section-i executive summary - welcome to … report m/s sri dwarika dheesh polymers pvt. ltd. team...
TRANSCRIPT
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 23 Authorized Signatory
SECTION-I
EXECUTIVE SUMMARY
1.1 Identification of Project
M/s Sri Dwarika Dheesh Polymers Pvt. Ltd. is an existing synthetic organic chemical
manufacturing industry situated at Plot F-448 and F-449, Matasya Industrial Area, Tehsil-
Alwar (Raj.). Earlier the unit was doing business in name of M/s S.A.S. Polymers Pvt. Ltd,
which has been remained to current “M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.” by RIICO
Alwar vide letter No 5666 dated 03.10.06 enclosed as Annexure I. The unit is presently
involved in manufacturing Azo- Di- Carbonamide (ADC) to tune of 3.00 MT/Day and Di -
Nitrosopenta Methylene Teramine (DNPT) to tune of 2.00 MT/Day. Now the company is
proposing to expand the manufacturing capacity of unit to the tune of 10 MT/Day including
Azo- Di- Carbonamide (ADC) to tune of 8.00 MT/Day and Di - Nitrosopenta Methylene
Teramine (DNPT) to tune of 2 MT/Day. The total existing plot area is 4000.00 Sq. m. The
proposed expansion will include the adjoining Plot No. F-447 of area 2000.00 Sq.m. Thus the
total Unit Area after expansion will be 6000.00 Sq. m.
The existing project cost is INR 402.11 Lac. The proposed capital investment in the expansion
is about INR 254.25 Lac. Thus, after expansion the project cost will be about INR 656.36 Lac.
The unit is categorized under category B 5 (f) as per the Gazette Notification dated Sep. 14th, 2006.
{Synthetic organic chemical industry (dyes, and dye intermediates; bulk drugs and intermediates
excluding drug formulation; synthetic rubbers; basic organic chemicals; other synthetic organic
chemicals and chemical intermediates) column 4 “Located in notified industrial area/estate”
1.2 Salient Features of the Project
S. No. Parameters Description
1. Promoter M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
2. Plant
Location
Plot No. F-447, F-448 and F-449, Matasya Industrial Area, Tehsil-
Alwar (Raj.).
Geographical Location:
Latitude: 27°30'28.57"N
Longitude: 76°41'44.67"E
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 24 Authorized Signatory
3. Plant Area 6000 Sq. m.
4. Plant
Capacity
The proposed manufacturing capacity of unit will be 10 MT/Day
including Azo- Di- Carbonamide (ADC) to tune of 8.00 MT/Day and
Di - Nitrosopenta Methylene Teramine (DNPT) to tune of 2 MT/Day.
Thus the annual manufacturing capacity will be 3600.00 MTPA in 360
working days/year
S.
No.
Name of Product Production capacity
Existing After Expansion
1. Azo-Di- Carbonamide
(ADC)
3.00 MT/Day
(1080.00 MTPA)
8.00 MT/Day
(2880 MTPA)
2. Di - Nitrosopenta
Methylene Teramine
(DNPT)
2.00 MT/Day
(720.00 MTPA)
2.00 MT/Day
(720.00 MTPA)
Total 5.00 MT/Day
(1800.00 MTPA)
10.00 MT/Day
(3600.00 MTPA)
5. Water
Requirement
The existing water demand and demand after proposed expansion is
given below:-
Particulars of Water Demand Water Requirement (KLD)
Existing After Expansion
Process & Washing Water 7.00 15.50
Water for Boiler 8.00 12.00
Water for Cooling Tower 20.00 30.00
Domestic Water 1.50 2.00
Daily Fresh Water 18.00 32.50
Daily Recycled Water 18.50 27.00
Total Water Demand 36.50 59.50
6. Source of
Water
RIICO Water Supply.
7. Total Waste
Water
Generation
The liquid waste generated in production process will be from washing
activity and domestic activities. The waste generation in existing unit
and after proposed expansion of unit is tabulated below:-
Particulars of Water Demand Waste Water (KLD)
Existing After Expansion
Industrial Waste Water 7.00 11.25
Domestic Waste Water 1.00 1.25
Total Waste Water 8.00 12.50
The source of industrial waste water is Cleaning of Reactor, Floor
Washing and Boiler & Cooling tower operations. The boiler and
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 25 Authorized Signatory
cooling tower blow down will be of high TDS while the characteristic
of waste water from Cleaning of Reactor will be depend on the various
operation of unit. This industrial waste water is being treated in ETP
and after expansion existing ETP will be use to handle the trade
effluent. The waste water from domestic activities is being handled
through existing septic tank followed by soak pit. Same septic tank will
be used after proposed expansion also.
8. Waste Water
Management
Domestic Waste Water:
The unit is generating 1.00 KLD of domestic wastewater in existing
operations and after the proposed expansion the unit will generate 1.25
KLD of domestic waste water. The waste water from domestic
activities is being handled through existing septic tank followed by soak
pit. Same septic tank will be used after proposed expansion also.
Industrial Waste Water:
In the current situation, the unit is generating 7.00 KLD of industrial
effluent wastewater. It is estimated that after the proposed expansion
the unit will generate 11.25 KLD of industrial waste water. The waste
water will be generated from ADC processing and washing, DNTP
scrubber, DNTP plant washing, blow down from boiler and cooling
tower. The steam from the boiler will be consumed in the
manufacturing process. This industrial waste water will be treated in
existing ETP of 15KLD capacity.
9. Power
Supply
The power demand and D.G. sets of the unit in existing and proposed
after expansion is tabulated below:
Particulars Existing After Expansion
Power Demand 550 kVA 1000 kVA
D.G Set 1x320 kVA 1x320 kVA
1x380 kVA
H.S.D for DG Set
(As and when required)
64 ltr/hr. 140 ltr/hr.
Coal consumption 1 TPD 2 TPD
The power demand is being met from JVVNL and after the proposed
expansion power demand will be met from the existing AVVNL
Connection.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 26 Authorized Signatory
10. Area of
Green Belt
2000 Sq. m. (33.33 % of the plant area) of RIICO Park adjoining to the
unit has been adopted for green belt development. Letter of adaptation
is attached as Annexure II.
670.00 Sq. m. (11.20 % of the plant area) is developed as green belt
inside the project unit.
11. Fuel
Required
The fuel requirement of the unit in existing and proposed after
expansion is tabulated below:
Particulars Existing After Expansion
H.S.D for DG Set
(As and when required)
64 ltr/hr. 140 ltr/hr.
Coal consumption 1 TPD 2 TPD
1.3 Raw Materials and their Source
The chemicals manufacturing industry requires variety of raw materials which are presently
being supplied from local markets, proposed raw material requirement is mentioned below.
