setting up and using qu100 - wastedataflo · •background •what is qu100? •setting up and...
TRANSCRIPT
• Background
• What is Qu100?
• Setting up and using Qu100
• Examples
• Tips
• Back allocation
Areas to be covered
• The key to using Question 100 is to fully
understand all the movements of your waste,
from collection to end UK destination or export.
• WDF’s original question set had become
stretched in situations where more complicated
disposal methods are being implemented (e.g.
large scale PFI contracts).
Background
• Example: A ‘traditional’ treatment system
Collection
Primary
Treatment
Landfill
Reprocessors
Rejects
• Example: A ‘complex’ treatment system
Collection
Recycling
Treatment
Landfill
Reprocessors
Rejects
Residual
Treatment
Secondary
Treatment
• Qu100 allows waste sent through several
treatment processes to be recorded in WDF,
which had not been possible previously.
• New question in WDF to record all the
treatments and end destinations of all your
residual, recycling, reuse and composting waste.
• It replaced Questions 19, 19a, 35, 51-65, 69 &
70.
• Used by all English LAs from Apr-Jun 2015
What is Qu100?
• The previous question set was a rigid structure
that data was fitted into. With Qu100 you build
the data entry structure as you need it to be.
• It allows the user to create a ‘tree’ structure that
traces the movements of waste after collection
to final destination. Essentially it’s like a flow
diagram you set up to suit your LA’s treatment
routes.
• It will have taken a little time to initially set up
Qu100, but now it has, you can load the tree
structure from previous quarters.
What is Qu100?
• Qu100 is available at the end of your question list.
• Before using Qu100, having your material and
selection lists set up properly makes it much easier
to use. Guidance on these can be found here:
• System Management: http://www.wastedataflow.org/documents/guidancenotes/SystemManual/GN
4_Section_2_WDF_Manual_System_Management_1.0f.pdf
Setting up Qu100
• Log into Data manager as normal.
• Roll over the ‘Data’ menu and
select ‘Data Entry’ from the drop
down.
• Pick the period for which you wish
to enter data.
• Scroll to the bottom of your
Question list click the Qu100
question heading to start.
Setting up Qu100
Setting up Qu100
• Qu100 uses a different layout to the previous
questions, providing a more visual interface
to track your material flows.
• This is achieved by creating a ‘tree’, with your
treatment methods as differing levels of
‘node’ on a ‘branch’; From primary facilities at
the root, to your final destinations at the end
of these branches as the ‘leaves’.
Qu100 Terminology The primary node is
the first facility
(barring transfer
stations) the
material goes to
after collection
In this example this
is the final node of
the branch, so can
also be described
as the leaf level
Primary/Root Node
Secondary Node
Tertiary Node
Branch
Tree (A collection
of different
branches)
Setting up Qu100
In the same way that in other questions, (qu19 for example),
you can load comments from previous months, in Qu100 you
will be able to load your tree structure from previous months.
So once your initial tree is in place it is likely that only
occasional growth or pruning will be required.
WARNING: loading a structure from a
previous month will overwrite any tree and
data in the current month. So if you are
going to load a structure make sure you
do this first.
Qu100 Layout
This side will show you the structure
of your tree as it grows; navigate
around it
Whilst this side will allow you to
add/edit/remove the ‘branches’ of your tree
and check your information balances.
Growing your tree: The basics • Click ‘Q100:Waste sent for treatment or disposal’ this allows
you to build a new branch. Do this each time you want to start a
new stream.
• Choose the facility/process type that your waste goes to in the
first instance from the drop down box.
• This list is similar to the list of Questions 19, 35 and 51-65 in
WasteDataFlow.
• Next to each choice is a reminder of the original question
number the option replaces.
Growing your tree: The basics
• You can now pick
the facility details
for the site.
• Click on the facility
box and a list of
your sites will
appear. Start
typing and once
you have 3 or
more characters
the list will start to
refine based on
what you’ve typed. • To choose a facility just click its name.
• Facilities can be added to your selection list via the
Selection lists option of the Management menu.
• N.B. the different colouring on the list confirms the status of the site. Black text for active, Red for deactivated, and
red highlight for locked. Do not use locked facilities as you will not be able to rollup your data!
Growing your tree: The basics • You now need to select
the ‘Waste Stream Type’
entering the
facility/process.
• Each Facility/Process has
designated waste stream
types, e.g. composters
have Green/ Food waste,
MRFs have Comingled or
Source segregated
recyclate etc.
• In this example, being a
Non-hazardous landfill,
you are limited to
Residual Waste.
