SECURITY FENCING PROGRAMME
BRIEFING TO THE DEPARTMENT OF CORRECTIONAL SERVICES
PORTFOLIO COMMITTEE
17 September 2013
SECURITY FENCING PROGRAMME
BRIEFING TO THE DEPARTMENT OF CORRECTIONAL SERVICES
PORTFOLIO COMMITTEE
17 September 2013
PURPOSEPURPOSE
At the request of the Parliamentary Portfolio Committee on
Correctional Services, the Department of Correctional Services
(DCS), in association with the Independent Development Trust
(IDT), have prepared a presentation to address the concerns
raised by the Committee:
• The Role of the IDT
• Management of the Programme
• Programme Budgets
At the request of the Parliamentary Portfolio Committee on
Correctional Services, the Department of Correctional Services
(DCS), in association with the Independent Development Trust
(IDT), have prepared a presentation to address the concerns
raised by the Committee:
• The Role of the IDT
• Management of the Programme
• Programme Budgets
THE IDT BACKGROUND THE IDT BACKGROUND
The 1997 Cabinet mandate is still in place: “The IDT must be transformed into a government development agency that will implement projects which are commissioned by government departments.”
Integrated into the public service delivery system in 1999 with the promulgation of the PFMA and listed as a Schedule 2 Major Public Entity. Achieved 10 successive years unqualified audit reports
Reports to Parliament through the Minister of Public Works, the Shareholder Representative and Executive Authority. Thus the IDT seeks to contribute towards the mandate, vision and strategic objectives of Department of Public Works (DPW)
Is a special purpose vehicle which has since 2000/01 directed over R14.5bn of government’s development investment.
Supports all spheres of government with the delivery of its mandate through programme implementation agreements.
Does not have a funded mandate. Charges a management fee in addition to recovering programme overhead costs.
The 1997 Cabinet mandate is still in place: “The IDT must be transformed into a government development agency that will implement projects which are commissioned by government departments.”
Integrated into the public service delivery system in 1999 with the promulgation of the PFMA and listed as a Schedule 2 Major Public Entity. Achieved 10 successive years unqualified audit reports
Reports to Parliament through the Minister of Public Works, the Shareholder Representative and Executive Authority. Thus the IDT seeks to contribute towards the mandate, vision and strategic objectives of Department of Public Works (DPW)
Is a special purpose vehicle which has since 2000/01 directed over R14.5bn of government’s development investment.
Supports all spheres of government with the delivery of its mandate through programme implementation agreements.
Does not have a funded mandate. Charges a management fee in addition to recovering programme overhead costs.
PROGRAMME EXPENDITUREPERFORMANCE TREND: 2009-10 TO
2012/13
PROGRAMME EXPENDITUREPERFORMANCE TREND: 2009-10 TO
2012/13
PROGRAMME DISTRIBUTION: 2012-2013PROGRAMME DISTRIBUTION: 2012-2013
Please note that the Criminal Justice Systems Facilities expenditure value above is a combination between DCS and DoJ&CD
All of the above departments have signed agreements governing their relationship with the IDT
Please note that the Criminal Justice Systems Facilities expenditure value above is a combination between DCS and DoJ&CD
All of the above departments have signed agreements governing their relationship with the IDT
Programme Category Total % Contribution
Criminal Justice Systems Facilities R 676 957 892 12.0%
Educational Facilities R 2 835 057 678 50.2%
Enterprise Development R 389 929 0.0%
Environmental Intervention R 128 263 491 2.3%
Food Security R 132 165 349 2.3%
Health Care & Facilities R 1 072 169 869 19.0%
Other R 2 879 554 0.1%
Poverty Relief & EPWP R 405 331 378 7.2%
Public Facilities R 79 685 255 1.4%
Sports, Arts and Culture R 71 331 560 1.3%
Water & Sanitation R 91 371 779 1.6%
Welfare Support and Facilities R 151 965 535 2.7%
Grand Total R 5 647 569 270 100.0%
THE IDT AND DEPARTMENTAL FUNDS TRANSFER
THE IDT AND DEPARTMENTAL FUNDS TRANSFER
Please note that the above extracts are from a letter from National Treasury tin response to the IDT dated 12 May 2009 and signed off by the then Chief Director: Governance Monitoring and Compliance, Jayce Nair highlighting the various departments concerns around “advance payments”
Please note that the above extracts are from a letter from National Treasury tin response to the IDT dated 12 May 2009 and signed off by the then Chief Director: Governance Monitoring and Compliance, Jayce Nair highlighting the various departments concerns around “advance payments”
DEPARTMENTAL FUNDS TRANSFER TO IDT DEPARTMENTAL FUNDS TRANSFER TO IDT
Please note that the above extracts are from a letter from National Treasury tin response to the IDT dated 12 May 2009 and signed off by the then Chief Director: Governance Monitoring and Compliance, Jayce Nair highlighting the various departments concerns around “advance payments”
Please note that the above extracts are from a letter from National Treasury tin response to the IDT dated 12 May 2009 and signed off by the then Chief Director: Governance Monitoring and Compliance, Jayce Nair highlighting the various departments concerns around “advance payments”
PROGRAMME DCSSF02PROGRAMME DCSSF02
DCSSF02DCSSF02
• The DCS and the IDT entered into a Memorandum of Agreement in October 2011 whereby the IDT would serve as an implementation agent.