Raw Material
Raw Materials Quantity/Day Storage Capacity
Existing Proposed Existing Proposed
For Azo- Di- Carbon amide (ADC)
Caustic Soda Lye 8.00 MT 15.00 MT 40.00 MT 100.00 MT
Liquid Chlorine 6.00 MT 11.00 MT 30.00 MT 18.00 MT
Sulphuric Acid 6.00 MT 14.00 MT 50.00 MT 50.00 MT
Liquid Ammonia 0.175 MT 0.25 MT 3.00 MT 3.00 MT
For Di- Nitrosopenta Methylene Teramine (DNPT)
Hexamine 1.50 MT 1.60 MT 30.00 MT 25.00 MT
Sodium Nitrate 1.75 MT 2.00 10.00 MT 25.00 MT
Hydrochloric Acid 4.00 MT 4.00 MT 15.00 KL 15.00 KL
General Chemical and Catalysts
Sodium Bicarbonate 0.50 MT 1.00 MT 25.00 MT 25.00 MT
Other Chemicals & Catalysts 0.25 MT 0.50 MT 15.00 MT 15.00 MT
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 27 Authorized Signatory
1.4 Product and Material Balance
The proposed manufacturing capacity of unit will be 10 MT/Day including Azo- Di-
Carbonamide (ADC) to tune of 8.00 MT/Day and Di - Nitrosopenta Methylene Teramine
(DNPT) to tune of 2 MT/Day. Thus the annual manufacturing capacity will be 3600.00
MTPA in 360 working Days/Year. The existing production capacity and capacity after
proposed expansion is tabulated below with their respective storage capacities:-
S.
No. Name of Product
Production Capacity Storage Capacity
Existing After Expansion Existing After
Expansion
1. Azo-Di-
Carbonamide (ADC)
3.00 MT/Day
(1080.00 MTPA)
8.00 MT/Day
(2880 MTPA) 15.00 MT 20.00 MT
2.
Di - Nitrosopenta
Methylene Teramine
(DNPT)
2.00 MT/Day
(720.00 MTPA)
2.00 MT/Day
(720.00 MTPA)
10.00 MT 5.00 MT
Total 5.00 MT/Day
(1800.00 MTPA)
10.00 MT/Day
(3600.00 MTPA) 25.00 MT 25.00 MT
1.5 Solid Waste
The solid waste generated from the unit will Ash from boiler, Spent/Used Oil and Sludge
from the wastewater treatment process. The anticipated quantities of solid waste is given
below in table
Waste Category as per
HWMR rules
Quantity Disposal/
Management Existing
After
Expansion
Ash -- 10.00 Kg/Day 20.00 Kg/Day To Cement and Brick
Manufacturing Unit.
Spent/Used
Oil 5.1 300 Lit/Annum 600 Lit/Annum
Sold to Authorized
Recycler/End Users
ETP Sludge 35.3 4.00 MTPA 5.50 MTPA UCCI Udaipur
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 28 Authorized Signatory
1.6 Pollution Control Measures
The source of air pollution in proposed project will be D.G. sets and Process emissions.
The source of air pollutant is described below:-
1. Point Source
There will be following point source emissions from the proposed expansion project
i. Boiler,
ii. DG sets (existing – 320 kVA, proposed - 380 kVA).
2. Process Emission
Process emissions are resulted from the manufacture of products. The emission from the process
majorly includes NH3 Emissions, HCl acid mist, and sodium-hypo chloride emissions.
3. Area Source (Fugitive Emission)
Emission during the Transportation
Particulate emissions occur whenever vehicles travel over a paved or unpaved road.
Particulate emissions from the paved roads are due to direct emissions from vehicles in the form
of exhaust, brake wear and tear emissions and re- suspension of loose material on the road
surface. The quantity of dust emissions from a given segment of unpaved road varies linearly
with the volume of traffic. Dust emissions also depend on the source parameters that
characterize the condition of a particular road and the associated vehicle traffic. During the
transportation of the materials, exhaust gas also contributes in the air pollution. The amount of
the exhaust gas and the level of the air pollutants depend
Management of Air Pollutants
To control the emissions generated during various operations in the industry following
mitigation measures will be adopted.
• Dedicated pipe lines for transfer of solvents from respective solvent storage tanks to
reactors in the production blocks.
• The flue gas from the boiler will be routed to the stack of 32 m through cyclone.
• The process emission will be treated through packed bed wet scrubber.
• D.G. set will be enclosed in acoustic enclosure. The stack height for D.G. set may be
calculated as below following the CPCB guidelines:-
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 29 Authorized Signatory
Stack of 4 m will be provided on each D.G. set.
1.7 Financial and Social Benefits
The PP has envisaged certain social activities around the proposed project as follows:
The PP aims to adopt many heath facilities in government PHC/ CHC for improvement in
health facilities or services.
Facility for village schools including classroom/ toilet construction, ceiling fans/ coolers or
books for school library.
The CSR will be finalized through the socioeconomic survey, after the grant of TOR and will be
submitted as a part of EIA report and presented at the time of presentation for EC.
1.8 Conclusion
“M/s Sri Dwarika Dheesh Polymers Pvt. Ltd” proposed project will not only contribute to the
growth of Indian economy but also strengthen the socioeconomic values/ status in the area. All
the latest and environment friendly technology will be adopted. The unit will also adopt all the
measures like pollution control equipments, effective EMP & DMP to prevent harm to
environment.
H = h + 0.2√kVA
Where
H = Stack height
h = height of building
H = 0.2x√380 kVA
H = 3.90 m.
H = h + 0.2√kVA
Where
H = Stack height
h = height of building
H = 0.2x√320 kVA
H = 3.58 m.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 30 Authorized Signatory
SECTION-II
INTRODUCTION
2.1 Identification of the Project and Background Information
2.1.1 Project
M/s Sri Dwarika Dheesh Polymers Pvt. Ltd. is an existing synthetic organic chemical
manufacturing industry situated at Plot F-448 and F-449, Matasya Industrial Area, Tehsil-
Alwar (Raj.). Earlier the unit was doing business in name of M/s S.A.S. Polymers Pvt. Ltd,
which has been remained to current “M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.” by RIICO
Alwar vide letter No 5666 dated 03.10.06 enclosed as Annexure I. The unit is presently
involved in manufacturing Azo- Di- Carbonamide (ADC) to tune of 3.00 MT/Day and Di -
Nitrosopenta Methylene Teramine (DNPT) to tune of 2.00 MT/Day. Now the company is
proposing to expand the manufacturing capacity of unit to the tune of 10 MT/Day including
Azo- Di- Carbonamide (ADC) to tune of 8.00 MT/Day and Di - Nitrosopenta Methylene
Teramine (DNPT) to tune of 2 MT/Day. The total existing plot area is 4000.00 Sq. m. The
proposed expansion will include the adjoining Plot No. F-447 of area 2000.00 Sq.m. Thus the
total Unit Area after expansion will be 6000.00 Sq. m.
The existing project cost is INR 402.11 Lac. The proposed capital investment in the expansion
is about INR 254.25 Lac. Thus, after expansion the project cost will be about INR 656.36 Lac.
