selected roads red · of the auditor-general on selected road works in ghana (1) tetteh quarshie to...
TRANSCRIPT
REPUBLIC OF GHANA
PERFORMANCE AUDIT REPORT
OF THE AUDITOR-GENERAL ON SELECTED
ROAD WORKS IN GHANA
(1) TETTEH QUARSHIE TO MADINA ROAD,
(2) AYAMFURI TO NEW OBUASE ROAD; AND
(3) THE BOLGATANGA, BAWKU TO POLIMAKOM ROAD
Our VisionOur Vision is to become a world-class Supreme Audit I n s t i t u t i o n d e l i v e r i n g professional, excellent and cost-effective services.
This report has been prepared in compliancewith Article 187(2) of the 1992 Constitutionof Ghana and Section 13(e) of the Audit Service Act, 2000 (Act 584)
Daniel Yaw DomelevoAuditor-GeneralGhana Audit Service28 November 2019
The study team comprised:Elliott Asiedu, Theophilus Eghan and Samuel A. Donkoh under the Supervision of Lawrence N. Ayagiba, Assistant Auditor-General and Benjamin G. Codjoe, Deputy Auditor-General in charge of Performance and Special Audits
This report can be found on the Ghana Audit Service website: www.ghaudit.org
For further information about the Ghana Audit Service, please contact:
The Director, Communication Unit Ghana Audit Service Headquarters Post Office Box MB 96, Accra.
Tel: 0302 664928/29/20 Fax: 0302 662493/675496 E-mail: [email protected]: Ministries Block 'O'
© Ghana Audit Service 2019
i |Performance Audit Report of the Auditor-General on selected Roads
TRANSMITTAL LETTER Ref. No. AG.01/102/Vol.2/132
Office of the Auditor-General Ministries Block “O”
P. O. Box MB 96 Accra
Tel. (021) 662493 Fax (021) 662493
GA-110-8787 28 November 2019
Dear Mr. Speaker,
PERFORMANCE AUDIT REPORT OF THE AUDITOR ON (1) TETTEH QUARSHIE
TO MADINA ROAD; (2) AYAMFURI TO NEW OBUASE ROAD; AND (3) THE
BOLGATANGA, BAWKU TO POLIMAKOM ROAD
I have the honour, in accordance with Article 187(2) of the 1992 Constitution of Ghana
Sections 13(e), and 16 of the Audit Service Act, 2000 (Act 584) to present to you a performance
audit report on selected roads.
The Government of Ghana invested GH¢ 8.24 billion in construction of new and upgrading of
old roads between 2012 and 2018 mostly funded by loans.
Ghana Highway Authority Act, Act 540 of 1997 mandates GHA, to design and supervise the
construction of trunk roads and in some cases render consultancy services to ensure contractors
meet specification.
The rampant deterioration of roads few months after their completion and handing over has
been a concern to many Ghanaians and questions have been asked about the quality of the road
works carried out. Similarly, complaints abound about delays in completing road works due to
variations and delayed payments contributing to cost overruns because of fluctuations and in
many cases interest on delayed payments.
Roads are integral part of the transport system as it links main cities, towns and villages. It
links agricultural production areas with local, regional and national markets and it carries in
excess of 97% of all passenger and freight traffic in Ghana and thus a main economic player.
The purpose of the audit was to assess and give assurance to Government that GHA ensures
roads awarded and constructed under their supervision meet the required standards and
guarantees Value for Money
ii |Performance Audit Report of the Auditor-General on selected Roads
We scoped three road projects constructed between 2012 and 2019, under “Client design
arrangement contract” method for the audit. The roads were Tetteh Quarshie –Madina,
Ayamfuri-New Obuase and the Bolgatanga Bawku-Polimakom) under implementation from
2014 to 2019 by the Ghana Highway Authority (GHA) to determine whether they met the
required standard specifications and guaranteed Value for Money.
Our audit disclosed that Feasibilities studies had been carried out but were not reviewed before
implementation to take note of traffic changes in time between the studies and implementation.
Budgetary estimates for the projects were based on preliminary/unrevised designs and
provisional sums and so did not give a true reflection on the final cost during implementation
through variations and additional costs.
We also noted that two contractors were sole sourced for the projects. We could not give our
opinion on the fairness of the selection of supervising consultants because there was no
evaluation report on how the selection was done.
I have made recommendations to GHA, in the area of project planning, budgeting and
implementation to bring about improvement in road construction to ensure the country gets
Value for Money for such projects
I also recommended to GHA to institutionalised prescribed maintenance schedules to prolong
road life in the country.
I trust that this report will meet the approval of Parliament.
Yours faithfully,
DANIEL YAW DOMELEVO AUDITOR-GENERAL THE RIGHT HON. SPEAKER OFFICE OF PARLIAMENT PARLIAMENT HOUSE ACCRA
iii |Performance Audit Report of the Auditor-General on selected Roads
Table of Contents
EXECUTIVE SUMMARY ...................................................................................................... vi
1.0 Introduction ..................................................................................................................... 1 1.1 Reasons for the Audit .................................................................................................. 1 1.2 Audit purpose and scope ............................................................................................. 3
1.2.1 Purpose ........................................................................................................................ 3
1.2.2 Scope ............................................................................................................................ 3
1.3 Audit Objective ........................................................................................................... 3
1.4 Methodology ............................................................................................................... 4
1.4.1 Sampling ...................................................................................................................... 4
1.5 Methods of data collection .......................................................................................... 6
1.5.1 Document review ......................................................................................................... 6
1.5.2 Interviews .................................................................................................................... 6
1.5.3 Field Inspection ........................................................................................................... 6
1.5.4 Material Laboratory Tests ............................................................................................ 9
2.0 Description of the audit area .............................................................................................. 11 2.1 Overview of the selected road projects ..................................................................... 14
2.1.1 Tetteh Quarshie to Madina Road Project ................................................................... 14
2.1.2 Ayamfuri to New Obuase Road Project .................................................................... 16
2.1.3 Bolgatanga-Bawku-Polimakom Road Project ........................................................... 17
2.2 Mandate of GHA ....................................................................................................... 19
2.2.1 Vision statement ........................................................................................................ 19
2.2.2 Mission statement ...................................................................................................... 19
2.3 Functions of GHA ..................................................................................................... 19 2.4 Sources of funding .................................................................................................... 20 2.5 Key players and stakeholders .................................................................................... 21
2.6 System description .................................................................................................... 22
iv |Performance Audit Report of the Auditor-General on selected Roads
3.0 FINDINGS, CONCLUSIONS AND RECOMMENDATIONS ....................................... 24 3.1.0 Introduction ............................................................................................................... 24 3.2 Planning for road projects (studies, design and budgeting) ............................................... 24
3.2.1 Feasibility Studies ........................................................................................................... 25
3.2.2 Project Design ................................................................................................................. 27
3.2.3 Budgeting ........................................................................................................................ 29
3.3.0 Procurement of consultant/contractors ........................................................................... 33
3.3.1 Procurement of Sonitra Limited for the Construction of the Tetteh Quarshie -Madina
Road Project ............................................................................................................................. 33
3.3.2 Procurement of China Jiangxi Corporation for International Economic and Technical
Cooperation for the construction of the Ayamfuri-New Obuase Road Project ....................... 36
3.3.3 Procurement of Consultants and Contractors for the Bolgatanga-Bawku-Polimakom
Road 40
3.3.3.1 Procurement of Messrs Queiroz Galvao Construction Limited for the construction of
the Bolgatanga-Bawku-Polimakom Road Project ................................................................... 40
3.4.0 Implementation of the project (managing scope, cost, time and ensuring project
quality) 45
3.4.1 Implementation of The Tetteh Quarshie- Madina Road Project ............................... 46
3.4.1.1 Scope management (variations) ................................................................................. 46
3.4.1.2 Cost management (Payment for works) ................................................................... 52
3.4.1.3 Time management (Completing the works on time) ................................................. 57
3.4.1.4 Delivering the road project to the quality specified .................................................. 60
3.4.2 Implementation of the Ayamfuri to New Obuase Road Project ............................... 66
3.4.2.1 Scope management (variations) ................................................................................. 66
3.4.2.2 Cost management (Payments for works) .................................................................. 70
v |Performance Audit Report of the Auditor-General on selected Roads
3.4.2.3 Time management (Completing the works on time) ................................................ 73
3.4.2.4 Delivering the road project to the quality specified ................................................... 74
3.4.3 Implementation of the Bolgatanga-Bawku-Polimakom Road Project ...................... 82
3.4.3.1 Scope management (variations) ................................................................................ 82
3.4.3.2 Cost management (Payment for works ) .................................................................. 83
3.4.3.3 Time management (Completing the works on time) ................................................ 86
3.4.3.4 Delivering the road project to the quality specified .................................................. 88
3.5 COMPLETION AND DOCUMENTATION ........................................................... 95
3.5.1 Completion ................................................................................................................ 95
3.5.1 Documentation ........................................................................................................... 96
3.6 OVERALL CONCLUSION ..................................................................................... 97 Appendixes, Analysis Sheets & Some Supporting Document ................................................ 99
Appendix 1. List of Documents reviewed ............................................................................... 99 Appendix 2. List of interviewees ........................................................................................... 100 Appendix 3. Field inspection and methodology .................................................................... 102
Appendix 4. Laboratory test results of asphalt core samples ................................................. 104 Appendix 5 Key players and their roles ................................................................................. 108 Appendix 6. Details of system description ............................................................................ 110
Appendix 7. Details of Variation Orders on Tetteh Quarshie Madina Road Project ............ 111 Appendix 8. Table of road widths, core thickness as measured on site and tests on concrete
structures ................................................................................................................................ 114 Appendix 9. Payment Details ............................................................................................... 120
vi |Performance Audit Report of the Auditor-General on selected Roads
EXECUTIVE SUMMARY
1. Ghana has about 78,401 km of road network linking communities in the
country thus promoting commerce and cultural integration. The Government
has invested GH¢ 8.24 billion in construction of new and upgrading of old
roads between 2012 and 2018 mostly through loans.
2. The roads are constructed under the supervision of the Ghana Highway
Authority, mandate by law Act 540 of 1997, to design and supervise the
construction of trunk roads and in some cases render consultancy services only
to ensure contractors meet specification.
3. The rampant deterioration of roads few months after their completion
and handing over has been a concern to many Ghanaian and the questions has
been asked about the quality of the works carried out. Similarly, complaints
abound about delays in completing roads works due to variations, delayed
payments resulting in cost overruns caused by fluctuations and in many cases
interest on delayed payments
4. In line with Section 13(e) of the Audit Service Act 2000, Act 584 the
Auditor-General commissioned an audit of selected roads procured between
2012 and 2019 by the Ghana Highway Authority (GHA) to determine whether
they met the required standards and guaranteed Value for Money as an
assurance on the performance of GHA.
What we did.
We selected three roads, (Tetteh Quarshie –Madina, Ayamfuri-New
Obuase and the Bolgatanga Bawku-Polimakom) procured under client
design arrangement contract method. We reviewed documents related
to the selected road projects, interviewed personnel, contractors and
consultants on the projects. We also inspected and took physical
vii |Performance Audit Report of the Auditor-General on selected Roads
measurements of the works as well as extracting core samples of the
roads which were tested in the laboratory.
The objective was to assess whether GHA;
i. followed accepted procedure and good practice in planning for road
projects (Feasibility studies, design and budgeting),
ii. followed due process in engagement of consultants and contractors to
execute the selected road projects,
iii. put measures in place to deliver the selected road projects within scope,
cost, time and to quality standards, and
iv. ensured the road projects were completed and all relevant certificates
issued (Contract documentation and maintenance schemes).
What we found
Planning for road projects
5. Feasibilities studies had been carried out but were not reviewed before
implementation to take note of traffic changes in time between the studies and
implementation. GHA provided estimates for the three projects to serve as
budget for the Ministry of Roads and Highways in sourcing for funds for the
projects. Apart from the Ayamfuri-New Obuase project, the budgets for the
Tetteh-Quarshie and Bolgatanga-Bawku-Polimakom road projects were based
on preliminary/unrevised designs and provisional sums and did not give a
true reflection of the final cost during implementation through variations and
additional costs.
viii |Performance Audit Report of the Auditor-General on selected Roads
Procurement of consultants and contractors
6. GHA generally followed the procurement laws and guidelines in
obtaining the services of the contractors for the three projects. It was difficult to
validate the fairness and transparency of the procurement processes for the
supervision consultant for the Ayamfuri-New Obuase road project and Sonitra
Limited for the Tetteh Quarshie Madina road project due to the absence of
evaluation reports and approval letters on the procurement. GHA used Sole
sourcing and restricted tendering as a preferred method for Queiroz Galvao
Construction Limited and Delin Consult for the Bolgatanga-Bawku-Polimakom
Project.
Implementation of the road projects within scope, cost, time and to quality
standards
7. The Tetteh Quarshie–Madina road project was largely constructed to the
required contract specification however the implementation process was
bedevilled by problems of poor management of scope, schedule, cost and
payment which resulted in significant cost and time overruns. The project
delayed by over 10 years and the variations and claims led to a rise in the Cedi
and US Dollar components of the contract sums by 624% and 187% respectively
from GH¢ 23,558,960.95 and US$ 17,414,431.78 to GH¢ 170,477,493.66 and US$
49,974,242.82.
8. The Ayamfuri-New Obuase road project took 64 months instead of 24
months to complete due to variations brought about by unknown site
conditions which should have been determined during the feasibility and
design stage. There were cost overruns of GH¢ 22,573,895.05 and US$
10,543,792.05 due to the variations, compensation of project affected persons,
relocation of utilities and claims for delay in payments. 12 out of 20 asphalt
ix |Performance Audit Report of the Auditor-General on selected Roads
cores extracted and measured along the stretch of the road did not meet the
specified of 100mm.
9. The Bolgatanga-Bawku-Polimakom road project had stalled as a result of
non-payment of IPC’s on time by the Road Fund Secretariat. The project, which
was supposed to have been completed in June 2019, is 19.45% complete. The
delay in payment of IPCs as at June 2019 has led to interest charges of GH¢
38,189,353.65 in addition to the original contract sum of GH¢ 612,743,844.64.
Completion and documentation
10. The Tetteh Quarshie-Madina and Ayamfuri New-Obuase Projects are
completed and GHA has issued completion certificates. The taking over
certificate for the Ayamfuri New-Obuase Project was issued on 14 September
2018. GHA took over the Tetteh Quarshie-Madina Project in sections beginning
on 23 May 2009 up to 13 February 2019.
11. Filing and maintenance of documents for the projects was not complete
and was difficult to have a complete trail of the progress of the projects
The way forward
Recommendations
12. Our review of planning processes for roads works supervised by GHA
shows that some efforts had been made to ensure that roads are properly
planned, designed and procured. To improve upon the planning processes, we
recommended that GHA should;
i. capture all intended roads projects in a strategic plan for planning
purposes and accountability.
ii. review design drawings of any project it intends to implement especially
where there has been a time laps between feasibility studies and
x |Performance Audit Report of the Auditor-General on selected Roads
implementation with its complementing bill of quantities prior to
tendering, and
iii. Estimates should be prepared from detailed drawings and not through
budgetary ceilings as practised to reduce the tendency of eliminating
items only to reintroduce them as variations
iv. Prepare adequately through planning to limit the use of sole sourcing,
v. Document all the processes leading to the award of contract including
evaluation reports, and
13. Analysis of data made available to us show that challenges exist during
implementation of road projects in the country in the areas of scope
management, payments for work done and ensuring projects are completed
within schedule to get the full benefit for users that has to be addressed. To
ensure proper implementation of current and future road projects, we
recommended that GHA should;
i. have complete drawings and designs that inform cost estimates and
clearly define the scope of works of all projects,
ii. desist from the practice of removing needed work items in order to
meet budget ceilings only to reintroduce them during implementation,
iii. Fulfil all relevant conditions of relocation and compensation precedent
to project commencement, and introduce cut off time to accept
payment of compensation to prevent residents taking advantage to
relocate on site earmark for road works.
iv. Treat additional works unrelated to ongoing projects not as variations
and should be subjected to separate procurement processes
v. Ensure that it seeks and obtains approval for all variations,
xi |Performance Audit Report of the Auditor-General on selected Roads
vi. Identify at an early stage the source of funding and possibly ring fence
such funds to meet all projected costs during implementation, and
vii. immediately institute and implement a policy on processing and
payment of IPCs within 56 days and sanction officers who delay each
IPC with cost of claims due to the delayed IPC.
1 |Performance Audit Report of the Auditor-General on selected Roads
CHAPTER ONE
1.0 Introduction
1.1 Reasons for the Audit
14. Roads play an essential part of economic development and can
contribute significantly to the socio-economic and cultural development of any
country. A good road network helps to link communities together and
enhances commerce, thereby improving the economic wellbeing of the citizens.
Roads have also enhanced cultural exchanges between communities and have
contributed to improved access to health care facilities in a timely manner.
15. Roads are integral part of the transport system as it links main cities,
towns and villages. It links agricultural production areas with local, regional
and national markets and it carries in excess of 97% of all passenger and freight
traffic in Ghana.
16. The Ministry of Roads and Highways estimates that Ghana has about
78,401 km of road network as of December 2017. Of this, 14,583 km are trunk
roads, 48,357 km are feeder roads and 15,462 km are urban roads. These roads
play a significant role in Ghana’s economy as road transport is the most widely
available form of transport (96%)1 in the country. At a press briefing, the
Minister of Roads and Highways, revealed that about 61 per cent of roads in
the country are classified as poor2.
17. Between 31 December 2012 and 1 January 2018, a total amount of about
GH¢ 8.24 billion3 was spent on construction of new and upgrading of old roads.
1https://www.gipcghana.com/invest-in-ghana/why-ghana/infrastructure/transportation-infrastructure.html (accessed on 18 Jul. 19) 2 url: https://www.myjoyonline.com/news/2017/December-31st/61-of-ghanas-classified-as-poor.php 3 Total disbursement by MRH from 2013 to 2017
2 |Performance Audit Report of the Auditor-General on selected Roads
Despite the investments in the road sector, drivers and passengers alike are
worried about the constant deterioration of roads, months after they have been
completed and handed over by contractors. The frequent repairs and
maintenance of the same roads repeatedly with attendant cost implications,
mean that new ones are never considered and undermines government’s quest
to expand the road network.
18. Ghana as a country is unable to finance road construction solely from
internally generated funds and has to resort to borrowing with interest
payments from international financial institutions such as World Bank, African
Development Bank, European Union, Japan bank for International Co-
operation etc. It becomes a double agony when a road constructed from a loan
starts deteriorating when the loan is yet to be settled. The public has expressed
similar sentiments and concerns about extended construction time of roads in
Ghana. In some instances, a road project scheduled to be completed within 24
calendar months sometimes take 60 months or more to complete.
19. With ever increasing budgetary demands from various sectors such as
Health Care, Agriculture, Education etc. there is the need to ensure that moneys
allocated for road construction are properly used. Year by year budgetary
allocation for roads works continue to increase as the road network is estimated
to grow. For instance, between 2014 and 2017 the Ministry of Roads and
Highways planned budget increased from GH¢ 2.1 billion to GH¢ 6.7 billion.
Proper planning and budgeting are therefore required to ensure value for
money to reduce the wastage, inconvenience to motorists and save the
country’s money. It must therefore be a priority that these roads meet the
prescribed quality specifications, cost and time, to serve their built-in project
life.
20. In view of this, the Auditor-General under his mandate in the Audit
Service Act (Act 584), 2000, Section 13(e), commissioned this Performance Audit
3 |Performance Audit Report of the Auditor-General on selected Roads
to assess and give assurance to Parliament and the general public that roads
constructed and supervised by the Ghana Highway Authority (GHA) meet the
required standards and ensure value for money.
1.2 Audit purpose and scope
1.2.1 Purpose
21. The purpose of the audit was to assess and give assurance to government
that GHA ensures roads awarded and constructed under their supervision
meet the required standards and guarantees Value for Money.
1.2.2 Scope
22. We carried out the audit on three selected Ghana Highway Authority
supervised roads, under implementation from 2012 to 2019. We carried out the
audit from March to June 2019 and focused on:
v. Planning (Studies, design and budgeting)
vi. Procurement of Contractors and Consultants (Selection and award of
contract)
vii. Execution of the project (managing scope, cost, schedules and ensure
project meets quality specifications)
viii. Closure of the projects (Contract documentation and maintenance
schemes)
1.3 Audit Objective
23. The objectives of the audit were to assess and determine within the focus
of the audit, whether GHA:
4 |Performance Audit Report of the Auditor-General on selected Roads
i. followed accepted procedure and good practice in planning for road
projects,
ii. followed due process in engagement of consultants and contractors to
execute the selected road projects,
iii. put measures in place to deliver the selected road projects within scope,
cost, time and to quality standards, and
iv. ensured the road projects were completed and all relevant certificates
issued (Contract documentation and maintenance schemes).
1.4 Methodology
24. We carried out the audit in accordance with the general requirement of
INTOSAI auditing standards for performance audit (ISSAI 3000). These
standards require that the audit is planned and performed in a manner as to
obtain reasonable assurance that the audit objectives are met. We engaged a
technical consultant, with over 20 years in civil and road construction for the
period of the audit to provide technical support to the audit team. In
accordance with Section 29(1) of the Audit Service Act 2000, Act 584, GHA was
given 30 days to respond to our observation made in the Management letter per
our letter dated October 18, 2019 reference PSAD/PAU/PROJ/09/05.
1.4.1 Sampling
25. The audit team sampled eight road projects from the progress reports on
ongoing GHA projects contracted under Works Designed by the Employer
arrangement. Out of the sample, three projects were selected for the focus of the
audit. The projects were selected based on:
i. Status of completion
5 |Performance Audit Report of the Auditor-General on selected Roads
o We selected roads which should have been completed by 31
December 2018.
ii. Type of pavement
o Asphaltic roads were considered due to the high cost of
construction and possibility of using the asphalt coring machine to
take core samples for measurement and testing.
iii. Cost
o Projects which had exceeded their initial contract sum were
chosen.
iv. Location
o The road projects were selected from the Greater Accra, Central
and Upper East Regions for the first phase of these audits.
v. Source of funds
o Projects funded through both GoG and foreign components.
26. On basis of the criteria above, we selected the road projects shown in Table 1.
Table 1: Road Projects Selected for Audit
No. Name of
Project
Region Year
commenced
Expected year
of completion
Initial Contract Sum Funding
Source
1 Tetteh
Quarshie-
Madina
Greater
Accra
2006 2009 GH¢ 23,558,960.95 plus US$
17,414,431.78
Consolidated
Fund
2 Ayamfuri -
New Obuase
Central 2013 2015 GH¢ 13,641,596.55 plus USD
20,694,136.82
World Bank
3 Bolgatanga-
Bawku-
Polimakom
road project
Upper
East
2016 2019 GH¢ 612,743,844.64 Road Fund
Source: GHA progress report on projects as at 31 December 2018
6 |Performance Audit Report of the Auditor-General on selected Roads
1.5 Methods of data collection
27. The team reviewed documents, interviewed key players in the
construction of the selected roads and inspected the selected roads to take
measurement and extract asphalt core samples for testing in the Laboratory. We
applied these procedures to enable us triangulate our evidence that we
considered necessary and appropriate to provide such assurance that our audit
objectives are met.
1.5.1 Document review
28. We reviewed documents on the planning and implementation of the
three projects provided by GHA, Contractors, Consultants, Ministry of Roads
and Highways. The documents were reviewed to give the audit team in-depth
information on the selected projects and collection of primary evidence for the
audit. Full details of documents reviewed is attached as Appendix 1.
1.5.2 Interviews
29. We interviewed key officials of GHA, Contractors, Consultants, Ministry
of Roads and Highways who were directly involved in the planning and
implementation of the selected projects. The interviews enabled us corroborate
or otherwise information from documents and site inspections. The interviews
were conducted between 26 March and 31 July 2019. The full list of interviewees
is attached as Appendix 2.
1.5.3 Field Inspection
30. The team inspected the three roads to obtain a first-hand information on
the status of the road project, the extent of works done, took measurements of
road width, Schmidt hammer measurements of concrete strength, as well as
asphalt cores for laboratory testing. The selection of locations to core was based
on standards used by the American Society of Testing Materials (ASTM) for
7 |Performance Audit Report of the Auditor-General on selected Roads
removal of compacted bituminous mixture (asphalt) for laboratory testing. Our
sampling was done according to ASTM D3665 whilst the coring of the road was
done in conformity to ASTM D5361.
31. We took ten asphalt core samples from the Tetteh Quashie - Madina Road
and 20 samples from the Ayamfuri – New Obuasi Road. The team also took
random Schmidt hammer readings for concrete drains, culverts and bridges
where they were accessible. Pictures of the field inspection are shown in
Pictures 1 to 6.
Picture 1: Extracted Asphalt Core
Sample from Tetteh Quarshie-
Madina road
Picture 2: Measuring Extracted Asphalt Core
Sample from Ayamfuri-New Obuase road
8 |Performance Audit Report of the Auditor-General on selected Roads
Source: Audit staff coring, measuring of road, April - June 2019
Picture 5: Coring of asphaltic concrete
on Ayamfuri-New Obuase road
Picture 6: Coring of asphaltic concrete on
Tetteh Quarshie-Madina road
Picture 4: Taking Schmidt Hammer
measurements
Picture 3: Taking road measurements
on Ayamfuri New Obuase road
9 |Performance Audit Report of the Auditor-General on selected Roads
32. Our inspection enabled us to measure the width of the road at the point
where the asphalt cores were taken to determine the width of carriageway and
shoulder. We measured the total length of the road using the odometer of the
trekking vehicle. These measurements were taken to enable the team compare
with the specification in the drawings and contract documents so we could
draw our conclusions. The details of the field inspection methodology are given
in Appendix 3.