Growing your tree: The basics
• Add the tonnage input to the Facility/Process
and click Save.
• You can now access the Source Splits,
Materials, Transfer Stations and Comments
sections. You can Expand or Collapse by
clicking the black arrow buttons.
• In this example you would not need to give
material types but for reprocessors, composters
etc., you will be forced to do this.
• If you use a Transfer Station for this branch,
you can add data in the relevant boxes.
• You can use Comments boxes as required.
• Remember to click Save when you are finished.
Tip: Click on the Save button to enter data. Do
not use the enter button on your keyboard.
• The previous slides covered simple waste movements, such as
waste direct to landfill. Q100 can also replace Q19/35 for waste
sent directly for recycling/reuse. Or, as in the example below, as
a substitute for commingled material going via a MRF (Qu58)
then on to reprocessing (Qu19)
• To add this second branch (waste stream) to your tree simply
click ‘Q100:Waste sent for treatment or disposal’ again and
then select ‘Materials recovery facility’ from the Facility/Process
drop down on the right.
Growing your tree: The basics
Growing your tree: The basics • As before, pick your facility
and waste stream type
• In this example, being a
MRF, you are limited to
Comingled recyclate.
• Enter the input tonnage to
the facility and save the
branch
Growing your tree: The basics
• At this point you will see that a
second branch has been
added to your tree, as shown
on the left hand ‘Waste
Movement Tree’ box.
• However, unlike the landfill
branch it is displayed with a red
triangle. This indicates an
incomplete branch.
At any stage you can change the destination by
clicking ‘Change’, rather than deleting and
starting again.
Growing your tree: The basics
• The branch is incomplete
at the moment as it has inputs
but no outputs.
• You will need to add
‘leaves’ or sub ‘branch(es)’
for this branch to show as
complete.
• To do this, make sure the branch is selected by clicking on it,
(highlighted in bold as above), and click the ‘New Output’ button.
Growing your tree: The basics
• As this example deals with a MRF
we will select dry recyclate for the
‘Output Waste Type’ and then
‘Reprocessor’ as the equivalent of
Qu19 for its destination.
• This will then bring up the
reprocessor destination list, from
which we can select our chosen
reprocessor before pressing Save.
Growing your tree: The basics
• You will have noticed prior to
saving, and again now, that the
tonnes output box was not
available for you to enter a number
into.
• This is because for output going to
a reprocessor it must be related to
the specific material type(s) as
was the case in Qu19. • Instead press the arrow button on the
Materials section and record the tonnages
against the appropriate categories.
Growing your tree: The basics • The materials shown by default
relate to the list you have set up
under the material list option from
the management menu.
• There are also options for
selecting any transfer stations
which may have been used and to
add comments which may be
relevant.
Growing your tree: The basics • With this done you will see that the
MRF node has turned yellow to
show that it has at least one output
for its waste. There are two things
we still need to complete.
1. Firstly our reprocessor node is now showing a warning triangle. This is
because in Qu100 we always need to show that a site is the end point,
or final destination of the material’s journey. As mentioned earlier,
Qu100 allows for multiple additional steps to be recorded. For example it
could be that the reprocessor rejects the waste to a secondary
reprocessor or to an EfW. We therefore need to actively confirm that in
this case this will be the end point for our material.
Growing your tree: The basics
• To finalise this branch make sure
the reprocessor is highlighted
and select new output.
• Press the ‘Final Destination’
button to confirm that this is the
end point of the waste’s journey
Growing your tree: The basics
• We can see now
how the Qu100
branch, mirrors our
earlier example.
• Select the output/process type
• There are three types of final
destination available. For now just
use ‘Final Destination’ , further info on
the use of ‘FD (Compliant)’ and ‘FD (non-
compliant)’ will be provided in due course
• Press ‘save’ and your final
destination node will be created
Growing your tree: The basics 2. Now that the final destination has
been added and the warning
triangle is gone we can return to
the yellow node (or branch) of the
MRF. Clicking the MRF node to
highlight it again now opens up a
new section: The Waste Movement
Summary.
• The Summary is available for any
yellow or blue level node and
provides a useful breakdown of
input and output to highlight any
imbalance that might exist.
• In this instance we can see that
of the 5000t input to the MRF we
have accounted for 1500t,
leaving 3500t which still needs to
be dealt with.
Growing your tree: The basics • The tree to the left has now been
expanded to represent how a typical
MRF would currently be reported.