2000 Sq. m. (33.33 % of the plant area) of RIICO Park adjoining to the unit has been adopted
for green belt development. Letter of adaptation is attached as Annexure II.
670.00 Sq. m. (11.20 % of the plant area) is developed as green belt inside the project unit.
Proponent
M/s Sri Dwarika Dheesh Polymers Pvt. Ltd. is registered with the DIC Alwar, Rajasthan, as a
small scale manufacturing unit.
The main object for which the Company has been established is to carry on the business of
manufacturing, organic chemicals namely ADC and DNPT. The Company is promoted by two
experienced promoter Mr. Vijay Kumar Gupta, Mr. Ugrasen Gupta, Mr. Ravindra Kumar Gupta
and Mr. Ashok Khurana.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 31 Authorized Signatory
2.2 Brief Description of Nature of the Project
The project is for expansion of existing unit. The unit is presently involved in manufacturing
Azo- Di- Carbonamide (ADC) to tune of 3.00 MT/Day and Di - Nitrosopenta Methylene
Teramine (DNPT) to tune of 2.00 MT/Day. Now the company is proposing to expand the
manufacturing capacity of unit to the tune of 10 MT/Day including Azo- Di- Carbonamide
(ADC) to tune of 8.00 MT/Day and Di - Nitrosopenta Methylene Teramine (DNPT) to tune of 2
MT/Day. The total existing plot area is 4000.00 Sq. m. The proposed expansion will include the
adjoining Plot No. F-447 of area 2000.00 Sq.m. Thus the total Unit Area after expansion will be
6000.00 Sq. m. 2000 Sq. m. (33.33 % of the plant area) of RIICO Park adjoining to the unit has
been adopted for green belt development. This will have positive impact on the environment.
Letter of adaptation is attached as Annexure II.
Need of the project & its importance to the Country and Region
2.3.1 Need of the project
The development of civilization is a continuous process. The invention of plastics came as boon
to mankind. Plastics are being used now days for making variety of products and have entered
in our day to day life of human being. The raw plastic is to be mixed with various chemicals to
increase its usage, moldable and blow-able proprieties. The blowing agent is a chemical
compound which under certain conditions evolves into gaseous phase and thus used for
manufacturing various foams and sponges. Azo-di-carbonamide (ADC) and Di-nitroso-
pentamethylene tetramine (DNPT) is the most versatile blowing agent for various types of
plastics and rubber respectively. The blowing agents are used in various materials/ products
such as shoe sole, thermal insulation, Gaskets, Life jackets, Rexine cloths, Seat cushions,
Package filter, PVC compounds and Engineering plastics.
2.3.2 Importance to the Country and Region
The proposed project will deliver products which are required in development of health
facilities in country. Industry will create employment for local population of the Villages.
Importance to the Region
Applicant will pay sales tax and other applicable taxes will be paid thereby contributing to the
regional revenue. The public revenue will further be put in public expenditure.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 32 Authorized Signatory
Importance to the Country
The industry and associated activities in the area bring about gain in gross domestic product
(G.D.P). Though there will be minor contribution by the proposed project but will add to the
gains in the G.D.P. It will partly cover the deficit and demand resulting in decreased imports of
steel from other state.
2.4 Demand- Supply gap
There is huge demand and supply gap for blowing agents. The following table gives an idea of
that gap.
Chart: The gap between production and demand in time scale
Year Production (In MT) Demand (in MT)
1985 2000 4000
1990 3000 5500
1995 4000 7000
2000 5000 8000
2002 7000 10,000
2008 10000 14000
2015 Unknown 20000
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 33 Authorized Signatory
Major producing areas/ Supply
Mostly the Private Companies are the main players in the production and supply of blowing
agents such as are High Polymer Lab, Faridabad, Demaco Polymer, Faridabad, Dwarkadeesh,
MIA Alwar, KSJN chemicals Pvt. Ltd etc. There is a large gap between the demand of blowing
agent and the supply of blowing agent. The proposed project aims to fill the demand – supply
gap through optimum allocation of natural resources required to meet the demand effectively.
2.5 Imports vs. Indigenous Production
The proposed project will help substitute blowing agent import from neighboring countries.
There will be no imports for the proposed project. Local villagers will be employed.
2.6 Export Possibility
The proposed expansion in industrial activity is prospecting exports to Nepal.
2.7 Domestic/ Export Markets
Domestic Market
Rubber Industry is considered as core sectors of Indian economy. The per capita consumption
of rubber in India is just 0.8 Kg against 14 Kg in the developed world. This huge gap offers
considerable growth for industries, besides in emerging new applications like rubberisation of
roads and seismic bearing.
The Plastic industry has also taken the great strides in the past few decades. The share of India’s
plastic industries is about 0.5 % of the India GDP. The immense potential of plastic industries
has motivated Indian manufacturers to acquire technical expertise and achieve superior quality.
Export Market
The proposed industry is prospecting exports in Nepal.
2.8 Employment Generation (Direct and Indirect) due to the Project
Direct Employment
Total employment in the Chemical plant will be around of 32 people after proposed expansion of
unit. Currently the unit is having manpower of 27 people. The local villagers will be given
employment. The existing man power and manpower requirement after proposed exapnsion in
the different heads of the unit is tabulated:-
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 34 Authorized Signatory
Details of Technical & Managerial Personnel
S. No. Workers Number
Existing After Expansion
1. Skilled Worker 19 20
2. General Worker 05 09
3. Administration 03 03
Total 27 32
Indirect Employment
Transportation and warehousing in the region will be needed to transfer the blowing
agent eventually. Therefore, transportation and logistical jobs such as truckers etc will
be generated.
There will be vocational training camps and development of technical man power within
the tehsil.
The proposed primary health centre in the study area aims to engage many people in the
health services.
There will be development of externalities for the workers such as petty shops (tea,
repair stations for trucks etc.) as supporting services.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 35 Authorized Signatory
SECTION-III
PROJECT DESCRIPTION
3.1 Type of Project
The unit is categorized under category B 5 (f) as per the Gazette Notification dated Sep. 14th
,
2006. {Synthetic organic chemical industry (dyes, and dye intermediates; bulk drugs and
intermediates excluding drug formulation; synthetic rubbers; basic organic chemicals; other
synthetic organic chemicals and chemical intermediates) column 4 “Located in notified
industrial area/estate”
M/s Sri Dwarika Dheesh Polymers Pvt. Ltd. is proposing expansion of existing unit. The unit is
presently involved in manufacturing Azo- Di- Carbonamide (ADC) to tune of 3.00 MT/Day and
Di - Nitrosopenta Methylene Teramine (DNPT) to tune of 2.00 MT/Day. Now the company is
proposing to expand the manufacturing capacity of unit to the tune of 10 MT/Day including
Azo- Di- Carbonamide (ADC) to tune of 8.00 MT/Day and Di - Nitrosopenta Methylene
Teramine (DNPT) to tune of 2 MT/Day. The total existing plot area is 4000.00 Sq. m. The
proposed expansion will include the adjoining Plot No. F-447 of area 2000.00 Sq.m. Thus the
total Unit Area after expansion will be 6000.00 Sq. m. 2000 Sq. m. (33.33 % of the plant area)
of RIICO Park adjoining to the unit has been adopted for green belt development. This will
have positive impact on the environment.
