Section 106 Programmatic Agreement 2011-12 Annual Report (Covering the period May 4, 2011 through May 3, 2012) FINAL Prepared by: Cultural Resources Section, Bureau of Project Delivery Pennsylvania Department of Transportation December, 2012 For the: Federal Highway Administration, Pennsylvania Division Pennsylvania State Historic Preservation Officer Advisory Council on Historic Preservation

Upload: lymien

Post on 20-Dec-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Section 106 Programmatic Agreement

2011-12 Annual Report (Covering the period May 4, 2011 through May 3, 2012)

FINAL

Prepared by:

Cultural Resources Section, Bureau of Project Delivery Pennsylvania Department of Transportation

December, 2012

For the:

Federal Highway Administration, Pennsylvania Division Pennsylvania State Historic Preservation Officer

Advisory Council on Historic Preservation

2

Part 1

I. Executive Summary/Introduction On March 18, 2010, the Pennsylvania Department of Transportation (PENNDOT), the Federal Highway Administration (FHWA), the Pennsylvania State Historic Preservation Officer (SHPO), and the Advisory Council on Historic Preservation (ACHP) executed a program-wide Programmatic Agreement (PA) under Section 106 of the National Historic Preservation Act.

The PA applies to Federal-Aid projects; it does not cover State-funded projects under the Pennsylvania History Code or projects that are subject to Section 106 through a USACE Section 404 Permit.

The Agreement delegates certain decision-making authority from FHWA to two

PennDOT groups at two levels of review. PennDOT District environmental staff, called District Designees (DD) that have had basic Cultural Resource training may exempt from the regulatory Section 106 process certain projects that are not likely to have effects on historic resources. All other projects must be reviewed by PennDOT Cultural Resource Professionals (CRPs) who meet the qualification standards published in 36 CFR 61. CRPs have the authority to make exemptions and findings of eligibility and effect in most cases. Under Stipulation X.D of the PA, PennDOT is required to prepare an annual report on activities carried out under the PA, for submission to the FHWA, SHPO and ACHP. The report is to be submitted to the signatories of the PA within 30 days of the anniversary of the execution of the PA. PennDOT did not begin to implement the PA until May 4 of 2010. With the agreement of FHWA and the SHPO, PennDOT established the review year as beginning on May 4th, with the report to be due June 4th each year. This document summarizes activities between May 4, 2011 and May 3, 2012. Under Appendix C of the PA, 724 projects were exempted from further review by DDs and CRPs. PennDOT CRPs reviewed an additional 389 non-exempt projects, many of which had multiple findings. The SHPO raised 7 objections to findings made under the PA.

3

This annual report also summarizes concerns raised by the public and consulting parties on particular projects, and reports on the training provided by PennDOT in order that CRPs and DDs can maintain their delegation to review projects under the PA. II. Programmatic Agreement

The Section 106 Programmatic Agreement delegates certain responsibilities from FHWA to PennDOT for consultation with the SHPO and consulting parties for determining a project’s APE, for soliciting consulting parties, for making findings and determinations of National Register eligibility and project effect, for consultation with native Tribal organizations, and for initiating consultation on the resolution of adverse effects. The PA also allows PennDOT to exempt projects from review if they meet certain conditions. The SHPO has agreed to focus their reviews on projects that have adverse effects and certain projects with no adverse effects. In lieu of SHPO review of every project, PennDOT will make findings publicly available and standardize seeking consulting parties through the establishment of a public involvement clearinghouse. The PA also incorporates some streamlining and time-saving measures: electronic documentation and more use of forms rather than reports; application of agreed-upon standard treatments to reduce consultation; use of a Deferral of Archaeological Testing form instead of execution of project PAs when archaeology cannot be completed before NEPA approval; and, use of a Letter of Agreement (LOA) to reduce the number of required legal signatures on agreement documents.

A. Electronic Documentation – Preservation Pennsylvania and Indiana University of Pennsylvania (IUP) Partnerships

One of the goals of the PA was to create a transparent process by making documents and findings easily accessible to the SHPO, Tribes, consulting parties and the public. To that end, Project PATH (Pennsylvania Transportation and Heritage) was launched in November of 2010 and is hosted by Preservation Pennsylvania. CRPs upload documentation and generate notifications to SHPO, consulting parties, and potential consulting parties through Project PATH. PennDOT has continued to work in partnership with Preservation Pennsylvania to maintain and upgrade the system. One upgrade this year allows the SHPO to post a response directly into PATH.

Another partnership with Indiana University of Pennsylvania (IUP)

dedicates a server for PennDOT to store documents with sensitive

4

archaeological information. Initially, all documentation was uploaded to the IUP server prior to the launch of Project PATH. Currently, reports and other documentation containing archaeological site information are housed on the IUP server, which is accessible to agencies and consulting parties with a password. Forthcoming upgrades to Project Path will enable archaeological documents to be housed securely on Preservation PA’s server.

B. Training and Delegation under the PA

The PA contains a requirement that anyone reviewing projects must

receive periodic training in order to maintain delegation to make exemptions or findings. PennDOT District Designees and CRPs are required to receive an overview of the PA, and attend a Section 106 course. Refreshers are required on a designated schedule. In addition, DDs and CRPs must attend the PHMC’s Essentials courses- the Basics course for DDs, and all four courses (Basics, Applications, Best Practices, Forum) for CRPs.

Appendix A lists the current DDs and CRPs and the training they have

taken. These tables also show the due dates for the various training requirements.

For the DDs, many of the Environmental staff have had Section 106

training more than 5 years ago and the exact date is not known. The requirement for Section 106 training every 5 years was established under the PA. Anyone who has not had Section 106 training in the last five years has until the end of 2013 to complete this requirement. PA refresher training for DDs is due every two years. Using the date of initial training under the new PA as a baseline, PA refresher training is due this year. Training is expected to be provided at the upcoming Environmental Manager’s Meeting in June, and as a webinar shortly thereafter. PHMC Essentials training is due by 3/23/15 for most DDs.

PA refresher training for the CRPs is required on a yearly basis and is

usually accomplished during the annual summer meeting of the PennDOT Cultural Resource staff and consultant CRPs.

Between May 4, 2011 and May 3, 2012, the following courses were made

available to CRPs and DDs. Section 106 PA Refresher for CRPs – August 30, 2011 PHMC Essentials Basics and Applications – May 17, 2011

5

Completing Section 106 - Feb 6-7, 2012

C. Public Outreach - Workshops and Conferences

As part of its efforts to educate the public on Section 106 and their opportunities and rights to participate in the process, and as part of its contractual arrangement with PennDOT, Preservation Pennsylvania sponsored several workshops across the state. Preservation PA also made presentations on Project PATH at two out-of-state conferences. PennDOT and the SHPO actively participated in six of these seven workshops/ conferences by making short presentations and answering questions from the attendees relative to Project PATH and the statewide Section 106 PA. These workshops are one of the efforts to make the process transparent to the wider public.

Government 2.0: Online Innovations to Link People with Projects The Statewide Conference on Heritage - May 19, 2011, Harrisburg, PA Collect, Record, Interpret, Share, Rinse and Repeat—Best Practices in CRM in Transportation. Committee on Historic and Archaeological Preservation in Transportation (ADC50) Transportation Research Board Mid-Year Meeting - July 26, 2011, Portland Oregon Preserving Pennsylvania Communities

Lawrence County Historical Society – September 10, 2011, New Castle, PA A New Approach to Transportation and Preservation

PAEP Conference - September 22, 2011, State College, PA ProjectPATH: You Have a Voice!

Chester County Historic Preservation Network– October 8, 2011, Chadds Ford, PA Government 2.0: Online Innovations to Link People with Projects

National Preservation Conference – October 20, 2011, Buffalo, New York Preserving Pennsylvania Communities

Delaware County Planning Commission – February 11, 2012, Media, PA

6

III. Summary of Projects Reviewed under the PA

The data in this section is derived from three sources: PennDOT’s CE Expert System, Project PATH, and information provided by the CRPs. The CE Expert System contains information on projects exempted from review, including the individual who made the exemption. Project PATH provided most of the data on CRP findings/postings, disagreements/objections by the SHPO, and concerns of the public/consulting parties. District 6-0 contributed information on public/ consulting party concerns.

A. Exemptions

Appendix C of the PA contains a list of project activities that may be

exempted from further Section 106 review provided that the activities meet certain conditions. The activities on the list, with the conditions imposed, have low potential to effect historic properties. Appendix C is divided into two sections, the A list and the B list. Activities on the A list may be exempted by DDs or CRPs, those on the B list can be exempted only by CRPs. Between May 4, 2011 and May 3, 2012, 724 projects were exempted by DDs and CRPs. Appendix B shows the list of projects that were exempted.

The following table summarizes the number of exemptions for each District and who made the exemptions.

District Designee CRP TOTAL 1 9 13 22 2 6 30* 36 3 36 137 173 4 19 58 77 5 60 18 78 6 0 60 60 8 45 39 84 9 30 24 54

10 35 9 44 11 28 28 56 12 32 8 40

TOTAL 300 424 724

*One exemption made by PHMC for an Enhancement Project

7

In most Districts, exemptions were made both by CRPs and DDs. In District 6-0, the CRPs made all exemptions.

B. CRP Findings/Postings

Projects that did not qualify to be exempt under Appendix C were

reviewed by the CRPs. There were a total of 807 findings/postings associated with 389 projects made on Project PATH between May 4, 2011 and May 3, 2012. Appendix C of this report contains the list of findings/postings. Each finding or posting is standardized by category (Column I on the list) and was used to generate the statistics in the table below.

Early Coordination Activities Geomorphological Testing Scoping/APE/Project Notification

7

99 Identification/Determination of Eligibility 88 Determination of Effect

Number of Projects No Historic Properties Affected No Adverse Effect Adverse Effect Number of Individual or Combined

Findings

231 179 39 13

311

Public Involvement Consulting Party Consultation Tribal Consultation

66 93

Resolution of Adverse Effects – Consultation and Preparation of Agreement documents

47

Standard Treatment 6 Mitigation Commitment Coordination 25 PHMC Finding/Recommendation (TE

Projects) 26

Early Coordination Activities includes information from the Early

Coordination category as well as the Scoping categories on the list. For those projects where an immediate finding of No Historic Properties Affected cannot be made after scoping, an Early Notification/Scoping form is posted. Geomorphological testing is used to determine the age and integrity of the soils and the probability for archaeological sites. Note that PennDOT has

8

actually conducted more geomorphology studies than the seven instances reported under Early Coordination. These seven represent stand-alone reports. When the results of a geomorphology study indicate that there is potential for archaeological sites and an archaeological survey is conducted, the geomorphology report is incorporated into the archaeological survey report and is not listed separately in Project PATH.

The data for Determination of Effect are presented in two ways. The first

number - 231- represents the number of projects where a Determination of Effect was made. There was a total of 179 findings of No Historic Property Affected, 39 No Adverse Effect, and 13 Adverse Effect. It should be noted that there may be more than one effect finding for a project, for example, when the finding for Archaeology and Above-ground was made separately, or when the effect determination was re-evaluated due to a design change. This is reflected in the second number - 311 – and is the total number of effect determinations that were posted in Project PATH.

Under Public Involvement, the totals represent the number of postings

made, not the number of individuals or organizations contacted. Each posting was sent to a number of tribes, individuals, or organizations. For Tribal consultation, the number of postings may not represent the actual number of times tribes were contacted. The notification to tribes was recently automated in Project PATH; prior to April 30, 2012 tribal notifications have been generated outside of the PATH environment, and the dates of these notifications may or may not have been entered into PATH.

The use of Standard Treatments was recorded for 6 projects. In five

cases, the standard treatment involves the use of geotextile and fill to protect archaeologically sensitive areas during construction. Another standard treatment was applied to the Allegheny County South Highland Ave. Bridge Reconstruction project, where the bridge contributes to the Pennsylvania Railroad Mainline. Interpretive panels about the Pennsylvania Railroad Mainline will be installed on the bridge.

C. Disagreements/Objections by the SHPO

Seven disagreements or objections were raised by the SHPO to findings or determinations made by PennDOT’s CRPs. This represents 2% of the Eligibility or Effect findings made by the CRPs. Appendix D describes each objection/disagreement and how it was resolved.

9

Determination of Eligibility - The SHPO disagreed with 4 determinations of

eligibility made by PennDOT. In all cases, the SHPO disagreed with PennDOT’s determination that a property is eligible for the National Register. In the SHPO’s opinion, these properties are not eligible. PennDOT accepted the SHPO’s opinion.

Determination of Effect - Two objections were made by the SHPO to

PennDOT’s determination of effect. The SHPO disagreed with PennDOT’s finding of No Adverse Effect for the the following two projects: Lancaster County, Conestoga Creek Road Bridge (MPMS 19799), and Lancaster County, SR 741/2035 Intersection (MPMS 85656). In the SHPO’s opinion, these projects would have an adverse effect to properties eligible for the National Register. After further consultation on each project, the SHPO agreed with both findings of No Adverse Effect.

Bridge Feasibility Analysis – The SHPO raised concerns with a historic

bridge feasibility analysis for the Somerset County, Maust Bridge Project (MPMS 23057). This report is prepared as an aid in considering alternatives, prior to making a determination of effect. The Maust bridge is unaltered and is one of five remaining eligible truss bridges in the county. The feasibility report considered several alternatives and concluded that the bridge should be replaced. It is the opinion of the SHPO that the report does not adequately support the stated purpose and need for the project, and that the bridge should be held to a higher standard of consideration for rehabilitation because there are so few eligible truss bridges left in Somerset County. Consultation is ongoing.

D. Concerns of the Public/Consulting Parties

PennDOT has made an effort to seek comment from the public and

consulting parties primarily through Project PATH, paper correspondence, public meetings, and meetings with consulting parties, as appropriate. The interest of the public in historic preservation varies across the state. In the southeastern portion, the public has a keen interest in historic preservation, while in other areas there is less interest. The table in Appendix E summarizes concerns expressed by the public and consulting parties on particular projects, and how these concerns were, or are, being addressed. Information was obtained from the CRPs and from documentation posted to Project PATH.

10

Historic preservation concerns were raised by consulting parties and the public on 12 projects. The focus of these concerns primarily involves the replacement or rehabilitation of historic bridges. In 6 instances, concerns were expressed that the historic bridges will be replaced rather than rehabilitated. Feasibility analyses for these 6 projects concluded that the bridges cannot be rehabilitated. PennDOT received commentary on two projects regarding the

rehabilitation of historic bridges. In one case, the consulting party wanted to ensure that PennDOT adheres to the Secretary’s Standards for Rehabilitation; in the second case, some of the consulting parties expressed opposition to the rehabilitation of a stone arch bridge. Other types of issues raised by consulting parties/public included

disagreement with a determination of eligibility for Pennypack Park. There was also concern with PennDOT’s proposed removal of a former church building for an intersection project, although it no longer functions as a church and has been determined not eligible because of extensive alteration. Lastly, specific recommendations for resolving adverse effect were proposed by a consulting party, some of which were incorporated into the MOA.

IV. Comments of Signatories on Part I of the Annual Report

In June of 2012, Part 1 of this report was circulated to the FHWA, the ACHP, the SHPO, and PennDOT Environmental Units for review and comment.

Written comments were received from FHWA and Matt Hamel of District 3-0. V. Part I Conclusions During the second year of operation under the Section 106 PA, over 1000 projects were considered under Section 106, of which 65% were exempted. Of the remainder, the CRPs made 88 Determinations of Eligibility, and there were 231 projects for which the CRPs made a Determination of Effect. In the latter category, 179 were findings of No Historic Properties Affected, 39 were No Adverse Effect, and 13 were Adverse Effect.

11

Seven objections/disagreements were raised by the SHPO. All have either been resolved, or consultation is in progress toward resolution. Consulting parties and the public raised concerns on 12 projects. PennDOT is working with these parties to consider their comments.

Several training opportunities were provided to the DDs and CRPs to help fulfill training requirements. In keeping with the intent to operate in a transparent manner, PennDOT and Preservation PA have continued to work in partnership to maintain and upgrade Project PATH, and to provide educational opportunities for the public and potential consulting parties on Section 106.

12

Part 2 Part 2 of the report summarizes the results of the annual review conducted by the signatories of the Section 106 PA, per Stipulation X.E, reports on progress made on the follow-up actions from the last annual review, and makes recommendations for improving the process. I. Results from the Annual Review Meeting (ARM)

Attendees: Carol Legard, ACHP (via conference call); Deborah Suciu Smith, FHWA; Doug McLearen, PHMC; Jean Cutler, PHMC; Kira Heinrich, PHMC; Barbara Frederick, PHMC; Ira Beckerman, PennDOT; Kara Russell, PennDOT; Chris Kula, PennDOT. On October 19, 2012, the signatories to the Section 106 PA met to review the performance of the second year of operation under the PA. Prior to the meeting, a randomly selected sample of projects from Districts 2, 4, and 10 were reviewed by representatives from PennDOT and the SHPO. The Districts were selected based on FHWA’s schedule for reviewing NEPA Categorical Exclusions that have been delegated to PennDOT. The projects were selected from findings of effect and exemptions that were made between May 4, 2011 and May 3, 2012. Review forms contained a list of questions focusing on decision-making, consultation, and documentation by the PennDOT Cultural Resource Professionals (CRP) and District Designees (DD). A maximum of 20 projects was targeted for review in each District, five each of Exemptions, No Historic Properties Affected, No Adverse Effect, and Adverse Effect findings. Generally, there were less than five No Adverse Effect and Adverse Effect findings per District. During the ARM, the signatories discussed the results of the SHPO/PennDOT review, and developed a list of questions on specific projects. A phone call was held with each District to discuss general observations and to request additional information or clarification on individual results. Information provided by the Districts is shown in italics.

A. Review of District 2-0

District Attendees: Rob Weed – Environmental Manager, Scott Shaffer - CRP, Matt Hamel - CRP

13

5 Exemptions, 3 findings of No Historic Properties Affected and 2 No Adverse Effect findings were reviewed. There were no findings of Adverse Effect made by District 2-0 during this annual review period. In general, District 2-0’s application of the PA is good. There is good coordination between Matt Hamel and Scott Shaffer. The exemptions made by the District were appropriate. MPMS 83253 - SR 1021 Cowanesque Rv III A question was raised about the proposed temporary construction easements. There was no indication either in the CE or the Archaeology finding that either geotextile would be used to protect these areas, or that these areas are disturbed. Scott Shaffer responded that there is documentation in the project file that the temporary construction areas are disturbed. MPMS 4758 - Bridge over Allegheny River, MPMS 78994 SR 322 Safety Improvement and MPMS 2933 Penns Creek Road Bridge District 2-0 was asked about the timing of tribal consultation. Tribal consultation was initiated rather late in the process, when the Archaeology report was posted on Project PATH with the effect finding, rather than after project scoping. Scott Shaffer answered that oftentimes, it is not clear whether an Archaeological investigation will be needed because a definitive scope of work for the project is not known until later in project development. By that point, notification can become a time management issue. Scott suggested that tribes may prefer to be notified later in the process, when something is found. ACHP and PennDOT guidance strongly recommends that consultation begin early in the project, however, Carol stated that if the tribes request to be notified later, we should follow their wishes. It was concluded that PennDOT/FHWA should follow up by asking each of the tribes their preference as to when they would like to receive initial notifications. MPMS 81515 – Jacks Creek Bridge The reviewers raised three questions. 1) Were Tribes contacted? There was no evidence of this in the documentation. 2) What was the effect finding for Archaeology and for the project? The documentation for Archaeology indicates both a No Effect and No Adverse Effect, and on Project PATH’s Project Details page, a No Effect finding for the project is checked. 3) Is there a need for

14

geotextile and fill? The use of protective geotextile and fill was not mentioned in the Archaeology documentation but was specified in the CEE. 1) Six tribes were consulted, but the documentation is in the District’s project files. This consultation occurred prior to the availability of electronic tribal forms on Project PATH. 2) The project finding is No Effect. At the time the finding was made the CRPs were still learning the Project PATH system and the electronic forms. 3) Earlier in the project, it was uncertain whether geotextile and fill would be necessary. As the project was designed, no geotextile and fill was needed. The District forgot to remove the statement from the CE document. MPMS 2933 – Penns Creek Road Bridge 1) The documentation neglected to discuss whether the bridge, while not individually eligible, contributes to the eligible rural historic district. Also missing was a discussion of how the new bridge would/would not affect the rural historic district. Matt Hamel responded that the bridge does not contribute to the historic district. 2) The project description in the CEE mentions the need for geotextile and fill for a causeway. This is not discussed in the Archaeology finding or in the CEE on the cultural resources or mitigation pages. The District responded that as the project design progressed, it was determined that geotextile and fill would not be needed. Reference to its use was inadvertently left in the project description. MPMS 92521 – Coalport Streetscape (Enhancement Project) What is the effect finding for the project? The Project Details page in Project PATH indicates a finding of No Adverse Effect, but the documentation shows a finding of No Historic Properties Affected. The District responded that the finding was No Historic Properties Affected. There was a short discussion requesting, in general, that Matt Hamel provide more justification when a project finding is No Adverse Effect. Conversely, if

15

there really is not effect then be less conservative and make a finding of No Historic Properties Affected rather than No Adverse Effect. MPMS 92530 – Monument Square Phase IV Cheryl Nagle of PHMC is listed in the environmental document (BRPA) as making an exemption for this project. There was also an effect finding prepared by Cheryl and the CRPs with inconsistent effect determinations. The District responded that there were many phases of funding for this project and initially, Cheryl was reviewing a submission under Dept. of Agriculture for a DCNR permit. The District used PHMC’s letter from that review. Cheryl should not have made the exemption in the BRPA. Matt Hamel attributed the inconsistency in marking the check boxes for the effect finding to learning the new system. B. Review of District 4-0 District Attendees: Greg Augustine – Environmental Manager, Kevin Mock - CRP, Kris Thompson - CRP 4 Exemptions, 5 findings of No Historic Properties Affect, 5 No Adverse Effect findings, and 3 findings of Adverse Effect were reviewed. District 4-0’s application of the PA is good. The CRPs Kevin Mock and Kris Thompson were cited as doing a good job. The exemptions made by the District were appropriate. The reviewers noted several projects (MPMS 9419, 9700, 68862) where there continues to be confusion over whether the projects are State-funded or Federally-funded. Under the Section 106 PA, FHWA is only responsible for those projects with federal funding. The District responded that project funding is fluid throughout the design process. Some projects are designed with state funds with the anticipation of federal funds later. There is inconsistent coding in MPMS regarding funding sources for these candidate projects.

16

MPMS 67522 – Middle Wyalusing Creek Bridge Replacement Use of geotextile and fill for the temporary bridge is noted in the Archaeology effect finding but not in the environmental document (BRPA). The District noted that there is paper documentation in the file that geotextile and fill will be used. There are some issues with incorrect information coming over from the scoping form and not being corrected later. MPMS 77378 – White Haven Engine House Project (Enhancement Phase II) This project has two phases. It appears that consulting party consultation was completed for Phase I but it is unclear whether consultation occurred for Phase II of the project. Consultation for Phase II of the project – geothermal wells – was done and has now been populated in Project PATH. Phase I Archaeology was completed before Project PATH was in effect. MPMS 9165 – County Rd. 16 Bridge Replacement Incorrect documentation in Project PATH led to confusion on the part of the reviewers. The finding for Archaeology appeared to be missing. The District has since posted the appropriate documentation for this project on Project PATH. The finding for Archaeology was included in the Determination of Effects report. MPMS 7838 – Harrison Avenue Bridge Archaeology was cleared as part of the effect report for historic structures and it was not evident whether an Archaeologist looked at this project. The SHPO requested that the CRP fill out the Archaeology Assessment and Finding form in the future. The District Archaeologist did look at the project and determined that no Archaeology was needed. There is a memo in the paper file. MPMS 9580 – New Milford RR Bridge Replacement PennDOT proposed a No Adverse Effect and SHPO disagreed. PennDOT accepted the SHPO’s opinion of adverse effect but there is a gap in the documentation between the determination of adverse effect and the LOA. What was the role of consulting parties?