• The Scope Statement compiled at the joint approach planning session between DCS and IDT is hereunder:
• To reposition and transform the Department of Correctional Services in the Criminal Justice system through the implementation of quick and long term infrastructure delivery interventions. Ensure effective and efficient integrated service delivery informed by the White Paper on Correctional Services.
• Approach adopted that 90% security is “no security at all”.
• DCS required a comprehensive security solution.
• The DCS and the IDT entered into a Memorandum of Agreement in October 2011 whereby the IDT would serve as an implementation agent.
• The Scope Statement compiled at the joint approach planning session between DCS and IDT is hereunder:
• To reposition and transform the Department of Correctional Services in the Criminal Justice system through the implementation of quick and long term infrastructure delivery interventions. Ensure effective and efficient integrated service delivery informed by the White Paper on Correctional Services.
• Approach adopted that 90% security is “no security at all”.
• DCS required a comprehensive security solution.
IDT APPROACH TO DCS REQUIREMENTSIDT APPROACH TO DCS REQUIREMENTS
PORTFOLIO GOVERNANCE STRUCTUREPORTFOLIO GOVERNANCE STRUCTURE
MEETINGS:
•Site Meetings (SM) (Level 4):
• Fortnightly
• IDT Regional, DCS Local and Regional, Engineers, Contractor
• Monitor site progress, challenges, compliance.
• Programme Progress Meeting (PPM) (Level 3):
• Monthly
• IDT National and DCS National, Engineers, Contractor
• National progress, operational issues, Contractor requests and submissions
MEETINGS:
•Site Meetings (SM) (Level 4):
• Fortnightly
• IDT Regional, DCS Local and Regional, Engineers, Contractor
• Monitor site progress, challenges, compliance.