Letter of adaptation is attached as Annexure II.
3.2 Location
The project is situated at Plot No. F-447, F-448 and F-449, Matasya Industrial Area, Tehsil-
Alwar (Raj.). The plot area is 6000Sq. m. The geographical location of the project is as
follows:- Geographical Location:
Latitude: 27°30'28.57"N
Longitude: 76°41'44.67"E
The location map of the proposed project site along with the map showing the surrounding
features of the project site is given as Figure- 1.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 36 Authorized Signatory
Figure-1: Location Map
2000 Sq. m. (33.33 % of the plant area) of RIICO Park adjoining to the unit has been adopted
for green belt development. Letter of adaptation is attached as Annexure II.
670.00 Sq. m. (11.20 % of the plant area) is developed as green belt inside the project unit. The
schematic plant layout of unit is given in below figure-2.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 37 Authorized Signatory
Figur-2: Plant Layout
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 38 Authorized Signatory
3.3 Details of Alternative Site Considered & Proposed Site Selection Criteria
No alternative site was examined because the project is proposed in the existing
facility of M/s Sri Dwarika Dheesh Polymers Pvt. Ltd. Which have following
favorable conditions of the proposed site:
Vicinity to Market
Availability of Land Area
Availability of RIICO Water supply
Availability of Local Labour
Availability of Power
Well developed transport route
Nearest Railway station: The nearest railway station is Alwar Railway
station which is at a distance of 9.50 km towards NNW.
Nearest Airport: Nearest airport is Sanganer Airport which is about 116.50
Km towards NE from site.
Nearest Highway: The nearest highway is NH 11 connecting Jaipur to Agra
in is at a distance of 55.80 km towards SSE of project site. MDR (Alwar –
Bharatpur) is at 2.75 Km towards NNE. The site is having well developed
road of RIICO Industrial area.
3.4 Size and Magnitude of Operation
M/s Sri Dwarika Dheesh Polymers Pvt. Ltd. is proposing the expansion of existing
industrial unit. The unit is presently involved in manufacturing Azo- Di- Carbonamide
(ADC) to tune of 3.00 MT/Day and Di - Nitrosopenta Methylene Teramine (DNPT)
to tune of 2.00 MT/Day. Now the company is proposing to expand the manufacturing
capacity of unit to the tune of 10 MT/Day including Azo- Di- Carbonamide (ADC) to
tune of 8.00 MT/Day and Di - Nitrosopenta Methylene Teramine (DNPT) to tune of 2
MT/Day.
Additional Cost Break Up
Table: Cost Breakup of the Plant (Proposed Cost)
S. No. Description Cost ( Rs in Lac.)
1 Land & Site Development 4.25
2 Building & Civil Construction 100.00
3 Plant & Machinery 150.00
Total Project Cost 254.25 Lac.
3.5 Process Description with Process Details
3.5.1 Manufacturing process of ADC-
It involves the reaction of caustic soda lye with chlorine, the intermediate product
involves the reaction with caustic soda, ammonia, sulphuric acid & catalysts and
finally the last intermediate reacts with chlorine gas as oxidizing agent in appropriate
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 39 Authorized Signatory
proportion in reaction vessels. The manufacturing process employs batch operation in
reaction vessels and the duration of one batch is approx. 36 hrs.
3.5.2 Manufacturing process of DNPT-
It involves the reaction of sodium nitrite, hexamine & hydrochloric acid in
appropriate proportion in the duration of one batch is approx 18 hrs.
After the formation of desired compounds from above reactions, it is first filtered &
then centrifuged, above 80 % of waste water is discharged in filtration & 15 % in
centrifugation. After squeezing the water in centrifuge the products are dried in tray
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 40 Authorized Signatory
dryers by hot air generator in G.I. trays & then pulverized in machine & blended in
mixture. After blending the products ADC & DNPT are packed in LDPE lined HDPE
bags & delivered to party.
3.6 Raw Material
The chemicals manufacturing industry requires variety of raw materials which are
presently being supplied from local markets, proposed raw material requirement is
mentioned below.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 41 Authorized Signatory
Raw Material
Raw Materials Quantity/Day Storage Capacity
Existing Proposed Existing Proposed
For Azo- Di- Carbon amide (ADC)
Caustic Soda Lye 8.00 MT 15.00 MT 40.00 MT 100.00 MT
Liquid Chlorine 6.00 MT 11.00 MT 30.00 MT 18.00 MT
Sulphuric Acid 6.00 MT 14.00 MT 50.00 MT 50.00 MT
Liquid Ammonia 0.175 MT 0.25 MT 3.00 MT 3.00 MT
For Di- Nitrosopenta Methylene Teramine (DNPT)
Hexamine 1.50 MT 1.60 MT 30.00 MT 25.00 MT
Sodium Nitrate 1.75 MT 2.00 10.00 MT 25.00 MT
Hydrochloric Acid 4.00 MT 4.00 MT 15.00 KL 15.00 KL
General Chemical and Catalysts
Sodium Bicarbonate 0.50 MT 1.00 MT 25.00 MT 25.00 MT
Other Chemicals & Catalysts 0.25 MT 0.50 MT 15.00 MT 15.00 MT
3.6.2 Source of Raw Material and mode of transport
The main raw material will be sourced from domestic market. There is sufficient
availability of shredded raw material in the domestic market. The raw material supply
to the site will be carried out by trucks and tankers.
3.6.3 Products
The proposed manufacturing capacity of unit will be 10 MT/Day including Azo- Di-
Carbonamide (ADC) to tune of 8.00 MT/Day and Di - Nitrosopenta Methylene
Teramine (DNPT) to tune of 2 MT/Day. Thus the annual manufacturing capacity will
be 3600.00 MTPA in 360 working days/year. The existing production capacity and
capacity after proposed expansion is tabulated below with their respective storage
capacities:-
S.
No. Name of Product
Production Capacity Storage Capacity
Existing After Expansion Existing After
Expansion
1. Azo-Di-
Carbonamide (ADC)
3.00 MT/Day
(1080.00 MTPA)
8.00 MT/Day
(2880 MTPA) 15.00 MT 20.00 MT
2.
Di - Nitrosopenta
Methylene Teramine
(DNPT)
2.00 MT/Day
(720.00 MTPA)
2.00 MT/Day
(720.00 MTPA)
10.00 MT 5.00 MT
Total 5.00 MT/Day
(1800.00 MTPA)
10.00 MT/Day
(3600.00 MTPA) 25.00 MT 25.00 MT
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 42 Authorized Signatory
3.7 Resource Optimization/ Recycling and Reuse envisaged in the Plant
The management of unit will work hard to optimize the resource utilization. The unit
will recycle the industrial process water to reduce the demand of daily fresh water.
