setting up of a greenfield integrated steel plant of …€¦ · power plant which will utilize...
TRANSCRIPT
PRE-FEASIBILITY REPORT
ON
SETTING UP OF A GREENFIELD INTEGRATED STEEL PLANT OF 0.7 MTPA WITH CAPTIVE POWER PLANT OF 70 MW
TO
SPINTECH TUBES PRIVATE LIMITED
SEPTEMBER 2018
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
TABLE OF CONTENTS
Page
- i -
1 - EXECUTIVE SUMMARY...................................................1-1
2 - INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION...............................................................2-1
2.1 Identification of the Project and Project Proponent ............... 2-1
2.2 Brief Description of the Nature of the Project ....................... 2-2
2.3 Need for the Project and Its Importance to the Country ........ 2-3
2.4 Demand-Supply Gap, Imports vs. Indigenous production, Export possibility & Domestic/ Export Markets ............................................................................. 2-5
2.5 Employment Generation (Direct and Indirect) due to the Project ............................................................................... 2-8
3 - PROJECT DESCRIPTION.................................................3-1
3.1 Type of Project ................................................................... 3-1
3.2 Location ............................................................................ 3-1
3.3 Details of alternate sites considered and the basis of selecting the proposed site.................................................. 3-3
3.3.1 Suitability of the Site for Integrated Steel Plant................. 3-3
3.4 Size or Magnitude of Operation ........................................... 3-6
3.5 Layout ............................................................................... 3-6
3.6 Project Description with Process Details .............................. 3-6
3.6.1 Iron Ore Grinding Unit for Pellet Plant.............................. 3-7
3.6.2 Pellet Plant ..................................................................... 3-9
3.6.3 Direct Reduction (DR) Plant ........................................... 3-12
3.6.4 Sinter Plant................................................................... 3-12
3.6.5 Blast Furnace ............................................................... 3-15
3.6.6 Pig Casting Machine ...................................................... 3-18
3.6.7 Steelmelt Shop .............................................................. 3-18
3.6.8 Annual Production from SMS ......................................... 3-22
3.6.9 Major Equipment and Facilities...................................... 3-22
3.6.10 Rolling Mills .................................................................. 3-22
3.7 Briquetting Plant for Ferrochrome Production.................... 3-29
3.7.1 Ferro-Alloy Plant ........................................................... 3-30
3.7.2 Air Separation Plant ...................................................... 3-32
3.7.3 Captive Power Plant....................................................... 3-34
3.7.4 Raw Materials ............................................................... 3-37
3.8 Road Logistics for Raw Material Transportation ................. 3-40
3.9 Resource Optimization/Recycle & Reuse envisaged in the project ............................................................................. 3-41
3.10 Availability of Water and Power ......................................... 3-41
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
TABLE OF CONTENTS
(Continued)
Page
- ii -
3.10.1 Water............................................................................ 3-41
3.10.2 Power ........................................................................... 3-42
3.11 Waste Generation and Management................................... 3-43
3.11.1 Waste Water Management .............................................. 3-43
3.11.2 Solid Waste Management ............................................... 3-44
3.11.3 Air Pollution.................................................................. 3-45
3.12 Schematic representations of the feasibility drawing which give information of EIA purpose .............................. 3-47
4 - SITE ANALYSIS..............................................................4-1
4.1 Connectivity....................................................................... 4-1
4.2 Land Form, Land Use and Land Ownership ......................... 4-2
4.2.1 Land Use of Project site ................................................... 4-2
4.3 Topography ........................................................................ 4-2
4.4 Existing Infrastructure ....................................................... 4-4
4.5 Soil Characteristics ............................................................ 4-4
4.6 Climatic Conditions ............................................................ 4-5
4.7 Social Infrastructure Available ............................................ 4-6
5 - PLANNING BRIEF ...........................................................5-1
5.1 Planning Concept ............................................................... 5-1
5.2 Population Projection ......................................................... 5-1
5.3 Land use planning.............................................................. 5-2
5.3.1 Integrated Steel Plant ...................................................... 5-2
5.4 Assessment of Infrastructure Demand ................................. 5-3
6 - PROPOSED INFRASTRUCTURE .......................................6-1
6.1 Industrial Area (Processing Area) ........................................ 6-1
6.2 Residential Area (Non Processing Area) ................................ 6-1
6.3 Greenbelt........................................................................... 6-1
6.4 Social Infrastructure .......................................................... 6-2
6.5 Connectivity....................................................................... 6-2
6.6 Drinking Water Management............................................... 6-2
6.7 Drainage and Sewerage System........................................... 6-3
6.8 Industrial Waste Management............................................. 6-3
6.9 Solid Waste Management .................................................... 6-3
6.10 Power Requirement and Supply/Source ............................... 6-4
7 - REHABILITATION AND RESETTLEMENT..........................7-1
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
TABLE OF CONTENTS
(Continued)
Page
- iii -
8 - IMPLEMENTATION SCHEDULE AND COST ESTIMATE .......8-1
8.1 Implementation Schedule ................................................... 8-1
8.2 Capital Cost Estimate......................................................... 8-4
8.3 Annual Manufacturing Expenses......................................... 8-5
8.4 Annual Sales Reasilsation................................................... 8-5
8.4.1 Return on Investment (ROI) ............................................. 8-6
9 - ANALYSIS OF PROPOSAL................................................9-1
9.1 Financial and Social Benefits of the Project ......................... 9-1
TABLES
Table 2-1 - Forecasted capacity and demand of steel by 2030-31.......... 2-5
Table 2-2 - Major Market Segments - 2030 .......................................... 2-7
Table 3-1 - Evaluation of SiteS based on Multiple Indicators ................ 3-5
Table 3-2 - Major plant units and facilites........................................... 3-7
Table 3-3 - Design Basis of Pellet Plants ............................................. 3-9
Table 3-4 - Typical Analyses of Raw Materials for Pellet Production ...... 3-9
Table 3-5 - Analyses of Raw Materials ............................................... 3-12
Table 3-6 - Design Basis of Sinter Plants........................................... 3-13
Table 3-7 - Typical Analyses of Raw Materials for Sinter production ... 3-13
Table 3-8 - Design Basis of Blast Furnace ......................................... 3-16
Table 3-9 - Typical Raw Materials Analysis (Dry Basis) ...................... 3-16
Table 3-10 - Characteristics of Molasses and Hydrated Lime .............. 3-29
Table 3-11 - Briquette Characterisitcs............................................... 3-30
Table 3-12 - Specific Power Consumption for Ferro-Alloy ................... 3-31
Table 3-13 - Specific Consumption of Raw Materials (Dry Basis)......... 3-31
Table 3-14 - Purity and Pressure of Oxygen, Nitrogen and Argon ........ 3-33
Table 3-15 - Estimated Annual requirements of Major Raw Materials ................................................................ 3-38
Table 3-16 - Unitwise requirement of Water....................................... 3-42
Table 3-17 - Solid Waste Generation ................................................. 3-44
Table 4-1 - Land use of Core Area ....................................................... 4-2
Table 4-2 - Summarised Meteorological Data ....................................... 4-6
Table 5-1 - Land use Break-up of the Project Area ............................... 5-2
Table 8-1 - Capital Cost Estimate ....................................................... 8-4
Table 8-2 - Annual Manufacturing Expenses (At rated Capacity Level) ....................................................................... 8-5
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
TABLE OF CONTENTS
(Continued)
Page
- iv -
FIGURES
Fig. 3-1 - Site Location Map................................................................ 3-2
Fig. 3-2 - Google Map showing Location of the Project.......................... 3-3
Fig. 3-3 - Schematic Diagram for Steps of EIA ................................... 3-48
Fig. 4-1 - Site Connectivity ................................................................. 4-1
Fig. 4-2 - Topographic Map of the Proposed Steel Plant Site ................. 4-4
Fig. 8-1 - Implementation Schedule .................................................... 8-3
DRAWINGS
Drg 11485-97A-000-LTL-0001 - Plant General Layout Drg 11485-97A-000-PRS-0002 - Process Flow Diagram
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
1-1
1 - EXECUTIVE SUMMARY
Spintech Tubes Private Limited (STPL) is one of the flagships
Company of M/S Gagan Group, well known in eastern India for their
quality products viz. TMT bars, billets, ingots, sponge iron etc. Gagan
Group is one of the fastest growing steel making company in eastern
India, started as a manufacturing company for iron & steel products in
2000 in Durgapur, West Bengal under the name of Shakambhari
Overseas Trades Pvt. Ltd (SOTPL). SOTPL established an ingot
manufacturing plant with a capacity of 72,000 TPA in Durgapur, West
Bengal. Gagan group is multiplying its business in terms of sales &
production by setting up an integrated steel plant at Jamuria, West
Bengal.
As a result, Gagan Ferrotech Limited (GFL) started
manufacturing sponge iron at Jamuria Industrial Area, Ikra in Burdwan
district in 2007. Now, STPL being incorporated as Private Limited
Company on 14th February 2017, intends to set up 0.7 MTPA Integrated
Steel Plant (ISP) with captive power plant of 70 MW capacity in Dhasal,
Jamuria at Paschim Bardhaman in West Bengal with an objective to
expand its operation in eastern India.
The major production facilities envisaged for this integrated
iron and steel plant of STPL will comprise pellet plant, sinter plant, DR
plant, blast furnace, steelmelt shop, long product mills, structural mill
and wire drawing facility. Ferro-alloy plants have also been envisaged in
order to produce FeMn, SiMn and FeCr. The plant will have its captive
power plant which will utilize surplus blast furnace gas, waste heat off
gas of DR plant, in-plant char and purchased coal to produce power. The
plant will also have its captive air separation plant for producing oxygen,
nitrogen and argon required by various units.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 1 - Executive Summary (cont’d)
1-2
The following section presents a brief outline of the
Pre-feasibility report for the proposed plan for setting up of the
aforementioned proposed projects.
Project Profile - Hot Metal .. 0.367 MTPA - DRI .. 0.495 MTPA - Liquid Steel .. 0.729 MTPA - Semis .. 0.712 MTPA - Captive Power .. 70 MW
Products for Sale Pellet .. 0.300 MTPA Pig Iron .. 0.046 MTPA Wire Rods .. 0.219 MTPA TMT Bars .. 0.250 MTPA Plain Structural .. 0.100 MTPA TLT Structures (Galvanised TLT Section) .. 0.100 MTPA Drawn Wires .. 0.030 MTPA Ferro Alloys .. 0.036 MTPA
Location Dhasal, Bahadurpur & Mamudpur villages of Jamuria Block, Paschim Bardhaman District
Iron Ore Grinding Unit 1.186 MTPA
Pellet plant 1.13 MTPA
Sinter plant 0.62 MTPA
DRI plant (coal based) 0.495 MTPA
Blast furnace 0.367 MTPA
Submerged Arc Furnace 0.0466 MTPA Chrome Ore Briquetting Plant 0.041 MTPA
Steelmaking Shop (SMS) 0.729 MTPA
Caster Shop 0.712 MTPA
Mill 0.699 MTPA
Captive Power Plant 70 MW
Major Facilities with Production capacity
Air Separation Plant 180 TPD
Major Raw Materials Coke, anthracite, non-coking coal, iron ore fines, PCI coal, steam coal, lime stone, dolomite, chrome ore (lump & fines), manganese ore, quartzite
Water consumption 276 cu m/hr
Water Source Ajay River of approx 7 km distance & Asansol Municipal Corp.
Power source & requirement
Annual energy consumption - 851 X 106 kWh, sourced from captive generating units & India Power Corporation Limited
Land details Around 240 acres
Employment generation
Construction phase - Around 1,200-1,500 casual and contract workers,
Operation phase - Approximately 1,150 direct employment & another 4,000 indirect employment
Implementation Schedule
27 months from ‘Go-ahead’ date
Capital Cost Around INR 3,200 Crore
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 1 - Executive Summary (cont’d)
1-3
The proposed Greenfield project would generate employment
opportunities, enhance local income and contribute to applicable
government revenues. Consequently the growth of allied small-medium
scale industries, trade & commercial establishments and local
entrepreneurship may be envisaged.