1.5.4 Material Laboratory Tests
33. These tests were conducted at the GHA Central Materials Laboratory and
the results were compared to the design specifications in order to draw
conclusions whether the materials used met specifications. Testing of the
materials in GHA Laboratory was to enable the team as part of the audit,
validate the capacity and existence of such a facility to GHA for their quality
assurance purposes for road construction in Ghana. To limit the risk of possible
tampering of test results in the laboratory, the team was present at all steps of
the processes supported by our technical adviser. Sample pictures of the
laboratory testing are shown in Pictures 7 and 8 whiles the test results are
presented in Appendix 4. We tested the asphalt sample for;
i. Grading (i.e. aggregate size distribution)
ii. Bitumen content (i.e. quantity of Bitumen in the asphaltic concrete).
iii. Density (i.e. the degree of compactness of the asphaltic concrete) and
iv. Air voids (i.e. air spaces in the asphaltic concrete)
v. Thickness
10 |Performance Audit Report of the Auditor-General on selected Roads
Picture 7: Size reduction of the asphalt
core samples
Picture 8: Removal of air voids from
loosened asphalt sample
Source: Laboratory testing of asphalt, April - June 2019
11 |Performance Audit Report of the Auditor-General on selected Roads
CHAPTER TWO
2.0 Description of the audit area
34. Roads have become an essential part of human endeavor and since the
creation of automobile to replace donkeys and camels as means of transports, the
need for well-networked and good roads to link communities have become a
necessity. National targets for growth and poverty reduction also rely on an
effective road transportation system. The inability to access services because roads
are not motorable is an important element of social exclusion which defines
poverty.
35. Providing accessibility to facilitate mobility and movement of goods and
services throughout the country underpins national growth and reduces poverty,
a key goal in the SDG for which Ghana has committed. In Ghana, 13.7% of the
national GDP4 is spent on infrastructure development, of which roads form a
significant portion. Yet the maintenance of the same roads repeatedly within a
short period after construction has become a drain on the country’s budget and a
concern to many.
36. Roads in Ghana are classified as Feeder Roads, Urban Roads or Highways
depending on the location and use which in turn determines the
design. Regardless of the category, these roads are needed to contribute to
economic development. Good roads enable faster movement of people to the
markets, hospitals, schools etc. Good roads have also been partly blamed for
increase in road accidents. In recent times, statistics from the NRSC reveal a high
number of deaths on our roads due to vehicular accidents. This nevertheless does
not mean that Government should relent in improving upon the quality and
length of roads in the country.
4 Provisional 2017 Annual Gross Domestic Product, Ghana Statistical Service (April 2018 edition)
12 |Performance Audit Report of the Auditor-General on selected Roads
37. To ensure efficient administration of trunk roads in the country, the Ghana
Highway Authority Decree 1974, (NRCD 298) was passed. This was later re-
enacted by Parliament as Act 540 of 1997 to bring it in conformity with the
constitution. According to Act 540, GHA is to design and supervise the
construction of trunk roads and in some cases render consultancy services only to
ensure contractors meet specification. The trunk road network is shown in Picture
9.
13 |Performance Audit Report of the Auditor-General on selected Roads
Picture 9: Trunk road network of Ghana
Source: Ghana Highway Authority
14 |Performance Audit Report of the Auditor-General on selected Roads
2.1 Overview of the selected road projects
2.1.1 Tetteh Quarshie to Madina Road Project
38. The Government of Ghana, under the Road Sector Development
Programme (RSDP), with financial support from development partners,
embarked on a rehabilitation programme of some major roads including the
Tetteh Quarshie to Mamfe Dualization Project of which the Tetteh Quarshie-
Madina road forms a section. The set objective of the Project was to contribute to
Government’s goal of poverty reduction and economic development by reducing
travel time, congestion and vehicle operating costs due to usage of the road for
both passenger and freight transport. Between 1998 and 1999, economic feasibility
studies and detailed engineering designs for the reconstruction of the entire trunk
road from Tetteh Quashie to Mamfe were prepared. The 39.6 km long trunk road
was then divided and packaged into four components for implementation under
separate contracts, and to facilitate parallel financing. The components were;
The Tetteh Quarshie Grade Separated Interchange,
The Tetteh Quarshie to Madina section (4.6 km),
The Madina to Pantang section (4.9 km), and
The Pantang to Mamfe section (30.1km)
39. The 4.6 km Tetteh Quarshie - Madina road project comprised asphalt
surfaced three-lane dual carriageways with sidewalks, bicycle lanes, drainage and
ancillary works. There was also to be two interchanges at University of Ghana,
Legon and Atomic Junction. The project was awarded in October 2006;
commenced in November 2006 and was expected to be completed in May 2009.
The estimated cost of the project was USD$ 17, 414, 431.78 and GH¢ 23,558,960.95
15 |Performance Audit Report of the Auditor-General on selected Roads
(the total equivalent of USD$ 43, 000, 0005). Pictures of the project are shown in
Pictures 10 to 13.
Picture 10: Section of Tetteh Quarshie-
Madina at Shiashi
Picture 11: Section of Tetteh Quarshie-
Madina towards University of Ghana
Picture 12: Tetteh Quarshie-Madina road
showing the Legon Underpass
Picture 13: Section of the Atomic Junction
Flyover
Source: Audit team field inspections of road projects, April - June 2019
5 Amount at the contract exchange rate of US$ 1: GHS 0.9207
16 |Performance Audit Report of the Auditor-General on selected Roads
2.1.2 Ayamfuri to New Obuase Road Project
40. The Ayamfuri – New Obuase road project is part of the Ayamfuri to
Asawinso Junction of Inter Regional Road 6 and Inter Regional Road 8. The project
comprised the rehabilitation of 26.0km of the road to asphalt to serve as an
effective north south corridor linking the north to the Takoradi Port in the south.
Apart from improvement in north south commerce the project was envisaged to
bring relative comfort and convenience for local roadside residents and road users
arising from dust reduction in dry weather and access problems in wet weather.
The feasibility studies commenced in 2007 and designs were completed in 2009.
The estimated cost of the project was about US$ 29 million, it commenced in
December 2012 and was expected to be completed in December 2014. Pictures 14
to 17 show sections of the road.
Picture 14: Section of the Ayamfuri-New
Obuase road
Picture 15: Section of the Ayamfuri-New
Obuase road
17 |Performance Audit Report of the Auditor-General on selected Roads
Picture 16: Section of the Ayamfuri-New
Obuase road
Picture 17: Section of the Ayamfuri-New
Obuase road
Source: Audit team field inspections of road projects, April - June 2019
2.1.3 Bolgatanga-Bawku-Polimakom Road Project
41. The Bolgatanga-Bawku-Polimakom road is a 116.1 km long road including
three bridges over the Red, Black and White Volta at Zualugu, Tilli and Zebilla. It
starts from Bolgatanga (Central Corridor) to link up with the Eastern Corridor
Road at Missiga. The project is expected to improve the efficient movement of
people, goods and services between Ghana, Burkina Faso and Togo to promote
the socio-economic development of the people in the sub-region. The project was
awarded in September 2016; commenced in December 2016 and was expected to
be completed in June 2019. The estimated cost of the project was US$
160,316,015.97 (GH¢ 612,743,844.64). Pictures 18 to 21 show sections of the road.
18 |Performance Audit Report of the Auditor-General on selected Roads
Picture 18: Section of the Bolagatanga-
Bawku-Polimakom road
Picture 19:Section of the Bolagatanga-
Bawku-Polimakom road
Picture 20: Section of the Bolagatanga-
Bawku-Polimakom road
Picture 21: Section of the Bolagatanga-
Bawku-Polimakom road
Source: Audit team field inspections of road projects, April - June 2019
19 |Performance Audit Report of the Auditor-General on selected Roads
2.2 Mandate of GHA
42. Ghana Highway Authority is mandated by Ghana Highway Authority Act,
1997 (Act 540) to ensure effective and efficient management of trunk roads. The
Act makes GHA the agency responsible for the administration, control,
development and maintenance of trunk roads and related facilities, subject to the
policies of the Ministry of Roads and Highways.
2.2.1 Vision statement
43. The vision of the Ghana Highway Authority is being a world-class provider
of safe road infrastructure.
2.2.2 Mission statement
44. GHA provides Road Infrastructure Engineering and Management Services:
project appraisal, feasibility studies and detailed design; contract preparation and
administration; maintenance and operation; civil engineering materials
prospecting and testing for roads, bridges and road safety facilities at best value –
least cost to support the socio-economic development of Ghana and beyond.
2.3 Functions of GHA
45. The functions of GHA as spelt out in the GHA Act relevant to the focus of
the audit are:
i. Plan, develop, maintain, protect and administer trunk roads and related
road works;
ii. Classify and lay down design standards on the different classes of trunk
roads;
iii. Undertake research or collaborate with any research Organization with
a view to facilitating the Authority’s planning, development and
maintenance activities;
20 |Performance Audit Report of the Auditor-General on selected Roads
iv. Maintain and preserve such records relating to its functions as it
considers expedient;
v. Maintain and update a list of designated trunk roads;
vi. Carry out, on a permanent basis, such necessary engineering traffic and
economic studies as it may consider necessary for the maintenance and
improvement of the trunk road network;
vii. Carry out either by its employees or through contractors with qualified
consultants, location and design studies (including right-of-way and
borrow pit requirements) necessary for programmed trunk road
improvement or rehabilitation projects and prepare corresponding
construction plans, specifications, cost estimates and other documents
required for proper tendering of the programmed works;
viii. Subject to existing enactments, tender, let and administer contracts for
trunk road improvement and rehabilitation project and for trunk road
maintenance activities for which contracting is considered by the
Authority to be cost effective or otherwise advantageous;
ix. Keep adequate records and operate a management information system
which provides the managers with timely and accurate information on
commitments and expenditure for works and services for which the
managers are responsible;
2.4 Sources of funding
46. Funding for road works are through the Ghana Road Fund, budgetary
allocations from Government of Ghana (GoG) and loans disbursed through the
Ministry of Finance (MoF). GHA is a road infrastructure and support agency
responsible for the maintenance and development of trunk roads under the
Ministry of Roads and Highways. Their budget is consolidated into the budget of
the Ministry of Roads and Highways (MRH). Table 2 indicates the budget,
approvals and releases by MRH to the road sector from 2013 to 2017.
21 |Performance Audit Report of the Auditor-General on selected Roads
Table 2: Budgeted and releases of funds for Road works from 2013-2017 (MR&H)
Year Total Planned budget, GH Approved, GH Disbursed, GH
2013 No data available 165,617,270.00 531,636,660.00
2014 2,087,381,700.00 747,030,416.00 1,223,681,240.00
2015 3,698,297,630.00 931,657,411.00 1,664,504,323.00
2016 5,279,909,020.00 624,624,197.00 3,084,015,085.92
2017 6,750,928,630.00 1,581,222,972.00 1,731,911,704.00
Total 17,816,516,980.00*6 4,050,152,266.00 8,235,749,012.92
Source: Extracted from Ministry of Roads and Highways Medium Term
Expenditure Framework (2016 – 2018)
47. A review of Table 2 show a trend observed where disbursements are higher
than approved budget and our audit reveal were due to arrears from previous
years which were not part of the budget submitted.
2.5 Key players and stakeholders
48. The Key Players for the audit are the Units and Departments that play a
direct role in the planning and implementation of the project. The stakeholders to
the audit are those institutions that support the Key Players in the execution of
their roles. The list of Key Players and stakeholders of the audit are shown in Table
3 and detailed in Appendix 5.
Likely higher because of absence of figures
22 |Performance Audit Report of the Auditor-General on selected Roads
Table 3: Key Players and Stakeholders
Key Players Stakeholders
Ministry of Roads and Highways Ministry of Finance
World Bank Ghana Road Fund
Ghana Highway Authority (All key
departments)
Regional Coordinating Council
Engineer’s Representative /Consultant Lands Commission
Contractors General public/communities
Survey department (Evaluation Unit) Electricity, Water and other Service
providers
Source: Audit team review of project documents and correspondence
2.6 System description
49. The system description for the planning and implementation of road
projects is shown in Figure 1 in Appendix 6.
23 |Performance Audit Report of the Auditor-General on selected Roads
Figure 1: System Description
Source: GAS Performance Audit Infrastructure Guide
24 |Performance Audit Report of the Auditor-General on selected Roads
CHAPTER THREE
3.0 FINDINGS, CONCLUSIONS AND RECOMMENDATIONS
3.1.0 Introduction
50. The Ghana Highway Authority (GHA) is responsible for the administration,
control, development and maintenance of trunk roads and related facilities in the
country. The audit of selected road projects examined the various processes of the
project life cycle to determine whether if in general, road works administered by
GHA guaranteed value for money. To enable the team draw conclusion on this
audit objective, we sought answers to our audit questions by analysing data
gathered using our audit methodology detailed in paragraphs 11 to 20 and
Appendices 3 and 4 of this report. Our findings, conclusions and
recommendations on the Tetteh Quarshie to Madina, Ayamfuri to New Obuase
and the Bolgatanga-Bawku-Polimakom Road Projects are presented in this
chapter under the following headings:
a. Planning for the road projects (Studies, design and budgeting)
b. Procurement of contractor / consultant
c. Project implementation
d. Project closure and documentation
3.2 Planning for road projects (studies, design and budgeting)
51. Ensuring that project objectives are met depend greatly on how well
planning was considered at the inception of the project. Planned road projects
define the project objective by stating in broad outline what the project has to
achieve and how it is to be operationalised including scope, procurement
methods, time and financing options. When planning is well undertaken, it allows
25 |Performance Audit Report of the Auditor-General on selected Roads
a more detailed look at project resource requirements and will include feasibility
studies, tender plans and construction plans. Feasibility studies in particular
provide information to determine appropriate design solutions, timelines and
resource needs for funding.
52. We reviewed the Roads project planning process carried out by GHA on
three selected roads by focusing on how feasibility studies were carried out to
support project designs and estimation.
3.2.1 Feasibility Studies
53. Section 3 (1) (g) of Ghana Highway Authority Act, 1997, Act 540 mandates
Ghana Highway Authority to carry out, on a permanent basis, such necessary
engineering traffic and economic studies as it may consider necessary for the
maintenance and improvement of the trunk road network. Standard industry
practice requires GHA to carry out a feasibility study to assess the financial and
technical viability of any project and propose preliminary designs prior to the
implementation of such projects. The feasibility study and design provide
information along the road corridor necessary for detailed design and costing of
the project.
54. The studies also highlight current and projected traffic, surface and
subsurface soil conditions, the extent of relocation of utilities and compensation
to Project Affected Persons (PAPs) along the proposed route. This provides
necessary baseline information for decision making as to whether to proceed to
implement a project or not, the options available and a preliminary estimate of the
cost of the project. Feasibility studies, documented in Feasibility reports are also a
pre-requisite to assess Donor funds for road projects and hence GHA is obliged to
produce feasibility reports for such projects.
26 |Performance Audit Report of the Auditor-General on selected Roads
55. We noted through review of project documents and correspondence, and
interviews with GHA management staff that the Authority adopted the FIDIC Red
Book (Works Designed by the Employer) concept for the implementation of the
three projects. Under this concept, the Employer (Ministry of Roads and
Highways) bares the responsibility for feasibility and design of the road project
whiles the contractor is responsible for implementing the designs of the Employer.
56. For the three projects, GHA indicated that it contracted private engineering
consultancy firms to carry out the feasibility studies. We noted that the Ayamfuri
- New Obuase Project feasibility study was done by M/S Carl Bro Intelligent
Solutions and M/S Axsys Engineering Limited in 2007 as part of the Awaso -
Ayamfuri - Bogoso IR8/IR6 and Gambia No. 2 - Kyeremaso IR8 Project. The World
Bank funded the feasibility and design studies for the Ayamfuri - New Obuase
Project. GHA provided the feasibility and design report for the project which
contained information on;
traffic analysis,
drainage structures,
topography,
soil and material investigation,
construction materials survey,
hydrological and hydraulic investigations and design,
geometric design,
pavement design and
structural design.
57. The report presented a draft tender dossier, cost estimate, implementation
schedule and an environmental and social impact assessment. The outcome of the
feasibility study indicated that the project was economically viable with a rate of
return of 21.5% above its test discount rate of 15%.
27 |Performance Audit Report of the Auditor-General on selected Roads
58. M/S Roughton and M/S Twum Boafo and Partners in 1998 as part of the
Tetteh Quarshie to Mamfe Dualization Project carried out feasibility study for the
Tetteh Quarshie to Madina Project, whilst M/S Delin Consult carried out the
study for the Bolgatanga-Bawku-Polimakom Project. However, feasibility reports
on these two projects were not available to us to confirm that they were carried
out.
3.2.2 Project Design
59. Section 3 (1) (i) of Ghana Highway Authority Act, 1997, Act 540 mandates
Ghana Highway Authority to carry out either by its employees or through
contractors with qualified consultants, location and design studies (including
right-of-way and borrow pit requirements) necessary for programmed trunk road
improvement or rehabilitation projects and prepare corresponding construction
plans, specifications, cost estimates and other documents required for proper
tendering of the programmed works.
60. We noted that GHA engaged private engineering consultancy firms to
design the road projects for the Tetteh Quarshie- Madina, Ayamfuri-New Obuase
and Bolgatanga-Bawku-Polimakom. These firms were;
M/S Roughton and M/S Twum Boafo and Partners
M/S Carl Bro Intelligent Solutions and M/S Axsys Engineering Limited,
and
M/S Delin Consult
61. We reviewed project files to determine if complete set of design drawings
were available before tender and construction drawings were issued to
contractors to enable the smooth progress of the projects. For the Tetteh Quarshie-
Mamfe road project, we noted that a complete set of designs and drawings
(general arrangement layouts, typical cross sections, geometric and layout
28 |Performance Audit Report of the Auditor-General on selected Roads
drawings, drainage layouts, traffic management, structural designs) were
produced as a component of the Tetteh Quarshie-Mamfe road project in 1998.
However, the project was put to tender in 2006 based on the 1998 designs and
drawings without review and updates. Since there was no review done, designs
continued to be carried out during construction which were captured as
variations. According to officials of the Survey and Design Department of GHA,
key components of the design such as interchanges had to be done to suit changed
conditions along the road when the project commenced which should have been
captured prior to tender if there was a review process.
62. For the Ayamfuri-New Obuasi project, there was a preliminary design in
2007 contained in the feasibility study report carried out by M/S Carl Bro
Intelligent Solutions and M/S Axsys Engineering Limited .We noted through
review of the contract document that in 2009, a consortium of consultants
(Grontmij/Carl Bro in association Comptran) carried out detailed designs and
drawings which was used to tender for the project in 2010. The design review
report of the Ayamfuri-New Obuase project indicated that the rate of increase for
traffic projections on that stretch were high, necessitating another review in 2013.
The review led to a modification of the pavement structure (shown in Table 4).
Slope stabilization designs were added in 2014 to cater for extremely soft and
unstable cut slope faces.
Table 4 : Design reviews on the pavement structures of Ayamfuri to New Obuase Road
Project
Initial pavement
design thickness
Revisions Comments
Wearing course:50mm
Binder course:80mm
Base:200mm
Sub-base:150mm
Wearing course:40mm
Binder course:60mm
Base:300mm
Sub-base:150mm
GHA indicated that the initial
design for the Base course would
not have been adequate considering
the expected traffic on the road
Source: Contract Documents and design review documents.
29 |Performance Audit Report of the Auditor-General on selected Roads
63. For the Bolgatanga-Bawku-Polimakom Road Project, we noted that Delin
Consult submitted revised design drawings based on their earlier feasibility
study, for the construction of the Bolgatanga-Bawku-Polimakom project to GHA
on 4th April 2017. The drawings contained general layout (typical cross section,
plan and longitudinal profile, bus bay details, etc.) and miscellaneous drawings
(drainage drawings, guard rail details, curve details, etc) for the road works only.
The revised drawings did not have any of the design drawings for the three
bridges over the River Kulaa, Red Volta and White Volta. Officials of GHA
indicated that the bridges were omitted from the design drawings because the
Contractor was expected to design and construct those during implementation as
part of his terms of reference.
3.2.3 Budgeting
64. Funding is key in any construction project to guarantee availability and
sustained cashflow to contractors for a successful implementation. The duty of
sourcing for funds for road projects rests with the Ministry of Roads and
Highways (Employer) and it is critical that prior to award of contract for any road
project, the Ministry identify a reliable source of funding. We expect GHA to
provide reasonable estimates based on drawings for budgeting purposes to enable
the Ministry secure adequate funding to meet all planned payment schedules
during implementation of projects.
65. For the three projects, GHA prepared initial estimates based on the design
drawings. Table 5 shows the funding source, initial estimates, contract sums and
the variances for the three projects.
30 |Performance Audit Report of the Auditor-General on selected Roads
Table 5 Funding source and contract sums for the three projects
Project Source of funding
Initial Estimate
Contract Sum Variance (%)
Tetteh Quarshie – Madina
GoG $39,808,210.18 $43,000,000.01 8.02
Ayamfuri – New Obuase
World Bank
$29,000,000.00 $ 29,983,613.53 3.39
Bolgatanga-Bawku-Polimakom
Road Fund
$137,731,076.80 $160,316,015.97 16.40
Source: Audit team review of Project Documents
66. From Table 5 we noted that the variance between the initial estimates and
the contract sums for Tetteh Quarshie- Madina and Ayamfuri- New Obuasi were
under 10% whiles that of Bolgatanga- Bawku- Polimakom project was above 10%.
67. We noted that the Ministry of Roads and Highways gave GHA budget
ceilings and so the Authority was compelled to fit its design estimates within the
provided budget. The fixed ceiling nature of budget provision meant that GHA
had to scale down on scope of road designs to meet the Ministry’s budget by
taking out some items from the bill of quantities. The scaled down designs were
later reintroduced as variation orders during construction.
68. We also noted from review of budgets and contract documents for the
projects that GHA through the Ministry identified the sources of funding for the
three projects. The World Bank funded Ayamfuri- New Obuasi project with a
dedicated account managed by the Ministry of Roads and Highways from which
all expenses were made during implementation of the project. The World Bank
account had an imprest of US$5.50 million for all World Bank funded projects
which is drawn down and replenished when the funds run out. For the Ayamfuri
Project, the World Bank provided US$58.5 million for implementation based on
the design estimate. The funds were secured and solely dedicated to that project.
31 |Performance Audit Report of the Auditor-General on selected Roads
69. We also noted that for Tetteh Quarshie-Madina and Bolgatanga-Bawku–
Polimakom, the source of funding was identified as GoG and Road Fund but
without a dedicated account to the project. Funds were disbursed as and when
the Ministry of Finance was able to allocate money to pay for works under the two
projects.
70. We also noted that the availability of a budget line for a road project as we
observed, did not guarantee payments, as disbursement of funds to pay for works
done depended on the availability of funds from either Road Fund or Central
Government. GoG road projects funds are not tied down to specific projects.
71. From our review of the budgetary allocations and releases to the Ministry
of Roads and Highways, we noted that there were yearly allocations to the project
by the Ministry. These projects were mainly those under GoG and Road fund and
as shown in Table 2 the allocations made were indications of intention to pay for
the works under the projects and not releases. As we found from our reviews, the
releases made for the projects were not commensurate with the quantum of works
carried out which needed to be paid. Consequently, the resources allocation and
releases for the GoG projects did not rely on the estimates made from the designs
to plan the payment as the releases were not sufficient to meet cost of payment for
work done.
Conclusion
72. There is no indication that the three selected roads were planned and
captured under GHA strategic plan for implementation. However, there has been
attempts at upgrading those roads which were due to the deteriorated nature of
the roads dating back 1998 as in the case of Tetteh Quarshie-Madina road and 2007
as in the Ayamfuri-New Obuase road. Feasibilities studies had been carried out
but were not reviewed before implementation to take note of the laps in time
between the studies and implementation.
32 |Performance Audit Report of the Auditor-General on selected Roads
73. GHA provided estimates for the three projects to serve as budget for the
Ministry of Roads and Highways in sourcing for funds for the projects. Unlike the
Ayamfuri-New Obuase road project, the estimates provided for the Tetteh
Quarshie-Madina and Bolgatanga-Bawku-Polimakom road projects were
however based on preliminary/unrevised designs and provisional sums which
affected the final cost during implementation.
74. Estimates as submitted are usually more of budgetary ceiling rather than
price estimates derived from the drawings thereby resulting in variations due to
the reintroduction of items dropped to meet the budgetary allocation. It is not
helpful for accountability and assessment for Value for Money and opens the
process for discretion and abuse.
75. Where the estimates for projects are not adequately determined, and are
based on budgetary ceilings, the extent and scope of work are arbitrarily varied
leading to cost overruns. As we have elaborated under 3.4 (Project
implementation), variations that were not budgeted for affected the completion
time of the project and increased the project budget beyond 50% in some instances.
Recommendation
76. Our review of planning processes for roads works supervised by GHA
shows that some efforts had been made to ensure that roads are properly designed
and budgeted for to ensure smooth implementation. However, the planning
process including studies, designs, and budgeting can be improved.
77. To improve upon the planning process, we recommend that GHA should;
vi. capture all intended roads projects in a strategic plan for planning purposes
and accountability.
vii. review design drawings of any project it intends to implement especially
where there has been a time laps between feasibility studies and
33 |Performance Audit Report of the Auditor-General on selected Roads
implementation with its complementing bill of quantities prior to
tendering, and
viii. Estimates should be prepared from detailed drawings and not through
budgetary ceilings as practised to reduce the tendency of eliminating items
only to reintroduce them as variations.