The used solvent will be sold to authorized recyclers.
3.8 Availability of Water & source, Energy/ Power Requirement & Source
3.8.1 Power Demand & its Source
The power demand and D.G. sets of the unit in existing and proposed after expansion
is tabulated below:
Particulars Existing After Expansion
Power Demand 550 kVA 1000 kVA
D.G Set 1x320 kVA 1x320 kVA
1x380 kVA
H.S.D for DG Set
(As and when required)
64 ltr/hr. 140 ltr/hr.
Coal consumption 1 TPD 2 TPD
The power demand is being met from JVVNL and after the proposed expansion
power demand will be met from the existing AVVNL Connection. By using energy
efficient lighting arrangement, motors (85% efficiency) & power factor correction
equipments, consumption shall be minimized.
3.8.2 Water Demand & its Source
The existing water demand and demand after proposed expansion is given below:-
Particulars of Water Demand Water Requirement (KLD)
Existing After Expansion
Process & Washing Water 7.00 15.50
Water for Boiler 8.00 12.00
Water for Cooling Tower 20.00 30.00
Domestic Water 1.50 2.00
Daily Fresh Water 18.00 32.50
Daily Recycled Water 18.50 27.00
Total Water Demand 36.50 59.50
The water requirement for the project will be fulfilled RIICO water Supply/tanker
supply. The existing and proposed water balance for proposed project is given below:
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 43 Authorized Signatory
Recycled
water
18.50 KLD
Domestic Purposes
1.50 KLD
Consumption
0.50 KLD
1.00 KLD
Waste Water
Total Water Demand 36.50 KLD
Fresh water Demand 18.00 KLD
Recycled Water 18.50 KLD
Cooling Tower
20.00 KLD
Evaporation
Loss 1.00 KLD
Septic Tank
Followed by
Soak Pit
ETP
7.00 KLD
Solar Evaporation
4.20 KLD
Green Belt Development
2.00 KLD
Process, Washing and
Caustic Dilution
7.00 KLD
Blow Down
0.50 KLD
Boiler
8.00 KLD
Evaporation
Loss 0.50 KLD ADC Drying
1.00 KLD
Consumed in Steam
Purging
7.00 KLD
Waste Water
6.00 KLD
Sludge Loss
0.80 KLD
Blow Down
0.50 KLD
Existing Water Balance of Unit
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 44 Authorized Signatory
3.9 Waste Generation & Management
Liquid
Domestic Waste Water:
The unit is generating 1.00 KLD of domestic wastewater in existing operations and
after the proposed expansion the unit will generate 1.25 KLD of domestic waste
water. The waste water from domestic activities is being handled through existing
septic tank followed by soak pit. Same septic tank will be used after proposed
expansion also.
Evaporation
Loss 0.75
KLD
Proposed Water Balance of Unit
Recycled
water
27.00
KLD
Domestic
Purposes
2.00 KLD
Consumption
0.75 KLD
1.25 KLD
Waste
Water
Total Water Demand 59.50 KLD
Fresh water Demand 32.50 KLD
Recycled Water 27.00 KLD
Cooling Tower
30.00 KLD
Evaporation
Loss
2.00 KLD
Septic Tank
Followed
by Soak Pit
ETP
11.25 KLD
Solar Evaporation
3.95 KLD
Green Belt
Development
6.00 KLD
Process and
Washing
11.00 KLD
Blow Down
1.00 KLD
Boiler
12.00 KLD
ADC
Drying
2.00 KLD
Consumed in
Steam Purging
10.50 KLD
Waste Water
9.00 KLD
Sludge Loss
1.30 KLD
Blow Down
0.75 KLD
Caustic
Dilution
4.00 KLD
DNTP
Scrubber
0.50 KLD
Waste Water
0.50 KLD
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 45 Authorized Signatory
Industrial Waste Water:
In the current situation, the unit is generating 7.00 KLD of industrial effluent
wastewater. It is estimated that after the proposed expansion the unit will generate
11.25 KLD of industrial waste water. The waste water will be generated from ADC
processing and washing, DNTP scrubber, DNTP plant washing, blow down from
boiler and cooling tower. The steam from the boiler will be consumed in the
manufacturing process. This industrial waste water will be treated in existing ETP of
15KLD capacity.
Solid
The solid waste generated from the unit will Ash from boiler, Spent/Used Oil and
Sludge from the wastewater treatment process. The anticipated quantities of solid
waste is given below in table
Waste Category as per
HWMR rules
Quantity Disposal/
Management Existing
After
Expansion
Ash -- 10.00 Kg/Day 20.00 Kg/Day To Cement and Brick
Manufacturing Unit.
Spent/Used
Oil 5.1 300 Lit/Annum 600 Lit/Annum
Sold to Authorized
Recycler/End Users
ETP Sludge 34.3 4.00 MTPA 5.50 MTPA UCCI Udaipur
3.10 Schematic Representation of the feasibility drawing which give information
of EIA purpose
As per the EIA Notifications dated 14th
September, 2006, it is mandatory for the
proposed activity to get Environmental Clearance before setting any project or
expansion/ modernization of any project. The detailed chart delineating the process is
given in Figure-3.6.
The purpose of this Environmental Impact Assessment (EIA) study is to provide
information on the nature and extent of environmental impacts arising from the
operation of the project and related activities taking place concurrently. The study
also focuses on the sensitive issues. For the purpose of the EIA study, the impact zone
for the implementation shall confine within a radius of about 10 km from the center of
the project site.
The objectives of the EIA study are as follows:
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 46 Authorized Signatory
i) To describe the existing and proposed project and associated works together with
the requirements for carrying out the development.
ii) To establish the baseline environmental and social scenario of the project
surroundings.
iii) To identify and describe the elements of the community and environment likely to
be affected by the developments.
iv) To identify, predict and evaluate environmental and social impacts expected to
raise during the operation phase of the project in relation to the sensitive receptors
v) To develop mitigation measures so as to minimize pollution, environmental
disturbance and nuisance during construction and operations of the plant.
vi) To design and specify the monitoring and auditing requirements necessary to
ensure the implementation and the effectiveness of the mitigation measures
adopted.
In terms of the EIA Notifications of the MoEF dated 14th
September, 2006, the
generic structure of EIA documents shall be as under:
Introduction
Project description
Analysis of Alternatives (Technology & Site)
Description of the Environment
Anticipated Environmental Impact & Mitigation Measures
Environmental Monitoring Program
Additional Studies
Project Benefits
Environmental Cost Benefits Analysis
EMP
Summary & Conclusion
Disclosure of Consultant Engaged
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 47 Authorized Signatory
Figure 3.6: Showing the Process of Environmental Clearance Procedure
Yes
Yes
Decision of EIAA
Issuing Clearance to
project proponent
Whether any new
project/expansion/modernization
fall under the purview of schedule
Rejection
Category B?