The peripheral development activities that would be
undertaken by the proposed project under Corporate Environment
Responsibility (CER) will focus on marginal communities and attempt to
bring forward an overall socioeconomic development with special
emphasis in the areas of education, training, health and infrastructure.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
2-1
2 - INTRODUCTION OF THE PROJECT/BACKGROUND INFORMATION
2.1 IDENTIFICATION OF THE PROJECT AND PROJECT PROPONENT
Spintech Tubes Private Limited (STPL) is one of the flagship
companies of M/S Gagan Group, well known in eastern India for their
quality products viz. TMT bars, billets, ingots, sponge iron etc. Gagan
Group is one of the fastest growing steel making company in eastern
India, started as a manufacturing company for iron & steel products in
2000 in Durgapur, West Bengal under the name of Shakambhari
Overseas Trades Pvt. Ltd (SOTPL). SOTPL established an ingot
manufacturing plant with a capacity of 72,000 TPA in Durgapur, West
Bengal. Gagan group is multiplying its business in terms of sales &
production by setting up an integrated steel plant at Jamuria, West
Bengal. As a result, Gagan Ferrotech Limited (GFL) started
manufacturing sponge iron at Jamuria Industrial Area, Ikra in Burdwan
district in 2007. Now, STPL being incorporated as Private Limited
Company on 14th February 2017, intends to set up 0.7 MTPA Integrated
Steel Plant (ISP) with captive power plant of 70 MW capacity in Dhasal,
Jamuria at Paschim Bardhaman in West Bengal with an objective to
expand its operation in eastern India.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 2 - Introduction of the Project/Background Information (cont’d)
2-2
2.2 BRIEF DESCRIPTION OF THE NATURE OF THE PROJECT
The brief profile of the projects is as follows:
Iron Ore Grinding Unit .. 1.186 MTPA Pellet Plant .. 1.13 MTPA Sinter Plant (1 x 60 sq m) .. 0.62 MTPA DR Plant (3 x 500 tpd) .. 0.495 MTPA Blast Furnace (1 x 350 cum) .. 0.367 MTPA Steel Melt Shop .. 0.729 MTPA EAF (1 x 50 T) IF (4 x 25 T) LF (2 x 50 T) Caster Shop .. 0.712 MTPA Rolling Mill .. 0.7 MTPA Bar Mill .. 0.25 MTPA Wire Rod Mill .. 0.25 MTPA Structural Mill .. 0.2 MTPA Ferro Alloy Plant Submerged Arc Furnace .. 20,854 Ton (1 x 12 MVA - FeCr Plant) Submerged Arc Furnace .. 25,659 Ton (1 x 12 MVA) - FeMn Plant .. 20,391 Ton - SiMn Plant .. 5,268 Ton Captive Power Plant .. 70 MW Air Separation Plant .. 180 TPD Intermediate products
Hot Metal .. 0.367 MTPA DRI .. 0.495 MTPA Liquid Steel .. 0.729 MTPA Semis .. 0.712 MTPA Saleable products
Pellet .. 0.300 MTPA Pig Iron .. 0.046 MTPA Wire Rods .. 0.219 MTPA TMT Bars .. 0.250 MTPA Plain Structural .. 0.100 MTPA TLT Structures .. 0.100 MTPA (Galvanised TLT Section - 50,000 T) Drawn Wires .. 0.030 MTPA Ferro Alloys .. 0.036 MTPA
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 2 - Introduction of the Project/Background Information (cont’d)
2-3
This chapter describes the major facilities envisaged for this
project. The major production facilities envisaged for this integrated iron
and steel plant will comprise pellet plant, sinter plant, DR plant, blast
furnace, steelmelt shop, long product mills, structural mill and wire
drawing facility. Ferro-alloy plants have also been envisaged in order to
produce FeMn, SiMn and FeCr. The plant will have its captive power
plant which will utilize surplus blast furnace gas, waste heat off gas of
DR plant, in-plant char and purchased coal to produce power. The plant
will also have its captive air separation plant for producing oxygen,
nitrogen and argon required by various units.
The integrated steel plant would falls under Category ‘A’ of
item 3(a) “Metallurgical Industries (ferrous & non-ferrous)” of the
Schedule to the EIA Notification 2006 and amendments thereunder vide
Notification No. S.O 3067 (E) dated 1st December 2009under the
Environment (Protection) Rules 1986.
2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY
In 2016-17, production of crude steel in India was about
101.0 MTPA with a growth of approximately 10.5% over 2015. India’s per
capita steel consumption is 61 kg, much lower than the global average of
208 kg. The Government of India has set pragmatic target of achieving
per capita steel consumption of 160 kgs by 2030-31 requiring a crude
steel production of 255 MT and capacity of 300 MT.
Indian economy is rapidly growing with key focus on
infrastructure and construction sector. Several initiatives mainly,
affordable housing, expansion of railway networks, development of
domestic shipbuilding industry, opening up of defence sector for private
participation, and the anticipated growth in the automobile sector, are
expected to create significant demand for steel in the country.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 2 - Introduction of the Project/Background Information (cont’d)
2-4
Major factors which carry the potential of raising the per
capita steel consumption in the country are listed below:
i) Infrastructure improvement initiatives, such as ‘Smart
Cities project’, 'Housing for All by 2022', ‘Atal Mission for Rejuvenation and Urban Transformation (AMRUT)’
ii) Manufacturing growth driven by Make-in-India
initiative iii) Encouraging use of Made in India steel for various
projects and levying of anti-dumping duties on certain steel products from Brazil, Russia, China, Korea, Japan and Indonesia.
iv) National Mineral Development Corporation expected to increase the iron ore production favoring steel production
v) Emergence of the rural market for steel buoyed by projects like MGNREGS, development of ‘Rurban Clusters’ under the Shyama Prasad Mukherjee Rurban Mission, Pradhan Mantri Gram Sadak Yojana, among others.
As per the National steel policy (NSP) 2017, in order to
achieve expected demand of 300 MT and per capita consumption of
160 kg of finished steel by 2030-31, steel demand would need to grow at
a CAGR of around 7-7.5 per cent during the period against a CAGR of
3.5 per cent -4 per cent over the last 5 years. This would mean that
capacity additions planned by most of the major steel players need to
come on stream in next few years.
As per NSP 2017, it is aimed to domestically produce value
added steel- special steel and alloys and focuses on pelletisation based
on BF/DR- IF/EAF technology.
The concept of the proposed project is aligned with the
current progress plan of the country.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 2 - Introduction of the Project/Background Information (cont’d)
2-5
2.4 DEMAND-SUPPLY GAP, IMPORTS VS. INDIGENOUS PRODUCTION, EXPORT POSSIBILITY & DOMESTIC/ EXPORT MARKETS
Total consumption of finished steel was 83.5 MT in FY16.
Driven by rising infrastructure development, growing demand for
automotives and lower per capita consumption compared to international
average, steel consumption is expected to reach 104 MT by the end of
2017. World Steel Association (WSA) has projected a growth of Indian
steel consumption of 7.1% at 94.91 MT in 2018, one of the highest
growing among the global steel producers.
The projected demand and capacity as per NSP 2017 would
be is as shown in Table 2-1.
TABLE 2-1 - FORECASTED CAPACITY AND DEMAND OF STEEL BY 2030-31
Sl. No. Parameters
Projections (2030-31), MT
1 Total crude steel capacity 300 2 Total crude steel demand/production 255 3 Total finished steel demand/production 230 4 Per capita finished steel consumption, kg 158
The import vs export of steel for the last few years is
presented below:
Industry Steel Industry: Import vs Export, MT
2013-14 2014-15 2015-16 2016-17 2017-18 Total Finished
Steel 5.45 5.99 9.32 5.59 11.71 4.08 7.23 8.24 7.482 9.62
Source : Joint Plant Committee Website : Ministry of Steel
From the above table it can be seen that over the last few
years, the gap between imports and exports have gradually declined due
to various factors like increase in Minimum Import price &
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 2 - Introduction of the Project/Background Information (cont’d)
2-6
implementation of a more stringent anti-dumping policy and there has
been a net export of steel in the last financial year. The National Steel
Policy (NSP) 2017 aims to increase export of steel and reduce import by
2030-31. As of March 2017, the capacity utilisation of steel producers is
set to increase with strong export demand and signs of revival in
domestic sales.
Steel products find application in multifaceted sectors
mainly dominated by areas of infrastructure & transport. Among the
many drivers of demand, the following are having maximum influence in
triggering consumption of finished steel products like Bars & Rods,
Structural and Plates:
Product/Category Application
Bars & Rods
Infrastructure - House Building
Fasteners & Wires
Bright Bars
Industry
Structural Infrastructure - High rises
Industrial Construction
Plates
Infrastructure - Bridges
Railways - Wagons, Coaches, Tankers
Industrial Construction
Defence Sector
Energy - Boilers, Pressure Vessels, Penstocks
HR Products
Tube making industry
Railways - Wagon & Coach
Automobiles
Industrial Machinery
Galvanized products
& Ferro alloys
Automobiles – Body panels & structural
members
Electrical Appliances & machine
Electronic equipment
Construction – Building panels, equipment &
machinery
Metallurgical Industries
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 2 - Introduction of the Project/Background Information (cont’d)
2-7
The NSP 2017 provides an overview of the segmental
composition of the projected Indian market for the year 2030-31 with
quantitative estimates of the likely demand and their associated growth
rates adopted for the study. A summary of the leading segments of the
domestic market is furnished in the Table 2-2.
TABLE 2-2 - MAJOR MARKET SEGMENTS - 2030
Market Segments Demand
(Million Tons) % Share
Infrastructure (Project Construction)
90 39%
Construction (Real Estate & Buildings)
45 20%
Engineering & Fabrication 43 19%
Energy 11 5%
Automotive 10 4%
Sub-total (Major Segments) 199 87%
Other Segments (Railways, Ship Building, Defence, Gas Pipelines, Packaging etc.)
31 13%
Total 230 100%
Source: NSP 2017
Barring project construction, other ‘heavy-weight’ or steel
intensive market segments like building construction, engineering and
fabrication etc. need not necessarily grow at rates faster than those of
the other comparatively less steel intensive segments. The segments like
automotives, defence sector, ship building, and gas pipelines hold out lot
of promise for the future of steel demand with near double digit annual
growths.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 2 - Introduction of the Project/Background Information (cont’d)
2-8
2.5 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT
In the construction & operation phases of the proposed
projects, both direct & indirect deployment of local work force would be
facilitated.
With respect to the proposed Integrated Steel Plant, it is
estimated that there would be a requirement of around 1,200 to 1,500
casual and contract workers, during the phase of construction.
Subsequently in the operation phase, approximately 1,150 personnel
would be directly employed with another 4,000 of indirect employment.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
3-1
3 - PROJECT DESCRIPTION
3.1 TYPE OF PROJECT
The proposed greenfield project would comprise the
following:
Integrated Steel Plant of 0.7 MTPA rolled capacity via BF/DRI-IF/EAF-Caster route and rolled through wire rod, bar and structural mill. This also includes:
i)) Captive generation of 70 MW of power ii)) Air separation plant of 180 TPD capacity iii) Ferro Alloy plant to produce 46,600 TPA ferro-alloys
3.2 LOCATION
The proposed ISP would be sited in Dhasal, Jamuria at
Paschim Bardhaman in West Bengal. The project site is located within
23040’45” to 23041’21” North latitude and 87007’45” to 87008’22” East
longitude.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-2
FIG. 3-1 - SITE LOCATION MAP
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-3
FIG. 3-2 - GOOGLE MAP SHOWING LOCATION OF THE PROJECT
3.3 DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF SELECTING THE PROPOSED SITE
3.3.1 Suitability of the Site for Integrated Steel Plant
The site selection criteria for the proposed 0.7 MTPA
integrated steel complex have been established considering the following
major factors:
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-4
i) Availability of adequate land for installation of the units
ii) Availability of suitable infrastructure in terms of connectivity and grid power
iii) Proximity of the site from Ajay River as water source iv) Availability of iron ores due to proximity to the mineral
belts of Odisha v) Ease of raw materials acquisition and products
transportation vi) Availability of economical labour force vii) The site does not require any Rehabilitation &
Resettlement (R&R) issues viii) No eco-sensitive zone and no wild life corridor within
10 km radius of the Project area ix) The area does not come under the critically polluted
area as identified by CPCB and no polluted stretch of river nearby
x) Scope for regional development
Three sites were primarily selected for the proposed project:
i) Site A - Dhasal ii) Site B - Seikhpur iii) Site C - Borjora. The analysis of
various criteria for selecting the most suitable location is shown in
Table 3-1.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-5
TABLE 3-1 - EVALUATION OF SITES BASED ON MULTIPLE INDICATORS
Indicators Site A - DHASAL Site B - SEIKHPUR Site C - BORJORA
Village/Town Tehasil District
Dhasal, Bahadurpur Jamuria Paschim Bardhaman
Sekpur Jamuria Paschim Bardhaman
Borjora town Bankura Sadar Bankura
Availability of land
240 acres 22 acres 45 acres
Status of land availability
Purchased - 113 acres Under process of
acquisition - 127 acres i) Govt. land - 35 acres ii) Private land - 92 acres
Purchased - 22 acres Yet to purchase any land
Type/category of land
Single crop land, barren land and water body
Industrial land Under West Bengal Govt. Land Bank
Distance from the nearby Railway Stations
Ikrah - around 2 km Tapasi - around 1.5 km Jamuria - around 6.8 km
Ikrah - around 0.3 km Tapasi - around 6.7 km Jamuria - around 1.4 km
Durgapur Railway Station - About 8.3 km
Distance from the National Highway
Around 4.7 km from NH-2 & around 700 m from NH-60
Around 4.5 km from NH-2 & around 6.8 km from NH-60
Around 11.0 km from NH-2
Whether homestead involved
No No Yes
Requirement of R&R issues
No No Yes
Water source
Ajay river at a distance of around 7.3 km and Asansol Municipal Corporation (AMC)
Ajay river at a distance of around 8.7 km
Damodar river at a distance of around 5 km
Power availability
India Power Corporation Limited (IPCL) - Power Agreement is available
IPCL - Power Agreement to be made
Damodar Valley Corporation (DVC) - No power agreement is available
Proximity to the ecological sensitive zone
No No No
Raw material source & linkage
Possible source of major raw material (iron ores) is Joda - Barbil and Koira & Sundergarh mines region of Odisha
Possible source of major raw material (iron ores) is Joda - Barbil and Koira & Sundergarh mines region of Odisha
Possible source of major raw material (iron ores) is Joda - Barbil and Koira & Sundergarh mines region of Odisha
Conclusion
Most suitable due to availability of adequate land, water, power and suitable from logistics point of view
Acquired land is inadequate for the proposed steel plant
Available land is not meeting the requirement for setting up of steel plant
Hence, Site A i.e. Dhasal site would be selected for the
proposed project.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-6
3.4 SIZE OR MAGNITUDE OF OPERATION
The proposed project would include production of the
following saleable products:
i) 0.7 MTPA long rolled products ii) 0.3 MTPA pellets iii) 0.05 MTPA pig iron iv) About 0.036 MTPA ferro-alloys
3.5 LAYOUT
The plant general layout of the proposed ISP is shown in
Drg. 11485-97A-000-LTL-0001.