17

The District responded that a bridge feasibility study was completed, consulting parties were solicited, and a consulting party meeting was held on resolving adverse effects. This information was inadvertently omitted from Project PATH and has since been added. MPMS 64824 – Wangum Bridge #29 1) Although there is evidence that there was consulting party consultation, it is difficult to track in Project PATH. The SHPO and PennDOT reviewers noted that this generally seems to be a problem for projects with adverse effects that have consulting parties. Kris Thompson responded that the history of consultation is in Project PATH but not organized in a way that is useful. Where should e-mails and written responses be posted? Changes are needed in the PATH system to better capture the history and content of consultation. PennDOT Central Office has noted this as a follow-up action. There has already been discussion 2) Who in the District reviewed this project for Archaeology? There is only a brief statement in the historic structures Determination of Effect report but does not indicate who determined that Archaeological studies were not needed. This is similar to the way Archaeology was handled under MPMS 7838 and 9165. See commentary under these projects. C. Review of District 10-0 District Attendees: Eric Buchan – Environmental Manager, Susanne Haney - CRP, Jonathan Daily - CRP 5 Exemptions, 5 findings of No Historic Properties Affected and 1 Adverse Effect findings were reviewed. There were no findings of No Adverse Effect made by District 10-0 during this annual review period. In general, the application of the 106 PA by the CRPs and DDs was good. There is good coordination between Susanne Haney and Jonathan Daily. With one exception, all of the exemptions were correctly applied. MPMS 78111 – Cherry Tree Bridge #1

18

The project, a superstructure replacement, was exempted by the DD but should have been exempted by the CRP. The A.4 exemption is limited to rehabilitation, not a complete superstructure replacement. The District Designee misunderstood the exemption and thought superstructure replacement was included in the A.4 exemption. MPMS 24861 – T-300 Graham Bridge, MPMS 83350 – Harrisville Bridge, and MPMS 89966 – Spur Run Bridge The CRPs appear to be taking a conservative approach and prepared an effect finding for each of these projects. Based the project descriptions, they appear to be eligible for an exemption. Susanne Haney responded that in each case, there was enough new right-of- way required to make the project ineligible for exemption. MPMS 24861 – T-300 Graham Bridge The effect finding stated that the 1983 bridge was evaluated as not eligible in the Historic Bridge Survey. However, the cutoff date for the survey was 1956. This is a typo. The bridge was built in 1938. It is not eligible for the National Register. MPMS 77912 – Cochran’s Mill No. 1 This project has an Adverse Effect and it appears that there was not an extensive effort made to solicit consulting parties. Some obvious organizations, such as the Historic Bridge Foundation, appear not to have been notified. Were any other groups solicited? The District responded that more organizations were solicited than are documented in Project PATH. Some of the records are in paper files.

II. General Commentary on the Performance of the Section 106 PA A portion of the ARM focused on discussion of more global issues related to the implementation of the PA. These fall into two main categories, consultation with consulting parties, and consideration of historic bridges including PennDOT’s historic bridge management plan for truss bridges.

19

A. Consultation with Consulting Parties While it is obvious that PennDOT is soliciting for consulting parties, it is not always clear how PennDOT is responding to consulting party comments. Project PATH is a tool for soliciting consulting parties and providing information, but it is not consultation, per se. Consultation is a dialogue. Carol feels that PennDOT can do a better job of demonstrating how the comments of consulting parties are considered by ensuring that we do respond, and also by posting these responses on Project PATH. It was pointed out during the review that it would be helpful to make upgrades to PATH so that consulting party comments and responses are better organized. B. Truss Bridge Management Plan There continues to be concern among historic preservation groups and individuals about the loss of historic bridges, and a perception among some consulting parties that PennDOT is not taking their views and comments into consideration. PennDOT is continuing to develop a statewide management plan for truss bridges. One goal of the plan is to move the evaluation of whether it is feasible to rehabilitate a truss bridge from Section 106 to project planning prior to NEPA/106. Currently, by the time the projects get to NEPA/106, it is generally too late to consider rehabilitation rather than replacement. This has contributed to some of the frustration consulting parties feel at being unable to have any influence in the consideration of alternatives to replacement. Carol requested to review a copy of the management plan when it is available. C. Review of Follow-up Actions from 2011 ARM

During the 2011 ARM, a number of follow-up actions were proposed by PennDOT to improve both the process and the forms used to review individual projects for the ARM. These are listed in the table below, which includes a status on the progress of each item (Status in yellow). The list was briefly reviewed during the 2012 ARM.

20

Item Deliverable A field will be added for recording the presence of historic properties in the APE

Revised Forms.

In the section on Consultation, PennDOT will revise and reorder the questions to 1) ask the question “Did consultation with Tribes/Nations/ Consulting Parties/ Public occur at the appropriate time in the Section 106 Process?,” separately of the tribes/nations and the consulting parties/public; and 2) regroup the questions so that all questions pertaining to tribal consultation are together, and the same with questions pertaining to the public/consulting parties An optional field will be added to the project information section that will allow the inclusion of a project history PennDOT will review the questions and add other response choices (e.g. N/A or Undetermined) where appropriate

Forms were revised. PennDOT will explore a mechanism for automating the inclusion of project information on the forms in order to reduce the time spent by the reviewers in filling out the forms

Project PATH report to Excel of required fields and Word Forms files with data merge fields.

Working with Preservation PA, a Word merge form was created that inputted some of the project information. This form was used in the 2012 review. Consulting Parties

On a case-by-case basis, PennDOT, in consultation with FHWA, will consider the use of mediation experts when there are difficult consulting parties or contentious issues. The technique should be added as an option in PennDOT Publication 295 – Public Involvement Handbook and Publication 689 – Cultural Resources Handbook.

Strike-off Letter for Pub 295. Check for next Pub 295 revision date. Put language in Pub 689 revision.

For projects where there are contentious issues or a lot of public interest, PennDOT, will consider increasing the number of consulting party meetings or other opportunities for consultation. Meetings could be held to correspond with the steps in the Section 106 process, or at other appropriate times in project development.

Strike-off Letter for Pub 295. Check for next Pub 295 revision date. Put language in Pub 689 revision.

Wording is being added to the CR Handbook; however Pub 295, the Public Involvement Handbook is not due for an update at this time.

PennDOT will explore the availability of training courses or workshops on effective interaction with the public and will inform project managers and the CRPs of training opportunities. PennDOT has identified a course offered by the National Preservation Institute on conflict resolution for cultural resources, and is planning to bring this training to Pennsylvania in the spring of 2012.

Conflict Resolution Class scheduled in Training Calendar. Set for August in District 6-0.

A workshop was offered in District 6-0 in August 2012. Bridge Management Plan

PennDOT will continue with the development of a management plan for truss bridges.

Management Plan and associated white paper.

PennDOT continues to work on a management plan. A draft plan is in internal review. Improving MOA’s

PennDOT will incorporate more explicit wording into stipulations regarding context sensitive solutions. This would be intended to produce better designs that consider context on a case-by-case basis, rather than contributing to rote decisions.

Provide expanded guidance in Pub 689.

21

This has proven to be very difficult. Unless very precise direction is provided, final design will largely ignore guidance. If very precise direction is provided in preliminary engineering, it is likely going to be unworkable in final design. Ultimately, better training on aesthetics for all civil engineers in college is needed. Exemptions

PennDOT will add clarification in the Cultural Resources Handbook that if a culvert is not exempt under PA Stipulation 2.b.1.a, the CRP must make a finding.

Revision to Pub 689.

The CR Handbook is being revised.

III. New Follow-up Actions Based on the observations of the PennDOT/SHPO project review team, and the discussion among the PA signatories during the ARM, several new follow-up actions were identified.

- In regards to the timing of consultation with Tribes, PennDOT and FHWA will ask each of the Tribes their preference as to when they would like to receive initial project notifications.

- PennDOT will provide Carol Legard with a copy of the draft Truss Bridge

Management Plan when it is available.

- PennDOT will discuss with Preservation PA possible changes to Project PATH that would make the history of consultation easier to follow.

- PennDOT will remind the CRPs of the importance of responding to consulting

parties who provide comments, that Project PATH is a tool for soliciting consulting parties and for posting comments and responses but is not a substitute for consultation.

- The SHPO is recommending more regular meetings to discuss other non-

project specific issues related to the program.

IV. Part 2 Conclusions

The review of PennDOT’s performance under the terms of the statewide Section 106 PA indicates that, in general, PennDOT CRPs and DDs are applying the PA according to the stipulations. Individual exemptions and effect findings made by Districts 2, 4 and 10 were reviewed. Although there were individual findings associated

22

with specific projects that necessitated follow-up or clarification, the implementation of the PA appears to be consistently and accurately applied. Follow-up actions identified during the 2010-11 ARM with the signatories were reviewed. PennDOT has made progress on several of the items targeted for improvement. A few new follow-up activities have been proposed based on the current ARM results. Consultation with consulting parties continues to be an area where PennDOT can improve. PennDOT will focus on documenting consultation with consulting parties and ensuring that there is a dialogue when concerns are raised. To address the concerns of many consulting parties on the replacement of historic bridges, PennDOT will continue to develop a historic truss bridge management plan that will include evaluating the feasibility of rehabilitation early in project planning prior to NEPA or Section 106.

23

Appendix A Training Lists for District Designees

And Cultural Resource Professionals

District

Employee Intro to 106 ( Every 5 years)Section 106

Date

Section 106

Due (Every 5

Years)

PA Overview

PA Overview

Due

( Every 2 years)

CR EssentialsEssentials Due

(Every 5 Years)Active

1 Kelly, Autumn 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

1 W olfgong, Chris Section 106 in the New Regulatory Environment 2/8/2006 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

2 W eed, Rob 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

2 W ard, Rick 12/31/2013 4/23/2010 12/31/2012 4/23/2015 YES

2 Peacock, Chris 12/31/2013 4/23/2010 12/31/2012 4/23/2015 YES

2 Stojek, Mary Beth Section 106 in the New Regulatory Environment 3/20/2007 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

2 Kinback, Jerry Section 106 in the New Regulatory Environment 5/12/2008 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

3 Franzen, Luke 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

3 Bunce, Kyle 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

3 Kennedy, Ray 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

4 Amy Lolli 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

4 Greg Augustine 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

4 Thomas Raskiewicz 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

5 Bruch, Steven

Section 106 Principles and Practice Completing

Section 106

10/20/2010

2/6 & 2/7 201212/31/2017 3/23/2010 12/31/2012 5/18/2010 5/18/2015 YES

5 Ruth, Jim Completing Section 106 2/6 & 2/7/2012 12/31/2017 3/23/2010 12/31/2012 5/18/2010 5/18/2015 YES

5 Neal, Jerry 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

5 Valesquez, Jose 12/31/2013

6 Eppley, Bob 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

6 Fischer, Dave 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

6 Radatti, Mark Section 106 Principles and Practice 10/20/2010 12/31/2015 3/23/2010 12/31/2012 5/18/2010 5/18/2015 YES

8 Aker, Judith 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

8 Sabitsky, Jesse Section 106 in the New Regulatory Environment 2/21/2007 12/31/2013 3/23/2010 12/31/2012 5/17/2011 3/23/2015 YES

8 Lightcap, Jay 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

8 Snyder, Terry 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

8 Okin, Sharon Completing Section 106 2/6 & 2/7 2012 12/31/2017 3/23/2010 12/31/2012 3/23/2015 YES

9 Yocum, Tom Section 106 in the New Regulatory Environment 3/20/2007 12/31/2013 3/23/2010 12/31/2012 5/17/2011 3/23/2015 YES

9 Cassarly, Bob Section 106 in the New Regulatory Environment 5/12/2008 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

9 Chestney, Jamie 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

9 McClellan, Sarah 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

9 Squillario, Attilio Section 106 in the New Regulatory Environment 2/8/2006 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

10 Buchan, Eric 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

11 Crouch, Todd Section 106 Principles and Practice 10/20/2010 12/31/2015 3/23/2010 12/31/2012 5/18/2010 5/18/2015 YES

11 Krobot, Nick Section 106 Principles and Practice 10/20/2010 12/31/2015 3/23/2010 12/31/2012 5/18/2010 5/18/2015 YES

11 Young, Mark 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

11 Kronz, George 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

12 Ansell. Kim 12/31/2013 3/23/2010 12/31/2012 3/23/2015 YES

ckula
Cross-Out

NamePA Overview

(Yearly)

PA Overview/

Refresher Active Comments

Ammerman, Jeremy 12/16/2010 8/30/2011 YES

Anthony, David 2/23/2010 8/30/2011 YES

Baker, Joe 2/23/2010 8/30/2011 YES

Beckerman, Ira 2/23/2010 8/30/2011 YES

Daily, Jonathan 2/23/2010 8/30/2011 YES

Hamel, Matt 2/23/2010 8/30/2011 YES

Haney, Susanne 2/23/2010 8/30/2011 YES

Harrower, Monica 2/23/2010 8/30/2011 YES

Knapp, Rebecca 5/4/2010 8/30/2011 YES

Kula, Chris 2/23/2010 8/30/2011 YES

Mock, Kevin 2/23/2010 8/30/2011 YES

Rowles, Ryan 2/23/2010 8/30/2011 YES

Russell, Kara 2/23/2010 8/30/2011 YES

Shaffer, Scott 2/23/2010 8/30/2011 YES

Spohn, Catherine 2/23/2010 8/30/2011 YES

Thompson, Kris 2/23/2010 8/30/2011 YES

Verbka, Joe 2/23/2010 8/30/2011 YES

c- Alfson, Mary 2/23/2010 8/30/2011 YES

c- Benack, Lisa 2/23/2010 8/30/2011 YES

c- Cabot, Susan 3/12/2010 8/30/2011 YES

c- Clouse, Jerry 2/23/2010 8/30/2011 YES

c- Gundy, Barb 3/12/2010 8/30/2011 YES

c- Joanne Keim 3/12/2010 8/30/2011 YES

c- Peters, Susan 3/12/2010 8/30/2011 YES

c- Shaffer Barb 4/27/2010 9/27/2011 YES

c-Steve Barry 3/12/2010 9/27/2011 YES

c-Bob Eiswert 3/12/2010 8/30/2011 YES

Name

Essentials -

CR Basics

( Every 5 Years)

Essentials -

CR Applications

( Every 5 Years)

Essentials -

CR Forum

(Every 5 Years)

Essentials - CR

Best Practices

(Every 5 Years)

Essentials Group

Due

Ammerman, Jeremy 5/17/2011 5/17/2011 12/16/2015

Anthony, David 2/23/2015

Baker, Joe 2/23/2015

Beckerman, Ira 3/5/2008 11/5/2009 2/23/2015

Daily, Jonathan 3/5/2008 11/14/2008 5/19/2009 2/23/2015

Hamel, Matt 5/18/2010 11/10/2010 5/20/2010 2/23/2015

Haney, Susanne 3/5/2008 11/14/2008 &

5/17/201111/5/2009 5/19/2009 2/23/2015

Harrower, Monica 3/5/2008 11/13/2008 11/10/2010 2/23/2015

Knapp, Rebecca 5/18/2010 5/19/2010 11/10/2010 5/20/2010 5/20/2015

Kula, Chris 5/17/2011 5/17/2011 2/23/2015

Mock, Kevin 3/5/2008 5/19/2010 11/10/2010 5/20/2010 2/23/2015

Rowles, Ryan 2/23/2015

Russell, Kara 11/5/2009 2/23/2015

Shaffer, Scott 5/18/2010 5/19/2010 2/23/2015

Spohn, Catherine 3/5/2008 11/13/2008 11/5/2009 5/19/2009 2/23/2015

Thompson, Kris 5/18/2010 11/14/2008 5/20/2010 2/23/2015

Verbka, Joe 5/17/2011 5/17/2011 11/10/2010 2/13/2015

c- Alfson, Mary 5/18/2010 5/19/2010 11/10/2010 5/20/2010 2/23/2015

c- Benack, Lisa 5/18/2010 5/19/2010 11/10/2010 5/20/2010 2/23/2015

c- Cabot, Susan 3/5/2008 11/13/2008 11/5/2009 5/19/2009 2/23/2015

c- Clouse, Jerry 2/23/2015

c- Gundy, Barb 5/18/2010 5/19/2010 11/5/2009 5/20/2010 2/23/2015

c- Joanne Keim 2/23/2015

c- Peters, Susan 3/5/2008 11/13/2008 11/5/2009 5/19/2009 2/23/2015

c- Shaffer Barb 5/15/2010 5/19/2010 11/5/2009 5/20/2010 2/23/2015

c-Steve Barry 3/5/2008 5/17/2011 2/23/2015

c-Bob Eiswert 5/17/2011 2/23/2015

Name Section 106 106 Date

Section 106

(Every 5 Years)

Due By

Ammerman, Jeremy Completing Section 106 2/6 & 2/7 2012 12/16/2015

Anthony, David Advanced Section 106 12/2/2009 2/23/2015

Baker, Joe ? 2/23/2015

Beckerman, Ira ? 2/23/2015

Daily, Jonathan Advanced Section 106 12/2/2009 2/23/2015

Hamel, Matt

Section 106 Principles and Practices

Advanced Section 106

2/5 & 2/6/2002

12/2/2009 2/23/2015

Haney, Susanne Section 106 in the New Regulatory Environment 3/20/2007 2/23/2015

Haney, Susanne Advanced Section 106 12/2/2009

Harrower, Monica Advanced Section 106 12/2/2009 2/23/2015

Knapp, Rebecca Section 106 Principles and Practices 10/20/2010 10/20/2015

Knapp, Rebecca Completing Section 106 2/6 & 2/7 2012

Kula, Chris Section 106 in the New Regulatory Environment 2/8/2005 2/23/2015

Kula, Chris Advanced Section 106 12/2/2009

Mock, Kevin Section 106 in the New Regulatory Enviroment 5/12/2008 2/23/2015

Mock, Kevin Advanced Section 106 12/2/2009

Rowles, Ryan Section 106 in the New Regulatory Environment 5/12/2008 2/23/2015

Rowles, Ryan Advanced Section 106 12/2/2009

Russell, Kara Advanced Section 106 12/2/2009 2/23/2015

Shaffer, Scott Advanced Section 106 12/2/2009 2/23/2015

Shaffer, Scott Completing Section 106 2/ 6 & 2/7 2012

Spohn, Catherine Advanced Section 106 12/2/2009 2/23/2015

Thompson, Kris Section 106 in the New Regulatory Environment 5/12/2008 2/23/2015

Thompson, Kris Advanced Section 106 12/2/2009

Verbka, Joe Completing Section 106 2/6 & 2/7 2012 2/23/2015

c- Alfson, Mary ? 2/23/2015

c- Benack, Lisa ? 2/23/2015

c- Cabot, Susan Section 106 in the New Regulatory Enviroment 2/21/2007 3/12/2015

c- Cabot, Susan Completing Section 106 2/6 & 2/7 2012

c- Clouse, Jerry ? 2/23/2015

c- Gundy, Barb Section 106in the New Regulatory Environment 2/6/2002 3/12/2015

c- Joanne Keim Section 106 in the New Regulatory Enviroment 5/12/2008 3/12/2015

c- Peters, Susan Section 106 Principles and Practice 10/20/2010 3/12/2015

c- Shaffer BarbNHI - Beyond Compliance: Historic Preservation in

Transporation Project Development Dec-10 4/27/2015

c-Steve Barry Advanced Section 106 Nov. 09 3/12/2015

c-Bob Eiswert Section 106 2000 3/12/2015

29

Appendix B List of Exemptions

DB District County SR Sec MPMS Project Exempt Proj Activities Stip C Activities Exemption Maker Date Comments Type Package Status

Main 1 Venango 4008 B00 58276 McCune Run Br B.1 David R Anthony 3/30/2012 There are no historic properties within or

adjacent to the project area. The bridge was

determined not eligible through the Historic

Bridge Inventory.

CE 1b Eval 14719 Preparation

Main 2 Potter 872 A04 82034 SR 872 Mill Creek A.5, B.1 Scott Shaffer 1/24/2012 CE BRPA Eval 13807 Preparation

Main 3 Bradford 9900 LBR 5276 T-730 over Spaulding Crk B.1 Scott C Shaffer | Historic Preservation

Specialist

7/29/2011 ED BRPA Eval 14085 Preparation

Main 4 Lackawanna 11 255 83938 SR 0011 Ov. Spring Brook B.2 Kevin Mock 10/19/2011 This project is exempt from Section 106

review per the 2010 PA Appendix C.2.B.2.

ED BRPA Eval 13981 EM Review

Main 4 Susquehanna 11 550 9672 US 11 Salt Lick Brdg A.7.a, B.2 Kevin Mock 9/30/2011 The project, as designed, should have no

effect to the library. The project should not

have temporary or permananent impacts

the Pratt Library property parcel.

CE BRPA Eval 12768 EM Review

Main 4 Susquehanna 81 511 75917 NTier Interstate 4R A.1.a, A.1.c, A.1.e, A.1.f, A.3, A.4, A.15 Kevin Mock 1/18/2012 All construction work will be within existing

PennDOT ROW.

CE 2 Eval 14723 Preparation

Main 4 Wayne 84 0 93740 NEPA 4-12A-BR 3 A.4, B.2 Amy Lolli 2/3/2012 ED BRPA Eval 14628 Preparation

Main 5 Berks 78 UC1 75840 Berks Bridge Under Clear. B.1 Kris Thompson 11/23/2011 CE BRPA Eval 14804 Preparation

Main 5 Berks 78 UC1 75840 Berks Bridge Under Clear. B.1 Kris Thompson 11/23/2011 CE BRPA Eval 14804 Preparation

Main 5 Berks 78 UC1 75840 Berks Bridge Under Clear. B.1 Kris Thompson 11/23/2011 CE BRPA Eval 14804 Preparation

Main 5 Berks 1010 BRM 91941 RATS BR Preserve & Repair A.4 Steven W. Bruch 11/10/2011 See attached project bridge list. CE 1b Reeval 14464 Preparation

Main 5 Lehigh 0 --- 92348 Jordan Creek Greenway A.8.c Jim Ruth 6/16/2011 CE BRPA Eval 12760 Preparation

Main 5 Lehigh 987 0 88390 LVTS Bridge Painting11-12 A.4 Jim Ruth 8/30/2011 ED BRPA Eval 13065 Preparation

Main 6 Bucks 13 HBJ 92184 Adj Box Beam Grp (J) B.2 Dr. Catherine Spohn 8/23/2011 CE BRPA Eval 13173 EM Review

Main 6 Bucks 13 HBJ 92184 Adj Box Beam Grp (J) B.2 Dr. Catherine Spohn 8/23/2011 CE BRPA Eval 13174 EM Review

Main 6 Bucks 13 HBJ 92184 Adj Box Beam Grp (J) B.2 Dr. Catherine Spohn 8/23/2011 CE BRPA Eval 13175 EM Review

Main 6 Bucks 13 HBJ 92184 Adj Box Beam Grp (J) B.2 Dr. Catherine Spohn 8/23/2011 CE BRPA Eval 13176 EM Review

Main 6 Bucks 13 HBJ 92184 Adj Box Beam Grp (J) B.2 Dr. Catherine Spohn 8/23/2011 CE BRPA Eval 13345 EM Review

Main 6 Bucks 232 HBK 92310 Adj Box Beam Group (K) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13790 Preparation

Main 6 Bucks 232 HBK 92310 Adj Box Beam Group (K) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13815 Preparation

Main 6 Bucks 232 HBK 92310 Adj Box Beam Group (K) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13878 Preparation

Main 6 Bucks 313 HBK 92310 Culvert Replace Group (K) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13786 EM Review

Main 6 Bucks 313 HBK 92310 Culvert Replace Group (K) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13787 EM Review

Main 6 Bucks 313 HBK 92310 Culvert Replace Group (K) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13788 EM Review

Main 6 Bucks 313 HBK 92310 Culvert Replace Group (K) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13789 On-Hold

Main 6 Bucks 313 HBK 92310 Culvert Replace Group (K) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13797 EM Review

Main 6 Bucks 313 HBK 92310 Culvert Replace Group (K) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13875 EM Review

Main 6 Bucks 313 HBK 92310 Culvert Replace Group (K) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13876 EM Review

Main 6 Bucks 313 HBK 92310 Culvert Replace Group (K) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13879 EM Review

Main 6 Chester 82 HBL 92311 Adj Box Beam Group (L) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13959 Preparation

Main 6 Chester 82 HBL 92311 Adj Box Beam Group (L) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13960 Preparation

Main 6 Chester 82 HBL 92311 Adj Box Beam Group (L) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13961 Preparation

Main 6 Chester 82 HBL 92311 Adj Box Beam Group (L) B.1 Monica Harrower 9/12/2011 CE BRPA Eval 13962 Preparation

Main 6 Chester 82 HBL 92311 Adj Box Beam Group (L) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13963 Preparation

Main 6 Chester 82 HBL 92311 Adj Box Beam Group (L) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13970 Preparation

Main 6 Chester 82 HBL 92311 Adj Box Beam Group (L) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13971 Preparation

Main 6 Chester 82 HBL 92311 Adj Box Beam Group (L) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13972 Preparation

Main 6 Chester 82 HBL 92311 Adj Box Beam Group (L) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13973 Preparation

Main 6 Chester 82 HBL 92311 Adj Box Beam Group (L) B.1 Monica Harrower 8/2/2011 CE BRPA Eval 13974 Preparation

Main 8 Cumberland 0 --- 92379 Bike & Ped Trail Network A.6.a, A.8.b Jeremy Ammerman 8/24/2011 Installation/upgrade bicycle adviory signs,

and construction of bike/ped paths.

