Senior Project Electrical Engineering 2010 Energy Monitoring Demarcus Hamm Advisor: Prof. Cherrice Traver Abstract Goals ECE Lab Connection Diagram Design Schematic Acknowledgements • Prof. Cherrice Traver • Lance Spallholz • Jay Dulmaa • Robert Tupelo-Schneck • Eric Truslow • Union College • Gary Thomas This project combines research of the Smart Grid system and energy monitoring systems. The project will use an energy monitoring system to simulate smart meters that will be used in the Smart Grid system. We will do this by using an energy monitoring system to measure the energy consumption in the electrical engineering labs. The analysis of this data will provide us information that could lead to energy savings by making us more aware of wasteful energy use or helping to create an energy management system. • Provide educational display for students, faculty, and visitors to raise awareness of energy consumption and Smart Grid ideas. • Gain information that could lead to future management systems which would lead to energy savings. • Create a system that could be expanded for greater benefits. This diagram shows which panel the outlets and lights in each ECE lab are connected to. The number beside the lines connected to the outlets show how many circuits on the panel are connected to outlets in the room. The lights in rooms 100, 102, 104, and 106 are connected to 2 circuits. The other lights are connected to only one. Design Requirements In order for us to meet our goals the system must meet certain design requirements. The design must: • Use wireless technology • Store data • Graphically display data • Contain a separate visible display • Monitor more than one circuit in a panel • Be expandable The design will use the TED 5002-G system which consist of two measuring and transmitting units (MTUs), four current transformers, and one gateway. The current transformers will clip on to four circuits and the panel and measure the current. The MTUs will sample the voltage and perform calculations to get real RMS power then send this information through the circuits to an outlet connected to the gateway. The gateway will then store the data and send it through the network to the visual display. Appliances Power Consumption (W) Room 106 Room 104 Room 102 Room 100 Total Monitor 84 672 1008 756 1092 3612 power save ~6 Computer 310 2480 3720 2790 4030 13330 power save ~3 Function generator 28 224 0 224 224 700 Lab Statio n Multimeter 10 80 0 80 80 250 8325 Power Supply 195 1560 0 1560 1560 4875 Oscilloscope 100 800 0 800 800 2500 Printer HP2300dn 426 426 0 0 0 852 standby 8.8 power save 8.4 Printer p4014 800 0 800 800 800 3200 power save 12 standby 17 Printer P3005dn 600 0 600 0 0 1200 power save 9 standby 9 Projector 370 0 370 370 370 1480 standby 6 Lights per bulb 32 2176 1536 2048 2048 7840 per unit 128 Maximum 8418 8034 9428 11004 Max Power Consumption in the Labs The table above shows the energy consumption in the ECE labs by load type and by room. The odd rooms and room 108 were not included because since these rooms are small and not as heavily used as others. This table was made to find out which type of load and which rooms used the most energy. After doing this our hypothesis was that since this was the maximum power consumption, the lights and the computers would be the highest because they are in use more than the other load types. Out of the rooms shown rooms 100 and 102 are the most commonly used. Communicatio n Diagram The figure above shows the communication layout in the project. The software is in circles and the hardware is in squares. The TED Footprints software comes with the TED system to display data. It is stored in the gateway and communicated to the Union College network. The It’s Electric software is a modified third party software we are using to display our data. It is run on antipasto and can be viewed from the network. The third party software was used because Footprints can not switch displaying minute, hour, and monthly data automatically. You also cannot tell which MTU you are observing without user interactions. Future Work • Software improvements • Add additional sensors to the set up • Change MTUs for 3 phase • Incorporate the circuits in the N100 panel MTU Compensation The display for the project will be in the ECE hall ways in a clear display case; therefore the following requirements must be met: • Must have internet access • Must be 2 inches depth or less • No user interactions required • Stand by when no one is around it To address the stand by mode we looked into passive infrared sensors that would turn the circuit off when no one is present and display options that have remotes to switch them into standby. Display Requirements The MTU has errors when working with 3 phase systems. The power factor calculation is off because of this and so the accuracy of the RMS real power suffers. To compensate for this we can connect the MTUs and CTs to one phase. This will take away our ability to use two different phases with one MTU. The other option is to wait and replace the MTUs when the 3 phase model is released in June.