3.3.0 Procurement of consultant/contractors
78. The Public Procurement Act, 2003, Act 663, (Part IV and V) provides
guidelines and directions for procuring the services of contractors and
consultants. Schedule 3 of the Act provides thresholds that procuring entities to
comply with when engaging in procurement activities. The Act provides uniform
procedures for the procurement of goods, works and services to secure a judicious,
economic and efficient use of state resources and to ensure that public
procurement is fair, transparent and non-discriminatory.
3.3.1 Procurement of Sonitra Limited for the Construction of the Tetteh
Quarshie -Madina Road Project
79. Section 47, 51, 53, 54, 55 and 59 of the Public Procurement Act, 2003 (Act
663) governs effective international competitive tendering and award of contract
where prequalification is a requirement.
80. GHA published a request for pre-qualification for the Tetteh Quarshie-
Madina Road Project in the Daily Graphic of 22 April 2006, inviting local and
international construction firms to apply for pre-qualification. In line with the PPA
requirements, the prequalification advertisement covered the scope of works;
qualification requirements; price for the prequalification documents; and the
place, time and deadline for submission as 4 May 2006. The criteria for qualifying
contractors contained in the advertisement and the pre-qualification documents
were;
34 |Performance Audit Report of the Auditor-General on selected Roads
Experience and satisfactory past performance on contracts of similar nature
and complexity;
Knowledge of working condition in developing countries
Capacity of contractors with respect to personnel, plant and equipment; and
Financial capacity.
81. From correspondence, we noted that nine (9) construction firms responded
to the advert, bought and submitted their prequalification documents. A three-
member panel carried out the pre-qualification exercise and submitted its report
on 17 May 2006.
82. Four out of the nine firms were shortlisted and invited per letters dated 9
June 2006, to submit tenders by 14 July 2006. Due to various requests for
clarification by the tenderers, GHA organized a pre-bid meeting on 30 June 2006
to resolve all queries, which resulted in a decision to extend the tender submission
date from 14 July 2006 to 28 July 2006.
83. We reviewed project correspondences and found that an Evaluation Panel
of three Principal Engineers, constituted on 31 July 2006, evaluated the tenders
and submitted its Evaluation Report which recommended Sonitra Ltd as the
lowest evaluated tenderer. The Evaluation Report was however not made
available to us for our review.
84. The Central Tender Review Board gave concurrent approval on 15
September 2006, to award the contract to the recommended tenderer, Sonitra Ltd
at the offer price of USD $ 24,882,462.46 and GH¢ 27,233,783.95 (the total
equivalent USD$ 54,458,972). In accordance with Section 64 (2)b of the Public
Procurement Act 2003, Act 663 the Board also gave approval to GHA to negotiate
the contract price with the lowest recommended tenderer.
85. As a result of the negotiations on 28 September 2006, some works and
services were scaled down and a lumpsum discount of US$511,000.00 was given
35 |Performance Audit Report of the Auditor-General on selected Roads
by Sonitra Limited, reducing the contract price to the MRH’s set budget limit of
USD$ 43,000,000. The final negotiated contract price thus comprised a local
component of GH¢ 23,558,960.95 and a foreign component of USD$ 17, 414,
431.78 (a total equivalent of USD$ 43, 000, 000). Table 6 shows the items that were
scaled down during the negotiation, their BoQ reference numbers, initial amount
and final negotiated amount in the BoQ.
Table 6: Items scaled down during the contract negotiation with Sonitra Limited
BoQ
Reference
Description Provisional Sum
(US$) – (Initial)
Provisional Sum
(US$) –
(Negotiated)
A211.1 Engineer’s Office 75,376.23 0
A212.1 Laboratory Equipment 19,942.42 0
A222.1 Telephone and E-mail Services 1,966.33 0
A231.1 Equipment/Furniture for ER’s
Office
103,778.19 0
A232.1 Equipment/Furniture for Lab 207,556.37 0
A260 Testing of materials 28,403.36 0
A420.1 Service Diversion 1,966.40 0
A420.3 Compensation to Property
Owners
937,204.56 0
A270.1 Adjustment Allowances 96,148.45 0
Total 1,472,342.31
Source: Extract from minutes of negotiation between GHA and Messrs Sonitra Limited
86. GHA accepted Sonitra’s tender by a letter dated 6 October 2006. On
submission of a Performance Security on 18 October 2006, the contract was signed
on 27 October 2006 by the Employer (Ministry of Transport) and the contractor
(Sonitra Ltd) and witnessed by GHA and the contractor’s representative. The
duration for the project was 30 calendar months for the Construction of Three-
36 |Performance Audit Report of the Auditor-General on selected Roads
Lane Dual Carriageway from Tetteh Quashie Interchange to Madina with Two
No. Interchanges and Service Lanes (4.6 Km).
87. GHA followed the laid down procedures in engaging the services of Sonitra
Limited to award the contract for the construction of the Tetteh Quarshie-Madina
road project.
3.3.2 Procurement of China Jiangxi Corporation for International Economic and
Technical Cooperation for the construction of the Ayamfuri-New Obuase Road
Project
88. Section 45, 51, 53, 54, 55 and 59 of the Public Procurement Act, 2003 (Act
663) governs effective international competitive tendering and award of contract.
The process involves the following:
Advertisement
Responding to queries by bidders
Opening of bids
Evaluation of bids
Award of Contract and
Submission of performance securities
89. We noted that GHA published an advert for the Ayanfuri-New Obuase
Road Project in the Ghanaian Times Newspaper of Tuesday 9 November 2010. The
mode of procurement was International Competitive Bidding (ICB). The deadline
for the submission of bids was at 10:00am on 11 January 2011. The bidders were
expected to submit a bid security of US$ 1.0 million valid for 120 days.
90. Twenty (20) international construction firms responded and bought the
tender documents which was priced at US$300.00. GHA organised a pre-bid
meeting on 7 December 2010 to address queries which the bidders raised on the
information in the bid document. As a result of the meeting and subsequent
37 |Performance Audit Report of the Auditor-General on selected Roads
queries by the bidders, GHA issued addendum 1 and 2 to the bid document in
response to the queries on 15 December 2010 and 23 December 2010 respectively.
GHA subsequently issued addendum 3 to the bid document on 11 January 2011
whiles extending the deadline for submission to 25 January 2011.
91. We noted that 11 out of 20 firms submitted bids for the project on the
deadline date of 25 January 2011. The tender opening was attended by 11 Officials
of GHA including the Deputy Chief Executive (Development) as the chairman.
Other attendees were a representative from the Ministry of Roads and Highways,
and 20 representatives from the bidding firms. The bids submitted by bidders are
shown in Table 6. The Engineer’s Estimate recorded at the bid opening was GH¢
56,644,069.05.
Table 7 : Bidders and bid prices at tender opening as recorded
No. Firm Bid Price
Local (GH¢) Foreign
1 Jiangxi Zhongmei Eng. Const. 21,060,328.86 and US$ 20,883,755.19
2 China Jiangsu Jianda Const. 69,579,004.35 or US$ 47,012,840.78
3 Posco Eng. & Const. Ltd 11,119,178.21 and US$ 28,351,763.34
4 China Harbour Eng. Co. Ltd. 32,696,486.36 and US$ 9,469,252.64
5 MSF Construction 20,187,233.47 and Euro 20,260,322.73
6 China Railway Wuju 31,263,637.33 and US$ 9,017,814.94
7 China Jiangxi Corp for
International Economic and
Technical cooperation
13,837,344.05 and US$ 20,672,163.26
8 Monte Adriano 13,342,604.97 and US$ 25,610,340.40
9 Progressive Construction Ltd. 62,464,994.87 and Nil
10 Abdullah A.M. Al Khodari 109,241,238.70 Nil
11 Oumarou Kanazoe/ Kanazoe 10,442,282.14 US$ 25,971,342.81
Source: Audit review of minutes of tender opening
38 |Performance Audit Report of the Auditor-General on selected Roads
92. GHA constituted a five-member evaluation panel with a deadline for
reporting as 18 February 2011. The panel comprised the following:
Principal Engineer GHA (RSED) – chairman
Senior Quantity Surveyor GHA – member
Senior Engineer GHA – member/secretary
Quantity Surveyor GHA – member
Senior Quantity Surveyor DUR – member.
93. The evaluation panel submitted a draft evaluation report through the GHA
Chief Executive to the Ministry of Roads and Highways on 24 March 2011. The
panel recommended M/S China Harbour Engineering Company Limited for the
execution of the contract with a corrected bid price of GH¢ 46,616,287.74 converted
to single currency which was 17.99% below the Engineer’s Estimate.
94. We found in a correspondence dated 14 April 2011 that, the Ministry
queried the evaluation report and requested GHA to provide a copy of the blank
tender document sold and the bids of the top four ranked bidders. The report was
queried because the Ministry was of the opinion that the justification for
disqualifying the lowest bidder (China Jiangxi Corporation for International
Economic and Technical Cooperation) based on not meeting the annual turnover
requirement stated in the bid document was not satisfactory even though GHA
stated its reasons for doing so. GHA revised and resubmitted the evaluation report
to the Ministry on 29 July 2011 for onward submission to the World Bank for their
no objection. The revised evaluation report recommended M/S China Jiangxi
Corporation for International Economic and Technical Cooperation for the
execution of the contract with a corrected bid price of GH¢ 13,708,256.55 and US$
20,801,250.75 which was 22.17% below the Engineer’s Estimate with a construction
period of 24 calendar months. In that regard GHA requested the bidders to extend
their bid validities to 25 January 2012, which they complied.
39 |Performance Audit Report of the Auditor-General on selected Roads
95. The World Bank in a letter dated 20 October 2011 queried the evaluation
report submitted and asked the Ministry to submit answers to the increase in cost
estimates from US$ 29.0 million to US$ 39.0 million equivalent. The Ministry
submitted its revised bid evaluation to the World Bank on the 15 December 2011.
The World Bank requested further clarifications and a downward review of the
cost of the project in February 2012 to fall within the budget threshold of US$ 29.0
million provided under the funding agreement. GHA reduced the scope of works,
adjusted the general items downward and reviewed the pavement design until
the World Bank was satisfied that all its queries had been sufficiently addressed,
and the project was within the threshold of the funding budget. Due to the delay
in obtaining the “no objection” from the World Bank, GHA requested the bidders
to extend their bid validity and security further for another 120 days (up to 25
August 2012).
96. On 26 September 2012 GHA wrote a letter of acceptance to M/S China
Jiangxi Corporation for International Economic and Technical Cooperation
(CIETEC), which was responded to on 3 October 2012. GHA and M/S China
Jiangxi CIETC met and the contract price was negotiated downwards from GH¢
13,708,256.55 and US$ 20,801,250.75. by 0.5% for each component.
97. The Contract was signed on 21 December 2012 by the Employer and the
Contractor witnessed by GHA and the contractor’s representative. The contract
sum was GH¢ 13,641,596.55 and US$ 20,694,136.82 with a construction period of
24 calendar months. M/S China Jiangxi CIETC provided a performance security
dated 14 October 2012 in the sums of US$ 2,069,413.68 and GH¢ 1,364,159.66
respectively and expiring on 28 December 2014.
98. GHA followed the laid down procedures in engaging the services of M/S
China Jiangxi CIETC to construct the Ayamfuri – New Obuase road project.
40 |Performance Audit Report of the Auditor-General on selected Roads
However, the delay in obtaining the “no objection” from the World Bank resulted
in the delay of the procurement process.
3.3.3 Procurement of Consultants and Contractors for the Bolgatanga-Bawku-
Polimakom Road
3.3.3.1 Procurement of Messrs Queiroz Galvao Construction Limited for the
construction of the Bolgatanga-Bawku-Polimakom Road Project
99. 44. For the procurement of the Bolgatanga-Bawku-Polimakom road project,
GHA used Single/Sole Sourcing procurement method. This method is used to
procure works from one selected supplier/contractor without competition even
though there may be other suppliers that can carry out the works. Section 40 (1)
(a-d) of the Public Procurement Act 2003 (Act 663) allows the Single/Sole method
when there is exclusivity, urgency, emergency, continuity and compatibility
subject to the approval of the Public Procurement Authority.
100. We noted from review of the negotiation report on the Bolgatanga-Bawku-
Polimakom road project that GHA invited Messrs Queiroz Galvao Construction
Limited to inspect the road corridor and submit a proposal for the reconstruction
because the company had demonstrated on other projects that it has the technical
capabilities and experience in handling such works.
101. GHA prepared a BoQ that Messrs Queiroz Galvao Construction Ltd. used
as a guide to prepare its financial proposal and submitted a quote of US$
176,115,129.23 for consideration. Compared with GHA estimates of US$
137,731,076.80, the amount submitted by the Contractor was above by 27.87% .
102. On 15 June 2016, Messrs Queiroz Galvao Construction Limited was invited
for negotiations. The negotiation team was made up of Director, Quantity
Surveying-GHA, Principal Quantity Surveyor-GHA, Deputy Director, Planning-
41 |Performance Audit Report of the Auditor-General on selected Roads
Ministry of Roads and Highways, Communication Manager-Queiroz Galvao and
Quantity Surveyor-Queiroz Galvao.
103. After the negotiation, the financial proposal of Queiroz Galvao reduced
from US$ 176,115,129.23 to US$ 160,316,015.97 (representing US$
1,147,587.89/km) whilst that of GHA went up from the US$ 137,731,076.80 to US$
147,637,316.91 (representing US$ 1,036,151.29/km). This was because during the
negotiations, both parties realised that the rates of the contractor were high and
that of GHA were low and so a middle ground had to be reached. As a result,
GHA revised it rates upwards whiles the contractor revised its rates downwards
to arrive at the final negotiated figure of US$ 160,316,015.97.The revised estimate
of Queiroz Galvao became 8.59% higher than that of GHA’s revised estimates.
During the negotiations, GHA asked Queiroz Galvao to design, dismantle and
reconstruct three concrete bridges located at Km 1+800 (Zuarungu), Km 30+800
(Tilli) and Km 61+700 (Zebilla).
104. GHA in a letter dated 26 August 2016 wrote to Queiroz Galvao accepting
and a contract was signed by the Minister for Roads and Highways on behalf of
Government of the Republic of Ghana and Construtora Queiroz Galvao on the 14
September 2016 at a contract sum of US$ 160,316,015.97. The duration for the
contract was 30 calendar months. The contractor submitted a Performance Bond
of GH¢ 183,823,153.39 (30% of contract sum) from Vanguard Assurance which was
valid for 4 years.
105. We noted that, although Section 40 (1) (a-d) of the Public Procurement Act
2003 (Act 663) allows for Single/Sole method GHA needed to demonstrate the
justification for using single source as an option and getting approval from the
PPA. Our review of the documents and correspondence files did not show that
GHA followed the laid down procedures in engaging the services of Messrs
42 |Performance Audit Report of the Auditor-General on selected Roads
Queiroz Galvao Construction Limited to award for the construction of the
Bolgatanga-Bawku-Polimakom Road Project.
3.3.3.1 Procurement of Messrs. Delin Consult Limited
106. Section 38 of the Public Procurement Act 2003 (Act 663) allows restricted
tendering subject to the approval of Public Procurement Authority (PPA) if
services are available only from a limited number of consultants or if the time and
cost required to examine and evaluate a large number of tenders is
disproportionate to the value of the service. Section 39 of the PPA Act also states
that in carrying out Restrictive tendering the entity is required to invite in a non-
discriminately manner consultants who can provide the service and publish in the
public procurement bulletin notice of the selective tendering award.
107. From review of correspondence, we noted that GHA sought PPA approval
to use restricted tendering to procure consultant for the Bolgatanga-Bawku-
Polimakom road project on 21 July 2016 and obtained approval on 26 August 2016.
We noted from the evaluation report that in September 2016, GHA issued Request
for Proposals (RFP) to three firms to provide proposals for the consultancy
services for the construction supervision of Bolgatanga-Bawku-Polimakom
Highway including Bawku-Bypass. The three firms which submitted their
proposals were Messr Daovtech Consult Limited (Daovtech), Messr Delin Consult
Limited (Delin) and Messr KPH Consult Limited (KPH).
108. After the submission and opening of proposals on 26 September 2016, the
Director of Planning set up an evaluation panel made up of the Chief Engineer
(Bridges division) as chairman with members being Principal Quantity Surveyor
(Quantity Surveying Division), Senior Engineer (Survey and Design Division),
Engineer (Contracts Division) and Engineer (Planning Division) to evaluate the
technical proposals.
43 |Performance Audit Report of the Auditor-General on selected Roads
109. GHA followed Section 74 of the PPA 2003 (Act 663) as amended by Section
36 of Act 914 in evaluating the technical proposals and the result of the process is
shown in Table 8.
Table 8: Technical evaluation criteria with scores for the proposed consultants
Evaluation Criteria Max.
Marks
Consultants
Delin Daovtech KPH
Specific experience relevant to the
assignment
10.00 4.00 3.20 4.20
Approach to the assignment 30.00 25.20 16.60 13.60
Qualification and competence of key staff 60.00 54.54 37.74 11.56
Total mark 100.00 83.74 54.52 29.36
Source: Audit team review of technical evaluation report dated October 2016
110. We noted that the pass mark set for the technical proposals was 80%. From
Table 8, Messrs. Delin Consult Limited which scored more than the 80% had its
financial proposals opened on 8 November 2016. The financial proposal quoted
by Messrs Delin Consult was US$ 3,431,800.00 (GH¢ 13,543,598.70). The
evaluation panel stated that based on the technical and financial scores obtained,
Messrs Delin Consult was qualified to undertake the assignment.
111. The evaluation panel in line with Section 75 (7) of the PPA, Act 663
recommended that GHA invites Delin Consult for negotiations on their evaluated
price of GH¢ 13,543,598.70 exclusive of taxes to provide Consultancy Services for
the construction Supervision of Bolgatanga-Bawku-Polimakom Highway
including Bawku Bypass for 32 calendar months.
112. The team however did not see any documentary evidence on the
negotiations that were supposed to be carried out between GHA and Delin
Consult before the acceptance of the contract. Again, GHA could not provide the
44 |Performance Audit Report of the Auditor-General on selected Roads
contract document for the team to verify the acceptance, the date of signing and
the contract sum.
Conclusion
113. From our review of documents, GHA generally followed the procurement
laws and guidelines in obtaining the services of the contractors for the three
projects. Sufficient time was also allocated to enable contractors purchase and
submits bids for evaluation. Nevertheless, the audit team could not validate the
fairness and transparency of the processes due to the absence of evaluation reports
and approval letters on the procurement of the supervision consultant for the
Ayamfuri-New Obuase road project, and procurement of Sonitra Limited for the
Tetteh Quarshie Madina road project. There was no reason for the use of Sole
sourcing and restricted tendering as a preferred method for the Queiroz Galvao
Construction Limited and Delin Consult other than to confirm lack of planning
for the project.
Recommendation
114. Our review of procurement for both consultants and contractors show that
the PPA guidelines were generally met. However, the process could be improved
to enhance accountability and to guarantee value for money.
115. To improve upon the procurement process, we recommend that GHA
should;
i. Prepare adequately through planning to limit the use of sole sourcing,
ii. Document all the processes leading to the award of contract including
evaluation reports, and
iii. Limit the scaling down of the scope of works as a means of reducing
contract sums during negotiations with winning bidders
45 |Performance Audit Report of the Auditor-General on selected Roads
3.4.0 Implementation of the project (managing scope, cost, time and ensuring
project quality)
116. Project implementation is the stage when the project team puts all the plans
initiated to deliver the works for its intended use. During implementation, GHA
is to ensure that processes are put in place to manage and control projects scope,
schedules and to ensure project quality. A poorly managed implementation stage
poses a risk to timely completion and adherence to project budget. We expect that
GHA had planned to implement the projects using baseline schedules which was
to guide them track progress of the works, payments for work done and manage
scope so as not to escalate project cost.
117. We reviewed the sources of variations that contributed to changes in scope
and assessed whether the scope changes were avoidable, necessary, and how these
changes impacted the project cost. We employed our audit methodology to review
the processes for controlling project schedules and whether GHA put in
appropriate steps to mitigate project delay. We also looked at the payment for
works and the quality control and assurance systems employed to deliver the
project to contract specifications.
118. The results of our assessment of the implementation of the selected road
projects have been presented under the following headings:
Scope management (Variations)
Cost management (Payment for works)
Time management (Completing the project on time) and
Ensuring project Quality (Delivering the project to the specified quality)
46 |Performance Audit Report of the Auditor-General on selected Roads
3.4.1 Implementation of The Tetteh Quarshie- Madina Road Project
3.4.1.1 Scope management (variations)
119. The scope of the Tetteh Quashie- Madina project was to construct a 4.6 km
dual carriage asphalt road with two interchanges at Legon and Atomic Junction.
Each carriageway is to have three lanes and a minimum width of 10.5m. There are
two-lane service roads on both sides of the two interchanges. The pavement
structure of the road is 750mm thick comprising 40mm thick asphalt wearing
course, 60mm thick binding course, 200mm thick crushed stone base, 200mm thick
natural gravel base and 250mm thick natural gravel sub-base. There are also pipe
and box culverts; surface water drainage works including channels and slope
protections; and construction of junctions, accesses, bus stops and lay-bys.
120. Under Clause 51 of the General conditions of contract, the Engineer (GHA)
has authority to make any variation of form, quality and quantity of the works
which is considered necessary and appropriate. Sub-Clause 2.1(e) of the Special
Conditions of contract however requires the Engineer (GHA) to obtain specific
approval from the employer (MRH) when issuing variations that would increase
the effective contract price by 15 percent or more. Also, the PPA, Act 663, Section
87 (1) requires the procurement entity (GHA) to obtain clearance from the Tender
Review Board (CTRB) that reviewed the contract, where a variations order result
in an aggregate increase in the contract sum by more than 10 percent.
121. We expect the completed works to be within the planned scope and all
variations to the scope to be justified and to have the required approvals from the
MRH and the appropriate Tender Review Board as required by the provisions of
the PPA, Act 663.
122. We reviewed progress reports, variation orders, and site inspections, and
found that 25 variation orders were issued in the course of the project which
resulted in the cost of the project increasing by GH 31,256,849.42 and US$
47 |Performance Audit Report of the Auditor-General on selected Roads
16,190,746.50 from the original contract sum of GH¢ 23,558, 960.95 and US$
17,414,431.78 detail of which is shown in Appendix 7.
123. Of the 25 Variation orders, 22 were for works that related to the Tetteh
Quashie-Madina road, whiles three were for other additional works unrelated to
the project. Table 9 shows the values of variations for both related and unrelated
additional works in the two currencies of the contract and as percentages of the
original contract price.
Table 9: Composition of variations in relation to the original contract sum
Amount in GH¢ Amount in US$
Original Contract Sum 23,558, 960.95 17,414,431.78
Variation Orders: 31,256,849.42 16,190,746.50
% of Total V.O.s of Contract sum 133% 93%
V.O.s related to the project
% of contract sum
19,634,952.03
83%
10,021,120.59
58%
V.O.s unrelated to the project
% of contract sum
11,621,897.39
49%
6,169,625.91
35%
Source: Audit team review and analysis of variations
124. On examining GHA’s scope/variations management of the Tetteh
Quarshie- Madina project, we found the following issues which we have
presented under following headings;
Significant differences between estimated quantities and implemented
quantities.
Reintroduction of items taken out from contract before commencement of
construction
Variation orders for additional works unrelated to the project.
Unapproved variation orders
48 |Performance Audit Report of the Auditor-General on selected Roads
Significant differences between estimated quantities and implemented
quantities
125. We compared the works estimated in the contract BoQ with measured
quantities and valuation of actual works executed (in the IPC) and found that the
actual quantities executed varied significantly from what was estimated in the
contract BoQ. These works as quantified in the contract BoQ were estimated to
cost GH¢ 21,364,292.69 and US$ 16,981,173.66 but ended up costing GH¢
45,360,890.72 and US$ 30,427,510.83 representing an increase of 112% and 79%
respectively. Examples of these items that increased were;
i. The acquisition of streetlight and traffic signalization materials for which a
provisional sum of US$ 1,000,000 was inserted in the BOQ, but ended up
costing US$ 1,338,787.87 and GHC 5,090,806.5.
ii. Earthworks which was estimated in the BOQ as GHC 2,884,025.81 and US$
2,096,265.90; but ended up costing GHC 3,582,855.70 and US$ 2,598,125.35.
This was largely due to the volume of excavation below ground surface soil
layer increasing by 112,087 m3; volume of excavation of trenches for
culverts increasing by 12,806 m3; and the placing and compaction of 48,406
m3 of imported hardcore filling which was not originally provided for in
the BoQ.
iii. Concrete structures including, culverts, retaining walls, concrete bus bays,
concrete pipe works, u-drains which were estimated in the BoQ as GHC
4,263,652.63 and US$ 3,086,940.05; but ended up costing GH¢ 4,309,691.29
and US$ 3,019,154.7.
iv. Roads and pavings which were estimated as GHC 5,292,094.34 and US$
3,836,479.14; but ended up costing GHC 5,921,388.78 and US$ 4,292,505.07.
49 |Performance Audit Report of the Auditor-General on selected Roads
v. Interchanges at Atomic Junction and Legon for which a provisional sum of
GH¢ 5,524,746 and US$ 4,000,000 was made in the contract BoQ; but ended
up costing GH¢ 15,697,908.53 and US$ 11,495,466.19.
126. The significant variance in cost between executed and estimated works
indicated that the estimates of quantities and costs at which the works were
tendered and awarded were below the scope of works intended. This was as a
result of the fact that the 1998 estimates were mainly based on provisional sums,
and were not reviewed and updated before the project was packaged for tender
in 2006.
