.59
349-439 10.36 10.68 11.08 11.49 11.89 12.33 12.78 13.21 13.68
439-499 9.60 9.87 10.21 10.57 10.91 11.29 11.69 12.07 12.48
499-559 8.76 8.96 9.25 9.54 9.82 10.15 10.48 10.80 11.16
559-619 8.15 8.31 8.55 8.80 9.04 9.32 9.61 9.89 10.20
619-679 7.34 7.44 7.63 7.83 8.00 8.23 8.46 8.68 8.93
679-739 6.17 6.19 6.29 6.40 6.49 6.63 6.79 6.92 7.09
739-1219 5.44 5.40 5.44 5.50 5.53 5.62 5.72 5.79 5.91
1219-1579 4.78 4.69 4.69 4.70 4.69 4.73 4.78 4.81 4.87
1579-2269 4.07 3.92 3.86 3.82 3.75 3.74 3.74 3.71 3.73
2269-2433 3.36 3.16 3.07 2.98 2.86 2.81 2.76 2.68 2.65
Thickness req. for Working Pressure
excluding Surge as per IS-5822695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
139-349 8.40 8.89 9.39 9.88 10.37 10.86 11.35 11.84 12.34
349-439 7.91 8.37 8.83 9.28 9.74 10.20 10.66 11.11 11.57
439-499 7.27 7.69 8.10 8.51 8.92 9.33 9.75 10.16 10.57
499-559 6.57 6.93 7.29 7.65 8.01 8.37 8.74 9.10 9.46
559-619 6.05 6.38 6.70 7.03 7.35 7.68 8.00 8.33 8.65
619-679 5.38 5.65 5.93 6.21 6.48 6.76 7.03 7.31 7.59
679-739 4.39 4.59 4.80 5.00 5.21 5.41 5.62 5.83 6.03
739-1219 3.77 3.93 4.08 4.24 4.40 4.56 4.72 4.88 5.04
1219-1579 3.21 3.33 3.44 3.56 3.68 3.80 3.92 4.04 4.16
1579-2269 2.61 2.67 2.75 2.82 2.89 2.96 3.04 3.11 3.19
2269-2433 2.00 2.03 2.07 2.10 2.14 2.17 2.21 2.24 2.27
Thickness req. for Working Pressure
including Surge as per IS-5822695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.66
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
139-349 10.71 11.01 11.39 11.77 12.13 12.54 12.96 13.36 13.79
349-439 10.22 10.49 10.83 11.18 11.51 11.88 12.27 12.63 13.03
439-499 9.59 9.80 10.10 10.41 10.69 11.02 11.36 11.67 12.03
499-559 8.89 9.05 9.30 9.56 9.78 10.06 10.35 10.62 10.92
559-619 8.38 8.50 8.72 8.94 9.13 9.37 9.62 9.85 10.11
619-679 7.70 7.78 7.95 8.12 8.26 8.45 8.66 8.84 9.05
679-739 6.72 6.73 6.82 6.92 6.99 7.12 7.25 7.36 7.50
739-1219 6.11 6.07 6.11 6.16 6.18 6.26 6.35 6.41 6.51
1219-1579 5.55 5.47 5.47 5.49 5.47 5.51 5.55 5.58 5.63
1579-2269 4.95 4.82 4.78 4.75 4.68 4.67 4.68 4.65 4.67
2269-2433 4.35 4.18 4.10 4.03 3.93 3.88 3.84 3.78 3.75
Required Thickness Length 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
139-349 210 10.95 11.31 11.75 12.20 12.64 13.12 13.61 14.09 14.59
349-439 90 10.36 10.68 11.08 11.49 11.89 12.33 12.78 13.21 13.68
439-499 60 9.60 9.87 10.21 10.57 10.91 11.29 11.69 12.07 12.48
499-559 60 8.89 9.05 9.30 9.56 9.82 10.31 11.13 11.13 11.91
559-619 60 8.38 8.50 8.74 9.53 9.53 10.31 11.13 11.13 11.91
619-679 60 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
679-739 60 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
739-1219 480 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
1219-1579 360 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
1579-2269 690 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
2269-2433 164 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.67
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Daily Demand 67.63
Supply Hrs 24
Design Discharge 67.63
C 140.00
Yeild Stress 450.00
Welding Efficiency 0.80
Design Factor for Working Pressure
excluding Surge0.9
Design Factor for Working Pressure
including Surge0.9
Outer Diameter 711.2 762 812.8 863.6 914.4 965.2 1016 1066.8 1117.6
Internal Diameter 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
Thickness req. for Collapsing
pressure7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
Rate of Friction 4.22 2.99 2.19 1.64 1.23 0.95 0.74 0.58 0.46
Normal Velocity 2.06 1.79 1.58 1.40 1.24 1.12 1.01 0.91 0.83
Velocity of Wave Pressure 1043.34 1026.09 1034.63 1041.08 1026.78 1032.96 1039.26 1027.05 1032.38
Water Hammer 219.23 187.25 166.18 148.30 130.13 117.62 106.92 95.64 87.67
Velocity Head 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-900 509.38 0.9 4.18 2.96 2.17 1.62 1.22 0.94 0.73 0.58 0.46
900-1500 566.62 0.6 2.79 1.98 1.45 1.08 0.81 0.63 0.49 0.38 0.31
1500-1950 621.07 0.45 2.09 1.48 1.09 0.81 0.61 0.47 0.37 0.29 0.23
1950-3810 681.69 1.86 8.63 6.12 4.49 3.35 2.52 1.94 1.52 1.19 0.95
3810-7050 679.32 3.24 15.04 10.67 7.82 5.84 4.39 3.38 2.64 2.07 1.66
7050-7230 621.38 0.18 0.84 0.59 0.43 0.32 0.24 0.19 0.15 0.12 0.09
7230-7440 560.54 0.21 0.97 0.69 0.51 0.38 0.28 0.22 0.17 0.13 0.11
7440-7500 518.41 0.06 0.28 0.20 0.14 0.11 0.08 0.06 0.05 0.04 0.03
7500-7560 455.28 0.06 0.28 0.20 0.14 0.11 0.08 0.06 0.05 0.04 0.03
7560-7740 405.35 0.18 0.84 0.59 0.43 0.32 0.24 0.19 0.15 0.12 0.09
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Raw Water Rising Main from WTP to Devidhar
Chainage Static Head LengthFrictional Head for Diameter
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.68
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
Chainage Static Head LengthFrictional Head for Diameter
7740-7860 359.17 0.12 0.56 0.40 0.29 0.22 0.16 0.13 0.10 0.08 0.06
7860-7980 308.25 0.12 0.56 0.40 0.29 0.22 0.16 0.13 0.10 0.08 0.06
7980-8040 254.91 0.06 0.28 0.20 0.14 0.11 0.08 0.06 0.05 0.04 0.03
8040-8100 201.38 0.06 0.28 0.20 0.14 0.11 0.08 0.06 0.05 0.04 0.03
8100-8190 142.28 0.09 0.42 0.30 0.22 0.16 0.12 0.09 0.07 0.06 0.05
8190-8250 81.05 0.06 0.28 0.20 0.14 0.11 0.08 0.06 0.05 0.04 0.03
8250-8312 35.05 0.062 0.29 0.20 0.15 0.11 0.08 0.06 0.05 0.04 0.03
Working Pressure excluding Surge 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-900 517.56 516.34 515.55 515.00 514.60 514.32 514.11 513.96 513.84
900-1500 573.41 572.60 572.07 571.70 571.43 571.25 571.11 571.00 570.93
1500-1950 627.16 626.55 626.16 625.88 625.68 625.54 625.44 625.36 625.30
1950-3810 694.32 691.81 690.18 689.04 688.21 687.63 687.21 686.88 686.64
3810-7050 698.36 693.99 691.14 689.16 687.71 686.70 685.96 685.39 684.98
7050-7230 626.22 625.97 625.81 625.70 625.62 625.57 625.53 625.50 625.47
7230-7440 565.51 565.23 565.05 564.92 564.82 564.76 564.71 564.67 564.65
7440-7500 522.69 522.61 522.55 522.52 522.49 522.47 522.46 522.45 522.44
7500-7560 459.56 459.48 459.42 459.39 459.36 459.34 459.33 459.32 459.31
7560-7740 410.19 409.94 409.78 409.67 409.59 409.54 409.50 409.47 409.44
7740-7860 363.73 363.57 363.46 363.39 363.33 363.30 363.27 363.25 363.23
7860-7980 312.81 312.65 312.54 312.47 312.41 312.38 312.35 312.33 312.31
7980-8040 259.19 259.11 259.05 259.02 258.99 258.97 258.96 258.95 258.94
8040-8100 205.66 205.58 205.52 205.49 205.46 205.44 205.43 205.42 205.41
8100-8190 146.70 146.58 146.50 146.44 146.40 146.37 146.35 146.34 146.33
8190-8250 85.33 85.25 85.19 85.16 85.13 85.11 85.10 85.09 85.08
8250-8312 39.34 39.25 39.20 39.16 39.13 39.11 39.10 39.09 39.08
Working Pressure including Surge 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-900 736.79 703.59 681.74 663.30 644.73 631.94 621.04 609.59 601.51
900-1500 792.63 759.84 738.25 720.00 701.57 688.87 678.03 666.64 658.60
1500-1950 846.39 813.80 792.34 774.18 755.81 743.16 732.36 721.00 712.97
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.69
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
Chainage Static Head LengthFrictional Head for Diameter
1950-3810 913.55 879.06 856.36 837.34 818.35 805.26 794.13 782.52 774.31
3810-7050 917.59 881.23 857.32 837.45 817.85 804.33 792.89 781.03 772.65
7050-7230 845.44 813.22 792.00 774.00 755.76 743.19 732.45 721.13 713.15
7230-7440 784.74 752.48 731.23 713.22 694.96 682.38 671.63 660.31 652.32
7440-7500 741.92 709.85 688.74 670.82 652.63 640.10 629.38 618.09 610.11
7500-7560 678.79 646.72 625.61 607.69 589.50 576.97 566.25 554.96 546.98
7560-7740 629.41 597.19 575.97 557.97 539.73 527.16 516.42 505.10 497.12
7740-7860 582.95 550.81 529.64 511.68 493.47 480.92 470.19 458.88 450.90
7860-7980 532.03 499.89 478.72 460.76 442.55 430.00 419.27 407.96 399.98
7980-8040 478.42 446.35 425.24 407.32 389.13 376.60 365.88 354.59 346.61
8040-8100 424.89 392.82 371.71 353.79 335.60 323.07 312.35 301.06 293.08
8100-8190 365.92 333.82 312.68 294.74 276.54 264.00 253.28 241.98 234.00
8190-8250 304.56 272.49 251.38 233.46 215.27 202.74 192.02 180.73 172.75
8250-8312 258.56 226.50 205.38 187.46 169.27 156.74 146.02 134.73 126.76
Thickness req. for Working Pressure
excluding Surge Barlow's equation695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-900 6.54 7.00 7.45 7.90 8.37 8.82 9.28 9.75 10.21
900-1500 7.24 7.76 8.26 8.77 9.29 9.80 10.31 10.83 11.34
1500-1950 7.92 8.49 9.04 9.60 10.17 10.73 11.29 11.86 12.42
1950-3810 8.77 9.37 9.97 10.57 11.19 11.80 12.40 13.03 13.64
3810-7050 8.82 9.40 9.98 10.57 11.18 11.78 12.38 13.00 13.61
7050-7230 7.91 8.48 9.04 9.60 10.17 10.73 11.29 11.86 12.42
7230-7440 7.14 7.66 8.16 8.66 9.18 9.69 10.19 10.71 11.22
7440-7500 6.60 7.08 7.55 8.01 8.50 8.96 9.43 9.91 10.38
7500-7560 5.80 6.23 6.64 7.05 7.47 7.88 8.29 8.71 9.12
7560-7740 5.18 5.55 5.92 6.28 6.66 7.03 7.39 7.77 8.13
7740-7860 4.59 4.93 5.25 5.57 5.91 6.23 6.56 6.89 7.21
7860-7980 3.95 4.24 4.51 4.79 5.08 5.36 5.64 5.92 6.20
7980-8040 3.27 3.51 3.74 3.97 4.21 4.44 4.67 4.91 5.14
8040-8100 2.60 2.79 2.97 3.15 3.34 3.52 3.71 3.90 4.08
8100-8190 1.85 1.99 2.12 2.25 2.38 2.51 2.64 2.78 2.91
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.70
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
Chainage Static Head LengthFrictional Head for Diameter
8190-8250 1.08 1.16 1.23 1.31 1.38 1.46 1.54 1.61 1.69
8250-8312 0.50 0.53 0.57 0.60 0.64 0.67 0.71 0.74 0.78
Thickness req. for Working Pressure
including Surge Barlow's equation695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-900 9.30 9.53 9.85 10.17 10.48 10.84 11.21 11.56 11.95
900-1500 10.01 10.30 10.66 11.04 11.41 11.82 12.24 12.65 13.08
1500-1950 10.69 11.03 11.44 11.87 12.29 12.75 13.22 13.68 14.16
1950-3810 11.54 11.91 12.37 12.84 13.31 13.81 14.33 14.84 15.38
3810-7050 11.59 11.94 12.38 12.84 13.30 13.80 14.31 14.82 15.35
7050-7230 10.68 11.02 11.44 11.87 12.29 12.75 13.22 13.68 14.17
7230-7440 9.91 10.20 10.56 10.94 11.30 11.71 12.12 12.53 12.96
7440-7500 9.37 9.62 9.95 10.29 10.61 10.98 11.36 11.72 12.12
7500-7560 8.57 8.76 9.04 9.32 9.58 9.90 10.22 10.53 10.86
7560-7740 7.95 8.09 8.32 8.56 8.78 9.04 9.32 9.58 9.87
7740-7860 7.36 7.46 7.65 7.85 8.02 8.25 8.49 8.70 8.96
7860-7980 6.72 6.77 6.91 7.07 7.20 7.38 7.57 7.74 7.94
7980-8040 6.04 6.05 6.14 6.25 6.33 6.46 6.60 6.73 6.88
8040-8100 5.37 5.32 5.37 5.43 5.46 5.54 5.64 5.71 5.82
8100-8190 4.62 4.52 4.52 4.52 4.50 4.53 4.57 4.59 4.65
8190-8250 3.85 3.69 3.63 3.58 3.50 3.48 3.47 3.43 3.43
8250-8312 3.27 3.07 2.97 2.88 2.75 2.69 2.64 2.56 2.52
Thickness req. for Working Pressure
excluding Surge as per IS-5822695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-900 7.03 7.41 7.79 8.18 8.57 8.95 9.34 9.73 10.12
900-1500 7.62 8.05 8.48 8.91 9.34 9.77 10.21 10.64 11.07
1500-1950 8.19 8.66 9.13 9.60 10.08 10.55 11.03 11.50 11.98
1950-3810 8.90 9.40 9.90 10.41 10.93 11.44 11.96 12.48 12.99
3810-7050 8.94 9.42 9.91 10.41 10.92 11.43 11.94 12.45 12.97
7050-7230 8.18 8.65 9.13 9.60 10.08 10.55 11.03 11.50 11.98
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.71
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
Chainage Static Head LengthFrictional Head for Diameter
7230-7440 7.53 7.96 8.39 8.82 9.25 9.68 10.11 10.54 10.97
7440-7500 7.08 7.48 7.88 8.28 8.67 9.07 9.47 9.87 10.27
7500-7560 6.41 6.76 7.11 7.46 7.81 8.16 8.51 8.86 9.21
7560-7740 5.89 6.20 6.51 6.82 7.13 7.45 7.76 8.07 8.38
7740-7860 5.39 5.67 5.95 6.22 6.50 6.78 7.05 7.33 7.61
7860-7980 4.85 5.09 5.33 5.56 5.80 6.04 6.28 6.52 6.76
7980-8040 4.28 4.48 4.67 4.87 5.07 5.27 5.47 5.66 5.86
8040-8100 3.71 3.86 4.02 4.18 4.33 4.49 4.65 4.81 4.96
8100-8190 3.08 3.19 3.30 3.41 3.52 3.63 3.75 3.86 3.97
8190-8250 2.42 2.48 2.55 2.61 2.68 2.74 2.81 2.87 2.94
8250-8312 1.92 1.95 1.98 2.01 2.04 2.07 2.10 2.13 2.16
Thickness req. for Working Pressure
including Surge as per IS-5822695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-900 9.34 9.53 9.80 10.08 10.34 10.64 10.96 11.25 11.58
900-1500 9.93 10.16 10.48 10.81 11.11 11.46 11.82 12.15 12.53
1500-1950 10.49 10.77 11.13 11.50 11.84 12.23 12.64 13.01 13.43
1950-3810 11.20 11.50 11.90 12.31 12.69 13.12 13.57 13.99 14.44
3810-7050 11.24 11.53 11.91 12.31 12.68 13.11 13.55 13.96 14.42
7050-7230 10.48 10.76 11.13 11.50 11.84 12.23 12.64 13.02 13.43
7230-7440 9.85 10.08 10.40 10.72 11.02 11.37 11.72 12.05 12.42
7440-7500 9.40 9.60 9.88 10.18 10.44 10.76 11.09 11.39 11.72
7500-7560 8.73 8.89 9.12 9.37 9.59 9.85 10.13 10.38 10.68
7560-7740 8.21 8.32 8.52 8.73 8.91 9.14 9.38 9.59 9.84
7740-7860 7.72 7.80 7.96 8.14 8.28 8.47 8.68 8.86 9.07
7860-7980 7.18 7.22 7.35 7.48 7.58 7.74 7.91 8.05 8.22
7980-8040 6.61 6.61 6.70 6.79 6.85 6.97 7.09 7.19 7.33
8040-8100 6.04 6.00 6.05 6.10 6.12 6.20 6.28 6.34 6.44
8100-8190 5.42 5.33 5.33 5.33 5.31 5.34 5.38 5.39 5.44
8190-8250 4.76 4.63 4.58 4.54 4.47 4.45 4.44 4.41 4.41
8250-8312 4.27 4.10 4.02 3.94 3.84 3.78 3.74 3.67 3.64
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.72
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
Chainage Static Head LengthFrictional Head for Diameter
Required Thickness Length 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-900 900 9.34 9.53 9.85 10.17 10.48 10.84 11.21 11.56 11.95
900-1500 600 10.01 10.30 10.66 11.04 11.41 11.82 12.24 12.65 13.08
1500-1950 450 10.69 11.03 11.44 11.87 12.29 12.75 13.22 13.68 14.16
1950-3810 1860 11.54 11.91 12.37 12.84 13.31 13.81 14.33 14.84 15.38
3810-7050 3240 11.59 11.94 12.38 12.84 13.30 13.80 14.31 14.82 15.35
7050-7230 180 10.68 11.02 11.44 11.87 12.29 12.75 13.22 13.68 14.17
7230-7440 210 9.91 10.20 10.56 10.94 11.30 11.71 12.12 12.53 12.96
7440-7500 60 9.40 9.62 9.95 10.29 10.61 10.98 11.36 11.72 12.12
7500-7560 60 8.73 8.89 9.12 9.53 9.59 10.31 11.13 11.13 11.91
7560-7740 180 8.21 8.32 8.74 9.53 9.53 10.31 11.13 11.13 11.91
7740-7860 120 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
7860-7980 120 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
7980-8040 60 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
8040-8100 60 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
8100-8190 90 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
8190-8250 60 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
8250-8312 62 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.73
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Daily Demand 67.63
Supply Hrs 24
Design Discharge 67.63
C 140.00
Yeild Stress 450.00
Welding Efficiency 0.80
Design Factor for Working Pressure
excluding Surge0.9
Design Factor for Working Pressure
including Surge0.9
Outer Diameter 711.2 762 812.8 863.6 914.4 965.2 1016 1066.8 1117.6
Internal Diameter 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
Thickness req. for Collapsing
pressure7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
Rate of Friction 4.22 2.99 2.19 1.64 1.23 0.95 0.74 0.58 0.46
Normal Velocity 2.06 1.79 1.58 1.40 1.24 1.12 1.01 0.91 0.83
Velocity of Wave Pressure 1043.34 1026.09 1034.63 1041.08 1026.78 1032.96 1039.26 1027.05 1032.38
Water Hammer 219.23 187.25 166.18 148.30 130.13 117.62 106.92 95.64 87.67
Velocity Head 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-1920 442.66 1.92 8.91 6.32 4.63 3.46 2.60 2.01 1.57 1.23 0.98
1920-2010 389.6 0.09 0.42 0.30 0.22 0.16 0.12 0.09 0.07 0.06 0.05
2010-2220 344.29 0.21 0.97 0.69 0.51 0.38 0.28 0.22 0.17 0.13 0.11
2220-4470 285.07 2.25 10.45 7.41 5.43 4.05 3.05 2.35 1.84 1.44 1.15
4470-4770 239.11 0.3 1.39 0.99 0.72 0.54 0.41 0.31 0.24 0.19 0.15
4770-5190 185.43 0.42 1.95 1.38 1.01 0.76 0.57 0.44 0.34 0.27 0.21
5190-5610 134.53 0.42 1.95 1.38 1.01 0.76 0.57 0.44 0.34 0.27 0.21
5610-10065 84.15 4.455 20.68 14.67 10.75 8.03 6.04 4.65 3.63 2.85 2.28
Working Pressure excluding Surge 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-1920 455.57 452.98 451.29 450.12 449.26 448.67 448.23 447.89 447.64
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Raw Water Rising Main from WTP to Devidhar
Chainage Static Head LengthFrictional Head for Diameter
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.74
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78Chainage Static Head Length
Frictional Head for Diameter
1920-2010 394.02 393.90 393.82 393.76 393.72 393.69 393.67 393.66 393.65
2010-2220 349.26 348.98 348.80 348.67 348.57 348.51 348.46 348.42 348.40
2220-4470 299.52 296.48 294.50 293.12 292.12 291.42 290.91 290.51 290.22
4470-4770 244.50 244.10 243.83 243.65 243.52 243.42 243.35 243.30 243.26
4770-5190 191.38 190.81 190.44 190.19 190.00 189.87 189.77 189.70 189.64
5190-5610 140.48 139.91 139.54 139.29 139.10 138.97 138.87 138.80 138.74
5610-10065 108.83 102.82 98.90 96.18 94.19 92.80 91.78 91.00 90.43
Working Pressure including Surge 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-1920 674.80 640.23 617.48 598.42 579.40 566.29 555.15 543.53 535.31
1920-2010 613.24 581.14 560.00 542.06 523.86 511.32 500.60 489.30 481.32
2010-2220 568.49 536.23 514.98 496.97 478.71 466.13 455.38 444.06 436.07
2220-4470 518.74 483.72 460.68 441.42 422.25 409.04 397.83 386.15 377.89
4470-4770 463.73 431.34 410.02 391.95 373.65 361.05 350.28 338.94 330.94
4770-5190 410.61 378.06 356.63 338.48 320.13 307.49 296.69 285.34 277.32
5190-5610 359.71 327.16 305.73 287.58 269.23 256.59 245.79 234.44 226.42
5610-10065 328.06 290.07 265.09 244.47 224.32 210.43 198.71 186.64 178.10
Thickness req. for Working Pressure
excluding Surge Barlow's equation695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-1920 5.75 6.14 6.52 6.90 7.30 7.70 8.09 8.50 8.89
1920-2010 4.98 5.34 5.69 6.04 6.40 6.75 7.10 7.47 7.82
2010-2220 4.41 4.73 5.04 5.35 5.67 5.98 6.29 6.61 6.92
2220-4470 3.78 4.02 4.25 4.50 4.75 5.00 5.25 5.51 5.76
4470-4770 3.09 3.31 3.52 3.74 3.96 4.18 4.39 4.62 4.83
4770-5190 2.42 2.59 2.75 2.92 3.09 3.26 3.42 3.60 3.77
5190-5610 1.77 1.90 2.02 2.14 2.26 2.38 2.51 2.63 2.76
5610-10065 1.37 1.39 1.43 1.48 1.53 1.59 1.66 1.73 1.80
Thickness req. for Working Pressure
including Surge Barlow's equation695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-1920 8.52 8.68 8.92 9.18 9.42 9.71 10.02 10.31 10.63
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.75
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78Chainage Static Head Length
Frictional Head for Diameter
1920-2010 7.74 7.87 8.09 8.31 8.52 8.77 9.03 9.28 9.56
2010-2220 7.18 7.27 7.44 7.62 7.78 8.00 8.22 8.42 8.66
2220-4470 6.55 6.55 6.65 6.77 6.87 7.02 7.18 7.32 7.51
4470-4770 5.86 5.84 5.92 6.01 6.08 6.19 6.32 6.43 6.57
4770-5190 5.19 5.12 5.15 5.19 5.21 5.27 5.35 5.41 5.51
5190-5610 4.54 4.43 4.42 4.41 4.38 4.40 4.44 4.45 4.50
5610-10065 4.14 3.93 3.83 3.75 3.65 3.61 3.59 3.54 3.54
Thickness req. for Working Pressure
excluding Surge as per IS-5822695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-1920 6.37 6.69 7.01 7.34 7.67 8.01 8.35 8.68 9.02
1920-2010 5.72 6.02 6.32 6.62 6.92 7.22 7.52 7.82 8.12
2010-2220 5.24 5.50 5.77 6.03 6.30 6.56 6.83 7.10 7.36
2220-4470 4.71 4.90 5.11 5.31 5.52 5.74 5.95 6.17 6.39
4470-4770 4.12 4.30 4.49 4.67 4.86 5.04 5.23 5.41 5.60
4770-5190 3.55 3.69 3.84 3.98 4.12 4.27 4.41 4.55 4.70
5190-5610 3.01 3.11 3.21 3.32 3.42 3.53 3.63 3.74 3.84
5610-10065 2.67 2.68 2.71 2.76 2.80 2.85 2.91 2.97 3.03
Thickness req. for Working Pressure
including Surge as per IS-5822695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-1920 8.69 8.81 9.02 9.25 9.45 9.70 9.96 10.20 10.48
1920-2010 8.04 8.14 8.33 8.53 8.69 8.91 9.14 9.34 9.58
2010-2220 7.57 7.63 7.79 7.95 8.08 8.26 8.45 8.62 8.83
2220-4470 7.04 7.04 7.13 7.23 7.31 7.44 7.58 7.70 7.85
4470-4770 6.46 6.44 6.51 6.59 6.64 6.75 6.86 6.94 7.07
4770-5190 5.89 5.83 5.86 5.90 5.91 5.97 6.04 6.09 6.17
5190-5610 5.35 5.25 5.24 5.24 5.21 5.23 5.27 5.27 5.32
5610-10065 5.01 4.83 4.75 4.68 4.59 4.56 4.55 4.50 4.50
Required Thickness Length 695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78
0-1920 1920 8.69 8.81 9.02 9.53 9.53 10.31 11.13 11.13 11.91
1920-2010 90 8.04 8.14 8.74 9.53 9.53 10.31 11.13 11.13 11.91
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.76
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
695.36 746.16 795.32 844.54 895.34 944.58 993.74 1044.54 1093.78Chainage Static Head Length
Frictional Head for Diameter
2010-2220 210 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
2220-4470 2250 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
4470-4770 300 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
4770-5190 420 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
5190-5610 420 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
5610-10065 4455 7.92 7.92 8.74 9.53 9.53 10.31 11.13 11.13 11.91
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.77
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
2035 2050 2035 2050 2035 2050 2035 2050
1 Daily Demand 41.673 67.633 41.673 67.633 41.673 67.633 41.673 67.633 ML
2 Pumping Hours 24.000 24.000 24.000 24.000 24.000 24.000 24.000 24.000 Hr
3 Rate of Pumping with 12% losses 46.674 75.749 46.674 75.749 46.674 75.749 46.674 75.749 MLD
Total Discharge 540.20 876.73 540.20 876.73 540.20 876.73 540.20 876.73 LPS
4 Efficiency of pump 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% 75.00% %
5 Length of Rising main DI pipe 139.00 139.00 2294.00 2294.00 8312.00 8312.00 10065.00 10065.00 M
6 Diameter, Type & class of Pipe 746.16 746.16 739.38 739.38 738.12 738.12 744.38 744.38 API 5L
7 Value of C for DI material 140.00 140.00 140.00 140.00 140.00 140.00 140.00 140.00 API 5L
8 Calculation of Static Head 63.98 63.98 658.08 658.08 509.38 509.38 442.66 442.66 M
9Calculation of Frictional Head for DI
pipe line
aCalculation of Frictional head per 1000
meter1.506 3.693 1.575 3.861 1.588 3.893 1.524 3.736
M per
1000M
bFrictional head for total length of Rising
main0.209 0.513 3.612 8.856 13.198 32.357 15.338 37.603 M
c Add for losses in bends and valve (20%) 0.04 0.10 0.72 1.77 2.64 6.47 3.07 7.52 M
d Total Frictional Head (10+11) 0.25 0.62 4.33 10.63 15.84 38.83 18.41 45.12 M
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Design of raw water pumping Machinery
Rising Main from Intake to
Desilting Tank
Rising Main from WTP to
Devidhar
Rising Main from Devidhar to
DummiunitDiscriptionSr.No.
Rising Main from Dummi to
Sanjauli
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.78
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
2035 2050 2035 2050 2035 2050 2035 2050
Rising Main from Intake to
Desilting Tank
Rising Main from WTP to
Devidhar
Rising Main from Devidhar to
DummiunitDiscriptionSr.No.
Rising Main from Dummi to
Sanjauli
10 Velocity Head 4.00 4.00 4.00 4.00 4.00 4.00 4.00 4.00 M
14 Total head on pump (8c+12+13) 68.23 68.60 666.41 672.71 529.22 552.21 465.07 491.78 M
Say 69.00 69.00 667.00 673.00 530.00 553.00 466.00 492.00
15Total BHP Reqiured (with 10 %
overloading) Q*h/(75*n)728.91 1183.00 7046.16 11538.55 5598.90 9481.15 4922.81 8435.31 BHP
730.00 1190.00 7050.00 11540.00 5600.00 9490.00 4930.00 8440.00 BHP
Provide 730.00 1190.00 1175.00 1925.00 935.00 1585.00 825.00 1410.00
working 1.00 1.00 6.00 6.00 6.00 6.00 6.00 6.00
stand by 1.00 1.00 3.00 3.00 3.00 3.00 3.00 3.00
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.79
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Design of Economic Size of Rising Main I N P U T D A T A
From : LSL at Intake ========= ========== ========= ============
TO : FSL at Desilting tank 1) Water requirement : Year Discharge
P I P E D A T A
A. Initial 2020 21.82 mld ----------------------- ---------------- ------------------ ---------------- ---------------------B. Intermediate 2035 41.67 mld Int DIAMETER MATERIAL Thickness HWC RATE Out Diameter
C. Ultimate 2050 67.63 mld mm Class Rs/M mm----------------------- ---------------- ------------------ ---------------- ---------------------
2) Pumping main LENGTH 139 M 695.36 API 5L 7.92 140 10027.57 711.20
3) Static head for pump ST.HEAD 63.98 M 746.16 API 5L 7.92 140 10864.82 762.00
4) Design period YEAR 30 yr. 795.32 API 5L 8.74 140 12789.03 812.80
5) Combined eff. of pump set EFF. % 75 % 844.54 API 5L 9.53 140 14816.58 863.60
6) Cost of pumping unit Rs./KW 13428 Rs 895.34 API 5L 9.53 140 15688.14 914.40
7) Interest rate INTEREST 12.00 % 944.58 API 5L 10.31 140 17915.06 965.20
8) Life of elec. motors P.Yrs 15 yr. 993.74 API 5L 11.13 140 20357.82 1016.00
9) Energy charges P/KWH 400.0 paise 1044.54 API 5L 11.13 140 21375.71 1066.80
10) Pumping hours for discharge PUMPING- 24 hrs 1093.78 API 5L 11.91 140 23962.96 1117.60
the end of 15 years HOURS========= ============ ========= =========== =========== ========= ============ ============= ========= ========== ========= ============
CALCULATIONS: 1st 15 years 2nd 15 years
1) Discharge at Start OF PERIOD 21.82 mld 41.67 mld
2) Discharge at the end of 15 yrs 41.67 mld 67.63 mld
3) Average Discharge 31.75 mld 54.65 mld
4) Ave.pumping hours during the period 18.28 hrs 19.39 hrs
5) KW required at combined 6.31 * H1 10.23 * H2 efficiency of pumping set
6) Ave.annual charges for electrical
energy Rs. 26710.3 * KW1 28333.7 * KW2========= ============ ========= =========== =========== ========= ============ ============= ========= ========== ========= ============
TABLE 1 - VELOCITY AND HEADLOSSES FOR DIFFERENT PIPE SIZES
---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- ---------------------- ----------------------- ---------------- ------------------ ---------------- ---------------------
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
CALCULATION OF LEAST-COST PIPE SIZE
RAW WATER RISING MAIN
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.80
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
139 m length
Sr. Pipe Frictional Head Velocity in including 63.98 m static head
No. Size in loss per m/s
mm. 1000 m 1st stage flow 2nd stage flow
1st 2nd 1st 2nd Frictional Total Frictional Total
stage stage stage stage loss Other* losses loss Other* losses
flow flow flow flow losses H1 losses H2---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- ---------------------- ----------------------- ---------------- ------------------ ---------------- ---------------------
1 695.36 1.72 4.22 1.27 2.06 0.24 0.02 64.24 0.59 0.06 64.63
2 746.16 1.22 2.99 1.10 1.79 0.17 0.02 64.17 0.42 0.04 64.44
3 795.32 0.89 2.19 0.97 1.58 0.12 0.01 64.12 0.30 0.03 64.32
4 844.54 0.67 1.64 0.86 1.40 0.09 0.01 64.08 0.23 0.02 64.23
5 895.34 0.50 1.23 0.77 1.24 0.07 0.01 64.06 0.17 0.02 64.17
6 944.58 0.39 0.95 0.69 1.12 0.05 0.01 64.04 0.13 0.01 64.13
7 993.74 0.30 0.74 0.62 1.01 0.04 0.00 64.03 0.10 0.01 64.09
8 1044.54 0.24 0.58 0.56 0.91 0.03 0.00 64.02 0.08 0.01 64.07
9 1093.78 0.19 0.46 0.51 0.83 0.03 0.00 64.01 0.06 0.01 64.05
>>> * Other losses = 10% of frictional loss
========= ============ ========= =========== =========== ========= ============ ============= ========= ========== ========= ============
TABLE 2 - KILOWATTS & COST OF PUMP SETS REQUIRED FOR DIFFERENT PIPE SIZES AND PIPE COST---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- ---------------------- ----------------------- ---------------- ------------------ ---------------- ---------------------
1st stage flow of 2nd stage flow of Cost Cost
41.67 million liters/day 67.63million liters/day of of
pipe 139
PIPE Class H1 Kw H2 Kw Pump per meter
Size of Total req'd Total req'd Cost @ Rs unit pipe
Sr. in PIPE head plus % head plus % 13428 length line
No. mm in 50 in 50 per kw THS 100
meters standby meters standby Rs THS ( Rs ) ( Rs )
---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- ---------------------- ----------------------- ---------------- ------------------ ---------------- ---------------------
1 695.36 7.92 64.00 605 65.00 998 13401 10027.57 1393.83
2 746.16 7.92 64.00 605 64.00 982 13186 10864.82 1510.21
3 795.32 8.74 64.00 605 64.00 982 13186 12789.03 1777.67
Rs THS
Total head (m) for
Pump
Cost @ Rs
13428
per kw
8124
8124
8124
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.81
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
4 844.54 9.53 64.00 605 64.00 982 13186 14816.58 2059.50
5 895.34 9.53 64.00 605 64.00 982 13186 15688.14 2180.65
6 944.58 10.31 64.00 605 64.00 982 13186 17915.06 2490.19
7 993.74 11.13 64.00 605 64.00 982 13186 20357.82 2829.74
8 1044.54 11.13 64.00 605 64.00 982 13186 21375.71 2971.22
9 1093.78 11.91 64.00 605 64.00 982 13186 23962.96 3330.85========= ============ ========= =========== =========== ========= ============ ============= ========= ========== ========= ============
TABLE 3 - COMPARATIVE STATEMENT OF OVERALL COST OF PUMPING MAIN FOR DIFFERENT PIPE SIZES---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- ---------------------- ----------------------- ---------------- ------------------ ---------------- ---------------------
1st stage flow 41.67 mld 2nd stage flow 67.63 mld
GRAND
TOTAL of
Cost Annual Capitalised Capitalised Cost Annual Capitalised Capitalised Capitalised Internal Outer
of Energy Energy Total of Energy Energy Total cost Diameter Diameter
Sr. pump Charges Charges Cost pump Charges Charges Cost for in in
No. sets sets 30 yrs (mm) (mm)
THS THS THS THS THS THS THS THS THS
( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs )---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- ---------------------- ----------------------- ---------------- ------------------ ---------------- -
1 8124 10773 73373 82891 13401 18851 128392 25905 108796 695.36 711.20
2 8124 10773 73373 83007 13186 18549 126335 25490 108497 746.16 762.00 Min
3 8124 10773 73373 83275 13186 18549 126335 25490 108765 795.32 812.80
4 8124 10773 73373 83557 13186 18549 126335 25490 109047 844.54 863.60
5 8124 10773 73373 83678 13186 18549 126335 25490 109168 895.34 914.40
6 8124 10773 73373 83987 13186 18549 126335 25490 109477 944.58 965.20
7 8124 10773 73373 84327 13186 18549 126335 25490 109817 993.74 1016.00
8 8124 10773 73373 84468 13186 18549 126335 25490 109958 1044.54 1066.80
9 8124 10773 73373 84828 13186 18549 126335 25490 110318 1093.78 1117.60
*** TABLE 3 shows that the most economical size of MAIN is : =
762.00 mm costing CAPITALISED Rs. 108497 thousands ==== ========= =========== =============================
8124
8124
8124
8124
8124
8124
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.82
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Design of Economic Size of Rising Main I N P U T D A T A
From : LSL at WTP ========= ========== ========= ============
TO : FSL at Devidhar 1) Water requirement : Year Discharge
P I P E D A T A
A. Initial 2020 21.82 mld ----------------------- ---------------- ----------------- ---------------- ---------------------B. Intermediate 2035 41.67 mld Int DIAMETER MATERIAL Thickness HWC RATE Out Diameter
C. Ultimate 2050 67.63 mld mm Class Rs/M mm----------------------- ---------------- ----------------- ---------------- ---------------------
2) Pumping main LENGTH 2245 M 689.30 API 5L 10.95 140 13802.92 711.20
3) Static head for pump ST.HEAD 509.38 M 739.38 API 5L 11.31 140 15517.63 762.00
4) Design period YEAR 30 yr. 789.30 API 5L 11.75 140 17193.63 812.80
5) Combined eff. of pump set EFF. % 75 % 839.20 API 5L 12.20 140 18969.23 863.60
6) Cost of pumping unit Rs./KW 13428 Rs 889.12 API 5L 12.64 140 20804.55 914.40
7) Interest rate INTEREST 12.00 % 938.97 API 5L 13.12 140 22793.26 965.20
8) Life of elec. motors P.Yrs 15 yr. 988.79 API 5L 13.61 140 24886.77 1016.00
9) Energy charges P/KWH 400.0 paise 1038.63 API 5L 14.09 140 27054.47 1066.80
10) Pumping hours for discharge PUMPING- 24 hrs 1088.42 API 5L 14.59 140 29359.51 1117.60
the end of 15 years HOURS========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
CALCULATIONS: 1st 15 years 2nd 15 years
1) Discharge at Start OF PERIOD 21.82 mld 41.67 mld
2) Discharge at the end of 15 yrs 41.67 mld 67.63 mld
3) Average Discharge 31.75 mld 54.65 mld
4) Ave.pumping hours during the period 18.28 hrs 19.39 hrs
5) KW required at combined 6.31 * H1 10.23 * H2 efficiency of pumping set
6) Ave.annual charges for electrical
energy Rs. 26710.3 * KW1 28333.7 * KW2========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
TABLE 1 - VELOCITY AND HEADLOSSES FOR DIFFERENT PIPE SIZES
---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- --------------------- ----------------------- ---------------- ----------------- ---------------- ---------------------
2245 m length
Sr. Pipe Frictional Head Velocity in including 509.38 m static head
No. Size in loss per m/s
Total head (m) for
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
CALCULATION OF LEAST-COST PIPE SIZE
RAW WATER RISING MAIN
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.83
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
mm. 1000 m 1st stage flow 2nd stage flow
1st 2nd 1st 2nd Frictional Total Frictional Total
stage stage stage stage loss Other* losses loss Other* losses
flow flow flow flow losses H1 losses H2---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- --------------------- ----------------------- ---------------- ----------------- ---------------- ---------------------
1 689.30 1.80 4.40 1.29 2.10 4.03 0.40 513.82 9.89 0.99 520.25
2 739.38 1.28 3.13 1.12 1.82 2.87 0.29 512.53 7.03 0.70 517.11
3 789.30 0.93 2.28 0.99 1.60 2.08 0.21 511.67 5.11 0.51 515.00
4 839.20 0.69 1.69 0.87 1.42 1.55 0.15 511.08 3.79 0.38 513.55
5 889.12 0.52 1.27 0.78 1.26 1.17 0.12 510.66 2.86 0.29 512.53
6 938.97 0.40 0.98 0.70 1.13 0.89 0.09 510.36 2.19 0.22 511.79
7 988.79 0.31 0.76 0.63 1.02 0.70 0.07 510.15 1.71 0.17 511.26
8 1038.63 0.24 0.60 0.57 0.92 0.55 0.05 509.98 1.34 0.13 510.86
9 1088.42 0.19 0.48 0.52 0.84 0.44 0.04 509.86 1.07 0.11 510.56
>>> * Other losses = 10% of frictional loss
========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
TABLE 2 - KILOWATTS & COST OF PUMP SETS REQUIRED FOR DIFFERENT PIPE SIZES AND PIPE COST---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- --------------------- ----------------------- ---------------- ----------------- ---------------- ---------------------
1st stage flow of 2nd stage flow of Cost Cost
41.67 million liters/day 67.63million liters/day of of
pipe 2245
PIPE Class H1 Kw H2 Kw Pump per meter
Size of Total req'd Total req'd Cost @ Rs unit pipe
Sr. in PIPE head plus % head plus % 13428 length line
No. mm in 50 in 50 per kw THS 100
meters standby meters standby Rs THS ( Rs ) ( Rs )
---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- --------------------- ----------------------- ---------------- ----------------- ---------------- ---------------------
1 689.30 10.95 514.00 4862 520.00 7982 107182 13802.92 30987.55
2 739.38 11.31 513.00 4852 517.00 7936 106565 15517.63 34837.07
3 789.30 11.75 512.00 4843 515.00 7905 106148 17193.63 38599.70
4 839.20 12.20 511.00 4833 514.00 7890 105947 18969.23 42585.93
5 889.12 12.64 511.00 4833 513.00 7875 105746 20804.55 46706.22
Rs THS
Pump
Cost @ Rs
13428
per kw
65287
65153
65032
64898
64898
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.84
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
6 938.97 13.12 510.00 4824 512.00 7859 105531 22793.26 51170.87
7 988.79 13.61 510.00 4824 511.00 7844 105329 24886.77 55870.79
8 1038.63 14.09 510.00 4824 511.00 7844 105329 27054.47 60737.30
9 1088.42 14.59 510.00 4824 511.00 7844 105329 29359.51 65912.09========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
TABLE 3 - COMPARATIVE STATEMENT OF OVERALL COST OF PUMPING MAIN FOR DIFFERENT PIPE SIZES---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- --------------------- ----------------------- ---------------- ----------------- ---------------- ---------------------
1st stage flow 41.67 mld 2nd stage flow 67.63 mld
GRAND
TOTAL of
Cost Annual Capitalised Capitalised Cost Annual Capitalised Capitalised Capitalised Internal Outer
of Energy Energy Total of Energy Energy Total cost Diameter Diameter
Sr. pump Charges Charges Cost pump Charges Charges Cost for in in
No. sets sets 30 yrs (mm) (mm)
THS THS THS THS THS THS THS THS THS
( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs )---------------- ---------------------- ---------------- ------------------- -------------------- ---------------- --------------------- ----------------------- ---------------- ----------------- ---------------- -
1 65287 86577 589664 685939 107182 150773 1026894 207191 893130 689.30 711.20 Min
2 65153 86399 588452 688442 106565 149904 1020976 205998 894440 739.38 762.00
3 65032 86239 587362 690994 106148 149318 1016985 205192 896186 789.30 812.80
4 64898 86061 586150 693634 105947 149035 1015057 204803 898437 839.20 863.60
5 64898 86061 586150 697754 105746 148752 1013130 204414 902168 889.12 914.40
6 64777 85900 585053 701001 105531 148450 1011073 203999 905000 938.97 965.20
7 64777 85900 585053 705701 105329 148166 1009139 203609 909310 988.79 1016.00
8 64777 85900 585053 710567 105329 148166 1009139 203609 914176 1038.63 1066.80
9 64777 85900 585053 715742 105329 148166 1009139 203609 919351 1088.42 1117.60
*** TABLE 3 shows that the most economical size of MAIN is : =
711.20 mm costing CAPITALISED Rs. 893130 thousands To keep the velocity less than 2 m/s 762 mm dia pipe is proposed. ==== ========= =========== =============================
64777
64777
64777
64777
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.85
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Design of Economic Size of Rising Main I N P U T D A T A
From : LSL at Devidhar ========= ========== ========= ============
TO : FSL at Dummi 1) Water requirement : Year Discharge
P I P E D A T A
A. Initial 2020 21.82 mld ------------------------ ----------------- ------------------ ---------------- ----------------------B. Intermediate 2035 41.67 mld Int DIAMETER MATERIAL Thickness HWC RATE Out Diameter
C. Ultimate 2050 67.63 mld mm Class Rs/M mm------------------------ ----------------- ------------------ ---------------- ----------------------
2) Pumping main LENGTH 8312 M 688.03 API 5L 11.59 140 14593.94 711.20
3) Static head for pump ST.HEAD 681.69 M 738.12 API 5L 11.94 140 16380.83 762.00
4) Design period YEAR 30 yr. 788.04 API 5L 12.38 140 18118.72 812.80
5) Combined eff. of pump set EFF. % 75 % 837.91 API 5L 12.84 140 19968.76 863.60