Upload: amberlynn-douglas

Post on 29-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Senior Project Electrical Engineering 2010 Energy Monitoring Demarcus Hamm Advisor: Prof. Cherrice Traver Abstract Goals ECE Lab Connection Diagram Design

Senior ProjectElectrical Engineering 2010

Energy MonitoringDemarcus HammAdvisor: Prof. Cherrice Traver

Abstract

Goals

ECE Lab Connection Diagram

Design Schematic

Acknowledgements• Prof. Cherrice Traver

• Lance Spallholz

• Jay Dulmaa

• Robert Tupelo-Schneck

• Eric Truslow

• Union College

• Gary Thomas

This project combines research of the Smart Grid system and energy monitoring systems. The project will use an energy monitoring system to simulate smart meters that will be used in the Smart Grid system. We will do this by using an energy monitoring system to measure the energy consumption in the electrical engineering labs. The analysis of this data will provide us information that could lead to energy savings by making us more aware of wasteful energy use or helping to create an energy management system.

• Provide educational display for students, faculty, and visitors to raise awareness of energy consumption and Smart Grid ideas.

• Gain information that could lead to future management systems which would lead to energy savings.

• Create a system that could be expanded for greater benefits.

This diagram shows which panel the outlets and lights in each ECE lab are connected to. The number beside the lines connected to the outlets show how many circuits on the panel are connected to outlets in the room. The lights in rooms 100, 102, 104, and 106 are connected to 2 circuits. The other lights are connected to only one.

Design Requirements

In order for us to meet our goals the  system must meet certain design requirements. The design must:

• Use wireless technology• Store data• Graphically display data• Contain a separate visible display• Monitor more than one circuit in a panel• Be expandable

The design will use the TED 5002-G system which consist of two measuring and transmitting units (MTUs), four current transformers, and one gateway. The current transformers will clip on to four circuits and the panel and measure the current. The MTUs will sample the voltage and perform calculations to get real RMS power then send this information through the circuits to an outlet connected to the gateway. The gateway will then store the data and send it through the network to the visual display.

AppliancesPower Consumption (W)

Room 106

Room 104

Room 102

Room 100 Total

Monitor 84 672 1008 756 1092 3612power save ~6Computer 310 2480 3720 2790 4030 13330power save ~3

Function generator 28 224 0 224 224 700Lab

StationMultimeter 10 80 0 80 80 250 8325Power Supply 195 1560 0 1560 1560 4875Oscilloscope 100 800 0 800 800 2500Printer HP2300dn 426 426 0 0 0 852standby 8.8power save 8.4Printer p4014 800 0 800 800 800 3200power save 12standby 17Printer P3005dn 600 0 600 0 0 1200power save 9standby 9Projector 370 0 370 370 370 1480standby 6Lights per bulb 32 2176 1536 2048 2048 7840per unit 128

Maximum 8418 8034 9428 11004

Max Power Consumption in the Labs

The table above shows the energy consumption in the ECE labs by load type and by room. The odd rooms and room 108 were not included because since these rooms are small and not as heavily used as others. This table was made to find out which type of load and which rooms used the most energy. After doing this our hypothesis was that since this was the maximum power consumption, the lights and the computers would be the highest because they are in use more than the other load types. Out of the rooms shown rooms 100 and 102 are the most commonly used.

Communication Diagram

The figure above shows the communication layout in the project. The software is in circles and the hardware is in squares. The TED Footprints software comes with the TED system to display data. It is stored in the gateway and communicated to the Union College network. The It’s Electric software is a modified third party software we are using to display our data. It is run on antipasto and can be viewed from the network. The third party software was used because Footprints can not switch displaying minute, hour, and monthly data automatically. You also cannot tell which MTU you are observing without user interactions.

Future Work• Software improvements

• Add additional sensors to the set up

• Change MTUs for 3 phase

• Incorporate the circuits in the N100 panel

MTU Compensation

The display for the project will be in the ECE hall ways in a clear display case; therefore the following requirements must be met:

• Must have internet access• Must be 2 inches depth or less• No user interactions required• Stand by when no one is around it

To address the stand by mode we looked into passive infrared sensors that would turn the circuit off when no one is present and display options that have remotes to switch them into standby.

Display Requirements

The MTU has errors when working with 3 phase systems. The power factor calculation is off because of this and so the accuracy of the RMS real power suffers. To compensate for this we can connect the MTUs and CTs to one phase. This will take away our ability to use two different phases with one MTU. The other option is to wait and replace the MTUs when the 3 phase model is released in June.