Page 1: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Sherwood Park Subdivision

Neighborhood Street Repair

Project #841060.06

City of Topeka Half Cent Sales Tax Project April 21, 2020

Page 2: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Scope of Work

Start date: Mid-May; Completion Date: Late August

Timeline

This project will construct significant street

improvements in the Sherwood Park Addition. The

improvements will include Mill/Overlay, full depth

pavement replacement as needed and selected

curb/gutter replacement where warranted. Neither SW

29th Street nor Indian Hills Road are included in the

project.

Page 3: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Scope of Work Examples Curb and gutter replacement

Page 4: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Scope of Work Examples Full depth patch

Page 5: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Scope of work examples Mill and Overlay

Page 6: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Frequently Asked QuestionsNote: Not all of the information on these FAQ slides will apply to you. Please

check your location on the plan sheets below after the FAQ to see what work

is planned in front of your house, on your street and throughout your

subdivision.

Access During Construction Curb Replacement Phase -Access may be restricted but

on-street parking nearby will be available.

ADA Ramp Replacement Phase – Sidewalks closed.

Street Asphalt Mill and Overlay Phase – Access may be restricted but on-street parking nearby will be available.

Final Surfacing Phase – The area to be paved will be closed during daytime hours only.

Page 7: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Frequently Asked QuestionsPrivate Property Replacement

Driveways Rule – The City will NOT repair/replace

driveways or courtesy walks. Contact the contractor if

interested in hiring this work out.

Sprinklers Rule – The City will NOT be responsible for

the sprinkler system and will not repair/replace

damaged sprinkler systems. Where curb and gutter is to

be replaced, sprinkler heads in the right of way will be

removed and lines capped. The heads will be returned

to the owner. The homeowner may have their sprinkler

heads removed by a landscape company if they wish.

Page 8: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Frequently Asked QuestionsInformational Door Hangers

The contractor, from time to time, will place

informational sheets on your front door. Please keep an

eye out for these notices. The door hangers will provide

information regarding the work schedule at least 48

hours in advance of construction.

Page 9: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Frequently Asked QuestionsHow you can help

Contact the right person the first time

During construction, you can help plus get answers more

quickly tor your questions and concerns by contacting

first the project inspector or the contractor’s job

superintendent. The City’s Project Engineer is Keith at

368-3842.

Limit the amount of water from sprinklers, sumps

that may wet the subgrade

Please limit lawn watering when construction is in your

area. It is OK for you to manually sprinkle your yard,

however when excess water finds its way into the work

zone, the contractor may be delayed by wet subgrade.

Please be conscientious with watering to avoid

contractor delays.

Page 10: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Frequently Asked QuestionsHow you can help

Construction flagging – yours and ours

If you have a sprinkler system and if curb work is

planned adjacent to your property, you may want to

have a sprinkler company remove the heads next to the

curb, otherwise the contractor may do it during

construction. However, the contractor will not reinstall

sprinkler heads or piping when the project is completed.

Please mark the sprinkler head next to the curb.

Please do not remove utility flags and/or surveyor

stakes. They are necessary.

Page 11: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Frequently Asked Questions

How you can help

Reach out ahead of time

If you are expecting a delivery, service call, or repair

visit, you may want to alert the companies prior to

construction in your area. The contractor will help with

access when possible and will assist with mail delivery

and trash pick up. If you have a mowing or landscape

service, be sure to let them know, too.

Contact the inspector or contractor if you have specific

medical or mobility disability concerns that will require

special accommodations.

Page 12: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Drawings of planned work in

the Sherwood Park Subdivision

Page 13: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Close-up Graphic 1

Page 14: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Close-up Graphic 2

Page 15: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Graphic of the entire

project – Interactive Maps

Username: nyCyxyzPassword: c9yvg9NLink https://files.gbateam.com/?u=nyCyxyZ&p=c9yvg9N

Use the Link, Username and Password to access the maps.

Page 16: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Contact list

Contractor – Hamm Asphalt, Inc.

Project Manager – NAME – (785) XXX-XXXX

Project Superintendent – NAME – (785) XXX-XXXX

City of Topeka

Project Engineer - Keith Duncan, PE – 368-3842

Construction Inspection – City of Topeka

NAME, INSPECTOR – XXX-XXXX

Page 17: Sherwood Park Subdivision Neighborhood Street Repair...Scope of Work Start date: Mid-May; Completion Date: Late August Timeline This project will construct significant street improvements

Project Contacts

Contractor – Hamms, Inc.

Project Manager – NAME – (785) XXX-XXXX

Project Superintendent – NAME – (785) XXX-XXXX

City of Topeka

Project Engineer - Keith Duncan, PE – 368-3842

Construction Inspection – City of Topeka

NAME, INSPECTOR – XXX-XXXX