CE 1a Eval 14771 Preparation

Main 8 Cumberland 641 28 87023 Newville Elementary FSRS B.5.a, B.5.b, B.6.a, B.6.b Jeremy Ammerman 6/1/2011 CE BRPA Eval 14047 Preparation

Main 8 Cumberland 1037 6 91925 Tower Road Bridge A.1.c, A.4 Rebecca Knapp 2/23/2012 ED BRPA Eval 14748 Preparation

     Evaluation & Re-Evaluation Cultural Resource Exemptions   (All Districts -- With Exemption Date Between 05/04/2011 And 05/03/2012)

Main 8 Cumberland 4029 3 88924 Longs Gap Road Bridge A.1.c, B.2 Rebecca Knapp 2/23/2012 The project will remain exempt provided

that no ground disturbing activities occur in

the northwestern quadrant, and that

geotextile and fill will be placed on the

ground surface before construction begins

for heavy equipment access or staging.

ED BRPA Eval 14749 Preparation

Main 8 Dauphin 441 25 91926 PA 441 Bridge A.4 Rebecca Knapp, Jeremy Ammerman 2/23/2012 ED BRPA Eval 14753 Preparation

Main 8 Dauphin 2003 20 80972 Vine St Bridge #1 PM A.4 Jesse Sabitsky 2/14/2012 A special provision will be included in the

construction contract that restricts access

to this resource.

CE BRPA Eval 14655 Preparation

Main 8 Dauphin 2003 20 80972 Vine St Bridge #1 PM A.4 Jesse Sabitsky 2/14/2012 CE BRPA Eval 14655 Preparation

Main 8 Dauphin 2018 12 93491 Main Street Resurfacing A.1.a, A.1.c, A.3 Rebecca Knapp & Jeremy Ammerman 9/27/2011 CE BRPA Eval 14143 Preparation

Main 8 Dauphin 2018 13 92299 Hummelstown Boro Streets A.1.a, A.3, A.7.a, A.7.b, A.7.c, B.6.b Rebecca Knapp 9/20/2011 CE 1b Eval 14492 Preparation

Main 8 Dauphin 3001 44 95226 Eisenhower Blvd Resurface A.1.a Judith Y. Aker 2/17/2012 ED BRPA Eval 14653 Preparation

Main 8 Franklin 0 ENH 92424 Norlo and Hillview Drive A.8.b Jeremy Ammerman 7/14/2011 CE BRPA Eval 14831 Preparation

Main 8 Franklin 4016 2 88948 Roxbury Road Bridge A.1.c, A.4 Rebecca Knapp 2/23/2012 ED BRPA Eval 14752 Preparation

Main 8 Lancaster 272 28 74956 South Reading Rd Bridge B.1 Jeremy Ammerman 6/1/2011 CE 1b Eval 14445 Preparation

Main 8 Lancaster 272 28 74956 South Reading Rd Bridge B.1 Jeremy Ammerman 6/1/2011 CE 1b Eval 14650 Preparation

Main 8 Lancaster 272 31 82468 North Reading Road A.1.a, A.1.c, A.1.f, A.3, A.6.a, A.7.c, B.2,

B.6.b

Jesse Sabitsky 12/7/2011 ED BRPA Eval 14396 Preparation

Main 8 Lancaster 272 34 87702 N. Reading Rd Bridge B.2 Jeremy Ammerman 7/6/2011 ED BRPA Eval 13108 Preparation

Main 8 Lancaster 897 27 80999 SR 897 over US 222 A.4 Judith Y. Aker 5/2/2012 This project is exempt from Section 106

since construction activities will be limited

to the bridge deck and roadway.

ED BRPA Eval 12732 Preparation

Main 8 Lancaster 1086 1 88945 Orchard Road Br Pres A.4 Judith Y. Aker 5/2/2012 This project is exempt from the Section 106

Programmatic Agreement since

construction activies include zone painting,

latex overlay and approach resurfacing.

ED BRPA Eval 12737 Preparation

Main 8 Lancaster 4020 14 89654 HBG Pike/ Dillerville Rd A.1.a, A.1.b, A.1.c, A.1.d, A.6.a, A.6.b, A.7.a,

A.7.b, A.7.c, B.4

Jeremy Ammerman 7/6/2011 CE 1b Eval 14151 Preparation

Main 8 Lebanon 0 LOC 94707 Cherry Street Resurface A.1.a, A.7.c Judith Y. Aker 1/19/2012 The District Archaeologist's

recommendation is that all work be

performed in the disturbed road, shoulder,

and sidewalk area.

CE 1b Eval 14751 Preparation

Main 8 Lebanon 0 LOC 94707 Cherry Street Resurface A.1.a, A.7.c Judith Y. Aker 1/19/2012 The District Archaeologist's

recommendation is that all work be

performed in the disturbed road, shoulder,

and sidewalk area.

CE 1b Eval 14810 Preparation

Main 8 Lebanon 72 44 87156 SR72 & Jonestown Rd Inter A.6.a, A.6.b, A.7.c, B.4 Rebecca Knapp 6/13/2011 CE 1b Eval 13119 Preparation

Main 8 Lebanon 322 30 82909 Horseshoe Pike Bridge 1 B.2 Jeremy Ammerman 5/27/2011 CE BRPA Eval 12825 Preparation

Main 8 York 116 34 87317 York Road 2 A.1.a, A.3, B.6.b Jeremy Ammerman 2/8/2012 CE BRPA Eval 14658 Preparation

Main 9 Bedford 36 10B 92552 Loysburg By-Pass Pres A.4 Attilio Squillario 2/7/2012 CE BRPA Eval 14385 Preparation

Main 9 Blair 764 17 91625 Sugar Run Br to 17th St A.1.a, A.6.b, A.7.c Jonathan E. Daily, Susanne Haney 8/1/2011 It was determined at the scoping field view

that no historic resources exist within the

project limits.

CE BRPA Eval 14345 Preparation

Main 9 Blair 865 05B 92545 Bellwood Br Dck Pres B.2 Jamie C. Chestney 2/7/2012 CE BRPA Eval 14352 Preparation

Main 9 Blair 1009 08B 92547 Frnkstwn Rd Br Dck Pres B.2 Jamie C. Chestney 2/10/2012 CE BRPA Eval 14354 Preparation

Main 9 Blair 2014 03B 22027 Loop Road Bridge B.1 Susanne Haney 12/13/2011 There are intact alluvial soils with the

potential for containing "in situ"

archaeological materials. Widening may not

excced 12 feet of the existing structure or a

Geomorphological & Phase I Archaeological

Survey is recommended.

CE BRPA Eval 12636 Preparation

Main 9 Blair 4013 05B 92546 Altoona 7 & 8th St Br Dck B.2 Jamie C. Chestney 2/10/2012 CE BRPA Eval 14353 Preparation

Main 9 Cambria 0 MSR 92442 Jtown Main St Imprvmnts A.1.a, A.1.b, A.6.c, A.7.a, A.7.b Sarah McClellan 4/30/2012 CE 1b Eval 14766 EM Review

Main 9 Cambria 160 07M 91637 Somerst Co Line to PA 756 A.1.a Sarah McClellan 9/8/2011 ED BRPA Eval 12877 Preparation

Main 9 Cambria 3037 05B 91685 Prospect Viaduct Pres A.4 Sarah McClellan 4/12/2012 CE BRPA Eval 14744 Preparation

Main 9 Huntingdon 913 05B 23053 Coalmont-Shoups Run Brdg B.1 Susanne M. Haney 3/29/2012 Based upon Line & Grade no additional

permanent r/w acquisitions are required,

and all TCEs are in areas of previous

disturbance. Project determined to be

Appendix C, B-List Exempt. See attached

email.

CE 1b Eval 11217 EM Review

Main 9 Somerset 1008 01B 23429 Mostoller Stonycreek Br B.1, B.3 Susanne Haney 12/28/2011 See attached. CE 1b Eval 13996 Preparation

Main 10 Jefferson 36 592 25839 Coolspring PM A.1.a, A.1.c, A.1.d, A.3, A.6.a Eric R. Buchan 4/11/2012 CE BRPA Eval 14821 Preparation

Main 11 Allegheny 0 --- 92363 PCTI-AirportCorridorMobil A.1.a, A.1.b, A.5, A.6.a, A.6.c, A.8.b, A.11 David Anthony 4/6/2012 The Montour Railroad is nearby however

there is no potential to physically or visually

affect the resource.

CE 1b Eval 14817 Preparation

Main 11 Allegheny 7203 LOC 81667 MN01 Montour Run #1 A.1.e, A.6.a, B.1 David Anthony 10/26/2011 Bridge is categorically not eligible. There are

no other historic resources within the

project area.

ED 1b Eval 14040 Preparation

Main 11 Beaver 18 B45 91582 18/32nd St - SR 551 A.1.a, A.1.c, A.1.e, A.3, A.6.a, A.6.b, A.7.a,

A.7.c

Nick Krobot 6/3/2011 Geneva College, a National Register Eligible

Historic District, is located outside the

project area. Geneva College will not be

impacted by this project.

CE BRPA Eval 12905 Preparation

Main 11 Beaver 3010 B04 93061 3010/Moffett Mill Slide A.15 Nick Krobot 6/13/2011 ED 1b Eval 12977 Preparation

Main 11 Beaver 3029 B02 93062 3029/Shivler Road Slide A.15 Nick Krobot 6/13/2011 ED 1b Eval 12976 Preparation

Main 11 Lawrence 2001 L07 93064 2001/Turkey Hill Slide A.15 Nick Krobot 6/13/2011 ED 1b Eval 12981 Preparation

Main 11 Lawrence 2022 L03 29481 Heinz Camp Road Bridge A.1.c, A.5, B.1 Joe Verbka 2/7/2012 CE 1b Eval 14487 Preparation

Main 12 Fayette 51 24R 87370 PA 51 Oliver to Bitner A.1.a Kim Ansell 6/1/2011 CE BRPA Eval 12933 Preparation

Main 12 Washington 18 F10 94558 D12 Small Bridge 2012-1 B.1 Ryan Rowles & David Anthony 1/24/2012 ED BRPA Eval 14578 Preparation

Main 12 Washington 18 F10 94558 D12 Small Bridge 2012-1 B.1 Ryan Rowles & David Anthony 1/24/2012 ED BRPA Eval 14578 Preparation

Main 12 Washington 18 F10 94558 D12 Small Bridge 2012-1 B.1 Ryan Rowles & Davis Anthony 1/24/2012 ED BRPA Eval 14578 Preparation

Main 12 Washington 18 F10 94558 D12 Small Bridge 2012-1 B.1 Ryan Rowles & David Anthony 1/24/2012 ED BRPA Eval 14578 Preparation

Main 12 Westmoreland 982 0 69256 PA 982 over US 30 B.1 Ryan Rowles & David Anthony 5/25/2011 ED BRPA Eval 14735 Preparation

Main 12 Westmoreland 2027 A10 79420 SR 2027 over Ninemile Run B.1 Ryan Rowles and David Anthony 5/4/2011 David Anthony hasn't scoped it yet ED BRPA Eval 13385 Preparation

Archive2 1 Crawford 8 09M 92829 SR 8:Co. Line to Central A.1.a, A.1.c, A.3, B.6.b David R. Anthony 12/21/2011 The Titusville Historic District is within the

project area. However, due to the nature of

the proposed activites, there will be no

affect the qualities which make the district

eligible for listing on the National Register of

Historic Places.

CE 1b Eval 14266 Approved

Archive2 1 Crawford 8 10M 93083 SR 8: Lake Rd - Co. Line A.1.a, A.1.c, A.3, A.6.a Christopher R. Wolfgong 9/7/2011 CE BRPA Eval 14158 Approved

Archive2 1 Crawford 198 B03 57964 PA 198 / Wolf Run Bridge A.1.a, A.1.c, B.1 David Anthony 1/3/2012 The bridge was determined not eligible

through the statewide bridge survey. There

are no previously identified cultural

resources within the area of potential

effect.

ED 1b Eval 14039 Approved

Archive2 1 Erie 0 T26 92869 Lakeside Dr Sidewalk A.8.b Autumn Kelley 1/25/2012 CE 1b Eval 14452 Approved

Archive2 1 Erie 18 B06 89114 SR 18 ov Connt Ck E. Brch A.1.a, A.1.c, A.3, B.1 David Anthony 1/9/2012 There are no cultural resources within the

project area.

ED BRPA Eval 14301 Approved

Archive2 1 Erie 18 B06 89114 SR 18 ov Connt Ck E. Brch A.1.a, A.1.c, A.3, B.1 David Anthony 1/9/2012 There are no cultural resources within the

project area.

ED BRPA Reeval 14709 Approved

Archive2 1 Erie 90 B12 94775 I-90 Bridges/SR 531 EB/WB A.1.a, A.1.c, A.3, A.4 Christopher R. Wolfgong 2/1/2012 The projects were discussed with the CRP's

and it was determined that the structure

was not eligible and was not within a

historic district.

ED BRPA Eval 14547 Approved

Archive2 1 Erie 90 B12 94775 I-90 Bridges/SR 531 EB/WB A.1.a, A.1.c, A.3, A.4 Christopher R. Wolfgong 2/1/2012 The projects were discussed with the CRP's

and it was determined that the structure

was not eligible and was not within a

historic district.

ED BRPA Eval 14547 Approved

Archive2 1 Erie 2020 B00 72639 Frnch Ck South Br/SR 2020 B.1 David Anthony 1/9/2012 There are no cultural resources within the

project area.

ED BRPA Eval 14378 Approved

Archive2 1 Erie 4101 B00 94668 Platz Rd Bridge Demo B.1 David R. Anthony 11/4/2011 There are no historic resources within the

project area.

ED BRPA Eval 13873 Approved

Archive2 1 Mercer 0 LOC 93069 Highland Road ADA/Resf A.1.a, A.3, B.6.b David R. Anthony 1/27/2012 There are structures over 50 years of age

present however there are no individually

eligble structures. There is not a historic

district present.

CE 1b Eval 14364 Approved

Archive2 1 Mercer 18 444 92987 SR 18: SR 58 to 6th Ave A.1.a, A.1.c, A.3, A.7.c David Anthony 8/26/2011 See Additional Information. ED 1b Eval 13621 Approved

Archive2 1 Mercer 58 11M 93066 SR 58: RT 18 to SR 4024 A.1.a, A.3, A.7.a, A.7.c, B.6.b David R. Anthony 10/20/2011 The northeastern boundary of the

Greenville Downtown Historic District is

located immediately west of the project

limit. Due the to the nature of the proposed

project, there is no potential to affect the

historic district.

CE 1b Eval 14135 Approved

Archive2 1 Mercer 80 A18 94792 I-80: MP 14.8 to MP 21.2 A.1.a, A.1.c, A.3 Christopher R. Wolfgong 2/8/2012 This is an Interstate resurfaceing project.

Work will be within the existing right of way.

CE BRPA Eval 14525 Approved

Archive2 1 Mercer 2014 B01 74686 SR 2014 over Wolf Ck #2 A.5, B.1 David Anthony 1/9/2012 The bridge was determined not eligible for

the National Register of Historic Places.

There are no other previously identified

cultural resources within the general area.

ED 1b Eval 14257 Approved

Archive2 1 Venango 80 B03 94777 I-80 Bridges/SR 38 EB/WB A.1.a, A.3, A.4 Christopher R. Wolfgong 2/8/2012 Interstate bridge repair/resurfacing project. ED BRPA Eval 14546 Approved

Archive2 1 Venango 80 B03 94777 I-80 Bridges/SR 38 EB/WB A.1.a, A.3, A.4 Christopher R. Wolfgong 2/8/2012 Interstate bridge repair/resurfacing project. ED BRPA Eval 14546 Approved

Archive2 1 Warren 0 --- 92383 Youngsville Streetscape A.1.a, A.7.a, B.5.b, B.6.b David Anthony 9/7/2011 CE 1b Eval 13012 Approved

Archive2 1 Warren 62 A01 82162 US 62 Intersections A.1.a, A.1.b, A.1.c, A.3, A.6.b, A.7.b Autumn Kelley 3/27/2012 All work will be done with in PennDOT right

of way.

CE 1b Eval 13111 Approved

Archive2 1 Warren 6006 B01 89103 Glade Bridge over Allegh A.4 Autumn Kelley 5/2/2012 Paving only therefore no impacts to cultural

resources.

ED BRPA Eval 14834 Approved

Archive2 1 Warren 7218 0 58317 Henry's Mill Bridge T-526 B.1, B.4 David Anthony 9/23/2011 There are no historic structures or

archaeological resourses (per JMV 9-23-

2011) within the project area.

CE 1b Eval 13053 Approved

Archive2 2 Centre 0 --- 92518 Howard Boro Bike/Ped Tr. A.8.c Scott Shaffer 2/24/2012 See attachment. CE BRPA Eval 14058 Approved

Archive2 2 Centre 80 B45 89259 Bellefonte Bridges B.2 Scott Shaffer 1/19/2012 ED BRPA Eval 14371 Approved

Archive2 2 Centre 80 B45 89259 Bellefonte Bridges B.2 Scott Shaffer 1/19/2012 ED BRPA Eval 14371 Approved

Archive2 2 Centre 80 B45 89259 Bellefonte Bridges B.2 Scott Shaffer 1/19/2012 ED BRPA Eval 14371 Approved

Archive2 2 Centre 80 B45 89259 Bellefonte Bridges B.2 Scott Shaffer 1/19/2012 ED BRPA Eval 14371 Approved

Archive2 2 Centre 80 B46 94436 I 80 Bridges over SR 26 A.4 Scott Shaffer 2/29/2012 ED BRPA Eval 14568 Approved

Archive2 2 Centre 80 B46 94436 I 80 Bridges over SR 26 A.4 Scott Shaffer 2/29/2012 ED BRPA Eval 14568 Approved

Archive2 2 Centre 350 A02 2911 SR 350 Clover Run B.1 Scott Shaffer 12/21/2011 ED BRPA Eval 13804 Approved

Archive2 2 Centre 1002 A11 85061 SR 1002 ov Big Rn BOX B.1 Scott Shaffer 4/27/2012 A Phase I archaeological survey found no

archaeological remains.

ED BRPA Eval 14503 Approved

Archive2 2 Clearfield 0 --- 92524 S. Brady St. Streetscape A.3, B.5.b, B.6.a, B.6.b Scott Shaffer 8/17/2011 CE BRPA Eval 12722 Approved

Archive2 2 Clearfield 0 --- 94679 Group 2-12-AWPM B.5.b Mary Beth Stojek 3/29/2012 CE BRPA Eval 14692 Approved

Archive2 2 Clearfield 255 260 88219 SR 255 Paving II A.1.a, A.6.c Scott Shaffer 11/10/2011 CE BRPA Eval 14590 Approved

Archive2 2 Clearfield 255 A06 69447 Sandy Lick Creek Bridge B.1 Scott Shaffer 7/20/2011 CE BRPA Eval 13033 Approved

Archive2 2 Clearfield 1004 R91 94608 Market Street RR Upgrade A.2 Robert R. Weed, Dist.Env.Mgr., 2-0 12/7/2011 Rehabilitation of existing railroad crossing CE BRPA Eval 14159 Approved

Archive2 2 Clearfield 2035 A01 3618 Sulphur Run Bridge B.1 Scott Shaffer 7/26/2011 ED BRPA Eval 13120 Approved

Archive2 2 Clearfield 4017 N02 88923 Beaver /Shaffer Intersect A.5, A.6.b Scott Shaffer 8/22/2011 CE BRPA Eval 13116 Approved

Archive2 2 Clearfield 4019 R92 95266 DuBois St. Lights & Gates A.2 Robert R. Weed, Dist.Env.Mgr., 2-0 3/15/2012 Rehabilitation of existing at-grade railroad

grade crossing devices under the RRX

Highway 130 Safety Program.

CE BRPA Eval 14619 Approved

Archive2 2 Clinton 144 A03 69039 Halls Run Bridge B.1 Scott Shaffer 12/5/2011 CE BRPA Eval 14067 Approved

Archive2 2 Clinton 144 A04 3854 Kettle Creek Deck Repl B.2, B.3 Scott Shaffer 7/20/2011 CE BRPA Eval 12930 Approved

Archive2 2 Clinton 2002 A04 81417 Bletz Hollow BOX B.1 Scott Shaffer 9/27/2011 ED BRPA Eval 12352 Approved

Archive2 2 Clinton 2004 A06 83018 Fishing Creek Deck Repl B.1 Scott Shaffer 9/16/2011 CE BRPA Eval 14192 Approved

Archive2 2 Elk 0 --- 92523 Wilcox Streetscape Ph 2 A.6.c, A.7.a, A.7.b, A.7.c, A.8.a Scott Shaffer 11/15/2011 CE BRPA Eval 12720 Approved

Archive2 2 Elk 1008 A01 82036 SR 1008 West Creek B.2 Scott Shaffer 2/14/2012 CE BRPA Eval 14529 Approved

Archive2 2 Juniata 2017 A02 88587 SR 2017 Stony Run BOX B.1 Scott Shaffer 5/19/2011 ED BRPA Eval 14094 Approved

Archive2 2 McKean 446 R89 62430 SR 446 Near Larabee A.6.a Robert R. Weed, Dist. Env. Mgr., 2-0 5/10/2011 CE BRPA Eval 12629 Approved

Archive2 2 McKean 1002 A02 83045 SR 1002 Deck - Allegheny A.4 Scott Shaffer 2/24/2012 CE BRPA Eval 12345 Approved

Archive2 2 McKean 1002 A03 69429 Champlin Hollow BOX B.1 Scott Shaffer 7/11/2011 ED BRPA Eval 14478 Approved

Archive2 2 Mifflin 0 --- 92530 Monument Square Phase IV A.8.a Cheryl L. Nagle (PHMC) 5/12/2011 none CE BRPA Eval 12693 Approved

Archive2 2 Mifflin 0 --- 93037 Monument Square Strtscape B.5.a, B.5.b, B.6.a, B.6.b Scott Shaffer 2/22/2012 PHMC Clearance letter attached. CE BRPA Eval 14486 Approved

Archive2 2 Mifflin 22 714 88309 SR 0022 Betterment Proj A.1.a, A.1.c, B.2 Scott Shaffer 5/31/2011 CE 1b Eval 12960 Approved

Archive2 2 Mifflin 22 R90 92863 SR 22/322 4 Lane At-Grade A.6.a Robert R. Weed, Dist. Env. Mgr. 2-0 9/8/2011 CE BRPA Eval 13117 Approved

Archive2 2 Potter 0 --- 92519 Oswayo Valley SRTS A.6.c, A.7.a, A.7.b, A.8.a Scott Shaffer 2/9/2012 CE BRPA Eval 12994 Approved

Archive2 2 Potter 244 A09 85499 SR 244 Lawson Hollow BOX B.1 Scott Shaffer 7/26/2011 ED BRPA Eval 14761 Approved

Archive2 2 Potter 1021 A02 83523 SR 1021 Cowanesque Rv III B.1 Scott Shaffer 2/27/2012 CE BRPA Eval 14113 Approved

Archive2 2 Potter 3001 A03 82040 SR 3001 Stone Lk Run BOX B.1 Jerry Kinback 9/15/2011 No historical or archaeological resources

were identified during the Scoping Field

View. See E. and E. Scoping Field View

meeting minutes attached below.