3.6 PROJECT DESCRIPTION WITH PROCESS DETAILS
The plant would be designed for a capacity of 0.7 MTPA
crude steel, which, would be cast into long products namely bars, wire
rods, structural sections, etc. for sale.
The proposed production of liquid steel and subsequent
rolling would be accomplished via Blast Furnace (BF)-Induction Furnace
(IF)-Electric Arc Furnace (EAF)-Caster route, followed by hot rolling for
production of long products.
The facilities at the production stage of 0.7 MTPA crude steel
are shown in Table 3-2.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-7
TABLE 3-2 - MAJOR PLANT UNITS AND FACILITES
Sl. No. Unit Facility
Production MTPA
1 Iron Ore Grinding Unit 1.2 MTPA 1.186
2 Pellet plant 1 x 1.13 MTPA 1.13
3 Sinter plant 1 x 60 sq. m 0.62
4 DRI plant (coal based) 3 x 500 TPD 0.495
5 Blast furnace 1 x 350 cum 0.367
6 Submerged Arc Furnace
1 x 12 MVA (FeCr), 1 x 12 MVA (FeMn, SiMn)
0.0466
7 Chrome Ore Briquetting Plant
1 x 10 TPH 0.041
8 Steelmaking Shop (SMS)
4 x 25 t IF 1 x 50 t LF
1 x 50 t EAF 1 x 50 t LF
0.729
9 Caster Shop Billet Caster - 1 x 3 strand Billet/Bloom Caster - 1 x 3 strand
0.712
10 Mill Bar mill - 1 x 0.25 MTPA Wire Rod Mill - 1 x 0.25 MTPA Wire drawing facility with 50% hot dip galvanizing - 0.03 MTPA Structural Mill with hot dip galvanizing - 1 x 0.2 MTPA
0.699
11 Captive Power Plant BF gas based - 10 MW DR kiln off gas based WHRB - 37.5 MW Char & Coal based AFBC boiler - 22.5 MW
70MW
12 Air Separation Plant 1 x 180 TPD 180 TPD
The production facilities would be adequately supported by
necessary auxiliary facilities such as raw materials unloading and
storage, proportioning of raw materials, electric power receiving and
distribution stations, various utility facilities, water treatment and
distribution system, etc.
The preliminary process flow sheet is shown in Drg.
11485-97A-000-PRS-0002. The following write-up lays down details of
the various process units.
3.6.1 Iron Ore Grinding Unit for Pellet Plant
The wet grinding unit of the 1.2 MTPA pellet plant is
designed to grind the iron ore fines of 62 to 63% Fe having top size
(-) 5 mm and to produce pellet feed material of size d80 (-) 45 microns.
The design basis is as follows:
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-8
Annual requirement of pellet feed, MTPA .. 1.2 Operating days per year .. 330 Operating hours per day .. 20
Based on the above assumptions, the annual operating
hours and rated throughput to the grinding system work out to around
6,600 and 182 ton per hour (tph) respectively.
The iron ore of top size (-)5 mm from the day bins will be
ground in one number of ball mill having capacity of 182 tph to the size
required for pelletization. The ball mill will be working in close circuit
with a set of classifying hydrocyclones. The overflow obtained from the
classifying hydrocyclones at size d80 45 microns will report to one
number concentrate thickener of around 22 m diameter for partial
dewatering. The clarified water obtained as overflow from the thickener
will be recycled back to the grinding system as process water. The
thickened slurry obtained as underflow from the thickener will be
pumped to two numbers pressure filter for final dewatering. The cake
obtained from the pressure filters having moisture content of 9 to 10%
will be conveyed to the pellet plant.
The list of major equipment for the overall plant is indicated
below:
i) Ball mill ii) Hydrocyclone clusters iii) Hydrocyclone feed pumps iv) Concentrate thickener
v) Concentrate thickener underflow pumps vi) Slurry holding tanks with agitator vii) Pressure filter feed pumps viii) Pressure filter process water pumps
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-9
3.6.2 Pellet Plant
It is envisaged to install one Pellet plant of capacity
1.13 MTPA to cater to the pellet requirement in DR kilns and mini blast
furnace (MBF) the additional 30,000 TPA pellet would be either sold off
or transferred to GFL plant.
The design basis considered for pellet plant is given in
Table 3-3.
TABLE 3-3 - DESIGN BASIS OF PELLET PLANTS
Parameters Value Requirement of pellet in MBF, tpy 94,100
Requirement of pellet in DR plant, tpy 737,600
Pellet for sale/inter-plant transfer, tpy 300,000
Total requirement of product pellet (>6 mm), tpy 1,131,700
Fines generation at pellet plant screen house(<6 mm), % 3
Annual generation of pellet fines, tpy 33,900
Gross pellet production, tpy 1,165,600
Operating days/year 330
The raw material (dry basis) and their typical analyses are
given in Table 3-4.
TABLE 3-4 - TYPICAL ANALYSES OF RAW MATERIALS FOR PELLET PRODUCTION
Fe,% SiO2,,% Al2O3,% CaO,% MgO,% LOI,% Pellet feed concentrate 62.50 3.25 3.10 - - 3.75
Bentonite 13.00 47.06 14.94 1.68 3.57 10.00
Dolomite 0.35 1.50 0.75 26.00 18.00 42.00
Limestone 0.56 1.55 1.65 48.00 2.70 41.00
Coal 0.50 3.50 1.75 0.23 0.13 91.00
Coke breeze 1.74 7.02 3.64 0.80 0.45 85.00
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-10
The indicative chemical analysis of pellet produced would be
as follows:
Fe, % .. 63.80 CaO/SiO2 ratio .. 0.15 CaO .. 0.60 SiO2 .. 3.90 Al2O3, % .. 3.40 MgO, % .. 0.17
Envisaged physical and metallurgical properties of pellet
would be as follows:
Size range, mm .. 6-18 Compressive strength, kg/pellet .. 250 Tumbling index: +6.3 mm, % .. 92 -500 micron, % .. 6
It is suggested that attainment of the above properties
should be ensured by adopting appropriate process parameters
established through necessary test work before implementation of the
project.
Filter cake, limestone, bentonite and coal fines will be stored
in separate bins. The materials from these bins will be drawn out in
requisite proportions and fed into high intensity mixer for thorough
mixing. Iron bearing dust collected by waste gas handling system and
plant dedusting system shall be recycled back to the mixer. Controlled
spray of water shall be provided for wetting the mix with approximately
8.5 to 9 per cent moisture.
The pre-wetted mixed material shall be transported by belt
conveyors to mixed material bins installed directly above the pelletising
discs. The wet-mix material shall be drawn from each bin into the disc
feeding chute via weigh feeder.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-11
Green pellets produced will be fed to a double deck roller
screen. While the sized green pellets are discharged across the width of
the traveling grate, the oversize and undersize factions are disintegrated
in a shredder and recycled to the plant.
Heat treatment of green pellet is carried out in the
induration furnace in stages comprising drying, pre-heating, induration
and cooling. Green pellets shall be dried and pre heated on the
travelling grate, hardened and indurated in the rotary kiln and cooled in
the annular cooler. The green pellets from the balling unit will be laid
across the full width of the chain grate. The green balls are dried and
preheated on the chain grate and pre-heating with exhaust gas from the
kiln and hot air from the cooler. The dried and preheated pellets from the
chain grate will be discharged to the rotary kiln for completion of
induration. After firing, fired pellets shall be cooled in a cooler. The
recuperated heat shall be utilised in the process by recycling the hot air
in drying and preheating zones.
The hardened and cooled pellets will be screened as per
requirement.
The pellet plant would comprise following facilities: i) Storage handling and preparation of coal, dolomite and
bentonite ii) Storage, Proportioning and mixing, Balling, induration
and cooling iii) Product pellet storage iv) Auxiliary facilities like fuel storage, laboratory, etc. v) Plant de-dusting system vi) Cranes, hoists and elevator vii) Plant electrics viii) Instrumentation and Level-1 ix) Plant communication system x) Utility system xi) Air-conditioning and ventilation system
xii) Fire fighting system
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-12
3.6.3 Direct Reduction (DR) Plant
For the production of Directly Reduced Iron (DRI),
3 x 500 TPD rotary kilns will be installed. The annual production from
all three numbers of kiln will be about 495,000 ton of DRI based on
300 days operation using iron ore pellets.
The rotary kiln charge will consist of iron ore pellets, non
coking coal and dolomite. The typical analyses of input raw materials
(dry basis) considered for DRI production is given in Table 3-5.
TABLE 3-5 - ANALYSES OF RAW MATERIALS
Fe,% SiO2,,% Al2O3,% CaO,% MgO,%
Pellet 63-64 3-4 3-4 0.5-1 0.1-0.2
Dolomite 0.35 1.50 0.75 26.00 18.00 FC,% Ash,% VM,% Non coking coal 52-54 22-24 23-25
Product DRI will contain about 86 per cent of Fe (total),
around 0.15 per cent carbon and the degree of metallization will be
about 90 per cent.
The facilities within the DR plant will comprise the following
major units:
i) Raw materials feeding system ii) Rotary kiln iii) Rotary cooler iv) Product (DRI) handling system v) Waste gas system
3.6.4 Sinter Plant
Sinter would constitute around 85% of the ferrous burden to
the blast furnaces. To meet the requirement of charge sinter one sinter
plant of around 60 sq m would be installed.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-13
The design basis considered for the sinter plant is given in
Table 3-6.
TABLE 3-6 - DESIGN BASIS OF SINTER PLANTS
Parameter Value Product sinter, tpy 623,000 Charge sinter, tpy 529,200 Screening at BF stock house, % 15 Operating days/year 330 Daily product sinter, tpd 1,886 No. of strand 1 Appx. suction area, sq m 60 Product sinter size, mm 5-50 Temperature of sinter at cooler discharge, oC
100
The raw material (dry basis) and their typical analyses are
given in Table 3-7.
TABLE 3-7 - TYPICAL ANALYSES OF RAW MATERIALS FOR SINTER PRODUCTION
Fe,
% SiO2,
% Al2O3,
% CaO,
% MgO,
% LOI,
%
Iron ore fines 62.50 3.25 3.10 0.09 0.06 3.50
Limestone 0.56 1.55 1.65 48.00 2.70 41.00
Coke breeze 1.74 7.02 3.64 0.80 0.45 85.00
Flue dust 36.30 9.75 1.55 6.20 1.60 37.50
Mill scale 69.50 1.23 1.22 0.68 0.25 5.00
Lime 0.00 3.0 2.50 83.00 3.20 4.00
Dolomite 0.35 1.50 0.75 26.00 18.00 42.00
The indicative chemical analysis of sinter produced would be
as follows:
Fe, % .. 54.64 CaO/SiO2 ratio .. 2.04 Al2O3, % .. 3.23
MgO, % .. 2.16
CaO, % .. 9.66
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-14
Envisaged physical and metallurgical properties of sinter
would be as follows:
ISO tumbler index (+6.3 mm) .. 76% (min) Reducibility index .. 65% (min) RDI (-3.15 mm) .. 28% (max) Sinter size range .. 5 to 50 mm Sinter mean size .. 18 mm
It is suggested that attainment of the above properties
should be ensured by adopting appropriate process parameters
established through necessary test work before implementation of the
project.
For various types of input materials, adequate number of
proportioning bins mounted on load cells to ascertain material level in
each bin and electronic weigh feeders under each bin will be provided to
draw required materials in proportions.
Mixing and nodulizing drum with internals and water
proportioning system for intimate mixing and nodulizing of sinter mix
will be provided for each sinter plant. Calcined lime will also be added
before entering to the mixing drum.
Sinter machine will be complete with hearth layer feeding
system, raw mix feeding system comprising anti segregation filling
method at the top of raw mix feed bin and drum feeder and segregation
device below it, ignition furnace, sinter breaker, crash deck, segregation
chute and the sinter strand proper comprising lifting wheel assembly,
lowering wheel assembly, support structure, sliding bars, thermal
compensation device, wind boxes with compensators, spillage chute, SG
iron pallet assembly with spring loaded sealing and high chrome grate
bar, lubrication system etc. Sintering will be performed during the
movement of the bed from ignition furnace to the discharge end.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-15
A suitable forced draft type circular cooler comprising
adequate number of fans, drives, cooler troughs, sealing etc will be
provided in order to discharge sinter below 100OC from cooler.
Waste heat recovery system from cooler for ignition furnace
combustion system and post heating of sinter bed will be optional for the
sinter machines.
Cooled sinter from sinter cooler will be fed to screening
system for separation of hearth layer material (10-20 mm), plant return
fines (0-5 mm) and product sinter (5-50 mm).
