![Page 1: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/1.jpg)
Senior Thesis Presentation: The Westlake Recreation Center
Summer PadgettFaculty Advisor: Dr. MistrickWestlake Recreation CenterWestlake, OhioElectrical / Lighting OptionApril 13th, 2004
![Page 2: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/2.jpg)
Building Information
Building Information:
• This facility serves as a park and recreation center for the citizens of Westlake.
• Total Building Area: 82,710 ft2
• Total cost of the construction: $15.3 million dollars
• Features four swimming pools, a gymnasium, locker rooms, a fitness room, a multi-purpose room, a babysitting room, a community room and recreation department offices.
![Page 3: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/3.jpg)
Discussion TopicsLIGHTING Redesign of the lighting and controls systems
for 3 indoor spaces ELECTRICAL Addition of a generator so that the gym may
be used as an emergency shelter and the corresponding load redistribution and emergency panel addition
CM Cost analysis of a power factor correctionHVAC Mechanical analysis of adding a more efficient
glazing to the windows in one of my spaces
![Page 4: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/4.jpg)
LIGHTING – Lobby
Total Ceiling Height: 27’-0”
SURFACES Reflective Wood Ceiling:
0.6 Burnt Sienna Quarry Floor
Tiles: 0.23
Alkyd Eggshell Walls: 0.5 Windows: 0.73
![Page 5: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/5.jpg)
LIGHTING – Lobby
Main Main EntranceEntrance
LOBBLOBBYY
LOUNGLOUNGE AREAE AREA
Stairs to Stairs to MezzanineMezzanine
ReceptiReception Areaon Area
SNACK SNACK AREAAREA
![Page 6: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/6.jpg)
LIGHTING – Lobby
Design Issues: Daylight
Design Ideas: Since the ceiling is so high, I wanted to
choose lighting that would bring it down some to make the lobby more inviting
Warm up the reception area so people will be drawn towards it
Carry in the fixture theme from outside
![Page 7: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/7.jpg)
LIGHTING – Lobby
Equipment Selection:Reception Area: 2’x2’ Fluorescent Troffers over the desks Fluorescent Wallwashers on back wall Mini-Pendants lining the exterior of the desk CFL Downlights where the ceiling is lower in
frontLobby: Arm-mounted sconces Metal Halide Pendants Downlights in the sitting area up the stairs Sconces lining the brick wall going up the stairs
![Page 8: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/8.jpg)
LIGHTING – Lobby
Renderings and Light Levels:
* THIS SLIDE STILL NEEDS WORK – LIGHT CALCS NOT YET COMPLETE - MAY NEED TWO SLIDES TO SHOW RENDERINGS – DAYLIGHT RENDERINGS MAY ALSO BE SHOWN HERE
![Page 9: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/9.jpg)
LIGHTING – Lobby
Renderings and Light Levels:
* UNDER CONSTRUCTION!!
![Page 10: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/10.jpg)
LIGHTING – Lobby
Renderings and Light Levels:
* UNDER CONSTRUCTION!!
![Page 11: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/11.jpg)
LIGHTING – Community Room
Total Ceiling Height: 13’-3”
SURFACES Ceiling: 0.78 Carpet Floor:
0.15 Alkyd Eggshell
Walls: 0.5 Windows:
0.73
![Page 12: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/12.jpg)
LIGHTING – Community Room
Main Main EntrancesEntrances
4 4 covescoves
Round Round tables tables throughothroughout the ut the roomroom
Moveable Moveable partitionpartition
WindoWindowsws
WindoWindowsws
WindoWindowsws
![Page 13: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/13.jpg)
Design Issues: Daylight
Design Ideas: Make the room less formal looking,
more business-like Flush Ceiling
LIGHTING – Community Room
![Page 14: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/14.jpg)
Equipment Selection:Option 1: Less Formal Indirect/Direct Pendants
hanging from coves CFL Downlights throughout the room Wall SconcesOption 2: Fluorescent strips in coves Small low-voltage MR16 downlights in coves Wall Sconces
* All bulbs 3000K
LIGHTING – Community Room
![Page 15: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/15.jpg)
Renderings and Light Levels:
LIGHTING – Community Room
* THIS SLIDE STILL NEEDS WORK – LIGHT CALCS NOT YET COMPLETE - MAY NEED TWO SLIDES TO SHOW RENDERINGS
![Page 16: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/16.jpg)
Renderings and Light Levels:
LIGHTING – Community Room
* UNDER CONSTRUCTION!!
![Page 17: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/17.jpg)
Renderings and Light Levels:
LIGHTING – Community Room
* UNDER CONSTRUCTION!!