ED BRPA Eval 14537 Approved

Archive2 3 Bradford 6 46 93873 US 6 over Mill Creek A.12, A.15 Matt Hamel 10/6/2011 Flood-related work that meets the criteria

of the Section 106 PA.

CE BRPA Eval 13435 Approved

Archive2 3 Bradford 6 114 94654 SR 6 over A.4, A.12 Matt Hamel 11/15/2011 CE BRPA Eval 13895 Approved

Archive2 3 Bradford 6 117 95338 US 6 over Wallace Run B.2 Matt Hamel 4/11/2012 ED BRPA Eval 14739 Approved

Archive2 3 Bradford 6 M35 87984 Sugar Cr to Tomjack Cr A.1.a, A.4 Kyle Bunce 7/8/2011 Allwork will be completed within the existing

footprint. CRP coordination is attached

below.

CE BRPA Eval 12820 Approved

Archive2 3 Bradford 6 M45 93751 US 6 Roadway Flood Repair A.1.a Kyle Bunce 9/19/2011 Coordination was conducted with the CRP

archaeologist. There no concerns.

CE BRPA Eval 13235 Approved

Archive2 3 Bradford 6 M45 93751 US 6 Roadway Flood Repair A.1.a Kyle Bunce 9/19/2011 Coordination was conducted with the CRP

archaeologist. There no concerns.

CE BRPA Reeval 13245 Approved

Archive2 3 Bradford 14 88 94448 SR 14 Flood Repair A.3 Matt Hamel 10/14/2011 CE BRPA Eval 13539 Approved

Archive2 3 Bradford 14 92 94610 SR 14 over Wolfe Creek A.4 Matt Hamel 3/15/2012 CE BRPA Eval 14615 Approved

Archive2 3 Bradford 14 94 94639 PA 14 Bank Repair A.1.c, A.1.d, A.4 Matt Hamel 11/15/2011 CE BRPA Eval 13892 Approved

Archive2 3 Bradford 154 45 93875 SR 154 ov Beech Flat Crk A.4 Matt Hamel 10/6/2011 Flood-related work that meets the criteria

of the Section 106 PA.

CE BRPA Eval 13436 Approved

Archive2 3 Bradford 154 60 94525 SR154ovLt Beech Flats Crk A.12 Scott Shaffer 11/10/2011 CE BRPA Eval 13906 Approved

Archive2 3 Bradford 187 35 93803 SR 187 over Trout Stream B.1 Matt Hamel and Scott Shaffer 1/3/2012 CE BRPA Eval 14238 Approved

Archive2 3 Bradford 187 39 93846 SR187 RoadwayFloodRepair A.1.a, A.1.c Matt Hamel 10/13/2011 93845: 2.A.1.a & 2.A.1.c; 93844: 2.A.1.a CE BRPA Eval 13504 Approved

Archive2 3 Bradford 187 41 93878 SR 187 over Trout Brook A.1.a, A.4 Matt Hamel 10/6/2011 Flood-related project components that

meet the criteria of the Section 106 PA.

CE BRPA Eval 13440 Approved

Archive2 3 Bradford 187 44 93973 SR 187 over Durrell Creek A.4, A.12, B.2 Matt Hamel 10/6/2011 Flood-related work that meets the criteria

of the Section 106 PA.

CE BRPA Eval 13437 Approved

Archive2 3 Bradford 187 46 93976 SR187 ov Tr WappaseningCr A.4 Matt Hamel 11/2/2011 CE BRPA Eval 13803 Approved

Archive2 3 Bradford 187 48 94096 SR 187 Flood Repair A.15 Matt Hamel 10/14/2011 CE BRPA Eval 13541 Approved

Archive2 3 Bradford 187 56 94409 SR 187 over Tb Susq River A.1.a Matt Hamel 10/31/2011 CE BRPA Eval 13767 Approved

Archive2 3 Bradford 187 59 94505 SR 187 over Trout Brook A.12 Scott Shaffer 11/10/2011 CE BRPA Eval 13893 Approved

Archive2 3 Bradford 220 151 94410 US 220 over Ladds Creek A.4, A.12 Matt Hamel 11/4/2011 CE BRPA Eval 13768 Approved

Archive2 3 Bradford 220 152 94506 US220ovTb SBr Towanda Crk A.12 Scott Shaffer 11/10/2011 CE BRPA Eval 13896 Approved

Archive2 3 Bradford 220 155 94622 US 220 Flood Repair A.15 Matt Hamel 10/24/2011 CE BRPA Eval 13682 Approved

Archive2 3 Bradford 220 M10 82194 New Albany to Monroeton A.1.a, A.4 Kyle Bunce 5/16/2011 Coordination with CRP's is attached below. CE 1b Eval 12775 Approved

Archive2 3 Bradford 220 M10 82194 South Branch to Monroeton A.1.a, A.4, A.5 Kyle Bunce 4/11/2012 Coordination with CRP's is attached below. CE 1b Reeval 14570 Approved

Archive2 3 Bradford 409 5 93879 SR 409 over Camp Creek A.4, A.15 Matt Hamel 10/6/2011 Flood-related project components that

meet the critera of the Section 106 PA.

CE BRPA Eval 13441 Approved

Archive2 3 Bradford 414 36 93768 SR414 Roadway FloodRepair A.1.a Kyle Bunce 9/21/2011 Coordination was conducted with the CRP

historian. There are no concerns.

CE BRPA Eval 13252 Approved

Archive2 3 Bradford 414 41 94281 SR 414 ov Tb Towanda Crk A.1.a, A.4, A.12 Matt Hamel 10/31/2011 CE BRPA Eval 13741 Approved

Archive2 3 Bradford 414 41 94281 SR 414 ov Tb Towanda Crk A.1.a, A.12, A.15 Matt Hamel 10/31/2011 CE BRPA Eval 13741 Approved

Archive2 3 Bradford 414 41 94281 SR 414 ov Tb Towanda Crk A.12, A.15 Matt Hamel 10/31/2011 CE BRPA Eval 13741 Approved

Archive2 3 Bradford 414 41 94281 SR 414 ov Tb Towanda Crk A.12 Matt Hamel 10/31/2011 CE BRPA Eval 13741 Approved

Archive2 3 Bradford 414 48 94499 SR 414 over Wallace Run A.4, A.12, A.15 Matt Hamel 11/4/2011 CE BRPA Eval 13776 Approved

Archive2 3 Bradford 414 50 94627 SR 414 RoadwayFloodRepair A.1.a, A.1.c, A.15 Matt Hamel 11/4/2011 CE BRPA Eval 13793 Approved

Archive2 3 Bradford 414 51 94640 PA 414 EmbankmentRepair A.4, A.12 Matt Hamel 11/15/2011 CE BRPA Eval 13904 Approved

Archive2 3 Bradford 467 13 94641 SR 467 BridgeFloodRepair A.4 Matt Hamel 11/15/2011 CE BRPA Eval 13899 Approved

Archive2 3 Bradford 514 5 93877 SR514 ovTbNBr Towanda Crk A.1.a, A.4, A.15 Matt Hamel 10/6/2011 Flood-related projects that meet the criteria

of the Section 106 PA.

CE BRPA Eval 13442 Approved

Archive2 3 Bradford 514 10 94584 SR514 ovTbNBr Towanda Crk A.12, A.15 Scott Shaffer 11/10/2011 CE BRPA Eval 13911 Approved

Archive2 3 Bradford 514 10 94584 SR514 ovTbNBr Towanda Crk A.12 Scott Shaffer 11/10/2011 CE BRPA Eval 13911 Approved

Archive2 3 Bradford 549 20 94540 SR 549 over Seeley Creek A.12, A.15 Scott Shaffer 11/10/2011 CE BRPA Eval 13908 Approved

Archive2 3 Bradford 706 4 94406 SR 706 over Cold Creek A.1.a, A.4, A.12 Matt Hamel 11/4/2011 CE BRPA Eval 13765 Approved

Archive2 3 Bradford 1022 20 94396 SR 1022 over Bullards Crk A.12 Matt Hamel 10/31/2011 CE BRPA Eval 13758 Approved

Archive2 3 Bradford 1022 20 94396 SR 1022 over Bullards Crk A.1.a, A.4 Matt Hamel 10/31/2011 CE BRPA Eval 13758 Approved

Archive2 3 Bradford 1038 11 93847 SR1038 ov Wappasening Crk A.1.a, A.1.c Kyle Bunce 9/30/2011 CE BRPA Eval 13394 Approved

Archive2 3 Bradford 1043 5 93848 SR 1043 over Saterlee Crk A.1.a, A.1.c, A.12 Kyle Bunce 10/1/2011 CE BRPA Eval 13396 Approved

Archive2 3 Bradford 1043 11 94401 SR 1043 over Tb Susq Rvr A.4, A.12 Matt Hamel 11/4/2011 CE BRPA Eval 13760 Approved

Archive2 3 Bradford 1043 12 94402 SR 1043 over Tb Susq Rvr A.1.a, A.15 Matt Hamel 11/4/2011 CE BRPA Eval 13762 Approved

Archive2 3 Bradford 1049 15 94273 SR1049 ov TrWappaseningCr A.12 Matt Hamel 10/17/2011 CE BRPA Eval 13604 Approved

Archive2 3 Bradford 1049 15 94273 SR1049 ov TrWappaseningCr A.1.a, A.1.c, A.4 Matt Hamel 10/17/2011 CE BRPA Eval 13604 Approved

Archive2 3 Bradford 1049 19 94554 SR 1049 over Russel Run A.12 Scott Shaffer 11/10/2011 CE BRPA Eval 13910 Approved

Archive2 3 Bradford 1056 6 94175 SR 1056 Flood Repair A.1.a Matt Hamel 10/14/2011 CE BRPA Eval 13537 Approved

Archive2 3 Bradford 1056 8 94592 SR 1056 over Susq River A.4 Matt Hamel 11/15/2011 CE BRPA Eval 13913 Approved

Archive2 3 Bradford 1056 9 94609 SR1056 RoadwayFloodRepair A.1.a, A.1.c Matt Hamel 11/4/2011 CE BRPA Eval 13794 Approved

Archive2 3 Bradford 2009 6 89971 SR2009 ov Panther Lick Rn A.4 Kyle Bunce 6/6/2011 CE BRPA Eval 12600 Approved

Archive2 3 Bradford 2010 13 94411 SR 2010 over Susq River A.4 Matt Hamel 11/2/2011 CE BRPA Eval 13769 Approved

Archive2 3 Bradford 2027 07M 94562 SR 2027 Pipe Replacement A.3 Matt Hamel 2/9/2012 ED BRPA Eval 14410 Approved

Archive2 3 Bradford 4013 24 94348 SR 4013 Flood Repair A.15 Matt Hamel 10/14/2011 CE BRPA Eval 13540 Approved

Archive2 3 Bradford 4014 19 94416 SR 4014 ov Leonards Creek A.12 Matt Hamel 10/31/2011 CE BRPA Eval 13721 Approved

Archive2 3 Bradford 4017 18 86454 DF Deck N-TIER 11-12 A.4 Kyle Bunce 7/15/2011 Coordination with the CRP historian is

attached below. No access or earth

disturbance will be required to complete

this project.

ED BRPA Eval 12855 Approved

Archive2 3 Bradford 4025 1 94813 SR 4025 ov Tb Bently Crk A.4 Kyle Bunce 12/15/2011 CE BRPA Eval 14130 Approved

Archive2 3 Columbia 0 LRD 95367 Columbia Bloom St Flood A.1.a, A.1.c Matt Hamel 3/19/2012 CE BRPA Eval 14554 Approved

Archive2 3 Columbia 11 100 93756 US11 Roadway Flood Repair A.1.a Kyle Bunce 9/14/2011 Coordination was conducted with CRP's and

there are no concerns.

CE BRPA Eval 13163 Approved

Archive2 3 Columbia 11 59E 93502 Flat Iron Enhancement A.6.c, A.7.a, A.7.b, A.7.c, A.8.a Matt Hamel 2/22/2012 CE BRPA Eval 14485 Approved

Archive2 3 Columbia 42 70 94010 SR 42 Flood Repair A.15 Matt Hamel 10/14/2011 CE BRPA Eval 13559 Approved

Archive2 3 Columbia 42 77 94184 SR42 Roadway Flood Repair A.1.a, A.1.c, A.12 Matt Hamel 10/14/2011 CE BRPA Eval 13564 Approved

Archive2 3 Columbia 42 82 94215 SR 42 over A.12 Matt Hamel 10/19/2011 CE BRPA Eval 13573 Approved

Archive2 3 Columbia 42 82 94215 SR 42 over A.12 Matt Hamel 10/19/2011 CE BRPA Eval 13573 Approved

Archive2 3 Columbia 42 84 94219 SR 42 ov T Roaring Creek A.1.a, A.1.c Matt hamel 10/17/2011 CE BRPA Eval 13578 Approved

Archive2 3 Columbia 42 85 94590 SR 42 ov Catawissa Creek A.4 Matt Hamel 11/15/2011 CE BRPA Eval 13943 Approved

Archive2 3 Columbia 61 105 94006 SR 61 Flood Repair A.15 Matt Hamel 10/14/2011 CE BRPA Eval 13561 Approved

Archive2 3 Columbia 61 105 94006 SR 61 Flood Repair A.15 Matt Hamel 10/14/2011 CE BRPA Eval 13561 Approved

Archive2 3 Columbia 61 105 94006 SR 61 Flood Repair A.15 Matt Hamel 10/14/2011 CE BRPA Eval 13561 Approved

Archive2 3 Columbia 61 105 94006 SR 61 Flood Repair A.1.a Matt Hamel 10/14/2011 CE BRPA Eval 13561 Approved

Archive2 3 Columbia 80 111 94587 I-80 ov Fishing Cr & T360 A.4 Matt Hamel 11/15/2011 CE BRPA Eval 13946 Approved

Archive2 3 Columbia 118 7 94220 SR 118 Trib W Br West Ck A.4 Matt Hamel 10/18/2011 CE BRPA Eval 13579 Approved

Archive2 3 Columbia 239 18 74029 SR 239 over West Creek B.1 Scott Shaffer and Matt Hamel 7/26/2011 According to Scott Shaffer and Matt Hamel,

PennDOT District 3-0 Cultural Resource

Professionals (CRPs), no archaeological and

historic concerns were noted. This project

can be cleared under Appendix C 2.B.1.

CE BRPA Eval 14334 Approved

Archive2 3 Columbia 254 36 94186 SR 254 over Culley Run A.1.a, A.12, A.15 Matt Hamel 10/19/2011 CE BRPA Eval 13567 Approved

Archive2 3 Columbia 254 37 94187 SR 254 over Fishing Creek A.4, A.15 Matt Hamel 10/19/2011 CE BRPA Eval 13635 Approved

Archive2 3 Columbia 254 39 94585 SR 254 over A.1.a, A.1.c Matt Hamel 11/15/2011 CE BRPA Eval 13947 Approved

Archive2 3 Columbia 487 68 93759 SR487 Roadway FloodRepair A.1.a Kyle Bunce 9/21/2011 Coordination was conducted with the CRP

historian and there are no concerns.

CE BRPA Eval 13254 Approved

Archive2 3 Columbia 487 84 94320 SR 487 over Coles Creek A.4, A.12 Matt Hamel 10/26/2011 CE BRPA Eval 13658 Approved

Archive2 3 Columbia 487 86 94623 SR 487 Flood Repair A.1.a, A.15 Matt Hamel 10/24/2011 CE BRPA Eval 13684 Approved

Archive2 3 Columbia 1022 19 94318 SR 1022 over old Channel A.4 Matt Hamel 10/26/2011 CE BRPA Eval 13659 Approved

Archive2 3 Columbia 2001 19 94814 SR 2001 over Roaring Crk A.4 Kyle Bunce 12/15/2011 CE BRPA Eval 14131 Approved

Archive2 3 Columbia 4013 18 94043 SR 4013 ov Deer Lick Run B.1 District CRPs 10/11/2011 A FAFA was submitted on 12-02-11 to the

PHMC, with a No Effect finding.

CE BRPA Eval 13695 Approved

Archive2 3 Lycoming 0 --- 93559 2011-2012 RPM Contract A.1.a Kyle Bunce 2/1/2012 CE BRPA Eval 14351 Approved

Archive2 3 Lycoming 0 52E 87132 Williamsport SRTS A.1.a, A.6.a, A.7.a, A.7.b, A.7.c, B.5.a, B.6.a,

B.6.b

Matt Hamel 1/20/2012 The proposed project will have No Effect to

both Cochran and Stevens schools, which

have been determined eligible for the

National Register of Historic Places. Jackson

and Sheridan schools are ineligible.

CE 1a Eval 9925 Approved

Archive2 3 Lycoming 0 55E 92516 Pathways to Health Ph II A.6.b, A.7.a, A.8.a Matt Hamel 7/14/2011 CE BRPA Eval 12914 Approved

Archive2 3 Lycoming 0 RRX 90597 Woodward Railroad Xing A.2 Kyle Bunce 1/5/2012 CE BRPA Eval 14231 Approved

Archive2 3 Lycoming 14 85 94084 SR 14 Flood Repair A.15 Matt Hamel 10/14/2011 CE BRPA Eval 13533 Approved

Archive2 3 Lycoming 44 53 94761 PA44 ov US220 AccidentRep A.4 Kyle Bunce 1/26/2012 ED BRPA Eval 14310 Approved

Archive2 3 Lycoming 44 53 94761 PA44 ov US220 AccidentRep A.1.a Kyle Bunce 1/26/2012 ED BRPA Eval 14310 Approved

Archive2 3 Lycoming 87 78 93775 SR87 Roadway FloodRepair A.1.c, A.3, A.6.a Kyle Bunce 10/3/2011 CE BRPA Eval 13402 Approved

Archive2 3 Lycoming 87 101 94504 SR 87 over Big Bear Creek A.1.a, A.1.c, A.3, A.4, A.15 Matt Hamel 10/24/2011 CE BRPA Eval 13681 Approved

Archive2 3 Lycoming 118 8 94347 SR 118 over Sugar Run A.4 Matt Hamel 10/24/2011 CE BRPA Eval 13672 Approved

Archive2 3 Lycoming 180 82 93948 I 180 ov Loyalsock Creek A.15 Kyle Bunce 9/23/2011 Coordination was conducted with the CRP

historian.

CE BRPA Eval 13271 Approved

Archive2 3 Lycoming 220 146 94193 US 220 over Muncy Creek A.4, A.15, B.2 Scott Shaffer 11/7/2011 CE BRPA Eval 13838 Approved

Archive2 3 Lycoming 220 146 94193 US 220 over Muncy Creek A.4, A.15 Scott Shaffer 11/7/2011 CE BRPA Eval 13838 Approved

Archive2 3 Lycoming 220 M17 87955 Clinton Co to SR 287 A.1.a, A.4 Kyle Bunce 7/20/2011 CE BRPA Eval 12908 Approved

Archive2 3 Lycoming 414 35M 92834 SR 414 Cedar Run Slide A.15 Matt Hamel 5/13/2011 CRP email is attached below. ED 1b Eval 12639 Approved

Archive2 3 Lycoming 414 35M 92834 SR 414 Cedar Run Slide A.15 Matt Hamel 5/13/2011 CRP email is attached below. ED 1b Reeval 12714 Approved

Archive2 3 Lycoming 654 23 6125 SR 654 over Mosquito Crk B.1 Matt Hamel 12/22/2011 CE BRPA Eval 14179 Approved

Archive2 3 Lycoming 973 24 93801 SR973 Roadway FloodRepair A.1.a, A.1.c Matt Hamel 10/12/2011 CE BRPA Eval 13490 Approved

Archive2 3 Lycoming 973 26 94181 SR 973 ov Loyalsock Creek A.1.a, B.1, B.4 Matt Hamel 10/17/2011 CE BRPA Eval 13724 Approved

Archive2 3 Lycoming 973 26 94181 SR 973 ov Loyalsock Creek A.1.a, B.1, B.4 Matt Hamel 10/17/2011 CE BRPA Reeval 14317 Approved

Archive2 3 Lycoming 973 27 94224 SR 973 ov Br Mill Creek A.4 Matt Hamel 10/12/2011 CE BRPA Eval 13493 Approved

Archive2 3 Lycoming 973 29 95292 SR 973 over Tr Larry's Cr B.1, B.3 Matt Hamel 3/16/2012 ED BRPA Eval 14667 Approved

Archive2 3 Lycoming 1003 22 6221 SR 1003 over Salt Run A.4 Matt Hamel 3/9/2012 ED BRPA Eval 14566 Approved

Archive2 3 Lycoming 2014 91 94595 SR 2014 ov Loyalsock Crk A.4 Matt Hamel 11/15/2011 CE BRPA Eval 13941 Approved

Archive2 3 Lycoming 2039 7 93950 SR2039 RoadwayFloodRepair A.1.a, A.1.c, A.1.f Kyle Bunce 9/28/2011 CE BRPA Eval 13354 Approved

Archive2 3 Lycoming 3026 2 87891 SR3026 ov Trb Beautys Run B.1 Matt Hamel 8/22/2011 ED BRPA Eval 14239 Approved

Archive2 3 Montour 54 80 94545 SR 54 over Mahoning Creek A.4 Matt Hamel 11/15/2011 CE BRPA Eval 13936 Approved

Archive2 3 Montour 54 73M 88621 SR 54 and Montour Street A.1.a, A.1.b Kyle Bunce 8/19/2011 CE 1b Eval 14170 Approved

Archive2 3 Montour 54 77M 93753 SR54 Roadway Flood Repair A.1.a Kyle Bunce 9/19/2011 Coordination was conducted with the CRP

archaeologist and there are no concerns.

Per coordination with the CRP historian, the

project is outside of the Danville Historic

District.

CE BRPA Eval 13234 Approved

Archive2 3 Montour 1003 17 86450 DF Deck SD-COG 2012 B.2 Matt Hamel and Scott Shaffer 1/10/2012 ED BRPA Eval 14193 Approved

Archive2 3 Montour 1007 15 83980 SR 1007 over Mud Creek B.1 Matt Hamel and Scott Shaffer 7/26/2011 ED BRPA Eval 14329 Approved

Archive2 3 Montour 2017 14 93938 SR2017 Slide Repair Flood A.1.a, A.15 Matt Hamel 10/14/2011 CE BRPA Eval 13524 Approved

Archive2 3 Northumberland 0 54E 92382 Wolverton Street Enhance A.1.a, A.1.e, A.6.c, A.7.a, A.7.b, A.8.a, A.8.b Matt Hamel, District 3-0 Cultural Resource

Profess

3/7/2012 CE BRPA Eval 14700 Approved

Archive2 3 Northumberland 0 RRX 90590 Chesnut St Railroad Xing A.2 Kyle Bunce 1/4/2012 CE BRPA Eval 14226 Approved

Archive2 3 Northumberland 0 RRX 90616 Shamokin RR Xing A.2, A.6.c Kyle Bunce 5/9/2011 See email attached below for coordination

with CRP.