Submission of application by proponent (Form-1, Pre- feasibility
report and Draft Term of Reference)
Scrutiny by SEAC
Scoping and communication of Term of Reference for EIA studies
to the proponent for EIA preparation
Submission of draft EIA /Summary EIA/ Application for Public
Consultation
Conducting Public Hearing by SPCB/PCC or any other public
agency/ authority engaged by regulatory authority
Submission of proceedings of the public hearing by the
SPCB/PCC to SEAC
Submission of final EIA by the proponent after improving EIA/
EMP
Appraisal by SEAC
Decision of SEIAA
IAA
Approval by SEAC
Reservation on the proposal conveyed to EAC
SEAC views on reservations sent to SEIAA
Specific Concerns
No Yes
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 48 Authorized Signatory
SECTION-IV
SITE ANALYSIS
4.1 Connectivity
The proposed site has well developed transport infrastructure.
Nearest Railway station: The nearest railway station is Alwar Railway
station which is at a distance of 9.50 km towards NNW.
Nearest Airport: Nearest airport is Sanganer Airport which is about 116.50
Km towards NE from site.
Nearest Highway: The nearest highway is NH 11 connecting Jaipur to Agra
in is at a distance of 55.80 km towards SSE of project site. MDR (Alwar –
Bharatpur) is at 2.75 Km towards NNE. The site is having well developed
road of RIICO Industrial area.
4.2 Land form, Land use and Land ownership
The land of total area 6000 Sq.m. has been allotted by RIICO to the unit. Land
allotment letter has been attached as Annexure III.
The plant site is located at Plot No. F-447, F-448 and F-449, Matasya Industrial Area,
Tehsil- Alwar (Raj.). The plant site is a flat land and land use surrounding the project
site mainly comprises of industrial and institutional settings.
4.3 Topography
The geographical location of the project is as under:
Geographical Location:
Latitude: 27°30'28.57"N
Longitude: 76°41'44.67"E
The study area is characterized by topography of more or less flat-topped hills, which
become predominant and precipitous in the southwestern parts of the district forming
the north continuation of the main Aravalli Ranges. The ridges of rocky and
precipitous hills for most part are parallel and are observable throughout the district.
The highest elevation of the study area is 300 MSL and the lowest elevation is 240
MSL. There is no perennial river within the study area. Although the District Alwar
has certain seasonal rivers including the Ruparel, Sabi, Chuhar, Sidh and Landoha,
which carry monsoon drainage from upland areas. The drainage pattern of study area
is tending towards east from the site. Jaisamand Lake is about 8.5 km towards south-
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 49 Authorized Signatory
west from the site and Hans Sarovar (lake) is about 6.8 km away from the site towards
East. In Alwar region agriculture is one of the sustaining activities and for good
agriculture the soil must be of very good quality. The region in general has a fertile
alluvial soil in almost all the areas outside the forest boundary where agriculture is
done and two to three crops have been taken by the farmers in a year. Nearly all types
of soils are found in this area viz. sandy, loamy, sandy-loamy and clayey.
The following types soil are found in area
Recent alluvium
Aravalli pediment
Fluvioaeolian
Soils of aravalli hills
Old alluvium
Figure : Soil composition of Alwar district
Source: ODP Report 1996, SPA
The above mentioned chart in figure 3.3 shows that the recent alluvium type of soil is the
most abundantly found soil in the district Alwar with 50 % share of the total type of soil
found in the area. While aravali pediment, soils of aravali hills, old alluvium and
fluvioaeolian soils are also found in the Alwar district.
4.4 Existing Land use Pattern
Study of land use in the area enables one to know about the land that can be used for
various development activities related with project. It also enables to envisage the
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 50 Authorized Signatory
future plans of expansion or new installation. The proposed land use of proposed
project as tabulated below:-
Description Area (Sq. m) % (Percentage)
Plant Area 4009 66.80
Road and Corridor 600 10.00
Green Belt Development 671 11.20
Open Area 720 12.00
Total 6,000 100
4.5 Existing Infrastructure
4.5.1 Water Supply
The existing water demand and demand after proposed expansion is given below:-
Particulars of Water Demand Water Requirement (KLD)
Existing After Expansion
Process & Washing Water 7.00 15.50
Water for Boiler 8.00 12.00
Water for Cooling Tower 20.00 30.00
Domestic Water 1.50 2.00
Daily Fresh Water 18.00 32.50
Daily Recycled Water 18.50 27.00
Total Water Demand 36.50 59.50
The water requirement for the project will be fulfilled from RIICO and tanker Water
supply
4.5.2 Power Requirement
The power demand and D.G. sets of the unit in existing and proposed after expansion
is tabulated below:
Particulars Existing After Expansion
Power Demand 550 kVA 1000 kVA
D.G Set 1x320 kVA 1x320 kVA
1x380 kVA
H.S.D for DG Set
(As and when required)
64 ltr/hr. 140 ltr/hr.
Coal consumption 1 TPD 2 TPD
The power demand is being met from JVVNL and after the proposed expansion
power demand will be met from the existing AVVNL Connection. By using energy
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 51 Authorized Signatory
efficient lighting arrangement, motors (85% efficiency) & power factor correction
equipments, consumption shall be minimized.
4.5.3 Connectivity
The proposed site has well developed transport infrastructure. The connectivity route
of site is listed below:
Nearest Railway station: The nearest railway station is Alwar Railway
station which is at a distance of 9.50 km towards NNW.
Nearest Airport: Nearest airport is Sanganer Airport which is about 116.50
Km towards NE from site.
Nearest Highway: The nearest highway is NH 11 connecting Jaipur to Agra
in is at a distance of 55.80 km towards SSE of project site. MDR (Alwar –
Bharatpur) is at 2.75 Km towards NNE. The site is having well developed
road of RIICO Industrial area.
4.6 Soil Classification
. In Alwar region agriculture is one of the sustaining activities and for good
agriculture the soil must be of very good quality. The region in general has a fertile
alluvial soil in almost all the areas outside the forest boundary where agriculture is
done and two to three crops have been taken by the farmers in a year. Nearly all types
of soils are found in this area viz. sandy, loamy, sandy-loamy and clayey.
The following types soil are found in area
Recent alluvium
Aravalli pediment
Fluvioaeolian
Soils of aravalli hills
Old alluvium
Figure Soil composition of Alwar district
Source: ODP Report 1996, SPA
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 52 Authorized Signatory
The above mentioned chart in figure 3.3 shows that the recent alluvium type of soil is the
most abundantly found soil in the district Alwar with 50 % share of the total type of soil
found in the area. While aravali pediment, soils of aravali hills, old alluvium and
fluvioaeolian soils are also found in the Alwar district.
4.7 Climatic Data from Secondary Sources
The climate of the study area is semi-arid and very hot in summer and extremely cold in
winter. The monsoon season is of very short duration. The cold season starts by the middle of
November and continues up to the beginning of March. The summer season follows thereafter
and extends up to the end of the June. The south-west monsoon continues from July to mid-
September. The period from mid-September to mid-November forms the post monsoon
season. The rainfall during the south-west monsoons constitutes about 80 % of the annual
rainfall. 577.7 mm is the annual average rainfall.