The sinter plant would comprise following facilities:
i) Proportioning system ii) Flux and fuel crushing iii) Mixing and nodulizing system iv) Sinter machine section v) Sinter cooler section vi) Sinter stabilizing section vii) Sinter storage and despatch viii) Waste gas system ix) Plant de-dusting system x) Cranes, hoists and elevator xi) Plant electrics xii) Instrumentation and Level-1 xiii) Plant communication system xiv) Utility system xv) Air-conditioning and ventilation system xvi) Fire fighting system 3.6.5 Blast Furnace
It has been envisaged that a mini blast furnace (MBF) of
350 cu m (useful volume, U.V.) will be installed for production of
367,500 ton of hot metal per year, out of which 58,900 tpy will be used
in induction furnaces and 259,400 tpy will be used in electric arc
furnace. Balance hot metal, i.e. 49,200 tpy will be cast in pig casting
machine. About 46,800 tpy of pig iron will be available for sale/inter
transfer.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-16
The blast furnace would incorporate all the modern
technological features. The design basis of blast furnace is given in
Table 3-8.
TABLE 3-8 - DESIGN BASIS OF BLAST FURNACE
Parameter Phase
Hot metal production, tpy 367,500 Daily production of hot metal, ton/day (avg.) 1,050 Useful volume, cu m (appx.) 350 Operating days 350 Burden: - Sinter, % 85 - Pellet, % 15 - Ore, % Nil O2 enrichment, % 4 Coke rate (including nut coke), kg/thm 465 PCI rate, kg/thm 100 Slag rate, kg/thm 400
The major raw materials for blast furnace comprise of sinter,
pellet, fluxes and coke. Pulverised coal will be injected through tuyeres
as auxiliary fuel. The typical analysis of raw materials envisaged is given
in Table 3-9.
TABLE 3-9 - TYPICAL RAW MATERIALS ANALYSIS (DRY BASIS)
Fe, % SiO2, % Al2O3, % CaO, % MgO, % Sinter 54.64 4.74 3.23 9.66 2.16
Pellet 63.8 3.90 3.4 0.60 0.17
Quartzite - 97.00 1.00 - -
Ash,% CSR CRI
Coke 12.50 62 25
Ash, % Fixed Carbon,%
PCI 15.00 70.00
The hot metal quality is expected to be as follows:
C, % .. 4.3 (max.) S, % .. 0.045 (max.) P, % .. 0.10 (max.)
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-17
The sinter from sinter plant, pellet, coke, quartzite etc. from
the raw material storage yard will be received on separate conveyors and
will be distributed to the stock house of blast furnace. The furnace will
be provided with conveyor belt charging system.
The furnace will be self-supporting free standing type. The
top equipment and platform at various levels around the furnace will be
supported by an independent tower structure. The blast furnace will be
provided with bell less top charging system and with modern facilities,
like above burden probe, heat flux and pressure profile measurement etc.
The cooling system will comprise of staves.
Automation and control system, which will include control of
hot blast temperature, charging etc., will be provided to take care of
smooth operation of blast furnace.
The blast furnace will be served by three internal combustion
chamber type stoves provided with ceramic burners to supply hot blast
at a temperature of about 11500C. The stoves will be fired with blast
furnace gas.
The blast furnace will be provided with one cast house,
having one taphole and one slag notch. Hydraulic mudgun & drilling
machine will be provided. One slag granulation system and dry slag pit
will be provided along with granulated slag handling system.
The plant comprises following facilities:
i) BF proper ii) Cast house iii) Slag granulation plant iv) Hot blast stoves v) Gas cleaning plant vi) Stock house and charging system
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-18
vii) Hot metal handling system viii) Cranes and hoists ix) Coal dust injection system x) Pig casting machine and ladle repair shop xi) Stockhouse and casthouse de-dusting system xii) Air blowing system xiii) Plant electrics xiv) Instrumentation, automation and control system xv) Communication system xvi) Water system xvii) Utility system xviii) Fire fighting system xix) Air conditioning and ventilation system
3.6.6 Pig Casting Machine
A double strand pig casting machine (PCM) of 2 x 700 tpd
capacity will be installed for production of pig iron. Necessary facilities
for preparation of lime wash required for coating the moulds will be
provided. Re-circulating water system for cooling of pigs including a
settling tank will be installed. Cold pig will be stored in pig storage yard
and further sold to the market/transferred internally.
3.6.7 Steelmelt Shop
Steelmelt shop will consist of Induction Furnace (IF), Electric
Arc Furnace (EAF), Ladle Furnace (LF), billet casting machine and billet
cum bloom casting machine with associated shop auxiliaries for
production of about 712,200 tpy of billet and blooms. The production of
liquid steel from induction furnaces will be around 288,000 tpy which
will be cast through billet caster to produce around 282,200 tpy of
billets. The production of liquid steel from electric arc furnace will be
around 441,000 tpy which will be cast through billet cum bloom caster
to produce around 235,900 billets and 194,000 tpy of blooms. However,
the liquid steel so produced by EAF and IF can be cast in either of the
casters as required. The billets so produced will cater to the wire rod and
bar mill whereas the blooms will cater to structural mill.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-19
Induction Furnace (IF) : It is proposed to install four
25-ton/12 MVA capacity IFs, with the combined heat size of
50 ton for this purpose, heats from two 25-ton IFs will be combined into
50 ton ladle for further processing. Any of the two induction furnaces out
of four Nos. will be operated in synchronized manner. The estimated
quantity of liquid steel from the IFs works out to be around 288,000 tpy
as per below basis.
Computation of annual production: No of furnaces .. 4 Capacity of IF .. 25 ton/12MVA Net operating days .. 320 Charge mix .. 68% DRI 17% Pig iron 15% scrap Tap-to-time, mins .. 160 Average number of heats/IF .. 9 Average number of heats/day from 4 IFs .. 36 Average number of heats/day after combining into 50 ton ladle .. 18 Liquid steel, ton/year .. 288,000 Major technical parameters are given as follows: No. of units .. 4 No. of crucibles .. 2/furnace Capacity .. 25 ton/12 MVA Metallic charge .. 68% DRI, 17% pig, 15% scrap
Electric Arc Furnace (EAF): In order to achieve the balance
liquid steel production, it is proposed to install one No. 50 ton/40 MVA
capacity EAF. The estimated quantity of liquid steel from the EAF works
out to be around 441,000 tpa as given below.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-20
Computation of annual production:
No of furnaces .. 1 Capacity of EAF .. 50 ton/40 MVA Number of operating days .. 315 Charge mix .. 50% hot metal 50% DRI Tap-to-Tap time, mins .. 52 Average number of heats/day/EAF .. 28 Liquid steel, ton/year .. 441,000
The salient features of the EAF are indicated below:
Number of furnaces .. 1, EBT type Furnace capacity .. 50 ton Furnace transformer .. 40 MVA Metallic charge, appx. .. 50% Hot metal, 50% DRI
Ladle furnace (LF): It is proposed to provide two Nos.
matching capacity LF i.e. 50 ton equipped with arc heating, inert gas
stirring and alloy addition facilities to treat the combined heats tapped
from two IFs simultaneously and heat tapped from EAF.
All the 46 heats coming from EAF and IFs can be
conveniently treated in two LFs with an average treatment cycle time
varying between 35 to 45 minutes per heat depending on the extent of
treatment required.
The relevant parameters of the LF are as follows:
No. of units .. 2 Nominal capacity, ton .. 50 Heating rate, deg C/min .. 4 to 5 Transformer rating, MVA .. 12 Type of unit .. Lift/lower roof type This unit will also be utilized to hold the heats for an
extended period of time, should it be necessary for any reason, such as,
sequencing of casting in CC machine, hold up in CC machine etc. All the
required features including both top and bottom rinsing, multi-strand
wire feeding, automatic temperature measurement and sampling
facilities will be provided.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-21
Billet Casting Machine: It is proposed to install
one 3-strand billet continuous casting unit in order to cast 288,000 tpy
of liquid steel produced from IFs. The caster will be designed to cast
100 mm, 130 mm and 160 mm sq billets. However, this caster will be
used to cast 100 mm sq and 130 mm sq billets as required by the wire
rod and bar mill. A casting time of 45 to 50 mins will be adopted to
match with the synchronized operation of two groups of IFs being
operated in staggered timing of 40 to 45 mins considering each IF
tap-to-tap time of 140 mins, thus making one combined 50 ton heat
available in every 50 mins to match a casting sequence of 2 heats.
One 3-strand billet caster will be able to cast the entire quantity of
288,000 tpa of liquid steel on the basis of casting 18 heats/day.
Assuming a yield of 98% from liquid steel to cast billets, the annual
quantity of billets will be 282,240 tpa.
The salient features of the billet caster are indicated below:
No. of machines .. 1 No. of strands .. 3 Type of machine .. Conventional billet
caster, radial bow type Mould .. Tubular mould Casting practice .. Open Ladle capacity, ton .. 50 Billet size, mm sq .. 100 to 160
Billet cum Bloom Casting Machine: It is proposed to install
one 3-strand billet cum bloom casting machine in order to cast the
envisaged liquid steel production. The caster will be designed to cast
130 mm-250 mm sq billets/blooms. A casting time of 48-50 mins is
adopted to match with EAF tap-to-tap time of 52 mins. One No. 3-strand
billet cum bloom caster will be able to cast the entire quantity of
441,000 tpa of liquid steel on the basis of casting 28 heats/day.
Assuming a yield of 97.5% from liquid steel to cast billets, the annual
quantity of billets will be 429,975 tpa.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-22
The salient features of the billet cum bloom caster are
indicated below:
No. of machine .. 1 No. of strands .. 3 Type of machine .. Conventional billet cum bloom caster, radial bow type Mould .. Tubular mould Casting practice .. open/closed Ladle capacity, ton .. 50 Billet/Bloom Size, mm sq .. 130 to 250
3.6.8 Annual Production from SMS
The annual production of SMS will be as below: Liquid steel, tpy .. 729,000 Semis, tpy .. 712,200
3.6.9 Major Equipment and Facilities
i) 4 x 25T/12 MVA IFs ii) 2 x 25T / 12 MVA LFs iii) 1 x 50T/40MVA EAF iv) IF & LF gas cleaning system v) EAF & LF gas cleaning system vi) Billet casting machine vii) Billet cum bloom casting machine viii) Raw Material handling system ix) Shop auxiliaries and maintenance facilities x) Shop cranes
3.6.10 Rolling Mills
Wire Rod Mill: The mill will be designed to produce of
0.25 MTPA wire rod. The input billet size will be as follows:
Section, sq mm .. 130x130, 160x160 Length, mm .. 6,000 Annual requirement, MTPA .. 0.26
Output from the mill will be as follows:
Wire rod, mm .. 5.5 to 16
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-23
Mill availability:
Calendar days .. 365
Maintenance (shutdown days .. 45 and holidays) No. of operating days per year .. 320 Yield:
Average Mill yield, % .. 96.5
The hot billets from the billet caster will be charged into
the induction furnace for temperature homogenization or cold billets
will be transferred from the cold charging grid through charging roller
table into the reheating furnace. The cold billets will be reheated to the
required rolling temperatures. The mill configuration will comprise
roughing stands, intermediate stands, finishing stands and finishing
block. The wire rods delivered from finishing block will pass through in-
line water cooling section, air cooling section, pinch roll and loop type
cooling conveyor system. The convoluted wire rod shall proceed to coil
reformers and down-enders and shall be loaded in conveyor. The coil
shall be compacted and tied by compacting machine, weighed by on-line
weighing machine, tagged and transferred to collecting tables.
Major equipment and facilities would be as follows:
i) Reheating furnace (For off-line charging of billets) ii) Induction furnace (For hot charging of billets) iii) Roughing stands iv) Intermediate stands v) Finishing stands vi) Finishing block vii) Water box cooling section viii) Loop cooling conveyor ix) Coil conveyor & tying station x) Weighing & collecting station
This mill will also be provided with roll and guide shop,
re-circulating water treatment facilities, laboratory etc.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-24
Rebar Mill: The mill is designed to produce of 0.25 MTPA
Rebar
The input billet size will be as follows:
Section, sq mm .. 130x130, 160x160 Length, mm .. 6000 Annual requirement, MTPA .. 0.26
Output from the mill will be as follows:
Rebar, mm .. 8 to 32
Mill availability:
Calendar days .. 365 Maintenance (shutdown days and holidays) .. 45 No. of operating days per year .. 320
Yield:
Average Mill yield, % .. 96.5
The hot billets from the billet caster will be charged into the
induction furnace for temperature homogenization followed by rolling
mill. The mill configuration will comprise roughing stands, intermediate
stands, and finishing stands. The bars delivered from finishing stands
will be passing through inline-water boxes cooling system. The finished
bars will be cut to cooling-bed lengths by dividing shears located
downstream of the water cooling lines. The cold shear placed after the
cooling bed will cut the bar layers into commercial lengths of 6 to 12 m.
Batches of finished length rebar will be transferred to the layer formation
area and automatic bar bundling stations which will count and sort the
rebars and form the bundles.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-25
Major equipment and facilities would be as follows:
i) Induction furnace (For hot charging of billets) ii) Roughing stands iii) Intermediate stands iv) Finishing stands v) Water box cooling section vi) Dividing Shear vii) Cooling bed viii) Cold shear ix) Layer formation area x) Weighing & collecting station
This mill will also be provided with roll and guide shop, re-
circulating water treatment facilities, laboratory etc.