CE BRPA Eval 12565 Approved

Archive2 3 Northumberland 45 23M 88941 Noaker St to Montour Co B.3 Matt Hamel 6/16/2011 CE BRPA Eval 12800 Approved

Archive2 3 Northumberland 61 110 94231 SR 61 ov NBr Shamokin Crk A.12 Scott Shaffer 11/9/2011 CE BRPA Eval 13839 Approved

Archive2 3 Northumberland 61 110 94231 SR 61 ov NBr Shamokin Crk A.4, A.15 Scott Shaffer 11/9/2011 CE BRPA Eval 13839 Approved

Archive2 3 Northumberland 61 113 94667 SR 61 ov Paxinos Creek A.4, A.12 Matt Hamel 11/15/2011 CE BRPA Eval 13984 Approved

Archive2 3 Northumberland 80 108 87602 I-80 Brg Epoxy Northd Co A.4 Kyle Bunce 2/2/2012 CE BRPA Eval 14356 Approved

Archive2 3 Northumberland 125 16R 90617 Shamokin RR Xing #2 A.2 Matt Hamel 1/19/2012 CE BRPA Eval 14495 Approved

Archive2 3 Northumberland 147 95 94238 SR 147 over Cogan Run A.4, A.15 Scott Shaffer 11/9/2011 CE BRPA Eval 13842 Approved

Archive2 3 Northumberland 147 96 94240 SR 147 over Scalholtz Crk A.1.a Scott Shaffer 11/9/2011 CE BRPA Eval 13843 Approved

Archive2 3 Northumberland 180 82M 93490 I-180 over SR 54 A.4 Kyle Bunce 7/20/2011 ED BRPA Eval 12924 Approved

Archive2 3 Northumberland 225 36 93951 SR 225 Embankment Flood 1 A.1.a, A.15 Matt Hamel 10/20/2011 CE BRPA Eval 13612 Approved

Archive2 3 Northumberland 225 36 93951 SR 225 Embankment Flood 1 A.1.c, A.15 Matt Hamel 10/20/2011 CE BRPA Eval 13612 Approved

Archive2 3 Northumberland 225 40 94052 SR225 BridgeRehabFlood 2 A.1.a, A.4 Matt Hamel 10/19/2011 CE BRPA Eval 13614 Approved

Archive2 3 Northumberland 225 43 94055 SR225 BridgeRehabFlood 5 A.1.a, A.15 Matt Hamel 10/19/2011 CE BRPA Eval 13636 Approved

Archive2 3 Northumberland 225 45 94105 SR 225 over Fiddlers Run A.1.a, A.1.c, A.15 Matt Hamel 10/20/2011 CE BRPA Eval 13640 Approved

Archive2 3 Northumberland 225 37M 79484 Trevorton to Shamokin A.1.a, A.1.c, A.3 Kyle Bunce 6/21/2011 Coordination was conducted with CRP's. See

attachment below.

CE 1b Eval 12788 Approved

Archive2 3 Northumberland 2009 5 88002 SR2009 ov Tb Shamokin Crk B.1 Scott Shaffer 8/17/2011 ED BRPA Eval 14369 Approved

Archive2 3 Northumberland 2040 5 94026 SR 2040 Flood Repair A.1.a Matt Hamel 10/17/2011 CE BRPA Eval 13544 Approved

Archive2 3 Northumberland 3010 11 94232 SR 3010 over Schwaben Crk A.15 Scott Shaffer 11/9/2011 CE BRPA Eval 13840 Approved

Archive2 3 Northumberland 3010 13 94241 SR3010ovTb Mahantango Crk A.4 Scott Shaffer 11/9/2011 CE BRPA Eval 13841 Approved

Archive2 3 Northumberland 3018 11 94602 SR 3018 Flood Repair A.4 Matt Hamel 10/18/2011 CE BRPA Eval 13634 Approved

Archive2 3 Northumberland 4009 11 94547 SR 4009 over Shamokin Crk A.4 Matt Hamel 11/15/2011 CE BRPA Eval 13937 Approved

Archive2 3 Northumberland 4018 16 94291 SR 4018 ov Indian Springs A.1.a, A.1.c, A.4, A.12 Matt Hamel 10/26/2011 CE BRPA Eval 13670 Approved

Archive2 3 Snyder 1011 16 88009 SR 1011 over Tb Penns Crk B.1 Matt Hamel 12/6/2011 ED BRPA Eval 14324 Approved

Archive2 3 Snyder 1017 7 6877 SR1017ov Rolling Green Rn B.1, B.3 Matt Hamel 12/12/2011 CE BRPA Eval 14137 Approved

Archive2 3 Snyder 4008 4 83482 SR 4008 over Middle Creek A.4 Kyle Bunce 8/17/2011 CE BRPA Eval 13068 Approved

Archive2 3 Sullivan 42 79 94195 SR 42 over Mosey Run A.1.c, A.4 Scott Shaffer 11/7/2011 CE BRPA Eval 13816 Approved

Archive2 3 Sullivan 87 73 93726 SR 87 Flood Damage A.6.a Matt Hamel 10/5/2011 These projects are exempt from Section 106

under the FHWA Emergency Relief

Programmatic Agreement Stipulation III,

(see email attached below for each project

and activity exemption).

CE BRPA Eval 13432 Approved

Archive2 3 Sullivan 87 83 93929 SR 87 Pipe Replace Flood A.1.a, A.1.c, A.3, A.15 Matt Hamel 10/12/2011 93929: 2.A.3, 2.A.15 and 2.A.1.a; 93982:

2.A.1.a & 2.A.1.c; 93983: 2.A.1.a & 2.A.1.c;

93984: 2.A.1.a, 2.A.4 and 2.A.15

CE BRPA Eval 13517 Approved

Archive2 3 Sullivan 87 98 94367 SR 87 over Lick Run A.4 Scott Shaffer 11/9/2011 CE BRPA Eval 13860 Approved

Archive2 3 Sullivan 87 99 94417 SR 87 ov Lt Loyalsock Crk A.15 Matt Hamel 10/14/2011 CE BRPA Eval 13591 Approved

Archive2 3 Sullivan 87 102 94542 SR 87 ov Lt Loyalsock Crk A.4 Matt Hamel 11/15/2011 CE BRPA Eval 13931 Approved

Archive2 3 Sullivan 87 103 94551 SR 87 over Loyalsock Crk A.4 Matt Hamel 11/15/2011 CE BRPA Eval 13932 Approved

Archive2 3 Sullivan 154 5 93729 SR 154 Flood Damage A.1.a Matt Hamel 10/5/2011 Shoulder backup work. CE BRPA Eval 13433 Approved

Archive2 3 Sullivan 154 44 93084 SR154 over Pole Bridge Rn A.4 Kyle Bunce 5/27/2011 CE BRPA Eval 12699 Approved

Archive2 3 Sullivan 154 48 93980 SR 154 ov Hoagland Branch A.4 Scott Shaffer 11/7/2011 CE BRPA Eval 13818 Approved

Archive2 3 Sullivan 154 52 94048 SR 154 Flood Repair A.1.a Matt Hamel 10/17/2011 CE BRPA Eval 13551 Approved

Archive2 3 Sullivan 154 59 94351 SR 154 ov Pole Bridge Run A.1.a, A.4 Scott Shaffer 11/9/2011 CE BRPA Eval 13863 Approved

Archive2 3 Sullivan 220 134 94077 SR 220 Flood Repair A.1.a Matt Hamel 10/17/2011 CE BRPA Eval 13550 Approved

Archive2 3 Sullivan 220 144 94190 US 220 RoadwayFloodRepair A.1.a Matt Hamel 10/11/2011 CE BRPA Eval 13482 Approved

Archive2 3 Sullivan 220 145 94192 US 220 over Birch Creek A.1.c, A.4, A.12 Scott Shaffer 11/7/2011 CE BRPA Eval 13826 Approved

Archive2 3 Sullivan 220 154 94553 US 220 over Outlet Creek A.4, A.12 Matt Hamel 11/15/2011 CE BRPA Eval 13939 Approved

Archive2 3 Sullivan 1004 28 95499 SR 1004 ov Lopez Creek DF B.2 Matt Hamel 4/20/2012 ED BRPA Eval 14778 Approved

Archive2 3 Sullivan 2003 4 82231 Sullivan Bridge Overlays A.4 Kyle Bunce 5/17/2011 ED BRPA Eval 12646 Approved

Archive2 3 Sullivan 2003 4 82231 Sullivan Bridge Overlays A.4 Kyle Bunce 5/17/2011 ED BRPA Reeval 14562 Approved

Archive2 3 Tioga 6 GRP 82229 Tioga Bridge Overlays A.4 Kyle Bunce 6/23/2011 All work will be completed within the

existing footprint. Coordination with the

CRP Historian is attached below.

ED BRPA Eval 12773 Approved

Archive2 3 Tioga 14 91 94533 SR 14 ov Tb Lycoming Crk A.1.c, A.1.d Matt Hamel 11/15/2011 CE BRPA Eval 13925 Approved

Archive2 3 Tioga 15 147 95265 US 15 over SR 2026 A.4 Matt Hamel 2/22/2012 ED BRPA Eval 14591 Approved

Archive2 3 Tioga 287 134 7039 SR 287 over Tioga River B.2 Scott Shaffer 7/27/2011 See email attached below. CE BRPA Eval 12983 Approved

Archive2 3 Tioga 328 GRP 82371 Tioga Bridge Painting A.4 Kyle Bunce 8/12/2011 CE BRPA Eval 12929 Approved

Archive2 3 Tioga 549 13 7329 SR 549 over Elk Run B.1 Matt Hamel 12/6/2011 CE BRPA Eval 14124 Approved

Archive2 3 Union 44 54R 95381 SR 44 RRX Allenwood A.2, A.6.c Kyle Bunce 4/25/2012 Coodination was conducted with CRP's. CE BRPA Eval 14592 Approved

Archive2 3 Union 45 57E 93049 Market Street Phase 2 A.7.b, A.8.a Matthew Hamel 7/29/2011 See attached letter. CE BRPA Eval 12946 Approved

Archive2 3 Union 235 2 7413 SR235 over Laurel Run B.1 Matt Hamel 12/6/2011 ED BRPA Eval 14325 Approved

Archive2 3 Union 3003 13 83986 SR 3003 over Tb Penns Crk B.1 Matt Hamel and Scott Shaffer 7/26/2011 ED BRPA Eval 14305 Approved

Archive2 4 Lackawanna 0 --- 93207 Bear Creek Water Line ROW A.3, A.13 Kevin Mock 9/15/2011 Acquisition of ROW for waterline from Bear

Creek village to interstate toll building.

ED 1a Eval 13059 Approved

Archive2 4 Lackawanna 6 BRC 94855 Dist Wide Bridge Cleaning A.4 Amy Lolli 3/23/2012 ED BRPA Eval 14625 Approved

Archive2 4 Lackawanna 11 0 92397 LLTS 4-12-BR 1 A.4, B.2 Amy Lolli 8/31/2011 ED BRPA Eval 12830 Approved

Archive2 4 Lackawanna 11 214 8400 Birney Plaza Signals A.1.a, A.3, A.5, A.6.a, A.6.b, A.7.a, A.7.c Greg Augustine 9/15/2011 Project originally cleared 7/7/2003 as Stip

D.2.

CE BRPA Eval 13198 Approved

Archive2 4 Lackawanna 81 0 93734 LLTS 4-12A-BR 1 A.1.a, A.1.c, A.1.d, A.1.e, A.3, A.15 Kevin Mock 1/31/2012 ED BRPA Eval 14769 Approved

Archive2 4 Lackawanna 81 D99 93269 Disposition #99, Rescigo A.14 Amy Lolli 7/6/2011 ED BRPA Eval 12843 Approved

Archive2 4 Lackawanna 171 270 8359 Elk Creek Bridge B.1 Kevin Mock 9/6/2011 Half-width construction of new bridge. CE BRPA Eval 13256 Approved

Archive2 4 Lackawanna 307 ELS 94696 SR 0307 Shoulders / ELRS A.1.a Greg Augstine 2/1/2012 Re-paving existing paved shoulders. CE BRPA Eval 14488 Approved

Archive2 4 Lackawanna 407 250 8311 Lackawanna Lake Br B.1 Kevin Mock 9/6/2011 On-line bridge replacement and detour. CE BRPA Eval 13255 Approved

Archive2 4 Lackawanna 435 252 8244 PA 435 Bridge ov SR 348 B.1 Kevin Mock 12/1/2011 Bridge is not eligible for the NR. No historic

properties effected by the proposed project.

CE 1b Eval 11942 Approved

Archive2 4 Lackawanna 438 253 83936 SR 438 Ov. SB Tunk. Ck A.4, B.2, B.3 Amy Lolli 8/19/2011 ED BRPA Eval 12846 Approved

Archive2 4 Lackawanna 632 60M 93457 Group 4-11-ST8 A.1.a Amy Lolli 9/12/2011 ED BRPA Eval 13131 Approved

Archive2 4 Lackawanna 1009 270 8008 SR 1009 over Fall Brook B.1 Kevin Mock 5/20/2011 On-line bridge replacement with detour. CE 1b Eval 9663 Approved

Archive2 4 Lackawanna 3005 250 8181 SR 3005 Ov. Gardners Crk B.1 Kevin Mock 11/15/2011 ED 1b Eval 8065 Approved

Archive2 4 Lackawanna 3019 270 8183 Main Street Bridge B.1 Kevin Mock 12/1/2011 The bridge is not eligible. There are no

historic properties near the bridge.

CE 1b Eval 11941 Approved

Archive2 4 Lackawanna 3020 EMG 92634 Linden Street Bridge Emer A.4, B.2 Amy Lolli 6/16/2011 CE BRPA Eval 12754 Approved

Archive2 4 Lackawanna 7410 EMG 8086 Main Street Bridge Moosic B.1 Kevin Mock 9/1/2011 The bridge was built in 1956 and

determined ineligible for the NRHP. There

are no recorded historic districts around the

bridge and the bridge does not contribute

to any historic districts.

CE BRPA Eval 13073 Approved

Archive2 4 Luzerne 0 --- 93126 Co Rd 21 Church Rd Paving A.1.a Kevin Mock 11/2/2011 CE BRPA Eval 13814 Approved

Archive2 4 Luzerne 11 0 70211 Pittston Streetscape Ph 1 A.1.a, A.1.b, A.3, A.7.a, A.7.b, A.7.c, A.8.a Kevin Mock 10/27/2011 CE 1b Reeval 13646 Approved

Archive2 4 Luzerne 29 LEE 94114 SR 29 Emg Road Repair A.12, A.15 Kevin Mock 9/29/2011 This project is exempt from Section 106

under the FHWA Emergency Relief

Programmatic Agreement Stipulation III, B.1

CE BRPA Eval 13363 Approved

Archive2 4 Luzerne 81 0 94908 All Weather Pavt Mark 12 A.1.f, A.6.b Amy Lolli 2/17/2012 CE BRPA Eval 14463 Approved

Archive2 4 Luzerne 81 357 67494 SR 0081 Bridges Laflin B.1 Kevin Mock 4/5/2012 This project is exempt from Section 106

review per the signed Programmatic

Agreement between FHWA, SHPO, and

PENNDOT.

CE BRPA Eval 14717 Approved

Archive2 4 Luzerne 81 357 67494 SR 0081 Bridges Laflin B.1 Kevin Mock 4/5/2012 This project is exempt from Section 106

review per the signed Programmatic

Agreement between FHWA, SHPO, and

PENNDOT.

CE BRPA Eval 14717 Approved

Archive2 4 Luzerne 81 357 67494 SR 0081 Bridges Laflin B.1 Kevin Mock 4/5/2012 This project is exempt from Section 106

review per the signed Programmatic

Agreement between FHWA, SHPO, and

PENNDOT.

CE BRPA Eval 14717 Approved

Archive2 4 Luzerne 81 357 67494 SR 0081 Bridges Laflin B.1 Kevin Mock 4/5/2012 This project is exempt from Section 106

review per the signed Programmatic

Agreement between FHWA, SHPO, and

PENNDOT.

CE BRPA Eval 14717 Approved

Archive2 4 Luzerne 81 357 67494 SR 0081 Bridges Laflin B.1 Kevin Mock 4/5/2012 This project is exempt from Section 106

review per the signed Programmatic

Agreement between FHWA, SHPO, and

PENNDOT.

CE BRPA Eval 14717 Approved

Archive2 4 Luzerne 81 357 67494 SR 0081 Bridges Laflin B.1 Kevin Mock 4/5/2012 This project is exempt from Section 106

review per the signed Programmatic

Agreement between FHWA, SHPO, and

PENNDOT.

CE BRPA Eval 14717 Approved

Archive2 4 Luzerne 81 357 67494 SR 0081 Bridges Laflin B.2 Kevin Mock 4/5/2012 This project is exempt from Section 106

review per the signed Programmatic

Agreement between FHWA, SHPO, and

PENNDOT.

CE BRPA Eval 14717 Approved

Archive2 4 Luzerne 81 357 67494 SR 0081 Bridges Laflin B.2 Kevin Mock 4/5/2012 This project is exempt from Section 106

review per the signed Programmatic

Agreement between FHWA, SHPO, and

PENNDOT.

CE BRPA Eval 14717 Approved

Archive2 4 Luzerne 92 LEE 94116 SR 92 Emg Road Repair A.1.a, A.3, A.12, A.15 Kevin Mock 9/28/2011 This project is exempt from Section 106

under the FHWA Emergency Relief

Programmatic Agreement Stipulation III, B.

1

CE BRPA Eval 13348 Approved

Archive2 4 Luzerne 118 LEE 94138 SR 118 Emg Road Repair A.1.a, A.1.c, A.12, A.15 Kevin Mock 10/6/2011 This project is exempt from Section 106

under the FHWA Emergency Relief

Programmatic Agreement Stipulation III, B.

1, 5 6, and 9.

CE BRPA Eval 13467 Approved

Archive2 4 Luzerne 1009 LEE 94632 Debris Removal (LEE) A.12 Kevin Mock 11/23/2011 This project is exempt from Section 106

under the FHWA ERPA Stip III, B.9; This

project has limited or no effect on historic

resources under the following

programmatic allowances in Appendix A:

FEMA PA I.L and III

CE BRPA Eval 13989 Approved

Archive2 4 Luzerne 3012 LEE 93968 Emergency Scour Repair A.4, A.12 Amy Lolli 9/28/2011 9/27/11- Guidance-For Section 106 Flood

Emergency Projects 2011. "This project has

limited or no effect on historic resources

under the following programmatic

allowances in App.A: FEMA Programmatic

Agreement - FEMA Funding - 3.(B) App. A.H.

- VI.A."

ED BRPA Eval 13287 Approved

Archive2 4 Luzerne 4013 LEE 94134 4013 & 4015 Emg Rd Repair A.1.a, A.1.c, A.3, A.12, A.15 Kevin Mock 9/29/2011 This project has limited or no effect on

historic resources under the following

programmatic allowences in Appendix A:

FEMA Programmatic Agreement V. B, C, G,

H

ED BRPA Eval 13366 Approved

Archive2 4 Luzerne 7208 BRG 8912 County Rd Br #30,Dorrance B.1 Kevin Mock 10/18/2011 This project is exempt from Section 106

review per the 2010 PA, Appendix C.2.B.1.c

and C.2.B.1.d

CE 1b Eval 3379 Approved

Archive2 4 Luzerne 7208 BRG 8913 County Rd Br #29,Dorrance B.1 Kevin Mock 10/18/2011 This project is exempt from Section 106

review, per the PA App. C.2.B.1.c and

C.2.B.1.d

CE 1b Eval 3380 Approved

Archive2 4 Luzerne 7230 BRG 8927 T-336 Br., Sugarloaf Twp B.1 Kevin Mock 11/2/2011 The bridge is not eligible for listing in the

National Register of Historic Places. A

geomorphological investigation found no

potential for archaeological resources.

CE 1b Reeval 13713 Approved

Archive2 4 Luzerne 7239 LEE 95248 Debris Removal A.3, A.12 Kevin Mock 2/17/2012 This project has limited or no effect on

historic resources under the following

programmatic allowances in Appendix A:

FEMA Programmatic Agreement: Stipulation

III.

CE BRPA Eval 14420 Approved

Archive2 4 Luzerne 7304 BRG 9037 Sidney St. BRG, W-B City B.1 Kevin Mock 9/20/2011 On line bridge replacement w/detour. All

work will be limited to existing ROW or

within temporary construction easement

adjacent to ROW.

CE BRPA Reeval 13243 Approved

Archive2 4 Pike 6 0 92398 NEPA 4-12-BR 3 A.4, B.2 Amy Lolli 7/26/2011 ED BRPA Eval 12821 Approved

Archive2 4 Pike 6 453 9337 SR 0006 Ov Sawkill Creek A.4, B.2 Amy Lolli 7/26/2011 ED BRPA Eval 12897 Approved

Archive2 4 Pike 84 448 75762 I84-I4R SR 6 to NY Line A.1.a, A.1.c, A.3, A.4, A.5 Kevin Mock 6/15/2011 Interstate highway exempted from NHPA.

All work will be completed within existing

ROW.

CE 1b Eval 12566 Approved

Archive2 4 Pike 590 60M 93572 Group 4-11-ST9 A.1.a Amy Lolli 9/12/2011 ED BRPA Eval 13132 Approved

Archive2 4 Susquehanna 29 551 9700 SR 29 over Snake Crk #1 B.1 Kevin Mock 7/29/2011 The project will include a temporary run-

around but will not affect historic properties

or archaeological resources.

ED BRPA Eval 12766 Approved

Archive2 4 Susquehanna 29 551 9700 SR 29 over Snake Crk #1 B.1 Kevin Mock 7/29/2011 The project will include a temporary run-

around but will not affect historic properties

or archaeological resources.

ED BRPA Reeval 13644 Approved

Archive2 4 Susquehanna 29 592 88584 SR 29 Slides, Phase 2 A.1.a, A.15 Amy Lolli 9/7/2011 ED BRPA Eval 14754 Approved

Archive2 4 Susquehanna 167 551 84836 Bridge Maint.-NT-2009 A.4 Amy Lolli 1/25/2012 ED BRPA Eval 14169 Approved

Archive2 4 Susquehanna 167 LEE 93972 SR 167 Emerg Brg Repair A.4, A.12 Amy Lolli 9/28/2011 9/27/11- Guidance-For Section 106 Flood

Emergency Projects 2011. "This project has

limited or no effect on historic resources

under the following programmatic

allowances in App.A: FEMA Programmatic

Agreement - FEMA Funding - 3.(B) App. A.H.

- VI.A."

CE BRPA Eval 13289 Approved

Archive2 4 Susquehanna 171 LEE 94118 SR 171 Emg Rd Repairs A.1.a, A.1.c, A.12, A.15 Kevin Mock 10/6/2011 This project is exempt from Section 106

under the FHWA Emergency Relief

Programmatic Agreement Stipulation III, B.

1, 5, 6, 9.

CE BRPA Eval 13390 Approved

Archive2 4 Susquehanna 267 552 9715 PA 267/Rigs Pond B.1 Kevin Mock 8/25/2011 ED BRPA Eval 12764 Approved

Archive2 4 Susquehanna 267 553 67522 Middle BR.Wyalusing CK B.1 Kevin Mock 8/25/2011 CE BRPA Eval 12767 Approved

Archive2 4 Susquehanna 267 ELS 92566 SR 267 Shoulder/Edgeline A.5 Amy Lolli 5/5/2011 CE BRPA Eval 12575 Approved

Archive2 4 Susquehanna 706 BRG 92399 NT 4-12-BR 2 A.4, B.2 Amy Lolli 8/19/2011 ED BRPA Eval 12381 Approved

Archive2 4 Susquehanna 706 LEE 94671 SR 706 Slope Failures A.1.c, A.3, A.15 Kevin Mock 3/29/2012 This pojrect is exempt from Section 106

under teh FHWA Emergency Relief

Programmatic Agreement Stipulation, III,B.

1 and 5.

CE BRPA Eval 14686 Approved

Archive2 4 Susquehanna 1010 551 67558 Salt Lick Ck, Great Bend B.1 Kevin Mock 8/5/2011 A geomorphological investigation for the

temporary run-around identified that the

entire APE is recent alluvium and has no

potential for archaeological resources.

There are no other historic properties.

CE BRPA Eval 12765 Approved

Archive2 4 Susquehanna 1025 LEE 94137 Emergency Road Repairs A.1.a, A.1.c, A.3, A.4, A.12, A.15 Kevin Mock 10/28/2011 This project has limited or no effect on

historic resources under the following

programmatic allownces in Appendix A:

FEMA Programmatic Agreement I.A, B, C;

V.C, G; VI.A.

