1
• 12 tables repaired
• 8 initially foreseen (T2+T4) + 4 repaired in addition (T6)
S.Evrard - EN-MEF 23.05.2012
Story-board (I)
2
1 Bunker assembly 2 shielding roof removal 3 service disconnection
4 table handling (see beam
tracks )
S.Evrard - EN-MEF 23.05.2012
Story-board (II)
3
5 spring removal
6 old motor removal
7 new motor installation
8 table back handling
S.Evrard - EN-MEF 23.05.2012
New hardware implemented on this worksite
1. PR537 crane made remotely controlled
2. Vision system deployed (10 cameras)
3. New remote controlled lifting jigs (1 and 2 hooks)
4. Inspection & Remote RP survey tool
5. On-line dosimetry
6. Improved communication means (headsets, audio conference during repair)
4
2
54 3
S.Evrard - EN-MEF 23.05.2012 5
XTAX table routing in TCC2
Dry run with dummy table routing accurately defined (X,Y,Z) and tested
T2
T4
T6
S.Evrard - EN-MEF 23.05.2012
Encountered challenging situations
Date début
Date fin Difficulté Solution
Ven 02/03 Ven 16/03 Personnel FSU et Altead pas conforme dosimétrie
Formation PCR et commande dosimètre en urgence
Lun 12/03 Ven 16/03 Vanne départ flexible cooling pas étanches
Pose de nouvelles vannes supplémentaires étanches + aspiration eau répandue au sol et stockage dans container 1m3
Mar 13/03 Palonnier automatique : 1 axe se coince lors de l’engagement ou lors du dégagement de façon aléatoire
Remplacement de deux boites d’axe automatique + tests concluants
Mer 11/04 Mer 11/04 Retrait moteur et accouplement compliqué sur table avale XTAX 042020
Chauffer au chalumeau l’accouplement et utilisation de vérin
Jeudi 12/04
Jeudi 12/04 Casse embouts vis pression clavette au remontage moteur
Pose pas de problème au démontage futur car retrait demi-coquille enlève toute pression sur clavette : laissé comme cela
Jeudi 12/04
Vendredi 13/04
Mauvais positionnement table T4 amont P0
Repositionnement coupelle voir doc recovery action
Jeudi 12/04
Vendredi 13/04
Vis interface grille cassée. Morceau coincé dans taraudage
Clamp ad hoc
Lundi 16/04
Mercredi 25/04
Depuis remise en eau XTAX T2 et T4 : fuite sur aimant MSN ligne H4 downstream XTAX
Isolement, décapotage aimant, remplacement joint défectueux
Mer 18/04 Mer 18/04 Retrait moteur et accouplement compliqué sur table avale XTAX 06
Arrache poulie utilisé
6
S.Evrard - EN-MEF 23.05.2012
Recovery action on 13/04/2012
‣During its removal, one cup housing the downstream right foot of the 043018 table felt down and must be repositioned.
‣Once re-installed, the table 043018 turned out to be misaligned by 4 cm at the level of the positioning grid system
‣Investigation on spare parts confirm our feeling of a wrong repositioning of the cup.
‣Decide an inspection on site
‣Dose rate estimate around 20 mSv/h shielding required
‣Shielding installation ( L shape 4 cm thick lead dose rate reduced to 2.3 – 2.7 mSv/h)
‣Removal of the felt down cup + 3 rollers & inspection of the 2 other cups
‣Replacement by spare parts
7
S.Evrard - EN-MEF 23.05.2012
Quality Assurance plan
‣One slip by repaired table
‣Who did what, when, how,…
‣Motor test report
‣Test in laboratory (motor only)
‣Test in the bunker (motor + gearbox)
‣Final test in place (motor + load, full range tested)
8
Operation Operateur Date Commentaire
Préparation électrique moteur
EN-STI J. Lendaro
Courant à vide : 4.2 Amesure par le variateur de fréquence avec câble de 250m
Montage accouplement moteur
EN-MEFA. Ebn RhamounS. Girod
Montage moteurEN-MEFA. Ebn RhamounS. Girod
23/03/2012Couple serrage Vis accouplement 25NmCouple serrage Vis fixation moteur 40 Nm
GraissageEN-MEFS. Evrard
23/03/2012 Capuchons absents
Test fonctionnel en place
EN-STIJ. Lendaro
26/03/2012
Test courant en chargeMontée : 4.5 ADescente : 4.2 AMesuré par le variateur de fréquence au BA80
Deconnexion hydraulique
S. Evrard EN-MEF 12/03/2012
Deconnexion electrique (Grille + moteurs)
J. Lendaro EN-STIM. Donze EN-STI
12/03/2012
Reconnexion hydraulique
S. Evrard EN-MEF 30/03/2012
Reconnexion electrique (Grille + moteurs)
C. Mitifiot EN-STIM. Donze EN-STI
29/03/2012
Photo accouplement :
H2 aval 021025
S.Evrard - EN-MEF 23.05.2012
Dosimetry stats
9
S.Evrard - EN-MEF 23.05.2012
Dosimetry stats
10
S.Evrard - EN-MEF 23.05.2012
Dosimetry stats
11
Motor repair procedure very well studied and optimised real dose <<<< estimates
Proximity intervention less optimised real doses = estimatesWays of improvement : cold cell or new connection design
S.Evrard - EN-MEF 23.05.2012
Dosimetry stats
12
Self-commitment of max 600 uSv/ person under control