session: [session title] · • frequency and voltage load shedding schemes operate from 250 msto...
TRANSCRIPT
Rhode Island Convention Center • Providence, Rhode Island
Department of Defense (DOD) ‐Environmental Security Technology Certification Program (ESTCP) ‐
Portsmouth Naval Shipyard ‐ Fast Load Shedding Microgrid
Session: [Session Title]
Russell Gagner, PENaval Facilities Engineering Command – Mid Atlantic
August [XX], 2016
Energy Exchange: Federal Sustainability for the Next Decade
Fast Load Shedding Bottom Line Up Front
2
Technology
• Microgrid Controls System (MCS) with intelligent fast load shedding• Battery Energy Storage System (BESS) / Inverter for Frequency Regulation with Independent
Operator for New England (ISO‐NE) and Microgrid Capacity
Problem/Solution:
• Shipyard on‐site generation assets are overloaded when utility grid fails, despite ample on‐site generation capacity for critical loads. Very high speed load shedding is required to maintain gas turbine generation stability under fault conditions.
• Frequency and voltage load shedding schemes operate from 250 ms to seconds…too slow. Contingency based systems operate in the range of 160 to 400 ms…too slow. The GE C‐90 fast load shedding system can perform complete operation in less than 20 ms.
Cost Savings & Improvements:
• Power outages can lead to six figure damages in terms of lost production and equipment damage.
• Reduces preemptive generation dispatching and/or islanding impacts.• Better aligns with EPA requirements for utilizing generation assets in “non‐emergency”
conditions.
Contractors: Ameresco, Inc., General Electric
Energy Exchange: Federal Sustainability for the Next Decade
Technical Objectives
3
Solve electric resiliency problem for Portsmouth Naval Shipyard Microgrid by reducing base wide outages caused by fault induced instability.
Maintain centralized power production to critical facilities and waterfront assets.
Demonstrate ability to integrate / control battery energy storage system (BESS) with on‐site generation
Demonstrate that these assets can help ISO solve grid stability and regulation issues in a cost‐competitive way with revenue potential for the Navy
Document applicability to nearly all DoD sites and industrial Microgrids.
Energy Exchange: Federal Sustainability for the Next Decade
Technology/Methodology Description
5
480 V
480 V480 V
34.5 kV
13.2 kV
Energy Exchange: Federal Sustainability for the Next Decade
Technology/Methodology Description
6
480 V
480 V480 V
34.5 kV
13.2 kV
Energy Exchange: Federal Sustainability for the Next Decade
Technology/Methodology Description
7
DG#1
DG#2
Main Substation Controllers
13.2 kV
HMI
Automation Programs
RTU
Router†
ISO-NEComm Circuits
Regulation Msgs
Shipyard SCADA
Power Plant
Substations 1-2
Loads served by
the PP
4 6
Sta. ServicePP Rect.
3
Trip signals
~
Controller
HMI BESS
Telemetry and control
High-speed logic onunder-freq / bkr trip
2
Substation 32
LoadsSubstation1
2Feeder Controllers
Trip9
Telemetry,status, control
P(gens,loads,plant)
1 MVA
Feeder Controllers
Telemetry & control
GTG#1
GTG#2
Overload signal
Substation 1
UtilityLoads
3Feeder Controller
Trip2
Telemetry and control
Loss of Utility
1. Monitor all sources and loads2. Loss of Utility3. Priority load shed to preserve
power plant and critical areas4. NAVFAC: Bring addition
generation on-line5. NAVFAC: Pick-up add’l critical
loads
Technical Approach
Energy Exchange: Federal Sustainability for the Next Decade
Construction Challenges: Constructability Risk
10
Breaker Unit Trip 52B CTs PTs LOOP FD RADIAL FD Generator
Franklin
F‐1 1A X* X** X
F‐1 2A X X X
F‐5 6A X X X
F‐9 2B X X X
F‐10 3B X X X
F‐12 1 X* X** X
AUX Cab X
* F‐1 and F‐12 are wired for future FLS Tripping however not used.
** F‐1 and F‐12 52B contacts are wired in series to indicate loss of utility to trigger FLS scheme.
Risks
Need to remove existing OOS SCADA wiring to clear paths.Franklin Substation has undergone three major modifications.Original switchgear did not have wires labeled from the factory.Oldest switchgear with older style components.Connection to Central Maine Power
Energy Exchange: Federal Sustainability for the Next Decade
Basic Commissioning
11
Pre‐Testing Inspections:
• Multi party wire by wire point to point verification of installation• Visual inspections of all hardware for damage, correct installation practices, proper labeling,
removal of any temporary wiring, and verification of correct position of test switches.
System Start‐up and integrity tests
Communications testing including Goose Messaging
System Input and Output Testing including verifying status in the server.
Human Machine Interface Verification
Key attributes of Plan: Significant formality and don’t trip anything!!!
Energy Exchange: Federal Sustainability for the Next Decade
Performance Verification Testing (PVT)
12
Phase 1 PVT: (not too stressful)
• Place System in Operation• Disable Tripping on Critical Feeders – Open Trip output on Test Switches• Enable Tripping on non‐Critical Feeders• Establish Summer and Winter MicroGrid Configurations• Simulate a Loss of Power Initiation
Outcome: Issues with load shed calculations. Corrections made and successfully retested.
Phase 2 PVT: (very stressful)
• Place System in Operation• Place MicroGrid in Winter Alignment (~10 MW production)• Pull the plug on the utility. Observe Operation. Restore Distribution System• Place System in Operation• Place MicroGrid in Summer Alignment (~5 MW Production)• Pull the plug on the utility. Observe Operation. Restore Distribution System
Outcome: 100% expected outcome – Success!! Concern….divorced from a perfectly good power source….what happens under fault conditions???
Energy Exchange: Federal Sustainability for the Next Decade
Real Life – In Service
13
First Week:
• Place System in Operation• Performed normal weekly testing of power plant diesel generators.• One unit tripped offline at 500 kW…initiating a 500 kW fast load shed event• Taking out most important building on shipyard…Commander’s office• Diesel Generators were improperly programmed…fixed!!
June 2016: First real life event…wish it was a squirrel!
• MicroGrid in Summer Alignment (~5 MW production)• Large phase to phase to ground fault of group operated air break switch just
upstream of shipyard intertie connection.• Fast load shed operated as designed… 1 ms after gas turbine tripped offline• Investigating gas turbine differential trip on fault outside zone of protection
July 2016: Second real life event…wow already…on a Monday morning .
• MicroGrid in Summer Alignment (~5 MW production) with diesels test underway• Single line to ground fault on utility provider• System worked flawlessly…retained power plant and all critical loads