ED BRPA Eval 13562 Approved

Archive2 4 Susquehanna 1027 11F 93713 Susq Emg Road Repairs A.1.a, A.3, A.12, A.15 Kevin Mock 9/22/2011 All work for the SR 1027 project should be

limited to within the existing ROW. If work is

to exceed these limits, the District

Archaeologist should be consulted to avoid

impacts to potential archaeological

resources.

ED BRPA Eval 13105 Approved

Archive2 4 Susquehanna 3023 FLD 74731 SR 3023 Slope Repair A.12, A.15 Kevin Mock 4/10/2012 There are no historic properties within the

project APE.

CE 1b Reeval 14671 Approved

Archive2 4 Wyoming 6 791 70153 Tunkhannock Park & Ride A.11 Kevin Mock 1/17/2012 The project is located within the National

Register-listed Tunkhannock Historic

District. The Project should be designed to

be sympathetic to the district.

CE BRPA Eval 14285 Approved

Archive2 4 Wyoming 6 ENH 65191 Iroquois Trail, Tioga St. A.8.c Kevin Mock 8/19/2011 The project will be on the existing alignment

of the abandoned Lehigh Valley Railroad

Montrose Branch. The line is not eligible for

the National Register.

CE BRPA Eval 14056 Approved

Archive2 4 Wyoming 29 LE2 94128 SR 29 Emg Road Repair A.1.a, A.1.c, A.12, A.15 Kevin Mock 10/12/2011 This project is exempt from Section 106

under the FHWA Emergency Relief

Programmatic Agreement Stipulation III, B.

1, 5, 6, 7, 8, 9.

CE BRPA Eval 13529 Approved

Archive2 4 Wyoming 29 LEE 93800 SR 29 Emergency Rd Repair A.1.a, A.1.c, A.3, A.15 Kevin Mock 9/22/2011 ED BRPA Eval 13261 Approved

Archive2 4 Wyoming 87 11F 93712 SR 87 Emg Road Repair A.1.a, A.1.c, A.12, A.15 Kevin Mock 9/12/2011 Seg. 210 cleared for cultural resources in

Aug 2010 (see ER# 10-8080-131) and Seg.

130 was cleared in Nov. 2007 (see ER# 06-

6035-131).

ED BRPA Eval 13104 Approved

Archive2 4 Wyoming 87 LEE 94131 87 & 3003 Emg Road Repair A.1.a, A.1.c, A.15 Kevin Mock 10/13/2011 This project is exempt from Section 106

under the FHWA Emergency Relief

Programmatic Agreement Stipulation III, B.

1. 5. 6. 8.

CE BRPA Eval 13483 Approved

Archive2 4 Wyoming 309 EMG 94432 SR 309 Void A.1.a, A.1.c, A.3, A.4, A.12, A.15 Kevin Mock 11/2/2011 This project is exempt from Section 106

under the FHWA Emergency Relief

Programmatic Agreement Stipulation III, B.

1, 5, 6.

CE BRPA Eval 13832 Approved

Archive2 4 Wyoming 1017 EN2 71689 College Ave. Stsc. Ph. II A.7.a, A.7.b, A.7.c, A.8.a, B.6.a Kevin Mock 9/21/2011 Factoryville is not eligible for the National

Register of Historic Places.

CE 1b Reeval 12647 Approved

Archive2 4 Wyoming 2005 LEE 94611 SR 2005 Slide A.12, A.15 Kevin Mock 4/11/2012 This project is exempt from Section 106

under the FHWA Emergency Relief

Programmatic Agreement Stipulation III, B.

1 and B.6.

ED BRPA Eval 14633 Approved

Archive2 4 Wyoming 2007 LEE 94771 SR 2007 over Martin Creek A.3, A.12 Kevin Mock 2/17/2012 This project has limited or no effect on

historic resources under the following

programmatic allowances in Appendix A:

FEMA Programmatic Agreement: Stipulation

III

ED BRPA Eval 14449 Approved

Archive2 4 Wyoming 2007 LEE 94771 SR 2007 over Martin Creek A.3, A.12 Kevin Mock 2/17/2012 This project has limited or no effect on

historic resources under the following

programmatic allowances in Appendix A:

FEMA Programmatic Agreement: Stipulation

III

ED BRPA Reeval 14701 Approved

Archive2 4 Wyoming 3001 11F 93695 SR 3001 over Mehoopany Ck A.1.a, A.1.e, A.3, A.12, A.15, B.1, B.2, B.4 Kevin Mock 9/12/2011 The bridge at Seg 180 had already been

cleared for cultural resources caused by

flooding in April 2010. There are no other

previously recorded historic properties

within the 3001 corridor.

ED BRPA Eval 13087 Approved

Archive2 4 Wyoming 3001 F11 93730 SR 3001 Emg Road Repair A.1.a, A.1.e, A.12, A.15 Kevin Mock 9/12/2011 There are no historic properties within this

section of SR 3001.

ED BRPA Eval 13106 Approved

Archive2 4 Wyoming 3001 IR2 94247 SR 3001 Mehoopany Ck Perm B.1, B.3, B.4 Kevin Mock 2/13/2012 The bridge at Seg 180 had already been

cleared for cultural resources caused by

flooding in April 2010. There are no other

previously recorded historic properties

within the 3001 corridor.

ED BRPA Eval 14426 Approved

Archive2 4 Wyoming 3002 11F 93209 SR 3002 Emg Road Repair A.1.a, A.1.c, A.1.d, A.12, A.15 Kevin Mock 9/21/2011 ED BRPA Eval 13089 Approved

Archive2 5 Berks 0 --- 95186 Group 5-12-GR1,3&5 A.1.c, A.1.e Steven W. Bruch 3/1/2012 Due to its low potential for effects to

cultural resources, the project is exempt

from further review in accordance with the

2010, Sec 106 PA, Appendix C - Exempted

Projects.

ED 1a Eval 14534 Approved

Archive2 5 Berks 10 LEE 94455 SR 10 Flood Repairs A.1.a Steven W. Bruch/Environmental Planner 10/11/2011 CE BRPA Eval 13464 Approved

Archive2 5 Berks 12 POC 94516 Surface Improvement 1A A.1.a Steven W. Bruch 12/20/2011 ED BRPA Eval 14032 Approved

Archive2 5 Berks 12 POC 94520 Surface Treatment 1E-Micr A.1.a Kris Thompson 3/1/2012 This project falls within the exemption

guidelines of the 2010 Section 106

Programmatic Agreement, with little

potential to affect historic resources.

ED BRPA Eval 14469 Approved

Archive2 5 Berks 61 AWP 94965 District 5 AWPM FY 11-12 A.6.c Steven W. Bruch 3/22/2012 Due to its low potential for effects to

cultural resources, the project is exempt

from further review in accordance with the

2010, Sec 106 PA, Appendix C - Exempted

Projects.

CE 1a Eval 14626 Approved

Archive2 5 Berks 78 20M 87631 I-78 Frystown-Rehrersburg A.1.a, A.1.e Steven W. Bruch 2/29/2012 CE BRPA Eval 14506 Approved

Archive2 5 Berks 78 20M 87631 I-78 Frystown-Rehrersburg A.1.a, A.1.e Steven W. Bruch 3/28/2012 CE BRPA Reeval 14676 Approved

Archive2 5 Berks 100 POC 94517 Surface Treatment 1B-Micr A.1.a Steven W. Bruch 12/19/2011 ED BRPA Reeval 14138 Approved

Archive2 5 Berks 422 17M 92820 422 West Shore Resurface A.1.a, A.1.c, A.3, A.4 Jim Ruth 6/17/2011 CE BRPA Eval 12780 Approved

Archive2 5 Berks 662 LEE 94454 SR 662 Flood Repairs A.1.a Steven Bruch 10/4/2011 CE BRPA Eval 13418 Approved

Archive2 5 Berks 1010 BRM 91941 RATS BR Preserve & Repair A.4 Steven W. Bruch 11/10/2011 See attached project bridge list. CE 1b Reeval 13710 Approved

Archive2 5 Berks 2021 POC 94519 Surface Treatment 1D-Micr A.1.a Kris Thompson 12/27/2011 The project involves activities with little

potential to affect cultural resources and

qualifies as an exemption under the 2010

Section 106 Programmatic Agreement.

ED BRPA Eval 14188 Approved

Archive2 5 Berks 4016 POC 94518 Surface Treatment 1C A.1.a Kris Thompson 12/27/2011 This project involves activities with little

potential to affect cultural resources and

qualifies as an exemption under the 2010

Section 106 Programmatic Agreement.

ED BRPA Eval 14173 Approved

Archive2 5 Carbon 54 PYR 92988 SR 54 Resurface A.1.a Steven W. Bruch 5/10/2011 ED BRPA Eval 12619 Approved

Archive2 5 Carbon 80 06M 94842 I-80 Resurface-Turnpike W A.1.a Steven W. Bruch 2/9/2012 ED BRPA Eval 14406 Approved

Archive2 5 Carbon 903 03M 93545 SR 903 Pavement Presrvatn A.1.a, A.1.c, A.3 Jim Ruth 8/15/2011 CE BRPA Eval 13031 Approved

Archive2 5 Carbon 903 03M 93545 SR 903 Pavement Presrvatn A.1.a, A.1.c, A.3 Jim Ruth 8/15/2011 CE BRPA Reeval 14016 Approved

Archive2 5 Carbon 940 POC 95369 Surface Improvement 2D A.1.a Kris Thompson 3/13/2012 ED BRPA Eval 14576 Approved

Archive2 5 Carbon 940 POC 95369 Surface Improvement 2D A.1.a Jim Ruth 3/21/2012 ED BRPA Eval 14632 Approved

Archive2 5 Carbon 1005 02X 95270 Tannery Rd RR Crossing A.6.a Steven W. Bruch 5/2/2012 Due to its low potential for effects to

cultural resources, the project is exempt

from further review in accordance with the

2010, Sec 106 PA, Appendix C - Exempted

Projects.

CE 1a Eval 14812 Approved

Archive2 5 Carbon 2015 POC 94253 Surface Treatment 2B A.1.a Kris Thompson 12/27/2011 The scope of work has little potential to

affect cultural resources and qualifies as an

exemption under the 2010 Section 106

Programmatic Agreement.

ED BRPA Eval 14162 Approved

Archive2 5 Carbon 2015 POC 94253 Surface Treatment 2B A.1.a Kris Thompson 3/1/2012 The scope of work has little potential to

affect cultural resources and qualifies as an

exemption under the 2010 Section 106

Programmatic Agreement.

ED BRPA Reeval 14530 Approved

Archive2 5 Carbon 9301 LEE 95238 SR 93 Truck Escape-Flood A.3, A.15 Kris Thompson 3/13/2012 There are no standing structures within the

APE, and the soil has been previously

disturbed by the original ramp construction.

The SOW conforms to the 2010 Section 106

Programmatic Agreement requirements.

ED 1a Eval 14552 Approved

Archive2 5 Lehigh 0 --- 95345 Major Sign Maint. 2012 A.6.a Jim Ruth 3/12/2012 ED BRPA Eval 14588 Approved

Archive2 5 Lehigh 78 0 94678 I-78 ER at MSE wall A.15 Steven W. Bruch 11/4/2011 Due to its low potential for effects to

cultural resources, the project is exempt

from further review in accordance with the

2010, Sec 106 PA, Appendix C - Exempted

Projects.

CE 1a Eval 13866 Approved

Archive2 5 Lehigh 78 AWP 92278 District 5-0 AWPM FY10-11 A.6.b, A.6.c Steven W. Bruch 5/25/2011 The work only includes only installing all

weather pavement markers (roadway

appurtenances).

CE 1a Eval 12676 Approved

Archive2 5 Lehigh 78 BRM 91942 LVTS BR Preserve & Repair A.4 Steven W. Bruch 8/10/2011 CE 1b Eval 12306 Approved

Archive2 5 Lehigh 309 10M 83115 SR 309 Betterment A.1.a, A.4 Steven W. Bruch 5/24/2011 CE BRPA Reeval 12682 Approved

Archive2 5 Lehigh 329 LEE 94456 SR 329 Flood Project A.1.a Steven W. Bruch/Environmental Planner 10/11/2011 CE BRPA Eval 13471 Approved

Archive2 5 Lehigh 378 01S 95190 378 HTCable MedianBarrier A.1.e Jim Ruth 4/3/2012 CE BRPA Eval 14710 Approved

Archive2 5 Lehigh 378 02B 85684 SR 378 over Saucon Creek A.4 Steven W. Bruch 10/26/2011 ED BRPA Eval 12448 Approved

Archive2 5 Lehigh 1006 LEE 95246 SR 1006 Flood Project A.1.a Steven W. Bruch 3/7/2012 CE BRPA Eval 14572 Approved

Archive2 5 Lehigh 1017 LEE 94730 SR 1017 Flood Repairs A.1.a, A.1.c Steven W. Bruch 11/17/2011 CE BRPA Eval 13992 Approved

Archive2 5 Lehigh 1021 LEE 93742 SR 1021 Flood Damage A.15 Steven W. Bruch 9/12/2011 CE BRPA Eval 13130 Approved

Archive2 5 Lehigh 1021 LEE 93742 SR 1021 Flood Damage A.15 Steven W. Bruch 9/12/2011 CE BRPA Reeval 13160 Approved

Archive2 5 Lehigh 2040 POC 94334 Surface Improvement 3A A.1.a Steven W. Bruch 1/30/2012 ED BRPA Eval 14316 Approved

Archive2 5 Lehigh 2040 POC 94334 Surface Improvement 3A A.1.a Steven W. Bruch 2/29/2012 ED BRPA Reeval 14526 Approved

Archive2 5 Lehigh 3014 POC 94337 Surface Treatment 3C A.1.a Kris Thompson 12/27/2011 The scope of work has little potential to

affect cultural resources and qualifies as an

exemption under the 2010 Section 106

Programmatic Agreement.

ED BRPA Eval 14165 Approved

Archive2 5 Lehigh 4040 POC 94335 Surface Treatment 3B-Micr A.1.a Steven W. Bruch 2/1/2012 ED BRPA Eval 14327 Approved

Archive2 5 Lehigh 4040 POC 94335 Surface Treatment 3B-Micr A.1.a Steven W. Bruch 2/29/2012 ED BRPA Reeval 14527 Approved

Archive2 5 Monroe 115 01S 94709 NEPA Cable Guiderail #2 A.1.c Steven W. Bruch 3/5/2012 CE BRPA Eval 14440 Approved

Archive2 5 Monroe 611 POC 94472 Surface Improvement 4A A.1.a, B.6.b Kris Thompson 11/14/2011 See above. ED BRPA Eval 13877 Approved

Archive2 5 Monroe 2012 POC 94473 Surface Improvement 4A A.1.a Jim Ruth 11/29/2011 ED BRPA Eval 14028 Approved

Archive2 5 Monroe 4006 POC 94474 Surface Improvement 4B A.1.a Steven W. Bruch 12/8/2011 ED BRPA Eval 13982 Approved

Archive2 5 Northampton 0 --- 92343 HellertownGov Cmplx Stscp A.8.a, B.5.b, B.6.a, B.6.b Kristina Thompson 4/18/2012 The scope of work conforms to the

requirements of the 2010 Section 106

Programmatic Agreement. No historic

district or eligible properties are present

within the APE.

CE BRPA Eval 14805 Approved

Archive2 5 Northampton 0 RLE 93569 Hanover Township-ARLE A.6.d Jim Ruth 5/3/2012 ED BRPA Eval 14835 Approved

Archive2 5 Northampton 0 RLE 94157 Lehigh Township ARLE A.6.c Jim Ruth 1/27/2012 ED BRPA Eval 14330 Approved

Archive2 5 Northampton 22 02M 93544 SR 22 Resurface A.1.a, A.1.c Jim Ruth 8/24/2011 CE BRPA Reeval 13048 Approved

Archive2 5 Northampton 33 LEE 94460 SR 33 Flood Repairs A.1.a Steven W. Bruch/Environmenal Planner 10/11/2011 CE BRPA Eval 13477 Approved

Archive2 5 Northampton 512 03X 95405 SR 512-Walnut St- RR Xing A.6.a Steven W. Bruch 5/3/2012 Due to its low potential for effects to

cultural resources, the project is exempt

from further review in accordance with the

2010, Sec 106 PA, Appendix C - Exempted

Projects.

CE 1a Eval 14813 Approved

Archive2 5 Northampton 611 LE1 94457 SR 611 Flood - Seg 40 A.1.a Steven W. Bruch 10/13/2011 CE BRPA Eval 13476 Approved

Archive2 5 Northampton 1015 LEE 93827 SR 1015 Flood Repairs A.1.a Steven Bruch, Environmental Planner 9/26/2011 As per an email from the District Cultural

Resource Professionals they do not have any

concerns with the proposed project.

CE BRPA Eval 13300 Approved

Archive2 5 Northampton 2012 POC 94557 Surface Treatment 5A A.1.a Kris Thompson 12/28/2011 The scope of work has low potential to

affect historic properties. The work qualifies

as an exemption under the 2010 Section

106 Programmatic Agreement.

ED BRPA Eval 14154 Approved

Archive2 5 Northampton 2018 POC 95370 Surface Improvement 5B A.1.a Kris Thompson 3/13/2012 ED BRPA Eval 14577 Approved

Archive2 5 Schuylkill 0 --- 95187 Group 5-12-GR2,4&6 A.1.c, A.1.e Steven W. Bruch 3/1/2012 Due to its low potential for effects to

cultural resources, the project is exempt

from further review in accordance with the

2010, Sec 106 PA, Appendix C - Exempted

Projects.

ED 1a Eval 14535 Approved

Archive2 5 Schuylkill 25 LEE 94464 SR 25 Flood Repairs A.1.a, A.1.c Steven W. Bruch/Environemental Planner 10/11/2011 CE BRPA Eval 13480 Approved

Archive2 5 Schuylkill 61 03B 12700 S. Liberty St Brg_SR 61 B.1, B.2 Kris Thompson 4/30/2012 The scope of work meets the 2010 Section

106 Programmatic Agreement exemption

criteria.

CE 1b Reeval 14234 Approved

Archive2 5 Schuylkill 61 POC 95393 Surface Treatment 6A-Micr A.1.a Jim Ruth 4/9/2012 ED BRPA Eval 14728 Approved

Archive2 5 Schuylkill 81 LEE 93738 I-81N/SR125 Flood Repairs A.1.a Steven W. Bruch 9/12/2011 CE BRPA Eval 13135 Approved

Archive2 5 Schuylkill 209 04M 92312 SR209 Bettermnt-Schuylkil A.1.a, A.1.c, A.3 Steven W. Bruch 8/9/2011 CE BRPA Eval 12971 Approved

Archive2 5 Schuylkill 209 LEE 94691 SR 209 Flood Repairs A.1.a Steven Bruch/Environmental Planner 11/4/2011 CE BRPA Eval 13868 Approved

Archive2 5 Schuylkill 209 POC 94555 Surface Improvement 6D A.1.a Jim Ruth/Assistant Environmental Manager 12/1/2011 ED BRPA Eval 14029 Approved

Archive2 5 Schuylkill 209 RLE 93546 Pottsville-Signal-ARLE A.6.a, A.6.b Jim Ruth 1/10/2012 CE 1a Eval 14152 Approved

Archive2 5 Schuylkill 443 04X 95262 MainSt SchuylkillHaven RR A.6.a Steven W. Bruch 4/30/2012 Due to its low potential for effects to

cultural resources, the project is exempt

from further review in accordance with the

2010, Sec 106 PA, Appendix C - Exempted

Projects.

CE 1a Eval 14811 Approved

Archive2 5 Schuylkill 443 LE1 94461 SR 443 Flood - Seg 20 A.1.a, A.1.c Steven W. Bruch/Environmental Planner 10/11/2011 CE BRPA Eval 13478 Approved

Archive2 5 Schuylkill 443 LE1 94461 SR 443 Flood - Seg 20 A.1.a Kristina Thompson/Historic Preservation

Specialist

10/14/2011 CE BRPA Eval 13478 Approved

Archive2 5 Schuylkill 501 LEE 94463 SR 501 Flood Repairs A.1.a, A.1.c Steven W. Bruch 10/11/2011 CE BRPA Eval 13479 Approved

Archive2 5 Schuylkill 645 LEE 93825 SR 645 Flood Repairs A.1.a Steven Bruch, Environmental Planner 9/26/2011 According to an email from the District

Cultural Resource Professionals, they have

no concerns regarding the project.

ED BRPA Eval 13294 Approved

Archive2 5 Schuylkill 895 05M 92415 SR 895 Betterment A.1.a, A.1.c, A.3 Steven W. Bruch 8/10/2011 CE BRPA Eval 12970 Approved

Archive2 5 Schuylkill 895 05M 92415 SR 895 Betterment A.1.a, A.1.c, A.3 Steven W. Bruch 9/29/2011 CE BRPA Reeval 13378 Approved

Archive2 5 Schuylkill 1006 POC 95395 Surface Improvement 6C A.1.a Steven W. Bruch 4/3/2012 ED BRPA Eval 14708 Approved

Archive2 5 Schuylkill 2003 POC 95394 Surface Treatment 6B A.1.a Kris Thompson 4/3/2012 All proposed work is within the existing

paved road surface. The work conforms to

the 2010 Section 106 requirements for an

exempt project.

ED BRPA Eval 14690 Approved

Archive2 6 Bucks 32 EMG 94233 SR 32 Emergency Flood Rep A.1.a, A.1.c Monica Harrower 10/12/2011 This project is excempt from Section 106

under the FHWA emergency Relief

Programmatic Agreement Stipulation III, B.1

and B.5.

CE BRPA Eval 13590 Approved

Archive2 6 Bucks 263 EMG 93821 Bucks&MontCo Flood Repair A.1.a, A.1.c, A.3, A.4, A.15, B.5.a Cathy Spohn, PhD. 9/16/2011 CE 1b Eval 13258 Approved

Archive2 6 Bucks 263 EMG 93821 Bucks&MontCo Flood Repair A.1.a, A.1.c, A.3, A.4, A.15, B.5.a Cathy Spohn, PhD. 9/16/2011 CE 1b Reeval 13273 Approved

Archive2 6 Bucks 2025 B11 93439 Bridge Maint Contract 1 B.2 Monica Harrower 9/20/2011 CE BRPA Eval 14548 Approved

Archive2 6 Bucks 2025 B11 93439 Bridge Maint Contract 1 B.2 Monica Harrower 9/20/2011 CE BRPA Eval 14550 Approved

Archive2 6 Bucks 2025 B11 93439 Bridge Maint Contract 1 A.4 Monica Harrower 9/20/2011 CE BRPA Eval 14551 Approved

Archive2 6 Bucks 2025 B11 93439 Bridge Maint Contract 1 A.4 Monica Harrower 11/7/2011 The exempt project activity (A.4) pertains to

bridge projects, except replacements. Date

of exemption is the in-house scoping

meeting held on 11/7/2011. See attendance

sheet attached.