6) Cost of pumping unit Rs./KW 13428 Rs 887.80 API 5L 13.30 140 21890.36 914.40
7) Interest rate INTEREST 12.00 % 937.61 API 5L 13.80 140 23974.33 965.20
8) Life of elec. motors P.Yrs 15 yr. 987.38 API 5L 14.31 140 26171.83 1016.00
9) Energy charges P/KWH 400.0 paise 1037.17 API 5L 14.82 140 28453.36 1066.80
10) Pumping hours for discharge PUMPING- 24 hrs 1086.91 API 5L 15.35 140 30878.52 1117.60
the end of 15 years HOURS========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
CALCULATIONS: 1st 15 years 2nd 15 years
1) Discharge at Start OF PERIOD 21.82 mld 41.67 mld
2) Discharge at the end of 15 yrs 41.67 mld 67.63 mld
3) Average Discharge 31.75 mld 54.65 mld
4) Ave.pumping hours during the period 18.28 hrs 19.39 hrs
5) KW required at combined 6.31 * H1 10.23 * H2 efficiency of pumping set
6) Ave.annual charges for electrical
energy Rs. 26710.3 * KW1 28333.7 * KW2========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
TABLE 1 - VELOCITY AND HEADLOSSES FOR DIFFERENT PIPE SIZES
---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- ----------------------
8312 m length
Sr. Pipe Frictional Head Velocity in including 681.69 m static head
Total head (m) for
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
CALCULATION OF LEAST-COST PIPE SIZE
RAW WATER RISING MAIN
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.86
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
No. Size in loss per m/s
mm. 1000 m 1st stage flow 2nd stage flow
1st 2nd 1st 2nd Frictional Total Frictional Total
stage stage stage stage loss Other* losses loss Other* losses
flow flow flow flow losses H1 losses H2---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- ----------------------
1 688.03 1.81 4.44 1.30 2.11 15.06 1.51 698.26 36.93 3.69 722.32
2 738.12 1.29 3.16 1.13 1.83 10.70 1.07 693.46 26.23 2.62 710.54
3 788.04 0.94 2.29 0.99 1.61 7.78 0.78 690.25 19.07 1.91 702.67
4 837.91 0.69 1.70 0.88 1.42 5.77 0.58 688.04 14.14 1.41 697.25
5 887.80 0.52 1.28 0.78 1.27 4.35 0.44 686.48 10.67 1.07 693.43
6 937.61 0.40 0.98 0.70 1.13 3.34 0.33 685.36 8.18 0.82 690.69
7 987.38 0.31 0.76 0.63 1.02 2.59 0.26 684.54 6.36 0.64 688.68
8 1037.17 0.25 0.60 0.57 0.93 2.04 0.20 683.94 5.00 0.50 687.19
9 1086.91 0.20 0.48 0.52 0.84 1.62 0.16 683.48 3.98 0.40 686.07
>>> * Other losses = 10% of frictional loss
========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
TABLE 2 - KILOWATTS & COST OF PUMP SETS REQUIRED FOR DIFFERENT PIPE SIZES AND PIPE COST---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- ----------------------
1st stage flow of 2nd stage flow of Cost Cost
41.67 million liters/day 67.63million liters/day of of
pipe 8312
PIPE Class H1 Kw H2 Kw Pump per meter
Size of Total req'd Total req'd Cost @ Rs unit pipe
Sr. in PIPE head plus % head plus % 13428 length line
No. mm in 50 in 50 per kw THS 100
meters standby meters standby Rs THS ( Rs ) ( Rs )
---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- ----------------------
1 688.03 11.59 698.00 6602 722.00 11083 148823 14593.94 121304.85
2 738.12 11.94 693.00 6555 711.00 10914 146553 16380.83 136157.49
3 788.04 12.38 690.00 6526 703.00 10791 144902 18118.72 150602.84
4 837.91 12.84 688.00 6507 697.00 10699 143666 19968.76 165980.34
Rs THS
Pump
Cost @ Rs
13428
per kw
88652
88021
87631
87376
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.87
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
5 887.80 13.30 686.00 6488 693.00 10638 142847 21890.36 181952.68
6 937.61 13.80 685.00 6479 691.00 10607 142431 23974.33 199274.63
7 987.38 14.31 685.00 6479 689.00 10576 142015 26171.83 217540.27
8 1037.17 14.82 684.00 6469 687.00 10546 141612 28453.36 236504.32
9 1086.91 15.35 683.00 6460 686.00 10530 141397 30878.52 256662.23========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
TABLE 3 - COMPARATIVE STATEMENT OF OVERALL COST OF PUMPING MAIN FOR DIFFERENT PIPE SIZES---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- ----------------------
1st stage flow 41.67 mld 2nd stage flow 67.63 mld
GRAND
TOTAL of
Cost Annual Capitalised Capitalised Cost Annual Capitalised Capitalised Capitalised Internal Outer
of Energy Energy Total of Energy Energy Total cost Diameter Diameter
Sr. pump Charges Charges Cost pump Charges Charges Cost for in in
No. sets sets 30 yrs (mm) (mm)
THS THS THS THS THS THS THS THS THS
( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs )---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- -
1 88652 117561 800692 1010649 148823 209348 1425841 287685 1298334 688.03 711.20 Min
2 88021 116724 794991 1019169 146553 206156 1404101 283299 1302468 738.12 762.00
3 87631 116208 791477 1029711 144902 203832 1388272 280105 1309816 788.04 812.80
4 87376 115869 789168 1042524 143666 202095 1376442 277718 1320242 837.91 863.60
5 87121 115531 786866 1055940 142847 200942 1368589 276134 1332074 887.80 914.40
6 87000 115371 785776 1072051 142431 200357 1364604 275330 1347381 937.61 965.20
7 87000 115371 785776 1090316 142015 199771 1360613 274525 1364841 987.38 1016.00
8 86866 115193 784564 1107934 141612 199205 1356758 273747 1381681 1037.17 1066.80
9 86745 115032 783467 1126874 141397 198902 1354695 273330 1400204 1086.91 1117.60
*** TABLE 3 shows that the most economical size of MAIN is : =
711.20 mm costing CAPITALISED Rs. 1298334 thousands To keep the velocity less than 2 m/s 762 mm dia pipe is proposed. ==== ========= =========== =============================
87000
86866
86745
87121
87000
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.88
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
Design of Economic Size of Rising Main I N P U T D A T A
From : LSL at Dummi ========= ========== ========= ============
TO : FSL at Ridge 1) Water requirement : Year Discharge
P I P E D A T A
A. Initial 2020 21.82 mld ------------------------ ----------------- ------------------ ---------------- ---------------------- -------------------B. Intermediate 2035 41.67 mld Int DIAMETER MATERIAL Thickness HWC RATE Out Diameter
C. Ultimate 2050 67.63 mld mm Class Rs/M mm------------------------ ----------------- ------------------ ---------------- ---------------------- -------------------
2) Pumping main LENGTH 10065 M 693.82 API 5L 8.69 140 10989.59 711.20
3) Static head for pump ST.HEAD 442.66 M 744.38 API 5L 8.81 140 12088.48 762.00
4) Design period YEAR 30 yr. 794.75 API 5L 9.02 140 13205.88 812.80
5) Combined eff. of pump set EFF. % 75 % 844.54 API 5L 9.53 140 14816.58 863.60
6) Cost of pumping unit Rs./KW 13428 Rs 895.34 API 5L 9.53 140 15688.14 914.40
7) Interest rate INTEREST 12.00 % 944.58 API 5L 10.31 140 17915.06 965.20
8) Life of elec. motors P.Yrs 15 yr. 993.74 API 5L 11.13 140 20357.82 1016.00
9) Energy charges P/KWH 400.0 paise 1044.54 API 5L 11.13 140 21375.71 1066.80
10) Pumping hours for discharge PUMPING- 24 hrs 1093.78 API 5L 11.91 140 23962.96 1117.60
the end of 15 years HOURS========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
CALCULATIONS: 1st 15 years 2nd 15 years
1) Discharge at Start OF PERIOD 21.82 mld 41.67 mld
2) Discharge at the end of 15 yrs 41.67 mld 67.63 mld
3) Average Discharge 31.75 mld 54.65 mld
4) Ave.pumping hours during the period 18.28 hrs 19.39 hrs
5) KW required at combined 6.31 * H1 10.23 * H2 efficiency of pumping set
6) Ave.annual charges for electrical
energy Rs. 26710.3 * KW1 28333.7 * KW2========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
TABLE 1 - VELOCITY AND HEADLOSSES FOR DIFFERENT PIPE SIZES
---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- ----------------------
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
CALCULATION OF LEAST-COST PIPE SIZE
RAW WATER RISING MAIN
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.89
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
10065 m length
Sr. Pipe Frictional Head Velocity in including 442.66 m static head
No. Size in loss per m/s
mm. 1000 m 1st stage flow 2nd stage flow
1st 2nd 1st 2nd Frictional Total Frictional Total
stage stage stage stage loss Other* losses loss Other* losses
flow flow flow flow losses H1 losses H2---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- ----------------------
1 693.82 1.74 4.27 1.28 2.07 17.51 1.75 461.92 42.93 4.29 489.89
2 744.38 1.24 3.03 1.11 1.80 12.43 1.24 456.34 30.48 3.05 476.19
3 794.75 0.90 2.20 0.97 1.58 9.04 0.90 452.60 22.16 2.22 467.03
4 844.54 0.67 1.64 0.86 1.40 6.72 0.67 450.05 16.48 1.65 460.79
5 895.34 0.50 1.23 0.77 1.24 5.06 0.51 448.22 12.40 1.24 456.30
6 944.58 0.39 0.95 0.69 1.12 3.90 0.39 446.95 9.55 0.96 453.17
7 993.74 0.30 0.74 0.62 1.01 3.04 0.30 446.01 7.46 0.75 450.87
8 1044.54 0.24 0.58 0.56 0.91 2.39 0.24 445.29 5.85 0.59 449.10
9 1093.78 0.19 0.46 0.51 0.83 1.91 0.19 444.76 4.68 0.47 447.81
>>> * Other losses = 10% of frictional loss
========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
TABLE 2 - KILOWATTS & COST OF PUMP SETS REQUIRED FOR DIFFERENT PIPE SIZES AND PIPE COST---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- ----------------------
1st stage flow of 2nd stage flow of Cost Cost
41.67 million liters/day 67.63million liters/day of of
pipe 10065
PIPE Class H1 Kw H2 Kw Pump per meter
Size of Total req'd Total req'd Cost @ Rs unit pipe
Sr. in PIPE head plus % head plus % 13428 length line
No. mm in 50 in 50 per kw THS 100
meters standby meters standby Rs THS ( Rs ) ( Rs )
---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- ----------------------
1 693.82 8.69 462.00 4370 490.00 7522 101005 10989.59 110610.20
2 744.38 8.81 456.00 4313 476.00 7307 98118 12088.48 121670.55
3 794.75 9.02 453.00 4285 467.00 7169 96265 13205.88 132917.15
Rs THS
Total head (m) for
Pump
Cost @ Rs
13428
per kw
58680
57915
57539
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.90
SHIMLA JAL PRABANDHAN NIGAM LIMITED Design
4 844.54 9.53 450.00 4256 461.00 7076 95017 14816.58 149128.86
5 895.34 9.53 448.00 4237 456.00 7000 93996 15688.14 157901.15
6 944.58 10.31 447.00 4228 453.00 6954 93378 17915.06 180315.12
7 993.74 11.13 446.00 4218 451.00 6923 92962 20357.82 204901.45
8 1044.54 11.13 445.00 4209 449.00 6892 92546 21375.71 215146.53
9 1093.78 11.91 445.00 4209 448.00 6877 92344 23962.96 241187.24========= ============ ========= =========== ============ ========= ============ ============= ========= ========== ========= ============
TABLE 3 - COMPARATIVE STATEMENT OF OVERALL COST OF PUMPING MAIN FOR DIFFERENT PIPE SIZES---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- ----------------------
1st stage flow 41.67 mld 2nd stage flow 67.63 mld
GRAND
TOTAL of
Cost Annual Capitalised Capitalised Cost Annual Capitalised Capitalised Capitalised Internal Outer
of Energy Energy Total of Energy Energy Total cost Diameter Diameter
Sr. pump Charges Charges Cost pump Charges Charges Cost for in in
No. sets sets 30 yrs (mm) (mm)
THS THS THS THS THS THS THS THS THS
( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs ) ( Rs )---------------- ---------------------- ---------------- -------------------- --------------------- ---------------- ---------------------- ------------------------ ----------------- ------------------ ---------------- -
1 58680 77816 529994 699284 101005 142084 967715 195251 894535 693.82 711.20
2 57915 76801 523081 702667 98118 138023 940056 189671 892338 744.38 762.00 Min
3 57539 76302 519683 710139 96265 135416 922300 186088 896227 794.75 812.80
4 57150 75786 516168 722447 95017 133659 910333 183674 906121 844.54 863.60
5 56894 75448 513866 728661 93996 132224 900560 181702 910363 895.34 914.40
6 56774 75287 512770 749859 93378 131355 894641 180507 930366 944.58 965.20
7 56639 75109 511557 773097 92962 130769 890650 179702 952799 993.74 1016.00
8 56518 74949 510467 782132 92546 130184 886666 178898 961030 1044.54 1066.80
9 56518 74949 510467 808172 92344 129900 884731 178508 986680 1093.78 1117.60
*** TABLE 3 shows that the most economical size of MAIN is : =
762 mm costing CAPITALISED Rs. 892338 thousands ==== ========= =========== =============================
56639
56518
56518
57150
56894
56774
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.91
FINANCIAL
STATEMENT
SHIMLA JAL PRABANDHAN NIGAM LIMITED Financial Statements
S.N. Year Population Tot. Qty. LtrsTotal Estt.
Charges
Electrical
Charges
Chemical
Charges
Maintainence
and Repairs
Total Direct
Charges
Total Cost of
Water per 1000
litre
1 2020 243250 21818159 12099060 306378016 2805000 43335283 364617359 45.79
2 2021 248264 23141800 13066758 339255565 3111906 45502047 400936276 47.47
3 2022 253279 24465441 14112102 374654925 3470534 47777149 440014710 49.27
4 2023 258293 25789082 15240894 412746081 3827727 50166006 481980708 51.2
5 2024 263308 27112724 16460052 453709716 4222957 52674307 527067031 53.26
6 2025 268322 28436365 17777190 497737848 4657541 55308022 575480601 55.45
7 2026 273337 29760006 19199508 545034520 5115026 58073423 627422477 57.76
8 2027 278351 31083647 20735070 595816515 5617102 60977094 683145781 60.21
9 2028 283366 32407288 22394034 650314122 6145639 64025949 742879744 62.8
10 2029 288380 33730929 24185442 708771949 6724546 67227247 806909184 65.54
11 2030 293395 35054571 26120808 771449773 7333888 70588609 875493078 68.43
12 2031 298409 36378212 28210368 838623450 7972038 74118039 948923896 71.47
13 2032 303424 37701853 30466794 910585871 8701297 77823941 1027577903 74.67
14 2033 308438 39025494 32903724 987647974 9435547 81715138 1111702383 78.05
15 2034 313453 40349135 35535948 1070139823 10271968 85800895 1201748635 81.6
16 2035 318467 41672776 38378502 1158411738 11115532 90090940 1297996712 85.34
17 2036 324814 43403489 41448462 1347315704 12151914 94595487 1495511567 94.4
18 2037 331161 45134202 44764098 1466388474 13263758 99325261 1623741592 98.56
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
O & M EXPENDITURE STATEMENT
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNL
SHIMLA JAL PRABANDHAN NIGAM LIMITED Financial Statements
S.N. Year Population Tot. Qty. LtrsTotal Estt.
Charges
Electrical
Charges
Chemical
Charges
Maintainence
and Repairs
Total Direct
Charges
Total Cost of
Water per 1000
litre
19 2038 337508 46864915 48344832 1594000232 14495680 104291524 1761132268 102.96
20 2039 343856 48595628 52212174 1730707194 15776578 109506101 1908202047 107.58
21 2040 350203 50326341 56389182 1877099852 17149208 114981406 2065619648 112.45
22 2041 356550 52057054 60899952 2033805008 18619715 120730476 2234055151 117.58
23 2042 362897 53787767 65771718 2201487929 20194630 126767000 2414221277 122.97
24 2043 369244 55518480 71033148 2380854630 21880075 133105350 2606873203 128.64
25 2044 375591 57249193 76715922 2572654282 23683638 139760617 2812814459 134.61
26 2045 381938 58979906 82853508 2777681762 25668210 146748648 3032952128 140.89
27 2046 388285 60710619 89482230 2996780354 27734205 154086080 3268082870 147.48
28 2047 394633 62441332 96641154 3230844601 29942442 161790384 3519218582 154.41
29 2048 400980 64172045 104372550 3480823322 32302126 169879904 3787377902 161.7
30 2049 407327 65902758 112721982 3747722804 34822970 178373899 4073641655 169.35
31 2050 413674 67633471 121739802 4032610176 37514964 187292594 4379157535 177.39
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNL
SHIMLA JAL PRABANDHAN NIGAM LIMITED Financial Statements
Year Supervisor Rate Amount Electrician Rate Amount
Pump
Operator/
Fitter etc.
Rate Amount Labour Rate AmountTotal Estt.
Charges
2020 1.0 14850 178200 2 12690 228420 76 10590 9594540 18 9990 2097900 12099060
2021 1.0 16038 192456 2 13705 246690 76 11437 10361922 18 10789 2265690 13066758
2022 1.0 17321 207852 2 14801 266418 76 12352 11190912 18 11652 2446920 14112102
2023 1.0 18707 224484 2 15985 287730 76 13340 12086040 18 12584 2642640 15240894
2024 1.0 20204 242448 2 17264 310752 76 14407 13052742 18 13591 2854110 16460052
2025 1.0 21820 261840 2 18645 335610 76 15560 14097360 18 14678 3082380 17777190
2026 1.0 23566 282792 2 20137 362466 76 16805 15225330 18 15852 3328920 19199508
2027 1.0 25451 305412 2 21748 391464 76 18149 16442994 18 17120 3595200 20735070
2028 1.0 27487 329844 2 23488 422784 76 19601 17758506 18 18490 3882900 22394034
2029 1.0 29686 356232 2 25367 456606 76 21169 19179114 18 19969 4193490 24185442
2030 1.0 32061 384732 2 27396 493128 76 22863 20713878 18 21567 4529070 26120808
2031 1.0 34626 415512 2 29588 532584 76 24692 22370952 18 23292 4891320 28210368
2032 1.0 37396 448752 2 31955 575190 76 26667 24160302 18 25155 5282550 30466794
2033 1.0 40388 484656 2 34511 621198 76 28800 26092800 18 27167 5705070 32903724
2034 1.0 43619 523428 2 37272 670896 76 31104 28180224 18 29340 6161400 35535948
2035 1 47109 565308 2 40254 724572 76 33592 30434352 18 31687 6654270 38378502
2036 1.0 50878 610536 2 43474 782532 76 36279 32868774 18 34222 7186620 41448462
2037 1.0 54948 659376 2 46952 845136 76 39181 35497986 18 36960 7761600 44764098
2038 1.0 59344 712128 2 50708 912744 76 42315 38337390 18 39917 8382570 48344832
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
ESTABLISHMENT CHARGES
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.94
SHIMLA JAL PRABANDHAN NIGAM LIMITED Financial Statements
Year Supervisor Rate Amount Electrician Rate Amount
Pump
Operator/
Fitter etc.
Rate Amount Labour Rate AmountTotal Estt.
Charges
2039 1.0 64092 769104 2 54765 985770 76 45700 41404200 18 43110 9053100 52212174
2040 1.0 69219 830628 2 59146 1064628 76 49356 44716536 18 46559 9777390 56389182
2041 1.0 74757 897084 2 63878 1149804 76 53304 48293424 18 50284 10559640 60899952
2042 1.0 80738 968856 2 68988 1241784 76 57568 52156608 18 54307 11404470 65771718
2043 1.0 87197 1046364 2 74507 1341126 76 62173 56328738 18 58652 12316920 71033148
2044 1.0 94173 1130076 2 80468 1448424 76 67147 60835182 18 63344 13302240 76715922
2045 1.0 101707 1220484 2 86905 1564290 76 72519 65702214 18 68412 14366520 82853508
2046 1.0 109844 1318128 2 93857 1689426 76 78321 70958826 18 73885 15515850 89482230
2047 1.0 118632 1423584 2 101366 1824588 76 84587 76635822 18 79796 16757160 96641154
2048 1.0 128123 1537476 2 109475 1970550 76 91354 82766724 18 86180 18097800 104372550
2049 1.0 138373 1660476 2 118233 2128194 76 98662 89387772 18 93074 19545540 112721982
2050 1 149443 1793316 2 127692 2298456 76 106555 96538830 18 100520 21109200 121739802
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.95
SHIMLA JAL PRABANDHAN NIGAM LIMITED Financial Statements
Sr. No. SubworksNo of
Units
Superinte
ndent
Manager
(A.E.E.)
Supervisor
/Asstt.
Manager
(A.E.)
Assitant
Supervisor/
Junior
manager
Operators Fitters HelpersElectrician/
MechanicWatchman
1 Pump House 5.00 0 0 0 35 30 0 0 5
2 RWRM 1.00 0 0 0 0 0 1 0 0
3 WTP 1.00 1 1 1 4 4 0 2 2
4 PWRM 3.00 0 0 0 0 3 3 0 0
5 ESR/GSR 5.00 0 0 0 0 0 0 0 5
6 Gravity Main 2.00 0 0 0 0 0 0 0 2
7 D/System 0.00 0 0 0 0 0 0 0 0
1 1 1 39 37 4 2 14
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Staff Pattern
Total
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.96
SHIMLA JAL PRABANDHAN NIGAM LIMITED Financial Statements
YearConnected
HP /KW
Connected
Max.
Demand In
KVA
Demand
Charges Per
KVA In Rs.
Demand
Charges in
Rs.
Tot. Qty. Ltrs
Rate of
Pumping in
lps
Hrs. of
Pumping
Running
KWH
Avg. unit
Energy
Charges in
Rs
10 % Fuel /Sur.
Charges on
unit charges
Power ChargesTotal Power
Charges
2020 13659 17074.1 1800 30733335.0 24436337.9 540.2 12.6 62646518.45 4.0 4.40 275644681.18 306378016.18
2021 13659 17074.1 1890 32270001.8 25918816.0 540.2 13.3 66447091.72 4.2 4.62 306985563.75 339255565.50
2022 13659 17074.1 1985 33883501.8 27401294.1 540.2 14.1 70247665 4.4 4.85 340771422.92 374654924.75
2023 13659 17074.1 2084 35577676.9 28883772.2 540.2 14.9 74048238.28 4.6 5.09 377168404.09 412746081.02
2024 13659 17074.1 2188 37356560.8 30366250.4 540.2 15.6 77848811.55 4.9 5.35 416353154.77 453709715.55
2025 13659 17074.1 2297 39224388.8 31848728.5 540.2 16.4 81649384.83 5.1 5.62 458513459.57 497737848.39
2026 13659 17074.1 2412 41185608.3 33331206.6 540.2 17.1 85449958.11 5.4 5.90 503848911.96 545034520.22
2027 13659 17074.1 2533 43244888.7 34813684.7 540.2 17.9 89250531.38 5.6 6.19 552571625.88 595816514.55
2028 13659 17074.1 2659 45407133.1 36296162.8 540.2 18.7 93051104.66 5.9 6.50 604906988.97 650314122.08
2029 13659 17074.1 2792 47677489.8 37778640.9 540.2 19.4 96851677.94 6.2 6.83 661094459.31 708771949.07
2030 13659 17074.1 2932 50061364.2 39261119.1 540.2 20.2 100652251.2 6.5 7.17 721388409.22 771449773.46
2031 13659 17074.1 3079 52564432.5 40743597.2 540.2 21.0 104452824.5 6.8 7.53 786059017.88 838623450.34
2032 13659 17074.1 3233 55192654.1 42226075.3 540.2 21.7 108253397.8 7.2 7.90 855393216.47 910585870.55
2033 13659 17074.1 3394 57952286.8 43708553.4 540.2 22.5 112053971.1 7.5 8.30 929695687.38 987647974.16
2034 13659 17074.1 3564 60849901.1 45191031.5 540.2 23.2 115854544.3 7.9 8.71 1009289922.25 1070139823.37
2035 13659 17074.1 3742 63892396.2 46673509.6 540.2 24.0 119655117.6 8.3 9.15 1094519341.47 1158411737.65
2036 22872 28590.5 3929 112336860.2 48611908.1 876.7 15.4 128581372.3 8.7 9.60 1234978844.30 1347315704.49
2037 22872 28590.5 4126 117953703.2 50550306.6 876.7 16.0 133708550.9 9.2 10.08 1348434771.10 1466388474.31
2038 22872 28590.5 4332 123851388.4 52488705.1 876.7 16.6 138835729.6 9.6 10.59 1470148843.59 1594000231.95
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
ENERGY CHARGES for Raw Water Rising Main
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.97
SHIMLA JAL PRABANDHAN NIGAM LIMITED Financial Statements
YearConnected
HP /KW
Connected
Max.
Demand In
KVA
Demand
Charges Per
KVA In Rs.
Demand
Charges in
Rs.
Tot. Qty. Ltrs
Rate of
Pumping in
lps
Hrs. of
Pumping
Running
KWH
Avg. unit
Energy
Charges in
Rs
10 % Fuel /Sur.
Charges on
unit charges
Power ChargesTotal Power
Charges
2039 22872 28590.5 4549 130043957.8 54427103.6 876.7 17.2 143962908.3 10.1 11.12 1600663236.39 1730707194.17
2040 22872 28590.5 4776 136546155.7 56365502.1 876.7 17.9 149090086.9 10.6 11.67 1740553696.25 1877099851.92
2041 22872 28590.5 5015 143373463.5 58303900.6 876.7 18.5 154217265.6 11.1 12.26 1890431544.12 2033805007.58
2042 22872 28590.5 5265 150542136.6 60242299.1 876.7 19.1 159344444.3 11.7 12.87 2050945792.55 2201487929.18
2043 22872 28590.5 5529 158069243.5 62180697.6 876.7 19.7 164471622.9 12.3 13.51 2222785386.82 2380854630.28
2044 22872 28590.5 5805 165972705.6 64119096.1 876.7 20.3 169598801.6 12.9 14.19 2406681576.17 2572654281.81
2045 22872 28590.5 6095 174271340.9 66057494.6 876.7 20.9 174725980.3 13.5 14.90 2603410421.00 2777681761.92
2046 22872 28590.5 6400 182984908.0 67995893.1 876.7 21.5 179853158.9 14.2 15.64 2813795446.21 2996780354.17
2047 22872 28590.5 6720 192134153.4 69934291.6 876.7 22.2 184980337.6 14.9 16.43 3038710448.06 3230844601.42
2048 22872 28590.5 7056 201740861.0 71872690.1 876.7 22.8 190107516.3 15.7 17.25 3279082461.47 3480823322.50
2049 22872 28590.5 7409 211827904.1 73811088.6 876.7 23.4 195234694.9 16.5 18.11 3535894899.92 3747722804.00
2050 22872 28590.5 7779 222419299.3 75749487.1 876.7 24.0 200361873.6 17.3 19.02 3810190876.26 4032610175.54
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.98
SHIMLA JAL PRABANDHAN NIGAM LIMITED Financial Statements
1 2020 243250 21818159 239.00 9000.00 2151000 40.00 16350.00 654000
2 2021 248264 23141800 253.00 9450.00 2390850 42.00 17168.00 721056
3 2022 253279 24465441 268.00 9923.00 2659364 45.00 18026.00 811170
4 2023 258293 25789082 282.00 10419.00 2938158 47.00 18927.00 889569
5 2024 263308 27112724 297.00 10940.00 3249180 49.00 19873.00 973777
6 2025 268322 28436365 311.00 11487.00 3572457 52.00 20867.00 1085084
7 2026 273337 29760006 326.00 12061.00 3931886 54.00 21910.00 1183140
8 2027 278351 31083647 340.00 12664.00 4305760 57.00 23006.00 1311342
9 2028 283366 32407288 355.00 13297.00 4720435 59.00 24156.00 1425204
10 2029 288380 33730929 369.00 13962.00 5151978 62.00 25364.00 1572568
11 2030 293395 35054571 384.00 14660.00 5629440 64.00 26632.00 1704448
12 2031 298409 36378212 398.00 15393.00 6126414 66.00 27964.00 1845624
13 2032 303424 37701853 413.00 16163.00 6675319 69.00 29362.00 2025978
14 2033 308438 39025494 427.00 16971.00 7246617 71.00 30830.00 2188930
15 2034 313453 40349135 442.00 17820.00 7876440 74.00 32372.00 2395528
16 2035 318467 41672776 456.00 18711.00 8532216 76.00 33991.00 2583316
17 2036 324814 43403489 475.00 19647.00 9332325 79.00 35691.00 2819589
18 2037 331161 45134202 494.00 20629.00 10190726 82.00 37476.00 3073032
19 2038 337508 46864915 513.00 21660.00 11111580 86.00 39350.00 3384100
Amount of
Alum
Chlorine
Requirement
(Tone)
Rate of
Chlorine
Amount of
Chlorine
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
CHEMICAL CHARGES
Sr. No. Year Population Tot. Qty. Ltrs
Alum
Requirement
(Tone)
Rate of
Alum
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.99
SHIMLA JAL PRABANDHAN NIGAM LIMITED Financial Statements
Amount of
Alum
Chlorine
Requirement
(Tone)
Rate of
Chlorine
Amount of
ChlorineSr. No. Year Population Tot. Qty. Ltrs
Alum
Requirement
(Tone)
Rate of
Alum
20 2039 343856 48595628 532.00 22743.00 12099276 89.00 41318.00 3677302
21 2040 350203 50326341 551.00 23880.00 13157880 92.00 43384.00 3991328
22 2041 356550 52057054 570.00 25074.00 14292180 95.00 45553.00 4327535
23 2042 362897 53787767 589.00 26328.00 15507192 98.00 47831.00 4687438
24 2043 369244 55518480 608.00 27644.00 16807552 101.00 50223.00 5072523
25 2044 375591 57249193 627.00 29026.00 18199302 104.00 52734.00 5484336
26 2045 381938 58979906 646.00 30477.00 19688142 108.00 55371.00 5980068
27 2046 388285 60710619 665.00 32001.00 21280665 111.00 58140.00 6453540
28 2047 394633 62441332 684.00 33601.00 22983084 114.00 61047.00 6959358
29 2048 400980 64172045 703.00 35281.00 24802543 117.00 64099.00 7499583
30 2049 407327 65902758 722.00 37045.00 26746490 120.00 67304.00 8076480
31 2050 413674 67633471 741.00 38897.00 28822677 123.00 70669.00 8692287
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNLPage No.100
SHIMLA JAL PRABANDHAN NIGAM LIMITED Financial Statements
Annual M &
R Charges
Annual
Depreciation
(3x8) (5x7)
1 2 3 4 5 6 7 8 9 10
For Proposed Components
1
Detail survey and investigation including
consultancy services and site
development etc.
5300000 5565000 5008500 0 0
2 Acquisition of Land for various structures 197061300 206914365 186222929 0 0
3 Road Restoration and Plantation 54000000 56700000 51030000 0 0
25376002 26644802 23980322 67 0.0039 0.50% 126880 93523
105522766 110798904 99719014 67 0.0039 0.50% 527614 388904
20471565 21495143 19345629 67 0.0039 0.50% 102358 75448
4Water Treatment Plant (42 MLD) at
Shikrodi252000000 264600000 238140000 67 0.0039 0.50% 1260000 928746
5Desilting Tank at Shikrodi Capacity:-
10.50 ML 52500000 55125000 49612500 67 0.0039 0.50% 262500 193489
6
RCC sump well of 11.27 ML capacity
each at Devidhar and Dummi 112722451 118358574 106522716 67 0.0039 0.50% 563612 415439
7 Earthwork for Rising Main 131858963 138451912 124606720 0 0
8 Providing & laying of various rising mains 1201083903 1261138099 1135024289 50 0.0076 0.0025 3002710 8626185
9HT Lines from Himachal Pradesh State
Electricity Board Limited579119000 608074950 547267455 20 0.0354 0.0250 14477975 19373268
135507922 142283318 128054986 20 0.0354 0.0250 3387698 4533147
109620606 115101637 103591473 20 0.0354 0.0250 2740515 3667138
102700025 107835027 97051524 20 0.0354 0.0250 2567501 3435624
13Pumping Machinery for Raw water and
Pure Water Stages501750000 526837500 474153750 20 0.0354 0.0250 12543750 16785043
16
Automation to Raw Water Pumping
Machinery, Pure Water Pumping
Machinery and WTP
32018000 33618900 30257010 20 0.0354 0.0250 800450 1071098
10
Construction of pump house cum
attendant quarter 2 Nos. of 600 Sqm.
Each at Devidhar and Dummi .
36654000 38486700 34638030 67 0.0039 0.50% 183270 135088
4 Raw water stages at Shikrodi
10Providing Errecting Substations at
Shikrodi, Devidhar and Dummi
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
STATMENT SHOWING ANNUAL M & R CHARGES
Sr.
No.Sub Work Net cost Gross cost
90% of
Gross Cost
Life in
Years
Depreciation
Factor% of M & R
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNL
SHIMLA JAL PRABANDHAN NIGAM LIMITED Financial Statements
Annual M &
R Charges
Annual
Depreciation
(3x8) (5x7)
Sr.
No.Sub Work Net cost Gross cost
90% of
Gross Cost
Life in
Years
Depreciation
Factor% of M & R
11Construction of staff quarters Type-I,II &
III.61090000 64144500 57730050 67 0.0039 0.50% 305450 225147
12 Construction of bridges at various points. 29100000 30555000 27499500 67 0.0039 0.50% 145500 107248
road.67500000 70875000 63787500 67 0.0039 0.50% 337500 248771
15 Solar Power Plant 500 Kwp 38000000 39900000 35910000 0 0
16Environmental Impact Assessment &
Environmental Management Plan.(L.S)10000000 10500000 9450000 0 0
3860956504 4054004329 43335283 60303306Total Rs.
Yash Innovative Solutions LLP
Aurangabad, Maharashtra
Executive Engineer
SJPNL
Construction of 12Km.5/7m wide Katcha 14
COST
ESTIMATES
Page - 103
SHIMLA JAL PRABANDHAN NIGAM LIMITED Cost Estimates
Sr.
No.Item of work
Amount
(Rs in Lac)
1Detail survey and investigation including consultancy
services and site development etc.L.S 53.00
2 Acquisition of Land for various structures Annexure-A 1970.61
3 Road Restoration and Plantation Annexure-B 540.00
Annexure-C 253.76
Annexure-D 1055.23
Annexure-E 204.72
5 Water Treatment Plant (42 MLD) at Shikrodi Annexure-F 2520.00
6 Desilting Tank at Shikrodi Capacity:- 10.50 ML Annexure-G 525.00
7
RCC sump well of 11.27 ML capacity each at Devidhar
and Dummi Annexure-H 1127.22
8 Earthwork for Rising Main Annexure-I 1318.59
9 Providing & laying of various rising mains Annexure-J 12010.84
10HT Lines from Himachal Pradesh State Electricity
Board LimitedAnnexure-K 5791.19
Annexure-L 1355.08
Annexure-M 1096.21
Annexure-N 1027.00
12Pumping Machinery for Raw water and Pure Water
StagesAnnexure-O 5017.50
13Automation to Raw Water Pumping Machinery, Pure
Water Pumping Machinery and WTPAnnexure-P 320.18
14Construction of pump house cum attendant quarter 2
Nos. of 600 Sqm. Each at Devidhar and Dummi .366.54
19Environmental Impact Assessment & Environmental
Management Plan.(L.S)L..S. 100.00
38609.57
772.19
1158.29
40540.04
405.40
Gross Total Rs. In Lac.
Gross Total Rs in Crore
Add 3% contingency
Consultancy fees for detailed design, tender documents, bid
management and construction & supervison @2 % of cost
Net Total Rs. In Lac.
Annexure-Q
Providing Errecting Substations at Shikrodi, Devidhar
and Dummi11
"GENERAL ABSTRACT OF COST"
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist.
Shimla (HP).
Raw water stages at Shikrodi 4
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
15 Construction of staff quarters Type-I,II & III. 610.90
16 Construction of bridges at various points. 291.00
17 Construction of 12 Km.5/7m wide Katcha road. 675.00
18 Solar Power Plant 500 Kwp Annexure-R 380.00
Page - 104
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-A
Sr.No. Description Qty Unit RateAmount (Rs.
In Lakh.)
1 Acquisition of land for 1No. WTP at Shikrodi village of area 300
mtr x200mtr. each ie 60000 sqm.60000 Sqm
2 Acquisition of land for 2 Nos. Storage tanks at Devidhar,
Dummi & of approximate size 50mx50m= 2500sqm. for each
tank.ie 2500x2=5000 sqm.
5000 Sqm
3 Acquisition of land for 2 Nos. pump houses Devidhar and
Dummi .=600sqm.each i.e. 600x2=1200sqm.1200 Sqm
4 Acquisition of land for laying of rising main & gravity main of
length 22891 rmt . for the portion proposed to be laid in the
private land which is approximately 12000 mtr. In length & 5mtr.
In width ie 12000x5=60000 sqm.
60000 Sqm
Total area of 1 to 4 above.
Average rate=(1822+2078+1461+885)/4 =1561.50 Per Sqm 126200 Sqm 1561.50 1970.61
Net Amount 1970.61
ABSTRACT OF COST
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Acquisition of Land for various structures
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 105
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-B
Sr.No. Description Qty Unit RateAmount (Rs. In
Lakh.)
1 Restoration of metalled road approximately
5000mtr.x 5m wide @ 1000/-sqm. 25000 Sqm 1000 250.00
2 Restoration of Kachha road approximately 3000mtr.x
5m wide @ 600/-sqm.ie 3000x5x600=90,00,000/-15000 Sqm 600 90.00
3 Plantation in forest land/ cost of trees etc. L.S
LS 200.00
Net Amount 540.00
ABSTRACT OF COST
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Road Restoration and Plantation
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 106
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-C
Sr. No. Description Qty Unit Rate Amount ( in Rs.)
1
Excavation in foundations, trenches etc., in earth work in all type of soil such
as pick work Kankar,moorum shungles including decomposed of soft and
hard rock upto all heights stacking the excavated earth not more than 3
meters clear from the edge of the excavation and then returning the stacked
soil in 15cm layers,when required into the plinths sides of foundations etc.,
consolidating each deposited layer bywhen required into the plinths sides of
foundations etc., consolidating each deposited layer by ramming and
watering and then disposing of all surplus excavated earth upto all leads and
lifts etc. complete in all respect.
As per Rate Analysis -20
In hard portion 3600.00 Cum 1164.15 4190947
In Soft portion 1350.00 Cum 283.58 382838
2
Prov. & laying cement conc.1:2:4 (1cement :2sand: 4graded stone aggregate
20 mm nominal size ) and curing complete e/c the cost of form work and
reinforcement in foundation & plinth. (PCC M-150)
As per Rate Analysis -21
for Appraoch Channel 56.25 Cum 6073.71 341646
3
Providing & laying cement concrete using nominal mix of " M - 30 " with 20
mm & down gauge nominal size graded stone aggregate) & curing complete
excluding the cost of form work & reinforcement for reinforced concrete work
in Bottom raft slab (M-300)
As per Rate Analysis -22
for Appraoch Channel 162.00 Cum 8744.85 1416666
Construction of Bulk Water Supply to Shimla on River Sutluj near Shikrodi Distt. Shimla (HP).
Approach Channel (L=50 m)
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 107
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-C
Sr. No. Description Qty Unit Rate Amount ( in Rs.)
4
Providing & laying cement concrete using nominal mix of " M - 30 " with 20
mm & down gauge nominal size graded stone aggregate) & curing complete
excluding the cost of form work & reinforcement for reinforced concrete work
ingrade slabs/ Landing / Vertical Walls/ Waist slab/ steps for staircase (RCC
M-300)
810.00 Cum 10306.55 8348303
As per Rate Analysis -36
5Providing mild steel/tor steel reinforcement for RCC work includng bending
binding and placing in position complete. 72900.00 Kg 63.06 4596772
As per Rate Analysis -38
6Dewatering charges for estimation purpose for head works in river basin or
dam
For Approach Channel 90m days X 2 pumps of 20 HP working for 16 Hrs per
day57600 Bhp-Hrs 59.00 3398400
7
Structural steel work riveted, bolted or welded in built up sections, trusses
and framed work, including cutting, hoisting, fixing in position and applying a
priming coat of approved steel primer all complete.
For Trashrack 7600.00 Kg 67.60 513760
8
Providing, erecting triple spur gear type Chain Pulley Block suitable for
capacity as below with 6 m lift complete with load chain and hand chain
suitable for above lift, tested to 50% over load as per IS 3832 carrying ISI
mark.
3 Tonne Capacity 1.00 No 20269.00 20269
9Providing, erecting Travelling Trolley of capacity as below with 6 m lift, tested
to 50% over load
3 Tonne Capacity 1.00 0 13085.00 13085
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 108
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-C
Sr. No. Description Qty Unit Rate Amount ( in Rs.)
10
Providing form work with steel plates 3.15 mm thick welded with angle iron in
frame30X30X5 mm so as to give a fair finish including centering shuttering
strutting and propping etc,with wooden battens and ballies,height of propping
and centring below supporting floor to ceiling not execding 4 meters, and
removal of the same for insitu-reinforced concrete and plain concrete work in
:- Sub analysis for manufacturing steel plates for shuttering steel work
welded in built up section I/c cutting fixing in positionin angles,plates etc.
As per Rate Analysis - 28, 29
For Vertical Wall 3600.00 Sqm 492.17 1771811
For Foundation 300.00 Sqm 291.46 87437
11 Working drawing, Structural Design and Approval 2.00% % 14703387 294068
Total Cost 25,376,002
Total Net Cost in Lacs. 253.76
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 109
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-C
Item
No.
Description of ItemNo. L B D Qty Unit
1
Excavation in foundations, trenches etc., in earth work in all
type of soil such as pick work Kankar,moorum shungles
including decomposed of soft and hard rock upto all
heights stacking the excavated earth not more than 3
meters clear from the edge of the excavation and then
returning the stacked soil in 15cm layers,when required into
the plinths sides of foundations etc., consolidating each
deposited layer bywhen required into the plinths sides of
foundations etc., consolidating each deposited layer by
ramming and watering and then disposing of all surplus
excavated earth upto all leads and lifts etc. complete in all
respect.
In hard portion 1 50.00 4.50 16 3600.00 Cum
In Soft portion 1 50.00 9.00 3 1350.00 Cum
2
Prov. & laying cement conc.1:2:4 (1cement :2sand:
4graded stone aggregate 20 mm nominal size ) and curing
complete e/c the cost of form work and reinforcement in
foundation & plinth. (PCC M-150)
for Appraoch Channel 1 50.00 7.50 0.15 56.25 Cum
3
Providing & laying cement concrete using nominal mix of "
M - 30 " with 20 mm & down gauge nominal size graded
stone aggregate) & curing complete excluding the cost of
form work & reinforcement for reinforced concrete work in
Bottom raft slab (M-300)
for Appraoch Channel 1 50.00 7.20 0.45 162.00 Cum
Construction of Bulk Water Supply to Shimla on River Sutluj near Shikrodi Distt. Shimla (HP).