4.8 Social Infrastructure Available
The basic infrastructure study helps one to understand the level of service available to
the people of the area.
Infrastructure/ colonies:
The proposed project is located in industrial area which has many industrial unit and
institutional setting in periphery.
Water supply
The water supply from RIICO and tanker supply is available within the industrial
area.
Transport and Communication
Transport accessibility is one of the important factors required for the overall
development of the area. All the villages have roads and means of transportation to
the towns are by city bus and auto.
4.8.1 Market Facilities
Commercial activities form the backbone of the economy. The study tends to tell the
kind of employment it generates for the people of the area and the kind of services it
provides for the attainment of a better living. Table 4.3 shows the nearest town to
each village. The project is located in MIA RIICO Industrial Area Alwar. Alwar city
has wide market potential.
4.8.2 Health Facility
Health is one of the most important development indicators, which needs to be studied
to know the quality of life in the area. Health care infrastructure is one of its
components, which give us an idea about the facilities available to villagers, and what
are the secondary and tertiary level institutions where the villagers seek treatment.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 53 Authorized Signatory
SECTION-V
PLANNING BRIEF
5.1 Planning Concept (type of industries, facilities, transportation etc) Town and
Country Planning/ Development Authority Classification
The development of civilization is a continuous process. The invention of plastics
came as boon to mankind. Plastics are being used now days for making variety of
products and have entered in our day to day life of human being. The raw plastic is to
be mixed with various chemicals to increase its usage, moldable and blow-able
proprieties. The blowing agent is a chemical compound which under certain
conditions evolves into gaseous phase and thus used for manufacturing various foams
and sponges. Azo-di-carbonamide (ADC) and Di-nitroso-pentamethylene tetramine
(DNPT) is the most versatile blowing agent for various types of plastics and rubber
respectively. The blowing agents are used in various materials/ products such as shoe
sole, thermal insulation, Gaskets, Life jackets, Rexine cloths, Seat cushions, Package
filter, PVC compounds and Engineering plastics.
In view of this and seeing bright future of in the sector in country the management of
M/s Sri Dwarika Dheesh Polymers Pvt. Ltd. is proposing expansion of existing
industrial unit for manufacturing of Azo- Di- Carbonamide (ADC) and Di -
Nitrosopenta Methylene Teramine (DNPT), situated at Plot No. F-447, F-448 and F-
449, Matasya Industrial Area, Tehsil- Alwar (Raj.).
The site is having roads and means of transportation to the towns are by Bus, Auto
etc. Water requirement for the proposed project will be 59.50 KLD after the proposed
expansion. The source of water for the project will be RIICO water supply/tanker
supply. Power requirement for the proposed project will be 1000 kVA and two DG
sets of 320 kVA and 380 kVA having 140 Lit/hr HSD requirement.
5.2 Population Projection
The manpower requirement of the project is 20 workers. Hence, there will be no
change in the population projection of the nearest and farther most villages of the
project. There are 3 villages with in 2 Km radius of the proposed project. The
population in the study area is as follows:-
Population of the study area (10 Km.):-
Distances Villages Households Total Males Females
0-2 km
1 DESULA 849 4815 2635 2180
2 DHADOLI 194 1167 631 536
3 KAMALPUR 111 643 352 291
Distances Villages Households Total Males Females
2 km & above
1 AGYARA 103 648 345 303
2 BAGAR MEO 319 2215 1172 1043
3 BAGAR RAJPUT 414 2799 1465 1334
4 BAHALA 651 3707 1981 1726
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 54 Authorized Signatory
5 BALONDKA 186 1248 654 594
6 BAMBOLI 532 3902 2119 1783
7 BARAGAON 361 2777 1417 1360
8 BHATESARA 113 756 383 373
9 BELAKA 575 3438 1836 1602
10 BHUAHA 106 903 463 440
11 CHANDUKI 89 905 483 422
12 CHAPARARA 134 984 502 482
13 CHOROTI
PAHAR
327 2342 1238 1104
14 DADAH 82 659 313 346
15 DADAR 501 2809 1510 1299
16 DIWAKARI 1196 6870 3725 3145
17 DUMEHRA 156 1088 575 513
18 GANDRALA 972 5869 3034 2835
19 GHEHOLI 145 929 488 441
20 GUJOKI 248 1665 899 766
21 HALDINA 588 4113 2226 1887
22 INDIRAGARH 135 827 443 384
23 INTARANA 122 905 467 438
24 JATPUR 56 462 233 229
25 JHORERA 106 664 366 298
26 KAIRWARA 379 2542 1337 1205
27 KAKROLI 115 625 334 291
28 KAIMALA 196 1358 714 644
29 KAIRWA JAT 323 2353 1272 1081
30 KESROLI 215 1309 682 627
31 KHANPUR 75 526 277 249
32 KHERLI SAIYED 347 2370 1249 1121
33 LIWARI 252 1491 788 703
34 LOHARWARI 126 1204 591 613
35 MAHWA 134 1028 544 484
36 MANNAKA 213 1780 944 836
37 MINAPURA 168 1383 761 622
38 MAUJDI KA BAS 153 1124 599 525
39 MORERA 97 653 343 310
40 MUNDPURI 58 460 240 220
41 NAGLA CHORAN 91 599 329 270
42 NANGLI 321 2033 1037 996
43 PALAKA 87 593 312 281
44 RAIBKA 454 3085 1619 1466
45 SAHROLI 283 1918 999 919
46 SAIPUR 274 1831 963 868
47 SANKLA 90 492 269 223
48 TULERA 496 3938 2079 1859
Total 14,318 94,804 50,237 44,567
*Sources: Census of India, 2001
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 55 Authorized Signatory
There are 51 villages in the 10 Km periphery of the proposed study area with 14,318
households. The population of the study area is 94,804.
5.3 Land Use Planning
The green belt will be developed on about 671.00 Sq. m. of land. This is 11.20% of
the total land area (8000Sq. m.). A 2000 Sq. m. (33.33 % of the plant area) RIICO
Park, adjoining to the unit has been adopted for green belt development. Letter of
adaptation is attached as Annexure II.
The proposed land use break up of site is tabulated below:
Description Area (Sq. m) % (Percentage)
Plant Area 4009 66.80
Road and Corridor 600 10.00
Green Belt Development 671 11.20
Open Area 720 12.00
Total 6,000 100
5.4 Assessment of Infrastructure Demand (Physical and Social)
The urban cities including Jaipur are suffering from shortage of adequate and hygienic
living conditions. This has resulted in mushrooming of unauthorized colonies which
lacks basic amenities. The entire project has been master planned in a way, which
keeps a perfect balance between greens and open spaces with wide roads, landscaped
parks, and planned community living.
Social Demand
On the basis of the preliminary site visit, the infrastructure demand in the villages
assessed on the basis of need and priority. The PP proposes to support education
facility. He also aims for financial help in government schools. Facility for village
schools including classroom/ toilet construction, ceiling fans/ coolers or books for
school library.