![Page 18: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/18.jpg)
LIGHTING – Multi-Purpose Room
Total Ceiling Height: 13’-0” around perimeter then slopes to 24’-0”
SURFACES Wood Ceiling:
0.2 Northern Hard
Maple Floor: 0.75
Alkyd Eggshell Walls:
0.5 Windows: 0.73
![Page 19: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/19.jpg)
LIGHTING – Multi-Purpose Room
Ballet Ballet barsbars
with full-with full-
lengthlength
mirrorsmirrors
on 3 of on 3 of thethe
wallswalls
EntrancEntrance from e from interiorinterior
Entrance Entrance from from exteriorexterior
Sloped, Sloped, wood wood ceilingceiling
SkylighSkylight in t in centercenter
![Page 20: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/20.jpg)
Design Issues: Daylight
Design Ideas: Incorporate lighting that will not
create a lot of glare on the highly reflective floor
Make the dance studio more inviting by adding some pendants
LIGHTING – Multi-Purpose Room
![Page 21: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/21.jpg)
Equipment Selection: Direct/Indirect pendants to hang from
the start of the skylight CFL Downlights around the perimeter
the room Wall Sconces Fluorescent strips in the coves
* All bulbs 3000K
LIGHTING – Multi-Purpose Room
![Page 22: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/22.jpg)
LIGHTING – Multi-Purpose Room
Renderings and Light Levels:
* THIS SLIDE STILL NEEDS WORK – LIGHT CALCS NOT YET COMPLETE - MAY NEED TWO SLIDES TO SHOW RENDERINGS
![Page 23: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/23.jpg)
LIGHTING – Multi-Purpose Room
Renderings and Light Levels:
* UNDER CONSTRUCTION!!
![Page 24: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/24.jpg)
LIGHTING – Multi-Purpose Room
Renderings and Light Levels:
* UNDER CONSTRUCTION!!
![Page 25: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/25.jpg)
LOAD REDISTRIBUTION PROCESS:
1) Determined Essential Loads: Gym lighting, receptacles Locker room lighting, receptacles Kitchen Lighting, Receptacles, and Equipment –
Refrigerator, ovens, microwaves HVAC equipment that services these areas
2) Sized a generator and emergency transfer switch based on the calculated loads (taking all demand factors into account)
3) Selected an emergency panel
4) Located generator 25’ from side of building (NEC code)
ELECTRICAL – GENERATOR ADDITION
![Page 26: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/26.jpg)
• The selected equipment will appear here with an explanation of why it was chosen
• A map of the gym in relation to the exits,
locker rooms and kitchen will also be shown
here
ELECTRICAL – GENERATOR ADDITION
![Page 27: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/27.jpg)
*Analyzed the financial impact of a power factor correction
based off of 12 months worth of utility bills
PROCESS1) PF = cos [tan-1(rKVA Demand/Measured KVA
load)]2) Calculated the PF for all 12 months Medium
General Service Schedule: REACTIVE DEMAND CHARGE = $0.48 per rKVA
3) Reactive billing demand = KW*(kVAR Hours/ kW Hours) – 30
5) Actual cost per month = Reactive billing demand*($0.48 / hour)
CM – PF CORRECTION
![Page 28: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/28.jpg)
PROCESS (continued):
6) With the existing and desired power factors use the capacitor correction table to find a multiplier
7) Multiply the building’s electrical load by this number to get the KVAR of capacitors required
RESULTS:Total KVAR cost for 2002: $1691.15100 KVAR of capacitors needed to correct PFCost of 100 KVAR capacitor = $828 (Sprague
Corp.)Total savings for one year = $863.15*Almost an immediate payback!!
CM – PF CORRECTION
![Page 29: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/29.jpg)
Here I plan to show the results of a mechanical
energy analysis when a more efficient glazing is
used on the windows in the lobby
CURRENT GLAZING PROPERTIES:1. Shading Coefficient: 0.812. Visible Light Transmittance: 73 percent3. Visible Light Reflectance: 17 percent4. Summer Value: 0.385. Winter U Value: 0.35
HVAC – MECHANICAL BREADTH
![Page 30: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/30.jpg)
Here I will show the new glazing properties and
heat load calculations
HVAC – MECHANICAL BREADTH
![Page 31: Senior Thesis Presentation: The Westlake Recreation Center Summer Padgett Faculty Advisor: Dr. Mistrick Westlake Recreation Center Westlake, Ohio Electrical](https://reader030.vdocuments.site/reader030/viewer/2022020106/56649e915503460f94b966cf/html5/thumbnails/31.jpg)
• Van Dijk, Westlake, Reed, Leskosky – Cleveland, OH
• Faculty Advisor Dr. Richard Mistrick• Dr. Martin Moeck• Professor Ken Davidson – PSU Facilities
Engineering• Michael Rump – Westlake Recreation
Department• Bob Kelly – Engineer for the City of Westlake• John Durkee – Bacik, Karpinski, & Associates• Rajeev Chokshi – VWRL Architects and
Engineers• Phil LiBassi, Principal – VWRL Architects and