Approach Channel (L=50 m)
Measurements
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 110
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-C
Item
No.
Description of ItemNo. L B D Qty Unit
4
Providing & laying cement concrete using nominal mix of "
M - 30 " with 20 mm & down gauge nominal size graded
stone aggregate) & curing complete excluding the cost of
form work & reinforcement for reinforced concrete work
ingrade slabs/ Landing / Vertical Walls/ Waist slab/
steps for staircase (RCC M-300)
for Appraoch Channel 2 50.00 0.45 18.00 810.00 Cum
5
Providing mild steel/tor steel reinforcement for RCC work
includng bending binding and placing in position complete. 972.00 75.00 72900.00 Kg
6Dewatering charges for estimation purpose for head works
in river basin or dam
For Approach Channel 90m days X 2 pumps of 20 HP
working for 16 Hrs per day57600.00 BHp-Hrs
7
Structural steel work riveted, bolted or welded in built up
sections, trusses and framed work, including cutting,
hoisting, fixing in position and applying a priming coat of
approved steel primer all complete.
For Trashrack 7600.00 Kg
8
Providing, erecting triple spur gear type Chain Pulley Block
suitable for capacity as below with 6 m lift complete with
load chain and hand chain suitable for above lift, tested to
50% over load as per IS 3832 carrying ISI mark.
3 Tonne Capacity 1 1 No
9Providing, erecting Travelling Trolley of capacity as below
with 6 m lift, tested to 50% over load
3 Tonne Capacity 1 1 No
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 111
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-C
Item
No.
Description of ItemNo. L B D Qty Unit
10 Providing form work with steel plates 3.15 mm thick welded
with angle iron in frame30X30X5 mm so as to give a fair
finish including centering shuttering strutting and propping
etc,with wooden battens and ballies,height of propping and
centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced
concrete and plain concrete work in :- Sub analysis for
manufacturing steel plates for shuttering steel work welded
in built up section I/c cutting fixing in positionin
angles,plates etc.
For Vertical Wall 4.00 50.00 18 3600.00 Sqm
For Foundation 1.00 50.00 6.00 300.00 Sqm
11 Working drawing, Structural Design and Approval 2.00% %
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 112
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Sr. No. Description Qty Unit Rate Amount (in Rs.)
1
Excavation in foundations, trenches etc., in earth work in all type of soil
such as pick work Kankar,moorum shungles including decomposed of
soft and hard rock upto all heights stacking the excavated earth not
more than 3 meters clear from the edge of the excavation and then
returning the stacked soil in 15cm layers,when required into the plinths
sides of foundations etc., consolidating each deposited layer bywhen
required into the plinths sides of foundations etc., consolidating each
deposited layer by ramming and watering and then disposing of all
surplus excavated earth upto all leads and lifts etc. complete in all
respect.
As per Rate Analysis -20
In hard Portion 16380.00 Cum 1164.15 19068808
In Soft Portion 5832.00 Cum 283.58 1653858
2
Prov. & laying cement conc.1:2:4 (1cement :2sand: 4graded stone
aggregate 20 mm nominal size ) and curing complete e/c the cost of
form work and reinforcement in foundation & plinth. (PCC M-150)
As per Rate Analysis -21
For Jack well 72.90 Cum 6073.71 442773
3
Providing & laying cement concrete using nominal mix of " M - 30 " with
20 mm & down gauge nominal size graded stone aggregate) & curing
complete excluding the cost of form work & reinforcement for
reinforced concrete work in Bottom raft slab (M-300)
As per Rate Analysis -22
For Jack well 275.62 Cum 8744.85 2410221
Construction of Bulk Water Supply to Shimla on River Sutluj near Shikrodi Distt. Shimla (HP).
Jackwell and Pump House (15 mx 24 m)
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 113
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Sr. No. Description Qty Unit Rate Amount (in Rs.)
4
Providing & laying cement concrete using nominal mix of " M - 30 " with
20 mm & down gauge nominal size graded stone aggregate) & curing
complete excluding the cost of form work & reinforcement for
reinforced concrete work in RCC Columns (M-300)
As per Rate Analysis -37
For Jack well up to floor slab 18 columns out of 28 merged in vertical
wall149.85 Cum 10190.05 1526980
5
Providing & laying cement concrete using nominal mix of " M - 30 " with
20 mm & down gauge nominal size graded stone aggregate) & curing
complete excluding the cost of form work & reinforcement for
reinforced concrete work in Beams, Braces and Lintels (M-300)
148.00 Cum 10306.55 1525402
As per Rate Analysis -36
6
Providing & laying cement concrete using nominal mix of " M - 30 " with
20 mm & down gauge nominal size graded stone aggregate) & curing
complete excluding the cost of form work & reinforcement for
reinforced concrete work ingrade slabs/ Landing / Vertical Walls/ Waist
slab/ steps for staircase (RCC M-300)
1607.55 Cum 10306.55 16568295
As per Rate Analysis -36
7
Providing & laying cement concrete using nominal mix of " M - 30 " with
20 mm & down gauge nominal size graded stone aggregate) & curing
complete excluding the cost of form work & reinforcement for
reinforced concrete work in RCC Chajjas (RCC M-300)
4.97 Cum 10306.55 51203
As per Rate Analysis -36
8Providing mild steel/tor steel reinforcement for RCC work includng
bending binding and placing in position complete. 228804.77 Kg 63.06 14427482
As per Rate Analysis -38
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 114
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Sr. No. Description Qty Unit Rate Amount (in Rs.)
9Brick work using common burnt clay building bricks (iind class) in
found. And plinth in 1:6 (1cement:6sand)131.50 Cum 9540.57 1254631
As per Rate Analysis -25
10
Rough side exterior cement plaster on wall up to a height of 10 mtr.
above ground level with a mixture of sand and gravel or crushed stone
graded from 6mm to 12 mm nominal size dashed over and including
fresh plaster in two coats, backing coat 10 mm cement plaster 1:3
(1cement:3sand) and finishing coat 10 mm cement mortor 1:3
(1cement:3sand) mixed with 10 % finely grounded hydrated lime by
volume of cement including arrises, chamfersb and/or rounded angles
not exceeding 80 mm in girth. (natural cement finish using ordinary
cement)
As per Rate Analysis -33
Total qty of external plaster for PH 1223.19 sqm 575.41 703832
11
20 mm cement plaster in single coat on fair side f brick/stone masonry
for interior plastering up to floor two level including arrises, internal
rounded angles, chamfers and/or rounded angles not exceeding 80mm
in girth and finished even and smooth .
As per Rate Analysis -32
Total qty of Internal plaster for PH 1297.16 sqm 232.29 301322
12
Providing and applying Two coats of wall care Putty on plastered
surface and Ceiling and Walls to prepare surface even and smooth of
approved make, etc complete.
1297.16 sqm 112.00 145282
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 115
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Sr. No. Description Qty Unit Rate Amount (in Rs.)
13
Providing, constructing coffer dam in river basin / dam storages as per
type design including excavation, filling the middle portion with B. C.
soil (in gunny bags if required). Providing impervious / semipervious
materials on both side of B.C. soil (in gunny bags if required) including
ramming, compacting to the satisfaction of Engneer-in-charge till the
completion of work including dismantling coffer dam after completion of
works and disposing off the material as directed by the Engineer-in-
charge.
6.00 m depth, 2.0 m top wdth and 1:1.5 side slope, length = 150m 36000.00 Cum 560.00 20160000
14Dewatering charges for estimation purpose for head works in river
basin or dam230400.00 BHp-Hrs 59.00 13593600
15
Providing and fixing rolling shutter fabricated from steel laths of
minimum thickness 0.9 mm with lock plate of 3.15 mm thickness
reinforced with 35 x 35 x 5 mm angle section fitted with sliding bolts
and handles for both sides, deep M.S. channel section of depth and
thickness not less than 65 mm and 3.15 mm respectively with hold fast
arrangements, M.S. Bracket plate 300 x 300 x 3.15 mm minimum size
and shape with square bar, suspension shaft of minimum 32 mm
diameter, hood cover of M.S. sheet not less than 0.9 mm thickness and
of any size at top and safety devices including mechanical gear
operation arrangement consisting of worm gear wheels and worms of
high grade cast iron or mild steel and one coat of red lead primer
etc.complete. (I.S. 62481979) (With mechanical gear) Spec. No. :BD-
T-55 Page No.510
54.00 Sqm 3893.00 210222
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 116
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Sr. No. Description Qty Unit Rate Amount (in Rs.)
16
Providing and fixing in position, Single shuttered aluminium extruded
powder coated openable door of overall size 0.90 m x 2.40 m with
aluminium door frame of powder coated section 101.60 x 4.75mm ,
3.18 mm thick and shutter comprising of powder coated section having
bottom and lock rail of size 150 mm x 44.5 mm x 3.00 mm thick top
rails 47.62 x 44.45 mm x 3.00 mm thick , vertical style 47.62 x 44.45
mm, 3.00 mm thick and for shutter plain glass panes 5 mm thick for top
panels and 12mm thick both side laminated phenol bonded particle
board panels for bottom panels etc. , I.S.I. mark , heavy duty, Hydraulic
floor spring of 150 kg capacity , having heavy duty concealed lock,
necessary beading, glazing clips, PVC gaskets, 250mm length tower
bolts, 150mm diam. pad handle, etc. as per detailed design and
drawing or as directed by engineer in charge including all materials ,
labours, and equipment etc.Complete
3.78 Sqm 7383.00 27908
17
Providing and fixing 50 mm x 50 mm Mild Steel square pipe
framedsteel windows of various sizes as per details with welded square
bars12 mm at 10 cm center to center without hot dip zinc coating
without / with ventilator including fabrication, glazing with plain /
obscuredglass panes 5 mm thick of approved type and quality, all
fixtures andfastenings and finishing with one coat of primer complete.
100.80 Sqm 2345.00 236376
18
Providing and fixing in position Mild steel fixed staggered ( Z Type )
Ventilator as per detailed drawing with hot deep zink coating including
fabricating with Mild steel 'Z 'Section of size 20mm x 25 mm and 3 mm
thick at weight 1.42 Kg/Rmt,with stainless steel mosquito net of 304
Grade,4 mm thick float glass ?as directed by Engineer In charge
including necessary welding, grinding, two coats of oil paint
etc.complete
27.00 Sqm 2834.00 76518
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 117
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Sr. No. Description Qty Unit Rate Amount (in Rs.)
19
Providing and applying priming coat on concrete/ masonary/ Asbestos
Cement plastered surfaces including scaffolding if necessary,preparing
the surface by thoroughly cleaning oil, grease, dirt and other foreign
matter and sand papering as required etc. complete.
1297.16 sqm 28.00 36320
20
Providing and applying two coats of exterior acraylic emulsion paint
confirming to corresponding I.S. of approved manufacture and of
approved colour to the plastered surfaces including cleaning,preparing
the plaster surface, applying primer coat ,scaffolding if necessary , and
watering the surface for two days etc complete.
1223.19 Sqm 208.00 254423
21
Providing and applying two coats of textured synthetic paint of
approved shade and quality and one coat of primer before applying
textured paint including scaffolding if necessary preparing surface by
thoroughly cleaning oil, grease, dirt and other materials as required,etc.
complete.
1297.16 Sqm 128.00 166036
22
Providing and applying priming coat over new/old steel and other metal
surfaces including preparing the surface by thoroughly cleaning oil,
grease, dirt and other foreign matter and scoured with wire brushes,
fine steel wool, scrappers and sand paper, scaffolding etc.complete.
181.80 Sqm 26.00 4727
23
Providing and laying machine cut machine polished machine cut Kota
stone slabs 20 to 25 mm thick for treads and risers of steps and
staircases, with rounded nosing for the treads on a bed of 1:4 cement
mortar including cement float, filling joints with neat cement slurry,
curing, polishing and cleaning etc. complete.
492.50 Sqm 1187.20 584694
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 118
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Sr. No. Description Qty Unit Rate Amount (in Rs.)
24
Providing and fixing in required position skirting or dado of polished
Kotah Stone slab 25 mm to 30 mm thick fixed on base on plaster of
cement mortar 1:4 including cement float, filling joints with cement
slurry, curing rubbing, polishing and cleaning complete.
6.51 Sqm 1014.20 6602
25
Providing and fixing G.I. pipe railing having 1.0 M height consisting 50
x 50 x 6 mm thick M. S. angles as verticals at 1.5 M c/c and additional
posts at every corner with 3 rows of 25 mm dia G.I. pipes of medium
class variety as horizontal and painting 3 coats of oil paint over 1 coat
of anticorrosive paint of approved colour and shade including cost of all
labour, transporting bends to curved shape, etc. complete.
231.00 RM 671.00 155001
26
Providing and fixing M.S. chequerred plate flooring of following
thickness supported on M.S.angles (25 x 25 x 5 mm size) including
welding, cutting and fabricating the plates to the required square or
rounding shape, making holes in the plate, including providing and
applying 3 coats of anticorrosive paint, etc. complete as directed by
Engineer-in-charge. 8 mm thick
16.00 Sqm. 3698.00 59168
27
Providing and fixing in position copper lightening conductor including
copper rod of 20 mm dia as per upper terminal 1.5 M long with a knob
at end and with conical spike at top, copper tape conductor 20 x 3 mm
size, copper earth plate of 3 mm thick and 0.81 sqm. in area, clamps at
1 M centre to centre including, necessary excavation, laying and fixing
the conductor, providing and fixing 40 mm G.I. pipe upto 3 M height
from ground and 0.5 M below ground including making all connections,
filling earthing pit with charcoal, salt, etc. &refilling & watering, etc.
complete as per specifications laid down in relevent I.S. codes. For
Tape of 10M length
1.00 No. 11804.00 11804
Extra Length 50.00 Mtr. 321.00 16050
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 119
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Sr. No. Description Qty Unit Rate Amount (in Rs.)
28
Providing cement based water proofing treatment to terraces (Indian
water proofing or alike) with brick bats laid in required slope to drain the
water for any span after cleaning the base surface. Applying a coat of
cement slurry admixed with approved water proofing compound and
laying the brick bats on bottom layer in C.M.1:5 admixed with approved
water proofing compound filling up to half depth of brick bats, curing
this layer for 3 days, applying cement slurry over this layer joints of
brick bats with C.M.1:3 admixed with approved water proofing
compound and finally top finishing with average 20 mm.thick layers of
same mortar added with jute fiber at 1 Kg per bag including finishing
the surface smooth with cement slurry admixed with approved water
proofing compound. Marking finished surface with false squares of
300mm x 300 mm. making the junctions at the parapet rounded and
tapered top for required height, with drip mould at the junction of plaster
and parapet and curing and covering 10 years Guarantee against
leakproofness on Court fee stamp paper of Rs. 500/- including ponding
test etc. complete.
360.00 sqm 854.74 307707
PWD SSR 2018-19 I.N.31.04 pg.no.255
29
Providing and fixing in position M.S. ladder 0.50 M wide consisting of
75 x 10 mm M.S. flats as stringers and 16 mm dia M.S. bars in double
rows as steps placed at 25 cm c/c including cost of material and labour
involved, welding, anchoring and applying 3 coats of anti-corrosive
paint, etc. complete as directed by Engineer-in-charge.
12.00 Rm 1281.00 15372
30
Providing and fixing in position C.I. dapuri steps or 22 mm dia. M.S.
bar step with proper anchorage, etc. and providing and applying 3
coats of ant-corrosive paint, etc. complete as directed by Engineer-in-
charge.
20.00 NO 220.00 4400
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 120
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Sr. No. Description Qty Unit Rate Amount (in Rs.)
31
Providing, hoisting and fixing in position C.I. manhole, frame and cover
of best quality and of required size and shape with locking
arrangements including applying 2 coats of anti-corrosive paint, etc.
complete. ii) Rate on weight basis for any size and type of frame
and cover.
2000.00 Kg 65.00 130000
32
Providing and fixing in position C.I. /M.S. rose pieces in intake wells
including cost of all materials and labour, painting with three coats of
anti-corrosive oil paint, etc.complete as directed by Engineer-in-charge.
1200 mm dia & 1.5 m Length 18000.00 Kg 79.00 1422000
33
Providing and fixing in position C.I. /M.S. Sluice gate in intake wells
including cost of all materials and labour, painting with three coats of
anti-corrosive oil paint, etc.complete as directed by Engineer-in-charge.
1200 mm dia 18000.00 Kg 85.00 1530000
34
Providing and fixing in position C.I. /M.S. Penstock Arrangement in
intake wells including cost of all materials and labour, painting with
three coats of anti-corrosive oil paint, etc.complete as directed by
Engineer-in-charge.
12.00 Nos 25000.00 300000
35
Providing structural steel work in rolled sections like joists, channels,
angles, tees, etc. as per detailed designs and drawings including fixing
in position without connecting plates, braces, etc. and one coat of
anticorrosive paint and over it two coats of oil painting of approved
quality and shade, etc. complete.(Bd-C-2/275) for Pump supporting
girders, Sluice gates and Penstcok Arrangement
7.00 MT 50552.00 353864
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 121
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Sr. No. Description Qty Unit Rate Amount (in Rs.)
36
Providing and installing mercury water level indicator for RCC ESR
and wash water tank site as per instructions of Engineer-in -charge at
ground level of the tank or nearing pump house or room for RCC ESR
having 15 mtrs. stage height and 5 mtrs. water storage height with
indication of water height in storage tank in metre and 1/10th of metre
including providing and installing 15 mm dia class ' B' G.I. piping with
necessary accessories from bottom of the tank upto the instrument as
per instructions of Engineer- in - charge.
2.00 No.'s 17496.00 34992
37
Providing form work with steel plates 3.15 mm thick welded with angle
iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and
ballies,height of propping and centring below supporting floor to ceiling
not execding 4 meters, and removal of the same for insitu-reinforced
concrete and plain concrete work in :- Sub analysis for manufacturing
steel plates for shuttering steel work welded in built up section I/c
cutting fixing in positionin angles,plates etc.
As per Rate Analysis - 28, 29
For Foundation 459.36 Sqm 291.46 133883
For RCC work 9898.95 Sqm 492.17 4871962
38 Working drawing, Structural Design and Approval 2.00% % 36952356 739047
Total Cost 105,522,766
Total Net Cost in Lacs. 1,055.23
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 122
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
1 Excavation in foundations, trenches etc., in earth work in all type of
soil such as pick work Kankar,moorum shungles including
decomposed of soft and hard rock upto all heights stacking the
excavated earth not more than 3 meters clear from the edge of the
excavation and then returning the stacked soil in 15cm layers,when
required into the plinths sides of foundations etc., consolidating each
deposited layer bywhen required into the plinths sides of foundations
etc., consolidating each deposited layer by ramming and watering
and then disposing of all surplus excavated earth upto all leads and
lifts etc. complete in all respect.
In hard Portion 1.00 21.00 30.00 26 16380.00 Cum
In Soft Portion 1.00 27.00 36.00 6 5832.00 Cum
2 Prov. & laying cement conc.1:2:4 (1cement :2sand: 4graded stone
aggregate 20 mm nominal size ) and curing complete e/c the cost
of form work and reinforcement in foundation & plinth. (PCC M-150)
For Jack well 1.00 18.00 27.00 0.15 72.90 Cum
3 Providing & laying cement concrete using nominal mix of " M - 30 "
with 20 mm & down gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work & reinforcement for
reinforced concrete work in Bottom raft slab (M-300)
For Jack well 1.00 17.40 26.40 0.6 275.62 Cum
Construction of Bulk Water Supply to Shimla on River Sutluj near Shikrodi Distt. Shimla (HP).
Jackwell and Pump House (15 mx 24 m)
Measurements
Measurements
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 123
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
4 Providing & laying cement concrete using nominal mix of " M - 30 "
with 20 mm & down gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work & reinforcement for
reinforced concrete work in RCC Columns (M-300)
For Jack well up to floor slab 18 columns out of 28 merged in
vertical wall10.00 0.45 0.90 37 149.85 Cum
For Pump house 21.00 0.45 0.90 12 102.06 Cum
Total 251.91 Cum
5 Providing & laying cement concrete using nominal mix of " M - 30 "
with 20 mm & down gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work & reinforcement for
reinforced concrete work in Beams, Braces and Lintels (M-300)
Brace beams below floor level
llel to 24 m span (external braces merged into verical wall) 60.00 0.30 0.45 3.55 28.76 Cum
llel to 15 m span (external braces merged into verical wall) 75.00 0.30 0.45 4.1 41.51 Cum
Floor Beams
llel to 24 m span (external braces merged into verical wall) 12.00 0.30 0.30 3.55 3.83 Cum
llel to 15 m span (external beams merged into verical wall) 15.00 0.30 0.30 4.10 5.54 Cum
Brace beams above floor level
llel to 24 m span 12.00 0.30 0.45 3.55 5.75 Cum
llel to 15 m span 15.00 0.30 0.45 4.10 8.30 Cum
Brace beams for panel Slab
llel to 24 m span 6.00 0.30 0.45 3.55 2.88 Cum
llel to 15 m span 5.00 0.30 0.45 4.10 2.77 Cum
Corbel Beam
llel to 24 m span 18.00 0.30 0.45 3.55 8.63 Cum
llel to 15 m span 6.00 0.30 0.45 4.10 3.32 Cum
Projection for Corbel 2.00 0.75 0.60 24.00 21.60 Cum
Roof Beam
llel to 24 m span 18.00 0.30 0.30 3.55 5.75 Cum
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 124
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
llel to 15 m span 7.00 0.30 0.30 4.10 2.58 Cum
llel to 15 m span 7.00 0.30 0.30 9.1 5.73 Cum
For staircase headroom 2.00 0.23 0.30 3.55 0.49 Cum
For staircase headroom 2.00 0.23 0.30 4.10 0.57 Cum
Total 148.00 Cum
6Providing & laying cement concrete using nominal mix of " M - 30 "
with 20 mm & down gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work & reinforcement for
reinforced concrete work ingrade slabs/ Landing / Vertical Walls/
Waist slab/ steps for staircase (RCC M-300)
a) Vertical walls
llel to 24 m span 2.00 24.00 0.45 37 799.20
llel to 15 m span 2.00 15.00 0.45 37 499.50
b) Staircase
steps 240.000 0.200 0.25 1.5 18.00
waist slab 16.000 4.243 1.5 0.15 15.27
landings 16.000 3.000 1 0.15 7.20
c) Slabs & Landings
pump house floor slab 1.00 15.00 24.00 0.6 216.00
gallery slabs 1.00 17.40 1.20 0.15 3.13
1.00 24.00 1.20 0.15 4.32
staircase openings @ floor slab -1.00 3.00 5.00 0.3 -4.50
pump openings @ floor slab -4.00 2.00 2.00 0.3 -4.80
pump house roof slab 1.00 15.00 24.00 0.15 54.00
staircase openings @ roof slab -1.00 3.00 5.00 0.15 -2.25
Headroom slab for staircase 1.00 3.00 5.50 0.15 2.48
Total 1607.55 Cum
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 125
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
7 Providing & laying cement concrete using nominal mix of " M - 30 "
with 20 mm & down gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work & reinforcement for
reinforced concrete work in RCC Chajjas (RCC M-300)
Lift 10 -15 m (RL 472 m) 2.000 16.200 0.60 0.1 1.94
2.000 25.200 0.60 0.1 3.02
Total 4.97 Cum
8 Providing mild steel/tor steel reinforcement for RCC work includng
bending binding and placing in position complete. 2288.05 100 kg / cum 228804.77 Kg
9 Brick work using common burnt clay building bricks (iind class) in
found. And plinth in 1:6 (1cement:6sand)
llel to 24 m span 12.00 0.23 3.55 10.65 104.35
llel to 15 m span 6.00 0.23 3.55 10.65 52.17
For Staff cabin 1.00 0.23 3.55 3.55 2.90 Cum
For Staff cabin 1.00 0.23 3.55 3.55 2.90 Cum
Dedudctions
Shutters -4.00 0.23 3.00 4.7 -12.97
Door of staff cabin -1.00 0.23 0.90 2.1 -0.43
Windows -32.00 0.23 1.50 1.2 -13.25
Ventilators -18.00 0.23 1.50 0.6 -3.73
Staircase door -1.00 0.23 0.90 2.1 -0.43
Total 131.50 Cum
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 126
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
10 Rough side exterior cement plaster on wall up to a height of 10 mtr.
above ground level with a mixture of sand and gravel or crushed
stone graded from 6mm to 12 mm nominal size dashed over and
including fresh plaster in two coats, backing coat 10 mm cement
plaster 1:3 (1cement:3sand) and finishing coat 10 mm cement
mortor 1:3 (1cement:3sand) mixed with 10 % finely grounded
hydrated lime by volume of cement including arrises, chamfersb
and/or rounded angles not exceeding 80 mm in girth. (natural
cement finish using ordinary cement)
llel to 24 m span 2.00 24.23 12.60 610.60
llel to 15 m span 2.00 15.23 12.60 383.80
chajjas top & bottom 4.00 16.20 0.60 38.88
4.00 25.20 0.60 60.48
For staircase headroom 2.00 3.23 3.00 19.38
For staircase headroom 2.00 5.23 3.00 31.38
For column projections 18.00 0.67 12.00 144.72
deductions
doors -0.50 0.90 2.10 -0.95
windows -16.00 1.50 1.20 -28.80
ventilators -9.00 1.50 0.60 -8.10
rolling shutters -2.00 3.00 4.70 -28.20
Total qty of external plaster for PH 1223.19 sqm
11 20 mm cement plaster in single coat on fair side f brick/stone
masonry for interior plastering up to floor two level including arrises,
internal rounded angles, chamfers and/or rounded angles not
exceeding 80mm in girth and finished even and smooth .
llel to 24 m span 2.00 24.00 12.00 576.00
llel to 15 m span 2.00 15.00 12.00 360.00
corbel top & bottom 4.00 24.00 0.75 72.00
Roof slab soffit 1.00 12.00 15.00 180.00
For staircase headroom 2.00 3.00 5.00 30.00
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 127
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
For panel slab soffit 1.00 24.00 5.00 120.00
For staff room 1.00 3.55 3.55 12.60
For staff room 1.00 3.55 3.55 12.60
deductions
doors -0.50 0.90 2.10 -0.95
windows -16.00 1.50 1.20 -28.80
ventilators -9.00 1.50 0.60 -8.10
rolling shutters -2.00 3.00 4.70 -28.20
Total qty of Internal plaster for PH 1297.16 sqm
12 Providing and applying Two coats of wall care Putty on plastered
surface and Ceiling and Walls to prepare surface even and smooth
of approved make, etc complete.
1297.16 sqm
13 Providing, constructing coffer dam in river basin / dam storages as
per type design including excavation, filling the middle portion with
B. C. soil (in gunny bags if required). Providing impervious /
semipervious materials on both side of B.C. soil (in gunny bags if
required) including ramming, compacting to the satisfaction of
Engneer-in-charge till the completion of work including dismantling
coffer dam after completion of works and disposing off the material
as directed by the Engineer-in-charge.
6.00 m depth, 2.0 m top wdth and 1:1.5 side slope, length = 150m 150 2.00 20.00 6.00 36000.00 Cum
14 Dewatering charges for estimation purpose for head works in river
basin or dam230400.00 BHp-Hrs
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 128
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
15 Providing and fixing rolling shutter fabricated from steel laths of
minimum thickness 0.9 mm with lock plate of 3.15 mm thickness
reinforced with 35 x 35 x 5 mm angle section fitted with sliding bolts
and handles for both sides, deep M.S. channel section of depth and
thickness not less than 65 mm and 3.15 mm respectively with hold
fast arrangements, M.S. Bracket plate 300 x 300 x 3.15 mm
minimum size and shape with square bar, suspension shaft of
minimum 32 mm diameter, hood cover of M.S. sheet not less than
0.9 mm thickness and of any size at top and safety devices
including mechanical gear operation arrangement consisting of
worm gear wheels and worms of high grade cast iron or mild steel
and one coat of red lead primer etc.complete. (I.S. 62481979) (With
mechanical gear) Spec. No. :BD-T-55 Page No.510
4.00 3.00 4.50 54.00 Sqm
16 Providing and fixing in position, Single shuttered aluminium extruded
powder coated openable door of overall size 0.90 m x 2.40 m with
aluminium door frame of powder coated section 101.60 x 4.75mm ,
3.18 mm thick and shutter comprising of powder coated section
having bottom and lock rail of size 150 mm x 44.5 mm x 3.00 mm
thick top rails 47.62 x 44.45 mm x 3.00 mm thick , vertical style
47.62 x 44.45 mm, 3.00 mm thick and for shutter plain glass panes
5 mm thick for top panels and 12mm thick both side laminated
phenol bonded particle board panels for bottom panels etc. , I.S.I.
mark , heavy duty, Hydraulic floor spring of 150 kg capacity , having
heavy duty concealed lock, necessary beading, glazing clips, PVC
gaskets, 250mm length tower bolts, 150mm diam. pad handle, etc.
as per detailed design and drawing or as directed by engineer in
charge including all materials , labours, and equipment
etc.Complete
2.00 0.90 2.1 3.78 Sqm
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 129
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
17 Providing and fixing 50 mm x 50 mm Mild Steel square pipe
framedsteel windows of various sizes as per details with welded
square bars12 mm at 10 cm center to center without hot dip zinc
coating without / with ventilator including fabrication, glazing with
plain / obscuredglass panes 5 mm thick of approved type and
quality, all fixtures andfastenings and finishing with one coat of
primer complete.
56.00 1.50 1.2 100.80 Sqm
18 Providing and fixing in position Mild steel fixed staggered ( Z Type )
Ventilator as per detailed drawing with hot deep zink coating
including fabricating with Mild steel 'Z 'Section of size 20mm x 25
mm and 3 mm thick at weight 1.42 Kg/Rmt,with stainless steel
mosquito net of 304 Grade,4 mm thick float glass ?as directed by
Engineer In charge including necessary welding, grinding, two coats
of oil paint
etc.complete
30.00 1.50 0.6 27.00 Sqm
19 Providing and applying priming coat on concrete/ masonary/
Asbestos Cement plastered surfaces including scaffolding if
necessary,preparing the surface by thoroughly cleaning oil, grease,
dirt and other foreign matter and sand papering as required etc.
complete.
1297.16 sqm
20 Providing and applying two coats of exterior acraylic emulsion paint
confirming to corresponding I.S. of approved manufacture and of
approved colour to the plastered surfaces including
cleaning,preparing the plaster surface, applying primer coat
,scaffolding if necessary , and watering the surface for two days etc
complete.
1223.19 Sqm
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 130
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
21 Providing and applying two coats of textured synthetic paint of
approved shade and quality and one coat of primer before applying
textured paint including scaffolding if necessary preparing surface by
thoroughly cleaning oil, grease, dirt and other materials as
required,etc. complete.
1297.16 Sqm
22 Providing and applying priming coat over new/old steel and other
metal surfaces including preparing the surface by thoroughly
cleaning oil, grease, dirt and other foreign matter and scoured with
wire brushes, fine steel wool, scrappers and sand paper, scaffolding
etc.complete.
181.80 Sqm
23 Providing and laying machine cut machine polished machine cut
Kota stone slabs 20 to 25 mm thick for treads and risers of steps
and staircases, with rounded nosing for the treads on a bed of 1:4
cement mortar including cement float, filling joints with neat cement
slurry,
curing, polishing and cleaning etc. complete.
Floor 1 24.00 15.00 360.00 sqm
Floor 1 24.00 5.00 120.00 sqm
For cabin room 1 5.00 5.00 25.00 sqm
Deductions
openings for staircase -1.00 2.50 5.00 -12.50 sqm
Total qty of flooring Total 492.50 sqm
24 Providing and fixing in required position skirting or dado of polished
Kotah Stone slab 25 mm to 30 mm thick fixed on base on plaster of
cement mortar 1:4 including cement float, filling joints with cement
slurry, curing rubbing, polishing and cleaning complete.
For skirting 1.00 78.00 0.1 7.80 sqm
Deductions
openings for door -1.00 0.90 0.10 -0.09 sqm
openings for shutter -4.00 3.00 0.10 -1.20 sqm
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 131
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
Total qty of skirting Total 6.51 sqm
25 Providing and fixing G.I. pipe railing having 1.0 M height consisting
50 x 50 x 6 mm thick M. S. angles as verticals at 1.5 M c/c and
additional posts at every corner with 3 rows of 25 mm dia G.I. pipes
of medium class variety as horizontal and painting 3 coats of oil
paint over 1 coat of anticorrosive paint of approved colour and
shade including cost of all labour, transporting bends to curved
shape, etc. complete.
For outside walkway 2 27.00 54.00 RM
2 18.00 36.00 RM
For inside walkway 1 24.00 24.00 RM
For staircase 30 3.90 117.00 RM
Total qty of railing 231.00 RM
26 Providing and fixing M.S. chequerred plate flooring of following
thickness supported on M.S.angles (25 x 25 x 5 mm size) including
welding, cutting and fabricating the plates to the required square or
rounding shape, making holes in the plate, including providing and
applying 3 coats of anticorrosive paint, etc. complete as directed by
Engineer-in-charge. 8 mm thick
4.00 2.00 2 16.00 Sqm
27 Providing and fixing in position copper lightening conductor including
copper rod of 20 mm dia as per upper terminal 1.5 M long with a
knob at end and with conical spike at top, copper tape conductor 20
x 3 mm size, copper earth plate of 3 mm thick and 0.81 sqm. in
area, clamps at 1 M centre to centre including, necessary
excavation, laying and fixing the conductor, providing and fixing 40
mm G.I. pipe upto 3 M height from ground and 0.5 M below ground
including making all connections, filling earthing pit with charcoal,
salt, etc. &refilling & watering, etc. complete as per specifications
laid down in relevent I.S. codes. For Tape of 10M length
1.00 No.
Extra Length 50.00 Mtr.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 132
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
28 Providing cement based water proofing treatment to terraces (Indian
water proofing or alike) with brick bats laid in required slope to drain
the water for any span after cleaning the base surface. Applying a
coat of cement slurry admixed with approved water proofing
compound and laying the brick bats on bottom layer in C.M.1:5
admixed with approved water proofing compound filling up to half
depth of brick bats, curing this layer for 3 days, applying cement
slurry over this layer joints of brick bats with C.M.1:3 admixed with
approved water proofing compound and finally top finishing with
average 20 mm.thick layers of same mortar added with jute fiber at
1 Kg per bag including finishing the surface smooth with cement
slurry admixed with approved water proofing compound. Marking
finished surface with false squares of 300mm x 300 mm. making the
junctions at the parapet rounded and tapered top for required height,
with drip mould at the junction of plaster and parapet and curing and
covering 10 years Guarantee against leakproofness on Court fee
stamp paper of Rs. 500/- including ponding test etc. complete.
1.00 15.00 24.00 360.00 sqm
29 Providing and fixing in position M.S. ladder 0.50 M wide consisting
of 75 x 10 mm M.S. flats as stringers and 16 mm dia M.S. bars in
double rows as steps placed at 25 cm c/c including cost of material
and labour involved, welding, anchoring and applying 3 coats of anti-
corrosive paint, etc. complete as directed by Engineer-in-charge.
12.00 1 12.00 RM
30 Providing and fixing in position C.I. dapuri steps or 22 mm dia. M.S.
bar step with proper anchorage, etc. and providing and applying 3
coats of ant-corrosive paint, etc. complete as directed by Engineer-
in-charge.
20.00 Nos
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 133
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
31 Providing, hoisting and fixing in position C.I. manhole, frame and
cover of best quality and of required size and shape with locking
arrangements including applying 2 coats of anti-corrosive paint, etc.
complete. ii) Rate on weight basis for any size and type of frame
and cover.
2000.00 kg
32 Providing and fixing in position C.I. /M.S. rose pieces in intake wells
including cost of all materials and labour, painting with three coats of
anti-corrosive oil paint, etc.complete as directed by Engineer-in-
charge.
1200 mm dia & 1.5 m Length 18000.00 kg
33 Providing and fixing in position C.I. /M.S. Sluice gate in intake wells
including cost of all materials and labour, painting with three coats of
anti-corrosive oil paint, etc.complete as directed by Engineer-in-
charge.
1200 mm dia 18000.00 kg
34 Providing and fixing in position C.I. /M.S. Penstock Arrangement in
intake wells including cost of all materials and labour, painting with
three coats of anti-corrosive oil paint, etc.complete as directed by
Engineer-in-charge.
12.00 Nos
35 Providing structural steel work in rolled sections like joists, channels,
angles, tees, etc. as per detailed designs and drawings including
fixing in position without connecting plates, braces, etc. and one
coat of anticorrosive paint and over it two coats of oil painting of
approved quality and shade, etc. complete.(Bd-C-2/275) for Pump
supporting girders, Sluice gates and Penstcok Arrangement
7.00 ton
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 134
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
36 Providing and installing mercury water level indicator for RCC ESR
and wash water tank site as per instructions of Engineer-in -charge
at ground level of the tank or nearing pump house or room for RCC
ESR having 15 mtrs. stage height and 5 mtrs. water storage height
with indication of water height in storage tank in metre and 1/10th of
metre including providing and installing 15 mm dia class ' B' G.I.
piping with necessary accessories from bottom of the tank upto the
instrument as per instructions of Engineer- in - charge.
2.00 No.'s
37Providing form work with steel plates 3.15 mm thick welded with
angle iron in frame30X30X5 mm so as to give a fair finish including
centering shuttering strutting and propping etc,with wooden battens
and ballies,height of propping and centring below supporting floor to
ceiling not execding 4 meters, and removal of the same for insitu-
reinforced concrete and plain concrete work in :- Sub analysis for
manufacturing steel plates for shuttering steel work welded in built
up section I/c cutting fixing in positionin angles,plates etc.
A For Foundation 1.00 17.40 26.40 459.36 Sqm
B For Vertical Wall 4.00 15.00 37 2220.00 Sqm
4.00 24.00 37 3552.00 Sqm
For Columns 10.00 2.70 37 999.00 Sqm
28.00 2.70 12 907.20 Sqm
For Beams
Brace beams below floor level
llel to 24 m span (external braces merged into verical wall) 60 1.5 3.55 319.50 Sqm
llel to 15 m span (external braces merged into verical wall) 75 1.5 4.1 461.25 Sqm
Floor Beams
llel to 24 m span (external braces merged into verical wall) 12 0.75 3.55 31.95 Sqm
llel to 15 m span (external beams merged into verical wall) 15 0.75 4.1 46.13 Sqm
Brace beams above floor level
llel to 24 m span 12 1.5 3.55 63.90 Sqm
llel to 15 m span 15 1.5 4.1 92.25 Sqm
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 135
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-D
Item
No.Description of Item Qty Unit
No L B D
Measurements
Brace beams for panel Slab
llel to 24 m span 6 0.9 3.55 19.17 Sqm
llel to 15 m span 5 0.9 4.1 18.45 Sqm
Corbel Beam
llel to 24 m span 18 1.5 3.55 95.85 Sqm
llel to 15 m span 6 1.5 4.1 36.90 Sqm
Projection for Corbel 2 1.35 24 64.80 Sqm
Roof Beam
llel to 24 m span 18 0.9 3.55 57.51 Sqm
llel to 15 m span 7 0.9 4.1 25.83 Sqm
llel to 15 m span 7 0.9 9.1 57.33 Sqm
For staircase headroom 2 0.53 3.55 3.76 Sqm
For staircase headroom 2 0.53 4.1 4.35 Sqm
Floor slab and Roof Slab 2 15 24 720.00 Sqm
staircase waist slab 16.00 4.24 1.50 101.82 Sqm
9898.95 Sqm
38 Working drawing, Structural Design and Approval 2.00% %
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 136
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-E
Sr. No. Description Qty Unit RateAmount ( in
Rs.)
1
Excavation in foundations, trenches etc., in earth work in all type of soil such as
pick work Kankar,moorum shungles including decomposed of soft and hard
rock upto all heights stacking the excavated earth not more than 3 meters
clear from the edge of the excavation and then returning the stacked soil in
15cm layers,when required into the plinths sides of foundations etc.,
consolidating each deposited layer bywhen required into the plinths sides of
foundations etc., consolidating each deposited layer by ramming and watering
and then disposing of all surplus excavated earth upto all leads and lifts etc.
complete in all respect.
As per Rate Analysis -20
For Peir Foudation 1055.12 Cum 988.04 1042499
2
Prov. & laying cement conc.1:2:4 (1cement :2sand: 4graded stone aggregate
20 mm nominal size ) and curing complete e/c the cost of form work and
reinforcement in foundation & plinth. (PCC M-150)
As per Rate Analysis -21
For Peir Foudation 49.43 Cum 6073.71 300248
3
Providing & laying cement concrete using nominal mix of " M - 30 " with 20 mm
& down gauge nominal size graded stone aggregate) & curing complete
excluding the cost of form work & reinforcement for reinforced concrete work in
Bottom raft slab (M-300)
As per Rate Analysis -22
For Peir Foudation 415.80 Cum 8744.85 3636109
Construction of Bulk Water Supply to Shimla on River Sutluj near Shikrodi Distt. Shimla (HP).
Approach Bridge (L= 60 m)
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 137
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-E
Sr. No. Description Qty Unit RateAmount ( in
Rs.)
4
Providing & laying cement concrete using nominal mix of " M - 30 " with 20 mm
& down gauge nominal size graded stone aggregate) & curing complete
excluding the cost of form work & reinforcement for reinforced concrete work
ingrade slabs/ Landing / Vertical Walls/ Waist slab/ steps for staircase (RCC M-
300)
558.75 Cum 10306.55 5758783
As per Rate Analysis -36
5
Providing & laying cement concrete using nominal mix of " M - 30 " with 20 mm
& down gauge nominal size graded stone aggregate) & curing complete
excluding the cost of form work & reinforcement for reinforced concrete work in
Beams, Braces and Lintels (M-300)
90.00 Cum 10306.55 927589
As per Rate Analysis -36
6Providing mild steel/tor steel reinforcement for RCC work includng bending
binding and placing in position complete. 106455.00 Kg 63.06 6712612
As per Rate Analysis -38
7
Providing and applying two coats of exterior acraylic emulsion paint confirming
to corresponding I.S. of approved manufacture and of approved colour to the
plastered surfaces including cleaning,preparing the plaster surface, applying
primer coat ,scaffolding if necessary , and watering the surface for two days etc
complete.
2137.70 Sqm 208.00 444642
8
Providing and fixing G.I. pipe railing having 1.0 M height consisting 50 x 50 x 6
mm thick M. S. angles as verticals at 1.5 M c/c and additional posts at every
corner with 3 rows of 25 mm dia G.I. pipes of medium class variety as
horizontal and painting 3 coats of oil paint over 1 coat of anticorrosive paint of
approved colour and shade including cost of all labour, transporting bends to
curved shape, etc. complete.
120.00 Rmt 671.00 80520
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 138
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-E
Sr. No. Description Qty Unit RateAmount ( in
Rs.)
0
Providing form work with steel plates 3.15 mm thick welded with angle iron in
frame30X30X5 mm so as to give a fair finish including centering shuttering
strutting and propping etc,with wooden battens and ballies,height of propping
and centring below supporting floor to ceiling not execding 4 meters, and
removal of the same for insitu-reinforced concrete and plain concrete work in :-
Sub analysis for manufacturing steel plates for shuttering steel work welded in
built up section I/c cutting fixing in positionin angles,plates etc.
As per Rate Analysis - 28, 29
For Foundation 462.00 Sqm 291.46 134653
For Other Components 2209.00 Sm 492.17 1087203
10 Working drawing, Structural Design and Approval 2.00% % 17335341.00 346707
Total Cost 20,471,565
Total Net Cost in Lacs. 204.716
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 139
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-E
No. L B D
1
Excavation in foundations, trenches etc., in earth work in all type of
soil such as pick work Kankar,moorum shungles including
decomposed of soft and hard rock upto all heights stacking the
excavated earth not more than 3 meters clear from the edge of the
excavation and then returning the stacked soil in 15cm layers,when
required into the plinths sides of foundations etc., consolidating each
deposited layer bywhen required into the plinths sides of foundations
etc., consolidating each deposited layer by ramming and watering
and then disposing of all surplus excavated earth upto all leads and
lifts etc. complete in all respect.
For Peir Foudation 11 10.90 4.40 2 1055.12 Cum
2
Prov. & laying cement conc.1:2:4 (1cement :2sand: 4graded stone
aggregate 20 mm nominal size ) and curing complete e/c the cost
of form work and reinforcement in foundation & plinth. (PCC M-150)
For Peir Foudation 11.00 10.70 4.20 0.1 49.43 Cum
3
Providing & laying cement concrete using nominal mix of " M - 30 "
with 20 mm & down gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work & reinforcement for
reinforced concrete work in Bottom raft slab (M-300)
For Peir Foudation 11.00 10.50 4.00 0.9 415.80 Cum
Construction of Bulk Water Supply to Shimla on River Sutluj near Shikrodi Distt. Shimla (HP).