Reintroduction of items taken out from contract before commencement of
construction
127. We also noted that 17 of the 25 Variation Orders issued were for the
reintroduction of work items that were removed just before the signing of the
contract, in order to match the contract sum to the project budget limit of US$
43,000,000. These works generally related to engineer’s office accommodation and
equipment; relocation of utilities; and compensation payments to property
owners. These works were fundamental and indispensable to the project and
therefore should have been included in the original scope of works when the
contract was awarded. During implementation, the works were reintroduced as
Variation Orders numbers 1,2A,3,4,5,6,7,8,9,10,12,16,19,21,22,23, and 24.
128. The decision to scale down the scope of works to meet budget limits
undermined the efficiency of the planning process as it created the impression of
making savings on the project but was actually a zero-sum game which hid
inevitable costs that should have been recognized and planned for.
50 |Performance Audit Report of the Auditor-General on selected Roads
Variation orders for additional works unrelated to the project.
129. We also found from our reviews that three variation orders (V.O. Nos. 11,
13, 20) amounting to GH¢ 11, 621,897.39 and US$ 6, 169,625.91, were issued to
instruct the contractor to carry out works that were not related to the Tetteh
Quashie-Madina road and therefore should have been procured separately as
different projects. A summary of these works is shown in Table 10 and detailed in
Appendix 7.
Table 10: A summary of works unconnected to the Tetteh Quashie-Madina road but were
executed as Variations
Variation
Order No.
Brief Description of Works Estimated Net Additions
Local GHȼ Foreign US$
11 Various works carried out at:
o Accra shopping mall
o Additional lane to Northwest loop of the
interchange
o Spintex underpass
o University of Ghana
Widen Baatsona Junction and signalize
Spintex Road (New Alignment)
Additional box culvert under the motorway
4,371,386.29
13 Construction of Kasoa Toll Plaza 600,613.87 434,838.25
20 Community 18 bridge
Improvement of Abattoir road to steel
bridge;
Asphalt overlay improvement to community
18 road
Asphalt overlay improvement to Atomic
Junction to Rawlings Circle road
Right-out and right-in slip roads linking the
motorway and community 18 bridge
Variation to shopping mall loops, Spintex.
6,649,897.23 5,734,787.66
Total 11,621,897.39 6,169,625.91
Source: Audit team review and analysis of variation orders
130. Management of GHA explained that these unrelated works were
emergency works and the urgency required meant that conducting separate
51 |Performance Audit Report of the Auditor-General on selected Roads
procurement processes and paying for mobilization of new contractors would not
have been economical. The Ministry of Roads and Highways through GHA
engaged Messrs Sonitra Limited to carry out these works as the contractor was
already on site executing the Tetteh Quashie-Madina road project and had also
demonstrated good competence on the job. Nevertheless, the practice of adding
on new projects to an ongoing project makes contract administration difficult as it
complicates project monitoring and tracking, project reporting, and leads to less
optimized decision-taking which contributes to delays and cost overruns.
Unapproved variation orders
131. On issuing V.O. 11, the aggregate value of all previous variations (i.e. V.O.1
to V.O.11) exceeded 10% of the contract sum and this required that GHA obtained
approval from CTRB for V.O. 11 and all 14 subsequent V.O.s, in line with Section
87(1) of the PPA, Act 663. We noted that GHA obtained approval for only two of
the 15 variations which required approval from the CTRB.
132. Also, from September 2009 when V.O.13 was issued, the cumulative
variations exceeded 15% of the effective contract sum, and in line with Sub-Clause
2.1(e) of the Special Conditions of contract, this required V.O.13 and all subsequent
V.O.s (i.e. 12 V.O.s in total) to be approved by the MRH before they were
implemented. From our review of project files, we found that only MRH
approvals for V.O. 3 and V.O. 20 were kept on file. GHA could not provide proof
that it obtained approvals from the MRH for the other 10 V.O.s. Failure to obtain
the necessary approvals for variation orders implied that GHA committed
government to projects and expenditures without authorization.
52 |Performance Audit Report of the Auditor-General on selected Roads
3.4.1.2 Cost management (Payment for works)
133. According to Sub-Clause 60.1 of the Special Conditions of contract, the
contractor is to submit monthly statements showing the amounts to which the
contractor considers himself to be entitled which shall include the estimated
contract value of works at base unit rates and prices; the value of variations;
fluctuation payments to reflect changes in costs and legislation; the value of
materials and plants delivered to site; amount withheld as retention; amount
deducted as repayment of advance payments; and any other sum that the
contractor is entitled to.
134. The Engineer on receipt of the statement, is to issue an Interim Payment
Certificate (IPC), certifying the amount due the contractor. Sub-Clause 60.8
requires the Employer to pay the amount certified on the IPC within 56 days after
the contractor has submitted the monthly statement to the Engineer for
certification. In the event of default by the Employer, the contractor shall be
entitled to interest on delayed payments compounded monthly at the Bank of
Ghana prime rate plus 2% (for the local component) and the London Inter-Bank
On-Lending Rate (LIBOR) plus 1% (for the foreign component), on all outstanding
amounts, from the date the amount should have been paid.
135. To determine whether the amounts certified by GHA and paid to the
contractor were for actual works done, valid and in accordance with the contract,
we reviewed payment documentation i.e. IPCs, valuations of work done,
calculations of fluctuations, calculations for interest on delayed payments, and the
contractor’s claims for losses and expenses incurred due to extensions of time
granted during the course of the project. We also visited the site to inspect the
project and noted the works done.
136. We found that between the first IPC date of 3 November 2006 and the last
IPC date 1 July 2019, 103 IPCs (i.e. 77 for works and 26 for other claims) were
53 |Performance Audit Report of the Auditor-General on selected Roads
issued by GHA, certifying a total amount of GH¢ 170,477,493.66 and US$
49,974,242.82 to the contractor. This was 624% more than the Cedi component and
187% more than the US Dollar component of the original contract sum of GH¢
23,558,960.95 and US$ 17,414,431.78. Details on IPCs issued in the course of the
project are shown in Appendix 9. The increase to the project cost was the result
of;
Extra costs due to variations and remeasured quantities
Price Fluctuations
Contractors claims for extension of time
Interest on delayed Payment
Extra costs due to variations and remeasured quantities
137. The total additional cost due to variations orders and remeasurements of
quantities was GH¢ 35,275,945.22 and US$ 19,600,234.47 which increased the
contract sum by 149.7% (Cedi component) and 112.5% (US Dollar). Out of this total
amount, GH¢ 23,645,047.83 (i.e. 100.4% of the Cedi component) and US$
13,430,608.56 (77.1% of the Dollar component) related to the Tetteh Quarshie –
Madina road project. Whilst, GH¢ 11,621,897.39 (49.3% of Cedi component) and
US$ 6,169,625.91 (35.4% of the component) were for execution of unrelated works
which have been detailed in Table 10 under scope management.
Price Fluctuations
138. Price fluctuations which amounted to GHC 61,891,295.69 and US$
5,240,469.41 were paid pursuant to Clause 70.1 of the Special conditions of contract
which allows specified amounts payable to the contractor to be adjusted to reflect
increases and decreases in costs of labour, materials, plants and equipment, by
application of a price adjustment factor determined by a formula stated in the
54 |Performance Audit Report of the Auditor-General on selected Roads
contract. The total fluctuation payments on the project were respectively 263% and
30% of the Cedi and the US Dollar components of the contract sum.
Contractors claims for extension of time
139. There were payments in respect of contractors claims for expenses due to
extensions of time, which was GHC 32,605,057.14 and US$ 7,575,794.56. The
payments of contractor’s claims for expenses were made pursuant to Clause 53.5
of the General Conditions of the contract, which entitled the contractor to
additional payments for losses and expenses the contractor had incurred due to
extensions of time resulting from reduction and suspension of works. These
expenses according to the contractor, comprised site and head office overhead
costs, depreciation and ownership cost of idling equipment, cost of idling
personnel for construction activities, cost of extending validity period of
performance security, and the cost of extending the insurance cover. The
contractor’s claims for these expenses due to extensions of time were paid via IPCs
58A, 77A and 77B, and was respectively 138% and 44% of the Cedi and the US
Dollar components of the contract sum.
Interest claims on delayed Payment
140. We compared the dates the contractor was paid against the due dates for
payment according to the contract, to ascertain whether amounts certified by the
Engineer were paid within the 56 days stipulated by Sub-Clause 60.8 of the
Conditions of contract. From our review of the payment of 103 IPCs, we found
that for 96 IPCs for which information was available to compute the period of
payments of the Cedi component of the IPCs, there were payment delays ranging
from 39 to 986 days beyond the stipulated 56 days. Six of the remaining seven IPCs
did not have claim submission dates and/or payment dates to enable us compute
the periods taken to pay for IPCs.
55 |Performance Audit Report of the Auditor-General on selected Roads
141. Similarly, for the US Dollar component payments, all 94 IPCs for which
information was available to compute the period of payments, experienced delays
in payment ranging from 42 to 1,507 days beyond 56 days. As of 30 June 2019 (the
time of our audit), the last issued IPC (i.e. IPC 77B) had not been paid and had
been outstanding for 50 days. The contractor made claims for interests on delayed
payments as per the contract amounting to GH¢ 18,998,533.10 and US$ 560,842.11
being 23% and 11% respectively of the total cost of the project. (The details of the
delays in payment is shown in Appendix 9).
142. From our analysis, delays in the payment of IPCs occurred in two forms.
The first was delay in the time taken to process IPCs for payments going beyond
the stipulated 56 days; and the second was delay due to Ministry of Finance (MoF)
failing to pay IPCs promptly after IPCs have been processed for payment.
143. We noted that GHA’s site representative vetted and validated the
contractor’s claims for payment subsequently issued the IPCs. GHA’s site
representative forwarded the IPCs to RCC for endorsement and onward
submission to GHA Head Office where they were crosschecked for accuracy. The
IPCs were forwarded to MRH for onward submission to the MoF for payment.
144. We reviewed 10 IPCs that were made available to us to determine the time
taken to process the IPCs at the various processing points. Table 11 shows the time
spent at each point in the processing of IPCs before they were submitted to MoF
for payment.
56 |Performance Audit Report of the Auditor-General on selected Roads
Table 11: Details of delay beyond 56 days
IPC
No.
Resident
Engineer
RCC GHA Total days
spent in
processing
IPCs
Delay beyond 56 days
Delay due
to
processing
Delay due to
non-payment
by MoF
Total Delay
(a) (b) (c) (P = a + b + c) D = (P – 56) (X) (D+X)
71 22 28 54 104 48 304 352
72 99 3 40 142 86 656 742
73 42 3 40 85 29 656 685
74 17 19 40 76 20 602 622
75 27 15 24 66 10 560 570
76 23 18 17 58 2 501 503
77 48 15 48 111 55 313 368
71A 19 14 181 214 158 81 239
74A 55 8 40 103 47 602 649
74B 72 12 19 103 47 602 649
Source: Audit team review of project IPCs
145. From Table 12, IPCs took between 2 and 158 days beyond the stipulated 56
days to process for submission to Ministry of Roads and Highways for onward
submission to Ministry of Finance. At Ministry of Finance, there were further
delays in honouring the IPCs ranging from 81 to 656 days.
146. We noted that GHA did not have institutional policies on how long IPCs
should stay at each processing point before the stipulated 56 elapses. As a result,
there were undue delays in processing the IPCs for payment. Also, the audit team
found through interviews that these delays were because of insufficient or
unavailable funds to meet project payment obligations when they fell due. This
was due to the fact that funds were not secured and ring-fenced for project, and
57 |Performance Audit Report of the Auditor-General on selected Roads
payments had to be made from general budgetary allocations to road sector which
were often spread too thin over various competing projects. For example, in 2014,
GH¢ 747,030,416.00 was allocated to the whole road sector but no payments were
made on the Tetteh Quashie-Madina road project although a total IPC value of
GH¢ 8,547,778.00 and US$ 2,605,119.00 had been certified for payment in that year.
3.4.1.3 Time management (Completing the works on time)
147. Construction works for the Tetteh Quashie-Madina Road with two
interchanges commenced on 17 November 2006 and was scheduled to be
completed on 17 May 2009, as the contract duration was 30 calendar months. We
noted from the Sectional Taking-Over Certificate that section 1+250 to 3 + 000 was
completed and taken over from the contractor on 23 May 2009. From review of
correspondences between GHA and the contractor, we found that in the course of
construction, a number of events caused by the Employer (MRH) and the
Employer’s representative (GHA) resulted in eight Extensions of Time (EOT) and
consequent revisions to the expected completion date from 17 May 2009 to 19
February 2019. The stated reasons and durations for the Extensions of Time (EOT)
are presented in Table 12.
58 |Performance Audit Report of the Auditor-General on selected Roads
Table 12: Reasons and durations for Extensions of Time issued on the Tetteh Quarshie-
Madina project
Extension of time Reasons for Extension of time Duration (Months)
1st Extension
17 May 2009 – 15
October 2009
Delays in issuing drawings to the
Contractor. Variation to the specification
of the drainage system.
5
2nd Extension
15 October 2009 –
15 March 2010
Delay in issuing drawings for the Legon
Underpass after approval for alternative
designs of Reinforced Earth Walls.
5
3rd Extension
15 March 2010 – 15
January 2011
Obstructions caused by existing high-
tension pylons and various utility lines
in the Right of Way. Contractor’s
inability to start execution of reinforced
earth walls due to existing utilities
10
4th Extension
15 January 2011 – 1
November 2011
Continuing presence of high-tension
pylons and various utility lines in the
Right of Way. Contractor was not able to
start execution of reinforced earth walls
due to existing utilities
9.5
5th Extension
1 November 2011 –
24 January 2012
Delays in handing over site to contractor
for Legon Underpass after relocation of
GT Vodafone cables
2.7
6th Extension
24 January 2012 –
31 May 2013
Delays in issuing design drawings to
correct identified faults in the design of
pier caps. Recurrent delay in payment of
IPC’s. Works were reduced and
suspended at several stages
16.22
7th Extension
31 May 2013 – 30
June 2017
Non-payment of IPC’s resulting in
suspension of works on site
49
8th Extension
30 June 2017 – 13
February 2019
Non-payment of IPC’s resulting in
suspension of works on site.
20
Total period of delay in months 117.42
Source: Audit team review of project correspondence and taking over certificates
59 |Performance Audit Report of the Auditor-General on selected Roads
148. As shown in Table 12 there were six EOTs which revised the expected
completion date to 31 May 2013. This was as a result of the following documented
reasons;
delays in handing over site and drawings to the contactor,
variations to specifications and designs,
obstructions to progress caused by existing utilities, and
delays in payment of IPCs
149. We noted that the contractor served notice on 2 October 2012 to MRH
through GHA, of its intention to reduce the rate of works due to continuing
problems of non-payment of IPCs and therefore its inability to commit to the 31
May 2013 completion date. Subsequently, the contractor gradually reduced the
rate of works from November 2012 and completely suspended works from
November 2015 to September 2016. The contractor resumed works in December
2016 and was given approval for a seventh EOT which changed the expected
completion date from 31 May 2013 to 30 June 2017.
150. The problem of non-payment of IPCs persisted resulting in further delays
beyond 30 June 2017, which necessitated an eighth Extension of Time, resetting
the completion date to 30 February 2019. The remaining section of the road was
taken over on 13 February 2019, which was the final substantial completion date
as per the contract.
151. We noted that GHA began the Tetteh Quarshie-Madina road project
without the full set of designs and drawings for the major components of the road.
Consequently, the project was stalled as a result of planning deficiencies brought
about by unfinalized road designs and drawings, unknown extent utilities to be
relocated and buildings affected by the road project. The drawing and designs
were supposed to be finalised as part of the project planning phase and handed
60 |Performance Audit Report of the Auditor-General on selected Roads
over to the contractor prior to commencement of the project. However, the designs
and drawings issued to the contractor in stages.
152. In total, there was approximately 117 months (or 10 years) of time overrun
beyond the initial 30-month duration for completion of the works. The extensions
of time resulted in additional costs to the project as indicated under payment sub-
finding.
3.4.1.4 Delivering the road project to the quality specified
153. Under Clause 8.1 of the General Conditions of Contract, the contractor is
obliged to execute and complete the works and remedy any identified defects in
accordance with the contract. According to Clause 36.1, all materials, plants and
workmanship for the works should be of the respective kinds described in the
contract and be in accordance with the Engineer’s instructions, and subjected from
time to time to such tests as the Engineer may require at such places as specified
in the contract.
154. Among the tests specified in the contract for materials were;
Grading,
Compaction,
Concrete tests, and
Asphalt tests
To determine whether the work done by the contractor conformed to contract
specifications, we inspected and measured the works done on site, cored the road
surface and took measurements of the thickness of the samples of the asphaltic
concrete layer in the presence of representatives of the contractor and GHA. Table
13 shows measurements we took on site of the road width, verge, bicycle lane and
walkways compared with specified dimensions in the contract.
61 |Performance Audit Report of the Auditor-General on selected Roads
Table 13: Auditors’ measurements of Tetteh Quarshie - Madina Road compared with
contract specified dimensions.
Chainage
in meters
(km)
Width of the
carriageway
in meters.
(Specified
width=10.5m)
Width of
Verge in
meters.
(Specified
width=2m)
Width of
Bicycle lane
in meters.
(Specified
width=2.5m)
Width of
Walk Way
in meters.
(Specified
width=3m)
Remarks
0 + 100 R 10.5 1.97 2.49 2.54 Width of walk way
did not meet
specification
1 + 600 R 10.5 1.92 2.55 2.53 Width of walk way
did not meet
specification
2 + 600 R 10.4 1.92 2.51 2.52 Width of walk way
did not meet
specification
3 + 100 R 10.4 1.91 2.52 2.52 Width of verge and
walk way did not
meet specification
3 + 000 L 10.6 1.94 2.37 2.64 Width of walk way
did not meet
specification
2 + 500 L 10.8 1.99 2.49 2.52 Width of walk way
did not meet
specification
1 + 000 L 10.6 2.00 2.49 2.52 Width of walk way
did not meet
specification
0 + 500 L 10.8 1.98 2.50 2.52 Width of walk way
did not meet
specification
4 + 350 R 6.6 1.95 2.47 2.53 Width of walkway
did not meet
specification
4 + 350 L 6.6 1.95 2.48 2.52 Width of walkway
did not meet
specification
(* represents service lane at Atomic Junction, L means left hand side and R means right hand side)
Source: Audit Field Inspection Results
62 |Performance Audit Report of the Auditor-General on selected Roads
155. From Table 13, the measurements of the road widths, verges, and bicycle
lanes met specification (given an assumed margin of error of 0.1m to compensate
for imperfections in measurement and calibrations). The measurements of the
walkways were in a range of 2.52m – 2.64m instead of the specified 3.0m.
156. We took 10 cores of the road asphalt surface layer at approximately 1 km
intervals from the two carriageways and measured the combined thicknesses of
the wearing and binder courses, to determine if they met the thickness
specification. Figure 2 shows the thickness measurements of the core samples
compared with the specified thickness of 100mm (shown as a red dashed line) and
the locations (chainages) at which the cores were taken. From Figure 2, the
thicknesses of 8 out of the 10 cores we measured, met the 100mm specification.
Figure 2: Measured thickness of asphalt core samples taken on the Tetteh Quarshie-
Madina road project
Source: Audit team inspection on 10 April 2019
120125
97
130
85
104 105115
110 110
0 + 100 R 1 + 600 R 2 + 600 R 3 + 100 R 4 + 350 R 4 + 350 L 3 + 000 L 2 + 500 L 1 + 000 L 0 + 500 L
Right Left
Th
ick
nes
s o
f co
re, m
m
Chainage
Measured thicknesses of core samples at various chainages
Passed Failed 100 mm thickness line
63 |Performance Audit Report of the Auditor-General on selected Roads
157. The samples were taken to the laboratory for testing to determine whether
the constituents of the asphalt concrete met specifications. The samples were
tested for the bulk density, air voids, bulk specific gravity, bitumen content and
grading. The laboratory results obtained are shown in Table 14. The laboratory
test results obtained indicated that the asphalt core samples tested were within the
specifications in the contract. See also Appendix 4 for details.
Table 14: Laboratory test results obtained for the Tetteh Quarshie-Madina road project
No. Average
Bulk
density
(gm/ml)
Average
Air
Voids
(%)
Bulk
Specific
Gravity
(gm/ml)
Asphalt
Bitumen
Content
(%)
Grading Average
Core
thickness
(mm)
Specifications
(Wearing
course)
3 - 5 4.5 – 5.5 40mm
Wearing
course batch 1
2.394 6.21 2.553 5.3 100% Within
Specification
38.75
Wearing
course batch 2
2.394 6.21 2.553 5.4 100% Within
Specification
Specifications
(Binder
course)
3 - 5 4.5 – 5.5 60mm
Binder course
batch 1
2.391 7.27 2.579 4.8 100% Within
Specification
72.87 Binder course
batch 2
2.391 7.27 2.579 4.5 100% Within
Specification
Source: Audit Service Consultant’s interpretation of laboratory test results on asphalt
core samples
158. We noted from our site inspections that even though the composition of the
asphalt met specifications, the road had developed pot holes at some sections of
the road from the first sectional taking over in 23 May 2009. Pictures of the
deteriorated sections observed is shown in Pictures 23 to 30. The road is supposed
to have a lifespan of 25years on condition of sustained routine maintenance
64 |Performance Audit Report of the Auditor-General on selected Roads
annually; and periodic maintenance of asphalt overlay which should be done once
the road surface condition has deteriorated to a level that is difficult to rectify by
routine maintenance, and is typically done between 6-8 years. We observed that
the 10 years of continuous use of the road without the regime of maintenance has
contributed to the early deterioration of the road even before the middle of the
project life as shown in pictures 22 to 29.
Picture 22: Pothole observed on the Tetteh
Quarshie Madina road
Picture 23: Pothole observed on the Tetteh
Quarshie Madina road
65 |Performance Audit Report of the Auditor-General on selected Roads
Picture 24: Deteriorated asphalt on the
Tetteh Quarshie Madina road
Picture 25: Expansion joint defect on the
atomic interchange concrete girder
Picture 26: Deteriorated asphalt on the
Tetteh Quarshie Madina road
Picture 27: Deteriorated asphalt on the
Tetteh Quarshie Madina road
66 |Performance Audit Report of the Auditor-General on selected Roads
Picture 28: Pothole observed on the Tetteh
Quarshie Madina road
Picture 29: Pothole observed on the Tetteh
Quarshie Madina road
Source : Audit team Inspection pictures taken by audit team on the Tetteh Quarshie-
Madina Road Project on 10 April 2019
3.4.2 Implementation of the Ayamfuri to New Obuase Road Project
3.4.2.1 Scope management (variations)
159. The scope of the Ayamfuri New Obuase Road Project (Lot 1) was to
rehabilitate and construct 26.0km of asphalt road. Within the 26.0km were three
bridges, eight box culverts and 53 No. pipe culverts of varying dimensions. The
width of the road carriage way was 7.3m with 2.0m shoulders on both sides. The
Project was supervised by M/S SAI Engineering Pvt on behalf of GHA and the
Employer (Ministry of Roads and Highways).
160. We used the odometer of the car to determine the length of the road
constructed and found it to be 26.0km from Ayamfuri to New-Obuase as specified
in the contract. The bridges and culverts had also been constructed as specified in
the original scope at the points as determined in the drawings.
161. Section 7 Sub-clause 13.1 of the General Conditions of Contract gives
authority to the Engineer to approve variations. When the variations are in excess
of 3% of the Accepted Contract Amount, he must seek approval from the
67 |Performance Audit Report of the Auditor-General on selected Roads
Employer. This is to ensure that the Employer is able to control the number of
variations on the project.
162. We noted from review of correspondence that during site clearance, the
number of trees, properties and farms affected were more than the estimates in
the BoQ. There were 951 trees cut instead of 43 stated in the BoQ while the number
of persons to be compensated was 255, and this was not captured by the BoQ. The
number of person compensated were contained in a valuation report prepared
and presented by Land commission to the GHA dated 28 September 2015 .The
volume of earthworks was 401,229m3 up from 7,000m3 in the BoQ, hence a
variation in the contract. Ghana Highway Authority (GHA) also varied the road
design by realigning some sections of the road to make it safe for traffic. These
changes resulted in Variation Order (VO) No.1.
163. The Employer obtained approval from the Central Tender Review Board to
vary the contract as per VO No.1 in the net amounts of GH¢ 2,907,257.32 and US$
3,127,390.88 on 4 June 2014.We noted that GHA instructed the Resident Engineer
to implement variation order number 1 on 20 January 2015. The variation involved
additions listed in Table 15.
68 |Performance Audit Report of the Auditor-General on selected Roads
Table 15: Details of Variation Order No. 1
SI No. Item Description Additional amount required
Amount in GH¢ Amount in US$
1 General items 130,660.00 208,953.35
2 Earthwork 539,783.53 868,626.83
3 Additional pavement thickness 692,737.50 1,112,475.00
4 Additional drainage structures 313,079.25 503,135.44
5 Slope and stabilisation 32,920.00 148,892.00
6 Relocation of utilities 933,780.92 -
7 Price contingency 264,296.12 284,308.26
Total 2,907,257.32 3,127,390.88
Source: Audit team review of approved Variation order No. 1 dated 20 January 2015
164. On 15 May 2015, the Resident Engineer (R.E.) wrote to GHA to request for
approval for Variation Order No. 2 which was to cater for price contingency
(fluctuations). According to the R.E., the variation was necessitated by the fact that
the rates quoted in the BoQ at the time of tender in January 2011 had to be adjusted
to the current market rates. We however noted that the BoQ did not make
provision for contingency to cater for price fluctuations hence V.O. 2 was raised
to pay for the fluctuations in accordance with Clause 13.8 of the General
Conditions of Contract (adjustment for changes in cost). GHA per a letter date 17
August 2015 got approval from Ministry of Roads and Highways for variation
order amounting to GH¢ 14,769,720.85 and US$ 2,547,262.12.
