Seminary Road Intersection
Improvements
Project Briefing
![Page 2: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/2.jpg)
MCDOT would like to brief the community on the ongoing work on the
Seminary Road Intersection Improvement project
Project Team
Project Description
Project Phasing
Schedule
Status
Q&A
![Page 3: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/3.jpg)
![Page 4: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/4.jpg)
![Page 5: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/5.jpg)
![Page 6: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/6.jpg)
![Page 7: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/7.jpg)
![Page 8: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/8.jpg)
![Page 9: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/9.jpg)
![Page 10: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/10.jpg)
![Page 11: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/11.jpg)
![Page 12: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/12.jpg)
![Page 13: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/13.jpg)
Construction Schedule
Start of Construction - March 2020
Combined Phases 1, 2 - July 2020
Phase 3 - September 2020
Phase 4 – December 2020
Phase 5 – February 2021
Phase 6 – March 2021
Intersection Seminary Rd and 2nd Ave - April 2021
Substantial Completion - April 2021
![Page 14: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/14.jpg)
Project Status
Currently working on Phases 1, 2
Completed storm drain, rough grading on Seminary Place ongoing
Curb and gutter, driveways and sidewalks along Seminary Place will be completed soon
Phase 3 will start next
![Page 15: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/15.jpg)
Seminary Place road closure
![Page 16: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/16.jpg)
Storm drain installation at Seminary Place
![Page 17: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/17.jpg)
Grading at Seminary Place and 2nd Ave
![Page 18: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/18.jpg)
Grading at Seminary Place
![Page 19: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/19.jpg)
Contact
Field Office: Tom Kidwell
301-328-5819 or 301-328-5810
Area Engineer: Bill Sittinger
Chief Construction: Marcelo Cortez
![Page 20: Seminary Road Intersection Improvements · 5/7/2020 · Construction Schedule Start of Construction - March 2020 Combined Phases 1, 2 - July 2020 Phase 3 - September 2020 Phase 4](https://reader036.vdocuments.site/reader036/viewer/2022070906/5f7ac60ef146ec49d868bac8/html5/thumbnails/20.jpg)
For more information and regular updates please visit our website or follow us on twitter
https://www.montgomerycountymd.gov/dot-dte/projects/seminary/index.html
https://twitter.com/MoCo_DTE #SeminaryRd
Q&A