Approach Bridge (L= 60 m)
Measurements
MeasurementsItem
No.Description of Item Qty Unit
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 140
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-E
No. L B D
MeasurementsItem
No.Description of Item Qty Unit
4
Providing & laying cement concrete using nominal mix of " M - 30 "
with 20 mm & down gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work & reinforcement for
reinforced concrete work ingrade slabs/ Landing / Vertical Walls/
Waist slab/ steps for staircase (RCC M-300)
Lift 0 - 5 m below and above GL
Vertical wall for Peir 11.00 7.50 1.00 3.5 288.75
Deck Slab 1.00 60.00 7.50 0.60 270.00
558.75 Cum
5
Providing & laying cement concrete using nominal mix of " M - 30 "
with 20 mm & down gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work & reinforcement for
reinforced concrete work in Beams, Braces and Lintels (M-300)
Deck slab beams 30 6 0.5 1 90.00 Cum
6Providing mild steel/tor steel reinforcement for RCC work includng
bending binding and placing in position complete. 1064.55 100 kg / cum 106455.00 Kg
7
Providing and applying two coats of exterior acraylic emulsion paint
confirming to corresponding I.S. of approved manufacture and of
approved colour to the plastered surfaces including
cleaning,preparing the plaster surface, applying primer coat
,scaffolding if necessary , and watering the surface for two days etc
complete.
Peirs 11.00 17.00 7.1 1327.70
Deck beams 30 6 2 1 360.00
Deck Slab 1.00 60.00 7.50 450.00
Total qty of exterior Painting 2137.70 Sqm
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 141
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-E
No. L B D
MeasurementsItem
No.Description of Item Qty Unit
8
Providing and fixing G.I. pipe railing having 1.0 M height consisting
50 x 50 x 6 mm thick M. S. angles as verticals at 1.5 M c/c and
additional posts at every corner with 3 rows of 25 mm dia G.I. pipes
of medium class variety as horizontal and painting 3 coats of oil
paint over 1 coat of anticorrosive paint of approved colour and
shade including cost of all labour, transporting bends to curved
shape, etc. complete.
Approach Bridge 2 60 120.00 Rmt
9 Providing form work with steel plates 3.15 mm thick welded with
angle iron in frame30X30X5 mm so as to give a fair finish including
centering shuttering strutting and propping etc,with wooden battens
and ballies,height of propping and centring below supporting floor to
ceiling not execding 4 meters, and removal of the same for insitu-
reinforced concrete and plain concrete work in :- Sub analysis for
manufacturing steel plates for shuttering steel work welded in built
up section I/c cutting fixing in positionin angles,plates etc.
For Foundation 11.00 10.50 4.00 462.00 Sqm
For piers 11.00 17.00 7 1309.00 Sqm
For Deck slab 1.00 60.00 7.50 450.00 Sqm
For Deck beams 30.00 6.00 2.50 450.00 Sqm
10 Working drawing, Structural Design and Approval 2.00% %
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 142
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-F
Sr. No. Description Qty (in MLD)Rate
(In Rs).Unit
Amount
(In Lac).
1 Design, Construction and commissioning of 1 Nos. water treatment plants of
capacity 42 MLD at Shikrodi which includes all civil, mechanical & electrical
works. The scope of work also includes inlet chambers, Flow measurement
system, Alum dosing system, pre and post chlorination, treatment for viral
conatamination, Flash mixers, clariflocculator with mechanical clarrifier & sludge
scrapping system, sludge collection & sludge disposal system, rapid sand filters
complete with back washing system having fully computerised automatic system
SCADA, PLC, plant building, Admin. Building, staff quarters, chemical house,
compound wall to entire premises, etc. alongwith clear water tank of 4 hour
detention capacity with pump house for pure water pumping machinery including
site development . This includes c/o back washing tanks, compressors for
agitating the filter media, recirculation sump and pump house, recirculation
pumping machinery, etc. with all machinery & fittings /piping thereof for WTP. @
Rs.60 Lakh per MLD i.e. 42 x 6000000 = 2520 Lakhs.
42.00 60.00 ML 2520.00
2520.00Total Rs. In Lac.
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Water Treatment Plant (42 MLD) at Shikrodi
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 143
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-G
Sr. No. Description Qty (in ML)Rate
(In Rs).Unit
Amount
(In Lac).
1Construction of RCC desilting tank taking detention/ storage period as 6
hours for 42 MLD scheme including all other necessary allied works10.50 5.00 ML 525.00
525.00Total Rs. In Lac.
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Desilting Tank at Shikrodi Capacity:- 10.50 ML
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 144
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-H
Sr. No. Description Qty (in ML)Rate
(In Rs).Unit
Amount
(In Lac).
1
C/O RCC Sump well at Devidhar for 4 hours storage
capacity.Against lifting of 67.60 mld in 24 hours.including compound
wall and all other necessary allied works11.27 5.00 ML 563.61
2
C/O RCC Sump well at Dummi for 4 hours storage capacity.Against
lifting of 67.60 mld in 24 hours.including compound wall and all other
necessary allied works11.27 5.00 ML 563.61
1127.22
ABSTRACT OF COST
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
RCC sump well of 11.27 ML capacity each at Devidhar and Dummi
Total Rs. In Lac.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 145
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-I
Sr. No. Description QtyRate
(In Lac).Unit
Amount
(In Lac).
Excavation in foundation trenches etc., in earth work in all kind of soil
such as pick work, jumper work, blasting work, chiselling work including
soft and hard rock decomposed, saturated soil or conglomerate
including black topping if any & stacking the excavated earth not more
3 metres. clear from the edge of excavation and then returning the
stacked soil in 15cm layers, when required into plinths and sides of
foundation etc. consolidating each deposited layer by ramming and
watering and then disposing of all surplus excavated earth up to all
leads and lifts as directed by the Engineer-in-charge.
As per Rate Analysis - 1
Rising Main 176000 547.71 Per cum 963.97
22000 x 4x 2 = 176000 cum
2 Cutting in earth work and disposal of excavated earth upto a lead of
20mtr. In pick jumper work. 50% each for laying of pipe line and civil
structures. 88000 402.98 Per cum 354.62
As per Rate Analysis - 3
1318.59Total Rs. In Lac.
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Earthwork for Rising Main
1
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 146
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-J
Sr. No. Description QtyRate
(In Rs).Unit
Amount
(In Lac).
1 Providing, laying & jointing of 762 mm outer dia pipe class API 5L X grade-65
standard with wall thickness of 7.92 mm with standing test pressure of 84
Kg./cm2
bevelled end weight 146.91 Kg. per mtr. as per API Code IS 3183-2007
in a random length of 4 to 7 mtr. and jointing with M.S. flange Table-34 after 100
mtrs. length as per IS 6392-1971 including bends of all degrees, tees made of
parent pipes including welding of flanges with pipe (3 layers) nuts & bolts,
rubber, gasket of 3mm thick ferodo make of relevant IS specification and other
joint jointed with butt welding including painting of pipes( two coats) outer side
with anticorrosive bituminous paint complete with in all leads and lifts and as
per the direction of Engineer-in-charge.
11565.40 32910.33 Rmt 3806.21
As per Rate Analysis - 45
2 Providing, laying & jointing of 762 mm outer dia pipe class API 5L X grade-65
standard with wall thickness of 8.74 mm with standing test pressure of 92
Kg./cm2
bevelled end weight 161.61 Kg. per mtr. as per API Code IS 3183-2007
in a random length of 4 to 7 mtr. and jointing with M.S. flange Table-34 after 100
mtrs. length as per IS 6392-1971 including bends of all degrees, tees made of
parent pipes including welding of flanges with pipe (3 layers) nuts & bolts,
rubber, gasket of 3mm thick ferodo make of relevant IS specification and other
joint jointed with butt welding including painting of pipes( two coats) outer side
with anticorrosive bituminous paint complete with in all leads and lifts and as
per the direction of Engineer-in-charge.
336.60 36092.17 Rmt 121.49
As per Rate Analysis - 46
ABSTRACT OF COST
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Providing & laying of various rising mains
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 147
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-J
Sr. No. Description QtyRate
(In Rs).Unit
Amount
(In Lac).
3 Providing, laying & jointing of 762 mm outer dia pipe class API 5L X grade-65
standard with wall thickness of 9.53 mm with standing test pressure of 101
Kg./cm2
bevelled end weight 176.29 Kg. per mtr. as per API Code IS 3183-2007
in a random length of 4 to 7 mtr. and jointing with M.S. flange Table-34 after 100
mtrs. length as per IS 6392-1971 including bends of all degrees, tees made of
parent pipes including welding of flanges with pipe (3 layers) nuts & bolts,
rubber, gasket of 3mm thick ferodo make of relevant IS specification and other
joint jointed with butt welding including painting of pipes( two coats) outer side
with anticorrosive bituminous paint complete with in all leads and lifts and as
per the direction of Engineer-in-charge.
2998.80 39499.31 Rmt 1184.51
As per Rate Analysis - 47
4 Providing, laying & jointing of 762 mm outer dia pipe class API 5L X grade-65
standard with wall thickness of 10.31 mm with standing test pressure of 109
Kg./cm2
bevelled end weight 190.93 Kg. per mtr. as per API Code IS 3183-2007
in a random length of 4 to 7 mtr. and jointing with M.S. flange Table-34 after 100
mtrs. length as per IS 6392-1971 including bends of all degrees, tees made of
parent pipes including welding of flanges with pipe (3 layers) nuts & bolts,
rubber, gasket of 3mm thick ferodo make of relevant IS specification and other
joint jointed with butt welding including painting of pipes( two coats) outer side
with anticorrosive bituminous paint complete with in all leads and lifts and as
per the direction of Engineer-in-charge.
948.60 42662.71 Rmt 404.70
As per Rate Analysis - 48
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 148
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-J
Sr. No. Description QtyRate
(In Rs).Unit
Amount
(In Lac).
5 Providing, laying & jointing of 762 mm outer dia pipe class API 5L X grade-65
standard with wall thickness of 11.13 mm with standing test pressure of 117
Kg./cm2
bevelled end weight 205.54 Kg. per mtr. as per API Code IS 3183-2007
in a random length of 4 to 7 mtr. and jointing with M.S. flange Table-34 after 100
mtrs. length as per IS 6392-1971 including bends of all degrees, tees made of
parent pipes including welding of flanges with pipe (3 layers) nuts & bolts,
rubber, gasket of 3mm thick ferodo make of relevant IS specification and other
joint jointed with butt welding including painting of pipes( two coats) outer side
with anticorrosive bituminous paint complete with in all leads and lifts and as
per the direction of Engineer-in-charge.
734.40 45826.47 Rmt 336.55
As per Rate Analysis - 49
6 Providing, laying & jointing of 762 mm outer dia pipe class API 5L X grade-65
standard with wall thickness of 11.91 mm with standing test pressure of 126
Kg./cm2
bevelled end weight 220.12 Kg. per mtr. as per API Code IS 3183-2007
in a random length of 4 to 7 mtr. and jointing with M.S. flange Table-34 after 100
mtrs. length as per IS 6392-1971 including bends of all degrees, tees made of
parent pipes including welding of flanges with pipe (3 layers) nuts & bolts,
rubber, gasket of 3mm thick ferodo make of relevant IS specification and other
joint jointed with butt welding including painting of pipes( two coats) outer side
with anticorrosive bituminous paint complete with in all leads and lifts and as
per the direction of Engineer-in-charge.
2111.40 48981.16 Rmt 1034.19
As per Rate Analysis - 50
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 149
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-J
Sr. No. Description QtyRate
(In Rs).Unit
Amount
(In Lac).
7 Providing, laying & jointing of 762 mm outer dia pipe class API 5L X grade-65
standard with wall thickness of 12.70 mm with standing test pressure of 134
Kg./cm2
bevelled end weight 234.67 Kg. per mtr. as per API Code IS 3183-2007
in a random length of 4 to 7 mtr. and jointing with M.S. flange Table-34 after 100
mtrs. length as per IS 6392-1971 including bends of all degrees, tees made of
parent pipes including welding of flanges with pipe (3 layers) nuts & bolts,
rubber, gasket of 3mm thick ferodo make of relevant IS specification and other
joint jointed with butt welding including painting of pipes( two coats) outer side
with anticorrosive bituminous paint complete with in all leads and lifts and as
per the direction of Engineer-in-charge.
3304.80 52131.34 Rmt 1722.84
As per Rate Analysis - 51
22000.00
8 Providing & fixing of cast carbon steel swing check valve (NRV)confirming
following specifications complete in all respect.
BS : 1868/API 6D
Class - 600
CCS (ASTM A 216 GR WCB)
Aluminum Painted
Bolted Cover
Renewable Seat
13% Cr. Steel (ASTM
A276 TYPE 410)
Flanges as Per ASME
B 16.5 CL - 600 R.F.
(Drilled) Serrated
B.T.P. - 150 Bar Hyd.
S.T.P. - 110 Bar Hyd.
(with Bye Pass Arrangement )
a) 750 mm dia 30.00 3995190.00 Each 1498.85
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 150
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-J
Sr. No. Description QtyRate
(In Rs).Unit
Amount
(In Lac).
9 Providing & fixing of cast carbon steel gate valve confirming to follwing
specifications complete in all respect. BS: 1414 / API : 600
Class - 600
CCS (ASTM A 216 GR WCB)
Aluminum Painted,
Bolted Bonnet, O/S &
Yoke Type, Rising Stem,
Renewable Seat,
Solid Flexible Wedge
SS (ASTM A : 276 TYPE 410 ) OR its Eq
Flanges as per ASME B 16.5 CL-600
R.F. (Drilled) Serrated
B.T.P. - 150 Bar Hyd.
S.T.P. - 110 Bar Hyd.
6.9 Bar AIR
(with Bevel Gear Arrangement )
a) 750 mm dia 30.00 4996150.00 Each 1498.85
c) 300mm dia 15.00 655280.00 Each 98.29
10 Constructing chamber for sluice valve with CI surface box 100mm top,160mm
bottom 7 180mm deep inside with chain lid & RCC top slab 1:2:4 mix 100mm
thick & foundation concrete 1:5:10 mix & inside plastering with cement mortar
1:3 finished with a floating coat of neat cement including curing complete.
1000x1000x1500mm. inside size with 300mm wall of stone masonry in cement
mortar 1:6. 75.00 43396.62 Each 32.55
As per Rate Analysis - 42
11 Providing & fixing of cast steel (IS: 210FG 200) double acting Air Valve G & K
Brass, Nut, Natural Rubber moulded on wooden balls ends flanged and drilled
as per IS 1538. 150 mm dia 50.00 73967.90 Each 36.98
12 C/O RCC anchor/thrust blocks. 800.00 29356.14 Each 234.85
As per Rate Analysis - 43
12010.84Total Rs . In Lac
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 151
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-K
Sr.
No.Description Qty
Rate
(In Lac).Unit
Amount
( In Lac).
1 Providing Supply of power including providing errecting
HT line from nearest Power station at Shikrodi, Devidhar
and Dummi. As per Quotation from HPSEBL
ABSTRACT OF COST
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
HT Lines from Himachal Pradesh State Electricity Board Limited
Total Rs. In Lac.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
1.00 Job 5791.19
5791.19
Page - 152
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-L
Sr. No. Description Qty Rate (Rs.) Unit Amount (Rs.)
3 PHASE, POWER TRANSFORMERS
Part A 500 KVA-66000 / 433Volt(for lighting &other purpose) 2 994940 No. 1989880
i) 11 MVA (66KVA) 2 14490202.10 No. 28980404.2
Providing of 66 kV EQUIPMENTS
1 i) Circuit Breaker- 72.5 kV SF - 6 CB 4 442000.00 No. 1768000
2 ii) Control and Relay Panel
3 Transformer Panel (HV)side with differential Relay 2 527000.00 No. 1054000
4 Bus Coupler Panel 4 721212.00 No. 2884848
5 Feeder Panel 4 491541.00 No. 1966164
6 iii) Isolator with out Earth blade- 72.5 kV,1250 A 6 151000.00 No. 906000
7
iv) Multi Core Multi ratio Current Transformers -66 kV, CURRENT
TRANSFORMER
12 58000.00 No.696000
8
v) Lightening Arrester-60 kV(SURGE ARRESTOR with surge
counter)
3 35400.00 No.106200
9 vi) PTs -33kV Potential Transformer 3 58869.00 No. 176607
10
Indoor Switchgear and allied Equipments comprising of Panel Board,
CTs, PTs etc.
36 kV, 2000 A, 25 kA I/C 2 2426000.00 No. 4852000
12KV, 1250 A , 12.5 KA I/C 2 543000.00 No. 1086000
11 SUBSTATION STRUCTURE
PER MT FOR C GRADE (For Snow Zone) 20 92000.00 MT 1840000
Total 48306103.2
Equipment Structures including Bus Bar, Earthing, Hardware Fitting,
disc insulator, pin insulator, AB switch etc. @ 10% ( on Sub Total 1
above )
10 %
4830610.32
(a) Power and Control Cables, Earthmat , E. I. etc. @ 13% (on Sub
Total 1 above)
13 %6279793.42
(b) Cable trays @ .75 % & Air-Conditioning @ .25 % i.e. on Sub-
Total-1
25 %483061.03
Spares @ 3%, (on item 1 to 6 above) 3 % 1449183.10
Estimate for 66 KV HT Substation for Pumping station at RW &PW at WTP Site
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 153
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-L
Sr. No. Description Qty Rate (Rs.) Unit Amount (Rs.)
Transportation @ 5 % & Insurance @ 1 % ( Total 06 % on Sub Total
1 above)
5 %2898366.19
Sub Total- II (Item 1 to 10) 64247117.26
(a) Erection & Commissioning Charges @ 10 % 10 %4830610.32
(b) Sub-station T & P* LS 500000.00
Civil Works ( as per Annexure H1 ) 3782000.00
Sub Total (Item 14+15+16) 73359727.58
Part B General Equipments
i) 200 V, Battery a/w Battery Charger & Distribution Board
a) D. C. Battery
i) 220 V, 400AH 1 902000.00 No. 902000
ii) 220 V,300AH 1 752000.00 No. 752000
iii) 220 V, 200AH 1 475000.00 No. 475000
iv) 48 V, 400AH 1 210000.00 No. 210000
v) 48 V, 200AH 1 129000.00 No. 129000
vi) 30 V, 100 AH 1 38000.00 No. 38000
b) Battery Charger
i) 200 V, 400AH 2 274000.00 No. 548000
ii) 200 V, 200AH 2 260000.00 No. 520000
iii) 48 V, 200 AH 2 212000.00 No. 424000
iv) 30 V, 100 AH 2 93000.00 No. 186000
v) 200 V, 300AH 2 260000.00 No. 520000
c) 220 V, D. C. Distribution Board 1 114000.00 No. 114000
d) 48 V D.C. Distribution Board 1 117000.00 No. 117000
e) 30 V D.C. Distribution Board 1 103000.00 No. 103000
f) 220V-30V- DC-DC Converter 1 152000.00 No. 152000
ii) Station Transformer
a) 250 kVA, 33 / 0.4 kV 1 428000.00 No. 428000
b) 250 kVA, 11 / 0.4 kV 1 371000.00 No. 371000
iii) 415 V, A.C. Distribution Board 1 1087000.00 No. 1087000
Part C d) Testing & Measuring Instruments
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 154
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-L
Sr. No. Description Qty Rate (Rs.) Unit Amount (Rs.)
i) Battery Leakage Detector, Meggar 1 1713800.00 No. 1713800
ii) Insulation Tester-Self Dioagnostic 5 kV Megger 1 671000.00 No. 671000
iii) 3-Phase Transformer Turns Ratio Tester, Megger 1 1630200.00 No. 1630200
iv) Digital Multimeter (AC/DC), 2mA-20A, Megger 1 26400.00 No. 26400
v) Digital Clamp Meter, Megger 1 30800.00 No. 30800
vi) Digital Earth Tester, Megger 1 309100.00 No. 309100
vii) All relay Universal Testing Kit 1 309100.00 No. 309100
viii) Motorised cum Manual Oil Testing Set (1KVA capacity) 1 257400.00 No. 257400
Disturbance Recorder 1 4560000.00 No. 4560000
Providing GPS device for time synchronisation of Protection relays
1785000.00
No.785000
Relay Testing Kit 1 5275000.00 No. 5275000
Tan Delta Testing Kit 1 5341000.00 No. 5341000
Circuit breaker Analyzer 1 7782000.00 No. 7782000
Battery Leakage Detector 1846000.00 0
Part D 1) CAPACITOR BANK WITH APFC SYSTEM-38 kV(66 kV), 7.2 (3x2.4+1.8) MVAR Capactor Bank with APFC Panel 1 9583000.00 set 9583000
RESIDUAL VOLTAGE TRANSFORMER
66kV/3/110-570 1 80000.00 No 80000
66 KV capacitor voltage transformer 1 110000.00 No 110000
1100 V Grade, HR-FRLS Copper Control Cables/LT Cables
1.1KV PVC, HR FRLS, Copper Control Cable (Un-screened)
2Cx2.5mm2 0.2 50000.00 Km 10000
4Cx2.5mm2 0.2 87000.00 Km 17400
7Cx2.5mm2 0.2 154000.00 Km 30800
10Cx2.5mm2 0.2 229000.00 Km 45800
12Cx2.5mm2 0.2 240000.00 Km 48000
19Cx2.5mm2 0.2 393000.00 Km 78600
2Cx4mm2 0.2 79000.00 Km 15800
4Cx4mm2 0.2 133000.00 Km 26600
1.1KV PVC, HR FRLS, Copper Control Cable (Screened)
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 155
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-L
Sr. No. Description Qty Rate (Rs.) Unit Amount (Rs.)
4Cx6mm2 0.2 220000.00 Km 44000
7Cx4mm2 0.2 358000.00 Km 71600
LT Cable, Copper Conductor (Armoured)
4Cx10mm2 0.05 264000.00 Km 13200
33kV&11kV HT XLPE Cables and Termination kits
33kV,1Cx630 mm2,XLPE,Al Conductor With armoured 0.05 942000.00 47100
Termination Kits for 33kV,1Cx630 mm2,XLPE,Al Conductor with
armoured
Indoor Type 0.6 11000.00 No 6600
Outdoor type 0.6 13000.00 No 7800
CURRENT TRANSFORMER
66 kV, TRANSFORMER
200-100/1-1-1-1A 12 53000.00 No. 636000
ISOLATOR]
ISOLATOR WITH EARTH SWITCH (Motorized) with Structure
72.5 kV,1250 A 2 215000.00 set 430000
i) 36 kV, 2000 A 2 192000.00 set 384000
ISOLATOR WITH EARTH SWITCH (Motorized) without Structure
72.5 kV,1250 A 2 179000.00 set 358000
i) 36 kV, 2000 A 2 167000.00 set 334000
ISOLATOR W/O EARTH SWITCH (Motorized) with structure
i) 36 kV,1250 A 2 147000.00 set 294000
ISOLATOR W/O EARTH SWITCH (Motorized) without structure
i) 36 kV,1250 A 2 123000.00 set 246000
SURGE ARRESTOR (with surge counter)
PORCELAIN TYPE
60 kV 2 35000.00 No. 70000
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 156
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-L
Sr. No. Description Qty Rate (Rs.) Unit Amount (Rs.)
POLYMER TYPE
60 kV 2 24000.00 No. 48000
Control and Relay Panel
66 kV, Transformer Panel (LV side) without diffrential Relay with
BCU 4 779000.00No.
3116000
Bus Coupler 4 769000.00 No. 3076000
Feeder panal without BCU 4 1604000.00 No. 6416000
Part E Item No.6A- Fencing
Supplying and erecting fencing sections having size 2.45m
height from ground level and 1.2m width by using angle iron size
50x50x6 mm erected in C.C.foundation 0.30x0.45x0.45 cm deep.The
section of the frame shall be fitted with flat iron support of size
25x6mm on top bottom and mid way and chain link jail of 3.26 mm
dia/10 SWG G.I. hard wire mesh of 50x50mm to the angle iron at
every distance of 30 cms,by angle studs complete duly painted with
one coats or red oxide and two coats of aluminium paint Size of
Fencing 30 x 45 Mtr
PWD DSR I.No. 10.2.18 / 146 for 2018-19 120 5603.85 No 672462
Item No.6B- Fencing gate
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 157
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-L
Sr. No. Description Qty Rate (Rs.) Unit Amount (Rs.)
Supplying and erecting double leaf hinged door each 150 cm in width
and 185 cm in height using 40 mm dia"B"grade ISI mark G.I.pipe
from all four sides with necessary bends,and cross supports of angle
iron 45x45x5mm with the door leaf covered with chain link jali 50x50
mm made from3.26 mm dia/10 SWG G.I wire with necessary flat iron
covering all around with necesary number of spikes of sie 10mm dia
at top and bottom at 150mm apart to match the height of fencing.The
door shall have latches and side channel of 100x50x5 mm regidly
welded for providing locking arrangement.Godraj/Navtal make
medium size lock with duplicate keys.The fencing complete erected
and pinted with anticorrosive red oxide paint and two coats of
prescribed enamel paint/silver paint.The channel iron of size 150 x75
mm by 2.5 m long shall be provided and erected at both sides of
gate. Size of Fencing 1500 mm x 3 Nos x 1 No = 2 Gates. Total 6
Nos required.
PWD DSR I.No. 10.2.20 / 147 for 2018-19 4 16158 No 64632
Total 135507921.58
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 158
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-M
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
3 PHASE, POWER TRANSFORMERS
Part A 315 KVA-66000 / 433Volt(for lighting &other purpose) 2 874798 No. 1749596
i) 10 MVA (66KVA) 2 13172911.00 No. 26345822
Providing of 33 kV EQUIPMENTS
1 i) Circuit Breaker- 72.5 kV SF - 6 CB 1 442000.00 No. 442000
2 ii) Control and Relay Panel 0
3 Transformer Panel (HV)side with differential Relay 1 527000.00 No. 527000
4 Bus Coupler Panel 1 721212.00 No. 721212
5 Feeder Panel 1 491541.00 No. 491541
6 iii) Isolator with out Earth blade- 72.5 kV,1250 A 2 151000.00 No. 302000
7
iv) Multi Core Multi ratio Current Transformers -66 kV, CURRENT
TRANSFORMER
3 58000.00 No.174000
8
v) Lightening Arrester-60 kV(SURGE ARRESTOR with surge counter) 3 35400.00 No.106200
9 vi) PTs -33kV Potential Transformer 3 58869.00 No. 176607
10
Indoor Switchgear and allied Equipments comprising of Panel Board,
CTs, PTs etc.
36 kV, 2000 A, 25 kA I/C 2 2426000.00 No. 4852000
12KV, 1250 A , 12.5 KA I/C 2 543000.00 No. 1086000
11 SUBSTATION STRUCTURE
PER MT FOR C GRADE (For Snow Zone) 12 92000.00 MT 1104000
Total 38077978
Equipment Structures including Bus Bar, Earthing, Hardware Fitting,
disc insulator, pin insulator, AB switch etc. @ 10% ( on Sub Total 1
above )
10 %
3807797.80
(a) Power and Control Cables, Earthmat , E. I. etc. @ 13% (on Sub
Total 1 above)
13 %4950137.14
(b) Cable trays @ .75 % & Air-Conditioning @ .25 % i.e. on Sub-Total-
1
25 %380779.78
Spares @ 3%, (on item 1 to 6 above) 3 % 1142339.34
Estimate for 66 KV HT Substation for Pumping station at Devidhar site
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 159
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-M
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
Transportation @ 5 % & Insurance @ 1 % ( Total 06 % on Sub Total
1 above)
5 %2284678.68
Sub Total- II (Item 1 to 10) 50643710.74
(a) Erection & Commissioning Charges @ 10 % 10 %3807797.80
(b) Sub-station T & P* LS 500000.00
Civil Works ( as per Annexure H1 ) 3782000.00
Sub Total (Item 14+15+16) 58733508.54
Part B General Equipments
i) 200 V, Battery a/w Battery Charger & Distribution Board
a) D. C. Battery
i) 220 V, 400AH 1 902000.00 No. 902000
ii) 220 V,300AH 1 752000.00 No. 752000
iii) 220 V, 200AH 1 475000.00 No. 475000
iv) 48 V, 400AH 1 210000.00 No. 210000
v) 48 V, 200AH 1 129000.00 No. 129000
vi) 30 V, 100 AH 1 38000.00 No. 38000
b) Battery Charger
i) 200 V, 400AH 2 274000.00 No. 548000
ii) 200 V, 200AH 2 260000.00 No. 520000
iii) 48 V, 200 AH 2 212000.00 No. 424000
iv) 30 V, 100 AH 2 93000.00 No. 186000
v) 200 V, 300AH 2 260000.00 No. 520000
c) 220 V, D. C. Distribution Board 1 114000.00 No. 114000
d) 48 V D.C. Distribution Board 1 117000.00 No. 117000
e) 30 V D.C. Distribution Board 1 103000.00 No. 103000
f) 220V-30V- DC-DC Converter 1 152000.00 No. 152000
ii) Station Transformer
a) 250 kVA, 33 / 0.4 kV 1 428000.00 No. 428000
b) 250 kVA, 11 / 0.4 kV 1 371000.00 No. 371000
iii) 415 V, A.C. Distribution Board 1 1087000.00 No. 1087000
Part C d) Testing & Measuring Instruments
i) Battery Leakage Detector, Meggar 1 1713800.00 No. 1713800
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 160
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-M
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
ii) Insulation Tester-Self Dioagnostic 5 kV Megger 1 671000.00 No. 671000
iii) 3-Phase Transformer Turns Ratio Tester, Megger 1 1630200.00 No. 1630200
iv) Digital Multimeter (AC/DC), 2mA-20A, Megger 1 26400.00 No. 26400
v) Digital Clamp Meter, Megger 1 30800.00 No. 30800
vi) Digital Earth Tester, Megger 1 309100.00 No. 309100
vii) All relay Universal Testing Kit 1 309100.00 No. 309100
viii) Motorised cum Manual Oil Testing Set (1KVA capacity) 1 257400.00 No. 257400
Disturbance Recorder 1 4560000.00 No. 4560000
Providing GPS device for time synchronisation of Protection relays
1785000.00
No.785000
Relay Testing Kit 1 5275000.00 No. 5275000
Tan Delta Testing Kit 1 5341000.00 No. 5341000
Circuit breaker Analyzer 1 7782000.00 No. 7782000
Battery Leakage Detector 1846000.00 0
Part D 1) CAPACITOR BANK WITH APFC SYSTEM-38 kV(66 kV), 7.2 (3x2.4+1.8) MVAR Capactor Bank with APFC Panel 1 9583000.00 set 9583000
RESIDUAL VOLTAGE TRANSFORMER
33kV/3/110-570 1 80000.00 No 80000
66 KV capacitor voltage transformer 1 110000.00 No 110000
1100 V Grade, HR-FRLS Copper Control Cables/LT Cables
1.1KV PVC, HR FRLS, Copper Control Cable (Un-screened)
2Cx2.5mm2 0.2 50000.00 Km 10000
4Cx2.5mm2 0.2 87000.00 Km 17400
7Cx2.5mm2 0.2 154000.00 Km 30800
10Cx2.5mm2 0.2 229000.00 Km 45800
12Cx2.5mm2 0.2 240000.00 Km 48000
19Cx2.5mm2 0.2 393000.00 Km 78600
2Cx4mm2 0.2 79000.00 Km 15800
4Cx4mm2 0.2 133000.00 Km 26600
1.1KV PVC, HR FRLS, Copper Control Cable (Screened)
4Cx6mm2 0.2 220000.00 Km 44000
7Cx4mm2 0.2 358000.00 Km 71600
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 161
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-M
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
LT Cable, Copper Conductor (Armoured)
4Cx10mm2 0.05 264000.00 Km 13200
33kV&11kV HT XLPE Cables and Termination kits
33kV,1Cx630 mm2,XLPE,Al Conductor With armoured 0.05 942000.00 47100
Termination Kits for 33kV,1Cx630 mm2,XLPE,Al Conductor with
armoured
Indoor Type 0.6 11000.00 No 6600
Outdoor type 0.6 13000.00 No 7800
CURRENT TRANSFORMER
66 kV, TRANSFORMER
200-100/1-1-1-1A 1 53000.00 No. 53000
ISOLATOR]
ISOLATOR WITH EARTH SWITCH (Motorized) with Structure
72.5 kV,1250 A 1 215000.00 set 215000
i) 36 kV, 2000 A 1 192000.00 set 192000
ISOLATOR WITH EARTH SWITCH (Motorized) without Structure
72.5 kV,1250 A 1 179000.00 set 179000
i) 36 kV, 2000 A 1 167000.00 set 167000
ISOLATOR W/O EARTH SWITCH (Motorized) with structure
i) 36 kV,1250 A 1 147000.00 set 147000
ISOLATOR W/O EARTH SWITCH (Motorized) without structure
i) 36 kV,1250 A 1 123000.00 set 123000
SURGE ARRESTOR (with surge counter)
PORCELAIN TYPE
60 kV 1 35000.00 No. 35000
POLYMER TYPE
60 kV 1 24000.00 No. 24000
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 162
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-M
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
Control and Relay Panel
66 kV, Transformer Panel (LV side) without diffrential Relay with BCU1 779000.00
No.779000
Bus Coupler 1 769000.00 No. 769000
Feeder panal without BCU 1 1604000.00 No. 1604000
Part E Item No.6A- Fencing
Supplying and erecting fencing sections having size 2.45m
height from ground level and 1.2m width by using angle iron size
50x50x6 mm erected in C.C.foundation 0.30x0.45x0.45 cm deep.The
section of the frame shall be fitted with flat iron support of size
25x6mm on top bottom and mid way and chain link jail of 3.26 mm
dia/10 SWG G.I. hard wire mesh of 50x50mm to the angle iron at
every distance of 30 cms,by angle studs complete duly painted with
one coats or red oxide and two coats of aluminium paint Size of
Fencing 30 x 45 Mtr
PWD DSR I.No. 10.2.18 / 146 for 2018-19 95 5603.85 No 532365.75
Item No.6B- Fencing gate
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 163
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-M
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
Supplying and erecting double leaf hinged door each 150 cm in width
and 185 cm in height using 40 mm dia"B"grade ISI mark G.I.pipe from
all four sides with necessary bends,and cross supports of angle iron
45x45x5mm with the door leaf covered with chain link jali 50x50 mm
made from3.26 mm dia/10 SWG G.I wire with necessary flat iron
covering all around with necesary number of spikes of sie 10mm dia
at top and bottom at 150mm apart to match the height of fencing.The
door shall have latches and side channel of 100x50x5 mm regidly
welded for providing locking arrangement.Godraj/Navtal make
medium size lock with duplicate keys.The fencing complete erected
and pinted with anticorrosive red oxide paint and two coats of
prescribed enamel paint/silver paint.The channel iron of size 150 x75
mm by 2.5 m long shall be provided and erected at both sides of gate.
Size of Fencing 1500 mm x 3 Nos x 1 No = 2 Gates. Total 6 Nos
required.
PWD DSR I.No. 10.2.20 / 147 for 2018-19 4 16158 No 64632
Total 109620606.29
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 164
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-N
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
3 PHASE, POWER TRANSFORMERS
Part A 10 MVA.(33KV*3.3KV) 2 13172911 No. 26345822
315 KVA-33000 / 433Volt(for lighting &other purpose) 2 874798 No. 1749596
Providing of 33 kV EQUIPMENTS
1 i) Circuit Breaker- 72.5 kV SF - 6 CB 1 246000.00 No. 246000
2 ii) Control and Relay Panel
3 Transformer Panel (HV)side with differential Relay 1 353000.00 No. 353000
4 Bus Coupler Panel 1 290000.00 No. 290000
5 Feeder Panel 1 333000.00 No. 333000
6 iii) Isolator with out Earth blade- 72.5 kV,1250 A 2 141000.00 No. 282000
7
iv) Multi Core Multi ratio Current Transformers -66 kV, CURRENT
TRANSFORMER
3 45000.00 No.135000
8
v) Lightening Arrester-60 kV(SURGE ARRESTOR with surge
counter)
3 9000.00 No.27000
9 vi) PTs -33kV Potential Transformer 3 27000.00 No. 81000
10
Indoor Switchgear and allied Equipments comprising of Panel
Board, CTs, PTs etc.
36 kV, 2000 A, 25 kA I/C 1 2426000.00 No. 2426000
12KV, 1250 A , 12.5 KA I/C 1 543000.00 No. 543000
11 SUBSTATION STRUCTURE
PER MT FOR C GRADE (For Snow Zone) 15 92000.00 MT 1380000
Total 34191418
Equipment Structures including Bus Bar, Earthing, Hardware Fitting,
disc insulator, pin insulator etc. @ 10% ( on Sub Total 1 above )
10 %
3419141.8
(a) Power and Control Cables, Earthmat , E. I. etc. @ 13% (on Sub
Total 1 above)
13 %4444884.34
(b) Cable trays @ .75 % & Air-Conditioning @ .25 % i.e. on Sub-
Total-1
25 %341914.18
ABSTRACT OF COST
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Estimate for 33 KV HT Substation for Pumping station at Dummi site
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 165
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-N
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
Spares @ 3%, (on item 1 to 6 above) 3 % 1025742.54
Transportation @ 5 % & Insurance @ 1 % ( Total 06 % on Sub
Total 1 above)
5 %2051485.08
Sub Total- II (Item 1 to 10) 45474585.94
(a) Erection & Commissioning Charges @ 10 % 10 % 3419141.8
(b) Sub-station T & P* LS 500000
Civil Works ( as per Annexure H1 ) 2696000
Sub Total (Item 14+15+16) 52089727.74
Part B General Equipments
a) D. C. Battery
i) 220 V, 400AH 1 902000.00 No. 902000
ii) 220 V,300AH 1 752000.00 No. 752000
iii) 220 V, 200AH 1 475000.00 No. 475000
iv) 48 V, 400AH 1 210000.00 No. 210000
v) 48 V, 200AH 1 129000.00 No. 129000
vi) 30 V, 100 AH 1 38000.00 No. 38000
b) Battery Charger
i) 200 V, 400AH 2 274000.00 No. 548000
ii) 200 V, 200AH 2 260000.00 No. 520000
iii) 48 V, 200 AH 2 212000.00 No. 424000
iv) 30 V, 100 AH 2 93000.00 No. 186000
v) 200 V, 300AH 2 260000.00 No. 520000
c) 220 V, D. C. Distribution Board 1 114000.00 No. 114000
d) 48 V D.C. Distribution Board 1 117000.00 No. 117000
e) 30 V D.C. Distribution Board 1 103000.00 No. 103000
f) 220V-30V- DC-DC Converter 1 152000.00 No. 152000
ii) Station Transformer
a) 250 kVA, 33 / 0.4 kV 1 428000.00 No. 428000
b) 250 kVA, 11 / 0.4 kV 1 371000.00 No. 371000
iii) 415 V, A.C. Distribution Board 1 1087000.00 No. 1087000
Part C d) Testing & Measuring Instruments
i) 200 V, Battery a/w Battery Charger & Distribution Board
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 166
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-N
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
i) Battery Leakage Detector, Meggar 1 1713800.00 No. 1713800
ii) Insulation Tester-Self Dioagnostic 5 kV Megger 1 671000.00 No. 671000
iii) 3-Phase Transformer Turns Ratio Tester, Megger 1 1630200.00 No. 1630200
iv) Digital Multimeter (AC/DC), 2mA-20A, Megger 1 26400.00 No. 26400
v) Digital Clamp Meter, Megger 1 30800.00 No. 30800
vi) Digital Earth Tester, Megger 1 309100.00 No. 309100
vii) All relay Universal Testing Kit 1 309100.00 No. 309100
viii) Motorised cum Manual Oil Testing Set (1KVA capacity) 1 257400.00 No. 257400
Disturbance Recorder 1 4560000.00 No. 4560000
Providing GPS device for time synchronisation of Protection relays
1785000.00
No.785000
Relay Testing Kit 1 5275000.00 No. 5275000
Tan Delta Testing Kit 1 5341000.00 No. 5341000
Circuit breaker Analyzer 1 7782000.00 No. 7782000
Battery Leakage Detector 1846000.00 0
Part D
1) CAPACITOR BANK WITH APFC SYSTEM-38 kV(33 kV), 7.2
(3x2.4+1.8) MVAR Capactor Bank with APFC Panel 1 9583000.00 set 9583000
2) RESIDUAL VOLTAGE TRANSFORMER
33kV/3/110-570 1 80000.00 No 80000
3) 1100 V Grade, HR-FRLS Copper Control Cables/LT Cables
1.1KV PVC, HR FRLS, Copper Control Cable (Un-screened)
2Cx2.5mm2 0.2 50000.00 Km 10000
4Cx2.5mm2 0.2 87000.00 Km 17400
7Cx2.5mm2 0.2 154000.00 Km 30800
10Cx2.5mm2 0.2 229000.00 Km 45800
12Cx2.5mm2 0.2 240000.00 Km 48000
19Cx2.5mm2 0.2 393000.00 Km 78600
2Cx4mm2 0.2 79000.00 Km 15800
4Cx4mm2 0.2 133000.00 Km 26600
1.1KV PVC, HR FRLS, Copper Control Cable (Screened)
4Cx6mm2 0.2 220000.00 Km 44000
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 167
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-N
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
7Cx4mm2 0.2 358000.00 Km 71600
LT Cable, Copper Conductor (Armoured)
4Cx10mm2 0.05 264000.00 Km 13200
33kV&11kV HT XLPE Cables and Termination kits
33kV,1Cx630 mm2,XLPE,Al Conductor With armoured 0.15 942000.00 Km 141300
4) Termination Kits for 33kV,1Cx630 mm2,XLPE,Al Conductor with
armoured
Indoor Type 0.6 11000.00 No 6600
Outdoor type 0.6 13000.00 No 7800
5) CURRENT TRANSFORMER
33 kV, TRANSFORMER
10-5/1-1-1A 12 46000.00 No. 552000
6) ISOLATOR
ISOLATOR WITH EARTH SWITCH (Motorized) with Structure
72.5 kV,1250 A 1 215000.00 set 215000
i) 36 kV, 2000 A 1 192000.00 set 192000
ISOLATOR WITH EARTH SWITCH (Motorized) without Structure
72.5 kV,1250 A 1 179000.00 set 179000
i) 36 kV, 2000 A 1 167000.00 set 167000
ISOLATOR W/O EARTH SWITCH (Motorized) with structure
i) 36 kV,1250 A 1 147000.00 set 147000
ISOLATOR W/O EARTH SWITCH (Motorized) without structure
i) 36 kV,1250 A 1 123000.00 set 123000
7) SURGE ARRESTOR (with surge counter)
PORCELAIN TYPE
60 kV 3 35000.00 No. 105000
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 168
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-N
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
POLYMER TYPE
60 kV 3 24000.00 No. 72000
8) Control and Relay Panel
Bus Coupler 1 950000.00 No. 950000
Feeder panal without BCU 1 746000.00 No. 746000
33 kV, Transformer Panel (LV side) without diffrential Relay with
BCU1
578000.00 No.578000
Part E Item No.1- Fencing
Supplying and erecting fencing sections having size 2.45m
height from ground level and 1.2m width by using angle iron size
50x50x6 mm erected in C.C.foundation 0.30x0.45x0.45 cm
deep.The section of the frame shall be fitted with flat iron support of
size 25x6mm on top bottom and mid way and chain link jail of 3.26
mm dia/10 SWG G.I. hard wire mesh of 50x50mm to the angle iron
at every distance of 30 cms,by angle studs complete duly painted
with one coats or red oxide and two coats of aluminium paint Size
of Fencing 30 x 45 Mtr
PWD DSR I.No. 10.2.18 / 146 for 2018-19 95 5603.85 No 532365.75
Item No.2- Fencing gate
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 169
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-N
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
Supplying and erecting double leaf hinged door each 150 cm in
width and 185 cm in height using 40 mm dia"B"grade ISI mark
G.I.pipe from all four sides with necessary bends,and cross supports
of angle iron 45x45x5mm with the door leaf covered with chain link
jali 50x50 mm made from3.26 mm dia/10 SWG G.I wire with
necessary flat iron covering all around with necesary number of
spikes of sie 10mm dia at top and bottom at 150mm apart to match
the height of fencing.The door shall have latches and side channel
of 100x50x5 mm regidly welded for providing locking
arrangement.Godraj/Navtal make medium size lock with duplicate
keys.The fencing complete erected and pinted with anticorrosive
red oxide paint and two coats of prescribed enamel paint/silver
paint.The channel iron of size 150 x75 mm by 2.5 m long shall be
provided and erected at both sides of gate. Size of Fencing 1500
mm x 3 Nos x 1 No = 2 Gates. Total 6 Nos required.