165. GHA presented a request for no objection to the World Bank for variation
order No.3 on 9 October 2017 through the Ministry of Roads and Highways. This
was as a result of redesign of sections of the road and additions during
construction. The V.O. 3 included additions to general items, demolition and site
69 |Performance Audit Report of the Auditor-General on selected Roads
clearance, earthworks, roads and pavings, signs and markings and drainage
structures as shown in Table 16.
Table 16: Details of variation order No. 3
Source: Variation Order No.3 dated 15 August 2017
166. There were three variation orders raised on the project, the total of which
was GH¢ 22,573,895.05 for the cedi component and US$ 10,543,792.05 for the
United States of America dollar component as shown in Table 17.
Table 17: Summary of variation orders and contract sum on Ayamfuri-Obuase Road
(Lot1)
Amount in GH¢ Amount in US$
Original Contract Sum 13,641,596.55 20,694,136.81
Variation Order No. 1 2,907,257.32 3,127,390.88
Variation Order No. 2 14,769,720.85 2,547,262.12
Variation Order No. 3 4,896,916.88 4,869,139.05
Total 13,641,596.55 22,573,895.05 20,694,136.81 10,543,792.05
Revised Contract Sum 36,215,491.60 31,237,928.86
Item Description Additional amount required
Amount in GH¢ Amount in US$
General items 2,115,387.89 399,579.84
Demolition and site clearance 22,732.50 36,525.28
Earthworks 1,919,736.70 3,084,869.40
Roads and Pavings 59,477.01 95,567.21
Signs and Markings 22,155.00 35,606.00
Drainage Structures 757,427.79 1,216,991.31
Estimated Net Additions 4,896,916.88 4,869,139.05
70 |Performance Audit Report of the Auditor-General on selected Roads
Source: Audit team review of variation orders
167. The variation orders resulted in an increase of approximately 165.5% for the
GH¢ component and 50% for the USD component above the contract sum. Our
analysis showed that VO. 2, was occasioned by additional quantities of works
which were not part of the initial contract’s BoQ and unknown site conditions
which were encountered during construction. We also observed that the six-year
lapse between the completion of the design and construction also accounted for
some changes along the road corridor, especially increase in settlements along the
road corridor resulting in payment of more compensation.
168. We observed that if the BoQ had captured all items, the need to issue VO 1
and 3 would not have been necessary. Similarly, compensation payment cut off
point were not instituted to avoid individual taking advantage of compensation
payment to build along the road corridor. We also noted that the delay in
commencement of the project for six years resulted in the high level of fluctuation
payment.
3.4.2.2 Cost management (Payments for works)
169. Sub Clause 14.7 (a and b) of the General Conditions of contract stipulates
that the Employer shall pay the contractor the first instalment of the advance
payment within 42 days after issuing the letter of acceptance or within 21 days
after receiving documents in accordance with sub-clause 4.2 (Performance
Security) and subclause 14.2 (Advance payment). We noted that the Employer
paid the Advance Mobilization of US$ 3,087,283.02 and GH¢ 1,936,739.55 to the
contractor on 15 and 16 April 2013 respectively. This was about six months after
the acceptance letter but two weeks before the project commenced.
170. The Employer shall pay the amount certified in each interim payment
certificate (IPC) within 56 days after the engineer receives the statement and
71 |Performance Audit Report of the Auditor-General on selected Roads
supporting documents. Also, Sub-Clause 14.8 (a and b) of the General Conditions
of contract stipulates that if the contractor does not receive payment in accordance
with sub clause 14.7 (payment), the contractor shall be entitled to receiving
financing charges compounded monthly on the amount unpaid during the period
of delay. The charges are to be calculated at an annual rate of three percentage
points above the discount rate of the central bank in the country of the currency
of payment and shall be paid in such currency. Regular payments of IPCs on time
ensures adequate cashflow available to the contractor in order for him to meet his
costs
171. We noted that between September 2013 and March 2019, 34 interim
payment certificates amounting to GH¢ 35,384,433.54 and US$ 26,054,962.91 were
raised and certified by the Resident Engineer. At the time of the audit, 27 IPCs
amounting to GH¢ 31,383,514.15 and US$ 23,543,992.37 had been honoured by the
Ministry of Roads and Highways. All payment certificates had exceeded the 56
days payment deadline as stipulated in Sub-Clause 14.7 (b) of the General
Conditions of Contract. These delayed IPCs attracted interest on delayed payment
which amounted to GH¢ 859,380.24 and US$ 79,024.10. The contractor made
claims for the interest amounts through IPCs 7A,14A,19A, 22A and 24A. Details
of the IPCs raised is attached as Table 29 in Appendix 9.
172. Our analysis of the trail of IPC 2 to IPC 27 which had been paid shown in
Table 18 indicates that it took between 17 to 173 days for the IPCs to move from
the site to the Director of Finance at GHA before being forwarded to the Ministry
of Roads and Highways for payment.
72 |Performance Audit Report of the Auditor-General on selected Roads
Table 18: Analyses of delays beyond 56 days
IPC No.
Processing time, days
Delay due to processing, days
Delay due to non-payment, days
Total Delay, days
GH¢ USD GH¢ USD
2 `31 0 32 32 32 32
3 51 0 38 36 38 36
4 17 0 86 98 86 98
5 78 22 14 17 36 39
6 75 19 42 23 61 42
7 124 68 41 51 109 119
8 107 51 8 12 59 63
9 93 37 36 90 73 127
10 69 13 35 54 48 67
11 70 14 48 43 62 57
12 69 13 29 47 42 60
13 79 23 58 66 81 89
14 47 0 83 84 83 84
15 112 56 22 107 78 163
16 89 33 22 22 55 55
17 81 25 - 102 - 127
18 117 61 - 61 - 122
19 100 44 - 99 - 143
20 83 27 - 124 - 151
21 117 61 - 50 - 111
22 117 61 - 48 - 109
23 96 40 17 17 57 57
24 131 75 166 71 241 146
25 173 117 44 44 161 161
26 115 59 31 31 90 90
27 76 20 11 11 31 31
Source: Audit review of IPCs 2 to 27
173. We noted that the delays in payment of IPCs for works were between 31
and 241 days. The Ministry of Roads and Highways stated that it had no control
over the delays since by the time the IPC got to the Ministry, the 56 days had
already elapsed. The delay in payment experienced at the Ministry was due to the
internal certification of the amount to be paid as the IPC had to be sent to the
World Bank desk at Ministry of Finance and back to the Ministry of Roads and
highways.
73 |Performance Audit Report of the Auditor-General on selected Roads
174. We noted the delays in processing IPCs at GHA was due to lack of
institutional policies on how long IPCs should stay at each processing point before
the stipulated 56 elapses resulting in undue delays in processing the IPCs for
payment. The delays at the Ministry were due to the World Banks procedurals on
payment and replenishment of funds since all World Bank funded road projects
were paid from a single source.
3.4.2.3 Time management (Completing the works on time)
175. Section 7 Sub-clause 8.2 of the General Conditions of Contract requires the
Contractor to complete all works stated in the contract, including passing of tests
as required for the purpose of Taking-Over, within the Time for Completion.
176. We noted that the project commenced on 2nd May 2013 and was scheduled
for completion on 1 May 2015 (24 months). On 20 January 2015, GHA granted the
contractor four (4) months extension of time from 1 May 2015 to 31 August 2015
due to earthwork quantities in a Variation Order No1. On 30 April 2015, the
Contractor again requested extension of time of 15 months to complete the project
citing the following reasons;
Actual quantities of works on site are beyond the BoQ quantities (from
7000m3 to 401,229m3
Unpaid compensation area of about 3.2km (10 communities) doted along
the project corridor hindering their complete access to site.
177. However, GHA granted the Resident Engineer a provisional approval of 6
months extension of time for the contractor to implement the works. This approval
was based on condition that MRH gives the contractor possession of the 3.2km
and ‘No Objection’ from the World Bank. The tentative revised completion date
was 28 February 2016. To mitigate further delay caused by lack of possession of
site at the 10 communities, GHA requested the contractor to pay for the
compensation of critical areas for reimbursement subsequently under the contract,
74 |Performance Audit Report of the Auditor-General on selected Roads
and the contractor obliged. We noted that an official approval of extension of time
had not been granted by the Ministry and the World Bank.
178. On 5 April 2017, GHA wrote to the Ministry recommending a 24-month
extension of time effective from 1 May 2015 to 1 June 2017 to enable the contractor
complete the works. This was as a result of delayed payment of compensation to
the project affected persons by the Ministry. The contractor requested for
extension of time to complete works remaining at Nkutumso which had delayed
due to compensation issues. GHA granted three (3) months extension from 30
September 2017 to 30 December to 2017. On 24 October 2017, the CEO of GHA
approved the request for extension of time.
179. As a result of the extension of time, the project was delayed for 36 months
denying the beneficiaries on that corridor easy access from one community to
another.
3.4.2.4 Delivering the road project to the quality specified
180. Section 8 of the General Conditions of Contract provides both standard and
special specifications which the Contractor is to adhere to. Section 2 of the
Specifications spells out the tests on materials and the required level of
workmanship required for the project. The tests include but not limited to:
Grading,
Compaction,
Concrete tests, and
Asphalt tests
181. The Specification for concrete works for drains and pipe culverts for
Ayamfuri-New Obuase project was C20/25. That of box culverts and bridges was
C25/30. For the road, the carriageway width was 7.3 m and shoulder width were
2.5 m in each direction. The structure of the pavement for the road was 550mm
75 |Performance Audit Report of the Auditor-General on selected Roads
made up of 40 mm Wearing course, 60mm Binder course, 300mm base and 150mm
sub-base.
182. The audit team inspected the works carried out by the contractor and
measured the length of the road, width of the carriageway and dimensions of
culverts. We also took Schmidt hammer readings of concrete structures. The team
extracted 20 asphalt core samples and measured the combined thicknesses of the
binder and wearing course. These measurements were taken in order to compare
our readings with the contract specifications and to note any deviations. Our
observations from the field inspection is shown in Tables 19 and 20 and Figure 3.
Table 19: Ayamfuri-New Obuase Project Schmidt Hammer Readings
Location of
Structure
(Chainage in
kilometers (km))
Type of
Structure
Schmidt Hammer
Reading (N/mm2)
Specified
Strength
(N/mm2)
Remarks
2 + 600 LHS Trapezoidal
drain
26 25 Met
specification
2 + 600 RHS Trapezoidal
drain
15 25 Did not
meet
specification
19 + 500 LHS
(Wing Wall)
Pipe Culvert 38 25 Met
specification
19 + 500 RHS
(Wing Wall)
Pipe Culvert 48 25 Met
specification
Source: Audit Field Inspection Results
76 |Performance Audit Report of the Auditor-General on selected Roads
Table 20: Ayamfuri-New Obuase Project road measurements
Chainage
in
kilometers
(km)
Width of
Road, as
measured
by audit
team in
meters
Width of
road as
specified
in
Contract
in meters
Width of
Shoulder
as
measured
in meters
(LHS)
Width of
Shoulder
as
measured
in meters
(RHS)
Specified
shoulder
Width on
both
sides in
meters
Remarks
1 + 300 7.20 7.3 2.65 2.80 2.5 Road
width did
not meet
specified
width
2 + 600 6.80 7.3 2.66 2.95 2.5 Road
width did
not meet
specified
width
3 + 900 7.20 7.3 2.53 3.17 2.5 Road
width did
not meet
specified
width
5 + 200 7.05 7.3 2.55 2.55 2.5 Road
width did
not meet
specified
width
6 + 500 7.20 7.3 2.60 2.45 2.5 Road
width did
not meet
specified
width
7 + 800 6.90 7.3 2.60 2.80 2.5 Road
width did
not meet
specified
width
9 + 100 7.18 7.3 2.65 2.62 2.5 Road
width did
not meet
77 |Performance Audit Report of the Auditor-General on selected Roads
specified
width
10 + 400 7.08 7.3 2.50 2.87 2.5 Road
width did
not meet
specified
width
11 + 700 7.18 7.3 2.50 2.82 2.5 Road
width did
not meet
specified
width
13 + 00 7.21 7.3 2.28 2.71 2.5 Road
width did
not meet
specified
width
14 + 300 6.90 7.3 2.60 3.00 2.5 Road
width did
not meet
specified
width
15 + 600 7.27 7.3 2.75 2.68 2.5 Road
width did
not meet
specified
width
16 + 900 7.00 7.3 2.69 2.71 2.5 Road
width did
not meet
specified
width
18 + 200 7.14 7.3 2.84 2.62 2.5 Road
width did
not meet
specified
width
19 + 500 6.93 7.3 2.71 2.91 2.5 Road
width did
not meet
78 |Performance Audit Report of the Auditor-General on selected Roads
specified
width
20 + 800 6.95 7.3 3.23 2.57 2.5 Road
width did
not meet
specified
width
22 + 100 7.09 7.3 2.73 2.68 2.5 Road
width did
not meet
specified
width
23 + 400 7.16 7.3 2.84 2.60 2.5 Road
width did
not meet
specified
width
24 + 700 6.70 7.3 2.90 3.00 2.5 Road
width did
not meet
specified
width
26 + 00 6.95 7.3 2.82 2.93 2.5 Road
width did
not meet
specified
width
Source: Audit Field Inspection Results April 2019
79 |Performance Audit Report of the Auditor-General on selected Roads
Figure 3: Graph of asphalt core thickness measurements
Source: Audit Field Inspection measurements (April 2019)
183. Our analysis of figure 3, shows that eight readings of the cored samples
were above the specified thickness of 100mm (red dotted line) which meant that
the core thicknesses met the specifications while the 12 readings below the red
dotted line did not meet the thickness specifications. We noted that the thickness
of the sample taken at Chainage 20+800km was 55mm instead of 100mm,
indicating a significant deviation from the specification. Our analysis of data
collected during field inspection (Tables 19 and 20 and Figure 3) indicates that the
Consultant and GHA did not ensure that 60% of the thickness of sampled cores
met the specifications. Our observations cast doubt on the quality of the test results
submitted which indicated that the works had met the specifications in the
contract.
118120
100
109
100
118
123
105
85
74
98
85
80
96
85 85
80
55
85
98
1 +300
2 +600
3 +900
5 +200
6 +500
7 +800
9 +100
10 +400
11 +700
13 +00
14 +300
15 +600
16 +900
18 +200
19 +500
20 +800
22 +100
23 +400
24 +700
26 +00
Th
ick
nes
s o
f co
re, m
m
Chainage 0 - 26 + 00 km
Measured thickness of core samples at various chainages
Passed Failed 100 mm thickness
80 |Performance Audit Report of the Auditor-General on selected Roads
184. The samples were taken to the laboratory for testing to determine whether
the constituents of the asphalt concrete met specifications. The samples were
tested for the bulk density, air voids, bulk specific gravity, bitumen content and
grading. The laboratory results obtained are shown in Table 21. The laboratory
test results obtained indicated that the air voids in the samples taken were above
8%. According to the Audit Service’s Consultant “The average air voids of 8.385%
recorded for the Ayamfuri New Obuasi road is on the high side. An approximate
“rule-of-thumb” is for every 1 percent increase in air voids (above 6-7 percent),
about 10 percent of the pavement life may be lost”. Going by this interpretation,
the Ayanfuri New Obuasi road with 8.385% of air voids will deteriorate faster than
expected.
Table 21: Laboratory test results obtained for the Ayamfuri – New Obuase road project
No. Average
Bulk
density
(gm/ml)
Average
Air
Voids
(%)
Bulk
Specific
Gravity
(gm/ml)
Asphalt
Bitumen
Content
(%)
Grading Average
Core
thickness
(mm)
Specifications
(Wearing
course)
3 - 5 4.5 – 5.5 40mm
Wearing
course batch 1
2.211 8.385 2.413 5.2 100% Within
Specification
41.285
Wearing
course batch 2
2.211 8.385 2.413 5.4 100% Within
Specification
Specifications
(Binder
course)
3 - 5 4.5 – 5.5 60mm
Binder course
batch 1
2.25 8.465 2.458 4.6 100% Within
Specification
52.485 Binder course
batch 2
2.25 8.465 2.458 4.7 100% Within
Specification
Source: Audit Service Consultant’s interpretation of laboratory test results on asphalt
core samples
81 |Performance Audit Report of the Auditor-General on selected Roads
185. We also noted that quality specifications for the specific components of
asphalt were made with minimum and maximum limits for grading of aggregates.
These are industry standards. However, our analysis of the graph from the
Laboratory test results show that although the readings show 100% within
specification, the contractors are 90% of the time gravitating towards the lower
minimum limits. (See appendix 4)
186. We noted from our site inspections that sections of the road had begun to
show signs of deterioration as at the time of the audit inspection in April 2019.
Pictures 30 to 33 show signs of degradation of sections of the Ayamfuri-New
Obuase road project.
Picture 30: Early degradation of a section
of the Ayamfuri- New Obuase project
Picture 31: Early degradation of a section
of the Ayamfuri- New Obuase project
82 |Performance Audit Report of the Auditor-General on selected Roads
Picture 32: Early degradation of a section of the
Ayamfuri- New Obuase project
Picture 33: Early degradation of a section of the
Ayamfuri- New Obuase project
Source: Audit Field Inspection on 15 April 2019
3.4.3 Implementation of the Bolgatanga-Bawku-Polimakom Road Project
3.4.3.1 Scope management (variations)
187. The scope of the Bolgatanga-Bawku-Polimakom Road Project was to
construct a 102.55km road with 3 bridges located at km 1+800 (Zuarungu), km
30+800 (Tilli) and km 61+700 (Zebilla). The road project is divided into 14 lots.
188. From review of progress reports and correspondence, we noted that the
road comprised 3km of asphalt concrete and the remaining 99.55km being double
surface dressing. Messrs Queiroz Galvao Construction Limited was to construct
the 2km dual carriageway asphalt road of width 14.6m from Bolgatanga and 1km
single carriageway asphalt in Zebilla Township. The double surface dressed
section of the road is a single carriageway with a width of 7.3m. In addition to the
road, the contractor was to construct 180 No. Pipe Culverts, 7 No. Box Culverts, 3
Toll plazas and 2 No. axle weighing stations along the road corridor.
83 |Performance Audit Report of the Auditor-General on selected Roads
189. At the time of the audit field inspection in May 2019, construction work had
stalled from October 2018 and actual physical progress was 19.45% instead of a
planned progress of 68.84%. The team noted that there were no scope changes to
the project.
3.4.3.2 Cost management (Payment for works )
190. Sub Clause 14.7 (a and b) of the General Conditions of contract stipulates
that the Employer shall pay the contractor the first instalment of the advance
payment within 42 days after issuing the letter of acceptance or within 21 days
after receiving documents in accordance with sub-clause 4.2 (Performance
Security) and subclause 14.2 (Advance payment). The Employer shall pay the
amount certified in each interim payment certificate within 56 days after the
engineer receives the statement and supporting documents. Regular payments of
IPCs on time ensures adequate cashflow available to the contractor in order for
him to meet his costs.
191. Also, Sub Clause 14.8 (a and b) of the General Conditions of contract
stipulates that if the contractor does not receive payment in accordance with sub
clause 14.7 (payment), the contractor shall be entitled to receiving financing
charges compounded monthly on the amount unpaid during the period of delay.
The charges are to be calculated at an annual rate of three percentage points above
the discount rate of the central bank in the country of the currency of payment and
shall be paid in such currency.
192. We noted from monthly progress reports and correspondence that Ghana
Highway Authority (GHA) after issuing an acceptance letter to the contractor,
Queiroz Galvao on 26 August 2016, paid the contractor an advance mobilisation
of GH¢ 91,911,576.70 on 11 September 2016. This was within the 42 days as
stipulated in the General Conditions of Contract.
84 |Performance Audit Report of the Auditor-General on selected Roads
193. We noted that between January 2017 and July 2019, 12 Interim Payment
Certificates (IPCs) amounting to GH¢ 122,627,434.02 were certified by the Resident
Engineer. IPC’s 2, 3, 7 and part of IPC 4 amounting to GH¢ 40,612,195.25 had been
paid and the rest are outstanding. We further noted that all the 12 certificates had
exceeded the 56 days payment deadline as stipulated in Sub Clause 14.7 (b) of the
General Conditions of Contract as shown in Table 22.
Table 22: Detailed of Payment to Contractor as at 31 July 2019
Source: Progress Report No. 23 and Correspondence from Queiroz Galvao
194. From Table 22, the contractor raised claims for interest on delayed payment
amounting to GH¢ 38,189,353.65 as per Sub Clause 14.8 of the General Conditions
of contract. This was an additional cost to the project, representing 31.28% of the
value of the certificates raised which has not yet been paid.
195. We analysed the trail of IPCs from the site to GHA to determine the time it
took to process the certificates before payment. We noted that the processing of
IPC No. Amount Certified (GH¢)
Days of Delay
Amount Outstanding
(GH¢)
Interest on Delayed
Payment (GH¢)
IPC 2 16,330,915.03 208
0.00 3,444,352.42
316
IPC 3 9,848,202.21 101
0.00 808,939.05
179
IPC 4 10,534,568.06
250
4,718,022.32
4,537,617.31 614
809
IPC 5 12,686,939.30 783 12,686,939.30 7,141,876.72
IPC 6 8,586,534.89 748 8,586,534.89 4,523,584.04
IPC 7 8,616,532.18 253 0.00 1,468,766.22
IPC 8 6,702,896.10 694 6,702,896.10 3,171,940.82
IPC 9 7,821,645.55 658 7,821,645.55 3,485,855.56
IPC 10 9,812,058.56 630 9,812,058.56 4,069,365.59
IPC 11 14,930,670.88 574 14,930,670.88 5,447,589.05
IPC 12 8,950,528.30 498 8,950,528.30 2,708,909.01
IPC 13 7,805,943.08 357 7,805,943.08 1,633,849.33
Total 122,627,434.02 82,015,238.78 38,189,353.65
85 |Performance Audit Report of the Auditor-General on selected Roads
the IPC starts from site where the RE vets and validates the contractor’s claims.
The Regional Coordinating Council (RCC) endorsed the IPCs and forwarded it to
GHA head office for final scrutiny before payments were made to the Contractor.
The actual examination of the IPC is done by the RE on site and crosschecked at
GHA head office.
196. We examined the endorsement dates on IPCs 2 to 13 (excluding IPC 11) and
found that it took between 70 and 111 days for the IPCs to move from the Resident
Engineer to Ministry of Roads and Highways for payment. According to
management of GHA, there are instances (in the case of IPCs 4,6,8,9,12 and 13)
where the 56 days stipulated in clause 14.7 elapse before the IPCs gets to GHA
head office. We noted that GHA did not have institutional policies on how long
IPCs should stay at each processing point before the stipulated 56 elapses resulting
in undue delays in processing the IPCs for payment. The details of the delays
beyond 56 days is presented in Table 23.
197. Based on the information in Table 23, delays in honouring certificates
beyond the stipulated time resulted in Contractors applying the clause on delayed
payment thereby needlessly increasing the project cost. In the given instance, if
the Contractor were to further apply Clause 14.7 (b) of the General Conditions of
Contract, Government of Ghana will pay an interest amount in excess of GH¢
38,189,353.65 in respect of IPCs that were outstanding per our calculation as at
time of the audit (July 2019).
86 |Performance Audit Report of the Auditor-General on selected Roads
Table 23: Details of delays beyond 56 days
IPC No.
No. of days spent
Total No. of days used
for processing
(P=a+b+c+e)
Delay beyond 56 days
Resident Engineer
(a)
GHA Regional Director
(b)
Regional Coordinati
ng Council (c)
GHA (e)
Delay due to processing (D=P-56)
Delay due to non-payment (X) as at the time of audit
Total delay (D+X)
2 33 1 9 27 70 14 194 208
302 316
3 21 0 24 37 82 26 75 101
153 179
4 11 9 54 22 96
40 210 250
574 614
769 809
5 16 4 28 22 70 14 769 783
6 20 0 58 20 98 42 702 748
7 8 14 34 21 77 21 228 253
8 13 11 42 21 87 31 663 694
9 14 20 36 19 89 33 625 658
10 20 8 26 30 84 28 602 630
12 44 5 37 25 111 55 443 498
13 21 8 29 40 98 42 315 357
Source: Audit Team review of IPCs 2 to 13
198. From our review of releases to the Road Fund from the Ministry of Finance,
other statutory sources and corroborated through our interview with Road Fund
Coordinator the delay in payment of the IPCs were also due to inadequate inflows
to meet the value of certificates to be paid.
199. Consequently, the delays in payment observed contributed to a slowdown
in the contractor’s rate of work on the 12 April 2017 and a complete halt in the
construction on 8 November 2017.
3.4.3.3 Time management (Completing the works on time)
200. According to the contract, the commencement date of the project was 4
December 2016 and the expected completion date was 4 June 2019 (30 calendar
87 |Performance Audit Report of the Auditor-General on selected Roads
months). We noted from correspondence and progress reports that on 12 April
2017, the contractor, Queiroz Galvao notified GHA of his intention to reduce the
rate of works due to delay in honouring Interim Payment Certificate (IPC) No. 2.
GHA acknowledged the contractor’s letter and his right under Sub-clause 16.1 of
the contract to reduce the rate of works on 12 May 2017. The contractor on 8
November 2017 wrote to inform GHA of his intention to suspend works due to
non-payment of IPCs 2,4,5,6,7,8,9 and 10. The contractor actually suspended
works on 30 November 2017. On 8 January 2018 GHA informed the Ministry of
Roads and Highways of the contractor’s suspension of the works, resulting in the
payment of the final instalment of IPC 2 on 18 January 2018. The contractor
resumed work on 12 March 2018 after the payment but at a slow pace.