CE BRPA Eval 14593 Approved

Archive2 6 Chester 0 269 92328 Scarlett Rd RR Warning De A.2, A.6.a Monica Harrower 11/18/2011 CE 1a Eval 14008 Approved

Archive2 6 Chester 0 271 94510 Norway Rd RR Grade Xing A.2, A.6.a Monica Harrower 11/18/2011 CE 1a Eval 14009 Approved

Archive2 6 Chester 0 272 94511 Oakland Ave RR Grade Xing A.2, A.6.a Monica Harrower 11/18/2011 CE 1a Eval 14010 Approved

Archive2 6 Chester 0 273 94512 Penn Green Rd RR Xing A.2, A.6.a Monica Harrower 11/18/2011 CE 1a Eval 14011 Approved

Archive2 6 Chester 0 EMG 94565 Bridge Emg Repair 2011 #4 A.1.c, B.1 Monica Harrower 1/19/2012 CE BRPA Eval 14294 Approved

Archive2 6 Chester 282 C11 93440 Bridge Maint Contract 2 B.2 Monica Harrower 9/19/2011 CE BRPA Eval 14182 Approved

Archive2 6 Chester 282 C11 93440 Bridge Maint Contract 2 A.4 Monica Harrower 9/19/2011 CE BRPA Eval 14186 Approved

Archive2 6 Chester 1005 EMG 94345 Bridge Emg Repair 2011 #2 B.2 Monica Harrower 11/2/2011 CE BRPA Eval 13966 Approved

Archive2 6 Chester 1005 EMG 94345 Bridge Emg Repair 2011 #2 B.2 Monica Harrower 11/2/2011 CE BRPA Eval 13966 Approved

Archive2 6 Chester 1005 EMG 94345 Bridge Emg Repair 2011 #2 B.2 Monica Harrower 11/2/2011 CE BRPA Eval 13966 Approved

Archive2 6 Chester 1005 EMG 94345 Bridge Emg Repair 2011 #2 B.2 Monica Harrower 11/3/2011 CE BRPA Eval 13966 Approved

Archive2 6 Chester 3026 EMG 94564 Bridge Emg Repair 2011 #3 B.2 Monica Harrower 10/31/2011 CE BRPA Eval 13956 Approved

Archive2 6 Chester 3026 EMG 94564 Bridge Emg Repair 2011 #3 B.2 Monica Harrower 10/31/2011 CE BRPA Eval 13956 Approved

Archive2 6 Chester 3026 EMG 94564 Bridge Emg Repair 2011 #3 B.2 Monica Harrower 10/31/2011 CE BRPA Eval 13956 Approved

Archive2 6 Chester 3026 EMG 94564 Bridge Emg Repair 2011 #3 B.2 Monica Harrower 11/1/2011 CE BRPA Eval 13956 Approved

Archive2 6 Chester 3043 274 94983 First Ave Grade Xing A.2, A.6.a Monica Harrower 2/17/2012 CE 1a Eval 14461 Approved

Archive2 6 Chester 3069 GRD 87281 Grove Road A.1.a, A.1.c, A.3 Catherine Spohn & Monica Harrower 12/13/2011 Original project clearance was processed

under minor project programmatic

agreement. Project was re-evaluated by

District QPs on 12/13/11 and it was

determined that the project is still exempt

per Appendix C.

CE 1b Reeval 13114 Approved

Archive2 6 Delaware 0 381 94909 Engle Street Grade Xing A.2, A.6.a Monica Harrower 1/9/2012 CE 1a Eval 14248 Approved

Archive2 6 Delaware 13 D11 93441 Bridge Maint Contract 3 B.2 Monica Harrower 9/19/2011 The Bridge was evaluated as part of District

6.0's Stone Arch Bridge Management Plan.

The bridge is not eligible for the NRHP.

CE BRPA Eval 14183 Approved

Archive2 6 Delaware 13 D11 93441 Bridge Maint Contract 3 A.4 Monica Harrower 9/19/2011 CE BRPA Eval 14185 Approved

Archive2 6 Delaware 13 D11 93441 Bridge Maint Contract 3 B.1 Catherine Spohn, Monica Harrower 11/7/2011 CE BRPA Eval 14175 Approved

Archive2 6 Montgomery 73 M11 93442 Bridge Maint Contract 4 B.1 Monica Harrower, Catherine Spohn 3/30/2012 The project activity (superstructure

replacement) is exempted under code 2.B.1.

CE BRPA Eval 14779 Approved

Archive2 6 Montgomery 73 M11 93442 Bridge Maint Contract 4 A.4 Monica Harrower 4/9/2012 This masonry arch was previously

determined not eligible for the NR.

CE BRPA Eval 14780 Approved

Archive2 6 Montgomery 73 M11 93442 Bridge Maint Contract 4 A.4 Monica Harrower and Cathy Spohn 4/19/2012 The proposed activities will be limited to the

existing right-of-way.

CE BRPA Eval 14785 Approved

Archive2 6 Montgomery 73 M11 93442 Bridge Maint Contract 4 A.4 Monica Harrower and Cathy Spohn 4/19/2012 The proposed activities will be limited to the

existing right-of-way.

CE BRPA Eval 14786 Approved

Archive2 6 Montgomery 4005 EMG 94726 SR 4005 o/Br Skippack Crk B.2 Monica Harrower 11/2/2011 CE BRPA Eval 13986 Approved

Archive2 6 Philadelphia 0 101 72946 City Wide 3R 101 (C) A.1.a, A.7.c Catherine Spohn 7/6/2011 CE 1b Reeval 12673 Approved

Archive2 8 Adams 0 RRX 94743 Pond Street RR Crossing A.2 Judith Y. Aker 11/21/2011 The project is in the Fruitbelt Historic

District. According to CRP Jeremy

Ammerman, the project is exempt since the

new lights are replacing the old lights in the

same location.

CE 1a Eval 14014 Approved

Archive2 8 Adams 16 35 82409 Waynesboro Pike No.2 A.1.a, A.1.c, A.3, A.6.a Jesse Sabitsky 6/6/2011 ED BRPA Eval 13041 Approved

Archive2 8 Adams 394 9 90862 PA 394 Restoration A.1.a, A.2, A.3, B.6.b Jeremy Ammerman 9/29/2011 ED BRPA Eval 14054 Approved

Archive2 8 Adams 1015 11 90863 New Oxford Overlay A.1.a, A.7.a, A.7.c Jeremy Ammerman, Rebecca Knapp 9/29/2011 New Oxford School (104974) is within the

project limits but there will be no effect.

ED BRPA Eval 14156 Approved

Archive2 8 Adams 8005 2 88933 US15/30 Interchange Ramps A.1.f Judith Y. Aker 10/17/2011 An eligible farmstead (J Wible Farm

#007291 ) is in the NW quadrant outside of

the PennDOT legal right-of-way. The

resurfacing of the existing ramps adjacent

to this resource is an exempt activity.

ED BRPA Eval 14141 Approved

Archive2 8 Cumberland 0 --- 92390 Lemoyne Streetscape Impr. A.3, A.8.a, B.6.a, B.6.b Jeremy Ammerman and Rebecca E. Knapp 9/16/2011 CE 1a Eval 13064 Approved

Archive2 8 Cumberland 0 RRX 94662 Stuart Rd Grade Crossing A.2 Judith Y. Aker 10/31/2011 CE 1a Eval 13791 Approved

Archive2 8 Cumberland 15 22 82413 Blue Gray Highway A.1.a, A.1.c, A.1.d, A.1.e, A.1.f, A.3 Judith Y. Aker 8/24/2011 CE BRPA Eval 13869 Approved

Archive2 8 Cumberland 15 28 94763 Ped Brdg Superstructure A.4 Judith Y. Aker 12/14/2011 ED BRPA Eval 14181 Approved

Archive2 8 Cumberland 81 63 91357 District 8-0 DMS/SMP Ph A A.6.d Judith Y. Aker 4/4/2012 CE BRPA Eval 14720 Approved

Archive2 8 Cumberland 81 64 94817 I81 Micro/Carlisle West A.1.a Judith Y. Aker 2/29/2012 ED BRPA Eval 14522 Approved

Archive2 8 Cumberland 114 22 89000 Main St & Trindle Rd A.1.a, A.3, B.6.b Jeremy Ammerman 8/4/2011 curb cuts must not impact any property

steps within Mechanicsburg Historic

Districts

CE 1b Eval 14065 Approved

Archive2 8 Cumberland 1010 21 90879 Market Street Resurfacing A.1.a, A.3, A.7.c Judith Y. Aker 7/1/2011 ED BRPA Eval 13070 Approved

Archive2 8 Cumberland 2018 9 82424 Carlisle Road A.1.a, A.1.e, A.3, A.7.c Judith Y. Aker 7/11/2011 ED BRPA Eval 12974 Approved

Archive2 8 Dauphin 0 --- 93966 ITS Maint Contract 12-15 A.6.d Judith Y. Aker 2/21/2012 ED 1a Eval 14439 Approved

Archive2 8 Dauphin 0 --- 94723 Lighting Maintenance 2012 A.6.b Judith Y. Aker 12/13/2011 ED 1a Eval 14120 Approved

Archive2 8 Dauphin 22 SIG 92168 Walnut Street Signals A.6.b Judith Y. Aker 7/14/2011 ED BRPA Eval 12892 Approved

Archive2 8 Dauphin 225 20 82437 PA Route 225 North Resurf A.1.a, A.1.c, A.3 Jeremy Ammerman & Rebecca Knapp 7/29/2011 ED BRPA Eval 13637 Approved

Archive2 8 Dauphin 300 8 19016 PA 283 Reconstruction 3 A.1.a, A.1.c, A.1.d, A.1.f, A.4, B.2, B.4 Rebecca Knapp 10/14/2011 The project will remain exempt provided no

right-of-way is taken from NRHP-listed or

eligible historic structures.

CE 1b Eval 13358 Approved

Archive2 8 Dauphin 325 8 93924 Emrg Repair Clarks Valley A.1.a, A.3, A.15 Jesse Sabitsky 9/28/2011 Slip linning of the 36" pipe & replacing the

18" pipe will not result in forseable impacts

to archaeological or historic resources.

CE BRPA Eval 13381 Approved

Archive2 8 Dauphin 2017 11 74516 Manada Creek Bridge 2 B.1 Rebecca Knapp 6/24/2011 Due to the initial uncertainty of the extent

of the project limits, this project was not

originally exempted. However, it is currently

clear that the project meets exemption

guidelines.

ED 1b Eval 12364 Approved

Archive2 8 Dauphin 8001 1 94833 Front St I-81 Ramp Brdges A.1.a, A.1.c, A.1.f, A.4 Judith Y. Aker 12/22/2011 CE BRPA Eval 14519 Approved

Archive2 8 Dauphin 8001 1 94833 Front St I-81 Ramp Brdges A.1.a, A.1.c, A.1.f, A.4 Judith Y. Aker 12/22/2011 CE BRPA Eval 14519 Approved

Archive2 8 Franklin 0 --- 93137 Line Painting 2012 A.1.a Judith Y. Aker 12/6/2011 Line painting is a roadway surface treatment

and is exempt under A-1a.

ED BRPA Eval 14074 Approved

Archive2 8 Franklin 0 --- 94917 Dist AWPM SFY 2012-2013 A.6.b Judith Y. Aker 2/6/2012 CE BRPA Eval 14373 Approved

Archive2 8 Franklin 0 RRX 94672 Church Road Crossing A.2 Judith Y. Aker 11/1/2011 CE 1a Eval 13813 Approved

Archive2 8 Franklin 75 7 87453 Fort Loudon Road Bridge A.4 Rebecca Knapp 8/5/2011 Given the minimal engineering scope of

work, no cultural resource impacts are

anticipated.

CE BRPA Eval 12208 Approved

Archive2 8 Franklin 316 15 90202 Wayne Highway Paving A.1.a, A.1.c, A.3, A.7.c Judith Y. Aker 10/12/2011 CE BRPA Eval 14180 Approved

Archive2 8 Franklin 1003 19 88946 Conocheague Creek Bridges A.4 Rebecca Knapp 8/5/2011 ED BRPA Eval 12209 Approved

Archive2 8 Franklin 3002 9 88947 Conococheague Cr Bridge1 A.4 Rebecca Knapp 8/5/2011 Given the limited bridge preservation scope

of work, combined with the fact that only

minor handwork activities will be conducted

underneath the existing bridge, no cultural

resource impacts are anticipated.

ED BRPA Eval 12210 Approved

Archive2 8 Lancaster 10 3 89263 Twin County Road A.1.a, A.1.c, A.3 Judith Y. Aker 8/23/2011 CE BRPA Eval 13809 Approved

Archive2 8 Lancaster 30 97 89187 US 30/ Ronks Road Intsct A.6.a, A.6.b Jeremy Ammerman 8/24/2011 A.6.a. - Installation or upgrade of regulatory

signs.; A.6.b. - Upgrade or replacement of

less than 50 year old lighting(mastheads or

poles), traffic signals.

CE 1b Eval 14005 Approved

Archive2 8 Lancaster 222 49 91016 SR 222 over PA Turnpike A.1.a, A.1.e, A.4, B.2 Jeremy D. Ammerman 6/22/2011 CE BRPA Eval 12823 Approved

Archive2 8 Lancaster 222 50 90909 South Church St Resurface A.1.a, A.1.c, A.3, A.7.c Judith Y. Aker 10/31/2011 ED BRPA Eval 14399 Approved

Archive2 8 Lancaster 222 50 90909 South Church St Resurface A.1.a, A.1.c, A.3, A.7.c Judith Y. Aker 1/5/2012 ED BRPA Eval 14399 Approved

Archive2 8 Lancaster 230 26 86479 Main Street A.1.a Judith Y. Aker 11/21/2011 CE BRPA Eval 14286 Approved

Archive2 8 Lancaster 340 10 89261 Old Philadelphia Pike A.1.a, A.1.c, A.3, A.6.a, A.7.c Jesse Sabitsky 9/13/2011 CE BRPA Eval 13831 Approved

Archive2 8 Lancaster 501 20 86477 Furnace Hills Pike A.1.a, A.1.c, A.3 Judith Y. Aker 6/21/2011 CE BRPA Eval 12973 Approved

Archive2 8 Lancaster 501 20 86477 Furnace Hills Pike A.1.a, A.1.c, A.3 Judith Y. Aker 6/21/2011 CE BRPA Reeval 14713 Approved

Archive2 8 Lancaster 741 RRX 94661 Rohrerstown Grade Crossin A.2 Judith Y. Aker 10/31/2011 CE 1a Eval 13798 Approved

Archive2 8 Lancaster 772 35 89262 Anderson Ferry Road A.1.a, A.1.d, A.3, A.7.c Jeremy Ammerman CRP, Jay Lightcap Env

Plnr

11/23/2011 A1a - Roadway and shoulder resurfacing.;

A1d - Guiderail extension at bridge.; A3 -

Drainage improvements, replacement and

cleaning activities.; A7c - ADA pedestrian

crosswalk slab at signal.

CE BRPA Eval 14216 Approved

Archive2 8 Lancaster 897 29 93777 SR 897 Bridge Replace B.1 Rebecca Knapp 9/15/2011 CE BRPA Eval 13361 Approved

Archive2 8 Lancaster 1002 9 91080 Lancaster Resurfacing A.1.a, B.6.a, B.6.b Jeremy Ammerman 7/20/2011 This project has been determined exempt by

the District Cultural Historian and

Archaeologist.

ED BRPA Eval 13045 Approved

Archive2 8 Lancaster 2001 9 91106 Octoraro Creek Bridge A.4 Jeremy Ammerman 6/1/2011 Bridge superstructure replacement. CE 1b Eval 13067 Approved

Archive2 8 Lancaster 4020 10 82481 Harrisburg Pike A.1.a, A.3 Judith Y. Aker 8/18/2011 ED BRPA Eval 13473 Approved

Archive2 8 Lebanon 0 --- 92873 Canilever Flashing Device A.2 Judith Y. Aker 5/4/2011 CE BRPA Eval 12596 Approved

Archive2 8 Lebanon 0 --- 94886 Klein Ave Culvert Emerg R A.1.a, A.1.c, A.15, B.2 Jeremy Ammerman 1/31/2012 CE 1a Eval 14157 Approved

Archive2 8 Lebanon 0 FSR 87026 Lebanon City FSRS B.6.b Jeremy Ammerman, PennDOT CRP 8/19/2011 No further archaeology work is needed as

no ground disturbing activities will occur.

Also, the project is located within the

Lebanon Historic District, but as a result of

the activities of the project, work is

exempted under Appendix C.

CE BRPA Eval 13619 Approved

Archive2 8 Lebanon 343 4 81007 Pine Grove St Bridge PM A.4 Jeremy Ammerman 9/16/2011 ED BRPA Eval 13957 Approved

Archive2 8 Lebanon 343 4 81007 Pine Grove St Bridge PM A.4 Jeremy Ammerman 9/16/2011 ED BRPA Eval 13957 Approved

Archive2 8 Lebanon 343 4 81007 Pine Grove St Bridge PM A.4 Jeremy Ammerman 9/16/2011 ED BRPA Reeval 14687 Approved

Archive2 8 Lebanon 343 4 81007 Pine Grove St Bridge PM A.4 Jeremy Ammerman 9/16/2011 ED BRPA Reeval 14687 Approved

Archive2 8 Lebanon 419 5 82597 Schaeffer Road A.1.a, A.1.c, A.3, B.6.b Jeremy Ammerman 10/28/2011 Participated in project scoping fieldview

October 27,2011.

CE BRPA Eval 14417 Approved

Archive2 8 Lebanon 422 30 95148 Main Street Sinkhole A.1.a Jeremy Ammerman 1/31/2012 CE 1a Eval 14308 Approved

Archive2 8 Perry 850 10 88994 Fort Robinson Road A.1.a, A.1.c, A.3 Jay Lightcap 7/27/2011 CE BRPA Eval 13833 Approved

Archive2 8 York 74 57 90939 Baltimore Pike A.1.a, A.3, A.6.a, A.7.c Jay Lightcap 12/13/2011 A1a - Roadway mill and overlay; A3 -

Crosspipe replacements; A6a - Update

regulatory signs; A7a - ADA curb cuts,

ramps, and drainage.

CE BRPA Eval 14442 Approved

Archive2 8 York 74 57 90939 Baltimore Pike A.1.a, A.3, A.6.a, A.7.c Jay Lightcap 12/12/2011 A1a - mill & overlay; A3 - drainage; A6a -

Sign updates; A7c - ADA curb cuts & ramps

CE BRPA Eval 14442 Approved

Archive2 8 York 74 57 90939 Baltimore Pike A.1.a, A.3, A.6.a, A.7.c Jay Lightcap 12/13/2011 A1a - mill & overlay; A3 - drainage; A6a -

Sign updates; A7c - ADA curb cuts & ramps

CE BRPA Eval 14442 Approved

Archive2 8 York 83 63 83618 ITS - York County A.6.d Judith Y. Aker 4/4/2012 CE BRPA Eval 14718 Approved

Archive2 8 York 181 15 90916 Main Street Resurfacing A.1.a, A.3, A.7.c Judith Y. Aker 11/7/2011 CE BRPA Eval 14142 Approved

Archive2 9 Bedford 0 BTT 92117 Broad Top Twp Rail Trail A.8.c Attilio Squillario 1/18/2012 See attached CR memo CE BRPA Eval 14288 Approved

Archive2 9 Bedford 26 16 91604 PA26 Ft Piper to Plank Rd A.1.a, A.1.c Attilio Squillario 2/7/2012 CE BRPA Eval 14382 Approved

Archive2 9 Bedford 26 12B 21557 Everett Truss Rehabs B.2 Jonathan Daily 11/1/2011 See attachments CE BRPA Eval 13812 Approved

Archive2 9 Bedford 26 12B 21557 Everett Truss Rehabs B.2 Jonathan Daily 11/1/2011 See attachments CE BRPA Eval 13812 Approved

Archive2 9 Bedford 26 12B 21557 Everett Truss Rehabs B.2 Jonathan Daily 11/1/2011 See attachment CE BRPA Eval 13812 Approved

Archive2 9 Bedford 30 28B 92555 Bedford Co Epoxy Overlays A.1.e, A.4 Attilio Squillario 2/23/2012 CE BRPA Reeval 14497 Approved

Archive2 9 Bedford 56 22M 88689 PA 56 Resurfacing B.1, B.2, B.3, B.4 Susan Haney 2/9/2012 See attached ED BRPA Eval 14134 Approved

Archive2 9 Bedford 99 10B 94779 I-99 over PA 869 A.4 Attilio Squillario 2/23/2012 CE BRPA Eval 14496 Approved

Archive2 9 Bedford 99 10B 94779 I-99 over PA 869 A.4 Attilio Squillario 2/23/2012 CE BRPA Eval 14496 Approved

Archive2 9 Bedford 220 15M 90238 Springs Rd-Cumberland Rd A.1.a, A.1.c, A.3 Attilio Squillario 2/1/2012 CE BRPA Eval 14204 Approved

Archive2 9 Bedford 2007 03B 88127 Tr W Sideling Hill Ck Brg A.4 Jonathan Daily/Susanne Haney 8/3/2011 See attached cultural resources materials. CE BRPA Eval 11989 Approved

Archive2 9 Bedford 3006 01B 21556 Wolf Camp Run Bridge A.4 Attilio Squillario 12/14/2011 See attached Cultural resources ED BRPA Eval 14126 Approved

Archive2 9 Bedford 7206 397 21367 T-397 Shaffers Ck #8 B.1 Susanne Haney 12/1/2011 See attachment CE BRPA Eval 13463 Approved

Archive2 9 Blair 0 --- 94628 Quarter Roundhouse Ph IV A.9 Jamie C. Chestney 3/21/2012 All work will take place within a newly

constructed building. No ground

disturbance is anticipated as part of this

project.

CE 1b Eval 14638 Approved

Archive2 9 Blair 0 AP3 92188 Altoona Paving Phase 3 A.1.a Robert A. Cassarly 5/26/2011 CE BRPA Eval 12644 Approved

Archive2 9 Blair 0 AP4 92861 Altoona Paving Phase 4 A.1.a Robert A. Cassarly 6/6/2011 CE BRPA Eval 12645 Approved

Archive2 9 Blair 0 NMS 92114 North Montgomery Sidewalk A.7.b, A.7.c, A.8.a Ryan Hostetter 3/1/2012 All work will be completed with no

anticipated impact to Historic Properties or

Archaeological Resources.

CE BRPA Eval 13687 Approved

Archive2 9 Blair 453 11B 22084 PA 453 Sink Run Bridge B.2 Jonathan E. Daily 9/20/2011 ED BRPA Eval 12465 Approved

Archive2 9 Blair 764 18 88544 Lloyd Street to 17th St A.1.a, A.6.b, A.7.c Robert A. cassarly 7/19/2011 No Historic Districts present, and all work

confined to existing pavement and sidewalk

surfaces.

CE BRPA Eval 12916 Approved

Archive2 9 Blair 1001 21B 22028 South Bellwood Bridge B.1 Susanne M. Haney 4/23/2012 See Remarks above CE BRPA Eval 12543 Approved

Archive2 9 Blair 4003 LBS 92115 Logan Blvd Sidewalks A.7.b Robert A. Cassarly 5/26/2011 CE BRPA Eval 12563 Approved

Archive2 9 Blair 4005 2 93904 Mill Run Wall A.1.a, A.12, A.15 Robert A. Cassarly, District Designee 1/9/2012 CE BRPA Eval 14246 Approved

Archive2 9 Blair 7201 304 21877 T-304 Gillans Run Bridge B.1 Jonathan E. Daily 2/22/2012 Soils within all the TCEs will need to be

protected with geotextile and at least 2 ft of

fill. All these soils must remain intact and

trees need to be cut by hand with no

grubbing.

ED BRPA Eval 11613 Approved

Archive2 9 Blair 7206 ROD 94782 Rodman Stockpile Bridge B.1 Jamie C. Chestney 3/7/2012 Superstructure replacement on existing

alignment. All work will take place within the

existing roadway and bridge deck. No

additional right-of-way (permanent and/or

temporary) is anticipated.

ED BRPA Eval 14574 Approved

Archive2 9 Cambria 0 SPS 92436 St. Peter Street Sidewalk A.8.a, B.6.a, B.6.b Sarah McClellan 6/17/2011 All work lmtd to prev. disturbed soils.

Project APE has little/no potential to yield

intact arch resources; no arch survey will be

necessary. No buildings located within APE

are eligible for NR. Buildings are vernacular

and/or significantly altered.