PWD DSR I.No. 10.2.20 / 147 for 2018-19 4 16158 No 64632
Total 102700025.49
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 170
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-O
Sr. No. Description Qty Rate Unit Amount
1 Supply & errection of pump[ing machinery alongwith its allied
accessories. complete with a provision of 100% stand by at raw
water stage and 50 % stand bye at each pure water stage
including surge control devices.
27875 18000 Per BHP 5017.50
i). Raw water stage. 365 X 2 X 2 1460 BHP
ii). WTP to Devidhar. 1175 X 6 X 1.5 10575 BHP
iii) Devidhar to Dummi 935 X 6 X 1.5 8415 BHP
vi).Dummi to Sanjauli 825 X 6 X 1.5 7425 BHP
Total 27875 BHP
5017.50Total Rs. In Lac.
Pumping Machinery for Raw water and Pure Water Stages
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 171
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
Raw Water Pumping Machinery
1
Ultrasonic level transmitter - Designing, Supplying, Installing, commissioning &
testing of
Ultrasonic Raddar type level transmitter CE marked with
following technical parameters at Raw Water Pump House
and Interfacing with PLC panel including mounting
arrangement.
Output-4-20 mA
Power supply - 24V DC ext.
Display - 4" LED
Range- 0 to …………... mtrs
Accuracy - +/- 0.25% of Full Scale or betterEnclosure- IP 67
Mounting - On PLC panel 1.00 75000 Each 75000
2
Pressure Transmitter - Designing, Supplying, Installing, commissioning & testing of
pressure transmitter CE markd with following technical parameters at Raw Water
Pump House and Interfacing with PLC panel including mounting arrangement.Output
4-20 mA Power supply - 24V DC ext. Display - 4" LED Accuracy - +/- 0.1 % of full
scale or better Enclosure- IP 67 4.00 35000 Each 140000
3
Power Analyser - Designing, Supplying, Installing, commissioning & testing of Power
Analyser interfacing to PLC Panel with modbus
communicatuion port , as per IEC 62053 and in the
prescribed format including mounting arrangement. 4.00 35000 Each 140000
4 PLC panel suitable for wireless communication 4.00 200000 Each 800000
5
PLC based control monitoring and communication software - Designing, Supplying,
Installing, commissioning & testing of PLC based control monitoring and
communication software as per IEC 61131 at Raw water Jackwell / Sump suitable for
monitoring and control of Raw water Pumps, Pressure Transmitters, Level
Transmitter, Flow Transmitter
complete. 4.00 50000 Each 200000
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Automation to WTP, Raw Water and Pure Water Pumping Machinery
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 172
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
6
Supplying, erecting & terminating PVC armouredcable 2
core 2.5 sq mm copper conductor continuous 5.48 sq mm
(12 SWG) G.I. earth wire complete erected with glands &
lugs, on wall/ trusses/pole or laid in provided trench/ pipe as
per specification no. CB-LT/CU 200.00 145.6 Mtr 29120
7Supplying and fixing Cat-6 STP cable suitable for LAN /
WAN as per specification in approved manner 200.00 92.96 Mtr 18592
8
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 2 Pair x 1 sq.mm as per
IS 694 copper Shielded twisted, multistranded armoured
cablew on wall in GI tray or on ground. 200.00 162.4 Mtr 32480
9
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 3 Pairs x1 sq.mm. as per
IS 694 copper Shielded, twisted, multi stranded armoured
cable on wall in GI tray or on ground.200.00 206.08 Mtr 41216
10
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 4.5 Pairs x 1.0 sq.mm as
per IS 694 copper shielded, twisted, multi stranded
armoured cable on wall in GI tray or on ground.200.00 303.52 Mtr 60704
11
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 8 Pairs x 1.0 sq.mm as
per IS 694 copper shielded, twisted, multi stranded
armoured cable on wall in GI tray or on ground.200.00 546.56 Mtr 109312
12
Providing & erecting Hot dipped Galvanised Ladder type
Cable tray manufactured from 16 swg (1.6 mm thick) GI
sheet of 150 mm width & 100 mm heightcomprising all
required standard accessories.200.00 716.8 Mtr 143360
13 Earthing 0 0
A
Providing pipe type earthing with 40mm. dia. G.l. pipe or 20 mm dia. G.l. Rod
complete with all materials as per specification No. EA-EP (10 for pumps + 2 for main
panel + 2 for APFC panel + 2 for Raw water pump panel) 5.00 1364.16 Each 6821
B GI earthing strip 150.00 199.36 Kg 29904
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 173
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
14
Surveillance system - Desiging,supplying,installing,commissioning & testing of CCTV
IR water proof camera suitable for upto 100ft.with IR
Dome camera,control key board,DVR,Hard Disk,cables,UPT transreceivers
etc.complete.1.00 25878 Nos 25878
15
Providing, erecting electric Valve actuators totally enclosed,
weather-proof and dust proof construction with IP-67,
protection class suitable for installation in any position
without lubrication, leakage or other operational difficulty
with special grease filled gear box and hand wheel for
emergency manual operation which will automatically disengage
on restoration of power to motor and with 10 watt
single phase space heater and continuous local mechanical
position indicator and individually replaceable counter gear
assembly and with two torque and four limit switches with
S.S. flap and operated with gear driven cams and of rating
250 Volt, 5 Amp, AC/DC, torque switch dial and with TEFC
squirrel cage induction motor working on 440 Volts +/- 10%,
3 phase, 50 Hz AC of intermittent duty rating S-2, insulation
class "F" and temp rise restricted to class "B" with IP - 67
protection class suitable for DOL starting and with three
thermostat and 30% over load margin. The torque rating of
reduction gear box shall be atleast 1.5 times max. torque
required for opening and closing of valve with integral
starter controls having four limit switches 1 for OPEN, 1 for
CLOSE & 2 Nos for intermidiate positions for interlocking
etc complete. with Third Party inspection 0 0
600 mm 4.00 118883.52 No 475535
0 0
16
Supplying and erecting armoured control cable with ISI
mark stranded / solid copper conductor 1.1 kV grade
complete erected on wall / panel or in provided trench in an
approved manner. 2.5 sq mm Copper conductor PVC insulated, armoured control
cable for Actuators 100.00 144.48 Mtr 14448
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 174
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
17
Assembled D.O.L. Starter
Supplying and erecting assembled DOL starter in provided
cubical panel, with ON-OFF push buttons, no volt coil, over
load element and required power and control wiring
complete for Actuators Up to 7.5 HP 4.00 1583.68 No 6335
Pure Water Pumping Machinery
18
Ultrasonic level transmitter - Designing, Supplying, Installing, commissioning &
testing of
Ultrasonic Raddar type level transmitter CE marked with
following technical parameters at Raw Water Pump House
and Interfacing with PLC panel including mounting
arrangement.
Output-4-20 mA
Power supply - 24V DC ext.
Display - 4" LED
Range- 0 to …………... mtrs
Accuracy - +/- 0.25% of Full Scale or betterEnclosure- IP 67
Mounting - On PLC panel 6.00 50000 Each 300000
19
Pressure Transmitter - Designing, Supplying, Installing, commissioning & testing of
pressure transmitter CE markd with following technical parameters at Raw Water
Pump House and Interfacing with PLC panel including mounting arrangement.Output
4-20 mA Power supply - 24V DC ext. Display - 4" LED Accuracy - +/- 0.1 % of full
scale or better Enclosure- IP 67 33.00 35000 Each 1155000
20
Power Analyser - Designing, Supplying, Installing, commissioning & testing of Power
Analyser interfacing to PLC Panel with modbus
communicatuion port , as per IEC 62053 and in the
prescribed format including mounting arrangement. 27.00 35000 Each 945000
21
PLC Panel - Designing, Supplying, Installing, commissioning & testing of PLC Panel.
Including PLC with CPU & Power supply unit, power supplyb cables interfacing cards,
interfacing cables, wireless modules with 25% extra quantity of all accessories.
27.00 50000 Each 1350000
22
PLC based control monitoring and communication software - Designing, Supplying,
Installing, commissioning & testing of PLC based control monitoring and
communication software as per IEC 61131 at Raw water Jackwell / Sump suitable for
monitoring and control of Raw water Pumps, Pressure Transmitters, Level
Transmitter, Flow Transmitter
complete. 3.00 45383.52 Each 136151
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 175
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
24
Supplying, erecting & terminating PVC armouredcable 2
core 2.5 sq mm copper conductor continuous 5.48 sq mm
(12 SWG) G.I. earth wire complete erected with glands &
lugs, on wall/ trusses/pole or laid in provided trench/ pipe as
per specification no. CB-LT/CU 600.00 145.6 Mtr 87360
25Supplying and fixing Cat-6 STP cable suitable for LAN /
WAN as per specification in approved manner 600.00 92.96 Mtr 55776
26
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 2 Pair x 1 sq.mm as per
IS 694 copper Shielded twisted, multistranded armoured
cablew on wall in GI tray or on ground. 600.00 162.4 Mtr 97440
27
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 3 Pairs x1 sq.mm. as per
IS 694 copper Shielded, twisted, multi stranded armoured
cable on wall in GI tray or on ground.600.00 206.08 Mtr 123648
28
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 4.5 Pairs x 1.0 sq.mm as
per IS 694 copper shielded, twisted, multi stranded
armoured cable on wall in GI tray or on ground.600.00 303.52 Mtr 182112
29
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 8 Pairs x 1.0 sq.mm as
per IS 694 copper shielded, twisted, multi stranded
armoured cable on wall in GI tray or on ground.600.00 546.56 Mtr 327936
30
Providing & erecting Hot dipped Galvanised Ladder type
Cable tray manufactured from 16 swg (1.6 mm thick) GI
sheet of 150 mm width & 100 mm heightcomprising all
required standard accessories.600.00 716.8 Mtr 430080
31 Earthing 0 0
A
Providing pipe type earthing with 40mm. dia. G.l. pipe or 20 mm dia. G.l. Rod
complete with all materials as per specification No. EA-EP (10 for pumps + 2 for main
panel + 2 for APFC panel + 2 for Raw water pump panel) 10.00 1364.16 Each 13642
B GI earthing strip 2500.00 199.36 Kg 498400
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 176
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
Providing, erecting electric Valve actuators totally enclosed,
weather-proof and dust proof construction with IP-67,
protection class suitable for installation in any position
without lubrication, leakage or other operational difficulty
with special grease filled gear box and hand wheel for
emergency manual operation which will automatically disengage
on restoration of power to motor and with 10 watt
single phase space heater and continuous local mechanical
position indicator and individually replaceable counter gear
assembly and with two torque and four limit switches with
S.S. flap and operated with gear driven cams and of rating
250 Volt, 5 Amp, AC/DC, torque switch dial and with TEFC
squirrel cage induction motor working on 440 Volts +/- 10%,
3 phase, 50 Hz AC of intermittent duty rating S-2, insulation
class "F" and temp rise restricted to class "B" with IP - 67
protection class suitable for DOL starting and with three
thermostat and 30% over load margin. The torque rating of
reduction gear box shall be atleast 1.5 times max. torque
required for opening and closing of valve with integral
starter controls having four limit switches 1 for OPEN, 1 for
CLOSE & 2 Nos for intermidiate positions for interlocking
etc complete. with Third Party inspection 0 0
600 mm 27.00 125000 No 3375000
0 0
32
Supplying and erecting armoured control cable with ISI
mark stranded / solid copper conductor 1.1 kV grade
complete erected on wall / panel or in provided trench in an
approved manner. 2.5 sq mm Copper conductor PVC insulated, armoured control
cable for Actuators 540.00 144.48 Mtr 78020
33
Assembled D.O.L. Starter
Supplying and erecting assembled DOL starter in provided
cubical panel, with ON-OFF push buttons, no volt coil, over
load element and required power and control wiring
complete for Actuators Up to 7.5 HP 27.00 1583.68 No 42760
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 177
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
34
Surveillance system - Desiging,supplying,installing,commissioning & testing of CCTV
IR water proof camera suitable for upto 100ft.with IR
Dome camera,control key board,DVR,Hard Disk,cables,UPT transreceivers
etc.complete.3.00 26772.48 Nos 80318
Water Treatment Plant 0 0
35
Open channel type ultrasonic flowmeter with FIT - Design, Supply, Installation,
Testing & calibration of open
chanel type ultrasonic flow Transmitter CE marked with
following technical parameters at Raw Water channel and
Interfacing with PLC panel including mounting arrangement.
Range- 0 - 5 mtrs
Output-4-20 mA
Power supply - 24V DC ext.
Display - 4" LED
Accuracy - +/- 0.25% of Full Scale or better
Enclosure- IP 68 2.00 45840.48 Nos 91681
36
PH analyser - Design, Supply, Installation, Testing of pH analyser as per
IUPAC( International Union for Pure & Applied Chemistry)at
A.F. and Interfacing with PLC panel including mounting
arrangement.
Range : 0-14 ,
pH Accuracy : Better than 0.1% of full scale ,
Supply Voltage : 24V dc,
Output : 4‐20 mA
As per IEC 61000-6-2 & IEC 61000-6-3 3.00 100000 Nos 300000
37
Turbidity Analyser - Design, Supply, Installation, commissioning, testing of Turbidity
Anayser as per ISO 7027 scattering light method at A.F. and Interfacing with PLC
panel. Turbidity analyser shall comprises of 3 components i.e. sensors,signal
distributor and transmitter with indicator. with 2 Outputs, 1 to PLC & anather to Local
Display with mounting arrangement.
Overall Range : 0‐2000 NTU
Accuracy : +/‐0.02 NTU
Supply Voltage : 230 V ac
Output : 4‐20 mA 3.00 275890.72 Nos 827673
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 178
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
38
Alum / PAC Dosing - Design, Supply, Installing commissioning and testing PLC
compatible Alum/PAC Mixing, Dosing and monitoring
system for Dosing at raw water channel by applying
suitable mechanism to control the available turbidity in
desired limit. This system includes level switches for tank. 1.00 325000 Nos 325000
39
Designing,Supplying, installing, commissioning & testing of Ultrasonic level
transmitter CE marked at each filter bed with following technical parameters
Interfacing with PLC panel including mounting arrangement.
Range- 0 - 5 mtrs
Output-4-20 mA
Power supply - 24V DC ext.
Display - 4" LED
Accuracy - +/- 0.25% of Full Scale or better
Enclosure- IP 65 16.00 50000 Nos 800000
40
Power Analyser - Designing, Supplying, Installing, commissioning & testing of Power
Analyser interfacing to PLC Panel with modbus communicatuion port, as per IEC
62053 and in the prescribed format including mounting arrangement. (for 2 Nos
Wash water pump & 2 Nos Blower)
7.00 35000 Each 245000
41
PLC Panel with HMI for Filter Bed - Designing, Supplying, Installing, commissioning &
testing of PLC Panel with HMI including PLC with CPU & Power supply unit, power
supply cable, Interfacing cards, interfacing cables, wireless modules with 25 % extra
quantity of all accessories.16.00 50000 Each 800000
42
Master PLC Panel - Design, Supply, Installing, Commissioning & Testing of Master
PLC control monitoring and communication panel as per IEC 61131 at Pure Water
Sump suitable for monitoring and control of pure water Pumps. Pressure
Transmitters, Level Transmitter, PH Transmitter, Turbidity Transmitter ,for all pumps
installed 2.00 1050000 Each 2100000
0 0
43Supplying and fixing Cat-6 STP cable suitable for LAN /
WAN as per specification in approved manner200.00 92.96 Mtr 18592
44
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 2 Pair x 1 sq.mm as per
IS 694 copper Shielded twisted, multistranded armoured
cablew on wall in GI tray or on ground. 200.00 162.4 Mtr 32480
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 179
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
45
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 3 Pairs x1 sq.mm. as per
IS 694 copper Shielded, twisted, multi stranded armoured
cable on wall in GI tray or on ground.200.00 206.08 Mtr 41216
46
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 4.5 Pairs x 1.0 sq.mm as
per IS 694 copper shielded, twisted, multi stranded
armoured cable on wall in GI tray or on ground. 200.00 303.52 Mtr 60704
47
Designing, Supplying, Installing, commissioning & testing
with Terminating & Interfacing of 8 Pairs x 1.0 sq.mm as
per IS 694 copper shielded, twisted, multi stranded
armoured cable on wall in GI tray or on ground.200.00 546.56 Mtr 109312
48
Providing & erecting Hot dipped Galvanised Ladder type
Cable tray manufactured from 16 swg (1.6 mm thick) GI
sheet of 150 mm width & 100 mm heightcomprising all
required standard accessories. 200.00 716.8 Mtr 143360
49
Pressure Transmitter for Blower and Wash Water Pumps Designing, Supplying,
Installing, commissioning & testing of pressure transmitter CE markd with following
technical parameters at Blower delivery and Interfacing with PLC panel.
Medium- Water
Pressure - 0-10 kg/cm2
Output 4-20 mA
Power supply - 24V DC ext.
Display - Large LED
Accuracy - +/- 0.5 % of full scale or better
Temp.- suitable for Amb.temp 4.00 35000 Nos 140000
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 180
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
50
Ultrasonic Level Transmitter for Wash Water Tank - Designing, Supplying, Installing,
commissioning & testing of Ultrasonic level transmitter CE marked with following
technical parameters and Interfacing with PLC panel including Mounting accessories.
Range- 0 - 5 mtrs
Output-4-20 mA
Power supply - 24V DC ext.
Display - 4" LED
Accuracy - +/- 0.25% of Full Scale or better
Enclosure- IP 65
3.00 50000 Nos 150000
51
Surveillance system - Desiging,supplying,installing,commissioning & testing of CCTV
IR water proof camera suitable for upto 100ft.with IR
Dome camera,control key board,DVR,Hard Disk,cables,UPT transreceivers
etc.complete.1.00 26772.48 Nos 26773
52
Flash Mixer & Clariflocculator - Designing, Supplying, Installing, commissioning &
testing with operation, controlling & Monitoring of Flash Mixer and Clarifloccutor
mechanism interfaced with Master PLC of WTP 2.00 50000 Nos 100000
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 181
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
53
Providing, erecting electric Valve actuators totally enclosed,
weather-proof and dust proof construction with IP-67,
protection class suitable for installation in any position
without lubrication, leakage or other operational difficulty
with special grease filled gear box and hand wheel for
emergency manual operation which will automatically disengage
on restoration of power to motor and with 10 watt
single phase space heater and continuous local mechanical
position indicator and individually replaceable counter gear
assembly and with two torque and four limit switches with
S.S. flap and operated with gear driven cams and of rating
250 Volt, 5 Amp, AC/DC, torque switch dial and with TEFC
squirrel cage induction motor working on 440 Volts +/- 10%,
3 phase, 50 Hz AC of intermittent duty rating S-2, insulation
class "F" and temp rise restricted to class "B" with IP - 67
protection class suitable for DOL starting and with three
thermostat and 30% over load margin. The torque rating of
reduction gear box shall be atleast 1.5 times max. torque
required for opening and closing of valve with integral
starter controls having four limit switches 1 for OPEN, 1 for
CLOSE & 2 Nos for intermidiate positions for interlocking
etc complete. with Third Party inspection 0 0
150 mm 20.00 85000 No 1700000
500 mm 16.00 110000 No 1760000
600 mm 24.00 125000 No 3000000
450 mm 2.00 135000 No 270000
0 0
54
Supplying and erecting armoured control cable with ISI
mark stranded / solid copper conductor 1.1 kV grade
complete erected on wall / panel or in provided trench in an
approved manner. 2.5 sq mm Copper conductor PVC insulated, armoured control
cable for Actuators 1000.00 144.48 Mtr 144480
0 0
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 182
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
55
Assembled D.O.L. Starter
Supplying and erecting assembled DOL starter in provided
cubical panel, with ON-OFF push buttons, no volt coil, over
load element and required power and control wiring
complete for Actuators Up to 7.5 HP 62.00 9000 No 558000
0 0
56
Design, Supply, Installation,Testing of Residual chlorine analyser / meter must have
automatic sensor cleaning facility at pure water sump and Interfacing with PLC panel.
Residual Chlorine meter shall comprises of 3 components i.e. sensors,flow through
assembly and transmitter with indicator and gives 2 outputs one to Local display &
other to PLC including Mounting arrangement. Overall
Range : 0 ‐
8 mg/l (ppm)
Accuracy : 2% of full scale Supply Voltage : 230
V ac
Output : 4 ‐ 20 mA
Membrane free sensor of 2 gold plated electrodes for long
term stability and reference electrode (ag/Agcl) must be
provided to avoid maintenance.
IP 65 Nema 4 housing protection class requird. 5.00 250000 No 1250000
Flow Meter 0 0
57
Supply, install and commission Electromagnetic Flow Meter (EMF) As Per ISO 4064,
for Raw/Pure water with accuracy +/-0.5% of measured value & protection as per
given specifications for size 100 mm-1000mm including sensor, transmitter surge
arrestor, cable suitable size for 25 mtrs built in GSM ( with Simcard and its
charges,valid for 36 months) including the pipe cutting, leveling and installation of
flow meter in the pipelines with necessary tool tackles, cranes including 36 months
guarantee etc complete, as may be required at site & based on technical
specifications (Annexure-A) attached 0 0
750 mm dia 7.00 520000 Nos 3640000
58
Constructing chamber for Water Meter including RCC foundation, vertical wall and
top slab 1:2:4 mix , bed concrete 1:4:8 mix with cement mortar 1:3 finished with a
floating coat of neat cement including curing complete. 2500x1500x2000mm. inside
size. 7.00 85053.92 Nos 595378
0 0
59 Providing , fabricating, fixing , jointing Specials of API grade material 1500.00 112 kg 168000
SCADA Software 0 0
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 183
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-P
Sr. No. Description Qty Rate (Rs.) UnitAmount
(Rs.)
60
Supply, Installation, Commissioning, Testing, Terminating & Interfacing Software
Design to PLC and commissioning of SCADA software with required hard tags plus
25% extra and with unlimited soft Tags & life time licence Development version
1.00 450000 Nos 450000
61
Developing/programming charges to install the software as
per logic defined by the dept.
1.00 250000 Nos 250000
62
Supply, Installation, Testing, Terminating & Interfacing Centralised Historian Server
grade Historian PC with Window 7 or latest window operating system & Historian
software development cost etc. complete 1.00 85000 Nos 85000
63
Supply, Installation, Testing, Terminating & Interfacing Secondary Computer Station
Secondary computer station etc.1.00 65000 Nos 65000
64Supply, Installation, Testing, Intgeration & Commissioning of 46" LCD monitor at
Conf. Room for display of total water system (Online) 1.00 98000 Nos 98000
65
Supplying and erecting window model mounted type room Air-Conditioner 3 star
230/250 V 50 cycles single phase A.C.supply 2 TRcapacity complete with gas
R410A/R32 at position in provided recess with wooden frame as per specification
No.AP-AC/WAC1.00 45000 Nos 45000
Total 32017997
Say 32018000
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 184
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-Q
Sr. No. Description Qty Rate Unit Amount
1 Construction of pump house cum attendant quarter 2 Nos. of 600 Sqm.
Each at Devidhar and Dummi.
1200 30545 Per Sqm. 366.54
As per PWD, Himachal Pradesh rates for plinth area for buildings of area
more than 500 sqm is 24436 in 2014 and increased by 25% for 5years.
2 Construction of staff quarters Type-I,II & III. 2000 30545 Per Sqm. 610.90
As per PWD, Himachal Pradesh rates for plinth area for buildings of area
more than 500 sqm is 24436 in 2014 and increased by 25% for 5years.
3 Construction of bridges at various points. 194 1.50 Per mtr. 291.00
2 Nos X 25 mtr Span = 50 mtr
3 Nos X 16 mtr Span = 48 mtr
4 Nos X 10 mtr Span = 40 mtr
8 Nos X 07 mtr Span = 56 mtr
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Pump House, Staff Quarter and Roads
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
4 Construction of 12 Km.5/7m wide Katcha road. 12.00 56.25 Per Km. 675.00
Total Rs. In Lac. 1943.44
Page - 185
SHIMLA JAL PRABANDHAN NIGAM LIMITED Annexure-R
Sr. No. Description Qty Rate Unit Amount
1
Providing, Constructing, Ereceting Solar Power Plant of 500 Kwp at Shikrodi,
Devidhar and Dummi as per availabilty of land including all fabrication, necessary
allied works etc complete500 76000 Kwp 38000000
Total In Rs. 38000000
Total In lac. 380.00
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Solar Power Plant 500 Kwp
ABSTRACT OF COST
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 186
RATE
ANALYSIS
Page - 187
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Name of work :- Providing Water Supply for Shimla town.
Cement/Steel/G.I Pipe
Dhalli Store (IPH)
6 K.M. 0.5 K.M.
By Mech Transport By Head load Site of work
Sand Deothi Solan
60 K.M. 0.5 K.M.
By Mech Transport By Head load Site of work
Aggrigate below 40 mm size
115 K.M 0.5 K.M.
Punchakula By Mech Transport By Head load Site of work
Aggrigate above 40 mm size
115 K.M 0.5 K.M.
By Mech Transport By Head load Site of work
Steel/wood/Frame/Shuttering and Shutter50 K.M 0.5 K.M.
Shimla By Mech Transport By Head load Site of work
Brick/MSERW Pipe/GI1460 K.M 0.5 K.M.
Chandigarh By Mech Transport By Head load Site of work
Flanges6 K.M. 0.5 K.M.
Local By Mech Transport By Head load Site of work
Soling Stone115 K.M 0.5 K.M.
By Mech Transport By Head load Site of work
Certified that lead is taken as per actual ,shortest and feasible as well as economical route by all means.
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Lead Statement
LEAD CHART
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 188
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
1) Cement from IPH 2) STEEL:
LEAD : By Mech. 50 Km. LEAD : By Mech. 50 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 106.22 0.00 1 Km. 0 106.22 0.00
2 Km. 0 124.09 0.00 2 Km. 0 124.09 0.00
3 Km. 0 141.79 0.00 3 Km. 0 141.79 0.00
4 Km. 0 159.04 0.00 4 Km. 0 159.04 0.00
5 Km. 1 175.55 175.55 5 Km. 1 175.55 175.55
5- 10 Km. 5 15.41 77.05 5- 10 Km. 5 15.41 77.05
10-20 Km. 10 13.15 131.50 10-20 Km. 10 13.15 131.50
Beyond 20 Km. 30 11.32 339.60 Beyond 20 Km. 30 11.32 339.60
TOTAL : 723.70 TOTAL : 723.70
2 By Head load 2 By Head load
1st. 1 Km. 0 431.84 0.00 1st. 1 Km. 0 911.43 0.00
1st. 100 Mtr 1 68.60 68.60 1st. 100 Mtr 1 144.81 144.81
Bey:1 Km.Per 1/2Km. 0 215.92 0.00 Bey:1 Km.Per 1/2Km. 0 455.72 0.00
Bey:100 Mtr Per 50 Mtr 8 20.18 161.44 Bey:100 Mtr Per 50 Mtr 8 42.59 340.72
Total : 230.04 Total : 485.53
3) Sand: 4)
LEAD : By Mech. 106 Km. LEAD : By Mech. 155 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 159.34 0.00 1 Km. 0 159.34 0.00
2 Km. 0 186.14 0.00 2 Km. 0 186.14 0.00
3 Km. 0 212.68 0.00 3 Km. 0 212.68 0.00
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
CARRIAGE OF MATERIALS
Stone aggregate below
40mm.:
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 189
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
4 Km. 0 238.56 0.00 4 Km. 0 238.56 0.00
5 Km. 1 263.33 263.33 5 Km. 1 263.33 263.33
5- 10 Km. 5 23.12 115.60 5- 10 Km. 5 23.12 115.60
10-20 Km. 10 19.73 197.30 10-20Km 10 19.73 197.30
Beyond 20 Km. 86 16.98 1460.28 Beyond 20 Km. 135 16.98 2292.30
TOTAL : 2036.51 TOTAL : 2868.53
2 By Head load 2 By Head load
1st. 1 Km. 0 732.74 0.00 1st. 1 Km. 0 732.74 0.00
1st. 100 Mtr 1 116.42 116.42 1st. 100 Mtr 1 116.42 116.42
Bey:1 Km.Per 1/2Km. 0 366.37 0.00 Bey:1 Km.Per 1/2Km. 0 366.37 0.00
Bey:100 Mtr Per 50 Mtr 8 34.24 273.92 Bey:100 Mtr Per 50 Mtr 8 34.24 273.92Total : 390.34 Total : 390.34
5) 6)
LEAD : By Mech. 65 Km. LEAD : By Mech. 50 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. Nos. Rate/ Km. 1 By Mech.
1 Km. 0 172.44 0.00 1 Km. 0 159.34 0.00
2 Km. 0 201.45 0.00 2 Km. 0 186.14 0.00
3 Km. 0 230.18 0.00 3 Km. 0 212.68 0.00
4 Km. 0 258.18 0.00 4 Km. 0 238.56 0.00
5 Km. 1 284.99 284.99 5 Km. 1 263.33 263.33
5- 10 Km. 5 25.02 125.10 5- 10 Km. 5 23.12 115.60
10-20 Km. 10 21.35 213.50 10-20 Km. 10 19.73 197.30
Beyond 20 Km. 45 18.38 827.10 Beyond 20 Km. 30 16.98 509.40
TOTAL : 1450.69 TOTAL : 1085.63
2 By Head load 2 By Head load
1st. 1 Km. 0 792.22 0.00 1st. 1 Km. 0 585.93 0.00
1st. 100 Mtr 1 125.86 125.86 1st. 100 Mtr 1 93.09 93.09
Bey:1 Km.Per 1/2Km. 0 396.11 0.00 Bey:1 Km.Per 1/2Km. 0 292.97 0.00
Bey:100 Mtr Per 50 Mtr 8 37.02 296.16 Bey:100 Mtr Per 50 Mtr 8 27.38 219.04
Stone aggregate 40mm
and above:
Timber(Local wood for
shuttering)and Shutter
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 190
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Total : 422.02 Total : 312.13
7) 7.1)
By Mech. 6 Km. By Mech. 1460 Km.
By Head : 0.5 Km. By Head : 0 Km.
1 By Mech. 1 By Mech.
1 Km. 0 106.22 0.00 1 Km. 0 106.22 0.00
2 Km. 0 124.09 0.00 2 Km. 0 124.09 0.00
3 Km. 0 141.79 0.00 3 Km. 0 141.79 0.00
4 Km. 0 159.04 0.00 4 Km. 0 159.04 0.00
5 Km. 1 175.55 175.55 5 Km. 1 175.55 175.55
5- 10 Km. 1 15.41 15.41 5- 10 Km. 5 15.41 77.05
10-20 Km. 0 13.15 0.00 10-20 Km. FALSE 13.15 0.00
Beyond 20 Km. 0 11.32 0.00 Beyond 20 Km. 1440 11.32 16300.80
TOTAL : 190.96 TOTAL : 16553.40
2 By Head load 2 By Head load
1st. 1 Km. 0 535.00 0.00 1st. 1 Km. 0 535.00 0.00
1st. 100 Mtr 1 85.00 85.00 1st. 100 Mtr 0 85.00 0.00
Bey:1 Km.Per 1/2Km. 0 267.50 0.00 Bey:1 Km.Per 1/2Km. 0 267.50 0.00
Bey:100 Mtr Per 50 Mtr 8 25.00 200.00 Bey:100 Mtr Per 50 Mtr 0 25.00 0.00
Total : 285.00 Total : 0.00
8) 9)
By Mech. 1466 Km. By Mech. 1460 Km.
By Head : 0 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 272.09 0.00 1 Km. 0 435.34 0.00
2 Km. 0 317.86 0.00 2 Km. 0 508.57 0.00
3 Km. 0 363.19 0.00 3 Km. 0 581.10 0.00
4 Km. 0 407.37 0.00 4 Km. 0 651.79 0.00
GI Pipe below 100mm
dia :
GI Pipe below 100mm
dia :
LEAD From IPH Store :LEAD From Chandigarh
:
MSERW Pipe 100mm
dia :
MSERW/CI Pipe 150mm
dia :
LEAD (From
Chandigarh to IPH and
IPH to Site) :
LEAD (From Chandigarh
to IPH and IPH to Site) :
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 191
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
5 Km. 1 449.68 449.68 5 Km. 1 719.48 719.48
5- 10 Km. 5 39.48 197.40 5- 10 Km. 5 63.16 315.80
10-20 Km. FALSE 33.69 0.00 10-20 Km. FALSE 53.91 0.00
Beyond 20 Km. 1446 29.00 41934.00 Beyond 20 Km. 1440 46.40 66816.00
TOTAL : 42581.08 TOTAL : 67851.28
2 By Head load 2 By Head load
1st. 1 Km. 0 1445.99 0.00 1st. 1 Km. 0 2037.28 0.00
1st. 100 Mtr 0 229.73 0.00 1st. 100 Mtr 1 323.68 323.68
Bey:1 Km.Per 1/2Km. 0 723.00 0.00 Bey:1 Km.Per 1/2Km. 0 1018.64 0.00
Bey:100 Mtr Per 50 Mtr 0 67.57 0.00 Bey:100 Mtr Per 50 Mtr 8 95.20 761.60
Total : 0.00 Total : 1085.28
10) 11)
By Mech. 1460 Km. By Mech. 1460 Km.
By Head : 0 Km. By Head : 0 Km.
1 By Mech. 1 By Mech.
1 Km. 0 725.57 0.00 1 Km. 0 989.42 0.00
2 Km. 0 847.62 0.00 2 Km. 0 1155.85 0.00
3 Km. 0 968.51 0.00 3 Km. 0 1320.69 0.00
4 Km. 0 1086.32 0.00 4 Km. 0 1481.35 0.00
5 Km. 1 1199.13 1199.13 5 Km. 1 1635.18 1635.18
5- 10 Km. 5 105.27 526.35 5- 10 Km. 5 143.55 717.75
10-20 Km. FALSE 89.85 0.00 10-20 Km. FALSE 122.52 0.00
Beyond 20 Km. 1440 77.34 111369.60 Beyond 20 Km. 1440 105.46 151862.40
TOTAL : 113095.08 TOTAL : 154215.33
2 By Head load 2 By Head load
1st. 1 Km. 0 3057.20 0.00 1st. 1 Km. 0 5373.33 0.00
1st. 100 Mtr 0 485.72 0.00 1st. 100 Mtr 0 853.71 0.00
Bey:1 Km.Per 1/2Km. 0 1528.60 0.00 Bey:1 Km.Per 1/2Km. 0 2686.67 0.00
Bey:100 Mtr Per 50 Mtr 0 142.86 0.00 Bey:100 Mtr Per 50 Mtr 0 251.09 0.00
Total : 0.00 Total : 0.00
MSERW Pipe 200mm
dia :
MSERW Pipe 250mm dia
:
LEAD (From
Chandigarh to IPH and
IPH to Site) :
LEAD (From Chandigarh
to IPH and IPH to Site) :
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 192
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
12) Flange / Sluice Valve 13) Bricks: Per 1000.Nos.
By Mech. 6 LEAD : By Mech. 1460 Km.
By Head : 0.5 By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 106.22 0.00 1 Km. 0 398.34 0.00
2 Km. 0 124.09 0.00 2 Km. 0 465.35 0.00
3 Km. 0 141.79 0.00 3 Km. 0 531.71 0.00
4 Km. 0 159.04 0.00 4 Km. 0 596.39 0.00
5 Km. 1 175.55 175.55 5 Km. 1 658.33 658.33
5- 10 Km. 1 15.41 15.41 5- 10 Km. 5 57.80 289.00
10-20 Km. 0 13.15 0.00 10-20 Km. FALSE 49.33 0.00
Beyond 20 Km. 0 11.32 0.00 Beyond 20 Km. 1440 42.46 61142.40
TOTAL : 190.96 TOTAL : 62089.73
2 By Head load 2 By Head load
1st. 1 Km. 0 911.43 0.00 1st. 1 Km. 0 1367.88 0.00
1st. 100 Mtr 1 144.81 144.81 1st. 100 Mtr 1 217.32 217.32
Bey:1 Km.Per 1/2Km. 0 455.72 0.00 Bey:1 Km.Per 1/2Km. 0 683.94 0.00
Bey:100 Mtr Per 50 Mtr 8 42.59 340.72 Bey:100 Mtr Per 50 Mtr 8 63.92 511.36
Total : 144.81 Total : 728.68
14) Soling Stone: 15 Building stone:
LEAD : By Mech. 115 Km. LEAD : By Mech. 65 Km.
By Head : 0.5 Km. By Head : 0.5 Km.
1 By Mech. 1 By Mech.
1 Km. 0 187.45 0.00 1 Km. 0 172.44 0.00
2 Km. 0 218.99 0.00 2 Km. 0 201.45 0.00
3 Km. 0 250.22 0.00 3 Km. 0 230.18 0.00
4 Km. 0 280.65 0.00 4 Km. 0 258.18 0.00
5 Km. 1 309.80 309.80 5 Km. 1 284.99 284.99
5- 10 Km. 5 27.20 136.00 5- 10 Km. 5 25.02 125.10
(Assumed as
locallyavailable) LEAD :
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 193
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
10-20 Km. 10 23.21 232.10 10-20 Km. 10 21.35 213.50
Beyond 20 Km. 95 19.98 1898.10 Beyond 20 Km. 45 18.38 827.10
TOTAL : 2576.00 TOTAL : 1450.69
2 By Head load 2 By Head load
1st. 1 Km. 0 732.74 0.00 1st. 1 Km. 0 792.22 0.00
1st. 100 Mtr 1 116.42 116.42 1st. 100 Mtr 1 125.86 125.86
Bey:1 Km.Per 1/2Km. 0 366.37 0.00 Bey:1 Km.Per 1/2Km. 0 396.11 0.00
Bey:100 Mtr Per 50 Mtr 8 34.24 273.92 Bey:100 Mtr Per 50 Mtr 8 37.02 296.16
Total : 390.34 Total : 422.02
A API Pipes A Flange / Sluice Valve
LEAD : By Mech. 1460 Km. LEAD : By Mech. 450 Km.
By Head : 0.5 Km. By Head : 0 Km.
1 By Mech. 1 By Mech.
1 Km. 0 101.17 0.00 1 Km. 0 101.17 0.00
2 Km. 0 116.25 0.00 2 Km. 0 116.25 0.00
3 Km. 0 131.16 0.00 3 Km. 0 131.16 0.00
4 Km. 0 145.64 0.00 4 Km. 0 145.64 0.00
5 Km. 1 159.41 159.41 5 Km. 1 159.41 159.41
5- 10 Km. 5 12.68 63.40 5- 10 Km. 5 12.68 63.40
10-20 Km. 10 10.48 104.80 10-20 Km. 10 10.48 104.80
Beyond 20 Km. 1440 8.71 12542.40 Beyond 20 Km. 430 8.71 3745.30
TOTAL : 12870.01 TOTAL : 4072.91
2 By Head load 2 By Head load
1st. 1 Km. 0 637.95 0.00 1st. 1 Km. 0 637.95 0.00
1st. 100 Mtr 1 101.37 101.37 1st. 100 Mtr 1 101.37 101.37
Bey:1 Km.Per 1/2Km. 0 318.98 0.00 Bey:1 Km.Per 1/2Km. 0 318.98 0.00
Bey:100 Mtr Per 50 Mtr 8 29.81 238.48 Bey:100 Mtr Per 50 Mtr 8 29.81 238.48
Total : 339.85 Total : 339.85
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 194
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
1689 KM by train from Jamnagar to Chandigarh @ Rs. 2376.00 per tonne
1689 X 2376 =Rs. 4013064
165 KM by Mech. Transport from Chandigarh to Site of Work
500 mtr by head loadBy Mech.
1 Km. 0 101.17 0.00
2 Km. 0 116.25 0.00
3 Km. 0 131.16 0.00
4 Km. 0 145.64 0.00
5 Km. 1 159.41 159.41
5- 10 Km. 5 12.68 63.40
10-20 Km. 10 10.48 104.80
Beyond 20 Km. 145 8.71 1262.95
TOTAL : 1590.56
By Head load
1st. 1 Km. 0 637.95 0.00
1st. 100 Mtr 0 101.37 0.00
Bey:1 Km.Per 1/2Km. 1 318.98 318.98
Bey:100 Mtr Per 50 Mtr 0 29.81 0.00
Total : 318.98
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 195
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. No. RATE UNIT
1 AGGREGATE 40 MM 550.00 /CUM
2 AGGREGATE 20 MM 725.00 /CUM
3 AGGREGATE 10 MM 725.00 /CUM
4 CEMENT 5120.00 /MT
5 SAND 650.00 /CUM
6 FINE SAND (FILTER MEDIA) 650.00 /CUM
7 M.R. TOR STEEL 4500.00 /QTL.
8 DRILLING EQUIPEMENT 3600.00 /DAY
9 SAFETY COILS 30.00 /COIL
10 DETONATORS 300.00 /100 Nos.
11 SPECIAL GELATINE 75.00 KG
12 STONE 500.00 /CUM
13 THROUGH BOUND STONE 1000.00 /100
14 MS ANGLE/ MS STRAPS 5000.00 /QTL.
15 WELDING CHARGES 4.00 /CMT.
16 WELDING CHARGES WITH GENERATOR SET 5.00 /CMT.
17 MS BOLTS 22 mm 5975.00 /QTL.
18 MS FLAT 5000.00 /QTL.
19 BOULDER/HARD STONE/PLUM 450.00 /CUM
20 CAST IRON M/H 90.00 /KG
21 BRICKS (I st Class) 4500.00 /1000
22 BRICKS II nd
Class) 4000.00 /1000
23 WHITE CEMENT 21500.00 /MT
24 Bitumen/Mexphalt 80/100 34500.00 /MT
25 KEROSENE OIL 14.00 /LTS.
26 DISEIL 76.00 /LTS.
27 M.OIL 285.00 /LTS.
28 FUEL WOOD 5.00 /KG
29 HIRING CHARGES OF TRUCK ( M.R.) 2500.00 /DAY
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
** BASIC RATE **
Name of work:- Hydraulic Design & Network Modelling for Shimla Water Supply
DESCRIPTION OF ITEM
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 196
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. No. RATE UNITDESCRIPTION OF ITEM
30 HIRE CHARGES OF PUMP 500.00 /DAY
31 HESSIAN CLOTH 25.00 /SQMT.
32 22mm RIVETS 6975.00 / QTL.