201. We noted that IPC 7 and part of IPC 4 were subsequently settled by 18 April
2018 which enabled the contractor remain at work but at a reduced rate. The
contractor suspended the works for the second time on 8 October 2018 due to
several reminders to GHA about non-payment of the remaining IPCs. On 25
October 2018, GHA wrote to the Ministry of Roads and Highways to inform them
of the suspension of works by the contractor due to non-payment of the remaining
IPCs. As of 31 July 2019, 31 calendar months after the start of the project in
December 2016, physical progress of work reported by the Resident Engineer was
19.45% (one month after the expected completion date of the project).
202. As a result of the reduced rate of works and the complete suspension by the
contractor, the project which was supposed to be completed on 4 June 2019 was
less than 20% complete.
88 |Performance Audit Report of the Auditor-General on selected Roads
3.4.3.4 Delivering the road project to the quality specified
203. Section 8 of the General Conditions of Contract provides both standard and
special specifications which the Contractor is to adhere to. Section 2 of the
Specifications spells out the tests on materials and the level of workmanship
required for the project. The tests include but are not limited to:
Grading,
Compaction
Concrete tests, and
Asphalt tests
204. The Specification for concrete strength for drains and pipe culverts for the
Bolgatanga-Bawku- Polimakom Road Project was C20/257. For the road, the
carriageway width was 7.3 m and shoulder width were 2.0m in each direction.
205. The audit team inspected the works carried out by the contractor and
measured the length of the road and width of the carriageway/shoulders in the
presence of the Contractor’s and GHA’s representatives. We also took Schmidt
hammer readings of concrete structures. These measurements were taken in order
to compare our readings with the contract specifications and to note any
deviations. Our measurement and readings from the field inspection are shown in
Tables 24 and 25.
7
89 |Performance Audit Report of the Auditor-General on selected Roads
Table 24: Bolgatanga Bawku Polimakom
Location of Structure
(Chainage in km)
Type of
Structure
Schmidt
Hammer
Reading
(N/mm2)
Specified
Strength
(N/mm2)
Remarks
33 + 052 (Head Wall) Pipe Culvert 38 25 Met Specification
34 + 844 (Wing Wall) Pipe Culvert 34 25 Met Specification
62 + 260 U-Drain 34 25 Met Specification
74 + 132 (Head Wall) Pipe Culvert 34 25 Met Specification
Source: Audit Field Inspection Results
Table 25: Bolgatanga Bawku Polimakom
Chainage
in km
Width of
Road, as
measured
by audit
team in
meters
Width of
road as
specified
in
Contract
in
meters
Width of
Shoulder
as
measured
in meters
(LHS)
Width of
Shoulder
as
measured
in meters
(RHS)
Specified
shoulder
Width on
both
sides in
meters
Remarks
30 + 700 7.5 7.3 2 2 2 Met Specification
34 + 844 7.4 7.3 2 2 2 Met Specification
41 + 925 7.6 7.3 2 2 2 Met Specification
47 + 775 8.0 7.3 2 2 2 Met Specification
54 + 790 7.4 7.3 2 2 2 Met Specification
58 + 790 8.0 7.3 2 2 2 Met Specification
62 + 260 7.4 7.3 2 2 2 Met Specification
74 + 175 7.7 7.3 2.2 2.2 2 Met Specification
Source: Audit Field Inspection Results
206. Our analysis of data collected during field inspection showed that the
Consultant ensured Queiroz Galvao adhered to the specifications in the contract.
We reviewed quality assurance results and found that the consultant ensured that
the contractor followed the quality control and quality assurance standards. We
90 |Performance Audit Report of the Auditor-General on selected Roads
also reviewed test results for concrete structures which indicated that the strength
specifications had been met for the works done so far. However, we noted that
due to the suspension of works, the embankments along the road were being
eroded since they had not yet been stone-pitched as shown in Picture 35. Pictures
34 to 37 show the state of the eroded road embankments which will have to be
redone again at a cost to the tax payer.
Picture 34: Stone pitched erosion
protection of embankment
Picture 35: deteriorated embankment of
road due to erosion
91 |Performance Audit Report of the Auditor-General on selected Roads
Picture 36: deteriorated embankment of
road due to erosion
Picture 37: deteriorated embankment of
road due to erosion
Conclusion
207. The Tetteh Quarshie –Madina road project was largely constructed to the
required contract specification with minimal deviations in the width of walkways
and observed defects probably contributed to by the fact that the affected section
of the road was taken-over in May 2009. This indicated that application of quality
control measures were relatively adequate. The implementation process was
however bedevilled by problems of poor management of scope, schedule, cost and
payment which resulted in significant cost and time overruns.
208. The scope of the works was changed by significant differences between
estimated quantities and implemented quantities; removal and reintroductions of
essential items; and inclusion of additional works that were not related to the
project. The total cost of variations resulted in a 133% and 93% increases
respectively to the Cedi and US Dollar components of the contract sum. Also, the
implementation stage was excessively prolonged by untimely issuing of design
drawings, obstructions by existing utility lines, and persistent delays in honouring
payment certificates. All these were largely consequences of poor planning i.e.
lack of adequate feasibility studies, design drawings and cost planning and
92 |Performance Audit Report of the Auditor-General on selected Roads
estimation. The total amount spent on the project at completion was GH¢
170,477,493.66 and US$ 49, 974,242.82 i.e. 624% and 187% respectively of the Cedi
and US Dollar components to the contract sum with the possibility of further
payments due to costs of Extension of Time which is yet to be claimed. The
numerous implementation problems also delayed the project by over 10 years.
209. The Ayamfuri-New Obuase road project was not completed on schedule
due to variations brought about by unknown site conditions which should have
been determined during the feasibility and design stage in order to inform the
project estimation. We are of the opinion that the cost overruns which occurred
were due to the variations which were unbudgeted and unforeseen in the
planning stage, compensation of project affected persons, relocation of utilities
and claims for delay in payments. The delay in completion was partly due to delay
in relocation of project affected persons and utilities as well as changes in the
design due to road safety concerns observed during implementation. The
thicknesses of the asphalt and the road widths measurements which did not meet
specification were due to failure of the project supervisors to institute thorough
quality control during asphalt works on the project which will impact on the
expected lifespan of the road.
210. The Bolgatanga-Bawku-Polimakom road project has not been completed
due to GHA’s inability to ensure that IPC’s were honoured on time by the Road
Fund Secretariat. The works on the road corridor has stalled and the project which
was supposed to have been completed in June 2019 is 19.45% complete thereby
denying users of the benefits thereof. The delay in payment of IPCs as at June 2019
has also led to interest charges thereby increasing the cost of the project. We are of
the opinion that, since the time of completing the project has elapsed, there is
going to be an extension of time to complete the project which will also be
associated with extra cost.
93 |Performance Audit Report of the Auditor-General on selected Roads
Recommendations
211. Analysis of data made available to us show that challenges exist during
implementation of road projects in the country that has to be addressed. The
challenges are in the areas of scope management, payments for work done and
ensuring projects are completed within schedule to get the full benefit for users.
212. To ensure proper implementation of current and future road projects, we
recommend that GHA should;
viii. have complete drawings and designs that inform cost estimates and
clearly define the scope of works of all projects,
ix. desist from the practice of removing needed work items in order to meet
budget ceilings only to reintroduce them during implementation,
x. Fulfil all relevant conditions of relocation and compensation precedent to
project commencement, and introduce cut off time to accept payment of
compensation to prevent residents taking advantage to relocate on site
earmark for road works.
xi. Treat additional works unrelated to ongoing projects not as variations and
should be subjected to separate procurement processes
xii. Ensure that it seeks and obtains approval for all variations,
xiii. Identify at an early stage the source of funding and possibly ring fence
such funds to meet all projected costs during implementation.
xiv. immediately institute and implement a policy on processing and payment
of IPCs within 56 days and sanction officers who delay each IPC with cost
of claims due to the delayed IPC,
94 |Performance Audit Report of the Auditor-General on selected Roads
xv. Draw and implement a maintenance schedules to prolong the project life
after they have been handed over after construction,
xvi. Take steps to construct the embankments of portions of the Bolgatanga-
Bawku-Polimakom road to prevent it from further deterioration so as not
to incur additional cost to the state.
95 |Performance Audit Report of the Auditor-General on selected Roads
3.5 COMPLETION AND DOCUMENTATION
3.5.1 Completion
213. Under Clause 48 of the General Conditions of the Contract, the Engineer
(GHA) is to issue a Taking - Over Certificate in respect of the whole or any
substantial part of the works that has been completed and has passed the required
tests, when the Engineer deems the works or any part of it to be substantially
completed and ready for use. In line with industry best practice, we expect GHA
to carry out take – over inspection, and ensure the contractor provides as-built
drawings and maintenance manuals (for Traffic Lights).
214. For the Tetteh Quarshie-Madina Project, we noted from project
correspondence that based on a request from the Minister of Roads and Highways,
the contractor completed section Ch. 1 + 025 to Ch. 3 + 000 to ease traffic
congestion in that section of the road. A team from GHA carried out take-over
inspection and prepared a snag list of defects which the contractor rectified. GHA
issued a Sectional Taking-Over Certificate for Ch. 1 + 025 to Ch. 3 + 000 on 23 May
2009. Following similar procedures, GHA took over the remaining portions of the
works and issued a Taking-Over Certificate on 13 February 2019, approximately
10 years from the first taking over. GHA obtained full set as-built drawings from
the contractor in electronic format.
215. For the Ayamfuri-New Obuase Road Project we noted that the Contractor
wrote to GHA for inspection of the works at substantial completion on 5th August
2017. The Resident Engineer inspected the road works and presented a pre-taking
over snag list to the contractor on 1 February 2018 for implementation. The snag-
list contained 130 defects observed and comments by the RE which the Contractor
was to rectify prior to the taking over inspection. The Resident Engineer Informed
the Chief Executive of GHA of the substantial completion inspection of the project
to take place on the 29 May 2018.
96 |Performance Audit Report of the Auditor-General on selected Roads
216. GHA formed an inspection team comprising officers from GHA head
office(seven), Project Supervision Team(nine) and the Contractors staff (4) to
inspect the works on the 28 May 2018. The inspection team made 18 observations
of defects on the road project for which GHA instructed the contractor to rectify.
217. A subsequent inspection was carried out on 17 August 2018 at which the
inspection team agreed that the activities the contractor was instructed to carry
out had been effected. This inspection was done in in the presence of;
Road Highway Director (C/R)
Resident Engineer
Materials Manager
Project Surveyor
Technical Officer Materials
Technical Officer, Survey
Secretary
CJIC Quantity Surveyor
218. Hence in accordance with Sub-clause 10.1 of the conditions of contract,
GHA issued the taking over certificate for the works in a letter dated 14 September
2018. The certificate was signed by the Deputy Chief Executive Development for
the Chief Executive. The project was in defects liability period at the time of the
audit inspection in April 2019.
3.5.1 Documentation
219. Filing and maintenance of documents was not complete and was difficult
to have a complete trail of the progress of the project. For example there were no
pre-qualification documents, copies of submitted tenders and evaluation reports
in the project files for us to review. Also, there was no segregation of documents
as different categories of documents were mixed in the project files. There were
97 |Performance Audit Report of the Auditor-General on selected Roads
missing variation orders, IPCs, minutes of site meetings and progress reports. This
problem makes project tracking and administration difficult as information for
management decisions was not kept in a systematic way.
3.6 OVERALL CONCLUSION
220. Following our review of the selected projects information, we are of the
opinion that projects planning need to be improved to ensure value for money.
The Survey and Design Unit of the GHA need to be supported to compile data on
the roads in the country to aid planning and review. The summary in Tables 26
shows the extent of cost and time wasted for which implementation of our
recommendation seek to address.
Table 26: Summary of project issues
Tetteh Quarshie – Madina Road Project
Contract sum GH¢ 23,558,960.95 US$ 17,414,431.78
Final cost (as at 30 June 2019) GH¢ 170,477,493.66 US$ 49,974,242.82
Projected completion time 30 months
Final completion time 147 months
Core Samples taken 10
Number passed 8
Variations (works related to
project)
GH¢ 23,654,047.83 USD 13,430,608.5
Variations (unrelated works) GH¢ 11,621,897.39 US$ 6,169,625.91
Fluctuations GH¢ 61,891,295.69 USD 5,240,469.41
Total interest on delayed
payment (Part of final contract
Sum)
GH¢ 18,998,533.10 US$ 560,842.11
Payment for extension of time GHC 32,605,057.14 US$ 7,575,794.56
Ayamfuri – New Obuase Road Project
Contract sum GH¢ 13,708,256.55 US$ 20,801,250.75.
Final cost (as at 30 June 2019) GH¢ 35,384,433.54 US$ 26,054,962.91
Projected completion time 24 months
Final completion time 64 months
Core Samples taken 20
Number passed 8
98 |Performance Audit Report of the Auditor-General on selected Roads
Variations (Total V.O.s
approved)
GH¢ 22,573,895.05 US$ 10,543,792.05
Work unrelated to contract Not applicable
Total interest on delayed
payment (Part of final contract
Sum)
GH¢ 859,380.24 US$ 79,024.10
Payment for extension of time Not applicable
Bolagatanga-Bawku-Polimakom Road Project
Contract sum GH¢ 612,743,844.64
Final cost (as at 31 July 2019) (214,539,010.71) Project not completed ongoing at
the time of the audit
Projected completion time 30 months
Final completion time Project Not yet completed
Core Samples taken None
Number passed Not applicable
Work unrelated to contract Not applicable
Total interest on delayed
payment(Part of final contract
Sum)
GH¢ 38,189,353.65 (cumulative and outstanding as
at 31/7/2019)
Payment for extension of time None
Source: Extracts from Audit findings
221. GHA’s strategic goal of cost effective road development in the country in
our opinion cannot be realised if delayed payment on certificates are not managed
to reduce interest which constitutes a significant portion of the final contract sums.
99 |Performance Audit Report of the Auditor-General on selected Roads
CHAPTER FOUR
Appendixes, Analysis Sheets & Some Supporting Document
Appendix 1. List of Documents reviewed
Contract Documents
Project Drawings
Correspondence
Monthly Progress reports
Minutes of site meetings
Interim payment certificates
2018 Annual Progress Report
2017 to 2037 Strategic Plan
Variation Orders
Ministry of Transportation Standard Specifications for road and bridge works (2007)
100 |Performance Audit Report of the Auditor-General on selected Roads
Appendix 2. List of interviewees
Acting Chief Executive
Deputy Chief Executive
o Development
o Administration
Directors
o Planning
o Survey and Design
o Quantity Surveying
o Contracts
o Materials
o Estate
Resident Engineers
o Tetteh Quarshie-Madina Road Project
o Ayamfuri-New Obuase Road Project
Other staff of GHA
Ministry of Roads and Highways
o Director (Finance)
o Deputy Director (Finance)
Road Fund Secretariat
o Coordinator
Ministry of Finance
Consultants
o Delin Consult
101 |Performance Audit Report of the Auditor-General on selected Roads
Chief Resident Engineer
Contractors’ Representatives
o Messrs Sonitra
Project Managers for
East Legon – Spintex Road Tunnel
Tetteh Quarshie - Madina Road Project
102 |Performance Audit Report of the Auditor-General on selected Roads
Appendix 3. Field inspection and methodology
CARRIAGEWAY
To ascertain existence of the road project and the status of completion
o Traverse the length of the road, ascertain start and finish point and
note the distance with the vehicle trip counter,
o note any defects on the surface of the road from start to finish and
record the locations and nature of defects.
o Observe the road safety features and measures instituted and
comment on their suitability or otherwise.
o Observe road signs and their location and comment on the quality
and adequacy.
o Observe any potential risk areas along the road that might be
susceptible to accidents.
Take measurements of the length, width and shoulders of the road with the
pedometer and compare with specifications and payments made.
Measurements were taken at intervals of 250m,500m, 1km, 2.5km and 5km
depending on the length of the road.
Inspect and count the number and types of culverts constructed and
compare with what was to be provided and paid for
o Determine culvert locations from project drawings and observe the
condition of the culvert with regards to whether the workmanship
was without defects, the culvert is performing its function and is not
silted
o Take measurements of dimensions (length, width, depth of the
culvert and compare with drawings (as-built)
o Take readings of strength of culverts and concrete drains with the
Schmidt hammer to compare with the strength required
o Changes in the road design implemented during construction.
103 |Performance Audit Report of the Auditor-General on selected Roads
CONCRETE TESTS
The Schmidt Hammer was used to test the strength of concrete structures. Nine
rebound values were taken at specific intervals of at least 5cm apart. Three
readings were taken for three rows of tests. The rebound values were recorded
on a data sheet.
The highest and lowest rebound readings were omitted and the average taken
of the remaining seven readings. The average value obtained was determined
from the rebound hammer strength computation graph. The average value
was read on the horizontal axis and the corresponding reading on the vertical
axis corresponded to the measured strength of the concrete component. The
measured strength obtained was compared with the strength specification to
determine whether it met the specification or not.
The Schmidt hammer tests were done on the internal walls of drains. For
culverts the headwall, wingwall and barrel.
ASPHALT
For the asphalt works, the audit team cored the road at intervals to collect
asphalt core samples. The core samples were taken at the centres, LHS and
RHS edges of the roads at intervals to obtain a minimum representative
sample in accordance with ASTM D979 and ASTM D5361.
The thicknesses of the asphalt cores were measured with a Vernier calliper
and recorded on the data collection sheet and compared with the specified
pavement thickness to observe any difference from the designed thickness.
The core samples were carefully stored in a containment box and taken to a
materials laboratory (GHA) to conduct tests to ascertain whether it met
specifications.
The laboratory test results were compared with the results of tests carried out
during construction.
The team cored the edges of the road to obtain samples of the pavement
thicknesses for the base and sub-base. The thickness of the cored base course
and sub-base sample were measured with a ruler and recorded on the data
recording sheet. The measurements were compared with the specified layer
thickness for the binder and wearing course.
104 |Performance Audit Report of the Auditor-General on selected Roads
Appendix 4. Laboratory test results of asphalt core samples
Grading curves for the Tetteh Quarshie Madina Road Project
Table 27: Grading curves for the Tetteh Quarhsie Madina Road Project (Wearing Course)
Source: Laboratory test results on extracted asphalt core samples dated 27 July 2009.
105 |Performance Audit Report of the Auditor-General on selected Roads
Table 28: Grading curves for the Tetteh Quarhsie Madina Road Project (Binder Course)
Source: Laboratory test results on extracted asphalt core samples dated 27 July 2009.
106 |Performance Audit Report of the Auditor-General on selected Roads
Table 29 Grading curves for the Ayamfuri-New Obuase Road Project (Wearing Course)
107 |Performance Audit Report of the Auditor-General on selected Roads
Source: Laboratory test results on extracted asphalt core samples dated 27 July 2009.
Table 30: Grading curves for the Ayamfuri-New Obuase Road Project (Binder Course)
Source: Laboratory test results on extracted asphalt core samples dated 27 July 2009
108 |Performance Audit Report of the Auditor-General on selected Roads
Appendix 5 Key players and their roles
Ministry of Road and Highways (MRH)
The Ministry of Roads and Highways (MRH) is responsible for formulating
policies for the road transport sector, establishing the regulatory framework for
road transport operations, investments and the development of an integrated road
transport system.
The Ministry of Roads and Highways (MRH) is the Employer or the Project Owner
and is represented by the Ghana Highway Authority acting for and on behalf of
the Government of Ghana. The responsibility of the ministry as employer is to pay
for projects being undertaken. MRH receives monthly progress report from GHA
on road projects and reports to Cabinet. The Ministry also approves IPCs before
they are submitted to MoFEP for payment.
Ministry of Finance and Economic Planning (MOFEP)
The Ministry of Finance and Economic Planning (MOFEP) provides the budget
for road projects. MOFEP also disburses funds to settle compensation of property
owners affected by the road construction and Interim Payment Certificates (IPCs)
submitted by GHA on behalf of contractors.
Ghana Highway Authority
The Ghana Highway Authority is under the Ministry of Roads and Highways and
is responsible for planning, developing and administering road projects.
The Chief Executive (CEO)
The CEO is the head of GHA and appoints the Resident Engineer. The CEO
approves changes suggested by the Resident Engineer. The CEO approves
subcontracting of any parts of the works, variation orders, and issues taking over
certificates. The CEO also reports on the status of road projects to the Ministry of
Roads and Highways.
The Development Department of GHA
The Deputy Chief Executive heads this department comprising Planning,
Contracts, Materials, Quantity Surveying, Bridges and Survey and Design
Divisions. The Planning Division conducts feasibility studies, identifies right of
109 |Performance Audit Report of the Auditor-General on selected Roads
way and buildings for demolition to make way for the road as well as assessing
properties for payment of compensation.
The Contracts Division prepares tender documents. The division also handles
tendering and tender evaluation, construction planning (including relocation of
utilities and compensation of affected properties) and reviewing IPCs.
The Materials Division is responsible for engineering studies and material
investigations. The division also prospects for materials for construction.
The Quantity Surveying Division is involved in the preparation of preliminary
cost estimates for projects. They also assist in the preparation of contract
documents and the verification of quantities on IPCs.
The Bridges Division is responsible for identifying locations and designing
bridges to be constructed.
The Survey and Design Division is responsible for gathering site information
through various surveys, designing the road to be constructed and preparing
engineering drawings for construction.
The Resident Engineer
The Resident Engineer receives contractor’s queries, issues instructions to the
contractor, ensures the contractor follows good practices and approves work done
by the contractor. The Resident Engineer also monitors progress of works and
gives the GHA Chief Executive regular reports on the project through a Monthly
Progress Report. He chairs monthly site meetings to discuss progress of work.
The Contractor
The Contractor is to execute the contract according to the drawings and
specifications. They maintain the project site, receive instructions from the
Resident Engineer and carries them out. They use sub-contractors and suppliers
of goods and services to carry out some aspects of the contract and apply
periodically for payment of work done. They conduct tests on materials and
components, and forward test results to the Resident Engineer for approval.
110 |Performance Audit Report of the Auditor-General on selected Roads
Appendix 6. Details of system description
Figure 4: System Description
Source: GAS Performance Audit Infrastructure Guide
111 |Performance Audit Report of the Auditor-General on selected Roads
Appendix 7. Details of Variation Orders on Tetteh Quarshie Madina Road
Project
Table 31 : Variation orders granted on the Tetteh Quarshie-Madina road project
Va
ria
tio
n
Ord
er N
o.