– The MRF
– A number of reprocessors which deal
with the different material outputs, (in
this case four)
– Rejects to landfill, and
– Rejects to EfW
• What you will notice now however is
that in Qu100 we need to go further
than this to complete the EfW node.
• If the data is available you can
record the EfW outputs in terms of
any metal or IBA recycling, landfilled
material and process loss from
incineration.
Growing your tree: The basics • Here the EfW node has been
completed.
• The use of the ‘process loss’
category does not feed into any
further calculation of NIs or LATS,
but it does allow for the movement
of waste to balance, as shown in the
summary box. It is therefore
important to use ‘process loss’ or
‘moisture loss’ wherever a loss
occurs, e.g. an incinerator, an MBT
etc.
• This MRF example has been set up
to mimic what you would be familiar
with from your MRF in the existing
question set. It could be however,
that something very different occurs
with the MRF material.....
Growing your tree: The basics
• In this example the MRF also rejects material to
a secondary MRF for further treatment.
• Prior to Q100 recording data in this way would
not have been possible, but there is now the
ability to represent much more complicated
movements of waste
Growing your tree: The basics -
Source Splits (optional)
• Up to now there has been an optional Question, Qu69, which when
used supported the creation of household waste factors. These factors
superseded the default ones based on collection tonnages and were
applied to the relevant NI and BVPI calculations.
• Qu69 wont work with Qu100 and so another solution to provide similar
functionality was needed.
• The root node source split box:
Growing your tree: The basics -
Source Splits (optional)
• Each primary/root level node you create will display the source split
box.
• It contains two, 2 way splits – Tonnes from HH Sources : Tonnes from non-HH sources
and
– Tonnes from WfH Sources : Tonnes from WnfH Sources
• The splits can be completed wherever breakdowns are known. This
may be none of them, or it may be all of them.
Specific examples
• The following section looks at how common waste management methods
can be recorded in Qu100
• It also looks at how more complex, but increasingly common, elements
can also be recorded.
• With Question 100 it helps to think of your waste management practices
as mass flows with the links between them.
• Guidance Document Examples….
Growing your tree: Tips • Mighty Oaks: The more information you put into Qu100 the larger it will
get, so it is important to get things in a logical order. You can also use the
‘+’ and ‘-’ buttons to condense parts you have completed:
From this:
…to this…
… to this!
Growing your tree: Tips What the nodes mean
This is a ‘top level’ node that should have some outputs or be confirmed
as a final destination, so may be a primary treatment facility or a
reprocessor for recycling/ reuse.
This is a ‘sub-level’ node that should have some outputs or be confirmed
as a final destination so may be a secondary or tertiary treatment facility
or a reprocessor for recycling/ reuse.
This is an end node where waste has been confirmed as being recycled,
reused or composted so would be found against these facility types.
This is an end node where waste has been landfilled to any type of landfill.
This is a warning node to let you know that you have added a Facility or
Process Type that WDF expected to have some sub level outputs.
Growing your tree: Tips
What the nodes mean
This node is designed to warn you that WDF expects an output
for one of your Processes/Facilities. When it disappears, WDF
is satisfied that you have added some kind of output. However,
it does not mean the data you have added is correct or
balances, this should be validated manually.
Growing your tree: Tips
Loading from previous quarters
• You can load your tree structure from previous
quarters by selecting a period and clicking Go.
• This will load a replica of the tree structure from
the chosen period, with all the same branches,
sub branches and destinations, but without any
tonnage data.
• You can then add this data in.
• By doing this you can develop your tree to
incorporate all the regular movements of your
waste over the months/quarters.
WARNING - if you load
from previous periods it
will overwrite anything you
have already entered this
period, so do this first!
Growing your tree: Tips
Pruning your tree
• You can delete any part of your tree
by clicking on it and clicking the
button.
• Please remember! If you delete a
part of your tree, all of its sub-
branches will also be deleted.
So deleting this…
Will also delete all these
Growing your tree: Tips
• You don’t have to delete a facility if you are going to replace it with another
of the same type.
• By clicking Change, you can replace it with another facility.
• This is handy if you are loading from previous quarters, but have a one-off
change to a particular destination.
Change rather than delete
Growing your tree: Tips
• Between WCAs and WDAs
• Qu100 opens up question elements relating to the treatment of residual waste to
WCAs which were previously not available, such as landfill options (previously
Qu51-53), MBT (previously Qu59) etc.
• However, it is not expected that a WCA will now take on the responsibility for
reporting these from the WDA. In fact doing so will likely double-count these
operations as the WDA will still be recording them.