33 LIME(UNSLAKED) 1000.00 / QTL.
34 M.S.PLATES 4500.00 / QTL.
35 R.S.JOISTS 5000.00 / QTL.
36 C.I.RUNGS 40.00 /KG
37 ENAMELLED PAINT(OTHER THAN WHITE) 200.00 / LTS.
38 KAIL WOOD (Ist CLASS) 44500.00 /CUM
39 KAIL WOOD (IInd CLASS) 33830.00 /CUM
40 CHIL WOOD (Ist CLASS) 18100.00 /CUM
41 CHIL WOOD (IInd CLASS) 15800.00 /CUM
42 DEODAR WOOD 45200.00 /CUM
43 SAW CHARGES OF SLEEPERS TO PLANKS 700.00 /CUM
44 SAW CHARGES OF SLEEPERS TO BATTENS 500.00 /CUM
45 WOODEN BALLIES OF KAIL 125.00 /RMT.
46 WIRE GAUGE 250.00 /SQMT.
47 CI VENT PIPE 1.80 Mtr.Long 750.00 /EACH
48 Barbed Wire 56.68 Per Kg. (RC)
49 Ready Mixed Paint (other than white) 150.00 /ltr
50 Ready Mixed Paint (Pink Primer) 200.00 /ltr
51 Ready Mixed Red Mixed Paint 150.00 /ltr
52 Sliding Door Bolt (250 x 16 mm) 95.00 Each
53 Sliding Door Bolt (200X16 mm) 65.00 Each
54 Tower Bolt (Barrel Type 250 x 10 mm 35.00 Each
55 Tower Bolt (Barrel Type 200 x 10 mm 30.00 Each
56 Tower Bolt (Barrel Type 100 x 10 mm 25.00 Each
57 Tower Bolt (Barrel Type 150 x 10 mm 20.00 Each
58 Dry DisTamper 65.00 Kg
59 Oil Bound DisTamper 125.00 /ltr
60 Handles 100 mm 20.00 Each
61 Handles 125 mm 30.00 Each
62 SFRC Man Hole Cover 1700.00 Each
63 Terrazo Tiles 900.00 /SQMT.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 197
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. No. RATE UNITDESCRIPTION OF ITEM
64 Pink Makrana Marble 20 mm thick 1200.00 /SQMT.
65 Glass Strips 10.00 /Mtr.
66 Mild Steel Screws 40 mm 40.00 /Cent
67 Mild Steel Screws 25 mm 30.00 /10 nos
68 Mild Steel Screws 20 mm 25.00 /10 nos
69 Cement Paint 250.00 /ltr
70 Wood Perservative(Oil TYpe) 180.00 /ltr
71 Glass 2 mm to 3 mm 375.00 /Mtr
72 Iron Hinges ( 100 x 30 x 19 mm ) 25.00 /Cent
73 Iron Hinges ( 50 x 30 x 15 mm ) 15.00 /Cent
74 Ceramic Tile (153 x 152 x 6 mm) 750.00 /Sqm
75 C.G.I.SHEET 0.63 mm THICK 8000.00 /MT
76 P.G.I. SHEET 6000.00 /MT
77 800.00 /Cent
78 MS Flange of all tables 64.00 /KG
79 70.00 /KG
80
81 73.00 /KG
82
83 1373.00 /Meter
84 1703.00 /Meter
85 2318.00 /Meter
86 2880.00 /Meter
87 0.00 /Meter
88 4350.00 /Meter
89 0.00 /Meter
90 6140.00 /Meter
91
92 100 MM 105.00 EACH
93 150 MM 124.00 EACH
94 200 MM 171.00 EACH
95 250MM 295.00 EACH
96 300 MM 390.00 EACH
97 350 MM 703.00 EACH
98 400 MM 798.00 EACH
Rubber Gasket EPDM
DI PIPE 250 MM DIA Including frieght charges Upto Kalka
DI PIPE 300 MM DIA Including frieght charges Upto Kalka
DI PIPE 350 MM DIA Including frieght charges Upto Kalka
API Pipes (IS/ISO:3183-2007) Gr, X -
42 , 600 mm dia
DI PIPE 150 MM DIA Including frieght charges Upto Kalka
DI PIPE 200 MM DIA
DI PIPE 400 MM DIA Including frieght charges Upto Kalka
DI PIPE 450 MM DIA Including frieght charges Upto Kalka
DI PIPE 500 MM DIA Including frieght charges Upto Kalka
Including frieght charges Upto Kalka
60 mm Thick Precast Interlocked Paver Blocks
API Pipes (IS/ISO:3183-2007) Gr, X -
42 450 mm dia
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 198
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. No. RATE UNITDESCRIPTION OF ITEM
99 450 MM 1121.00 EACH
100 500 MM 1350.00 EACH
101 Plastic Steps 166.00 EACH
(B)
Sr. No. Rate i/c P/H Basic Rate Unit
1 FITTER (G-I) 292.00 252.00 /DAY
2 FITTER (G-II) 292.00 252.00 /DAY
3 MASON(G-1) 292.00 252.00 /DAY
4 MASON(G-II) 292.00 252.00 /DAY
5 PAINTER(G-I) 292.00 252.00 /DAY
6 PAINTER(G-II) 265.00 225.00 /DAY
7 BLACK SMITH (G-I) 292.00 252.00 /DAY
8 BLACK SMITH (G-II) 292.00 252.00 /DAY
9 CARPENTER G-I 292.00 252.00 /DAY
10 CARPENTER G-II 292.00 252.00 /DAY
11 BELDAR 250.00 210.00 /DAY
12 BHISTI 250.00 210.00 /DAY
13 MATE 250.00 210.00 /DAY
14 STONE DRESSER 250.00 210.00 /DAY
15 BHANDHANI 250.00 210.00 /DAY
16 DRILLER 250.00 210.00 /DAY
17 STONE CHISLER 250.00 210.00 /DAY
18 WHITE WASHER 265.00 210.00 /DAY
19 PUMP OPERATOR 262.00 252.00 /DAY
20 BLASTER 250.00 210.00 /DAY
21 Electrician 371.00 300.00 /DAY
22 BELDAR SKILLED 292.00 252.00 /DAY
RATE OF LABOUR AS APPLICABLE IN DEPTT. Vide Govt. notification No.FIN - ( PR ) B ( 7) - 33/2010 dt. 07-04-2017
Designation
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 199
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. No. RATE UNITDESCRIPTION OF ITEM
Certified that above rates of materials are the lowest one pervailing markets rates & rates of labour have been taken as
applicable in this Department as per latest notification as issued by the Govt.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 200
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
76.00 285.00 250.00 2500.001 2 3 4 5 6 7 8 9 10 11 12 13 14
1 12.00 5.65 17.30 5.77 438.52 0.22 62.70 1500.00 2500.00 4501.22 796.68
2 12.75 5.12 26.48 8.83 671.08 0.33 94.05 1500.00 2500.00 4765.13 930.69 134.01
3 13.12 4.69 34.14 11.38 864.88 0.43 122.55 1500.00 2500.00 4987.43 1063.42 132.73
4 13.50 4.34 40.72 13.57 1031.32 0.51 145.35 1500.00 2500.00 5176.67 1192.78 129.36
5 13.88 4.06 46.60 15.53 1180.28 0.58 165.30 1500.00 2500.00 5345.58 1316.65 123.87
6 14.25 3.82 51.84 17.28 1313.28 0.65 185.25 1500.00 2500.00 5498.53 1439.41 122.76
7 14.63 3.62 56.68 18.89 1435.64 0.71 202.35 1500.00 2500.00 5637.99 1557.46 118.05
8 15.10 3.46 61.36 20.45 1554.20 0.77 219.45 1500.00 2500.00 5773.65 1668.68 111.22
9 15.38 3.31 65.58 21.86 1661.36 0.82 233.70 1500.00 2500.00 5895.06 1780.98 112.30
10 15.75 3.17 69.40 23.13 1757.88 0.87 247.95 1500.00 2500.00 6005.83 1894.58 113.60 115.59
11 16.13 3.06 73.32 24.44 1857.44 0.92 262.20 1500.00 2500.00 6119.64 1999.88 105.30
12 16.50 2.96 77.04 25.68 1951.68 0.96 273.60 1500.00 2500.00 6225.28 2103.14 103.26
13 16.88 2.87 80.62 26.87 2042.12 1.01 287.85 1500.00 2500.00 6329.97 2205.56 102.42
14 17.25 2.78 83.84 27.95 2124.20 1.05 299.25 1500.00 2500.00 6423.45 2310.59 105.03
15 17.63 2.71 87.30 29.10 2211.60 1.09 310.65 1500.00 2500.00 6522.25 2406.73 96.14
16 18.00 2.64 90.48 30.16 2292.16 1.13 322.05 1500.00 2500.00 6614.21 2505.38 98.65
17 18.38 2.58 93.72 31.24 2374.24 1.18 336.30 1500.00 2500.00 6710.54 2600.98 95.60
18 18.75 2.52 96.72 32.24 2450.24 1.21 344.85 1500.00 2500.00 6795.09 2696.46 95.48
19 19.13 2.47 99.86 33.29 2530.04 1.25 356.25 1500.00 2500.00 6886.29 2787.97 91.51
20 19.50 2.42 102.80 34.27 2604.52 1.29 367.65 1500.00 2500.00 6972.17 2881.06 93.09 98.65
21 19.88 2.38 105.96 35.32 2684.32 1.32 376.20 1500.00 2500.00 7060.52 2966.61 85.55
22 20.25 2.34 108.96 36.32 2760.32 1.36 387.60 1500.00 2500.00 7147.92 3054.67 88.06
23 20.63 2.30 111.80 37.27 2832.52 1.40 399.00 1500.00 2500.00 7231.52 3144.14 89.47
24 21.00 2.26 114.48 38.16 2900.16 1.43 407.55 1500.00 2500.00 7307.71 3233.50 89.36
25 21.38 2.23 117.50 39.17 2976.92 1.48 421.80 1500.00 2500.00 7398.72 3317.81 84.31
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT
Sl.No.
Lead
inK.M.
(L)
Average speed Km/hour(s)No.of Trips
No.
No.of Km.
done
2NL+6
Litre of
diesel
consumed
Litre of
Diesel @
per Ltr.
Litres of
M.Oil
consumed
Cost of
M.Oil @
per litre
Cost of 6
Beldar @
per day
Hire
Charges
of Truck
@ per day
Total
cost
Col.No6+
8+9+10
Cost per
trip
Increase in
Cost per
Km over
previous
Km.
Average
cost per
additional
Km.after
five Km.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 201
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
26 21.75 2.20 120.40 40.13 3049.88 1.51 430.35 1500.00 2500.00 7480.23 3400.10 82.29
27 22.13 2.17 123.18 41.06 3120.56 1.54 438.90 1500.00 2500.00 7559.46 3483.62 83.52
28 22.50 2.14 125.84 41.95 3188.20 1.57 447.45 1500.00 2500.00 7635.65 3568.06 84.44
29 22.88 2.11 128.38 42.79 3252.04 1.60 456.00 1500.00 2500.00 7708.04 3653.10 85.04
30 23.25 2.09 131.40 43.80 3328.80 1.64 467.40 1500.00 2500.00 7796.20 3730.24 77.14 84.92
796.68 930.69 1063.42 1192.78 1316.65 115.59 98.651 2 3 4 5 6 7 8 9 10 11 12
1 Lime, moorum , building rubish. 6 cu.m 6.00 1 cu.m 132.78 155.12 177.24 198.80 219.44 19.27 16.44
2 Earth work. 6 cu.m 4.80 1 cu.m 165.98 193.89 221.55 248.50 274.30 24.08 20.55
3 Manure or sludge 6 cu.m 5.52 1 cu.m 144.33 168.60 192.65 216.08 238.52 20.94 17.87
4 Excavated rock. 6 cu.m 3.00 1 cu.m 265.56 310.23 354.47 397.59 438.88 38.53 32.88
5 Sand,stone agg. below 40mm 5 cu.m 5.00 1 cu.m 159.34 186.14 212.68 238.56 263.33 23.12 19.73
6Stone agg.40mm & above,build.
Stones.5 cu.m 4.62 1 cu.m 172.44 201.45 230.18 258.18 284.99 25.02 21.35
7Soling stone, stone block & stone
for filling crates5 cu.m 4.25 1 cu.m 187.45 218.99 250.22 280.65 309.80 27.20 23.21
8 Bricks. 2000Nos. 2000.00 1000 Nos. 398.34 465.35 531.71 596.39 658.33 57.80 49.33
9 Bricks tiles. 3200Nos. 3200.00 1000 Nos. 248.96 290.84 332.32 372.74 411.45 36.12 30.83
10 Slates. 14450Nos. 14450.00 1000 Nos. 55.13 64.41 73.59 82.55 91.12 8.00 6.83
11 Terrazzo Tiles. 2500Nos. 2500.00 1000 Nos. 318.67 372.28 425.37 477.11 526.66 46.24 39.46
12
Cement G.I. CI. AC. CC pipes
below 100mm dia & other heavy
materials.
7.50 Tonne 7.50 1 Tonne 106.22 124.09 141.79 159.04 175.55 15.41 13.15
13 Steam Coal 5.5 Tonne 5.50 1 Tonne 144.85 169.22 193.35 216.87 239.39 21.02 17.94
14 Steel i/c C.G.I & A.C.sheet. 7.50 Tonne 7.50 1 Tonne 106.22 124.09 141.79 159.04 175.55 15.41 13.15
15 Timber 5 cu.m 5.00 1 cu.m 159.34 186.14 212.68 238.56 263.33 23.12 19.73
16 Tar Bitumen etc. 4.50 Tonne 4.50 1 Tonne 177.04 206.82 236.32 265.06 292.59 25.69 21.92
17 R.C.C.,A.C. Hume, steel
C.I.Pipes:- 80 mm dia329.40m 329.40 100m 241.86 282.54 322.84 362.11 399.71 35.09 29.95
11.32
16.98
19.98
42.46
26.54
5.88
18.87
25.78
18.38
5Km. BEYOND
5Km.UP TO
10 Km.
BEYOND
10Km.UP
TO 20 Km.
84.9213
14.15
17.69
15.44
15.38
28.31
16.98
33.97
11.32
S.No MATERIALS CAPACITY NET QTY.TO
BE PAID
AFTER
DEDUCTION
OF VOIDS.
UNITS COST PER UNIT MATERIAL/DISTANCE GIVEN BELOW1 Km. 2Km. 3Km. 4Km. BEYOND 20Km /Km.
CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALS
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 202
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
796.68 930.69 1063.42 1192.78 1316.65 115.59 98.651 2 3 4 5 6 7 8 9 10 11 12
5Km. BEYOND
5Km.UP TO
10 Km.
BEYOND
10Km.UP
TO 20 Km.
84.9213
S.No MATERIALS CAPACITY NET QTY.TO
BE PAID
AFTER
DEDUCTION
OF VOIDS.
UNITS COST PER UNIT MATERIAL/DISTANCE GIVEN BELOW1 Km. 2Km. 3Km. 4Km. BEYOND 20Km /Km.
CARRIAGE OF MATERIAL BY MECHANICAL TRANSPORT INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALS
18 100 mm dia 292.80m 292.80 100m 272.09 317.86 363.19 407.37 449.68 39.48 33.69
19 125 mm dia 219.6m 219.60 100m 362.79 423.81 484.25 543.16 599.57 52.64 44.92
20 150 mm dia 183m 183.00 100m 435.34 508.57 581.10 651.79 719.48 63.16 53.91
21 200 mm dia 109.80m 109.80 100m 725.57 847.62 968.51 1086.32 1199.13 105.27 89.85
22 250 mm dia 80.52m 80.52 100m 989.42 1155.85 1320.69 1481.35 1635.18 143.55 122.52
23 300 mm dia 62.22m 62.22 100m 1280.42 1495.81 1709.13 1917.04 2116.12 185.78 158.55
24 350 mm dia 43.92m 43.92 100m 1813.93 2119.06 2421.27 2715.80 2997.84 263.18 224.61
25 400 mm dia 32.94m 32.94 100m 2418.58 2825.41 3228.35 3621.07 3997.12 350.91 299.48
26 450 /500mmdia 25.62m 25.62 100m 3109.60 3632.67 4150.74 4655.66 5139.15 451.17 385.05
27 600, 700, 750 & 800 mm dia 18.30m 18.30 100m 4353.44 5085.74 5811.04 6517.92 7194.81 631.64 539.07
28 900,1000,1100 & 1200 mm dia. 11.00m 11.00 100m 7242.55 8460.82 9667.45 10843.45 11969.55 1050.82 896.82
331.46
464.04
772.00
38.67
46.40
77.34
105.46
136.48
193.35
257.80
29.00
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 203
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
1 2 3 4 5 6 7 8 9 10 11
LIGHT MATERIALS A : 7.67 250.00 1917.50 2301.00
1 Lime, moorum and building rubish. 35 cu.m 35.00 1 cu.m 1917.50 65.74 27.39 93.13 586.15 293.08
2 .Earth work. 35 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
3 Manure or sludge 35cu.m 32.20 1 cu.m 1917.50 71.46 29.77 101.23 637.09 318.55
4 Excavated rock. 35 cu.m 17.50 1 cu.m 1917.50 131.49 54.79 186.28 1172.50 586.25
5 Sand,stone agg.below 40mm size. 28 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
6 Stone agg.40mm & above,build. Stones. 28 cu.m 25.90 1 cu.m 1917.50 88.84 37.02 125.86 792.22 396.11
7 Soling stone, stone block & stone for filling crates 28 cu.m 28.00 1 cu.m 1917.50 82.18 34.24 116.42 732.74 366.37
8 Bricks. 15000 Nos 15000.00 1000 Nos. 1917.50 153.40 63.92 217.32 1367.88 683.94
9 Bricks tiles.24000
Nos.24000.00 1000 Nos. 1917.50 95.88 39.95 135.83 854.93 427.47
10 Slates.80000
Nos.80000.00 1000 Nos. 1917.50 28.76 11.98 40.74 256.38 128.19
11 Terrazzo Tiles. 15000 Nos 15000.00 1000 Nos. 1917.50 153.40 63.92 217.32 1367.88 683.94
HEAVY MATERIALS A : 9.20 250.00 2300.00 B : =(Col.No.7/2+Col.No.7*1.40/2) 2760.00
1Stone blocks G.I,C.C. pipes below 100mm dia and
other heavy materials.46 Tonne 46.00 1 Tonne 2300.00 60.00 25.00 85.00 535.00 267.50
2 cement 57 Tonne 57.00 1 Tonne 2300.00 48.42 20.18 68.60 431.84 215.92
3 Steel including C.G.I & asbestos sheet. 27 Tonne 27.00 1 Tonne 2300.00 102.22 42.59 144.81 911.43 455.72
4 Timber 42 cu.m 42.00 1 cu.m 2300.00 65.71 27.38 93.09 585.93 292.97
FO
R 1
KM
.
BE
YO
ND
1
KM
./E
VE
RY
1/2
KM
.
No's Beldar @ B : =(Col.No.7/2+Col.No.7*1.40/2)
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
No's Beldar @
CARRIAGE OF MATERIAL BY MANUAL LABOUR INCLUDING LOADING/UNLOADINGAND STACKING OF MATERIALS
S.N
o
MATERIALS
CA
PA
CIT
Y
NE
T Q
TY
.TO
BE
PA
ID
AF
TE
R
DE
DU
CT
IO
N O
F
VO
ID
S.
UN
IT
S
CO
ST
OF
8 H
OU
RS COST OF CARRIGE INCLUDING LOADING AND STACKING
FO
R F
IR
ST
50
MT
R
FO
R E
VE
RY
AD
D.
LE
AD
OF
50
MT
RS
OR
PA
RT
TH
ER
E O
F
BE
YO
ND
50
MT
RS
UP
TO
FO
R 1
00
MT
R
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 204
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
1 2 3 4 5 6 7 8 9 10 11
FO
R 1
KM
.
BE
YO
ND
1
KM
./E
VE
RY
1/2
KM
.
S.N
o
MATERIALS
CA
PA
CIT
Y
NE
T Q
TY
.TO
BE
PA
ID
AF
TE
R
DE
DU
CT
IO
N O
F
VO
ID
S.
UN
IT
S
CO
ST
OF
8 H
OU
RS COST OF CARRIGE INCLUDING LOADING AND STACKING
FO
R F
IR
ST
50
MT
R
FO
R E
VE
RY
AD
D.
LE
AD
OF
50
MT
RS
OR
PA
RT
TH
ER
E O
F
BE
YO
ND
50
MT
RS
UP
TO
FO
R 1
00
MT
R
5 Tar Bitumen etc. 46 Tonne 46.00 1 Tonne 2300.00 60.00 25.00 85.00 535.00 267.50
6Concrete, R.C.C. Hume, steel C.I.Pipes:-
100mm dia1702m 1702.00 100m 2300.00 162.16 67.57 229.73 1445.99 723.00
7 Concrete, R.C.C. Hume, steel C.I.Pipes:- 125mm dia 1391m 1391.00 100m 2300.00 198.42 82.67 281.09 1769.15 884.58
8 Concrete, R.C.C. Hume, steel C.I.Pipes:- 150mm dia 1208m 1208.00 100m 2300.00 228.48 95.20 323.68 2037.28 1018.64
9 Concrete, R.C.C. Hume, steel C.I.Pipes:- 200mm dia 805m 805.00 100m 2300.00 342.86 142.86 485.72 3057.20 1528.60
10 Concrete, R.C.C. Hume, steel C.I.Pipes:- 250mm dia 458m 458.00 100m 2300.00 602.62 251.09 853.71 5373.33 2686.67
11 Concrete, R.C.C. Hume, steel C.I.Pipes:- 300mm dia 366m 366.00 100m 2300.00 754.10 314.21 1068.31 6724.09 3362.05
12 Concrete, R.C.C. Hume, steel C.I.Pipes:- 350mm dia 256m 256.00 100m 2300.00 1078.13 449.22 1527.35 9613.31 4806.66
13 Concrete, R.C.C. Hume, steel C.I.Pipes:- 400mm dia 220m 220.00 100m 2300.00 1254.55 522.73 1777.28 11186.42 5593.21
14Concrete, R.C.C. Hume, steel C.I.Pipes:-
450mm,500mm dia165m 165.00 100m 2300.00 1672.73 696.97 2369.70 14915.16 7457.58
15Concrete, R.C.C. Hume, steel C.I.Pipes:-
600,700,750 & 800mm dia150m 150.00 100m 2300.00 1840.00 766.67 2606.67 16406.73 8203.37
16Concrete, R.C.C. Hume, steel C.I.Pipes:-
900,1000,1100&1200mm dia125m 125.00 100m 2300.00 2208.00 920.00 3128.00 19688.00 9844.00
17Asbestes cement pipes: - 50mm dia =5032 pipes
of 2m length 10064m10064m 10064.00 100m 2300.00 27.42 11.43 38.85 244.59 122.30
18As bestes cement pipes: - 80mm dia 1620 pipes of
2m length=3660 3660m 3660.00 100m 2300.00 75.41 31.42 106.83 672.39 336.20
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 205
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
1 2 3 4 5 6 7 8 9 10 11
FO
R 1
KM
.
BE
YO
ND
1
KM
./E
VE
RY
1/2
KM
.
S.N
o
MATERIALS
CA
PA
CIT
Y
NE
T Q
TY
.TO
BE
PA
ID
AF
TE
R
DE
DU
CT
IO
N O
F
VO
ID
S.
UN
IT
S
CO
ST
OF
8 H
OU
RS COST OF CARRIGE INCLUDING LOADING AND STACKING
FO
R F
IR
ST
50
MT
R
FO
R E
VE
RY
AD
D.
LE
AD
OF
50
MT
RS
OR
PA
RT
TH
ER
E O
F
BE
YO
ND
50
MT
RS
UP
TO
FO
R 1
00
MT
R
19As bestes cement pipes:- 100mm dia 1281 pipes of
2m length=2562m2562m 2562.00 100m 2300.00 107.73 44.89 152.62 960.64 480.32
20As bestes cement pipes:- 125mm dia 1100 pipes of
2m length= 2200m2200m 2200.00 100m 2300.00 125.45 52.27 177.72 1118.58 559.29
21As bestes cement pipes:- 150mm dia 915 pipes of
2m length =1830m1830m 1830.00 100m 2300.00 150.82 62.84 213.66 1344.78 672.39
22As bestes cement pipes:- 200mm dia 800 pipes of
2m length= 1600m1600m 1600.00 100m 2300.00 172.50 71.88 244.38 1538.22 769.11
23As bestes cement pipes:- 250mm dia 700 pipes of
2m length= 1400m1400m 1400.00 100m 2300.00 197.14 82.14 279.28 1757.80 878.90
24As bestes cement pipes:- 300mm dia 600 pipes of
2m length= 1200m 1200m 1200.00 100m 2300.00 230.00 95.83 325.83 2050.77 1025.39
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 206
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
RATE ANALYSIS - 1
Details of cost for 10 Cubic meters :
Sr. Item Unit Qty. Rate Amount
1 Pick Work
1 Labour : Beldar Each 8.32 250.00 2080
Bhisti Each 0.28 250.00 70
Add for water charges @ 1.5% 32.25
Total Rs. 2182.25
Add 10% for Contractor profit 218.23
Add 5% for overhead charges 109.11
Cost of 10 cubic meters Rs. 2509.59
Cost per cum Rs. 250.96
2 Chiselling work in hard rock (Where blasting is prohibitted)1 Labour:
Beldar Each 11.71 250.00 2927.50
Stone Chiseller Each 23.43 250.00 5857.50
Black smith (G-II) Each 0.59 292.00 172.28
Total 8957.28
Add 10% Contractor profit 895.73
Add 5% Overhead Charges 447.86
Cost of 10 cubic meters Rs. 10300.87
Cost per cum Rs. 1030.09
Classification of soil Amount
Pick Work (70%) 250.96 70% 175.67
Chiselling Work (Hard work) (30%) 1030.09 30% 309.03
Average Rate 484.70
Add labour cess @ 1.00 % 484.70 1% 4.85
Add 12 % GST 12.0% 58.16
Total Cost Rs. Per Cum 547.71
Details of cost for 1 Cubic meters :
Sr. Item Unit Qty. Rate Amount
A Material
1 Stone for soling, filing crates Cum 1 500.00 500
B Carriage
115 K.M. by Mechanical Transport Cum 1 2576.00 2576
0.5 K.M. by Head Load Cum 1 390.34 390.34
C Labour
Beldar Each 0.8 250.00 200.00
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Client : Shimla Municipal Corporation
Analysis of Rates - 1
Excavation in foundations, trenches etc., in earth work, lift upto 1.5m stacking the soil not more than 3 meters clear from
the edge of the excavation and then returning the stacked soil in 15cm layers, when required into the plinths sides of
foundations etc., consolidating each deposited layer by ramming and watering and then disposing of all surplus excavated
earth as directed within a lead of 20 meters.
RATE ANALYSIS - 2
Providing and packing Soling stone and filling crate
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 207
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Gross total 3666.34
Add 10% Contractor profit 10% 366.63
Add 5% Overhead Charges 5% 183.32
Add labour cess @ 1.00 % 1% 36.66
Add 12 % GST 12.0% 439.96
Total Cost Rs. Per Cum 4692.92
Detail of cost for 10 cubic metre
1. Soft rock.
Sr. Item Unit Qty. Rate Amount.
Drilling equipment Day 0.18 3600.00 648.00
Material
Special gelatine (80%) kg. 2.520 75.00 189.00
Detonators ordinary 100 Nos 12.00 300.00 36.00
Safety fuse wire (coil 10 Mtrs length) Coil 1.00 30.00 30.00
Labour
Hole Driller each 0.54 250.00 135.00
Blaster each 0.36 250.00 90.00
Beldar each 6.67 250.00 1667.50
Total 2795.50
Add 10% Contractor profit 279.55
Add 5% Overhead Charges 139.78
Total 3214.83
Cost for 10 cum. 3214.83
Cost for 1 cum 321.48
Detail of cost for 10 cubic metre
2. Hard Rock
Drilling equipment Day 0.28 3600.00 1008.00
Material
Special gelatine (80 % ) Kg. 3.92 75.00 294.00
Detonators ordinary 100 Nos. 14.00 300.00 42.00
Safety fuse wire (coil 10 mtr. length ) Coil 1.25 30.00 37.50
Labour
Hole Driller Each 0.84 250.00 210.00
Blaster Each 0.56 250.00 140.00
Beldar Each 8.33 250.00 2082.50
Total 3814.00
Add 10% Contractor profit 381.4
Add 5% Overhead Charges 190.7
Total 4386.10
Cost for 10 cum 4386.10
Cost of per cum 438.61
Classification of Rocks Amount
Soft Rock (70%) 321.48 70% 225.04
Hard Rock (30%) 438.61 30% 131.58
Average Rate 356.62
Add labour cess @ 1.00 % 356.62 1% 3.57
Add 12 % GST 12.0% 42.79
Total Cost Rs. Per Cum 402.98
Analysis of Rate - 3
Cutting in earth work and disposal of excavated earth upto a lead of 20 Mtrs soft rock.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 208
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
Material
Cement Tonne 0.17 5,120.00 870.40
Sand Cum 0.47 650.00 305.50
20mm stone aggregate Cum 0.24 725.00 174.00
40mm stone aggregate Cum 0.65 550.00 357.50
Subtotal 1707.40 A
Carriage of stone aggregate: 40mm and above
65 K.M. by Mechanical Transport Cum 0.65 1450.69 942.95
0.5 K.M. by Head Load Cum 0.65 422.02 274.31
Carriage of stone aggregate: Below. 40mm
155 K.M. by Mechanical Transport Cum 0.24 2868.53 688.45
0.5 K.M. by Head Load Cum 0.24 390.34 93.68
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.47 2036.51 957.16
0.5 K.M. By Head Load Cum 0.47 390.34 183.46
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.17 723.70 123.03
0.5 K.M. By Head Load Tonne 0.17 230.04 39.11
Subtotal 3302.15 B
labour
Beldar Each 2.09 250.00 522.50
Bhisti Each 0.27 250.00 67.50
Mason 1st Class Each 0.05 292.00 14.60
Mason 2nd Class Each 0.05 292.00 14.60
Mate Each 0.04 250.00 10.00
Beldar for extra ramming Each 0.25 250.00 62.50
Sundries L.S. 15.00
Subtotal 706.70 C
5,716.25
Add for water charges @1.5% 85.74
5,801.99
Add 10% Contractor profit 580.20
Add 5% Overhead Charges 290.10
Add labour cess @ 1.00 % 58.02
Add 12 % GST 696.247426.55
S.R. stone masonary in CM 1:4 Detail of cost for one cu.m
Description of Items Qty. Rate Unit Amount
Materials
Cement mortor 1:4. 0.30 7,342.75 Cum. 2202.83
Stone at quarry 1.21 500.00 Cum. 605.00
through stone 7.00 10.00 Each 70.00
Subtotal 2877.83 A
Carriage of Building Stone
65 Km by machenical transport 1.37 1450.69 Cum. 1987.45
0.5 Km. by head load 1.37 422.02 Cum. 578.17
Subtotal 2565.62 B
Labour
Stone dresser 2.83 250.00 Each. 707.5
Mason 1st. class 1.06 292.00 Each. 309.52
Mason 2 nd. class 1.06 292.00 Each. 309.52
Beldar 2.65 250.00 Each. 662.5
RATE ANALYSIS - 4
P/L Cement Concrete work 1:4:8 (1cement :4sand :8stone aggregate 40mm nominal size) and curing complete
excluding cost of form work in :- Foundations & plinth
Details of Cost for 1 Cubic Meter
Total Rs.(A+B+C)
Net Total Rs.
Cost for 1 Cubic Meter
ANALYSIS OF RATE - 5
Squared rubble masonry coursed with hard stone of approved quality in foundation and plinth including raking out joints in
cement mortor.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 209
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
Sundaries L.S. Each. 50.00
Subtotal 2039.04 C
7482.49
112.24
7,594.73
Add 10% Contractor profit 759.47
Add 5% Overhead Charges 379.74
Add labour cess @ 1.00 % 75.95
Add 12 % GST 911.379721.25
Detail of cost for 10 Sqm
Material Unit Qty Rate Amount.
Cement (0.2225 cum. Or o.32 Tonne) Tonne 0.15 5120.00 768.00
Sand Cum. 0.178 650.00 115.70
10mm stone aggregate. Cum. 0.8900 725.00 645.25
20mm stone aggregate Cum. 0.267 725.00 193.58
Total 1722.53 (A)
Carriage for Stone agg below 40mm
155 Km by Mech Transport cum 0.356 2868.53 1021.20
0.5 0.5 K mtrs. by head load cum 0.356 390.34 138.96
Carriage for Sand
106 Km by Mech Transport cum 0.178 2036.51 362.50
0.5 0.5 Kmtrs. by head load cum 0.178 390.34 69.48
Carriage for Cement
50 Km by Mech Transport Tonne 0.15 723.70 108.56
0.5 Kmtrs. by head load Tonne 0.15 230.04 34.51
Total 1735.20 (B)
Labour
Mason 2nd class Each 1.35 292.00 394.20
Beldar Each 2.16 250.00 540.00
Bhashti Each 0.27 250.00 67.50
Sundaries L.S. 25.00
Total 1026.70 (C)
Total (A)+(B)+(C) 4484.42
Add for water charges @ 1.5% 67.27
4,551.69
Add 10% Contractor profit 455.17
Add 5% Overhead Charges 227.58
Add labour cess @ 1.00 % 45.52
Add 12 % GST 546.20582.62
(a)Foundation footing basis of columns etc and mass concrete
Detail of cost for 10 Sqm.
Sr. Description. Unit Qty. Rate. Amount
Material
Rate as per above in Sub Analysis. Sqm. 10.15200 6201.80 62960.7
Battens IInd class kail wood
6 X 1 X 0.075 X 0.10m. = 0.045 cum.
Wastage @ 5% per kg. = 0.002 cum.
Add 1.5% water charges.
Net Total Rs.
Cost for 1 Cubic Meter
Analysis of Rate for Flooring - 6
P/L cement concrete flooring 1:2:4 ( 1cement: 2sand: 4 graded stone aggregate 20mm nominal size) laid in one
layer finished with a floating coat of neat cement. 40 mm thick.
Net Total Rs.
Cost for 1 Cubic Meter
ANALYSIS OF RATES - 7
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a
fair finish including centering shuttering strutting and propping etc,with wooden battens and ballies,height of
propping and centring below supporting floor to ceiling not execding 4 meters, and removal of the same for insitu-
reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for shuttering steel
work welded in built up section I/c cutting fixing in positionin angles,plates etc.
Total (A+B+C)
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 210
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
Total Qty:- = 0.047 cum.. Cum. 0.047 33,830.00 1590.01
Ballies 125mm dia Kail wood
6 X 1.50 = 9.00 Rmt.
Wastage @ 5% per kg. = 0.45Rmt.
Total Qty:- =9.45 Rmt. Rmt. 9.45 125.00 1181.25
Carriage of Timber :-
Ballies 125mm dia Kail wood
9.45 X 0.785 X (0.125)2 = 0.116 cum.
Battens IInd class kail wood =0.047 cum.
Total Qty:- = 0.163 cum..
50 K.M.by Mechanical Transport. Cum. 0.163 723.70 117.96
0.5 M.by head load. Cum. 0.163 485.53 79.14
Total Rs:- 2968.36
Carriage cost of wood i.e.1/16 Rs:- 12.32
Each. 0.01 62960.7 629.61
cent 0.01 62960.7 629.61
Cum. 0.0625 2968.36 185.52
cent 0.05 2968.36 148.42
Labour:- For assembling errection and dismentling etc.
Carpenter 2nd class. Each. 0.52 292.00 151.84
Beldar. Each. 1.30 250.00 325
Total Rs:- 2070.00
Sundries @ 10% of labour cost. Rs:- 207
Total Rs:- 2277
Add 10% Contractor profit 227.70
Add 5% Overhead Charges 113.85
Add labour cess @ 1.00 % 22.77
Add 12 % GST 273.242914.56
291.46
d)Columns,Pillar;Posts and struts Square Rectangular and Polygonal in Plan
Sr. Description. Unit Qty. Rate. Amount
Rate as per above in Sub Analysis. Sqm. 5.46 6201.80 33861.84
Ballies 125mm dia.(Kail wood 2nd class.) Meter 15.96 125.00 1995.00
50 Carriage of Timber :-K.M.by Mechanical Transport. Cum. 0.196 723.70 141.85
0.5 Carriage of Timber :-M.by head load. Cum. 0.196 485.53 95.16
Total Rs:- 2232.01
Carriage cost of wood i.e.1/16 Rs:- 14.81
Each. 0.01 33861.84 338.62
cent 0.01 33861.84 338.62
Cum. 0.0625 2232.01 139.5
Add 5% for using repeatedly including repair removal of
dents cleaning concrete deposits & appling
Cost for 10 Sq.m
Cost per Sqmt. Rs:-
ANALYSIS OF RATES - 8
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a
fair finish including centering shuttering strutting and propping etc,with wooden battens and ballies,height of
propping and centring below supporting floor to ceiling not execding 4 meters, and removal of the same for insitu-
reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for shuttering steel
work welded in built up section I/c cutting fixing in positionin angles,plates etc.
Detail of cost for area in contact 4 X 0.30 X 3.50 = 4.20 Sqm.
Assuming that steel plates shall become unservicable
after being used 100 times.Hence cost for using once:-
1/100
Add 1% for using repeatedly including repair removal of
dents cleaning concrete deposits & appling oiling and
greasing etc.
Assuming that Timber shall become unservicable after
being used 16 times.Hence cost for using once = 1/16
Assuming that Timber shall become unservicable after
being used 16 times.Hence cost for using once = 1/16
Assuming that steel plates shall become unservicable
after being used 100 times. Hence cost for using once:-
1/100
Add 1% for using repeatedly including repair removal of
dents cleaning concrete deposits & appling oiling and
greasing etc.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 211
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
cent 0.05 2232.01 111.6
Labour:- For assembling errection and dismentling etc.
Carpenter 2nd class. Each. 0.59 292.00 172.28
Beldar. Each. 1.47 250.00 367.50
Total Rs:- 1468.12
Sundries @ 10% of labour cost. On Rs:- 539.78 Rs:- 146.812
Total Rs:- 1614.932
Add 10% Contractor profit 161.49
Add 5% Overhead Charges 80.75
Add labour cess @ 1.00 % 16.15
Add 12 % GST 193.792067.11
492.17
Sr. Description. Unit Qty. Rate. Amount
Material:-
3.15 mm Thick M.S. Plate.
0.90 X 0.60 = 0.54 Sqm.
Weight @ 24.72kg per Sqm. =13.35kg.
Wastage @ 5% per kg. =0.66kg
Total Qty:- =14.01kg or 0.14 Qtl. Qtl. 0.14 4500.00 630.00
Angle iron in frame 30X30X5mm Size
2(0.90+0.60) = = 3.00 Rmt.
Weight @ 2.20kg per Rmt.. =13.35kg.
Wastage @ 5% per kg. =0.33kg
Total Qty:- =6.93kg or 0.0693 Qtl. Qtl. 0.0693 5,000.00 346.50
Sub Total Rs. 976.50 A
Carriage of M.S. Plate and angles.
M.S.Plate. = 0.140 Qtl
Angle iron =0.0693 Qtl.
Total Qty:- =0.2093 Qtl or 0.02093 Tonne.
50 K.M.by Mechanical Transport. Tonne 0.02093 723.70 15.15
0.5 M.by head load. Tonne 0.02093 485.53 10.16
Sub Total Rs. 25.31 B
Labour.
Black Smith Ist. Class. Each 0.066 292.00 19.27
Bandhani Each 0.066 250.00 16.50
Beldar Each 0.154 250.00 38.5
Sundries Each 10
Sub Total Rs. 84.27 C
Welding charges by Electric Plant CM. 300.00 5.00 1500.00 D
Total Rs. (A+B+C+D) 2586.08
Add 1.5% water charges. Rs:- 38.79
Add 10% Contractor profit 258.61
Add 5% Overhead Charges 129.30
Add labour cess @ 1.00 % 25.86
Add 12 % GST 310.333348.97
6201.80
ANALYSIS OF RATES - 9
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a
fair finish including centering shuttering strutting and propping etc,with wooden battens and ballies,height of
propping and centring below supporting floor to ceiling not execding 4 meters, and removal of the same for insitu-
reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for shuttering
steel work welded in built up section I/c cutting fixing in positionin angles,plates etc. Detail of cost for
90cm X 60cm size of plates complete 0.54 Sqm.
Cost for 0.54 Sqmt.Rs:-
Cost per Sqmt. Rs:-
Cost per Sqmt. Rs:-
Add 5% for using repeatedly including repair removal of
dents cleaning concrete deposits & appling
Cost for 10 Sq.m
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 212
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
Discription Unit Qty. Rate Amount
Materials
Cement Tonne 0.32 5,120.00 1638.40
Sand Cum 0.445 650.00 289.25
10mm stone aggregate Cum 0.22 725.00 159.50
20mm stone aggregate Cum 0.67 725.00 485.75
Subtotal 2572.90 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.89 2868.53 2552.99
0.5 K.M. by Head Load Cum 0.89 390.34 347.40
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.45 2036.51 916.43
0.5 K.M. by Head Load Cum 0.45 390.34 175.65
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.32 723.70 231.58
0.5 K.M. by Head Load Tonne 0.32 230.04 73.61
Subtotal 4297.66 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 245.00 66.15
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 294.00 14.70
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 693.65 (C)
(A+B+C) 7564.21
Add for water charges @1.5% 7,564.21 1.50% 113.46
7677.67
Add 1% Labour cess 7,677.67 1.00% 76.78
Add GST 12.00% 921.32Add 10% C.P.and 5% Over head charges
except on cost of store issue items,such as
Cement
6039.27 15% 905.89
Rs:- 9,581.66
Unit Qty. Rate Amount
Material
Cement mortar 1:4
(1cement:4sand) Cum. 0.165 7,342.75 1211.55
Subtotal 1211.55 (A)
20 mm cement plaster in single coat on fair side f brick/stone masonry for interior plastering up to floor two level including
arrises, internal rounded angles, chamfers and/or rounded angles not exceeding 80mm in girth and finished even and
smooth .
In cement mortar 1:4
Details of cost for 10 Sqm.
Desciption
RATE ANALYSIS - 11
RATE ANALYSIS - 10
Providing & laying cement concrete 1:2:4, 20mm nominal size & curing complete for RCC work in: Suspended floor,
roofs, landing and shelves and their supports, balconies, beams, girders, bressumers and cantilever upto floor two level.
Details of Cost for 1 Cubic Meter
Total
Gross Total
Cost for one cubic meter
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 213
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
Labour :
Mason II nd class Each 0.80 294.00 235.20
Beldar Each 0.80 245.00 196.00
Bhishti Each 0.98 245.00 240.10
Sundries(Scaffolding etc.) L.S. 45.00
Subtotal 716.30 (B)
Total (A+B) 1927.85
Add for water charges @1.5% 1,927.85 1.50% 28.92
Gross Total 1956.77
Add 1% Labour cess 1,956.77 1.00% 19.57
Add GST 12.00% 234.81Add 10% C.P.and 5% Over head charges
except on cost of store issue items,such as
Cement
745.22 15% 111.78
Cost for 10 square meter Rs:- 2,322.93
Cost of 1 Sqm. Rs:- 232.29
Unit Qty. Rate Amount
Material
Cement mortar 1:3
(1cement:3sand) Cum. 0.224 8,268.73 1852.2
Sand & Gravel Crushed stone graded from 6
mm to 12mm Cum. 0.1 725.00 72.5
Grounded hydrated lime Kg 9.28 100.00 928
Subtotal 2852.7 (A)
Labour :
Mason II nd class Each 1.71 294.00 502.74
Beldar Each 1.58 245.00 387.10
Bhishti Each 1.7 245.00 416.50
Sundries(Scaffolding etc.) L.S. 45.00
Extra labour for coping
Mason II nd class Each 0.25 294.00 73.50
beldar Each 0.25 245.00 61.25
Extra labour for dashing of crushed stone
Mason II nd class Each 0.5 294.00 147.00
beldar Each 0.5 245.00 122.50
bhisti Each 0.1 245.00 24.50
sundries ( scaffolding etc.) 10.00
Subtotal 1790.09 (B)
Total (A+B) 4642.79
Add for water charges @1.5% 4,642.79 1.50% 69.64
RATE ANALYSIS - 12
Rough side exterior cement plaster on wall up to a height of 10 mtr. above ground level with a mixture of sand and gravel
or crushed stone graded from 6mm to 12 mm nominal size dashed over and including fresh plaster in two coats, backing
coat 10 mm cement plaster 1:3 (1cement:3sand) and finishing coat 10 mm cement mortor 1:3 (1cement:3sand) mixed
with 10 % finely grounded hydrated lime by volume of cement including arrises, chamfersb and/or rounded angles not
exceeding 80 mm in girth. (natural cement finish using ordinary cement)
In cement mortar 1:3
Details of cost for 10 Sqm.
Desciption
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 214
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
Gross Total 4712.43
Add 1% Labour cess 4,712.43 1.00% 47.12
Add GST 12.00% 565.49
Add 10% C.P.and 5% Over head charges
except on cost of store issue items,such as
Cement
2860.23 15% 429.03
Cost for 10 square meter Rs:- 5,754.08
Cost of 1 Sqm. Rs:- 575.41
Unit Qty. Rate Amount
Materials
Cement Tonne 0.40 5,120.00 2048.00
Sand Cum 0.425 650.00 276.25
10mm stone aggregate Cum 0.28 725.00 203.00
20mm stone aggregate Cum 0.57 725.00 413.25
Subtotal 2940.50 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.85 2868.53 2438.25
0.5 K.M. by Head Load Cum 0.85 390.34 331.79
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.425 2036.51 865.52
0.5 K.M. by Head Load Cum 0.425 390.34 165.89
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.40 723.70 289.48
0.5 K.M. by Head Load Tonne 0.40 230.04 92.02
Subtotal 4182.95 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.28 245.00 68.60
Mason 1st Class Each 0.06 294.00 17.64
Mason 2nd Class Each 0.06 294.00 17.64
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 701.98 ( C)
Total (A+B+C) 7825.43
Add for water charges @1.5% 7,825.43 1.50% 117.38
Gross Total 7942.81
Add 1% Labour cess 7,942.81 1.00% 79.43
Add GST 12.00% 953.14Add 10% C.P.and 5% Over head charges
except on cost of store issue items,such as
Cement
5894.81 15% 884.22
Cost for one cubic meter Rs:- 9,859.60
Discription
Details of Cost for 1 Cubic Meter
RATE ANALYSIS - 13
Prov.& laying c.conc. 1:2:4 (1cement:2 sand:4 graded stone aggregate 20mm nominal size) & curing complete e/c cost of
form work & reinforcement for RCC work in wall i/c attached, buttresses, columns, pillasters ,their caps & bases & string
courses etc. up to floor two level.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 215
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.40 5,120.00 2048.00
Sand Cum 0.425 650.00 276.25
10mm stone aggregate Cum 0.28 725.00 203.00
20mm stone aggregate Cum 0.57 725.00 413.25
Subtotal 2940.50 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.85 2868.53 2438.25
0.5 K.M. by Head Load Cum 0.85 390.34 331.79
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.425 2036.51 865.52
0.5 K.M. by Head Load Cum 0.425 390.34 165.89
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.40 723.70 289.48
0.5 K.M. by Head Load Tonne 0.40 230.04 92.02
Subtotal 4182.95 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 245.00 66.15
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 294.00 14.70
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Extra for laying CC in RCC work due to delay
etc.