Brief Description
Value of Variations
%
of
Co
ntr
act
Su
m
Local (GHȼ) Foreign (US$)
1 ER’s Facilities 48,700.10 (52,891.26) 0.00
2 Some general items, site allowance, Ammonia printer cartridge & adjustment
52,465.19 - 0.13
2A Urban roads (Relocation) (412.88)
0.00
3 Relocation of damaged Telecom Plants along Tetteh Quarshie-Madina Road (Okponglo)
24,137.85 - 0.06
4 Construction of Fence walls for Ghana Standards Board and Gulf House
122,886.07
0.31
5 ER’s Facilities 59,846.31
0.15
6 Advance payment to the Subcontractor (Energy Ventures GH. Ltd) for the supply and installation of 33kV tower overhead line along Tetteh Quarshie to Madina
183,000.00 - 0.46
7 Relocation in front of Emmanuel Eye Clinic – Subcontractor M/S Zigma Engineering Company Ltd
7,045.00
0.02
8 Relocation of Medium Voltage Pylons 89,707.82
0.23
9 Part Compensation payment for buildings/structures and crops affected by the project
68,681.28 - 0.17
10 Settlement of bill for relocation of underground cable near sub-station opposite Total Filling Station
4,310.26
0.01
11 Emergency Works to Improve Traffic Flow on Spintex Road 4,371,386.29
11.04
12 Rent for residential accommodation 4,392.00
0.01
13 Construction of Kasoa Toll Plaza 600,613.87 434,838.25 2.53
14 Atomic and Legon Interchange 10,155,162.53 7,495,466.19 66.34
15 Office Laptops and Car Maintenance 6,176.28
0.02
16 ER’s Facilities & Site allowance 184,170.59
0.47
17 General Item Part 1- Extension of Time 3,076,051.89 2,227,108.88 12.95
19 Survey Accessories 5,732.66
0.01
20 Variation to emergency works to improve traffic flow on Spintex road and the community 18 Abattoir road (Dept. of Urban Roads
6,649,897.23 5,734,787.66 30.13
21 Equipment in FDN Lab. GHA Entral Lab ElWalk - 12,648.91 0.03
22 Relocation of 265mm HPDE PN 10 (UG). 54,839.61
0.14
23 Relocation of Vodafone plant at Atomic Junction 63,194.05 - 0.16
24 Final Compensation Payment for buildings/structures affected by the project
308,607.55
0.78
25 Street Light & Traffic Lights), General Item For Extended Contract Period To May 2013, ER's Facilities To May 2013
5,150,793.90 338,787.87 13.80
112 |Performance Audit Report of the Auditor-General on selected Roads
VARIATION ORDER No.11 (27/03/2009) (Emergency Works to Improve Traffic Flow on Spintex Road)
Description Estimated Omissions (GHȼ) Estimated Additions (GHȼ)
Emergency Works to Improve Traffic Flow on Spintex Road
4,371,386.29
Estimated Net Addition 4,371,386.29
Item Description Total Cedi Equivalent GHȼ
1
ACCRA SHOPPING MALL Create an exclusive exit lane from the mall that will join the Spintex road
22,482.25
2 Additional lane on the SE loop onto the liberation road 34,931.91
3 2No. Lay byes to be created on the SE loop with a separator and a well-defined
17,635.95
4 Create a walkway on the SE loop by slabbing the open drain and raising it by
31,687.78
5 Create additional exit lane from Spintex roundabout onto Motorway
64,598.15
6
TETTEH QUARSHIE ROUNDABOUT-MADINA ROAD An additional lane to be added to the North-West loop on the interchange by asphalting
40,306.05
7
SPINTEX UNDERPASS Extend existing 2No 1.5 m pipe culverts on the Spintex road by 6 m on either side
9,648.65
8 Undertake widening of Spintex road/underpass junction to accommodate left turn
49,599.17
9
Widen Baatsona Junction and signalize Add the following Provsional items
Provide an additional box culvert under the motorway to segregate movement and reduce
174,357.11
650,000.00
10 Signalized the Junction and link with Boundary Road 60,000.00
11
Spintex Road (New Alignment) Re-program signal timings at Linkb/liberation road and Woolworth Pelican crossings
2,000.00
12
Community 18 and its environs Develop a right-out slip from the Motorway (near abbatoir) unto the community 18 road
678,576.80
13 Develop a righ-in slip onto the Motorway (near the abbatoir) from the community 18 Road
555,199.23
14 University of Ghana 207,588.67
Sub-Total (A) 2,598,612.71
Specified Provisional sums (B)
Total of Bill less specified provisional sums (A-B) = (C)
Add: Contingency (D) {Physical: 10% of (C) **{Price 60% of (C) “ 259,861.27 1,559,167.62
Grand total (A+D) 4,417,641.60
Adjustment allowance, Add/Subtract (1.78% of 2,598,612.71) 46,255.31
Total to form of bid 4,371,386.29
Note ** Fluctuation on the project currently stand @ 1.6
113 |Performance Audit Report of the Auditor-General on selected Roads
Variation Order No.20 Variation to emergency works to improve traffic flow on Spintex road and the community 18 & Abattoir road (Dept. of Urban roads)
Brief description Estimated Omissions Estimated Additions
Local Cedis US Dollars Local Cedis US Dollars
Omissions A. Emergency works to improve traffic flow on Spintex road (V.O.1)
23,423,108,282.67
141,118.50
Additions B. General items for emergency works
C. Community 18 bridge
D. A right-out slip from motorway unto COM. 18 bridge & right-in slip unto motorway from COM. 18 bridge
E. Variation to improve abattoir road to steel bridge
F. Variation to improve community 18 road (Asphalt overlay)
G. Variation to improve atomic junction to Rawlings Circle road (Asphalt overlay)
H. Variation to shopping mall, loops, Spintex
I. Method Related charges (18.34%)
Sub-Total Less
9,087,690,696.00
11,996,410,923.76
15,079,219,402.00
7,211,275,015.00
10,685,591,853.00
3,152,637,040.00
20,181,769,465.33
12,527,486,138.41
890,679.92
1,094,680.24
521,627,37
772,594.11
225,382.00
1,460,311.13
910,631.39
89,922,080,533.50
23,423,108,282.67
5,875,906.16
141,118.50
Estimated Net Additions 66,498,972,250.83 5,734,787.66
114 |Performance Audit Report of the Auditor-General on selected Roads
Appendix 8. Table of road widths, core thickness as measured on site and tests
on concrete structures
Tetteh Quarshie – Madina Road Project
Table 32: Measured thicknesses of core samples from the Tetteh Quarshie Madina Road
Core Sample No. Chainage Thickness of Core, mm
1 0 + 100 R 120
2 1 + 600 R 125
3 2 + 600 R 97
4 3 + 100 R 130
5 4 + 350 R 85
6 4 + 350 L 104
7 3 + 000 L 105
8 2 + 500 L 115
9 1 + 000 L 110
10 0 + 500 L 110
Source: Audit team field inspection results
Table 33: Summary Statistics on core samples from the Tetteh Quarshie Madina Road
Specified combined thicknesses of wearing and binder courses 100 mm
Criteria Count
>=100 8
<100 2
Total number of samples 10
Average thickness of asphalt core samples 110.1 mm
Maximum thickness of asphalt core samples 130 mm
Minimum thickness of asphalt core samples 85 mm
Source: Audit team field inspection results
115 |Performance Audit Report of the Auditor-General on selected Roads
Table 34: Stratified Random Sampling on the Tetteh Quarshie Madina Road Project
km LHS RHS
4.5 1 2 3 4 5 6 7 8
4 48 47 46 45 44 43 91 92 93 94 95 96
3.5 37 38 39 40 41 42 90 89 88 87 86 85
3 36 35 34 33 32 31 79 80 81 82 83 84
2.5 25 26 27 28 29 30 78 77 76 75 74 73
2 24 23 22 21 20 19 67 68 69 70 71 72
1.5 13 14 15 16 17 18 66 65 64 63 62 61
1 12 11 10 9 8 7 55 56 57 58 59 60
0.5 1 2 3 4 5 6 49 50 51 52 53 54
0
Source: Audit team worksheet
116 |Performance Audit Report of the Auditor-General on selected Roads
Ayamfuri New Obuase Road Project
Table 35: Measured thicknesses of core samples from the Ayamfuri New Obuase Road
Lot 1
Sample Chainage (km)
Thickness of Core, mm
Width of shoulder LHS, m
Width of shoulder RHS, m
Width of Road, m
1 1 + 300 118 2.65 2.80 7.20
2 2 + 600 85 2.66 2.95 6.79
20 3 + 900 120 2.53 3.17 7.20
19 5 + 200 74 2.55 2.55 7.05
3 6 + 500 98 2.60 2.45 7.20
18 7 + 800 85 2.60 2.80 6.90
4 9 + 100 80 2.65 2.62 7.18
5 10 + 400 96 2.50 2.87 7.08
17 11 + 700 100 2.50 2.82 7.18
16 13 + 00 109 2.28 2.71 7.21
6 14 + 300 85 2.60 3.00 6.90
7 15 + 600 85 2.75 2.68 7.27
15 16 + 900 100 2.69 2.71 7.00
8 18 + 200 118 2.84 2.62 7.14
14 19 + 500 80 2.71 2.91 6.93
13 20 + 800 55 3.23 2.57 6.95
9 22 + 100 123 2.73 2.68 7.09
10 23 + 400 85 2.84 2.60 7.16
12 24 + 700 98 2.90 3.00 6.70
11 26 + 00 105 2.82 2.93 6.95
Source: Audit team field inspection results
Table 36: Summary Statistics on core samples from the Ayamfuri New Obuase Road
Specified combined thicknesses of wearing and binder courses 100 mm
Criteria Count
>=100 8
<100 12
Total number of samples 20
Average thickness of asphalt core samples 95 mm
Maximum thickness of asphalt core samples 123 mm
Minimum thickness of asphalt core samples 55 mm
Source: Audit team field inspection results
117
|P
erf
orm
an
ce A
ud
it R
ep
ort
of
the
Au
dit
or-
Ge
ne
ral
on
se
lect
ed
Ro
ad
s
Tab
le 3
7: N
on
-Des
tru
ctiv
e S
chm
idt
Ham
mer
Tes
t R
esu
lt S
hee
t fo
r so
me
con
cret
e st
ruct
ure
s o
n t
he
Ay
amfu
ri N
ew O
bu
ase
Ro
ad L
ot
1
GH
AN
A A
UD
IT S
ER
VIC
E T
EC
HN
ICA
L A
UD
IT F
IEL
D C
HE
CK
LIS
T
NO
N-D
ES
TR
UC
TIV
E S
CH
MID
T H
AM
ME
R T
ES
T R
ES
UL
T S
HE
ET
▲
TE
ST
ED
B
Y:
DA
TE
: 15
/04
/20
19
TIT
LE
:
TE
CH
NIC
AL
AU
DIT
OF
SE
LE
CT
ED
RO
AD
S I
N G
HA
NA
▼
NA
ME
OF
P
RO
JEC
T:
R
EH
AB
ILIT
AT
ION
OF
TH
E A
YA
MF
UR
I-N
EW
OB
UA
SE
RO
AD
LO
T 1
A
YA
MF
UR
I-N
EW
OB
UA
SE
RO
AD
Lo
t 1
LO
CA
TIO
N
OF
S
TR
UC
TU
RE
SC
HM
IDT
HA
MM
ER
TE
ST
RE
AD
ING
S
(NB
: im
pac
t p
oin
ts s
ho
uld
be a
t le
ast
20 m
m
ap
art
)
AD
JUS
TE
D
AV
ER
AG
E
RE
AD
ING
TE
ST
A
NG
LE
(0
˚/90˚
/270˚
)
PR
OB
AB
LE
S
TR
EN
GT
H
(N/m
m2)
SP
EC
IFIE
D
ST
RE
NG
TH
(N
/mm
2)
RE
MA
RK
S
1
2
3
4
5
6
7
8
9
Tra
pe
zo
idal
d
rain
R
emar
ks
Ch
2 +
600
L
HS
33
24
32
23
31
29
28
27
33
29
.000
0°
26
25
P
AS
SE
D
Ch
2 +
600
R
HS
16
13
16
22
23
27
22
23
14
19
.000
0°
#
N/
A
25
#N
/A
Pip
e C
ulv
ert
W
ing
wall
Ch
19
+ 5
00
LH
S
38
38
37
40
34
34
37
41
30
37.0
00
0°
38
25
PA
SS
ED
Pip
e C
ulv
ert
H
ea
d w
all
Ch
19
+ 5
00
LH
S
43
41
43
40
41
42
36
44
40
41.0
00
90°
48
25
PA
SS
ED
Sou
rce:
Au
dit
team
fie
ld i
nsp
ecti
on r
esu
lts
118
|P
erf
orm
an
ce A
ud
it R
ep
ort
of
the
Au
dit
or-
Ge
ne
ral
on
se
lect
ed
Ro
ad
s
Ta
ble
38:
Str
ati
fied
Ra
nd
om
Sa
mp
lin
g o
n t
he
Ay
am
furi
New
Ob
ua
se R
oa
d
A
yam
furi
New
Ob
uase
26 k
m -
1.3
km
in
terv
al
km
L
HS
R
HS
26
80
79
78
77
Fro
m 0
to
26
24.7
73
74
75
76
Fro
m26
to
0
23.4
72
71
70
69
22.1
65
66
67
68
20.8
64
63
62
61
19.5
57
58
59
60
18.2
56
55
54
53
16.9
49
50
51
52
15.6
48
47
46
45
14.3
41
42
43
44
13
40
39
38
37
11.7
33
34
35
36
10.4
32
31
30
29
9.1
25
26
27
28
7.8
24
23
22
21
6.5
17
18
19
20
5.2
16
15
14
13
3.9
9
10
11
12
2.6
8
7
6
5
1.3
1
2
3
4
0
S
ourc
e: A
udi
t te
am w
orks
heet
119
|P
erf
orm
an
ce A
ud
it R
ep
ort
of
the
Au
dit
or-
Ge
ne
ral
on
se
lect
ed
Ro
ad
s
Bo
lgata
ng
a -
Baw
ku
-Po
lim
ak
om
Ro
ad
Pro
ject
T
able
39:
No
n-d
estr
uct
ive
Sch
mid
t h
amm
er t
est
resu
lt s
hee
t fo
r so
me
con
cret
e st
ruct
ure
s fo
r th
e B
olg
atan
ga
-Baw
ku
-Po
lim
ako
m R
oad
Pro
ject
GH
AN
A A
UD
IT S
ER
VIC
E T
EC
HN
ICA
L A
UD
IT F
IEL
D C
HE
CK
LIS
T
NO
N-D
ES
TR
UC
TIV
E S
CH
MID
T H
AM
ME
R T
ES
T R
ES
UL
T S
HE
ET
▲
TE
ST
ED
BY
:
DA
TE
:
TIT
LE
: T
EC
HN
ICA
L A
UD
IT O
F S
EL
EC
TE
D R
OA
DS
IN
GH
AN
A
▼
NA
ME
OF
PR
OJE
CT
: B
olg
ata
ng
a B
awk
u P
oli
mak
om
ro
ad
LO
CA
TIO
N
OF
S
TR
UC
TU
RE
SC
HM
IDT
HA
MM
ER
TE
ST
RE
AD
ING
S
(NB
: im
pac
t p
oin
ts s
ho
uld
be a
t le
ast
20 m
m
ap
art
)
AD
JUS
TE
D
AV
ER
AG
E
RE
AD
ING
TE
ST
A
NG
LE
(0
˚/90˚
/27
0˚)
PR
OB
AB
LE
S
TR
EN
GT
H
(N/m
m2)
SP
EC
IFIE
D
ST
RE
NG
TH
(N
/mm
2)
RE
MA
RK
S
1
2
3
4
5
6
7
8
9
Lo
t 6
Pip
e C
ulv
ert
33 +
052
(H
ead
wal
l)
39
33
41
33
32
35
45
38
39
37.0
00
0°
38
25
PA
SS
ED
34 +
844
(W
ing
wal
l)
32
34
34
33
34
40
33
33
35
34.0
00
0°
34
25
PA
SS
ED
Lo
t 10
U-D
rain
62 +
260
35
33
34
38
34
35
32
35
32
34
.000
0°
34
25
P
AS
SE
D
Rin
g C
ulv
ert
(H
ead
wal
l)
74 +
132
30
35
36
30
37
36
34
36
32
34
.000
0°
34
25
P
AS
SE
D
Sou
rce:
Au
dit
team
fie
ld i
nsp
ecti
on r
esu
lts
120
|P
erf
orm
an
ce A
ud
it R
ep
ort
of
the
Au
dit
or-
Ge
ne
ral
on
se
lect
ed
Ro
ad
s
Ap
pen
dix
9.
Pa
ym
en
t D
eta
ils
Pa
ym
en
t d
eta
ils
for
Te
tte
h Q
ua
rsh
ie-M
ad
ina
Ro
ad
Pro
ject
Ta
ble
40:
Pa
ym
ent
det
ail
s fo
r T
ette
h Q
ua
rsh
ie-M
ad
ina
Ro
ad
Pro
ject
IPC
N
O
Co
ntr
act
or'
s S
UB
MIS
SIO
N
DA
TE
IPC
C
ER
TIF
IED
D
AT
E
IP
C A
MT
¢
IP
C A
MT
$
A
MT
PA
ID ¢
A
MT
PA
ID $
D
ue
Da
te
D
ela
ys
¢
D
ela
ys
$
1
3
-No
v-0
6 8
,85
2,4
32.8
8
8
,85
2,4
32.
88
N
/A
N
/A
2
30
-Ma
r-0
7 3
0-M
ar-
07
64
9,8
48
.54
4
58,8
76.3
5
6
32
,45
0.6
9
453
,686
.69
2
5-M
ay
-07
10
1 N
/A
3
19
-Ju
l-07
1
9-J
ul-
07
1,7
61,
217
.11
1
,200
,053
.89
1
,76
2,7
02.
89
1,1
93,5
37.4
6
13
-Sep
-07
14
0 1
46
4
21
-Sep
-07
2-O
ct-0
7 9
35
,04
4.1
3
608
,496
.59
92
0,0
76.
52
5
97,5
81.4
6
16
-No
v-0
7 7
6 8
2
5
16
-No
v-0
7 2
1-N
ov
-07
67
8,4
64
.86
4
63,8
40.0
0
6
54
,63
6.8
1
442
,949
.82
1
1-J
an
-08
12
5 1
43
5A
2
7-N
ov
-07
27
-No
v-0
7
32,
163
.01
10,0
22.9
2
32
,16
3.0
1
1
0,0
22.9
2
22
-Ja
n-0
8 2
39
23
9
6
22
-Ja
n-0
8 2
8-J
an
-08
79
8,3
29.8
6
487
,855
.79
77
3,9
07.
39
4
87,4
74.7
4
18
-Ma
r-0
8 1
83
19
9
7
20
-Feb
-08
4-M
ar-
08
63
3,9
68.7
8
409
,011
.30
65
2,1
08.
21
4
32,2
04.3
8
16
-Ap
r-0
8 1
54
17
0
7A
1
2-M
ar-
08
12
-Ma
r-0
8
1
34,
171
.00
34,6
78.0
0
1
32
,61
3.7
7
3
4,2
98.1
3
7-M
ay
-08
17
6 1
82
8
18
-Ma
r-0
8 3
1-M
ar-
08
85
0,0
40.4
6
863
,862
.26
45
0,9
91.
20
4
13,3
22.6
9
13
-Ma
y-0
8 1
70
17
6
9
17
-Ap
r-0
8 2
4-A
pr-
08
71
2,5
38.8
4
436
,263
.81
38
3,2
07.
78
4
56,9
27.5
7
12
-Ju
n-0
8 1
40
14
6
10
19
-Ma
y-0
8 2
2-M
ay
-08
1
,03
1,2
71.1
0
442
,234
.52
65
4,3
05.
18
4
40,2
65.8
1
14
-Ju
l-08
1
08
11
4
10
A
4-J
un
-08
4-J
un
-08
3
6,8
03.2
1
6
,240
.78
3
6,8
03.
21
6
,240
.78
3
0-J
ul-
08
92
98
11
13
-Ju
n-0
8 1
9-J
un
-08
91
8,1
62.1
2
496
,329
.15
55
7,0
63.
81
5
01,4
01.6
8
8-A
ug
-08
83
89
12
17
-Ju
l-08
2
1-J
ul-
08
1
,41
8,4
41.4
0
923
,464
.53
73
7,4
99.
74
9
23,8
72.1
6
11
-Sep
-08
95
96
13
18
-Au
g-0
8 1
9-A
ug
-08
1
,23
6,0
13.4
5
449
,951
.42
84
6,6
51.
99
4
45,3
63.0
1
13
-Oct
-08
57
64
14
25
-Sep
-08
28
-Sep
-08
1
,44
5,7
93.9
4
895
,519
.70
87
0,0
91.
58
8
77,2
34.2
8
20
-No
v-0
8 1
11
11
1
15
21
-Oct
-08
30
-Oct
-08
82
8,1
45.0
4
444
,391
.22
50
1,2
98.
12
4
17,6
69.4
5
16
-Dec
-08
19
2 1
98
16
18
-No
v-0
8 2
4-N
ov
-08
99
8,0
50.9
8
381
,783
.45
75
8,3
44.
35
3
81,8
83.4
2
13
-Ja
n-0
9 1
64
17
0
16
A
16
-Dec
-08
16
-Dec
-08
24
9,2
40.0
0
43
,431
.00
24
5,6
07.
42
43
,209
.84
1
0-F
eb-0
9 N
/A
N
/A
121
|P
erf
orm
an
ce A
ud
it R
ep
ort
of
the
Au
dit
or-
Ge
ne
ral
on
se
lect
ed
Ro
ad
s
IPC
N
O
Co
ntr
act
or'
s S
UB
MIS
SIO
N
DA
TE
IPC
C
ER
TIF
IED
D
AT
E
IP
C A
MT
¢
IP
C A
MT
$
A
MT
PA
ID ¢
A
MT
PA
ID $
D
ue
Da
te
D
ela
ys
¢
D
ela
ys
$
17
18
-Dec
-08
5-J
an
-09
91
8,4
91.0
0
765
,409
.14
54
0,1
24.
91
5
32,7
18.7
2
12
-Feb
-09
22
1 1
95
18
16
-Feb
-09
19
-Feb
-09
1
,17
2,0
09.5
4
618
,941
.47
67
9,8
85.
55
6
18,5
33.7
4
13
-Ap
r-0
9 1
61
13
5
19
17
-Ma
r-0
9 2
0-M
ar-
09
69
5,6
00.1
8
866
,390
.17
47
2,9
46.
53
3
34,3
70.9
0
12
-Ma
y-0
9 2
55
25
5
19
A
15
-Ap
r-0
9 1
5-A
pr-
09
11
4,3
99.0
0
15
,681
.00
11
3,0
99.
14
15
,538
.45
1
0-J
un
-09
22
6 2
26
20
19
-Ma
y-0
9 1
-Ju
n-0
9
3,2
84,
631
.17
23,1
70.7
3
2,3
69
,30
0.5
9
2
3,1
71.3
5
14
-Ju
l-09
1
92
19
2
21
6-A
ug
-09
12
-Au
g-0
9
4,1
67,
255
.27
1
,268
,357
.30
3
,27
4,9
73.
22
1,2
69,2
83.8
8
1-O
ct-0
9 1
13
11
3
22
24
-Au
g-0
9 1
-Sep
-09
3
,12
7,7
08.4
3
444
,371
.30
1
,90
7,4
67.
57
7
51,1
63.5
6
19
-Oct
-09
95
95
23
3-S
ep-0
9 1
5-S
ep-0
9
1,3
40,
892
.21
6
80,0
35.1
3
7
06
,20
0.9
2
510
,521
.54
2
9-O
ct-0
9 8
5 8
5
23
A
11
-Au
g-0
9 1
6-S
ep-0
9
2
36,
266
.00
18,1
85.0
0
2
35
,98
4.4
6
1
7,9
61.7
7
6-O
ct-0
9 N
/A
N
/A
24
22
-Oct
-09
22
-Oct
-09
1
,19
2,9
77.0
0
595
,451
.00
40
1,5
28.
20
6
38,1
69.1
1
17
-Dec
-09
N/
A
N/
A
25
19
-No
v-0
9 1
9-N
ov
-09
65
6,5
54.4
7
388
,615
.00
47
1,0
18.
63
3
88,6
16.0
9
14
-Ja
n-1
0 N
/A
N
/A
25
A
30
-No
v-0
9 3
0-N
ov
-09
3
9,3
58.7
1
1
,770
.83
3
9,3
58.
71
1
,770
.83
2
5-J
an
-10
40
1 4
10
26
19
-Ja
n-1
0 2
1-J
an
-10
89
4,2
05.9
2
565
,103
.00
50
8,0
44.
80
5
61,4
39.6
3
16
-Ma
r-1
0 3
51
36
0
27
16
-Ma
r-1
0 1
9-M
ar-
10
1
,19
6,5
46.7
1
812
,146
.00
84
8,0
63.
22
7
29,6
21.3
3
11
-Ma
y-1
0 2
95
30
4
27
A
25
-Feb
-10
20
-Ap
r-1
0
6
01,
728
.00
8,9
91.0
0
5
97
,63
5.7
1
8,9
05.5
6
22
-Ap
r-1
0 3
14
32
3
28
19
-Ma
r-1
0 2
2-A
pr-
10
87
8,9
41.7
8
559
,767
.86
79
5,5
50.
99
5
42,3
38.0
7
14
-Ma
y-1
0 2
92
30
1
29
7-M
ay
-10
7-M
ay
-10
72
0,2
12.7
2
397
,300
.44
77
9,7
20.
29
4
12,0
71.9
2
2-J
ul-
10
24
3 2
52
30
7-J
un
-10
10
-Ju
n-1
0
1,1
03,
271
.00
6
00,8
82.9
9
1,1
31
,38
8.4
7
605
,537
.92
2
-Au
g-1
0 3
80
38
5
31
10
-Au
g-1
0 1
2-A
ug
-10
1
,42
5,1
10.6
9
677
,704
.00
1
,27
0,8
72.
92
6
55,5
01.2
1
5-O
ct-1
0 3
16
32
1
32
13
-Sep
-10
16
-Sep
-10
1
,08
0,3
99.2
2
578
,460
.00
97
8,4
39.
52
6
05,5
36.3
6
8-N
ov
-10
28
2 2
87
33
14
-Oct
-10
20
-Oct
-10
81
7,3
31.9
9
305
,401
.82
81
7,3
31.
98
3
05,4
02.2
8
9-D
ec-1
0 2
92
30
1
34
8-N
ov
-10
11
-Dec
-10
82
9,9
66.8
1
455
,306
.00
82
9,9
66.
81
4
55,3
06.4
3
3-J
an
-11
26
7 2
76
35
16
-Dec
-10
23
-Dec
-10
80
6,4
78.5
0
472
,270
.00
80
6,4
78.
50
4
72,2
70.1
8
10
-Feb
-11
22
9 2
38
36
22
-Feb
-11
22
-Feb
-11
72
2,2
49.7
3
421
,015
.00
71
5,7
59.
68
4
19,8
09.8
7
19
-Ap
r-1
1 1
61
17
0
36
A
20
-Ap
r-1
1 2
1-A
pr-
11
46
2,7
04.0
0
25
,292
.00
46
1,0
99.
77
25
,205
.98
1
5-J
un
-11
10
4 1
13
37
27
-Ap
r-1
1 2
7-A
pr-
11
1
,00
0,9
04.3
7
492
,270
.00
90
7,3
35.
39
4
93,4
80.3
3
22
-Ju
n-1
1 9
7 1
06
122
|P
erf
orm
an
ce A
ud
it R
ep
ort
of
the
Au
dit
or-
Ge
ne
ral
on
se
lect
ed
Ro
ad
s
IPC
N
O
Co
ntr
act
or'
s S
UB
MIS
SIO
N
DA
TE
IPC
C
ER
TIF
IED
D
AT
E
IP
C A
MT
¢
IP
C A
MT
$
A
MT
PA
ID ¢
A
MT
PA
ID $
D
ue
Da
te
D
ela
ys
¢
D
ela
ys
$
38
16
-Ju
n-1
1 1
5-J
un
-11
1
,48
8,2
05.6
2
647
,875
.00
1
,67
6,8
41.
07
6
43,6
15.8
7
11
-Au
g-1
1 9
9 9
7
39
15
-Ju
l-11
2
1-J
ul-
11
1
,15
8,7
33.2
4
535
,490
.88
1
,18
5,7
21.
02
5
34,5
68.3
9
9-S
ep-1
1 1
18
12
5
40
19
-Au
g-1
1 2
3-A
ug
-11
1
,07
6,6
38.6
2
512
,946
.49
1
,09
7,4
09.
52
5
28,3
31.5
0
14
-Oct
-11
83
90
40
A
23
-Au
g-1
1 3
0-A
ug
-11
49
2,4
70.0
0
21
,858
.00
49
2,2
10.