Structural Mill: The mill is designed for production of
0.2 MTPA structural products. The mill will have the facility of
0.05 MTPA of Zn coated products.
Billets of 160 x 160 mm size from caster will be fed to the
induction furnace followed by rolling mill. Bloom sizes of 250 x 250 mm
will also be rolled and charged into the reheating furnace. The input
billet/bloom size will be as follows:
Section, sq mm .. 160x160, 250x250 Length, mm .. 6,000 Annual requirement, MTPA .. 0.210
Output from the mill will be as follows:
Equal Angles, mm .. 45x4/5 to 200x8/10/12 Unequal Angles, mm .. 45x30x4 and 45x30x5 ISMB, ISMC, Flats, mm .. 125, 150, 175, and 200
Mill availability:
Calendar days .. 365 Maintenance (shutdown days and holidays) .. 45 No. of operating days per year .. 320
Yield:
Average Mill yield, % .. 95
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-26
Input material (bloom/billet) from caster will be transferred
from the cold charging grid through charging roller table into the
reheating furnace. The input material which will be heated in the
reheating furnace will be rolled in Break-down mill, followed by 3-high
reversing mill. The mill will also be able to take billet directly from caster
which will be fed into the mill trough induction furnace. The mill
configuration will comprise Break-down mill, 3-high reversing roughing
stands, intermediate stands and finishing stands. The finished products
will be cut to the cooling-bed lengths by dividing shears. The material
after cooling bed is straightened in horizontal straightener. After
straightener the material will be cut in commercial length by cold saw.
After that the product will passes through magnetic stackers, bundling
and unloading station.
Major equipment and facilities would be as follows:
i) Reheating furnace (For off-line charging of billets) ii) Roughing stands iii) Break-down mill iv) Induction furnace (For hot charging of billets) v) Roughing stands vi) Intermediate stands vii) Finishing stands viii) Section cooling and diving shear ix) Cooling bed x) Multi-strand straightener xi) Cold Saw xii) Stacking section xiii) Strapping station xiv) Weighing and collecting station
This mill will also be provided with roll and guide shop, re-
circulating water treatment facilities, laboratory etc.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-27
Galvanizing Facility of TLT Sections: The galvanizing
facilities will be installed for processing structural products.
Product to be galvanized .. TLT section Capacity, MTPA .. 0.05
The size range of TLT section will be as follows:
Equal angles, mm .. 45x4/5 to 200x8/10/12 Unequal angles, mm .. 45x30x 4 and 45x30x5
Wire Drawing Facility: The wire drawing facility is designed
to produce 100 ton per day (tpd) of finished wires. The production will
consist of 50 tpd of galvanized wires and black wires each. Annually,
30,000 tpy of drawn wires will be produced out of which 15,000 tpy of
wires will be galvanized.
Wire rod coils will be directly fed to the pickling section
followed by wire drawing and galvanizing facilities. The input wire rod
size and other details will be as follows:
Dia., mm .. 5.5 to 8.0 Coil OD, mm .. 1250 Requirement, tpd .. 101.5 Steel Grade .. Mild steel
Output (Wires) sizes will be as follows:
Sl. No. Sizes 1. 20 gauge (0.81 mm)
2. 18 gauge (1.02 mm)
3. 14 gauge (1.63 mm)
4. 12 gauge (2.06 mm)
5. 10 gauge (2.65 mm)
Machine availability:
Calendar days .. 365 Maintenance (shutdown days and holidays) .. 45 No. of operating days per year .. 320
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-28
Yield:
Average yield, % .. 98.5
The processes involved in producing the wires of above
grades or quality from wire rods mainly consist of pickling,
rinsing, boraxing/phosphating (depending on product requirement),
drying, feeding, drawing, annealing or stress relieving, galvanizing
etc depending upon the sizes and types of wires to be finished.
All wire rods will be either pickled or passed through mechanical
descaler for scale removal before drawing. The wire rod coils will be
pickled in hydrochloric acid and rinsed in water. After water rinsing
lime or borax coating will be given, followed by drying in the baking oven.
Phosphating will be done for specific types of wires depending on the end
use envisaged for the processed wires. The pickled wire rods are drawn
to required size in multiple block continuous wire drawing machine
depending on the starting wire rod size and finished wire size.
The number of blocks required for drawing varies with the number of
passes to be given for producing the specific size of wire from wire rod
which in turn depends on the starting wire rod size, finished wire
size, grade of finished wire etc. Intermediate annealing or patenting
may be required to avoid work hardening. Facilities for galvanizing
have also been provided.
The wire drawing facilities will be complete with storage
yard, Effluent Treatment Plant (ETP), re-circulating water treatment
facilities, ECR, laboratory, die shop, electrical and mechanical
maintenance/workshop facilities, automation control rooms etc.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-29
3.7 BRIQUETTING PLANT FOR FERROCHROME PRODUCTION
Briquetting plant will be installed to produce about
41,200 ton of finished briquettes per year suitable for production of
ferrochrome. The plant will be designed based on the following
assumptions:
No. of working days per year .. 330 No. of working shifts per day .. 2 No. of working hours per shift .. 8
Based on the above assumptions, the effective annual
operating hours work out to 5,280 and the capacity of the briquetting
plant is estimated to around 10 ton per hour (tph).
Chrome ore fines of size (-) 7 mm will be fed to the plant. 6 to
7% molasses and 3 to 4% hydrated lime will be used as binders for
briquetting chrome ore fines. The characteristics of molasses and
hydrated lime proposed to be used in the plant are given in Table 3-10.
TABLE 3-10 - CHARACTERISTICS OF MOLASSES AND HYDRATED LIME
A. Molasses Specific gravity 1.4 Sugar content, % 50 Viscosity at 200/400 C (cP) 5500/800
B. Hydrated lime Ca (OH)2, % (min) 80 Size, d90 200 mesh Moisture, % (max.) 1 Bulk density 0.5-0.7
The product will be chrome ore briquettes suitable for
production of ferro-chrome in submerged arc furnaces. The
characteristics of the briquettes envisaged to be produced in the plant
are given in Table 3-11.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-30
TABLE 3-11 - BRIQUETTE CHARACTERISITCS
Briquette size, (L x B x H), mm 70 x 45 x 25 pillow shaped Bulk density of briquette 1.5-2.2 ton/cu m Angle of repose, degree 38 Compressive strength, N: - After pressing - After 24 hours
150 400
The run of mines (r.o.m.) chrome ore fines will be screened
at 7 mm and delivered to the briquetting plant by conveyor system. The
chrome ore fines will be fed to a rotary dryer for reducing the moisture
content to about 1 to 2 per cent for proper briquetting. The dried ore
from the rotary dryer will be stored in a storage bin. Hydrated lime will
be screened at 1 mm to separate the tramp oversize and will be stored in
a lime silo.
Dried chrome ore fines and hydrated lime drawn from the
respective storage bins will be intimately mixed in a Muller mixer.
Molasses will be added at controlled rate to the muller mixer and will be
mixed with ore-lime mixture.
The mixture will be fed to a briquetting machine. The
briquettes thus produced will be screened in a rubber deck vibrating
screen with 10 mm opening. The undersize from screen will be recycled
back to the mixer. The finished green briquettes obtained as oversize of
the screen will be delivered to a slow moving conveyor and stacked in a
new store house for complete curing to achieve the desired strength.
3.7.1 Ferro-Alloy Plant
In order to fulfill the internal requirement of ferrochrome
(FeCr), ferromanganese (FeMn), and silicomanganese (SiMn) in house and
for sale, it is proposed to install 2 x 12 MVA semi closed submerged arc
furnaces (SAF) with necessary facilities to produce 46,513 tpa
ferro-alloys comprising 20,854 tpy FeCr; 20,391 tpy FeMn and 5,268 tpa
SiMn.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-31
Operating days of the furnace has been considered as 350.
Different parameters of design basis considered for the plant are given in
Tables 3-12 & 3-13.
TABLE 3-12 - SPECIFIC POWER CONSUMPTION FOR FERRO-ALLOY
Specific Power Consumption SiMn FeMn FeCr
kWh/ton kWh/ton kWh/ton 3,800 2,700 3,600
TABLE 3-13 - SPECIFIC CONSUMPTION OF RAW MATERIALS (DRY
BASIS)
Specific Consumption(1) Raw Materials SiMn FeMn FeCr
kg/ton kg/ton kg/ton Chrome ore briquette - - 1,977 Cr chips - - 347 Mn ore 750 2,600 - FeMn slag 1,500 - - Quartzite 400 - 220 Coke 400 400 520 Magnesite - - 81 Dolomite - 30 71 Electrode paste 25 18 13
The likely analysis of ferro-chrome is indicated below:
C, % .. ~8 Cr, % .. 60-61 Fe, % .. 27-29 The likely analysis of ferro-manganese is indicated below:
C, % .. 6-8 Mn, % .. 65-70 Fe, % .. 24-26 The likely analysis of silico manganese is indicated below:
C, % .. 1-2 Mn, % .. 65-68 Si, % .. 18-21
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-32
The facilities within the ferro alloy plant will comprise the
following major units:
i) Reheating furnace ii) SAF iii) Furnace transformer iv) Furnace electrode assembly v) Furnace cover vi) Gas cleaning plant vii) Furnace tapping viii) Casting ix) Product separation and storage x) Weighing and collecting station
3.7.2 Air Separation Plant
To meet the requirement of industrial gases like oxygen,
nitrogen and argon for various process facilities, Cryogenic type Air
Separation Plant of 180 ton per day (tpd) capacity is envisaged to be
installed. The oxygen plant will have adequate liquid generation and
storage capacity so as to supply the gases for 72 hours in an event of
stoppage of ASP. Oxygen will be available at pressure levels of 40 kscg
which will be reduced to 16 kscg and 8 kscg through pressure reducing
station as per the need. Nitrogen will be available at pressure 20 kscg.
Argon will be available at pressure 10 to 12 kscg.
Buffer vessels and pressure reducing stations for oxygen,
nitrogen and argon will be provided to cater to various peak
requirements of the process.
Oxygen: Oxygen will be required mainly for EAF refining
operation, and heating, cutting operation in the caster and other general
purpose usage. Oxygen will also be required for enrichment of cold blast
to the stoves of the blast furnace. The hourly requirement of oxygen will
be around 4,270 N cu m/hr.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-33
Nitrogen: Nitrogen will be mainly required for gas cleaning,
cooling of the blast furnace bell-less top, PCI coal conveying, gas line
purging and general purpose along with instrumentation applications.
The hourly requirement of nitrogen will be around 1120 N Cum/hr.
Argon: Argon will be mainly required for ladle stirring,
tundish nozzle shrouding, etc. The hourly requirement of argon will be
around 40 N Cum/hr.
Pressure of product oxygen, nitrogen and argon will be
raised by internal compression without the need of booster compressor.
The purity and pressure of product oxygen, nitrogen and argon available
from the air separation plant are given in Table 3-14.
TABLE 3-14 - PURITY AND PRESSURE OF OXYGEN, NITROGEN AND ARGON
Medium Pressure Purity kscg % Oxygen 40 99.5 Nitrogen 20 99.99 Argon 10 to 12 99.999
The plant can be turned down to a level of 60% without any
change in the purity of the products.
The low pressure internal compression design is envisaged
for this 180 tpd air separation plant. The plant will consist of feed air
compressors, air pre-cooling and purification unit, heat exchangers and
expansion turbines, rectification column, hydrogen and acetylene
removal system, cryogenic pumping and purification facilities, pipework
etc.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-34
The cryogenic section of the air separation plant will be
designed for outdoor installation. A positive pressure inside the cold box
will be maintained by nitrogen to restrain the diffusion of air into the
cold box. The cold box will be designed for the prevention of explosions
from acetylene and other hydrocarbon accumulation.
The liquid oxygen, nitrogen and argon storage tanks will be
of double-walled construction. The annular space for liquid oxygen and
nitrogen tanks will be filled with non-inflammable insulating material
(perlite) and maintained under positive nitrogen pressure. For the argon
liquid storage tanks, the interspace is evacuated and filled with nitrogen.
3.7.3 Captive Power Plant
A Captive Power Plant of 70 MW capacity is envisaged. The
total power will be generated from BF gas fired boilers, Waste Heat
Recovery Boilers (WHRB) working on off gas of DR Plant, and coal and
char fired Atmospheric Fluidized Bed Combustion (AFBC) Boilers. About
10 MW of power will be generated from BF Gas fired boilers, 37.5 MW of
power will be generated from WHRB working on off gas of DR Plant and
22.5 MW power will be generated from char and purchased coal fired
AFBC Boilers. Five (5) Nos. 70 tph boilers, 2 x 35 MW turbo-generators
and other auxiliaries are envisaged.
The off gas from the DRI Kiln, will be utilized in a set of
WHRB for generation of high pressure steam. The steam thus generated
will be utilized for generation of electric power in turbine generator sets.
The non magnetics (char) from the DR Kiln, will be charged
in Atmospheric Fluidized Bed Combustion (AFBC) Boiler, along with
purchased coal for generation of high pressure steam.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-35
The BF Gas which is in excess after catering to the various
mill furnaces and stove heating will be burnt in gas fired boilers to raise
high pressure steam which in turn will be utilized in turbo-generators to
generate electric power.