• Therefore as a general rule we ask that WCAs only report the following
facility/process types at the root/primary level: – Material Reprocessing Facility (MRF) (Qu58)
– Reprocessors – Recycling (Qu19)
– Exporters – Recycling
– Reuse (Qu35)
– Exporters – Reuse
– Anaerobic or Aerobic Digestion Segregated (Qu61)
– In-vessel Composting (Qu62)
– Windrow or other Composting (Qu63)
Avoiding double counting
Saving and rolling up your data
Rolling up your data is no different because you’re completing Qu100 BUT
there are a couple of things to note:
1. Qu100 does not have a Question complete box
so it is up to you to ensure you have properly
finished the question.
Back Allocation
• The original WDF question scheme was not designed to accommodate
back-allocation
• As a result the method required to ensure nothing was double-counted
between the WCAs and WDA as well as allowing for correct indicator
calculation was a complex one.
• Qu100 however has been designed to allow for a simpler application of
back-allocation in situations where it is used.
• In situations where residual waste is collected by a WCA which is
subsequently processed by their WDA, with recycling extracted and “back-
allocated” to the original collection authority, the process below should be
followed.
• Back-allocation example:
• In this example 100t of residual material is collected by the WCA.
• This is then taken by the WDA and processed directly after collection
(e.g. via a residual MRF (rMRF)) so as to recover some of the
recyclable materials it contains.
• This results in 70t remaining as a residual output which is sent to
landfill.
• Of the 30t of recycling 20t is sent to Reprocessor A, which ultimately
rejects 5t of it at the gate.
• The remaining 10t of recycling from the rMRF is sent to Reprocessor B
with all of it being accepted for recycling.
• N.B. In a real situation the actual site details would be used in place of
reprocessor A and B.
How the WDA should record:
Rather than the pre-Qu100 situation where tonnages were subtracted from
Qu23 and treatment outputs, with Qu100 the tonnages are to be recorded in
the same way as they would if back-allocation were not occurring.
Q23 – All 100t recorded against the appropriate collection method
Qu100 – 100t input to the appropriate treatment (here a rMRF).
- 70t output to landfill
- 20t output to reprocessor A
- reprocessor A has two outputs
- 5t of gate rejects to landfill
- 15t of recyclate confirmed by the use of a final destination
- 10t of output to reprocessor B
- 10t of recyclate confirmed by the use of a final destination
Comments should be added to the reprocessor nodes A and B to note that
this material is back-allocated to the WCA(s). The breakdown of recyclate
amongst multiple WCAs should be described in the comments of the relevant
reprocessor node.
How the WCA should record:
In the example above for the WDA, 25t of the 100t collected as residual waste
was ultimately sent to a final recycling destination. It is this 25t which is then
back-allocated to the WCA (N.B. not the 30t with 5t of rejects).
With Qu100 all material which is residual waste at the point of collection,
irrespective of future treatment, should be recorded as such and so entered into
Qu23.
Q23 – All 100t recorded against the appropriate collection method.
Qu100 – 25t input to the new process type of “Material from WDA” (N.B. this
must be selected as a root level node), with a waste stream type of residual
waste. Only 25t is entered here as only 25t was ultimately recycled by the WDA.
- 15t output to reprocessor A (only the 15t of material eventually
accepted as
recyclate from the WDA’s return should be recorded by the WCA).
- 15t of recyclate confirmed by the use of a final destination
- 10t of output to reprocessor B
- 10t of recyclate confirmed by the use of a final destination.
Why has a change been made?
For the WDA waste movements are recorded in a way which correctly
represents how the material is collected and processed. Back-allocation only
affects the return in terms of the comments which have been used.
For the WCA the material is being correctly recorded as material collected as
residual waste; unlike the previous system which required material to be split
between Qu23 and Qu18.
The use of the “Material from WDA” process allows the back-allocated
tonnages to be clearly identified and so can be included in applicable
calculations such as NI192, but then omitted from any figures which feed
through to WDA calculations (as the WDA has recorded the recycling tonnages
in their own return any feed through from the WCA would be double-counting).
Other items
• Due to the flexibility of Qu100 the structure of the raw data which sits
behind it has had to be created in a different format to that of the original
question set.
• This means that a significant amount of re work has been undertaken on
the validation sheet, PI sheet and other reports to get them working from
Qu100.
• Your LA’s PI sheet, accessible through the data authorisation page, will
provide you with details PI information for your LA.
• A summary of headline PI figures is available from the summary reports
page for all LAs using Qu100