75
21
,867
.13
1
8-O
ct-1
1 7
9 8
6
41
12
-Oct
-11
17
-Oct
-11
1
,52
4,3
27.9
6
555
,598
.00
1
,51
9,9
22.
53
5
53,8
71.4
0
7-D
ec-1
1 1
35
14
1
41
A
10
-Oct
-11
4-N
ov
-11
38
3,5
11.0
0
15
,988
.00
38
5,4
04.
20
16
,026
.31
5
-Dec
-11
13
7 1
43
42
10
-No
v-1
1 1
7-N
ov
-11
92
6,7
91.5
8
335
,821
.46
93
1,1
70.
18
3
36,0
03.5
6
5-J
an
-12
11
9 1
40
42
A
24
-No
v-1
1 2
4-N
ov
-11
6
5,9
51.0
0
2
,321
.00
6
6,1
20.
62
2
,272
.37
1
9-J
an
-12
10
5 1
26
43
9-D
ec-1
1 1
5-D
ec-1
1
1,0
74,
825
.92
4
34,7
85.0
0
1,0
01
,03
1.9
8
403
,516
.78
3
-Feb
-12
10
5 1
11
44
17
-Ja
n-1
2 2
4-J
an
-12
1
,41
5,9
01.0
0
613
,401
.00
1
,40
5,2
69.
87
6
42,7
44.9
6
13
-Ma
r-1
2 1
14
13
1
45
13
-Feb
-12
21
-Feb
-12
1
,32
6,9
98.9
0
461
,590
.00
1
,32
6,8
17.
30
4
81,4
02.1
3
9-A
pr-
12
10
9 1
22
46
14
-Ma
r-1
2 1
9-M
ar-
12
1
,71
0,9
99.0
0
649
,466
.00
1
,71
0,9
98.
72
6
01,6
57.3
2
9-M
ay
-12
79
92
47
18
-Ap
r-1
2 2
0-A
pr-
12
1
,89
2,9
11.6
6
685
,289
.00
1
,86
9,7
25.
88
6
81,5
42.1
7
13
-Ju
n-1
2 4
4 5
7
48
14
-Ma
y-1
2 1
4-M
ay
-12
1
,92
9,9
64.9
0
612
,957
.00
1
,93
0,1
30.
41
6
46,9
74.7
7
9-J
ul-
12
14
7 1
56
49
15
-Ju
n-1
2 1
9-J
un
-12
2
,08
5,6
41.2
6
713
,861
.00
2
,08
5,6
41.
27
7
13,8
60.7
9
10
-Au
g-1
2 1
18
14
0
50
16
-Ju
l-12
2
0-J
ul-
12
1
,46
7,9
17.0
0
513
,271
.00
1
,46
9,0
42.
76
5
13,6
63.2
6
10
-Sep
-12
87
10
9
50
A
1-A
ug
-12
1-A
ug
-12
35
7,7
26.0
0
11
,155
.00
31
3,7
12.
26
11
,485
.52
2
6-S
ep-1
2 N
/A
N
/A
51
16
-Au
g-1
2 2
7-A
ug
-12
3
,82
7,7
22.6
0
635
,310
.00
1
,87
5,7
22.
60
6
35,3
11.0
9
11
-Oct
-12
95
99
52
19
-Sep
-12
19
-Sep
-12
1
,98
8,3
15.0
0
696
,239
.00
1
,96
5,1
29.
37
6
92,4
92.8
0
14
-No
v-1
2 5
2 1
50
7
52
A
15
-Oct
-12
18
-Oct
-12
23
9,0
17.0
0
10
,332
.00
23
9,2
18.
07
10
,135
.45
1
0-D
ec-1
2 9
86
25
9
53
15
-Oct
-12
17
-Oct
-12
3
,39
4,7
00.5
9
695
,744
.00
3
,39
4,7
00.
59
6
95,7
43.3
5
10
-Dec
-12
98
6 2
59
54
14
-No
v-1
2 1
4-N
ov
-12
1
,17
7,3
76.0
0
398
,301
.00
1
,18
8,2
93.
35
4
02,0
50.4
5
9-J
an
-13
26
8 2
71
55
17
-Dec
-12
17
-Dec
-12
1
,39
4,3
66.0
0
459
,725
.00
1
,39
4,3
36.
14
4
59,7
24.0
5
11
-Feb
-13
69
3 1
41
8
55
A
17
-Ja
n-1
3 1
7-J
an
-13
30
9,3
49.0
0
15
,002
.00
30
7,6
47.
35
9
,649
.20
1
4-M
ar-
13
66
2 1
38
7
56
22
-Feb
-13
22
-Feb
-13
1
,67
3,6
63.0
0
566
,791
.00
1
,67
3,6
62.
82
5
66,7
90.7
0
19
-Ap
r-1
3 6
26
13
51
57
26
-Ma
r-1
3 2
6-M
ar-
13
1
,31
6,5
57.0
0
435
,481
.00
1
,31
6,5
56.
87
4
52,6
60.4
2
21
-Ma
y-1
3 5
94
13
19
123
|P
erf
orm
an
ce A
ud
it R
ep
ort
of
the
Au
dit
or-
Ge
ne
ral
on
se
lect
ed
Ro
ad
s
IPC
N
O
Co
ntr
act
or'
s S
UB
MIS
SIO
N
DA
TE
IPC
C
ER
TIF
IED
D
AT
E
IP
C A
MT
¢
IP
C A
MT
$
A
MT
PA
ID ¢
A
MT
PA
ID $
D
ue
Da
te
D
ela
ys
¢
D
ela
ys
$
58
15
-Ma
y-1
3 1
5-M
ay
-13
1
,69
2,8
60.0
0
555
,575
.00
1
,66
9,6
73.
78
5
51,8
26.5
2
10
-Ju
l-13
7
13
71
3
58
A
1-J
ul-
13
4-J
ul-
13
7
,00
3,9
55.8
8
4,0
02,5
88.8
3
7,0
03
,95
5.8
8
4
,002
,588
.83
2
6-A
ug
-13
39
42
59
16
-Ju
l-13
2
1-J
ul-
13
1
,94
9,7
17.0
0
519
,645
.00
1
,94
9,7
17.
49
5
19,6
45.0
3
10
-Sep
-13
48
2 1
20
7
60
13
-Sep
-13
18
-Sep
-13
1
,49
6,2
41.0
0
450
,194
.00
1
,48
3,6
24.
69
4
46,1
85.0
1
8-N
ov
-13
59
2 5
92
61
22
-No
v-1
3 2
2-N
ov
-13
1
,93
7,8
72.6
0
320
,828
.00
1
,75
1,3
09.
36
2
69,3
53.7
4
17
-Ja
n-1
4 7
27
73
5
61
A
9-N
ov
-13
9-D
ec-1
3
2,4
10,
139
.00
99,1
24.0
0
7
25
,97
6.9
7
1
4,9
35.9
6
4-J
an
-14
74
0 7
48
62
22
-Ja
n-1
4 2
2-J
an
-14
1
,21
2,2
41.0
0
416
,375
.00
2
,05
4,4
89.
61
3
29,7
83.6
1
19
-Ma
r-1
4 6
66
67
4
63
31
-Ma
r-1
4 3
1-M
ar-
14
1
,54
7,0
81.0
0
466
,447
.00
1
,45
7,6
72.
55
4
39,7
13.2
1
26
-Ma
y-1
4 5
98
60
6
64
16
-Ma
y-1
4 1
6-M
ay
-14
1
,29
0,5
04.0
0
324
,562
.00
1
,29
0,5
04.
21
3
24,5
61.8
8
11
-Ju
l-14
5
52
56
0
64
A
19
-Ma
y-1
4 1
9-M
ay
-14
8
3,5
18.0
0
2
,132
.00
8
2,7
82.
46
2
,198
.92
1
4-J
ul-
14
54
9 5
57
65
23
-Ju
l-14
2
3-J
ul-
14
1
,45
9,9
51.0
0
486
,650
.00
1
,33
9,4
42.
14
4
12,9
12.1
7
17
-Sep
-14
48
4 4
92
66
18
-Sep
-14
23
-Sep
-14
1
,51
1,5
36.0
0
458
,041
.00
1
,52
4,8
87.
03
4
32,5
20.6
8
13
-No
v-1
4 4
27
43
5
67
21
-No
v-1
4 2
1-N
ov
-14
1
,44
2,9
47.0
0
450
,912
.00
1
,51
1,0
32.
99
3
49,0
62.9
8
16
-Ja
n-1
5 3
63
37
1
68
24
-Feb
-15
12
-Ma
r-1
5
2,8
97,
994
.00
4
34,2
45.0
0
2,9
11
,34
5.2
3
463
,100
.80
2
1-A
pr-
15
26
8 2
76
68
A
13
-Feb
-15
18
-Ma
r-1
5
3,4
28,
312
.00
-
3,4
28
,56
7.3
7
-
10
-Ap
r-1
5 2
79
N/
A
69
20
-Ma
y-1
5 2
-Ju
n-1
5
2,1
17,
091
.00
4
59,3
91.0
0
2,1
16
,83
5.4
6
459
,391
.11
1
5-J
ul-
15
35
1 3
51
69
A
4-A
ug
-15
4-A
ug
-15
1
,84
1,1
42.0
0
22
,595
.70
1
,41
9,2
15.
61
22
,595
.70
2
9-S
ep-1
5 2
75
27
5
70
8-S
ep-1
5 8
-Sep
-15
15
5,2
12.8
1
391
,078
.00
1
,55
5,2
12.
81
3
91,0
78.1
6
3-N
ov
-15
42
3 4
23
71
18
-No
v-1
5 2
3-N
ov
-15
2
,10
1,1
82.0
0
426
,839
.00
2
,10
1,1
82.
01
4
26,8
03.9
3
13
-Ja
n-1
6 3
52
35
2
71
A
10
-Ma
r-1
6 1
1-M
ar-
16
6
,46
0,2
16.0
0
54
,183
.00
5
,87
0,7
28.
19
55
,072
.86
5
-Ma
y-1
6 2
39
23
9
71
B
22
-Sep
-16
14
-Oct
-16
42
3,7
11.0
0
2
95.0
0
3
95
,89
1.1
9
2
77.3
8
17
-No
v-1
6 8
02
80
2
72
21
-No
v-1
6 1
3-D
ec-1
6
7,1
39,
425
.00
1
,349
,521
.00
4
,86
2,0
64.
61
1,1
28,3
88.8
3
16
-Ja
n-1
7 7
42
74
2
73
17
-Ja
n-1
7 2
6-J
an
-17
2
,57
7,0
30.0
0
588
,521
.00
2
,44
5,5
69.
67
5
57,8
32.9
5
14
-Ma
r-1
7 6
85
68
5
74
21
-Ma
r-1
7 2
4-M
ar-
17
3
,03
5,2
26.2
9
688
,645
.95
3
,03
5,2
26.
29
6
88,6
45.9
5
16
-Ma
y-1
7 6
22
62
2
74
A
22
-Feb
-17
6-A
pr-
17
2
,35
7,6
34.9
2
216
,087
.17
2
,35
7,6
34.
92
2
16,0
87.1
7
19
-Ap
r-1
7 6
49
64
9
74
B
22
-Feb
-17
24
-Ap
r-1
7
1,0
18,
877
.93
15,0
83.8
8
1,0
18
,87
7.9
3
1
5,0
83.8
8
19
-Ap
r-1
7 6
49
64
9
124
|P
erf
orm
an
ce A
ud
it R
ep
ort
of
the
Au
dit
or-
Ge
ne
ral
on
se
lect
ed
Ro
ad
s
IPC
N
O
Co
ntr
act
or'
s S
UB
MIS
SIO
N
DA
TE
IPC
C
ER
TIF
IED
D
AT
E
IP
C A
MT
¢
IP
C A
MT
$
A
MT
PA
ID ¢
A
MT
PA
ID $
D
ue
Da
te
D
ela
ys
¢
D
ela
ys
$
75
12
-Ma
y-1
7 2
2-M
ay
-17
2
,75
7,3
91.0
0
564
,827
.00
2
,45
6,9
69.
47
5
61,0
64.3
8
7-J
ul-
17
57
0 5
70
76
18
-Ju
l-17
1
-Au
g-1
7
3,3
00,
300
.94
7
49,0
63.7
3
3,3
00
,30
0.9
4
749
,063
.73
1
2-S
ep-1
7 5
03
50
3
77
30
-No
v-1
7 1
9-D
ec-1
7
4,2
27,
602
.08
8
08,5
97.0
7
4,2
27
,60
2.0
6
808
,597
.07
2
5-J
an
-18
36
8 3
68
77
A
19
-Ma
r-1
8 1
9-M
ar-
18
11
,38
7,9
62.5
5
3,1
11,6
82.4
4
1
1,3
87
,96
2.5
5
3
,111
,682
.44
1
4-M
ay
-18
25
9 2
59
77
B
24
-Ju
n-1
9 1
-Ju
l-1
9
1
4,2
13,
138
.71
4
61,5
23.2
9
1
4,2
13
,13
8.7
1
461
,523
.29
1
9-A
ug
-19
N/
A
N/
A
To
tal
18
5,8
64,
929
.69
5
1,2
46,4
46
.75
1
69
,88
6,3
64.
71
4
9,4
22,9
33.2
1
Sou
rce:
Au
dit
team
rev
iew
of
Inte
rim
Pay
men
t C
erti
fica
tes
for
the
Tet
teh
Qu
arsh
ie M
adin
a R
oad
Pro
ject
125
|P
erf
orm
an
ce A
ud
it R
ep
ort
of
the
Au
dit
or-
Ge
ne
ral
on
se
lect
ed
Ro
ad
s
Pa
ym
en
t d
eta
ils
for
Ay
am
furi
to
Ne
w O
bu
ase
Ro
ad
Pro
ject
Ta
ble
41:
Pa
ym
ent
det
ail
s fo
r A
ya
mfu
ri t
o N
ew O
bu
ase
Ro
ad
Pro
ject
IPC
No
. S
ub
mis
sio
n
da
te
Da
te
sub
mit
ted
to
M
RH
Da
ys
to
MR
H
Am
ou
nt
cert
ifie
d
D
ue
Da
te
Da
te p
aid
D
ela
y
GH
¢
US
D
G
H¢
U
SD
G
H¢
U
SD
2
24
/08
/2
013
24
/09
/2
013
31
1,5
13
,000
.63
1,8
80
,816
.35
19
/10
/2
013
20
/11
/2
013
20
/11
/2
013
32
32
3
07
/01
/2
014
27
/02
/2
014
51
84
9,45
9.7
0 1
,07
5,3
04.6
0 0
4/
03/
201
4 1
1/
04/
201
4 0
9/
04/
201
4 3
8 3
6
4
05
/03
/2
014
22
/03
/2
014
17
52
3,38
5.6
6 6
39,
890
.63
30
/04
/2
014
25
/07
/2
014
06
/08
/2
014
86
98
5
10
/04
/2
014
27
/06
/2
014
78
82
6706
.5
94
8,50
5.4
4 0
5/
06/
201
4 1
1/
07/
201
4 1
4/
07/
201
4 3
6 3
9
6
30
/04
/2
014
14
/07
/2
014
75
47
2118
.5
50
2194
.01
25
/06
/2
014
25
/08
/2
014
06
/08
/2
014
61
42
7
28
/06
/2
014
30
/10
/2
014
12
4 7
37,
320
.42
67
6,66
9.6
5 2
3/
08/
201
4 1
0/
12/
201
4 2
0/
12/
201
4 1
09
11
9
7A
2
3/
07/
201
4 1
0/
03/
201
5 2
30
57
,227
.37
- 1
7/
09/
201
4 0
8/
06/
201
5 -
26
4 -
8
11
/10
/2
014
26
/01
/2
015
10
7 3
,27
0,5
10.1
2 3
657
40.4
8 1
6/
12/
201
4 1
3/
02/
201
5 1
7/
02/
201
5 5
9 6
3
9
07
/12
/2
014
10
/03
/2
015
93
4,4
25
,361
.11
43
6,37
5.9
9 0
1/
02/
201
5 1
5/
04/
201
5 0
8/
06/
201
5 7
3 1
27
10
05
/02
/2
015
15
/04
/2
015
69
3,3
43
,866
.32
45
6,21
6.6
2 0
2/
04/
201
5 2
0/
05/
201
5 0
8/
06/
201
5 4
8 6
7
11
25
/03
/2
015
03
/06
/2
015
70
2,1
11
,846
.64
13
3065
3.46
2
0/
05/
201
5 2
1/
07/
201
5 1
6/
07/
201
5 6
2 5
7
12
08
/05
/2
015
16
/07
/2
015
69
1,0
49
,860
.22
73
3,93
8.3
6 0
3/
07/
201
5 1
4/
08/
201
5 0
1/
09/
201
5 4
2 6
0
13
06
/06
/2
015
24
/08
/2
015
79
1,0
26
,200
.40
48
7,74
9.9
8 0
1/
08/
201
5 2
1/
10/
201
5 2
9/
10/
201
5 8
1 8
9
14
08
/07
/2
015
24
/08
/2
015
47
1,0
92
,617
.05
76
3,06
3.3
0 0
2/
09/
201
5 2
4/
11/
201
5 2
5/
11/
201
5 8
3 8
4
14
A
25
/07
/2
015
24
/08
/2
015
30
22
7,54
6.5
4 2
0,4
53.2
4 1
9/
09/
201
5 2
2/
12/
201
5 1
6/
03/
201
6 9
4 1
79
15
10
/08
/2
015
30
/11
/2
015
11
2 1
,08
5,9
83.9
7 6
79,
368
.66
05
/10
/2
015
22
/12
/2
015
16
/03
/2
016
78
16
3
16
02
/09
/2
015
30
/11
/2
015
89
1,9
22
,011
.87
13
4951
1.31
2
8/
10/
201
5 2
2/
12/
201
5 2
2/
12/
201
5 5
5 5
5
17
04
/10
/2
015
24
/12
/2
015
81
-
1,5
31
,290
.30
29
/11
/2
015
-
04
/04
/2
016
-
12
7
18
07
/11
/2
015
03
/03
/2
016
11
7 -
1
,14
9,4
53.7
4 0
2/
01/
201
6 -
0
3/
05/
201
6 -
1
22
19
07
/12
/2
015
16
/03
/2
016
10
0 -
7
84,
924
.19
01
/02
/2
016
-
23
/06
/2
016
-
14
3
19
A
16-
03-1
6
28
8,18
4.5
8 2
0,0
36.7
6 N
ot
Pa
id
126
|P
erf
orm
an
ce A
ud
it R
ep
ort
of
the
Au
dit
or-
Ge
ne
ral
on
se
lect
ed
Ro
ad
s
20
26
/01
/2
016
18
/04
/2
016
83
-
1,0
96
,125
.10
22
/03
/2
016
-
20
/08
/2
016
-
15
1
21
01
/04
/2
016
27
/07
/2
016
11
7 -
1
,40
3,6
22.4
7 2
7/
05/
201
6 -
1
5/
09/
201
6 -
1
11
22
04
/06
/2
016
29
/09
/2
016
11
7 -
3
98,
182
.22
30
/07
/2
016
-
16
/11
/2
016
-
10
9
22
A
05
/07
/2
016
20
/02
/2
017
23
0 2
86,
421
.75
38
,534
.10
30
/08
/2
016
28
/02
/2
017
28
/02
/2
017
182
1
82
23
26
/08
/2
016
30
/11
/2
016
96
48
2,86
1.2
2 4
23,
489
.19
23
/10
/2
016
19
/12
/2
016
19
/12
/2
016
57
57
24
03
/12
/2
016
13
/04
/2
017
13
1 1
,84
0,7
96.4
8 1
,49
4,1
17.8
3 2
8/
01/
201
7 2
6/
09/
201
7 2
3/
06/
201
7 2
41
14
6
25
27
/04
/2
017
17
/10
/2
017
17
3 1
,45
8,5
56.7
8 7
44,
037
.22
22
/06
/2
017
30
/11
/2
017
30
/11
/2
017
1
61
16
1
26
23
/01
/2
018
18
/05
/2
018
11
5 2
,43
8,8
14.9
8 1
,61
6,4
10.5
1 2
0/
03/
201
8 1
8-0
6-2
018
1
8-06
-20
18
90
90
27
05
/10
/2
018
20
/12
/2
018
76
34
1,03
9.9
2 5
17,
353
.42
30
/11
/2
018
3
1-12
-20
18
31
-12
-201
8 3
1 3
1
28
05
/10
/2
018
20
/01
/2
019
10
7 1
,28
3,9
40.1
0 4
82,
405
.00
30
/11
/2
018
No
t p
aid
N
ot
pa
id
212
2
12
29
29
/12
/2
018
22
/03
/2
019
83
2,0
87
,754
.80
1,4
91
,175
.36
23
/02
/2
019
No
t p
aid
N
ot
pa
id
127
1
27
30
25
/03
/2
019
21
/05
/2
019
57
34
1,03
9.9
1 5
17,
353
.42
20
/05
/2
019
No
t p
aid
N
ot
pa
id
41
41
T
OT
AL
3
5,3
84,4
33
.54
26
,054
,96
2.9
1
So
urc
e: R
esid
ent
En
gin
eers
Pa
ym
ent
Rec
ord
s, G
HA
Tra
nsp
ort
Sec
tor
Pro
ject
(T
SP
)Co
ntr
act
or’
s G
ener
al
Led
ger
(6
Ju
ne
20
19)
an
d M
inis
try
of
Ro
ad
s a
nd
Hig
hw
ay
s T
SP
Acc
ou
nt
Det
ail
s R
epo
rt (
10
Ju
ne
20
19
).
127
|P
erf
orm
an
ce A
ud
it R
ep
ort
of
the
Au
dit
or-
Ge
ne
ral
on
se
lect
ed
Ro
ad
s
Pa
ym
en
t d
eta
ils
for
Bo
lgata
ng
a-B
aw
ku
-Po
lim
ak
om
Ta
ble
42:
Pa
ym
ent
det
ail
s fo
r B
olg
ata
nga
-B
aw
ku
-Po
lim
ak
om
Ro
ad
Pro
ject
SN
IP
C N
o.
Da
te o
f A
pp
lica
tio
n
De
ad
lin
e f
or
Pa
ym
en
t
Am
ou
nt
Cert
ifie
d
Gh
c
Am
ou
nt
Paid
Gh
c P
ay
men
t D
ate
Da
ys
of
De
lay
Am
ou
nt
Ou
tsta
nd
ing
In
tere
st o
n d
ela
ye
d
pa
ym
en
t
1 IP
C 1
A
dv
ance
28
-Oct
-16
23-D
ec-1
7 91
,911
,576
.70
91,9
11,5
76.7
0 11
-Sep
-16
- 0
2 IP
C 2
11
-Jan
-17
08-M
ar-1
7 16
,330
,915
.03
3,00
0,00
0.00
02
-Oct
-17
208
0 3,
444,
352.
42
2 IP
C 2
11
-Jan
-17
08-M
ar-1
7
13,3
30,9
15.0
3 18
-Jan
-18
316
0
3 IP
C 3
17
-Feb
-17
14-A
pr-
17
24-J
ul-
17
808,
939.
05
3 IP
C 3
17
-Feb
-17
14-A
pr-
17
9,84
8,20
2.21
9,
848,
202.
28
10-O
ct-1
7 17
9 0
4 IP
C 4
18
-Mar
-17
13-M
ay-1
7 10
,534
,568
.06
816,
545.
75
18-J
an-1
8 53
6 9,
718,
022.
32
4,53
7,61
7.31
4
IPC
4
18-M
ar-1
7 13
-May
-17
17-J
an-1
9
4 IP
C 4
18
-Mar
-17
13-M
ay-1
7
-
5 IP
C 5
13
-Ap
r-17
08
-Ju
n-1
7 12
,686
,939
.30
0 -
510
12,6
86,9
39.3
0 7,
141,
876.
72
6 IP
C 6
17
-May
-17
12-J
ul-
17
8,58
6,53
4.89
0
- 47
5 8,
586,
534.
89
4,52
3,58
4.04
7 IP
C 7
13
-Ju
n-1
7 08
-Au
g-1
7 8,
616,
532.
18
8,61
6,53
2.18
18
-Ap
r-18
26
5 0
1,46
8,76
6.22
8 IP
C 8
11
-Ju
l-17
05
-Sep
-17
6,70
2,89
6.10
0
- 42
1 6,
702,
896.
10
3,17
1,94
0.82
9 IP
C 9
09
-Au
g-1
7 04
-Oct
-17
7,82
1,64
5.55
0
- 38
5 7,
821,
645.
55
3,48
5,85
5.56
10
IPC
10
12-S
ep-1
7 07
-No
v-1
7 9,
812,
058.
56
0 -
357
9,81
2,05
8.56
4,
069,
365.
59
11
IPC
11
08-N
ov
-17
03-J
an-1
8 14
,930
,670
.88
0 -
291
14,9
30,6
70.8
8 5,
447,
589.
05
12
IPC
12
23-J
an-1
8 20
-Mar
-18
8,95
0,52
8.30
0
- 19
4 8,
950,
528.
30
2,70
8,90
9.01
13
IPC
13
13-J
un
-18
08-A
ug
-18
7,80
5,94
3.08
0
- 84
7,
805,
943.
08
1,63
3,84
9.33
To
tal
85,9
13,7
48.
84
8,6
16,5
32.1
8
7
7,2
97
,21
6.6
6 3
8,1
89
,35
3.6
5
Mission
Statement
The Ghana Audit Service exists
To promote
·
good governance in the areas of transparency,
accountability and probity in Ghana’s public financial
management system
By auditing
·
to recognized international standards and reporting
our audit results
And
· reporting to Parliament