All the boilers will raise steam at a fixed pressure and
temperature. The entire steam will be fed into a steam boiler. This will
carry the steam to the turbo-generator sets.
The excess power, after meeting the plant requirements, will
be exported to the external grid.
The power plant will have four WHRBs, two AFBC Boilers,
one gas fired boiler and two Turbo-generator (TG) sets of 35 MW capacity
each, along with other accessories. Each WHRB boiler will have a
normal capacity of 24.5 tons per hour and the normal capacity of the
AFBC boiler will be around 100 t/hr. The normal capacity of Gas fired
boiler will be 50 tph.
Waste Heat Recovery Boilers (WHRB): The major technical
parameters of WHRB are given below:
Type .. Single drum, natural circulation, multi-pass, semi-outdoor Number of WHRB .. 4 Normal continuous rating, ton/hr .. 24.5 Steam pressure at superheater .. 66 outlet, ksca Steam temperature at superheater .. 485+5 outlet, OC Feed water temperature at economiser outlet, OC .. 130 Inlet temperature of DR Kiln flue gas OC .. 900 Exit temperature of flue gas, OC .. 180
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-36
Atmospheric Fluidized Bed Combustion (AFBC) Boiler:
The major technical parameters of AFBC boilers are given below:
Steam output, max continuous rating (MCR), tph .. 100 Steam pressure at superheater outlet, ksca .. 6 Steam temperature at superheater outlet, OC .. 85 Feed water temperature at economiser inlet, OC .. 40 Exit temperature of the fuel gas, OC .. 60 Quanity of AFBC Boilers .. 2
Gas fired Boiler and Auxiliaries: There will be one gas
fired boiler of capacity 50 tph for burning of BF Gas and generation of
high pressure steam.
Type .. Single drum, natural circulation, multi-pass, semi-outdoor Number of gas fired boiler .. 1 Normal continuous rating, ton/hr .. 50 Steam pressure at superheater .. 67 outlet, ksca Steam temperature at superheater .. 540+5 outlet, OC Feed water temperature at economiser outlet, OC .. 130
Steam Turbine: The steam turbine will be of bleed cum
condensing type with two bleeds suitable for deaerator and LP heater for
feed water heating. The rated capacity of the turbine will be 35 MW as
measured at generator terminals. Major technical parameters of the
turbine are given below:
Type .. Single cylinder, multistage straight condensing machine Maximum rated capacity .. 35 x 2 of turbine, MW Steam conditions at turbine inlet
Pressure, ksca .. 67 Temperature, OC .. 535+5 No. of bleeds .. 2 (one for deaerator & one for LP heater) Condenser pressure, ksca .. 0.1 Circulating cooling water .. 34/42 temperature at inlet to condenser, OC
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-37
Steam turbine will be complete with auxiliaries like lube oil
system, governing system, condenser, condenser vacuum system,
condenser extraction pumps, condensate and feed water heating system
etc.
The major system/equipment in the power plant is given
below:
i) Waste Heat Recovery Boilers (WHRB) and its
auxiliaries ii) Atmospheric Fluidized Bed Combustion (AFBC) Boiler and its auxiliaries iii) Gas fired Boilers iv) Steam Turbo Generator (TG) and its auxiliaries v) Water system vi) Fire fighting system vii) Power generation, distribution and evacuation viii) Instrumentation and controls ix) Compressed air system x) Air conditioning & ventilation system xi) TG building crane
3.7.4 Raw Materials
Integrated Steel Plant: The estimated annual requirements
of major raw materials for the integrated steel plant are presented in
Table 3-15.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-38
TABLE 3-15 - ESTIMATED ANNUAL REQUIREMENTS OF MAJOR RAW MATERIALS
Sl. No.
Major Raw materials
Estimated Quantity,
tons Indicative
Analysis, % Likely source Mode of
transport
1 Coke 219,920 FC - 90 Merchant cokery in
India/abroad Rail/Sea/
Road
2 Anthracite 18,384 Ash - 9 VM - 4 FC - 87
International market Sea
3 Non coking Coal
400,950 Ash - 23 VM - 24 FC - 53
International market Sea/Rail/ Road
4 Iron ore fines 1,597,228 Fe - 62.0-63.0 SiO2 - 3.0-3.5 Al2O3 - 3.0-3.2 LOI - 3.5-4.0
Procured from the Joda-Barbil and Koira & Sundargarh mines region, Odisha
Rail/Road
5 PCI coal 36,750 Ash - 10-15 VM - 15-20 FC - 71
International market Sea
6 Limestone 73,287 SiO2 - 1.55 Al2O3 - 1.65 CaO - 48 MgO - 2.7 LOI - 41
Purchased from mines in Sundergarh district, Odisha or quarries in Jukehi-Katni-Niwar area in Central India
Rail/Road
7 Calcined lime 48,132 CaO Domestic Rail/Road
8 Dolomite 82,698 SiO2 - 1.6 Al2O3 - 0.6 CaO - 28 MgO - 19 LOI - 45
Purchased from mines in Sundergarh district, Odisha & Baradwar regions in Chattisgarh
Rail/Road
9 Chrome Ore Fines
37.106 Cr2O3 - 46-49 FeO - 17-19 SiO2 - 2-4 Al2O3 - 10-11
Procured from the mines in Sukinda regions, Odisha
Rail/Road
10 Chrome Ore lump
7,236 Cr2O3 - 50-51 FeO - 18-19 SiO2 - 3-4 Al2O3 - 11-12
Procured from the mines in Sukinda regions, Odisha
Rail/Road
11 Manganese Ore
56,968 Mn - 45-47 SiO2 - 6-8 Al2O3 - 4.3-6.3
Procured from the mines of Manganese Ore India Limited (MOIL) in MP & Odisha.
Rail/Road
12 Steam coal 143,416 FC - 40-45 Ash - 40-45 S - 0.4-0.5
Domestic Rail/Road
13 Bentonite 11,724 Fe - 13.0 SiO2 - 47.0 Al2O3 - 15.0 MgO - 3.6 LOI - 10.0
International market Sea/Rail/ Road
14 Quartzite 21,395 SiO2 - 97.0 Al2O3 - 1.0
Procured from Chaibasa, Ranchi and Hazaribagh areas of Jharkhand
Sea/Rail)/ Road
Apart from the major raw materials mentioned below, other
materials like hydrated lime, molasses, quartz fines, electrode paste,
fluorspar, zinc would also be required.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-39
Raw Material handling & Storage system: Raw materials
(viz. ore fines, non coking coal, purchase coke and flux) will be received
in plant by road through trucks from various sources. The raw materials
will be unloaded directly to stockyard. Roads all around the pile has
been considered for to and fro movement of trucks for the same.
The raw materials hence received will be stacked in regular
piles with excavator or payloader. Iron ore fines required for Pellet plant
and Sinter plant will be stored in same piles. PCI coal will be unloaded
and stored in the within the blast furnace area. Raw materials required
for ferro-chrome plant will be unloaded and stored separately in the
vicinity of plant.
There will be two weighbridges for incoming materials and
one weighbridge for dispatch of finished products, slags etc. for weighing
of trucks.
List of major facilities of raw material handling system is
presented in below.
i) Road weigh bridge ii) Flux crusher iii) Coal crusher (non coking coal) iv) Vibrating screen v) Coke screen vi) Coke breeze crusher vii) Rod gate viii) Rack and pinion gate ix) Flap gate x) Vibrating feeder xi) Belt scale xii) Sampler xiii) Metal detector xiv) Magnetic separator xv) Belt scale xvi) Reversible shuttle conveyor xvii) Belt feeder xviii) Belt conveyors xix) Hoist xx) Dust suppression system
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-40
3.8 ROAD LOGISTICS FOR RAW MATERIAL TRANSPORTATION
Road logistics has been considered for transportation of raw
materials required for the proposed plant. Gagan Ferro Tech Limited
(parent company of STPL) is located in the vicinity of the proposed plant
site. It is served by a railway siding at Topsia for handling iron ore and
another railway siding at Asansol for handling coke & coal. The same
railway sidings are envisaged to cater to the requirement of the proposed
plant.
Around 2.8 MTPA of raw material would be transported by
road (NH-60) to the plant. About 0.75 MTPA of coke & coal would be
received at Asansol siding and 1.9 MTPA at Topsia siding. The balance
would be transported by road from the nearest sea port and/or local
market. Considering dumpers of 20 T capacity, it is estimated that
400 nos. dumpers would be required per day i.e. 20 dumpers/hour. The
above estimated dumper movement will be accommodated conveniently
as planned for plant logistics.
Considering installation of railway yard within the plant,
total incoming rakes would be three Nos. per day, i.e. two rakes from
Topsia and one rake from Asansol. In order to accommodate all three
rakes, three railway tracks would be required along with one additional
track for engine escape line and two wagon tipplers. The total length of
the yard would be around 2.0 km. Adequate space for providing the
above mentioned yard is not available within the plant. Also, future
expansion of the plant is not envisaged.
In view of the above, road logistics for raw material
transportation has been found suitable and railway yard has not been
considered. However, adequacy study regarding the capacity of existing
railway sidings and traffic load study for NH-60 would be carried out to
ensure sufficient handling capacity for the proposed plant.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-41
3.9 RESOURCE OPTIMIZATION/RECYCLE & REUSE ENVISAGED IN THE PROJECT
The steel plant would be designed with state-of-art
technology for optimum consumption of energy & other resources. By
product BF gas would be reused within the plant as in-plant fuel and
also to produce power in the CPP. Waste heat from DR off gas would be
used to produce power in WHRB. One of the major solid waste, Char
from DR would be used to generate power in AFBC boiler in addition to
purchased steam coal. In addition, adopting a compact layout for the
Plant would enable to optimise the utilisation of land, which is another
critical resource. By utilising the fines and scrap generated during the
process within the plant for the production process, usage of raw
materials is optimised. Water consumption would also be optimised by
treatment of water to the extent possible and recycle of treated water as
make-up in the network. Solid byproducts would be reused to the extent
feasible.
3.10 AVAILABILITY OF WATER AND POWER
3.10.1 Water
The estimated requirement of raw water to the reservoir will
be at a rate of 276 cu m/hr. Water is proposed to be sourced from Ajay
River by laying a pipeline of approx 7 km & Asansol Municipal
Corporation. For the requirement of makeup water as above, M/S
Spintech Tubes have already applied to Municipality and Irrigation
Departments.
An earthen raw water storage reservoir of about
100,000 lakh cu m water holding capacity has been considered to meet
about 15 days’ make-up water requirement. From the reservoir raw
water shall be pumped to the Raw Water Treatment Plant (RWTP). The
treated raw water would be distributed in the plant’s make-up water
circuit. The unit wise requirement of water is shown in Table 3-16.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-42
TABLE 3-16 - UNITWISE REQUIREMENT OF WATER
Sl. No.
Consumer Plants Make-up Water Requirement
(cu m per hour) 1. Pellet plant 20
2. Grinding unit of pellet plant 12
3. DRI plant 53
4. Raw material handling and storage system 8
5. Sinter plant 15
6. Blast furnace (including pig casting M/C and slag granulation plant)
30
7. Ferro alloy plant 12
8. Induction furnace 10
9. EAF 10
10. Ladle Furnace - 1 5
11. Ladle Furnace - 2 5
12. Billet caster 17
13. Billet cum bloom caster 20
14. Wire rod mill 14
15. Bar mill 14
16. Structural mill 12
17. Air separation (oxygen) plant 16
18. In-plant captive power plant 22 19. Softening plant 13
20. DM water 13
21. Drinking and sanitation 3
22. Wire drawing facility 2
23. Miscellaneous requirements including losses from reservoirs
2
24. Total Make-up Water (Sl. Nos. 1 to 23) 328
25. Recovery as treated effluent from CETP and reused in RWTP
54
26. RWTP reject Loss, Raw water reservoir evaporation loss etc.
2
Grand Total (Sl. No. 24 - Sl. No. 25 + Sl. No. 26) 276
3.10.2 Power
The estimated power requirements of various plant units
including utilities and auxiliary facilities for the Plant is indicated below:
Annual energy consumption, kWh x 106 .. 851 15-min maximumdemand, MW .. 141
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-43
The power requirement would be met from the following
sources:
i) India Power Corporation Limited at 132kV/220 kV as per requirement
ii) Captive power Plant based on surplus BF Gas, WHRB & AFBC boiler
The sent out captive generation would be 64 MW and the
power sourced from the grid would be 77 MW.
DG sets of adequate capacities are proposed for the plant
units as well as CPP auxiliaries to cater to the requirement of safe
shutdown and safety of personnel during total black-out condition when
power supplies to plant network from both the sources viz. grid and CPP
have failed.
3.11 WASTE GENERATION AND MANAGEMENT
3.11.1 Waste Water Management
Waste water generated from the different areas of the plant
will be treated in suitable treatment facilities and recycled back to the
process, facilitating adequate re-use of water in the respective
recirculating systems and economizing on the make-up water
requirement. The blow down from various direct/indirect cooling water
(DCW/ICW) circuits of pellet plant, sinter plant, oxygen plant, waste
effluent from power plant and DM-softening plant, EAF, IF and LF,
Caster and Mill shall be collected in a blow-down sump, treated in the
Central Effluent Treatment Plant (CETP) and reused within the plant.