• Programme Progress Meeting (PPM) (Level 3):
• Monthly
• IDT National and DCS National, Engineers, Contractor
• National progress, operational issues, Contractor requests and submissions
MOA GOVERNANCE REQUIREMENTSMOA GOVERNANCE REQUIREMENTS
MEETINGS:
• Programmes Steering Committee (PSC) (Level 2)
• Monthly
• IDT National, DCS National and invited Service Providers
• Responsible for oversight of all DCS/IDT Projects
• Client Meeting (CM) (Level 1)
• Monthly
• IDT National, DCS National
• Responsible for oversight of all DCS/IDT Projects
MEETINGS:
• Programmes Steering Committee (PSC) (Level 2)
• Monthly
• IDT National, DCS National and invited Service Providers
• Responsible for oversight of all DCS/IDT Projects
• Client Meeting (CM) (Level 1)
• Monthly
• IDT National, DCS National
• Responsible for oversight of all DCS/IDT Projects
MOA GOVERNANCE REQUIREMENTSMOA GOVERNANCE REQUIREMENTS
PSC RESPONSIBILITIESPSC RESPONSIBILITIES
• Oversight
• Time
• Cost (Scope Management)
• Quality
• Budgetary Control
• Monthly meetings and co-ordination
• Programme Delivery
• Liaison with respect to local and regional issues
• Ensure Compliance with the MOA
• Oversight
• Time
• Cost (Scope Management)
• Quality
• Budgetary Control
• Monthly meetings and co-ordination
• Programme Delivery
• Liaison with respect to local and regional issues
• Ensure Compliance with the MOA
SCOPE OF WORKS 1 of 2 (External)SCOPE OF WORKS 1 of 2 (External)
• High Security Fences
• Agricultural and Perimeter Fences
• Fibre and Copper Network
• Closed Circuit Television
• External Lighting along fences
• Gates
• High Security Fences
• Agricultural and Perimeter Fences
• Fibre and Copper Network
• Closed Circuit Television
• External Lighting along fences
• Gates
• Sallyports and Guardhouses
• Earthworks and Civils
• Electrical Infrastructure
• Generators
• Detection Systems
• Sallyports and Guardhouses
• Earthworks and Civils
• Electrical Infrastructure
• Generators
• Detection Systems
• Access Control Points:• X-Ray machines
• Metal detectors
• Biometric readers
• Turnstiles
• Closed Circuit Television
• Workstations
• Intercoms
• Uninterrupted Power Supplies
• Access Control Points:• X-Ray machines
• Metal detectors
• Biometric readers
• Turnstiles
• Closed Circuit Television
• Workstations
• Intercoms
• Uninterrupted Power Supplies
• Software systems:• Integrated Security
Management System
• Prison management System
• Graphic User Interfaces
• General:• Cabling and Wi-Fi network
• Cell Phone Detection
• Prison Doors
• Software systems:• Integrated Security
Management System
• Prison management System
• Graphic User Interfaces
• General:• Cabling and Wi-Fi network
• Cell Phone Detection
• Prison Doors
SCOPE OF WORKS 2 of 2 (Internal)SCOPE OF WORKS 2 of 2 (Internal)
TENDER PROCESS-PSP AND CONTRACTORTENDER PROCESS-PSP AND CONTRACTOR
• Open Tender process undertaken to procure a Professional Service
Provider and Contractor.
• The Professional Consultant and Contractor were appointed by
February 2012 for the “Installation of high security of 27 Prisons
(Correctional Centres) on 13 Facilities as well as associated integrated
security systems and sallyports that go with the fencing” for a tender
value of R476m.
• Open Tender process undertaken to procure a Professional Service
Provider and Contractor.
• The Professional Consultant and Contractor were appointed by
February 2012 for the “Installation of high security of 27 Prisons
(Correctional Centres) on 13 Facilities as well as associated integrated
security systems and sallyports that go with the fencing” for a tender
value of R476m.
PROJECT EXECUTION PLANPROJECT EXECUTION PLAN
• Contractor was advised to begin procurement immediately to accelerate delivery.
• This instruction was imperative due to the fact that the grade of steel used for the fencing needed to be fabricated by the local steel foundries.
• The fence manufacturer also had to switch over their factory to manufacture the customised fencing for DCSSF02.
• At the beginning of the programme, an assessment was conducted to confirm the scope of works meets the operational requirements. This process is called the Project Execution Plan (PrEP). This led to a mitigation of scope variance at a very early stage.
• PrEP reports were produced which considered the operational needs of each facility. This had resulted in quantity fluctuations as opposed to rate fluctuations. Only the original tendered rates were used.
• Contractor was advised to begin procurement immediately to accelerate delivery.
• This instruction was imperative due to the fact that the grade of steel used for the fencing needed to be fabricated by the local steel foundries.
• The fence manufacturer also had to switch over their factory to manufacture the customised fencing for DCSSF02.
• At the beginning of the programme, an assessment was conducted to confirm the scope of works meets the operational requirements. This process is called the Project Execution Plan (PrEP). This led to a mitigation of scope variance at a very early stage.
• PrEP reports were produced which considered the operational needs of each facility. This had resulted in quantity fluctuations as opposed to rate fluctuations. Only the original tendered rates were used.
PROJECT EXECUTION PLANPROJECT EXECUTION PLAN
PrEP Results
•15 Correctional Centres on 8 Facilities within the Tender amount.