Labour for 1 Cum
Beldar Each 0.10 245.00 24.50
Bhisti Each 0.20 245.00 49.00
Mason 1st Class Each 0.04 294.00 11.76
Mason 2nd Class Each 0.04 294.00 11.76
Mate Each 0.04 245.00 9.80
Extra labour for lifting the material, Beldar Each 0.17 245.00 41.65
Subtotal 842.12 ( C)
Total (A+B+C) 7965.57
Add for water charges @1.5% 7,965.57 1.50% 119.48
Gross Total 8085.05
Add 1% Labour cess 8,085.05 1.00% 80.85
Add GST 12.00% 970.21Add 10% C.P.and 5% Over head charges
except on cost of store issue items,such as
Cement
6037.05 15% 905.56
Cost for one cubic meter Rs:- 10,041.66
RATE ANALYSIS - 14
P/L cement concrete 1:1.5:3 (1cement:2sand:4graded stone aggregate 20mm nominal size E/C cost of form work &
reinforcement for rcc work in suspended floor, roofs, landing & shelves & their support balconies, beams, girders,
bressumers & cantilever up to floor two level.
Details of Cost for 1 Cubic Meter
Discription
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 216
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.61 5,120.00 3123.20
Sand Cum 0.25 650.00 162.50
10mm stone aggregate Cum 0.342 725.00 247.95
20mm stone aggregate Cum 0.418 725.00 303.05
Subtotal 3836.70 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
0.5 K.M. by Mechanical Transport Cum 0.76 2868.53 2180.08
0 K.M. by Head Load Cum 0.76 390.34 296.66
Carriage of Sand
0.5 K.M. by Mechanical Transport Cum 0.25 2036.51 509.13
0 K.M. by Head Load Cum 0.25 390.34 97.59
Carriage of Cement
0.5 K.M. by Mechanical Transport Tonne 0.61 723.70 441.46
0 K.M. by Head Load Tonne 0.61 230.04 140.32
Subtotal 3665.24 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 294.00 79.38
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 245.00 12.25
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 0.00 0.00
Sundries L.S. 15.00
Extra for laying CC in RCC work due to delay
etc.
Labour for 1 Cum
Beldar Each 0.10 245.00 24.50
Bhisti Each 0.20 245.00 49.00
Mason 1st Class Each 0.04 294.00 11.76
Mason 2nd Class Each 0.04 294.00 11.76
Mate Each 0.04 245.00 9.80
Extra labour for lifting the material, Beldar Each 0.17 245.00 41.65
Subtotal 791.65 ( C)
Total (A+B+C) 8293.59
Add for water charges @1.5% 8,293.59 1.50% 124.40
Gross Total 8417.99
Add 1% Labour cess 8,417.99 1.00% 84.18
Add GST 12.00% 1010.16Add 10% C.P.and 5% Over head charges
except on cost of store issue items,such as
Cement
5294.79 15% 794.22
Cost for one cubic meter Rs:- 10,306.55
Details of Cost for 1 Cubic Meter
RATE ANALYSIS - 15
P/L cement concrete of M30 grade (1:1:3) (1cement:1sand:3graded stone aggregate 20mm nominal size E/C cost of
form work & reinforcement for rcc work in suspended floor, roofs, landing & shelves & their support balconies, beams,
girders, bressumers & cantilever up to floor two level. (Slab for For RCC GSR)
Details of Cost for 1 Cubic Meter
Discription
RATE ANALYSIS - 16
P/L cement concrete of M30 grade (1:1:3) (1cement:1sand:3graded stone aggregate 20mm nominal size) & curing
complete e/c cost of form work & reinforcement for RCC work in wall i/c attached, buttresses, columns, pillasters ,their
caps & bases & string courses etc. up to floor two level. (Wall for For RCC GSR)
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 217
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.61 5,120.00 3123.20
Sand Cum 0.25 650.00 162.50
10mm stone aggregate Cum 0.342 725.00 247.95
20mm stone aggregate Cum 0.418 725.00 303.05
Subtotal 3836.70 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
0 K.M. by Mechanical Transport Cum 0.76 2868.53 2180.08
0 K.M. by Head Load Cum 0.76 390.34 296.66
Carriage of Sand
0 K.M. by Mechanical Transport Cum 0.25 2036.51 509.13
0 K.M. by Head Load Cum 0.25 390.34 97.59
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.61 723.70 441.46
0 K.M. by Head Load Tonne 0.61 230.04 140.32
Subtotal 3665.24 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.28 245.00 68.60
Mason 1st Class Each 0.06 294.00 17.64
Mason 2nd Class Each 0.06 294.00 17.64
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 701.98 ( C)
Total (A+B+C) 8203.92
Add for water charges @1.5% 8,203.92 1.50% 123.06
Gross Total 8326.98
Add 1% Labour cess 8,326.98 1.00% 83.27
Add GST 12.00% 999.24Add 10% C.P.and 5% Over head charges
except on cost of store issue items,such as
Cement
5203.78 15% 780.57
Cost for one cubic meter Rs:- 10,190.05
Unit Qty Rate Amount
Material:-
Mild Steel Bars Qtl. 1.00
Wastage @ 5% Qtl. 0.05
Total 1.05 Qtl. 1.05 4,500.00 4725.00 (A)
6 K.M By Mechanical Transport Tonne 0.105 723.70 75.99
0.5 K.M ByHead load. Tonne 0.105 485.53 50.98
Subtotal 126.97 (B)
Labour:-
Black Smith Ist class Each 1.00 292.00 292.00
Beldar Each 1.00 245.00 245.00
Sundries LS 10.00
Subtotal 547.00 ( C)
Total (A+B+C) 5398.97
Add for water charges @1.5% 5,398.97 1.50% 80.98
Discription
RATE ANALYSIS - 17
Providing mild steel/tor steel reinforcement for RCC work includng bending binding and placing in position complete.
Detail of cost for 1 Qtl.
Description.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 218
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
Gross Total 5479.95
Add 1% Labour cess 5,479.95 1.00% 54.80
Add GST 12.00% 657.59
Add 10% C.P.and 5% Over head charges
except on cost of store issue items,such as
Steel
754.95 15% 113.24
Cost per Qtl Rs:- 6,305.59
Cost per Kg Rs:- 63.06
Cement Mortar 1:4 ( 1CEMENT : 4SAND)
Sr.No Item Unit Qty. Rate Amount
Material
Cement Tonne 0.38 5,120.00 1,945.60
Sand Cum 1.07 650.00 695.50
Subtotal 2,641.10 (A)
Carriage
Carriage of Sand
106 K.M. by Mechanical Transport Cum 1.07 2036.51 2,179.07
0.5 K.M. by Head Load Cum 1.07 390.34 417.66
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.38 723.70 275.01
0.5 K.M. by Head Load Tonne 0.38 230.04 87.42
Subtotal 2,959.16 (B)Labour measuring,carrying, depositing and
mixing
Beldar Each 0.9 245.00 220.50
Bhisti Each 0.08 245.00 19.60
Sundries L.S. 36.02
Subtotal 276.12 (C)
Total (A+B+C) 5,876.38
Add for water charges @1.5% 5,876.38 1.50% 88.15
Gross Total 5964.53
Add 1% Labour cess 5,964.53 1.00% 59.65
Add GST 12.00% 715.74Add 10% C.P.and 5% Over head charges
except on cost of store issue items,such as
Cement
4018.93 15% 602.84
Cost for one cubic meter Rs:- 7,342.75
Cement Mortar 1:3 ( 1CEMENT : 3SAND)
Sr.No Item Unit Qty. Rate Amount
Material
Cement Tonne 0.51 5,120.00 2,611.20
Sand Cum 1.07 650.00 695.50
Subtotal 3,306.70 (A)
Carriage
Carriage of Sand
0 K.M. by Mechanical Transport Cum 1.07 2036.51 2,179.07
0 K.M. by Head Load Cum 1.07 390.34 417.66
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.51 723.70 369.09
0 K.M. by Head Load Tonne 0.51 230.04 117.32
Details of cost for 1cum
RATE ANALYSIS - 19
Details of cost for 1cum
RATE ANALYSIS - 18
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 219
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Item Unit Qty. Rate Amount
Subtotal 3,083.14 (B)Labour measuring,carrying, depositing and
mixing
Beldar Each 0.9 245.00 220.50
Bhisti Each 0.08 245.00 19.60
Sundries L.S. 36.02
Subtotal 276.12 (C)
Total (A+B+C) 6,665.96
Add for water charges @1.5% 6,665.96 1.50% 99.99
Gross Total 6765.95
Add 1% Labour cess 6,765.95 1.00% 67.66
Add GST 12.00% 811.91Add 10% C.P.and 5% Over head charges
except on cost of store issue items,such as
Cement
4154.75 15% 623.21
Cost for one cubic meter Rs:- 8,268.73
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 220
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Details of cost for 10 Cubic meters :
Sr. Item Unit Qty. Rate Amount
Pick Work
1 Labour : Beldar Each 8.32 250.00 2080
Bhisti Each 0.28 250.00 70
Add for water charges @ 1.5% 32.25
Total Rs. 2182.25
Add 10% for Contractor profit 218.23
Add 5% for overhead charges 109.11
Cost of 10 cubic meters Rs. 2509.59
Cost per cum Rs. 250.96 (A)
Add labour cess @ 1.00 % = 2.51
30.12
Total Rs. 283.58
CHISELLING WORK IN HARD ROCK(WHERE BLASTING IS PROHOBITED)
Labour
Beldar each 11.71 250.00 2927.50
Stone Chiseller each 23.43 250.00 5857.50
Black smith (G-II) each 0.59 294.00 173.46
Total 8958.46
Add 10% for Contractor profit 895.85
Add 5% for overhead charges 447.92
Cost of 10 cubic meters Rs. 10302.23
Cost per cum Rs. 1030.22
Add labour cess @ 1.00 % = 10.30
123.63
Total Rs. 1164.15
Classification of soil Amount
Pick Work 20% 283.58 56.72
Chiselling Work (Hard work) 80% 1164.15 931.32
Average Rate 988.04 (B)
per cum
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla
(HP).
RATE ANALYSIS - 20
Excavation in foundations, trenches etc., in earth work in all type of soil such as pick work
Kankar,moorum shungles including decomposed of soft and hard rock upto all heights stacking
the excavated earth not more than 3 meters clear from the edge of the excavation and then
returning the stacked soil in 15cm layers,when required into the plinths sides of foundations etc.,
consolidating each deposited layer bywhen required into the plinths sides of foundations etc.,
consolidating each deposited layer by ramming and watering and then disposing of all surplus
excavated earth upto all leads and lifts etc. complete in all respect.
GST 12.0%
GST 12.0%
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 221
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
DETAIL OF COST FOR ONE CUM
Sr.
No.Qty. Rate Unit Amount
(A) MATERIAL:-
STONE AGGREGATE 20 mm 0.22 CUM 0.22 725.00 CUM 159.50STONE AGGREGATE 10 mm 0.11 CUM 0.11 725.00 CUM 79.75SAND 0.445 CUM 0.445 650.00 CUM 289.25CEMENT 0.32 MT 0.32 5120.00 MT 1638.40
TOTAL 2166.90 1)(B) CARRIAGE OF MATERIALS:-
STONE AGGREGATE 20 mm BY MECH. TPT. 40.00 KM 0.22 801.75 CUM 176.39BY HEAD LOAD. 1.00 KM 0.22 718.18 CUM 158.00STONE AGGREGATE 10 mm BY MECH. TPT. 40.00 KM 0.11 801.75 CUM 88.19BY HEAD LOAD. 1.00 KM 0.11 718.18 CUM 79.00SANDBY MECH. TPT. 65.00 KM 0.445 1157.50 CUM 515.09BY HEAD LOAD. 1.00 KM 0.445 718.18 CUM 319.59CEMENTBY MECH. TPT. 15.00 KM 0.32 288.32 MT 92.26BY HEAD LOAD. 1.00 KM 0.32 423.08 MT 135.39
TOTAL 1563.91 2)(C ) LABOUR:-
BELDAR 2.09 294.00 EACH 614.46BHISTI 0.27 245.00 EACH 66.15MASON(G-I) 0.05 294.00 EACH 14.70MASON(G-II) 0.05 294.00 EACH 14.70MATE 0.04 245.00 EACH 9.80BELDAR FOR EXTRA RAMMING 0.25 294.00 EACH 73.50
ANALYSIS OF RATE -21Prov. & laying cement conc.1:2:4(1cement:2sand:4graded stone aggregate 20 mm nominal size ) and curing complete e/c the cost of form
work and reinforcement in foundation & plinth.
Description of item
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 222
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr.
No.Qty. Rate Unit AmountDescription of item
SUNDRIES LS 50.00EXTRA FOR LAYING C.CONC. IN RCC WORKBELDAR 0.10 EACH 0.00BHISTI 0.20 EACH 0.00MASON(G-1) 0.04 EACH 0.00MASON(G-II) 0.04 EACH 0.00MATE 0.04 EACH 0.00
TOTAL 843.31 3)ADD EPF 12.5% 105.41
TOTAL (1 to 3) 4574.12Add 1.50 % for water Charges 4574.12 68.61Add for Mechanical Mixer and Vibratot etc. LS 20.00
Total (1+2+3) 4662.73ADD 10% Contractor's Profit except EPF 4662.73 466.27Add 5% over Head Charges on all amount i.e. on Rs. 4662.73 233.14
Sub Total Rs = 5362.14
Add Labour Cess @ 1.00 % 0n Rs.= 4662.73 (+ ) Rs. 46.63ADD 12% GST 559.53
G.Total Rs.= 6073.71SAY Rs. 6073.71
EXCEPT EPF
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 223
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr.
No.Qty. Rate Unit AmountDescription of item
DETAIL OF COST FOR ONE CUM
S.No. Qty. Rate Unit Amount
(A) MATERIAL:-STONE AGGREGATE 20 mm 0.58 CUM 0.58 725.00 CUM 420.50STONE AGGREGATE 10 mm 0.20 CUM 0.20 725.00 CUM 145.00SAND 0.390 CUM 0.39 650.00 CUM 253.50CEMENT 0.56 MT 0.56 5120.00 MT 2867.20
TOTAL 3686.20 1)(B) CARRIAGE OF MATERIALS:-
STONE AGGREGATE 20 mm BY MECH. TPT. 40.00 KM 0.580 801.75 CUM 465.02BY HEAD LOAD. 1.00 KM 0.580 718.18 CUM 416.54STONE AGGREGATE 10 mm BY MECH. TPT. 40.00 KM 0.200 801.75 CUM 160.35BY HEAD LOAD. 1.00 KM 0.200 718.18 CUM 143.64SANDBY MECH. TPT. 65.00 KM 0.390 1157.50 CUM 451.43BY HEAD LOAD. 1.00 KM 0.390 718.18 CUM 280.09CEMENTBY MECH. TPT. 10.00 KM 0.560 288.32 MT 161.46BY HEAD LOAD. 1.00 KM 0.560 423.08 MT 236.92
TOTAL 2315.45 2)(C ) LABOUR:-
BELDAR 2.09 245.00 EACH 512.05BHISTI 0.27 245.00 EACH 66.15MASON(G-I) 0.05 294.00 EACH 14.70MASON(G-II) 0.05 294.00 EACH 14.70MATE 0.04 245.00 EACH 9.80
ANALYSIS OF RATE -22Providing & laying cement concrete using nominal mix of " M - 30 " with 20 mm & down gauge nominal size graded stone aggregate) &
curing complete excluding the cost of form work & reinforcement for reinforced concrete work in : - Foundation and Plinth
Description of item
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 224
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr.
No.Qty. Rate Unit AmountDescription of item
BELDAR FOR EXTRA RAMMING 0.25 245.00 EACH 61.25SUNDRIES LS 30.87EXTRA FOR LAYING C.CONC. IN RCC WORKBELDAR 0.10 245.00 EACH 24.50BHISTI 0.20 245.00 EACH 49.00MASON(G-1) 0.04 294.00 EACH 11.76MASON(G-II) 0.04 294.00 EACH 11.76MATE 0.04 245.00 EACH 9.80
TOTAL 816.34 3)ADD EPF 12.5 % 102.04
TOTAL (1 to 3) 6817.99Add 1.50 % for water Charges 6817.99 102.27Add for Mechanical Mixer and Vibrator etc. LS 50.00
Total (1+2+3) 6970.26ADD 10% Contractor's Profit except store issue items 4103.06 410.31Add 5% over Head Charges on all amount i.e. on Rs. 6970.26 348.51
Sub Total Rs = 7729.08
Add Labour Cess @ 1.00 % 0n Rs.= 7729.08 (+ ) Rs. 77.29ADD 12 % GST 836.43
G.Total Rs.= 8744.84SAY Rs. 8744.85
EXCEPT EPF
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 225
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr.
No.Qty. Rate Unit AmountDescription of item
(DETAIL OF COST FOR1.00 Kg)
S.No. Qty. Rate Unit Amount
(A) MATERIAL:-TOR STEEL 1.00 QTL.ADD 5% FOR WASTAGE 0.05 QTL.
TOTAL 1.05 QTL. 1.050 4500.00 Qtl. 4725.00Total 4725.00 1)
(B) CARRIAGE (STEEL,CGI & ASBESTOS SHEETS)BY MECH. TPT. 10.00 KM 0.105 231.92 MT 24.35BY HEAD LOAD. 1.00 KM 0.105 893.24 MT 93.79
Total 118.14 2)
(C ) LABOUR:- B/SMITH (G-I) 1.00 262.50 EACH 262.50BELDAR 1.00 294.00 EACH 294.00SUNDRIES I/c COST OF BINDING WIRE. LS 100.00
Total 656.50 3)ADD EPF 12.5% 82.06
EXCEPT EPF TOTAL (1 to 3) 5499.64TOTAL 5499.64
ADD 10% Contractor's Profit except store isuue items 774.64 77.46Add 5% (Over Head Charges) 5499.64 274.98
Sub Total = 5852.08Add Labour Cess @ 1.00 % 0n Rs.= 5499.64 (+ ) Rs. 55.00
ADD 12 % GST 659.96G.Total Rs.= 6649.10
COST PER Kg. 66.49
ANALYSIS OF RATE -23
PROV.MILD STEEL/TOR STEEL REINFORCEMENT FOR RCC WORK I/C BENDING,BINDING & PLACING IN POSITION COMPLETE UPTO
FLOOR TWO LEVEL
Description of item
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 226
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr.
No.Qty. Rate Unit AmountDescription of item
(DETAILS FOR 10 M 2)
S.No. Qty. Rate Unit Amount
(A) MATERIAL:-
CEMENT MORTOR IN 1:4 0.231 5418.01 CUM 1251.56
TOTAL 1251.56 1)
(B ) LABOUR:-
1.53 294.00 EACH 449.82
1.53 294.00 EACH 449.82
1.48 245.00 EACH 362.60
TOTAL 1262.24 2)
ADD EPF 12.5% 157.78
TOTAL (1+2) 2513.80
Add 1.50 % for water Charrges 2513.80 37.71
TOTAL 2551.51
TOTAL 2551.51
ADD 10% Contractor's Profit except store isuue items 1299.95 130.00
1299.95 65.00
Sub Total = 2746.51
Add Labour Cess @ 1.00 % 0n Rs.= 1382.68 (+ ) Rs. 13.83
ADD GST 12% 301.66
G.Total Rs.= 3219.78
Toal:- 3219.80
Per sqm 321.98
Add 5 % (Over Head Charges)
ANALYSIS OF RATE -24
20 mm thick cement plaster in two coats on rough side of brick/stone maonry for interior plastering 1:4 (1cement:4 sand)
MASON(G-II)
BELDAR
BHISTI
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 227
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr.
No.Qty. Rate Unit AmountDescription of item
(DETAILS FOR ONE M 3)
S.No. Qty. Rate Unit Amount
(A) MATERIAL:-
CEMENT MORTOR IN 1:6 0.24 4640.90 CUM 1113.82
BRICKS(IInd CLASS) 475.00 4000.00 /1000 1900.00
(B) CARRIAGE OF BRICKS:- TOTAL 3013.82 1)
M.TPT.FOR BRICKS 150.00 KM 475.00 5916.93 /1000 2810.54
H.L. FOR BRICKS 1.00 KM 475.00 1340.49 /1000 636.73
TOTAL 3447.27 2)
(C ) LABOUR:-
MASON (G-I) 0.50 294.00 EACH 147.00
MASON (G-II) 0.50 294.00 EACH 147.00
BELDAR 1.80 294.00 EACH 529.20
BHISTI 0.20 245.00 EACH 49.00
SUNDRIES LS 50.00
TOTAL 922.20 3)
ADD 12.5 % EPF 115.28
TOTAL (1TO 3)EXCEPT EPF 7383.29
Add 1.50 % for water Charrges 7383.29 110.75
TOTAL 7494.04
TOTAL 7494.04
ANALYSIS OF RATE -25
Brick work using common burnt clay building bricks (iind class) in found. And plinth in 1:6 (1cement:6sand) in foundation & plinth
Description of item
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 228
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr.
No.Qty. Rate Unit AmountDescription of item
ADD 10% Contractor's Profit except store isuue items,EPF 6380.22 638.02
6380.22 319.01
Sub Total = 8451.07
Add Labour Cess @ 1.00 % 0n Rs.= 7494.04 (+ ) Rs. 74.94
ADD GST 12 % 899.28
G.Total Rs.= 9540.57
SAY Rs. 9540.57
Add 5 % (Over Head Charges) except store isuue items,EPF
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 229
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr.
No.Qty. Rate Unit AmountDescription of item
S.No. Qty. Rate Unit Amount
(A) MATERIAL:-
CEMENT 0.25 5120.00 MT 1280.00
SAND 1.07 650.00 CUM 695.50
TOTAL 1975.50 1)
(B) CARRIAGE OF MATERIAL:-
CEMENT
By Mech. Transport. 15.00 KM 0.25 288.32 MT 72.08
By head load 1.00 KM 0.25 423.08 MT 105.77
SAND
By Mech. Transport. 65.00 KM 1.07 1157.50 CUM 1238.53
By head load 1.00 KM 1.07 718.18 Cum. 768.45
TOTAL 2184.83 2)
(C ) LABOUR:-
BELDAR 0.90 294.00 EACH 264.60
BHISTI 0.08 245.00 EACH 19.60
SUNDRIES LS 42.63
TOTAL 326.83 3)
EPF 12.5% 40.85
TOTAL (1+2+3) 4487.16
Add 1.50 % for water Charrges 4487.16 67.31
ANALYSIS OF RATE -26
CEMENT MORTOR I:6 (1CEMENT : 6 SAND)
Description of item
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 230
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr.
No.Qty. Rate Unit AmountDescription of item
TOTAL 4554.47
TOTAL 4554.47
ADD 10% Contractor's Profit except store isuue items 0.00 0.00
0.00 0.00
Sub Total = 4554.47
Add Labour Cess @ 1.00 % 0n Rs.= 4554.47 (+ ) Rs. 45.54
G.Total Rs.= 4640.86
SAY Rs. 4640.85
SAY Rs. 4640.90
Add 5 % (Over Head Charges)
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 231
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr.
No.Qty. Rate Unit AmountDescription of item
S.No. Qty. Rate Unit Amount
(A) MATERIAL:-CEMENT 0.38 5120.00 MT 1945.60SAND 1.07 650.00 CUM 695.50
TOTAL 2641.10 1)(B) CARRIAGE OF MATERIAL:-
CEMENTBy Mech. Transport. 15.00 KM 0.38 288.32 MT 109.56By head load 1.00 KM 0.38 423.08 MT 160.77SANDBy Mech. Transport. 65.00 KM 1.07 1157.50 CUM 1238.53By head load 1.00 KM 1.07 718.18 Cum. 768.45
TOTAL 2277.31 2)(C ) LABOUR:-
BELDAR 0.90 294.00 EACH 264.60BHISTI 0.08 245.00 EACH 19.60SUNDRIES LS 42.63
TOTAL 326.83 3)ADD EPF 12.5% 40.85
TOTAL (1+2+3) 5245.24Add 1.50 % for water Charrges 5245.24 78.68
TOTAL 5323.92TOTAL 5323.92
ADD 10% Contractor's Profit except store isuue items 0.00 0.000.00 0.00
Sub Total = 5323.92
Add Labour Cess @ 1.00 % 0n Rs.= 5323.92 (+ ) Rs. 53.24G.Total Rs.= 5418.01
TOTAL 5418.01
ANALYSIS OF RATE -27
CEMENT MORTOR I:4 (1CEMENT :4SAND)
Description of item
EXCEPT EPF
Add5 % (Over Head Charges)
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 232
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
(a)Foundation footing basis of columns etc and mass concrete
Detail of cost for 10 Sqm.
Sr. Description. Unit Qty. Rate. Amount
Material
Rate as per above in Sub Analysis. Sqm. 10.15200 6201.80 62960.7
Battens IInd class kail wood
6 X 1 X 0.075 X 0.10m. = 0.045 cum.
Wastage @ 5% per kg. = 0.002 cum.
Total Qty:- = 0.047 cum.. Cum. 0.047 33,830.00 1590.01
Ballies 125mm dia Kail wood
6 X 1.50 = 9.00 Rmt.
Wastage @ 5% per kg. = 0.45Rmt.
Total Qty:- =9.45 Rmt. Rmt. 9.45 125.00 1181.25
Carriage of Timber :-
Ballies 125mm dia Kail wood
9.45 X 0.785 X (0.125)2 = 0.116 cum.
Battens IInd class kail wood =0.047 cum.
Total Qty:- = 0.163 cum..
50 K.M.by Mechanical Transport. Cum. 0.163 723.70 117.96
0.5 M.by head load. Cum. 0.163 485.53 79.14
Total Rs:- 2968.36
Carriage cost of wood i.e.1/16 Rs:- 12.32
Each. 0.01 62960.7 629.61
cent 0.01 62960.7 629.61
Cum. 0.0625 2968.36 185.52
Assuming that Timber shall become unservicable after being used 16
times.Hence cost for using once = 1/16
ANALYSIS OF RATES - 28
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for shuttering
steel work welded in built up section I/c cutting fixing in positionin angles,plates etc.
Assuming that steel plates shall become unservicable after being used 100
times. Hence cost for using once:- 1/100
Add 1% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling oiling and greasing etc.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 233
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
cent 0.05 2968.36 148.42
Labour:- For assembling errection and dismentling etc.
Carpenter 2nd class. Each. 0.52 292.00 151.84
Beldar. Each. 1.30 250.00 325
Total Rs:- 2070.00
Sundries @ 10% of labour cost. Rs:- 207
Total Rs:- 2277
Add 10% Contractor profit 227.70
Add 5% Overhead Charges 113.85
Add labour cess @ 1.00 % 22.77
Add 12 % GST 273.242914.56
291.46
Add 5% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling
Cost for 10 Sq.m
Cost per Sqmt. Rs:-
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 234
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
d)Columns,Pillar;Posts and struts Square Rectangular and Polygonal in Plan
Sr. Description. Unit Qty. Rate. Amount
Rate as per above in Sub Analysis. Sqm. 5.46 6201.80 33861.84
Ballies 125mm dia.(Kail wood 2nd class.) Meter 15.96 125.00 1995.00
50 Carriage of Timber :-K.M.by Mechanical Transport. Cum. 0.196 723.70 141.85
0.5 Carriage of Timber :-M.by head load. Cum. 0.196 485.53 95.16
Total Rs:- 2232.01
Carriage cost of wood i.e.1/16 Rs:- 14.81
Each. 0.01 33861.84 338.62
cent 0.01 33861.84 338.62
Cum. 0.0625 2232.01 139.5
cent 0.05 2232.01 111.6
Labour:- For assembling errection and dismentling etc.
Carpenter 2nd class. Each. 0.59 292.00 172.28
Beldar. Each. 1.47 250.00 367.50
Total Rs:- 1468.12
Sundries @ 10% of labour cost. On Rs:- 539.78 Rs:- 146.812
Total Rs:- 1614.932
Add 10% Contractor profit 161.49
Add 5% Overhead Charges 80.75
Add labour cess @ 1.00 % 16.15
Add 12 % GST 193.792067.11
492.17Cost per Sqmt. Rs:-
ANALYSIS OF RATES - 29
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for shuttering
steel work welded in built up section I/c cutting fixing in positionin angles,plates etc.
Detail of cost for area in contact 4 X 0.30 X 3.50 = 4.20 Sqm.
Assuming that steel plates shall become unservicable after being used 100
times.Hence cost for using once:- 1/100
Add 1% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling oiling and greasing etc.
Assuming that Timber shall become unservicable after being used 16
times.Hence cost for using once = 1/16
Add 5% for using repeatedly including repair removal of dents cleaning
concrete deposits & appling
Cost for 10 Sq.m
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 235
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Sr. Description. Unit Qty. Rate. Amount
Material:-
3.15 mm Thick M.S. Plate.
0.90 X 0.60 = 0.54 Sqm.
Weight @ 24.72kg per Sqm. =13.35kg.
Wastage @ 5% per kg. =0.66kg
Total Qty:- =14.01kg or 0.14 Qtl. Qtl. 0.14 4500.00 630.00
Angle iron in frame 30X30X5mm Size
2(0.90+0.60) = = 3.00 Rmt.
Weight @ 2.20kg per Rmt.. =13.35kg.
Wastage @ 5% per kg. =0.33kg
Total Qty:- =6.93kg or 0.0693 Qtl. Qtl. 0.0693 5,000.00 346.50
Sub Total Rs. 976.50 A
Carriage of M.S. Plate and angles.
M.S.Plate. = 0.140 Qtl
Angle iron =0.0693 Qtl.
Total Qty:- =0.2093 Qtl or 0.02093 Tonne.
50 K.M.by Mechanical Transport. Tonne 0.02093 723.70 15.15
0.5 M.by head load. Tonne 0.02093 485.53 10.16
Sub Total Rs. 25.31 B
Labour.
Black Smith Ist. Class. Each 0.066 292.00 19.27
Bandhani Each 0.066 250.00 16.50
Beldar Each 0.154 250.00 38.5
Sundries Each 10
Sub Total Rs. 84.27 C
Welding charges by Electric Plant CM. 300.00 5.00 1500.00 D
ANALYSIS OF RATES - 30
Providing form work with steel plates 3.15 mm thick welded with angle iron in frame30X30X5 mm so as to give a fair finish including centering
shuttering strutting and propping etc,with wooden battens and ballies,height of propping and centring below supporting floor to ceiling not execding 4
meters, and removal of the same for insitu-reinforced concrete and plain concrete work in :- Sub analysis for manufacturing steel plates for
shuttering steel work welded in built up section I/c cutting fixing in positionin angles,plates etc. Detail of cost for 90cm X 60cm size of plates
complete 0.54 Sqm.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 236
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Total Rs. (A+B+C+D) 2586.08
Add 1.5% water charges. Rs:- 38.79
Add 10% Contractor profit 258.61
Add 5% Overhead Charges 129.30
Add labour cess @ 1.00 % 25.86
Add 12 % GST 310.333348.97
6201.80
Cost for 0.54 Sqmt.Rs:-
Cost per Sqmt. Rs:-
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 237
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Discription Unit Qty. Rate Amount
Materials
Cement Tonne 0.32 5,120.00 1638.40
Sand Cum 0.445 650.00 289.25
10mm stone aggregate Cum 0.22 725.00 159.50
20mm stone aggregate Cum 0.67 725.00 485.75
Subtotal 2572.90 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.89 2868.53 2552.99
0 K.M. by Head Load Cum 0.89 390.34 347.40
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.45 2036.51 916.43
0 K.M. by Head Load Cum 0.45 390.34 175.65
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.32 723.70 231.58
0 K.M. by Head Load Tonne 0.32 230.04 73.61
Subtotal 4297.66 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 245.00 66.15
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 294.00 14.70
Mate Each 0.04 245.00 9.80
RATE ANALYSIS - 31
Providing & laying cement concrete 1:2:4, 20mm nominal size & curing complete for RCC work in: Suspended floor, roofs, landing and shelves and their
supports, balconies, beams, girders, bressumers and cantilever upto floor two level.
Details of Cost for 1 Cubic Meter
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 238
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 693.65 (C)
(A+B+C) 7564.21
Add for water charges @1.5% 7,564.21 1.50% 113.46
7677.67
Add 1% Labour cess 7,677.67 1.00% 76.78
Add GST 12.00% 921.32
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement6039.27 15% 905.89
Rs:- 9,581.66
Total
Gross Total
Cost for one cubic meter
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 239
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Material
Cement mortar 1:4
(1cement:4sand) Cum. 0.165 7,342.75 1211.55
Subtotal 1211.55 (A)
Labour :
Mason II nd class Each 0.80 294.00 235.20
Beldar Each 0.80 245.00 196.00
Bhishti Each 0.98 245.00 240.10
Sundries(Scaffolding etc.) L.S. 45.00
Subtotal 716.30 (B)
Total (A+B) 1927.85
Add for water charges @1.5% 1,927.85 1.50% 28.92
Gross Total 1956.77
Add 1% Labour cess 1,956.77 1.00% 19.57
Add GST 12.00% 234.81
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement745.22 15% 111.78
Cost for 10 square meter Rs:- 2,322.93
Cost of 1 Sqm. Rs:- 232.29
20 mm cement plaster in single coat on fair side f brick/stone masonry for interior plastering up to floor two level including arrises, internal rounded angles,
chamfers and/or rounded angles not exceeding 80mm in girth and finished even and smooth .
In cement mortar 1:4
Details of cost for 10 Sqm.
Desciption
RATE ANALYSIS - 32
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 240
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Material
Cement mortar 1:3
(1cement:3sand) Cum. 0.224 8,268.73 1852.2
Sand & Gravel Crushed stone graded from 6 mm to 12mm Cum. 0.1 725.00 72.5
Grounded hydrated lime Kg 9.28 100.00 928
Subtotal 2852.7 (A)
Labour :
Mason II nd class Each 1.71 294.00 502.74
Beldar Each 1.58 245.00 387.10
Bhishti Each 1.7 245.00 416.50
Sundries(Scaffolding etc.) L.S. 45.00
Extra labour for coping
Mason II nd class Each 0.25 294.00 73.50
beldar Each 0.25 245.00 61.25
Extra labour for dashing of crushed stone
Mason II nd class Each 0.5 294.00 147.00
beldar Each 0.5 245.00 122.50
RATE ANALYSIS - 33
Rough side exterior cement plaster on wall up to a height of 10 mtr. above ground level with a mixture of sand and gravel or crushed stone graded from 6mm
to 12 mm nominal size dashed over and including fresh plaster in two coats, backing coat 10 mm cement plaster 1:3 (1cement:3sand) and finishing coat 10
mm cement mortor 1:3 (1cement:3sand) mixed with 10 % finely grounded hydrated lime by volume of cement including arrises, chamfersb and/or rounded
angles not exceeding 80 mm in girth. (natural cement finish using ordinary cement)
In cement mortar 1:3
Details of cost for 10 Sqm.
Desciption
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 241
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
bhisti Each 0.1 245.00 24.50
sundries ( scaffolding etc.) 10.00
Subtotal 1790.09 (B)
Total (A+B) 4642.79
Add for water charges @1.5% 4,642.79 1.50% 69.64
Gross Total 4712.43
Add 1% Labour cess 4,712.43 1.00% 47.12
Add GST 12.00% 565.49
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement2860.23 15% 429.03
Cost for 10 square meter Rs:- 5,754.08
Cost of 1 Sqm. Rs:- 575.41
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 242
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.40 5,120.00 2048.00
Sand Cum 0.425 650.00 276.25
10mm stone aggregate Cum 0.28 725.00 203.00
20mm stone aggregate Cum 0.57 725.00 413.25
Subtotal 2940.50 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.85 2868.53 2438.25
0 K.M. by Head Load Cum 0.85 390.34 331.79
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.425 2036.51 865.52
0 K.M. by Head Load Cum 0.425 390.34 165.89
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.40 723.70 289.48
0 K.M. by Head Load Tonne 0.40 230.04 92.02
Subtotal 4182.95 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.28 245.00 68.60
Mason 1st Class Each 0.06 294.00 17.64
Mason 2nd Class Each 0.06 294.00 17.64
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 701.98 ( C)
Discription
Details of Cost for 1 Cubic Meter
RATE ANALYSIS - 34
Prov.& laying c.conc. 1:2:4 (1cement:2 sand:4 graded stone aggregate 20mm nominal size) & curing complete e/c cost of form work & reinforcement for RCC
work in wall i/c attached, buttresses, columns, pillasters ,their caps & bases & string courses etc. up to floor two level.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 243
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Total (A+B+C) 7825.43
Add for water charges @1.5% 7,825.43 1.50% 117.38
Gross Total 7942.81
Add 1% Labour cess 7,942.81 1.00% 79.43
Add GST 12.00% 953.14
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement5894.81 15% 884.22
Cost for one cubic meter Rs:- 9,859.60
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 244
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.40 5,120.00 2048.00
Sand Cum 0.425 650.00 276.25
10mm stone aggregate Cum 0.28 725.00 203.00
20mm stone aggregate Cum 0.57 725.00 413.25
Subtotal 2940.50 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
155 K.M. by Mechanical Transport Cum 0.85 2868.53 2438.25
0 K.M. by Head Load Cum 0.85 390.34 331.79
Carriage of Sand
106 K.M. by Mechanical Transport Cum 0.425 2036.51 865.52
0 K.M. by Head Load Cum 0.425 390.34 165.89
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.40 723.70 289.48
0 K.M. by Head Load Tonne 0.40 230.04 92.02
Subtotal 4182.95 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 245.00 66.15
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 294.00 14.70
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Extra for laying CC in RCC work due to delay etc.
RATE ANALYSIS - 35
P/L cement concrete 1:1.5:3 (1cement:2sand:4graded stone aggregate 20mm nominal size E/C cost of form work & reinforcement for rcc work in suspended
floor, roofs, landing & shelves & their support balconies, beams, girders, bressumers & cantilever up to floor two level.
Details of Cost for 1 Cubic Meter
Discription
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 245
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Labour for 1 Cum
Beldar Each 0.10 245.00 24.50
Bhisti Each 0.20 245.00 49.00
Mason 1st Class Each 0.04 294.00 11.76
Mason 2nd Class Each 0.04 294.00 11.76
Mate Each 0.04 245.00 9.80
Extra labour for lifting the material, Beldar Each 0.17 245.00 41.65
Subtotal 842.12 ( C)
Total (A+B+C) 7965.57
Add for water charges @1.5% 7,965.57 1.50% 119.48
Gross Total 8085.05
Add 1% Labour cess 8,085.05 1.00% 80.85
Add GST 12.00% 970.21
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement6037.05 15% 905.56
Cost for one cubic meter Rs:- 10,041.66
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 246
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.61 5,120.00 3123.20
Sand Cum 0.25 650.00 162.50
10mm stone aggregate Cum 0.342 725.00 247.95
20mm stone aggregate Cum 0.418 725.00 303.05
Subtotal 3836.70 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
0 K.M. by Mechanical Transport Cum 0.76 2868.53 2180.08
0 K.M. by Head Load Cum 0.76 390.34 296.66
Carriage of Sand
0 K.M. by Mechanical Transport Cum 0.25 2036.51 509.13
0 K.M. by Head Load Cum 0.25 390.34 97.59
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.61 723.70 441.46
0 K.M. by Head Load Tonne 0.61 230.04 140.32
Subtotal 3665.24 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.27 294.00 79.38
Mason 1st Class Each 0.05 294.00 14.70
Mason 2nd Class Each 0.05 245.00 12.25
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 0.00 0.00
Sundries L.S. 15.00
Extra for laying CC in RCC work due to delay etc.
RATE ANALYSIS - 36
P/L cement concrete of M30 grade (1:1:3) (1cement:1sand:3graded stone aggregate 20mm nominal size E/C cost of form work & reinforcement for rcc work
in suspended floor, roofs, landing & shelves & their support balconies, beams, girders, bressumers & cantilever up to floor two level. (Slab for For RCC GSR)
Details of Cost for 1 Cubic Meter
Discription
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 247
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Labour for 1 Cum
Beldar Each 0.10 245.00 24.50
Bhisti Each 0.20 245.00 49.00
Mason 1st Class Each 0.04 294.00 11.76
Mason 2nd Class Each 0.04 294.00 11.76
Mate Each 0.04 245.00 9.80
Extra labour for lifting the material, Beldar Each 0.17 245.00 41.65
Subtotal 791.65 ( C)
Total (A+B+C) 8293.59
Add for water charges @1.5% 8,293.59 1.50% 124.40
Gross Total 8417.99
Add 1% Labour cess 8,417.99 1.00% 84.18
Add GST 12.00% 1010.16
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement5294.79 15% 794.22
Cost for one cubic meter Rs:- 10,306.55
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 248
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty. Rate Amount
Materials
Cement Tonne 0.61 5,120.00 3123.20
Sand Cum 0.25 650.00 162.50
10mm stone aggregate Cum 0.342 725.00 247.95
20mm stone aggregate Cum 0.418 725.00 303.05
Subtotal 3836.70 (A)
Carriage :
Carriage of stone aggregate:-below 40mm.
0 K.M. by Mechanical Transport Cum 0.76 2868.53 2180.08
0 K.M. by Head Load Cum 0.76 390.34 296.66
Carriage of Sand
0 K.M. by Mechanical Transport Cum 0.25 2036.51 509.13
0 K.M. by Head Load Cum 0.25 390.34 97.59
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.61 723.70 441.46
0 K.M. by Head Load Tonne 0.61 230.04 140.32
Subtotal 3665.24 (B)
Labour :
Beldar Each 2.09 245.00 512.05
Bhisti Each 0.28 245.00 68.60
Mason 1st Class Each 0.06 294.00 17.64
Mason 2nd Class Each 0.06 294.00 17.64
Mate Each 0.04 245.00 9.80
Beldar for extra ramming Each 0.25 245.00 61.25
Sundries L.S. 15.00
Subtotal 701.98 ( C)
Discription
Details of Cost for 1 Cubic Meter
RATE ANALYSIS - 37
P/L cement concrete of M30 grade (1:1:3) (1cement:1sand:3graded stone aggregate 20mm nominal size) & curing complete e/c cost of form work &
reinforcement for RCC work in wall i/c attached, buttresses, columns, pillasters ,their caps & bases & string courses etc. up to floor two level. (Wall for For
RCC GSR)
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 249
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Total (A+B+C) 8203.92
Add for water charges @1.5% 8,203.92 1.50% 123.06
Gross Total 8326.98
Add 1% Labour cess 8,326.98 1.00% 83.27
Add GST 12.00% 999.24
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement5203.78 15% 780.57
Cost for one cubic meter Rs:- 10,190.05
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 250
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Unit Qty Rate Amount
Material:-
Mild Steel Bars Qtl. 1.00
Wastage @ 5% Qtl. 0.05
Total 1.05 Qtl. 1.05 4,500.00 4725.00 (A)
By Mech TransportK.M By Mechanical Transport Tonne 0.105 723.70 75.99
0 K.M ByHead load. Tonne 0.105 485.53 50.98
Subtotal 126.97 (B)
Labour:-
Black Smith Ist class Each 1.00 292.00 292.00
Beldar Each 1.00 245.00 245.00
Sundries LS 10.00
Subtotal 547.00 ( C)
Total (A+B+C) 5398.97
Add for water charges @1.5% 5,398.97 1.50% 80.98
Gross Total 5479.95
Add 1% Labour cess 5,479.95 1.00% 54.80
Add GST 12.00% 657.59
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Steel
754.95 15% 113.24
Cost per Qtl Rs:- 6,305.59
Cost per Kg Rs:- 63.06
RATE ANALYSIS - 38
Providing mild steel/tor steel reinforcement for RCC work includng bending binding and placing in position complete.
Detail of cost for 1 Qtl.