Water required for toilet flushing, floor washing etc. shall be provided
from CETP after primary treatment. Other effluents will be further
treated to the desired extent with suitable treatment facility in CETP and
recycled back to make-up water reservoir and re-used. Reject Water
generated in CETP will be used for slag quenching in SMS. Blow-down
water from the Blast-Furnace circuits will be used in slag granulation
Plant and other low-end applications.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-44
Sewage generated from toilet blocks etc would be collected by
means of suitable sewer system for treatment in Sewage Treatment Plant
(STP). Biological solid waste generated from STP would be used as
manure for development of greenery. Chemical sludge and salt would be
sent to near-by secured landfill site.
3.11.2 Solid Waste Management
The estimated generation of major solid wastes and its
utilization as envisaged for the production of 0.7 MTPA steel is presented
in Table 3-17. It may be seen that maximum effort would be taken to
reutilize & reuse of the by-products either for various in-plant use or
sold to outside agencies for value recovery & reuse.
TABLE 3-17 - SOLID WASTE GENERATION
Solid Wastes Expected
generation, TPA Management Scheme
Char 89,100 Used to generate power in AFBC boiler along with purchased steam coal
BF Slag 1,47,000 Granulation in Slag granulation plant and sell to cement manufacturers for production of Slag cement
Steelmaking Slag 1,59,318 Use in construction purposes mainly for filling of low-lying areas & road sub grade preparation.
BF Flue Dusts 5,513 Reuse in Agglomeration
Mill Scales 8,339 Reuse in agglomeration
Ferro alloy & SiMn Slag
39,769 Used for filing of low-lying area after recovery of metallics
Caster scale 3,645 Reuse in agglomeration
Caster scrap 13,140 Recycle in induction furnace
Fly Ash 95,788 Sell to agencies for manufacture of pozzolona cement, bricks, etc
Bottom Ash 23,948 Would be stored in ash pond and used for road making
Besides the above, there would be other solid wastes like
clarifier sludges, ESP/Bag Filter dust, refractory debris etc. generated
from the proposed steel plant. These would be reused/recycled within
the plant to the extent possible and the balance would be transferred to
Authorised agencies for reuse/recovery of materials/disposal as per
prevailing regulations.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-45
3.11.3 Air Pollution
Various process operations would generate particulate dusts,
oxides of sulphur and nitrogen and carbon dioxide to the environment.
The emission would be from the stacks as well as there would be fugitive
emission of dusts from open & closed areas.
Fugitive dust emissions generating from the handling and
stockpiling of raw material in open stockyards would be controlled by
water sprinkling at regular intervals. All closed zone working areas
such as raw materials handling zone, conveyor transfer points, dust
generation points at screen would be provided with dust extraction (DE)
systems/dry fogging (DF) at several emission points to control the
fugitive dust emissions. DE system shall consist of suction hood followed
by bag filter/ESP, ducts, extraction fans and stack of appropriate height.
Sinter plant: There would be cleaning of waste gas in dry
type ESP before venting it off to the atmosphere through a stack of
adequate height. Dust generated in the material & product handling and
in various transfer points would be mitigated with DE system based on
dry type ESP. Partial recirculation of waste gas would be adopted for
heat recovery and energy conservation measures.
Pellet Plant: Emissions from Pellet Plant would mainly be
from Induration Process, which are controlled by installation of ESP with
adequate height of chimneys.
Blast furnace: In addition to cleaning of BF gas in gas
cleaning plant (GCP), the main sources of air pollution would be stock
house and cast house. The BF stock house would be provided with DE
systems complete with dust extraction hoods, ESP/ Bag Filter, ID fan
and stack of adequate height. Similarly, the cast house would have
separate fume collection system during taping of hot metal and slag,
equipped with bag filter/ESP for separation of particulates before venting
through a stack of appropriate height.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-46
Heat recovery from stove waste gas shall be installed for
preheating of BF Gas and combustion air for stoves. In addition, energy
conservation would be carried out through installation of TRT and
pulverized coal injection.
DR Plant: At the kiln inlet, a dust settling chamber (DSC)
will be provided for allowing the dust to settle before passing through the
after burning chamber (ABC). The ABC will be supplied with additional
air by a fan for burning the combustible matter contained in the kiln
off-gas.
The waste gas from the ABC would be cleaned in dry type
ESP and would be further used to generate steam in a waste heat
recovery boiler (WHRB).
Steel Melting Shop: There would be two combined gas
cleaning facilities and FE system for EAF & LF and IF & LF. The gas
cleaning system would be complete with water cooled duct, combustion
chamber, fume and gas cooler, bag house, ID fan and stack for venting
off to the atmosphere.
Secondary fumes would be generated at several points
during ladle transfer, raw materials charging, liquid steel tapping and
secondary refining points. All the fumes from each of the process
operation would be collected by FE systems and taken through bag filter
before venting out clean air into the atmosphere through a stack of
appropriate height.
Rolling Mills: The off-gases generated from the reheating
furnace would contain particulates, CO2 and NOx. NOx emissions would
be controlled by optimising the excess air supply and proper burner
design. In addition fume extraction (FE) system would be installed. The
flue gas, which is fairly clean, would be vented through a stack of
adequate height.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-47
The structural products & a fraction of the wire rods would
undergo hot dip galvanisation in molten zinc baths. These processes
would generate vapours and fumes which would be controlled by fume
extraction systems.
Captive Power Plant:
Waste heat recovery type power plant: The sensible heat of
the hot flue gas from coke oven would be utilised for generation of
electrical power. The off-gas from the power plant containing SO2 and
NOx would be vented to the atmosphere through a stack of adequate
height.
BF gas fired power plant: There would be generation of power
based on combustion of BF gas. The flue gas from boilers mainly
containing NOx would be vented off to the atmosphere through stack of
adequate height.
AFBC Boiler: Char and steam coal would be burnt in the
boiler for generation of power. The flue gas thus generated from the
boiler would be vented through stack of appropriate height. ESPs would
be provided to capture the fly ash.
3.12 SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY
DRAWING WHICH GIVE INFORMATION OF EIA PURPOSE
As per the Environment Impact Assessment (EIA)
notification dated 14th September 2006 and subsequent amendments,
this project falls under category A. It would be required to prepare
EIA/EMP report to obtain the Environmental Clearance (EC) for the
project from the MoEFCC. The schematic diagram given in Fig. 3-4
represents the steps required for EIA to obtain the EC.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 3 - Project Description (cont’d)
3-48
FIG. 3-3 - SCHEMATIC DIAGRAM FOR STEPS OF EIA
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
4-1
4 - SITE ANALYSIS
4.1 CONNECTIVITY
The site is located in Dhasal, Mamudpur & Bahadurpur
villages of Jamuria block of Paschim Bardhaman district in West Bengal.
The location is well connected by road and rail. The nearest railway
station is Ikrah Junction. Asansol junction and Raniganj stations are
two other major railway stations in the area. Jamuria Road is the access
road for reaching the plant site. NH 60 runs in South East direction at
an distance of approx 2 km from the project site. Kazi Nazrul Islam
International Airport, Andal is around 15 km in South East direction
while NSC Bose International Airport at Kolkata is around 160 km from
the project site. The nearest sea port Haldia is within 300 km away from
the site. The site connectivity is shown in Fig. 4-1.
FIG. 4-4 - SITE CONNECTIVITY
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 4 - Site Analysis (cont’d)
4-2
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP
The major land use in the study area is agriculture followed
by collieries operation. No reserve or protected forest is present within
the study area however scattered vegetation patches covering small areas
are present in the south and South West direction of the project site.
Approx 113 acres land have already purchased by STPL.
4.2.1 Land Use of Project site
The proposed site for setting up of the Greenfield ISP project
is located within the jurisdiction of Jamuria Block of Paschim
Bardhaman District of west Bengal. The geographical location of the
project site lies within 23040’45” to 23041’21” North latitude and
87007’45” to 87008’22” East longitude.
240 acres of land would be required for the proposed ISP
project. The proposed site primarily consists of a mixture of single crop
land, poor crop land, water logged area, pond & barren land as shown in
Table 4-1.
TABLE 4-1 - LAND USE OF CORE AREA
Land use Area (Acres) % use Agricultural land 21.36 8.9 Poor Crop land 98.16 40.9 Water logged area 45.31 18.8 Pond 13.37 5.6 Barren land 61.80 25.8
Total 240.00 100.0
4.3 TOPOGRAPHY
Jamuria is characterized by undulating topography with
rugged hilly terrains in the western parts. The western half of the area
resembles a promontory jutting out from the hill ranges of Chottnagpur
plateau and consists of barren, rocky and rolling country with a Laterite
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 4 - Site Analysis (cont’d)
4-3
soil rising into rocky hillocks, the highest being 227 m. Ajay-Barakar
divide is a convex plateau, the average altitude being 150 m from the
mean sea level. The gradient is westerly to the west and to the east it is
northerly towards Ajay and southerly towards Damodar below the
latitude. The average elevation of Bardhaman plain is about 104 m above
the Mean Sea Level (MSL). This area is a low lying alluvial plains with
riverine aggregates.
The rocky undulating topography with laterite soil found in
Paschim Bardhaman district is a sort of extension of the Chota Nagpur
plateau. For ages the area was heavily forested and infested with
plunderers and marauders. The discovery of coal in the 18th century led
to industrialization. Most of the forests in the coal-bearing areas have
been cleared but some areas in the eastern part of the district remained
thickly forested till more recent times and some are still there. The
eastern part of the district gradually slopes down to the rice plains of the
agriculturally rich Purba Bardhaman district.
The study area is mainly drained by River Ajay which flows
along northern side at a distance of about 7.3 kms. The direction of flow
of the river is controlled by slope which in general is from North to South
East. Ajay River is of high significance in the region as it caters to the
water requirements to most of the villages and the majority of the
industrial units in the region.
The general topography of the project site is pediplain. The
other areas are divided into shallow weathered buried pediplain, Flood
plain, and valley hill & rivers. The topographic features of the study area
may be seen from Survey of India Topo Sheet No. 73 M2. The
Topographic map is shown in Fig 4-2.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 4 - Site Analysis (cont’d)
4-4
FIG. 4-5 - TOPOGRAPHIC MAP OF THE PROPOSED STEEL PLANT SITE
4.4 EXISTING INFRASTRUCTURE
The site is located at Dhasal under Jamuria block in district
Paschim Bardhaman of West Bengal. The location is well connected by
road & rail. The proposed site is only 2.0 km away from NH 60. Ikrah
Railway station is about 2.0 km away & Kazi Nazrul Islam Airport is
around 15.0 km away for the proposed site.
4.5 SOIL CHARACTERISTICS
Soil of the project site is red lateritic soil with high Fe, sandy
loamy texture with medium water holding capacity. The pH level found to
in the range of 5.5 to 6.0, which indicate moderately acidic soil which
870 15’
230 45’
230 40’
230 35’
870 05’ 870 10’ 870 00’
Topo Map No - 73 M2
Proposed Project Site
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 4 - Site Analysis (cont’d)
4-5
has deficient available nutrients to plants for growth. The presence of
nutrients like nitrogen, phosphate, potash, manganese and humus are
insufficient. Hence, the soil is non fertile and low productive for
cultivation.
4.6 CLIMATIC CONDITIONS
The Paschim Bardhaman experiences a mixed transitional
climate between the tropical wet and dry climate and the more humid
subtropical climate. The winter season starts from about the middle of
November and continues till the end of February. The monsoon is
followed by a mild, dry winter. March to May is dry summer intervened
by tropical cyclonic storms. June to September is wet summer while
October is autumn.
Average temperature during summer season is 31OC while at
the cold season is 22OC. Average annual rainfall is around 1,350 mm, of
which the bulk of rainfall occurring around the July-September period.
The wind blows predominantly from South (S)/South West
(SW) during the period from March to August and for rest part of the
year wind generally blows from North (N) and North West (NW) directions.
The summarized meteorological data of Burdwan district is shown in
Table 4-2.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 4 - Site Analysis (cont’d)
4-6
TABLE 4-2 - SUMMARISED METEOROLOGICAL DATA Location .. Burdwan
Lat/Long .. 23O14′ N; 87O51′ E Elevation above MSL .. 32 m
Parameters Summer Monsoon Post-
Monsoon Winter Max. DB temperature (OC) 46.8 45.6 38.0 38.8
Average DB temperature (OC) 31.2 29.7 27.1 22.0
Relative Humidity (%) 56.0 79.3 74.8 55.8
Average Wind Speed (kmph) 7.7 8.4 5.0 3.2
Predominant wind direction S, SW S, SE,SW E, SE N, NW
Total rainfall (mm) 131.2 819.7 359.8 27.8
Source: IMD - Climatic Normals (1951-1980)
4.7 SOCIAL INFRASTRUCTURE AVAILABLE
i) The economy of Paschim Burdwan district is divided into the agricultural sector (52%) and non agricultural sector (48%).The primary crop grown in the district is that of Paddy followed by Jute, Mesta, Sugarcane, Potato and Oil seeds
ii) Small & Medium scale manufacturing units have mushroomed around the Iron and Cement Industries. The economic activities within these manufacturing units facilitate employment to the local populace
iii) Educational institutions like Bahadurpur High School, Dhasal F.P School (Primary) and Kazi Nazrul Islam Mahavidyalaya at Churulia are operational in the district
iv) Transport & Communication infrastructure in district is characterized by Ikrah Railway Station and bus routes from Jamuria to Raniganj/Asansol/Haripur/ Kolkata. Kutcha road connects Dhasal and Jamuria to NH 60. The nearest arirport is Kazi Nazrul Islam Airport located in Durgapur
v) Financial institutions like Axis Bank, State Bank of India, Bank of India and HDFC Bank are operational in Jamuria
vi) Primary Health Centres are located in Jamuria and Bahadurpur and Churulia
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
5-1
5 - PLANNING BRIEF
5.1 PLANNING CONCEPT
The proposed steel plant would be located near Dhasal,
Jamuria Block, Paschim Bardhaman. The total land area of the
proposed project would be 240 acres spread across 3 villages (Dhasal,
Mamudpur & Bahadurpur) in Jamuria block of Paschim Bardhaman.