The assessment will be identified in the socio economic survey, after grant of TOR
and will be submitted at the time final presentation regarding EC.
5.5 Amenities/ Facilities
The project site office, small workshop, first aid room, stack yard & rest shelter will
be established. Clean drinking water will be provided. The toilets will be provided
separately for males and females.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 56 Authorized Signatory
SECTION-VI
PROPOSED INFRASTRUCTURE
6.1 Industrial Area
The project is located in RIICO industrial area MIA Alwar which has many
industrial unit and institutional settings such as M/s Ajanta Polymers, M/s K.S. Jain
Polymers and M/s Green Field Industries etc.
6.2 Residential Area
As such no individual area is proposed in this project. Only rest room for workers will
be provided at site. The work force shall be put in the town nearby, which has all
facilities like water, power etc.
6.3 Green Belt
The green belt will be developed on about 671.00 Sq. m. of land. This is 11.20% of
the total land area (8000Sq. m.). A 2000 Sq. m. (33.33 % of the plant area) RIICO
Park, adjoining to the unit has been adopted for green belt development. Letter of
adaptation is attached as Annexure II. Increasing vegetation in the form of greenbelt is
one of the preferred methods to mitigate air pollution. Plants serve as a sink for
pollutants, act as a barrier to break the wind speed as well allow the dust and other
particulates to settle out there. It also helps to reduce the noise level to some extent.
The following species can be used in greenbelt development to serve as noise
breakers:
• Tectona grandis (Teak);
• Butea monosperma (Palash);
• Leucana leucocephala (Subabual);
• Mangifera indica (Aam); and
• Dalbergia Sissoo (Shisham).
6.4 Social Infrastructure (Corporate Social Responsibility)
The PP proposes the following permanent structures within a 10.0 km periphery of the
project.
The PP proposes to ambulance in the village area. The PP also
proposes medicines for water borne diseases especially for children.
Health camps will be organized for children. These children will be
examined for the water borne diseases and prescribed.
The proposed infrastructure will be further identified in the socioeconomic survey,
after the grant of TOR and will be submitted at the time of final presentation
regarding EC.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 57 Authorized Signatory
6.5 Connectivity
The proposed site is well accessible through railways and road transport.
Nearest Railway station: The nearest railway station is Alwar Railway
station which is at a distance of 9.50 km towards NNW.
Nearest Airport: Nearest airport is Sanganer Airport which is about 116.50
Km towards NE from site.
Nearest Highway: The nearest highway is NH 11 connecting Jaipur to Agra
in is at a distance of 55.80 km towards SSE of project site. MDR (Alwar –
Bharatpur) is at 2.75 Km towards NNE. The site is having well developed
road of RIICO Industrial area.
6.6 Drinking Water Management
The existing water demand and demand after proposed expansion is given below:-
Particulars of Water Demand Water Requirement (KLD)
Existing After Expansion
Process & Washing Water 7.00 15.50
Water for Boiler 8.00 12.00
Water for Cooling Tower 20.00 30.00
Domestic Water 1.50 2.00
Daily Fresh Water 18.00 32.50
Daily Recycled Water 18.50 27.00
Total Water Demand 36.50 59.50
The water requirement for the project will be fulfilled from RIICO and tanker Water
supply
6.7 Sewerage System
The unit is generating 1.00 KLD of domestic wastewater in existing operations and
after the proposed expansion the unit will generate 1.25 KLD of domestic waste
water. The waste water from domestic activities is being handled through existing
septic tank followed by soak pit. Same septic tank will be used after proposed
expansion also.
6.8 Industrial Waste Management
In the current situation, the unit is generating 7.00 KLD of industrial effluent
wastewater. It is estimated that after the proposed expansion the unit will generate
11.25 KLD of industrial waste water. The waste water will be generated from ADC
processing and washing, DNTP scrubber, DNTP plant washing, blow down from
boiler and cooling tower. The steam from the boiler will be consumed in the
manufacturing process. This industrial waste water will be treated in existing ETP of
15KLD capacity.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 58 Authorized Signatory
6.9 Solid Waste Management
The solid waste generated from the unit will Ash from boiler, Spent/Used Oil and
Sludge from the wastewater treatment process. The anticipated quantities of solid
waste is given below in table:
Waste
Category as
per
HWMR rules
Quantity Disposal/
Management Existing
After
Expansion
Ash -- 10.00 Kg/Day 20.00 Kg/Day To Cement and Brick
Manufacturing Unit.
Spent/Used
Oil 5.1
300
Lit/Annum
600
Lit/Annum
Sold to Authorized
Recycler/End Users
ETP Sludge 34.3 4.00 MTPA 5.50 MTPA UCCI Udaipur
6.10 Power Requirement & Supply/ Source
The power demand and D.G. sets of the unit in existing and proposed after expansion
is tabulated below:
Particulars Existing After Expansion
Power Demand 550 kVA 1000 kVA
D.G Set 1x320 kVA 1x320 kVA
1x380 kVA
H.S.D for DG Set
(As and when required)
64 ltr/hr. 140 ltr/hr.
Coal consumption 1 TPD 2 TPD
The power demand is being met from JVVNL and after the proposed expansion
power demand will be met from the existing AVVNL Connection. By using energy
efficient lighting arrangement, motors (85% efficiency) & power factor correction
equipments, consumption shall be minimized.
Prefeasibility Report M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Team Institute of Science and Technology M/s Sri Dwarika Dheesh Polymers Pvt. Ltd.
Authorized Signatory 59 Authorized Signatory
SECTION-VII
REHABILITATION AND RESETTLEMENT PLAN
7.1 Rehabilitation and Resettlement Plan
The project is proposed to come up at the land owned by promoters therefore no
displacement is involved and therefore rehabilitation and resettlement plan is not
required. The socio-economy of the area will be submitted in EIA report.
7.2 Project Schedule & Cost Estimates
Presently the project is only under planning stage & therefore likely date of starting
and completion is not been formulated. The construction activity will be started only
after obtaining EC. The schedule of construction and commissioning of
manufacturing facility will be formulated only after obtaining EC.
7.3 Analysis of Proposal (Final Recommendations)
Financial and Social benefits with special emphasis on the benefit to the local people
including tribal population, if any, in the area.
The project will cater the domestic market and it will add to revenue generation of the
district/state. It aims to provide additional employment to the local population of the
tehsil. The proposed project aims to fulfill its social sustainable responsibility though
promoting and maintaining permanent structures as follows:-
The PP proposes to ambulance in the village area. The PP also proposes
medicines for water borne diseases especially for children.
Health camps will be organized for children. These children will be examined
for the water borne diseases and prescribe medicines.
As per the preliminary site visit, the above activities were identified on the need based
requirement of the study area. Further activities will be analyzed, after the analysis of
the baseline data generation and socio- economic survey. Appropriate investment of
about Rs 65.00 Lac will be contributed for sustainable development of the area.