Description.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 251
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cement Mortar 1:4 ( 1CEMENT : 4SAND)
Sr.No Item Unit Qty. Rate Amount
Material
Cement Tonne 0.38 5,120.00 1,945.60
Sand Cum 1.07 650.00 695.50
Subtotal 2,641.10 (A)
Carriage
Carriage of Sand
106 K.M. by Mechanical Transport Cum 1.07 2036.51 2,179.07
0 K.M. by Head Load Cum 1.07 390.34 417.66
Carriage of Cement
50 K.M. by Mechanical Transport Tonne 0.38 723.70 275.01
0 K.M. by Head Load Tonne 0.38 230.04 87.42
Subtotal 2,959.16 (B)
Labour measuring,carrying, depositing and mixing
Beldar Each 0.9 245.00 220.50
Bhisti Each 0.08 245.00 19.60
Sundries L.S. 36.02
Subtotal 276.12 (C)
Total (A+B+C) 5,876.38
Add for water charges @1.5% 5,876.38 1.50% 88.15
Gross Total 5964.53
Add 1% Labour cess 5,964.53 1.00% 59.65
Add GST 12.00% 715.74
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement4018.93 15% 602.84
Cost for one cubic meter Rs:- 7,342.75
Details of cost for 1cum
RATE ANALYSIS - 39
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 252
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. Description. Unit Qty. Rate. Amount
Cement Mortar 1:3 ( 1CEMENT : 3SAND)
Sr.No Item Unit Qty. Rate Amount
Material
Cement Tonne 0.51 5,120.00 2,611.20
Sand Cum 1.07 650.00 695.50
Subtotal 3,306.70 (A)
Carriage
Carriage of Sand
0 K.M. by Mechanical Transport Cum 1.07 2036.51 2,179.07
0 K.M. by Head Load Cum 1.07 390.34 417.66
Carriage of Cement
0 K.M. by Mechanical Transport Tonne 0.51 723.70 369.09
0 K.M. by Head Load Tonne 0.51 230.04 117.32
Subtotal 3,083.14 (B)
Labour measuring,carrying, depositing and mixing
Beldar Each 0.9 245.00 220.50
Bhisti Each 0.08 245.00 19.60
Sundries L.S. 36.02
Subtotal 276.12 (C)
Total (A+B+C) 6,665.96
Add for water charges @1.5% 6,665.96 1.50% 99.99
Gross Total 6765.95
Add 1% Labour cess 6,765.95 1.00% 67.66
Add GST 12.00% 811.91
Add 10% C.P.and 5% Over head charges except on cost of store
issue items,such as Cement4154.75 15% 623.21
Cost for one cubic meter Rs:- 8,268.73
RATE ANALYSIS - 40
Details of cost for 1cum
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 253
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. No. Item of work Quantity Rate Unit Amount
1 Excavation in foundation trenches etc. in earth work lift upto 1.5 mtr.
stacking the excavated soil not more than 3 mtr. clear from the edge
of excavation and then returning the stacked soil in 15cm layers
when required into plinths sides of foundation etc. consolidating each
deposited layer by ramming and watering then disposing of all
surplus soil as directed within a lead of 20mtr. in soft & hard rock.
12 547.71 Per cum. 6572
2 Providing & laying cement concrete 1:4:8 in foundation & plinth. 0.9 7426.55 Per Cum. 6684
4 Providing & laying cement concrete 1:2:4, 20mm nominal size &
curing complete for RCC work in: Suspended floor, roofs, landing
and shelves and their supports, balconies, beams, girders,
bressumers and cantilever upto floor two level.
4.5 9581.66 Per Cum. 43117
5 Providing tor steel reinforcement for RCC work. 315.00 63.06 Per Kg. 19863
76236
Rate Anlysis - 41 Detail of cost for One chamber
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Constructing chamber for sluice valve with CI surface box 100mm top,160mm bottom & 180mm deep inside with chain lid & RCC top slab 1:2:4 mix
100mm thick & foundation concrete 1:4:8 mix & inside plastering with cement mortar 1:6 finished with a floating coat of neat cement including curing
complete. 1000x1000x1500mm. inside size with 400mm wall of stone masonry in cement mortar 1:6.
Total Rs. For one chamber
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 254
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. No. Item of work Quantity Rate Unit Amount
1 Excavation in foundation trenches etc. in earth work lift upto 1.5 mtr.
stacking the excavated soil not more than 3 mtr. clear from the edge
of excavation and then returning the stacked soil in 15cm layers when
required into plinths sides of foundation etc. consolidating each
deposited layer by ramming and watering then disposing of all surplus
soil as directed within a lead of 20mtr. in soft & hard rock.
3.97 547.71 Per cum. 2174
2 Providing & laying cement concrete 1:4:8 in foundation & plinth. 0.66 7426.55 Per Cum. 4902
3 Squared rubble masonry coursed with hard stone of approved quality
in cement mortar 1:6.
3.17 9721.25 Per Cum. 30816
4 Providing & laying cement concrete 1:2:4, 20mm nominal size &
curing complete for RCC work in: Suspended floor, roofs, landing
and shelves and their supports, balconies, beams, girders,
bressumers and cantilever upto floor two level.
0.23 9581.66 Per Cum. 2204
5 Providing tor steel reinforcement for RCC work. 21.00 63.06 Per Kg. 1324
6 20mm cement plaster in single coat on rough side of brick/stone
masonry for interior plastering in cement mortar 1:3
6.00 232.29 Per Sqmt. 1394
7 Cement concrete flooring 1:2:4 (1 cement:2 sand: 4 graded stone)
20mm nominal size with a floating coat of neat cement 40mm thick.
1.00 582.62 Per Sqmt. 583
43397
Rate Anlysis - 42 Detail of cost for One chamber
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Constructing chamber for sluice valve with CI surface box 100mm top,160mm bottom & 180mm deep inside with chain lid & RCC top slab 1:2:4 mix
100mm thick & foundation concrete 1:4:8 mix & inside plastering with cement mortar 1:6 finished with a floating coat of neat cement including curing
complete. 1000x1000x1500mm. inside size with 400mm wall of stone masonry in cement mortar 1:6.
Total Rs. For one chamber
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 255
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. No. Item of work Quantity Rate Unit Amount
1 Excavation in foundation trenches etc. in earth work lift upto 1.5 mtr.
stacking the excavated soil not more than 3 mtr. clear from the edge
of excavation and then returning the stacked soil in 15cm layers when
required into plinths sides of foundation etc. consolidating each
deposited layer by ramming and watering then disposing of all surplus
soil as directed within a lead of 20mtr. in soft & hard rock.
2.19 547.71 Per cum. 1199.48
2 Providing & laying cement concrete 1:4:8 (1 cement:4 sand 8 graded
stone aggregate 40mm nominal size) and curing complete excluding
cost of form work in:- foundation & plinth.0.36 7426.55 Per Cum. 2673.56
Providing & laying cement concrete 1:2:4, 20mm nominal size &
curing complete for RCC work in: 0.87 9,859.60 Per Cum. 8577.85
(a)foundation footintg basis of columns and like mass concrete.
(b)Columns pillar posts and struts upto floor two level. 0.57 9859.60 Per Cum 5619.97
4 Providing mild steel/Tor steel reinforcement for R.C.C. work including
bending, binding and placing in position complete upto floor two level.
Tor steel.141 63.06 Per Kg. 8890.88
Providing form work with steel plates 3.15mm thick welded with angle
iron in frame 30x30x5mm so as to give a fair finish including centring
shuttering strutting and propping etc., with wooden battens and
ballies, height of propping and centring below supporting floor to
ceiling not exceeding 4 meters and removal of the same for in-situ-
reinforced concrete and plain concrete work in:-
a)Foundation, footing, basis of columns etc., and mass concrete.3.2 291.46 Per Sqmt. 932.66
ABSTRACT OF COST
Construction of Bulk Water Supply to Shimla on River Sutlej near Shikrodi Dist. Shimla (HP).
Rate Anlysis - 43 SH:-Construction of RCC Anchor Block
3
5
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 256
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. No. Item of work Quantity Rate Unit Amount
b) Columns pillar posts and struts square, rectangular or polygonal in
plan. 2.97 492.17 Per Sqmt. 1461.74
29356.14Total Rs. In Lac.
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 257
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Sr. No Descrtiption QtyRate (Rs
Lakh)
Amount (Rs
Lakh)
A FOUNDATIONS
a)Transformer Foundation & Road cum
Rail Track1 8.76792 8.76792
b) EQUIPMENTS
I) Circuit Breaker 1 1.325626 1.325626
ii) Isolator with out Earth blade 2 0.511462 1.022924
iii) Multi Core Multi ratio Current
Transformers1 0.240074 0.240074
iv) Lightening Arrester 1 0.240074 0.240074
v) PTs 1 0.240074 0.240074
B Columns Foundation6 1.638766 9.832596
C Periphery Fencing1 5.239876 5.239876
D Cable Trenches1 6.99346 6.99346
E Fire Fighting Equipments1 3.39235 3.39235
F Spreading of Shingles1 0.524544 0.524544
Total 37.819518
SCHEDULE OF COST ANALYSIS OF CIVIL WORKS FOR 1 NO. TRANSFORMER BAY
66 kV SIDE (SINGLE BUS BAR)
Note- As per HPSDCL Superintending Engineer (Design,) Electrical System, HPSEBL, Hamirpur
(H.P.) ANNEXURE- H1 , ABOVR RATES ARE PROPOSED FOR ESTIMATE PURPOSE.
Rate Analysis -44
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 258
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Providing and laying & jointing in trenches of 762 mm dia pipe class API 5L X grade -65 Standard Prov. and fixing M.S.flanges ISI marked conforming to IS-6392-1972 table 28
with wall thickness 7.92 mm with standing test pressure 84 kg. per CM Square.plain end weight. pressure…………...N/mm2 welded on both sides of 762 mm dia ERW pipe class API 5LX grade 65
146.91 kg.per mtr.as per API code in a random length of 4 mtr to 7 mtr and jointing with M.S.flange with nuts,bolts and 3mm thick ferrado make gasket.The welding is to conform to IS-3138-1986 including
Detail of cost for 100 Rmt. welding bolting and Gasket complet as per API 5LX as per table 28 weight @ 30.51 each.
Description Unit. Qty. Rate. Amount. DETAIL OF COST FOR 1 JOINTS.
API Pipe 762 MM dia. = 100.00 Rmt. Sr No Description Unit. Qty. Rate. Amount.
Add 2% for bends. 2.00 Rmt. i Flanges as per Table 28
Sr No.Total :- 102.00 Rmt. Weight. @ 146.91 Kg. Kg. 14984.82 83.50 1251232.47 ii Weight of flange per pair. 2 61.02 Kg. Kg. 61.02 64.00 3905.28
1 Add for zinc coating Kg. 14984.82 32.50 487006.65 iii Nuts& bolts of size 52mmx367mm 24 Nos. per pair.
Total 1738239.12 iv wt @ 23%of flanges total wt. 24 x 14.03 Kg. 14.03 64.00 897.92
Add 18% GST. 312883.04 Total Rs:- 4803.20
Add 3 % Entry tex 52147.17 Add 12.36% Excise Duty 0.00
Add 0.5% for inspection charges. 8691.20 Total Rs:- 4803.20
Total:- 2598967.18 Add 18% GST 864.58
1460 Km by Mech Transport Kg. Tonne. 14.98 12870.01 192792.75 Add 3 % Entry tex 144.10
0.5 Km by head load Kg. Tonne. 14.98 339.85 5090.95 Add 0.5% for inspection charges. 24.02
v Gasket Each 1.00 1350.00 1350.00
vi Welding charges. One Layer Inner side & Two Layer in Outer Side
Cost for flanges of 762 mm dia as per table = 28 inner. 3.14 x 76.20 x 3 x 2 1435.61
(Rates as per detail attached) Pair. 1.00 19027.46 19027.46
welding of every pipe for 100 mtr length 18 joints by taking 5.5 mtr average length. outer 3.14 x 76.20 x 3 x 2 1435.61
Two Layer outer side of the pipe. Total 2871.22 P/CM. 2871.22 4.00 11484.88
18.18 x 3.14 x 4 CM. CM. 17401.31 4.00 69605.24 vi Carriage of flanges :-
Labour for laying (Detail of cost for 514 kg) Total Wt. 75.05 Kg. or. 0.08 Tonne.
Fitter 0.20 x 58.4 450 K.M.By Mechanical Transport. Tonne. 0.08 4072.91 305.67
Assistant Fitter. 0.20 x 58.4 0.5 K.M.By Head Load. Tonne. 0.08 339.85 25.51
Beldar. 1.60 x 400 Unloading and staking charges Tonne. 0.08 339.85 25.51
Sundries. LS. 10.00 Total Rs:- 19027.46
Total Rs:- 526.8 Add 10% C.P.&5% O.H.Charges i.e on R.s. 17994.77 2699.2155
1.02 excluding cost of taxes. Total Rs:- 21752.18
Cost for Kg. 15059.87 1.02 15361.07
Labour for jointing (Detail for 10 Joints.) Kg.
Plumber 0.30 x 78.60
Assistant Plumber 0.30 x 78.60
Beldar. 1.20 x 300.00
Sundries. LS. 10.00
Labour for 10 joints Rs:- 467.20
Labour per joints Rs:- 46.72 joint 18.18 46.72 849.45
3LP & epoxy Painting two or more coat in and out side of the pipe.
inner side. 3.14 x 0.75 x 0
Outer side 3.14 x 0.76 x 100
Sqm. 239.27 0 0.00
Hasion cloth wraping = 0.762 x 3.14 2.39 Sqm.
Clothe = 2.39 x 50.00 = 119.50
Bitumen = 2.39 x 2.00 = 4.78 20.00
Fuel wood = 5.57 x 5.00 = 27.85
Sundries.
Painter 0.072 x 262.00
Beldar. 0.20 x
Total Qty. 2.39 x 100 = 239.00 Sqm. 239.00 0.00 0.00
Add 12 % GST on labour 10297.89
Total 2911991.99
Add 10% C.P.& 5% over head charges except on taxes & painting i.e.on Rs. 379041.00
Cost for 100 Rmt. Rs:- 3291032.99
Cost for 1.00 Rmt. Rs:- 32910.33
18.86
250.00 50.00
2526940.00
10.00
Cost per Kg.Rs:-
15059.87
262.00
262.00
250.00
0.00
239.27
239.27
119.50
95.60
27.85
250.00
ANALYSIS OF RATES. -45 ANALYSIS OF RATES.
capable of with standing test
14984.82 30.51
14984.82
14984.82
76.20 17401.31
292.00
292.00
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 259
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Providing and laying & jointing in trenches of 762 mm dia pipe class API 5L X grade -65 Standard Prov. and fixing M.S.flanges ISI marked conforming to IS-6392-1972 table 28
with wall thickness 8.74 mm with standing test pressure 92 kg. per CM Square.plain end weight. pressure…………...N/mm2 welded on both sides of 762 mm dia ERW pipe class API 5LX grade 65
161.61 kg.per mtr.as per API code in a random length of 4 mtr to 7 mtr and jointing with M.S.flange with nuts,bolts and 3mm thick ferrado make gasket.The welding is to conform to IS-3138-1986 including
Detail of cost for 100 Rmt. welding bolting and Gasket complet as per API 5LX as per table 28 weight @ 30.51 each.
Description Unit. Qty. Rate. Amount. DETAIL OF COST FOR 1 JOINTS.
API Pipe 762 MM dia. = 100.00 Rmt. Sr No Description Unit. Qty. Rate. Amount.
Add 2% for bends. 2.00 Rmt. i Flanges as per Table 28
Sr No.Total :- 102.00 Rmt. Weight. @ 161.61 Kg. Kg. 16484.22 83.50 1376432.37 ii Weight of flange per pair. 2 61.02 Kg. Kg. 61.02 64.00 3905.28
1 Add for zinc coating Kg. 16484.22 32.50 535737.15 iii Nuts& bolts of size 52mmx367mm 24 Nos. per pair.
Total 1912169.52 iv wt @ 23%of flanges total wt. 24 x 14.03 Kg. 14.03 64.00 897.92
Add 18% GST. 344190.51 Total Rs:- 4803.20
Add 3 % Entry tex 57365.09 Add 12.36% Excise Duty 0.00
Add 0.5% for inspection charges. 9560.85 Total Rs:- 4803.20
Total:- 2859023.12 Add 18% GST 864.58
1460 Km by Mech Transport Kg. Tonne. 16.48 12870.01 212097.76 Add 3 % Entry tex 144.10
0.5 Km by head load Kg. Tonne. 16.48 339.85 5600.73 Add 0.5% for inspection charges. 24.02
v Gasket Each 1.00 1350.00 1350.00
vi Welding charges. One Layer Inner side & Two Layer in Outer Side
Cost for flanges of 762 mm dia as per table = 28 inner. 3.14 x 76.20 x 3 x 2 1435.61
(Rates as per detail attached) Pair. 1.00 19027.46 19027.46
welding of every pipe for 100 mtr length 18 joints by taking 5.5 mtr average length. outer 3.14 x 76.20 x 3 x 2 1435.61
Two Layer outer side of the pipe. Total 2871.22 P/CM. 2871.22 4.00 11484.88
18.18 x 3.14 x 4 CM. CM. 17401.31 4.00 69605.24 vi Carriage of flanges :-
Labour for laying (Detail of cost for 514 kg) Total Wt. 75.05 Kg. or. 0.08 Tonne.
Fitter 0.20 x 58.4 450 K.M.By Mechanical Transport. Tonne. 0.08 4072.91 305.67
Assistant Fitter. 0.20 x 58.4 0.5 K.M.By Head Load. Tonne. 0.08 339.85 25.51
Beldar. 1.60 x 400 Unloading and staking charges Tonne. 0.08 339.85 25.51
Sundries. LS. 10.00 Total Rs:- 19027.46
Total Rs:- 526.8 Add 10% C.P.&5% O.H.Charges i.e on R.s. 17994.77 2699.2155
1.02 excluding cost of taxes. Total Rs:- 21752.18
Cost for Kg. 16559.27 1.02 16890.46
Labour for jointing (Detail for 10 Joints.) Kg.
Plumber 0.30 x 78.60
Assistant Plumber 0.30 x 78.60
Beldar. 1.20 x 300.00
Sundries. LS. 10.00
Labour for 10 joints Rs:- 467.20
Labour per joints Rs:- 46.72 joint 18.18 46.72 849.45
3LP & epoxy Painting two or more coat in and out side of the pipe.
inner side. 3.14 x 0.74 x 0
Outer side 3.14 x 0.76 x 100
Sqm. 239.27 0 0.00
Hasion cloth wraping = 0.762 x 3.14 2.39 Sqm.
Clothe = 2.39 x 50.00 = 119.50
Bitumen = 2.39 x 2.00 = 4.78 20.00
Fuel wood = 5.57 x 5.00 = 27.85
Sundries.
Painter 0.072 x 262.00
Beldar. 0.20 x
Total Qty. 2.39 x 100 = 239.00 Sqm. 239.00 0.00 0.00
Add 12 % GST on labour 10481.42
Total 3193575.63
Add 10% C.P.& 5% over head charges except on taxes & painting i.e.on Rs. 415641.76
Cost for 100 Rmt. Rs:- 3609217.40
Cost for 1.00 Rmt. Rs:- 36092.17
18.86
250.00 50.00
0.00
2770945.08
10.00
Cost per Kg.Rs:-
16559.27
262.00
262.00
250.00
0.00
239.27
239.27
119.50
95.60
27.85
250.00
ANALYSIS OF RATES. -46 ANALYSIS OF RATES.
capable of with standing test
16484.22 30.51
16484.22
16484.22
76.20 17401.31
292.00
292.00
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 260
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Providing and laying & jointing in trenches of 762 mm dia pipe class API 5L X grade -65 Standard Prov. and fixing M.S.flanges ISI marked conforming to IS-6392-1972 table 28
with wall thickness 9.53 mm with standing test pressure 101 kg. per CM Square.plain end weight. pressure…………...N/mm2 welded on both sides of 762 mm dia ERW pipe class API 5LX grade 65
176.29 kg.per mtr.as per API code in a random length of 4 mtr to 7 mtr and jointing with M.S.flange with nuts,bolts and 3mm thick ferrado make gasket.The welding is to conform to IS-3138-1986 including
Detail of cost for 100 Rmt. welding bolting and Gasket complet as per API 5LX as per table 28 weight @ 30.51 each.
Description Unit. Qty. Rate. Amount. DETAIL OF COST FOR 1 JOINTS.
API Pipe 762 MM dia. = 100.00 Rmt. Sr No Description Unit. Qty. Rate. Amount.
Add 2% for bends. 2.00 Rmt. i Flanges as per Table 28
Sr No.Total :- 102.00 Rmt. Weight. @ 176.29 Kg. Kg. 17981.58 83.50 1501461.93 ii Weight of flange per pair. 2 61.02 Kg. Kg. 61.02 64.00 3905.28
1 Add for zinc coating Kg. 17981.58 32.50 584401.35 iii Nuts& bolts of size 52mmx367mm 24 Nos. per pair.
Total 2085863.28 iv wt @ 23%of flanges total wt. 24 x 14.03 Kg. 14.03 64.00 897.92
Add 18% GST. 375455.39 Total Rs:- 4803.20
Add 3 % Entry tex 62575.90 Add 12.36% Excise Duty 593.68
Add 0.5% for inspection charges. 10429.32 Total Rs:- 5396.88
Total:- 3118725.24 Add 12% GST 647.63
1460 Km by Mech Transport Kg. Tonne. 17.98 12870.01 231402.78 Add 3 % Entry tex 161.91
0.5 Km by head load Kg. Tonne. 17.98 339.85 6110.50 Add 0.5% for inspection charges. 26.98
v Gasket Each 1.00 1350.00 1350.00
vi Welding charges. One Layer Inner side & Two Layer in Outer Side
Cost for flanges of 762 mm dia as per table = 28 inner. 3.14 x 76.20 x 3 x 2 1435.61
(Rates as per detail attached) Pair. 1.00 19424.96 19424.96
welding of every pipe for 100 mtr length 18 joints by taking 5.5 mtr average length. outer 3.14 x 76.20 x 3 x 2 1435.61
Two Layer outer side of the pipe. Total 2871.22 P/CM. 2871.22 4.00 11484.88
18.18 x 3.14 x 4 CM. CM. 17401.31 4.00 69605.24 vi Carriage of flanges :-
Labour for laying (Detail of cost for 514 kg) Total Wt. 75.05 Kg. or. 0.08 Tonne.
Fitter 0.20 x 58.4 450 K.M.By Mechanical Transport. Tonne. 0.08 4072.91 305.67
Assistant Fitter. 0.20 x 58.4 0.5 K.M.By Head Load. Tonne. 0.08 339.85 25.51
Beldar. 1.60 x 400 Unloading and staking charges Tonne. 0.08 339.85 25.51
Sundries. LS. 10.00 Total Rs:- 19424.96
Total Rs:- 526.8 Add 10% C.P.&5% O.H.Charges i.e on R.s. 17994.77 2699.2155
1.02 excluding cost of taxes. Total Rs:- 22149.69
Cost for Kg. 35382.89 1.02 36090.55
Labour for jointing (Detail for 10 Joints.) Kg.
Plumber 0.30 x 78.60
Assistant Plumber 0.30 x 78.60
Beldar. 1.20 x 300.00
Sundries. LS. 10.00
Labour for 10 joints Rs:- 467.20
Labour per joints Rs:- 46.72 joint 18.18 46.72 849.45
3LP & epoxy Painting two or more coat in and out side of the pipe.
inner side. 3.14 x 0.74 x 0
Outer side 3.14 x 0.76 x 100
Sqm. 239.27 0 0.00
Hasion cloth wraping = 0.762 x 3.14 2.39 Sqm.
Clothe = 2.39 x 50.00 = 119.50
Bitumen = 2.39 x 2.00 = 4.78 20.00
Fuel wood = 5.57 x 5.00 = 27.85
Sundries.
Painter 0.072 x 262.00
Beldar. 0.20 x
Total Qty. 2.39 x 100 = 239.00 Sqm. 239.00 0.00 0.00
Add 12 % GST on labour 12785.43
Total 3494994.14
Add 10% C.P.& 5% over head charges except on taxes & painting i.e.on Rs. 454936.74
Cost for 100 Rmt. Rs:- 3949930.88
Cost for 1.00 Rmt. Rs:- 39499.31
250.00
ANALYSIS OF RATES. -47 ANALYSIS OF RATES.
capable of with standing test
17981.58 30.51
17981.58
17981.58
76.20 17401.31
292.00
292.00
10.00
Cost per Kg.Rs:-
35382.89
262.00
262.00
250.00
0.00
239.27
239.27
119.50
95.60
27.85
18.86
250.00 50.00
0.00
3032911.59
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 261
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Providing and laying & jointing in trenches of 762 mm dia pipe class API 5L X grade -65 Standard Prov. and fixing M.S.flanges ISI marked conforming to IS-6392-1972 table 28
with wall thickness 10.31 mm with standing test pressure 109 kg. per CM Square.plain end weight. pressure…………...N/mm2 welded on both sides of 762 mm dia ERW pipe class API 5LX grade 65
190.93 kg.per mtr.as per API code in a random length of 4 mtr to 7 mtr and jointing with M.S.flange with nuts,bolts and 3mm thick ferrado make gasket.The welding is to conform to IS-3138-1986 including
Detail of cost for 100 Rmt. welding bolting and Gasket complet as per API 5LX as per table 28 weight @ 30.51 each.
Description Unit. Qty. Rate. Amount. DETAIL OF COST FOR 1 JOINTS.
API Pipe 762 MM dia. = 100.00 Rmt. Sr No Description Unit. Qty. Rate. Amount.
Add 2% for bends. 2.00 Rmt. i Flanges as per Table 28
Sr No.Total :- 102.00 Rmt. Weight. @ 190.93 Kg. Kg. 19474.86 83.50 1626150.81 ii Weight of flange per pair. 2 61.02 Kg. Kg. 61.02 64.00 3905.28
1 Add for zinc coating Kg. 19474.86 32.50 632932.95 iii Nuts& bolts of size 52mmx367mm 24 Nos. per pair.
Total 2259083.76 iv wt @ 23%of flanges total wt. 24 x 14.03 Kg. 14.03 64.00 897.92
Add 18% GST. 406635.08 Total Rs:- 4803.20
Add 3 % Entry tex 67772.51 Add 12.36% Excise Duty 0.00
Add 0.5% for inspection charges. 11295.42 Total Rs:- 4803.20
Total:- 3377719.72 Add 18% GST 864.58
1460 Km by Mech Transport Kg. Tonne. 19.47 12870.01 250579.09 Add 3 % Entry tex 144.10
0.5 Km by head load Kg. Tonne. 19.47 339.85 6616.88 Add 0.5% for inspection charges. 24.02
v Gasket Each 1.00 1350.00 1350.00
vi Welding charges. One Layer Inner side & Two Layer in Outer Side
Cost for flanges of 762 mm dia as per table = 28 inner. 3.14 x 76.20 x 3 x 2 1435.61
(Rates as per detail attached) Pair. 1.00 19027.46 19027.46
welding of every pipe for 100 mtr length 18 joints by taking 5.5 mtr average length. outer 3.14 x 76.20 x 3 x 2 1435.61
Two Layer outer side of the pipe. Total 2871.22 P/CM. 2871.22 4.00 11484.88
18.18 x 3.14 x 4 CM. CM. 17401.31 4.00 69605.24 vi Carriage of flanges :-
Labour for laying (Detail of cost for 514 kg) Total Wt. 75.05 Kg. or. 0.08 Tonne.
Fitter 0.20 x 58.4 450 K.M.By Mechanical Transport. Tonne. 0.08 4072.91 305.67
Assistant Fitter. 0.20 x 58.4 0.5 K.M.By Head Load. Tonne. 0.08 339.85 25.51
Beldar. 1.60 x 400 Unloading and staking charges Tonne. 0.08 339.85 25.51
Sundries. LS. 10.00 Total Rs:- 19027.46
Total Rs:- 526.8 Add 10% C.P.&5% O.H.Charges i.e on R.s. 17994.77 2699.2155
1.02 excluding cost of taxes. Total Rs:- 21752.18
Cost for Kg. 36876.17 1.02 37613.69
Labour for jointing (Detail for 10 Joints.) Kg.
Plumber 0.30 x 78.60
Assistant Plumber 0.30 x 78.60
Beldar. 1.20 x 300.00
Sundries. LS. 10.00
Labour for 10 joints Rs:- 467.20
Labour per joints Rs:- 46.72 joint 18.18 46.72 849.45
3LP & epoxy Painting two or more coat in and out side of the pipe.
inner side. 3.14 x 0.74 x 0
Outer side 3.14 x 0.76 x 100
Sqm. 239.27 0 0.00
Hasion cloth wraping = 0.762 x 3.14 2.39 Sqm.
Clothe = 2.39 x 50.00 = 119.50
Bitumen = 2.39 x 2.00 = 4.78 20.00
Fuel wood = 5.57 x 5.00 = 27.85
Sundries.
Painter 0.072 x 262.00
Beldar. 0.20 x
Total Qty. 2.39 x 100 = 239.00 Sqm. 239.00 0.00 0.00
Add 12 % GST on labour 12968.21
Total 3774979.73
Add 10% C.P.& 5% over head charges except on taxes & painting i.e.on Rs. 491291.37
Cost for 100 Rmt. Rs:- 4266271.11
Cost for 1.00 Rmt. Rs:- 42662.71
250.00
ANALYSIS OF RATES. -48 ANALYSIS OF RATES.
capable of with standing test
19474.86 30.51
19474.86
19474.86
76.20 17401.31
292.00
292.00
10.00
Cost per Kg.Rs:-
36876.17
262.00
262.00
250.00
0.00
239.27
239.27
119.50
95.60
27.85
18.86
250.00 50.00
0.00
3275275.83
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 262
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Providing and laying & jointing in trenches of 762 mm dia pipe class API 5L X grade -65 Standard Prov. and fixing M.S.flanges ISI marked conforming to IS-6392-1972 table 28
with wall thickness 11.13 mm with standing test pressure 117 kg. per CM Square.plain end weight. pressure…………...N/mm2 welded on both sides of 762 mm dia ERW pipe class API 5LX grade 65
205.54 kg.per mtr.as per API code in a random length of 4 mtr to 7 mtr and jointing with M.S.flange with nuts,bolts and 3mm thick ferrado make gasket.The welding is to conform to IS-3138-1986 including
Detail of cost for 100 Rmt. welding bolting and Gasket complet as per API 5LX as per table 28 weight @ 30.51 each.
Description Unit. Qty. Rate. Amount. DETAIL OF COST FOR 1 JOINTS.
API Pipe 762 MM dia. = 100.00 Rmt. Sr No Description Unit. Qty. Rate. Amount.
Add 2% for bends. 2.00 Rmt. i Flanges as per Table 28
Sr No.Total :- 102.00 Rmt. Weight. @ 205.54 Kg. Kg. 20965.08 83.50 1750584.18 ii Weight of flange per pair. 2 61.02 Kg. Kg. 61.02 64.00 3905.28
1 Add for zinc coating Kg. 20965.08 32.50 681365.10 iii Nuts& bolts of size 52mmx367mm 24 Nos. per pair.
Total 2431949.28 iv wt @ 23%of flanges total wt. 24 x 14.03 Kg. 14.03 64.00 897.92
Add 18% GST. 437750.87 Total Rs:- 4803.20
Add 3 % Entry tex 72958.48 Add 12.36% Excise Duty 0.00
Add 0.5% for inspection charges. 12159.75 Total Rs:- 4803.20
Total:- 3636183.48 Add 18% GST 864.58
1460 Km by Mech Transport Kg. Tonne. 20.97 12870.01 269884.11 Add 3 % Entry tex 144.10
0.5 Km by head load Kg. Tonne. 20.97 339.85 7126.65 Add 0.5% for inspection charges. 24.02
v Gasket Each 1.00 1350.00 1350.00
vi Welding charges. One Layer Inner side & Two Layer in Outer Side
Cost for flanges of 762 mm dia as per table = 28 inner. 3.14 x 76.20 x 3 x 2 1435.61
(Rates as per detail attached) Pair. 1.00 19027.46 19027.46
welding of every pipe for 100 mtr length 18 joints by taking 5.5 mtr average length. outer 3.14 x 76.20 x 3 x 2 1435.61
Two Layer outer side of the pipe. Total 2871.22 P/CM. 2871.22 4.00 11484.88
18.18 x 3.14 x 4 CM. CM. 17401.31 4.00 69605.24 vi Carriage of flanges :-
Labour for laying (Detail of cost for 514 kg) Total Wt. 75.05 Kg. or. 0.08 Tonne.
Fitter 0.20 x 58.4 450 K.M.By Mechanical Transport. Tonne. 0.08 4072.91 305.67
Assistant Fitter. 0.20 x 58.4 0.5 K.M.By Head Load. Tonne. 0.08 339.85 25.51
Beldar. 1.60 x 400 Unloading and staking charges Tonne. 0.08 339.85 25.51
Sundries. LS. 10.00 Total Rs:- 19027.46
Total Rs:- 526.8 Add 10% C.P.&5% O.H.Charges i.e on R.s. 17994.77 2699.2155
1.02 excluding cost of taxes. Total Rs:- 21752.18
Cost for Kg. 38366.39 1.02 39133.72
Labour for jointing (Detail for 10 Joints.) Kg.
Plumber 0.30 x 78.60
Assistant Plumber 0.30 x 78.60
Beldar. 1.20 x 300.00
Sundries. LS. 10.00
Labour for 10 joints Rs:- 467.20
Labour per joints Rs:- 46.72 joint 18.18 46.72 849.45
3LP & epoxy Painting two or more coat in and out side of the pipe.
inner side. 3.14 x 0.74 x 0
Outer side 3.14 x 0.76 x 100
Sqm. 239.27 0 0.00
Hasion cloth wraping = 0.762 x 3.14 2.39 Sqm.
Clothe = 2.39 x 50.00 = 119.50
Bitumen = 2.39 x 2.00 = 4.78 20.00
Fuel wood = 5.57 x 5.00 = 27.85
Sundries.
Painter 0.072 x 262.00
Beldar. 0.20 x
Total Qty. 2.39 x 100 = 239.00 Sqm. 239.00 0.00 0.00
Add 12 % GST on labour 13150.61
Total 4054960.71
Add 10% C.P.& 5% over head charges except on taxes & painting i.e.on Rs. 527686.25
Cost for 100 Rmt. Rs:- 4582646.96
Cost for 1.00 Rmt. Rs:- 45826.47
250.00
ANALYSIS OF RATES. -49 ANALYSIS OF RATES.
capable of with standing test
20965.08 30.51
20965.08
20965.08
76.20 17401.31
292.00
292.00
10.00
Cost per Kg.Rs:-
38366.39
262.00
262.00
250.00
0.00
239.27
239.27
119.50
95.60
27.85
18.86
250.00 50.00
0.00
3517908.32
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 263
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Providing and laying & jointing in trenches of 762 mm dia pipe class API 5L X grade -65 Standard Prov. and fixing M.S.flanges ISI marked conforming to IS-6392-1972 table 28
with wall thickness 11.91 mm with standing test pressure 120 kg. per CM Square.plain end weight. pressure…………...N/mm2 welded on both sides of 762 mm dia ERW pipe class API 5LX grade 65
220.12 kg.per mtr.as per API code in a random length of 4 mtr to 7 mtr and jointing with M.S.flange with nuts,bolts and 3mm thick ferrado make gasket.The welding is to conform to IS-3138-1986 including
Detail of cost for 100 Rmt. welding bolting and Gasket complet as per API 5LX as per table 28 weight @ 30.51 each.
Description Unit. Qty. Rate. Amount. DETAIL OF COST FOR 1 JOINTS.
API Pipe 762 MM dia. = 100.00 Rmt. Sr No Description Unit. Qty. Rate. Amount.
Add 2% for bends. 2.00 Rmt. i Flanges as per Table 28
Sr No.Total :- 102.00 Rmt. Weight. @ 220.12 Kg. Kg. 22452.24 83.50 1874762.04 ii Weight of flange per pair. 2 61.02 Kg. Kg. 61.02 64.00 3905.28
1 Add for zinc coating Kg. 22452.24 32.50 729697.80 iii Nuts& bolts of size 52mmx367mm 24 Nos. per pair.
Total 2604459.84 iv wt @ 23%of flanges total wt. 24 x 14.03 Kg. 14.03 64.00 897.92
Add 18% GST. 468802.77 Total Rs:- 4803.20
Add 3 % Entry tex 78133.80 Add 12.36% Excise Duty 0.00
Add 0.5% for inspection charges. 13022.30 Total Rs:- 4803.20
Total:- 3894116.51 Add 18% GST 864.58
1460 Km by Mech Transport Kg. Tonne. 22.45 12870.01 288931.72 Add 3 % Entry tex 144.10
0.5 Km by head load Kg. Tonne. 22.45 339.85 7629.63 Add 0.5% for inspection charges. 24.02
v Gasket Each 1.00 1350.00 1350.00
vi Welding charges. One Layer Inner side & Two Layer in Outer Side
Cost for flanges of 762 mm dia as per table = 28 inner. 3.14 x 76.20 x 3 x 2 1435.61
(Rates as per detail attached) Pair. 1.00 19027.46 19027.46
welding of every pipe for 100 mtr length 18 joints by taking 5.5 mtr average length. outer 3.14 x 76.20 x 3 x 2 1435.61
Two Layer outer side of the pipe. Total 2871.22 P/CM. 2871.22 4.00 11484.88
18.18 x 3.14 x 4 CM. CM. 17401.31 4.00 69605.24 vi Carriage of flanges :-
Labour for laying (Detail of cost for 514 kg) Total Wt. 75.05 Kg. or. 0.08 Tonne.
Fitter 0.20 x 58.4 450 K.M.By Mechanical Transport. Tonne. 0.08 4072.91 305.67
Assistant Fitter. 0.20 x 58.4 0.5 K.M.By Head Load. Tonne. 0.08 339.85 25.51
Beldar. 1.60 x 400 Unloading and staking charges Tonne. 0.08 339.85 25.51
Sundries. LS. 10.00 Total Rs:- 19027.46
Total Rs:- 526.8 Add 10% C.P.&5% O.H.Charges i.e on R.s. 17994.77 2699.2155
1.02 excluding cost of taxes. Total Rs:- 21752.18
Cost for Kg. 39853.55 1.02 40650.62
Labour for jointing (Detail for 10 Joints.) Kg.
Plumber 0.30 x 78.60
Assistant Plumber 0.30 x 78.60
Beldar. 1.20 x 300.00
Sundries. LS. 10.00
Labour for 10 joints Rs:- 467.20
Labour per joints Rs:- 46.72 joint 18.18 46.72 849.45
3LP & epoxy Painting two or more coat in and out side of the pipe.
inner side. 3.14 x 0.74 x 0
Outer side 3.14 x 0.76 x 100
Sqm. 239.27 0 0.00
Hasion cloth wraping = 0.762 x 3.14 2.39 Sqm.
Clothe = 2.39 x 50.00 = 119.50
Bitumen = 2.39 x 2.00 = 4.78 20.00
Fuel wood = 5.57 x 5.00 = 27.85
Sundries.
Painter 0.072 x 262.00
Beldar. 0.20 x
Total Qty. 2.39 x 100 = 239.00 Sqm. 239.00 0.00 0.00
Add 12 % GST on labour 13332.64
Total 4334143.26
Add 10% C.P.& 5% over head charges except on taxes & painting i.e.on Rs. 563972.86
Cost for 100 Rmt. Rs:- 4898116.12
Cost for 1.00 Rmt. Rs:- 48981.16
250.00
ANALYSIS OF RATES. -50 ANALYSIS OF RATES.
capable of with standing test
22452.24 30.51
22452.24
22452.24
76.20 17401.31
292.00
292.00
10.00
Cost per Kg.Rs:-
39853.55
262.00
262.00
250.00
0.00
239.27
239.27
119.50
95.60
27.85
18.86
250.00 50.00
0.00
3759819.07
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 264
SHIMLA JAL PRABANDHAN NIGAM LIMITED Rate Analysis
Providing and laying & jointing in trenches of 762 mm dia pipe class API 5L X grade -65 Standard Prov. and fixing M.S.flanges ISI marked conforming to IS-6392-1972 table 28
with wall thickness 12.70 mm with standing test pressure 134 kg. per CM Square.plain end weight. pressure…………...N/mm2 welded on both sides of 762 mm dia ERW pipe class API 5LX grade 65
234.67 kg.per mtr.as per API code in a random length of 4 mtr to 7 mtr and jointing with M.S.flange with nuts,bolts and 3mm thick ferrado make gasket.The welding is to conform to IS-3138-1986 including
Detail of cost for 100 Rmt. welding bolting and Gasket complet as per API 5LX as per table 28 weight @ 30.51 each.
Description Unit. Qty. Rate. Amount. DETAIL OF COST FOR 1 JOINTS.
API Pipe 762 MM dia. = 100.00 Rmt. Sr No Description Unit. Qty. Rate. Amount.
Add 2% for bends. 2.00 Rmt. i Flanges as per Table 28
Sr No.Total :- 102.00 Rmt. Weight. @ 234.67 Kg. Kg. 23936.34 83.50 1998684.39 ii Weight of flange per pair. 2 61.02 Kg. Kg. 61.02 64.00 3905.28
1 Add for zinc coating Kg. 23936.34 32.50 777931.05 iii Nuts& bolts of size 52mmx367mm 24 Nos. per pair.
Total 2776615.44 iv wt @ 23%of flanges total wt. 24 x 14.03 Kg. 14.03 64.00 897.92
Add 18% GST. 499790.78 Total Rs:- 4803.20
Add 3 % Entry tex 83298.46 Add 12.36% Excise Duty 0.00
Add 0.5% for inspection charges. 13883.08 Total Rs:- 4803.20
Total:- 4151518.81 Add 18% GST 864.58
1460 Km by Mech Transport Kg. Tonne. 23.94 12870.01 308108.04 Add 3 % Entry tex 144.10
0.5 Km by head load Kg. Tonne. 23.94 339.85 8136.01 Add 0.5% for inspection charges. 24.02
v Gasket Each 1.00 1350.00 1350.00
vi Welding charges. One Layer Inner side & Two Layer in Outer Side
Cost for flanges of 762 mm dia as per table = 28 inner. 3.14 x 76.20 x 3 x 2 1435.61
(Rates as per detail attached) Pair. 1.00 19027.46 19027.46
welding of every pipe for 100 mtr length 18 joints by taking 5.5 mtr average length. outer 3.14 x 76.20 x 3 x 2 1435.61
Two Layer outer side of the pipe. Total 2871.22 P/CM. 2871.22 4.00 11484.88
18.18 x 3.14 x 4 CM. CM. 17401.31 4.00 69605.24 vi Carriage of flanges :-
Labour for laying (Detail of cost for 514 kg) Total Wt. 75.05 Kg. or. 0.08 Tonne.
Fitter 0.20 x 58.4 450 K.M.By Mechanical Transport. Tonne. 0.08 4072.91 305.67
Assistant Fitter. 0.20 x 58.4 0.5 K.M.By Head Load. Tonne. 0.08 339.85 25.51
Beldar. 1.60 x 400 Unloading and staking charges Tonne. 0.08 339.85 25.51
Sundries. LS. 10.00 Total Rs:- 19027.46
Total Rs:- 526.8 Add 10% C.P.&5% O.H.Charges i.e on R.s. 17994.77 2699.2155
1.02 excluding cost of taxes. Total Rs:- 21752.18
Cost for Kg. 41337.65 1.02 42164.4
Labour for jointing (Detail for 10 Joints.) Kg.
Plumber 0.30 x 78.60
Assistant Plumber 0.30 x 78.60
Beldar. 1.20 x 300.00
Sundries. LS. 10.00
Labour for 10 joints Rs:- 467.20
Labour per joints Rs:- 46.72 joint 18.18 46.72 849.45
3LP & epoxy Painting two or more coat in and out side of the pipe.
inner side. 3.14 x 0.74 x 0
Outer side 3.14 x 0.76 x 100
Sqm. 239.27 0 0.00
Hasion cloth wraping = 0.762 x 3.14 2.39 Sqm.
Clothe = 2.39 x 50.00 = 119.50
Bitumen = 2.39 x 2.00 = 4.78 20.00
Fuel wood = 5.57 x 5.00 = 27.85
Sundries.
Painter 0.072 x 262.00
Beldar. 0.20 x
Total Qty. 2.39 x 100 = 239.00 Sqm. 239.00 0.00 0.00
Add 12 % GST on labour 13514.29
Total 4612923.70
Add 10% C.P.& 5% over head charges except on taxes & painting i.e.on Rs. 600210.66
Cost for 100 Rmt. Rs:- 5213134.36
Cost for 1.00 Rmt. Rs:- 52131.34
250.00
ANALYSIS OF RATES. -51 ANALYSIS OF RATES.
capable of with standing test
23936.34 30.51
23936.34
23936.34
76.20 17401.31
292.00
292.00
10.00
Cost per Kg.Rs:-
41337.65
262.00
262.00
250.00
0.00
239.27
239.27
119.50
95.60
27.85
18.86
250.00 50.00
0.00
4001404.40
Yash Innovative Solutions LLPAurangabad, Maharashtra Executive Engineer SJPNL
Page - 265
DRAWINGS