Most of the raw materials would be transported through
covered trucks by road after unloading at railway station. The raw
materials and products would be covered fully during the transportation
to avoid spillage & fugitive emissions. The transportation load would not
add much to the existing load on the said road network.
The proposed steel plant involving semi-mechanized
operations would be a labour intensive one. Local construction labourers
as well as direct & indirect labourers would be engaged for the operation.
Suitable plantation programme would be undertaken to cover
the boundary areas with thick & tall plants tom arrest the air-borne
pollutants within the plant premises.
5.2 POPULATION PROJECTION
The census data of 2011 for district of Burdwan indicates a
total population of 7,717,563. In the year 2017, the erstwhile district of
Burdwan was divided into Purba Bardhaman and Paschim Bardhaman.
The proposed Greenfield project currently falls under the
block of Jamuria in the district of Paschim Bardhaman.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 5 - Planning Brief (cont’d)
5-2
The total population of Jamuria block (as indicated in the
census data) for the years 2001 and 2011 are 1,12,799 and 1,23,176
respectively. The computed decadal growth is that of 9.20 %. Hence the
projected population of Jamuria block for the year 2018 is calculated to
be around 1,31,110.
5.3 LAND USE PLANNING
5.3.1 Integrated Steel Plant
The total area for steel plant would be 240 acres, consisting
of government and private land. The area would house the following
facilities:
i) Raw material storage yard ii) Sinter plant iii) Pellet plant iv) DRI plant v) Ferro alloy & Briquetting plant vi) Blast Furnace vii) Steel Melt Shop with casters viii) Air separation plant ix) Mills (Structural, Bar & Wire rods) x) Wire drawing facilities xi) RWTP, STP & CETP xii) Captive power plant
The land use break-up of the project area (240 acres) is
shown in Table 5-1.
TABLE 5-1 - LAND USE BREAK-UP OF THE PROJECT AREA
Land Use Acres % Use Built up area 108.4 45.2 Raw Material Storage area 24.9 10.4 Waste Disposal area 2.7 1.1 Water Body 3.2 1.3 Greenery 79.2 33.0 In-plant Roads 21.6 9.0
Total 240.0 100.0
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 5 - Planning Brief (cont’d)
5-3
The total greenbelt, comprising of about 33% of total plant
area of about 79.2 acres, would be reserved in the layout. The layout
would also house canteen, administrative buildings, workshop, stores
etc.
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND
i) Support towards adequate sanitation facilities and awareness programmes (in the areas of hygiene, vector borne diseases and HIV) for the local population
ii) Support towards industrial and vocational training (for
both local male & female youth members) and adult education of the marginal communities
iii) Support towards provision of adequate mobile medical
facilities
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
6-1
6 - PROPOSED INFRASTRUCTURE
6.1 INDUSTRIAL AREA (PROCESSING AREA)
The site is located at Dhasal under Jamuria block in district
Paschim Bardhaman of West Bengal. The location is well connected by
road & rail. The proposed site is 2.0 km away from NH 60. Ikrah
Railway station is about 2.0 km away & Kazi Nazrul Islam Airport is
around 15.0 km away for the proposed site.
The existing infrastructure for the proposed steel plant as
well as connectivity has been discussed in Chapter-4.
6.2 RESIDENTIAL AREA (NON PROCESSING AREA)
No residential facilities have been considered for the
proposed project.
6.3 GREENBELT
It is obligatory to develop dense greenbelt area in proposed
project plant as per CPCB guidelines. Green belt is proposed to be
developed in compliance with the regulatory norms. This would not only
prevent the fugitive dust emissions but also improve the peripheral
appearance of the plant from aesthetics point of view. Unpaved areas, if
any, within the plant boundary would be provided with grass/tree cover.
Depending on the type of soil suitable for growth, higher
survival rate in the region, large leaf index area, nativity of the species
and pollution load, following are the proposed species of trees which may
be planted as greenbelt at the steel plant site at Jamuria:
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 6 - Proposed Infrastructure (cont’d)
6-2
List of selected tree species for greenbelt development: 1. Akashmoni - Acacia moniliformis (Fabaceae) 2. Arjun - Terminalia arjuna (Combretaceae) 3. Kassod - Cassia siamea (Fabaceae) 4. Chatim - Alstonia scholaris (Apocynaceae) 5. Jamun - Syzygium cuminiin (Myrtaceae) 6. Kanchan - Bauhinia acumiata (Fabaceae) 7. Kath badam - Terminalia catappa (Combretaceae) 8. Neem - Azadirachta indica (Meliaceae) 9. Siraish - Albizia lebbeck (Fabaceae) 10. Sisoo - Dalbergia sisso (Fabaceae)
6.4 SOCIAL INFRASTRUCTURE
i) Support towards government initiatives relating to sanitation
ii) Support towards industrial and vocational training for youth of marginal communities
iii) Support towards strengthening of existing medical facilities & allied camps/awareness programmes to cater to the local population
iv) Support towards repairing of local approach and link roads for better communication
6.5 CONNECTIVITY
The project location has good connectivity in respect of road
& rail. The site is only 2.0 km away from the NH 60. Ikrah Railway
station is 2.0 km away. Nearest Airport (Kazi Nazrul Islam Airport) is
about 15 km away from the project site. The connectivity has been
described in detail in chapter 2.
6.6 DRINKING WATER MANAGEMENT
The total water requirement for drinking & sanitation would
be 3 cu m/hr approximately, which is proposed to be drawn from the
plant water system and the total water requirement of the plant would be
sourced from Ajay River approximately 7 km away from the plant site
and Asansol Municipal Corporation.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 6 - Proposed Infrastructure (cont’d)
6-3
The drinking and sanitary water system will be provided to
meet the water requirement of the plant personnel. Drinking quality
water also will be required at the quality control laboratory. Clarified
water received from the plant make-up water system will be filtered and
chlorinated to convert it into drinking quality water. The drinking water
will be collected in a 50 cu m overhead storage tank from which drinking
water will be distributed to the various consumers.
6.7 DRAINAGE AND SEWERAGE SYSTEM
Open type drain has been envisaged for the plant storm
water drainage. The drains will be laid generally by the side of the roads.
Storm water run-off, collected through arterial and trunk drain, will be
discharged to water treatment plant for treatment and treated water will
be discharged to pond. Overflow water from pond will be discharged to
the existing re-routed canal of the plant. Sanitary faecal sewage will be
collected from the ablution blocks through pipeline and the same will be
connected to a sewage treatment plant. The effluent from sewage
treatment plant will be utilized for the development and maintenance of
greenery.
6.8 INDUSTRIAL WASTE MANAGEMENT
The proposed project would generate various types of wastes
including liquid effluents and solid wastes, which have been detailed in
Chapter-3.
6.9 SOLID WASTE MANAGEMENT
Major solid wastes produced in the ISP would be namely
blast furnace slag, SMS slag, char and coal ash among others. The solid
waste management has been discussed in details in Chapter-3.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 6 - Proposed Infrastructure (cont’d)
6-4
6.10 POWER REQUIREMENT AND SUPPLY/SOURCE
Power sources at two different voltage levels are available in
Asansol area, 132 kV and 220 kV. M/s India Power Corporation Limited
(IPCL) will arrange for the required power supply from their 132 kV
substation located within a km from this project site. Necessary grid
strengthening, if required, for meeting the short circuit fault level, will be
done by grid authority before implementation of the project. Power
supply from 220kV line can also be adopted if 132 kV line/grid
strengthening is not found suitable. The estimated power requirements &
supply/source for the proposed integrated steel plant has been stated in
more details in Chapter-3.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
7-1
7 - REHABILITATION AND RESETTLEMENT
The land acquisition process for the proposed Greenfield
project does not entail issues of ‘Rehabilitation and Resettlement’ of local
human settlements including those of encroacher and squatter groups.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
8-1
8 - IMPLEMENTATION SCHEDULE AND COST ESTIMATE
This chapter indicates the overall implementation schedule
of the project and the capital cost estimate.
8.1 IMPLEMENTATION SCHEDULE
It is envisaged that the project will be completed within a
period of twenty seven months from “Go Ahead”.
The schedule has been developed on the basis of the
estimated quantum of work, expected delivery and installation period of
equipment and commissioning of the plant facilities in shortest possible
time.
Completion of major activities from “Go Ahead”:
Pellet Plant .. 24 months Sinter Plant .. 24 months DR Plant .. 25 months Blast Furnace .. 27 months Steel Melt Shop .. 27 months Wire Rod Mill .. 24 months Bar Mill .. 24 months Structural Mill .. 24 months FeMn and FeSi Plant .. 23 months Ferro Chrome Plant .. 23 months Captive Power Plant .. 22 months Air Separation Plant .. 22 months
The preliminary overall implementation schedule for the
project, indicating the time period required for completing the major
activities like ordering of main process equipment, basic & detail
engineering for the project, manufacturing & supply to site, construction
(civil & structural work and erection including cold trials/testing) and
readiness of the plant is presented below in the form of a Bar Chart in
Fig. 8-1.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 8 - Implementation Schedule and Cost Estimate (cont’d)
8-2
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 8 - Implementation Schedule and Cost Estimate (cont’d)
8-3
FIG. 8-6 - IMPLEMENTATION SCHEDULE
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 8 - Implementation Schedule and Cost Estimate (cont’d)
8-4
8.2 CAPITAL COST ESTIMATE
This section presents the capital cost estimates,
manufacturing expenses and return on investment (ROI) for the project.
The order-of-magnitude capital cost is projected in this
section. This comprise as erected mechanical and electrical equipment
including related civil and structural steelwork and cost towards design,
engineering and consultancy and administration during construction.
Provision has also been considered for contingency, margin money,
preliminary & preoperative expenses and IDC for arriving at the total
capital cost.
The estimate is based on information available with
CONSULTING ENGINEERS for similar facilities. Applicable taxes and
duties have been considered in all of the estimated costs.
The breakdown of order-of-magnitude plant cost is indicated
in Table 8 -1.
TABLE 8-1 - CAPITAL COST ESTIMATE
Item Amount Rs. crore
Land and land development 89 Plant and equipment (as erected) including civil and structural work
2,400
Infrastructure and construction facilities 16 Design, engineering and administration during construction
118
Contingency 262
Total Plant Cost 2,885
Margin money, Preliminary & pre-operative expenses & IDC
315
Total Capital Cost 3,200
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 8 - Implementation Schedule and Cost Estimate (cont’d)
8-5
It is seen from the table above that the order-of-magnitude
plant cost (Gross of GST) of the plant will be about Rs 3,200 crore.
8.3 ANNUAL MANUFACTURING EXPENSES
The annual manufacturing expenses for the project have
been estimated at rated capacity level under the following heads:
a) Raw materials, b) Utilities and services, c) Consumables and refractories, d) Repair and maintenance, f) Salaries and wages g) Admin and sales overhead.
The estimated annual manufacturing expenses for the plant
at the rated capacity level are given in Table 8-2.
TABLE 8-2 - ANNUAL MANUFACTURING EXPENSES (AT RATED CAPACITY LEVEL)
Item description Amount, Rs. crore
Raw materials 1,772 Utilities and services 241 Consumables and refractories 253 Repair and maintenance 44 Salaries & wages 50 Overhead expenses 32
Annual manufacturing expenses 2,392
8.4 ANNUAL SALES REASILSATION
The annual sales realisations at rated capacity level have
been estimated at about Rs. 3,028 crore.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report 8 - Implementation Schedule and Cost Estimate (cont’d)
8-6
8.4.1 Return on Investment (ROI)
Return of investment has been calculated based on the gross
profit at first year of 100 per cent capacity utilization and capital cost of
the Project and given below.
A. Sales realization, Rs crore 3,028
B. Manufacturing expenses 2,392
C. Gross profit (A-B) 636
D. Capital cost 3,200
E. ROI, % (C/D) 20
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
9-1
9 - ANALYSIS OF PROPOSAL
9.1 FINANCIAL AND SOCIAL BENEFITS OF THE PROJECT
The proposed Greenfield project would
i) generate local direct & indirect employment opportunities and improve local income
ii) augment the development of ancillary small-medium
scale industries, trade & commercial establishments and local entrepreneurship
iii) promote diversification in skill set amongst young
adults iv) enhance local land prices v) contribute to the district and state revenue
The peripheral development activities that would be
undertaken by the proposed project under Corporate Environment
Responsibility (CER) will focus on marginal communities and attempt to
bring forward an overall social development with emphasis in the areas
of education, training, health and social & physical infrastructure.
SPINTECH TUBES PVT LIMITED Greenfield Integrated Iron & Steel Plant of 0.7 MTPA with Captive Power Plant of 70 MW in Jamuria Pre-Feasibility Report
i