PrEP Results
•15 Correctional Centres on 8 Facilities within the Tender amount.
Region Management Area Facility/Correctional Centre
Gauteng Johannesburg JHB Med A, Med B, Female, Juvenile
Kgosi Mampuru II Pretoria Local
KZN Durban Umzinto
Pietermaritzburg Pietermaritzburg
Free State Kroonstad Harrismith
Eastern Cape Mthatha Mthatha
Western Cape Goodwood Goodwood
Pollsmoor Pollsmoor Max, Med A,B,C, Female
IMPLEMENTATIONIMPLEMENTATION
PreP Results cont.
•Balance of 12 Correctional Centres on 5 Facilities : Access on hold until further funds allocation from DCS.
PreP Results cont.
•Balance of 12 Correctional Centres on 5 Facilities : Access on hold until further funds allocation from DCS.
IMPLEMENTATIONIMPLEMENTATION
Region Management Area
Facility/Correctional Centres
Gauteng Modderbee Modderbee
Free State Kroonstad Kroonstad Med A,B, Female, Juvenile
Eastern Cape St Albans St Albans
Mpumalunga Barberton Barberton
KZN Durban Westville Med A,B,C, Female, Juvenile
PROGRESS AS AT 15 JULY 2013PROGRESS AS AT 15 JULY 2013
Preliminary & General (P&G’s) are defined as those expenses which include overhead costs and site establishment.
A “bond store” system was implemented where material was procured and stored at a central warehouse for distribution to various sites.
Preliminary & General (P&G’s) are defined as those expenses which include overhead costs and site establishment.
A “bond store” system was implemented where material was procured and stored at a central warehouse for distribution to various sites.
The bond store principle was initiated at the beginning of the DCSSF02 contract due to the large amounts of fencing material that needed to be manufactured and stored on location at the fence manufacturers on site warehouse.
Due to the need to finalise the PrEP process which led to a variance in final quantities this storage method was used as an interim point of transfer.
Cognisance must be taken of the fact that the fencing panels range between 6-8 metres in length and have a standard width of 3 metres, hence this led to the panels being transferred across the country by road from the Cape using abnormal vehicles.
The bond store has ceased to exist in the course of 2012 as the final quantities had been agreed by the PrEP process and dispatched from the suppliers “bond store” in the Cape directly to the respective fencing sites nationally.
The bond store principle was initiated at the beginning of the DCSSF02 contract due to the large amounts of fencing material that needed to be manufactured and stored on location at the fence manufacturers on site warehouse.
Due to the need to finalise the PrEP process which led to a variance in final quantities this storage method was used as an interim point of transfer.
Cognisance must be taken of the fact that the fencing panels range between 6-8 metres in length and have a standard width of 3 metres, hence this led to the panels being transferred across the country by road from the Cape using abnormal vehicles.
The bond store has ceased to exist in the course of 2012 as the final quantities had been agreed by the PrEP process and dispatched from the suppliers “bond store” in the Cape directly to the respective fencing sites nationally.
BOND STOREBOND STORE
PROJECTED COMPLETION DATESPROJECTED COMPLETION DATES
PROGRESS PHOTOSPROGRESS PHOTOS
HarrismithHarrismith
PietermaritzburgPietermaritzburg PietermaritzburgPietermaritzburg
HarrismithHarrismith
UmzintoUmzinto
PROGRESS PHOTOSPROGRESS PHOTOS
PretoriaPretoria GoodwoodGoodwood
PollsmoorPollsmoor JohannesburgJohannesburg
MthathaMthatha
PROGRAMMES CHALLENGESPROGRAMMES CHALLENGES
• Excessive Rainfall hampered the implementation process
• Existing services, no records exist
• Poor soil conditions hamper progress on most of the sites
• Inconvenience caused due to the new security measures e.g. parking for staff affected
• Construction in a “live” facility, requires that the facility is fully secure at all times.
• Excessive Rainfall hampered the implementation process
• Existing services, no records exist
• Poor soil conditions hamper progress on most of the sites
• Inconvenience caused due to the new security measures e.g. parking for staff affected
• Construction in a “live” facility, requires that the facility is fully secure at all times.
Thank YouThank You