CE BRPA Eval 12794 Approved

Archive2 9 Cambria 53 22 22429 Cresson Hgh Level Br B.1 Susanne Haney/Jonathan Daily 11/21/2011 CE 1b Eval 9754 Approved

Archive2 9 Cambria 164 1 93099 Portage to Munster Resurf A.1.a, A.3 Sarah McClellan 3/2/2012 CE BRPA Eval 14516 Approved

Archive2 9 Cambria 271 15B 92549 Maple Ave Bridge Pres A.4 Sarah McClellan 2/7/2012 CE BRPA Eval 12438 Approved

Archive2 9 Cambria 3007 GWW 64489 Goucher Wheel & Walk Way A.7.b Sarah McClellan 11/22/2011 CE 1b Eval 450 Approved

Archive2 9 Cambria 7301 EMG 94990 Hickory St Emg Bdg Repair A.4 Sarah McClellan 1/13/2012 CE BRPA Eval 14264 Approved

Archive2 9 Huntingdon 0 BSI 92120 Bryan Street Streetscape A.7.a, A.8.a Jonathan E. Daily, Susanne M. Haney 7/15/2011 CE BRPA Eval 14017 Approved

Archive2 9 Somerset 30 15 95220 US30 - T-832 to PA160 A.1.a, A.1.c Attilio Squillario 2/7/2012 CE BRPA Eval 14383 Approved

Archive2 9 Somerset 30 PRL 92440 Rt 30 Park & Ride A.11 Attilio Squillario 12/13/2011 See SFV minutes for approved use. CE 1b Eval 14121 Approved

Archive2 9 Somerset 219 32B 94075 Somerset US219 Culvert 2 B.1, B.3, B.4 Susanne Haney/J. Daily 3/13/2012 CE BRPA Eval 14116 Approved

Archive2 9 Somerset 219 33B 74435 Somerset US 219 Culvert 1 B.1 Jonathan Daily 12/14/2011 See attachment CE BRPA Eval 13000 Approved

Archive2 9 Somerset 1003 02B 23569 W Listie Wells Ck Culvert B.1 Jonathan Daily 1/4/2012 See attached ED BRPA Eval 13781 Approved

Archive2 9 Somerset 1011 01B 74457 Wells Creek Trib Bridge B.2 Susanne Haney 4/3/2012 CE BRPA Eval 14727 Approved

Archive2 9 Somerset 2031 02M 88822 Garrett Shortcut Resurfac A.1.a, A.1.c, A.3 Attilio Squillario 12/14/2011 See attachment (CR.pdf) CE BRPA Eval 14123 Approved

Archive2 9 Somerset 2037 02B 23574 Bigby Run Bridge B.1 Jonathan Daily 11/2/2011 See attachments CE BRPA Eval 13707 Approved

Archive2 9 Somerset 2047 01B 23572 SR2047 Bluelick Creek Br B.1 Susanne Haney 9/30/2011 See attachments and mitigation

commitments.

CE BRPA Eval 12867 Approved

Archive2 9 Somerset 3001 1 23364 Fort Hill Casselman Brdg B.1 Susanne Hanney 10/17/2011 See attached CE 1b Eval 11909 Approved

Archive2 9 Somerset 3001 1 23364 Fort Hill Casselman Brdg B.1 Susanne Hanney 10/17/2011 See attached CE 1b Reeval 14022 Approved

Archive2 9 Somerset 7210 628 23348 T-628 Quemahoning Dam Brg A.1.c, A.1.e, B.2 Susanne Haney 1/17/2012 CE 1b Eval 11711 Approved

Archive2 10 Armstrong 0 --- 83161 2012 Armstrong Br Preserv A.4 Eric Buchan 10/20/2011 ED BRPA Eval 14033 Approved

Archive2 10 Armstrong 0 --- 83161 2012 Armstrong Br Preserv A.4 Eric Buchan 10/20/2011 ED BRPA Reeval 14240 Approved

Archive2 10 Armstrong 1016 150 74209 Calhoun School Road Br. B.1 Susanne Haney 8/18/2011 Protect TCE's with geotextile. Limit ground

disturbance. No historic structures.

ED BRPA Eval 13423 Approved

Archive2 10 Armstrong 1028 150 24124 Oscar Bridge A.4 Eric R. Buchan 7/29/2011 CE BRPA Eval 13062 Approved

Archive2 10 Butler 0 --- 83169 2012 Butler Br Preserv A.4 Eric Buchan 10/20/2011 ED BRPA Eval 14034 Approved

Archive2 10 Butler 58 257 77992 PA 58 McMurray Run Bridge B.1 Susanne Haney 5/13/2011 Exempted as per avoidance measures CE 1b Eval 9105 Approved

Archive2 10 Butler 68 202 93051 PA 68 Evans City West PM A.1.a, A.1.c, A.3 Eric R. Buchan 5/18/2011 CE BRPA Eval 12747 Approved

Archive2 10 Butler 79 255 92837 I-79/US 422 Interchange A.1.b, A.1.f, B.1 Susanne Haney 10/26/2011 CE 1b Eval 14171 Approved

Archive2 10 Butler 79 255 92837 I-79/US 422 Interchange A.1.b, A.1.f, B.1 Susanne Haney 10/26/2011 CE 1b Reeval 14358 Approved

Archive2 10 Butler 79 257 95044 I-79 Harmony NB/SB Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14553 Approved

Archive2 10 Butler 79 257 95044 I-79 Harmony NB/SB Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14553 Approved

Archive2 10 Butler 228 201 93053 PA 228 Mars West PM A.1.a, A.1.c, A.3 Eric R. Buchan 5/18/2011 CE BRPA Eval 12746 Approved

Archive2 10 Butler 1027 250 79608 East Unity Road Bridge B.1 Susanne Haney 8/18/2011 ED BRPA Eval 13424 Approved

Archive2 10 Clarion 0 --- 83114 2012 Clarion Br Preserv A.4 Eric Buchan 10/20/2011 ED BRPA Eval 14035 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 0 95043 I-80 Clarion/Butler Br PM A.4 Eric Buchan 2/10/2012 ED BRPA Eval 14504 Approved

Archive2 10 Clarion 80 MS2 95223 I-80 Clarion MicroSurface A.1.a Eric R. Buchan 2/23/2012 Project will consist of patching and and the

placement of a micro-surface treatment on I-

80 from Seg 624 / 1267 to Seg 720/2430

EB. Seg 625/0964 to Seg 721/2351 in

Clarion Township, Clarion County.

CE BRPA Eval 14502 Approved

Archive2 10 Clarion 322 351 25214 Day Bridge A.4 Eric Buchan 10/20/2011 CE BRPA Eval 13977 Approved

Archive2 10 Clarion 368 350 91303 Parker Truss Bridge PM A.4 Eric R. Buchan 7/13/2011 ED BRPA Eval 13967 Approved

Archive2 10 Clarion 4015 350 83260 Mahles Run Bridge B.1 Susanne Haney 8/18/2011 TCE's do not need geotextile protection. ED BRPA Eval 13425 Approved

Archive2 10 Indiana 0 --- 83175 2012 Indiana Br Preserva A.4 Eric Buchan 10/20/2011 ED BRPA Eval 14036 Approved

Archive2 10 Indiana 56 454 91310 Seward Truss Bridge PM A.4 Eric R. Buchan 7/13/2011 CE BRPA Eval 14038 Approved

Archive2 10 Indiana 580 450 78111 Cherry Tree Bridge #1 A.4 Eric R. Buchan 7/5/2011 CE 1b Reeval 12409 Approved

Archive2 10 Indiana 3056 450 25581 J M Junction Bridge B.1 Susanne Haney 9/2/2011 ED BRPA Eval 13426 Approved

Archive2 10 Jefferson 0 --- 83067 2012 Jefferson Br Preserv A.4 Eric Buchan 10/20/2011 ED BRPA Eval 14037 Approved

Archive2 10 Jefferson 80 546 95058 I-80 Jeffersn Concrete EB A.1.a, A.1.c Eric R. Buchan 1/19/2012 CE BRPA Eval 14465 Approved

Archive2 10 Jefferson 219 551 26074 Crenshaw Bridge #1 B.1 Susanne Haney 1/24/2012 CE 1b Eval 13594 Approved

Archive2 10 Jefferson 219 552 83286 Crenshaw Bridge #2 B.1 Susanne Haney 1/24/2012 CE 1b Eval 13595 Approved

Archive2 11 Allegheny 0 --- 81712 TH10 Thoms Run Rd A.1.c, A.3, A.6.a, B.1 David Anthony 2/8/2012 There are no historic properties within or

adjacent to the project area. The structure

is a pipe culvert and not eligible for the

National Register of Historic Places.

ED 1b Eval 14514 Approved

Archive2 11 Allegheny 0 LOC 74985 Children Hospital Ped Br B.1 David Anthony 6/20/2011 CE 1a Eval 12771 Approved

Archive2 11 Allegheny 0 TEH 61754 GAP-Keystone Metals Trail A.8.c David Anthony 11/28/2011 The project is to be constructed entirely

upon a former railroad spur that is

discontiguous with historic railroad

corridors in the area.

CE 1a Eval 14273 Approved

Archive2 11 Allegheny 0 TEH 77212 Frick Park Trail Ext9Mile A.8.b Nick Krobot 6/17/2011 CE 1a Reeval 12776 Approved

Archive2 11 Allegheny 19 A60 78280 19 Banksville/McFar-Pkwy A.1.a, A.1.c, A.1.e, A.3, A.4, A.6.a, A.6.b,

A.7.a, A.7.c

David Anthony 1/11/2012 There are no historic resources within or

adjacent to the project area. The Truevine

Baptist Church (BHP007501) appears on the

CRGIS but the resource has been

demolished (replaced by modern

commercial structures).

CE BRPA Eval 14258 Approved

Archive2 11 Allegheny 19 A60 78280 19 Banksville/McFar-Pkwy A.1.a, A.1.c, A.1.e, A.3, A.4, A.6.a, A.6.b,

A.7.a, A.7.c

David Anthony 1/11/2012 There are no historic resources within or

adjacent to the project area. The Truevine

Baptist Church (BHP007501) appears on the

CRGIS but the resource has been

demolished (replaced by modern

commercial structures).

CE BRPA Eval 14258 Approved

Archive2 11 Allegheny 19 A60 78280 19 Banksville/McFar-Pkwy A.1.a, A.1.c, A.1.e, A.3, A.4, A.6.a, A.6.b,

A.7.a, A.7.c

David Anthony 1/11/2012 There are no historic resources within or

adjacent to the project area. The Truevine

Baptist Church (BHP007501) appears on the

CRGIS but the resource has been

demolished (replaced by modern

commercial structures).

CE BRPA Eval 14258 Approved

Archive2 11 Allegheny 19 A60 78280 19 Banksville/McFar-Pkwy A.1.a, A.1.c, A.1.e, A.3, A.4, A.6.a, A.6.b,

A.7.a, A.7.c

David Anthony 1/11/2012 There are no historic resources within or

adjacent to the project area. The Truevine

Baptist Church (BHP007501) appears on the

CRGIS but the resource has been

demolished (replaced by modern

commercial structures).

CE BRPA Eval 14258 Approved

Archive2 11 Allegheny 19 A60 78280 19 Banksville/McFar-Pkwy A.1.a, A.1.c, A.1.e, A.3, A.4, A.6.a, A.6.b,

A.7.a, A.7.c

David Anthony 1/11/2012 There are no historic resources within or

adjacent to the project area. The Truevine

Baptist Church (BHP007501) appears on the

CRGIS but the resource has been

demolished (replaced by modern

commercial structures).

CE BRPA Eval 14258 Approved

Archive2 11 Allegheny 28 A29 50962 28/ Bridge Pres-Millvale A.1.a, A.1.c, A.1.f, A.4, A.5 George Kronz 2/23/2012 CE BRPA Eval 14501 Approved

Archive2 11 Allegheny 28 A29 50962 28/ Bridge Pres-Millvale A.1.c, A.1.f, A.4, A.5 George Kronz 2/23/2012 CE BRPA Eval 14501 Approved

Archive2 11 Allegheny 28 A29 50962 28/ Bridge Pres-Millvale A.1.c, A.1.f, A.4, A.5 George Kronz 2/23/2012 CE BRPA Eval 14501 Approved

Archive2 11 Allegheny 28 A29 50962 28/ Bridge Pres-Millvale A.1.c, A.1.f, A.4, A.5 George Kronz 2/23/2012 CE BRPA Eval 14501 Approved

Archive2 11 Allegheny 28 A29 50962 28/ Bridge Pres-Millvale A.1.c, A.1.f, A.4, A.5 George Kronz 2/23/2012 CE BRPA Eval 14501 Approved

Archive2 11 Allegheny 30 A21 28347 Ardmore EB/Electric A.1.c, A.3, A.6.a, A.6.b, B.1 David Anthony 6/20/2011 CE 1b Reeval 12781 Approved

Archive2 11 Allegheny 48 A27 93056 48/Haymaker Road Slide A.3, A.15 Nick Krobot 6/28/2011 CE 1b Eval 12851 Approved

Archive2 11 Allegheny 50 TEH 71919 Tri-Boro Streetscape A.1.a, A.6.b, A.6.c, A.7.a, A.7.b, A.7.c, A.8.a,

A.11

Nick Krobot 11/14/2011 CE 1b Eval 14006 Approved

Archive2 11 Allegheny 50 TEH 71919 Tri-Boro Streetscape A.1.a, A.6.b, A.6.c, A.7.a, A.7.b, A.7.c, A.8.a,

A.11

Nick Krobot 11/14/2011 CE 1b Reeval 14790 Approved

Archive2 11 Allegheny 51 A76 93057 51/Island Avenue Slide A.7.a, A.15 Nick Krobot 6/13/2011 CE 1b Eval 12850 Approved

Archive2 11 Allegheny 51 A76 93057 51/Island Avenue Slide A.7.a, A.15 Nick Krobot 6/13/2011 CE 1b Reeval 12963 Approved

Archive2 11 Allegheny 65 A48 91785 65/CampHorne-Kilbuck A.1.a, A.1.c, A.3, B.5.a, B.6.b David Anthony 1/27/2012 There are historic resources adjacent to the

project area however the limited nature of

the project will have no visual or physical

impacts to those resources.

CE BRPA Eval 14388 Approved

Archive2 11 Allegheny 65 A49 91591 65, Ohio Rv/Walnut - Rapp A.1.a, A.1.c, A.3, A.4, A.6.a, A.7.c, B.5.a,

B.6.b

David R. Anthony 2/6/2012 There are no National Register of Historic

Places eligible or listed properties or

districts within the project.

CE BRPA Eval 14422 Approved

Archive2 11 Allegheny 65 A49 91591 65, Ohio Rv/Walnut - Rapp A.1.a, A.1.c, A.3, A.6.a, A.7.c, B.5.a, B.6.b David R. Anthony 2/6/2012 There are no National Register of Historic

Places eligible or listed properties or

districts within the project.

CE BRPA Eval 14422 Approved

Archive2 11 Allegheny 65 A49 91591 65, Ohio Rv/Walnut - Rapp A.1.a, A.1.c, A.3, A.6.a, A.7.c, B.5.a, B.6.b David R. Anthony 2/6/2012 There are no National Register of Historic

Places eligible or listed properties or

districts within the project.

CE BRPA Eval 14422 Approved

Archive2 11 Allegheny 130 A21 92318 TriBoro Bin Wall Repair A.1.c, A.3, A.15 Nick Krobot 6/17/2011 The site was field viewed on 6/16/11. CRGIS

was used as part of the review process.

CE 1b Eval 13056 Approved

Archive2 11 Allegheny 148 A10 91733 148/Walnut-5th&5th/Jerome A.1.a, A.3, A.6.b, A.7.c, B.2 David Anthony 11/23/2011 The Jerome Street Bridge is National

Register listed, however the proposed

structure work is limited to the roadway

portion of the bridge and will not adversely

affect the qualities of the structure that

make it eligible for the National Register.

CE BRPA Eval 14104 Approved

Archive2 11 Allegheny 366 A04 71116 366/Bull Creek - Tarentum A.1.a, A.1.c, A.1.d, A.1.e, A.3, A.4, A.6.a,

A.6.b, A.7.a, A.7.c, B.2

Joe Verbka 8/23/2011 CE 1b Eval 13333 Approved

Archive2 11 Allegheny 376 A48 85967 I376(279)Median Bar Repl A.1.e, A.4 Todd C. Crouch 7/20/2011 The proposed project is limited to median

barrier replacement and expansion dam

replacement on the I-376 bridge over Bell

Road. Therefore the proposed project will

have no effect to Historic or Archaeological

resources.

CE BRPA Eval 12972 Approved

Archive2 11 Allegheny 579 A05 75903 I579-1 Vets Br./XTown Ph2 B.2, B.5.a David R Anthony 6/15/2011 There are no National Register listed or

eligible structures within the APE. Since this

is an urban environment, there are historic

structures within the viewshed of the APE.

However the nature of the project will not

affect any historic resources.

CE 1b Reeval 12459 Approved

Archive2 11 Allegheny 885 A39 91844 Clairton/College-Leban Ch A.1.a, A.1.b, A.1.c, A.3, A.6.b Todd C Crouch 7/28/2011 CE BRPA Eval 13154 Approved

Archive2 11 Allegheny 885 A39 91844 Clairton/College-Leban Ch A.1.a, A.1.b, A.1.c, A.3, A.5, A.6.b, A.7.c Todd C Crouch 7/28/2011 CE BRPA Reeval 14261 Approved

Archive2 11 Allegheny 1001 A29 27434 Bridge St/ov Pine Creek A.1.c, A.1.e, A.4, A.7.c George Kronz 7/28/2011 The proposed project consists of

replacement of the existing bridge deck and

minor repairs to the substructure. The

proposed project will not have any impacts

on historic structures or archaeological

resources.

CE BRPA Eval 12978 Approved

Archive2 11 Allegheny 1001 A30 63332 Freeport Rd/Barge Basin A.1.a, A.4, A.7.a George M. Kronz 7/25/2011 There are no historic or archaeological

resources within the project area.

CE 1b Eval 12979 Approved

Archive2 11 Allegheny 1013 A15 93058 1013/Saxonburg Blvd Slide A.15 Nick Krobot 6/13/2011 CE 1b Eval 12884 Approved

Archive2 11 Allegheny 3028 A04 93059 3028/Presto Sygan Slide A.3, A.15 Nick Krobot 6/13/2011 ED 1b Eval 12912 Approved

Archive2 11 Allegheny 3098 A03 27431 SR 3098/Glass Run Bridge B.1, B.3, B.4, B.5.a, B.5.b Joseph M. Verbka 8/23/2011 ED 1b Eval 13081 Approved

Archive2 11 Allegheny 7430 0 56943 Dewey St Br A.7.a, A.7.c, B.1 David Anthony 11/28/2011 No historic resources were identified within

the proposed project area.

CE 1b Eval 14201 Approved

Archive2 11 Allegheny 7448 LOC 79934 Homeville Cr. Br. #4 HV04 A.1.a, A.1.c, A.3, A.5, A.7.a, B.1 David Anthony 11/18/2011 ED 1b Eval 14069 Approved

Archive2 11 Allegheny 7473 LOC 76447 Thompson Run Bridge 5 A.5, A.6.a, B.2 David Anthony 8/26/2011 Bridge is not eligible. Union Railroad is an

eligible linear resource. A TCE and aerial

easement is needed for the Union Railroad.

There is no potential to physically or visually

affect the Union Railroad.

CE 1b Eval 13324 Approved

Archive2 11 Beaver 51 B45 88294 51/Ohio State - SR4004 A.1.a, A.1.c, A.1.e, A.3, A.4, A.6.a Todd C. Crouch 11/28/2011 There are no historic resources located

within the proposed project area.

CE BRPA Eval 14241 Approved

Archive2 11 Beaver 151 B04 70801 PA151 Bocktown/Raredon Rn B.1 David Anthony 12/1/2011 The bridge is not eligible. ED 1b Eval 14072 Approved

Archive2 11 Beaver 288 B05 29069 PA 288 Br/Camp Run B.1 Joseph M. Verbka 9/13/2011 See remarks section below. ED 1b Eval 13403 Approved

Archive2 11 Beaver 376 B05 94644 Beaver Valley over 3024 A.1.a, A.4 Todd C. Crouch 3/15/2012 There are no historic resources located

within the project area.

CE BRPA Eval 14757 Approved

Archive2 11 Beaver 376 B05 94644 Beaver Valley over 3024 A.1.a, A.4 Todd C. Crouch 3/15/2012 There are no historic resources located

within the project area.

CE BRPA Eval 14757 Approved

Archive2 11 Beaver 588 B16 93063 588/Stiffen Hills Slide A.15 Nick Krobot 6/13/2011 CE 1b Eval 12849 Approved

Archive2 11 Beaver 1015 B01 28925 SR 1015, Hartzell Rd Br B.1 David Anthony 11/18/2011 There are no cultural resources within the

APE.

ED 1b Reeval 13997 Approved

Archive2 11 Beaver 3016 B09 28996 Greengarden Rd Slide A.1.c, A.3, A.15 Nick Krobot 1/27/2012 CRGIS was used to research the project area

and no hisorical or archeological resources

were identified in the project area.

CE 1b Eval 14454 Approved

Archive2 11 Lawrence 108 L12 29375 108/N. Castle-Harlansburg B.1 Joseph M. Verbka 6/22/2011 CE 1b Eval 12697 Approved

Archive2 11 Lawrence 551 L06 29470 PA 551/Deer Run B.1 Joseph Verbka 9/12/2011 ED 1b Eval 13404 Approved

Archive2 12 Fayette 21 0 92371 D12 SPC 2c SINC-UP A.6.b Kim Ansell 10/19/2011 CE BRPA Eval 13639 Approved

Archive2 12 Fayette 21 08R 92979 PA21 Springdale-Land Fill A.1.a, A.1.c Kim Ansell 6/1/2011 CE BRPA Eval 12837 Approved

Archive2 12 Fayette 51 0 93073 PA 51 SR 201 to Randall's A.1.a, A.3 Kim Ansell 6/1/2011 CE BRPA Eval 12882 Approved

Archive2 12 Fayette 119 13M 91125 US 119 over US 40 Preserv B.2 Kim Ansell 4/13/2012 ED BRPA Eval 14681 Approved

Archive2 12 Fayette 119 23R 82945 US119 Pechin Rd - Walmart A.1.a, A.1.c Kim Ansell 6/1/2011 ED BRPA Eval 12913 Approved

Archive2 12 Fayette 1048 0 87989 D12 Bridge Preserv 2011-1 B.2, B.3 Kim Ansell 8/8/2011 The project is bridge preservation, no

excavation work. Also, none of the bridges

are NR eligible, see attached email.

ED BRPA Eval 13237 Approved

Archive2 12 Fayette 2010 01M 95033 Brdg Preservation 2012-2 B.2 Kim Ansell 3/6/2012 None of the bridges are eligible for the

National Register of Historic Places.

ED BRPA Eval 14564 Approved

Archive2 12 Fayette 2010 01M 95033 Brdg Preservation 2012-2 B.2 Kim Ansell 3/6/2012 ED BRPA Eval 14564 Approved

Archive2 12 Fayette 2010 01M 95033 Brdg Preservation 2012-2 B.2 Kim Ansell 3/6/2012 ED BRPA Eval 14564 Approved

Archive2 12 Fayette 2010 01M 95033 Brdg Preservation 2012-2 B.2 Kim Ansell 3/6/2012 ED BRPA Eval 14564 Approved

Archive2 12 Fayette 2010 01M 95033 Brdg Preservation 2012-2 B.2 Kim Ansell 3/6/2012 ED BRPA Eval 14564 Approved

Archive2 12 Fayette 2010 01M 95033 Brdg Preservation 2012-2 B.2 Kim Ansell 3/6/2012 ED BRPA Eval 14564 Approved

Archive2 12 Fayette 2010 01M 95033 Brdg Preservation 2012-2 B.2 Kim Ansell 3/6/2012 The bridge is not eligible for the National

Register according to the Historic Bridge

Survey.

ED BRPA Eval 14564 Approved

Archive2 12 Fayette 2010 01M 95033 Brdg Preservation 2012-2 B.2 Kim Ansell 3/6/2012 The bridge is not National Register eligible

according to the Historic Bridge Survey.

ED BRPA Eval 14564 Approved

Archive2 12 Fayette 2010 01M 95033 Brdg Preservation 2012-2 A.4 Kim Ansell 4/20/2012 The bridge is not eligible for the National

Register according to the Historic Bridge

Survey.

ED BRPA Eval 14564 Approved

Archive2 12 Fayette 2010 01M 95033 Brdg Preservation 2012-2 A.4 Kim Ansell 4/20/2012 The bridge is not eligible for the National

Register according to the Historic Bridge

Survey.

ED BRPA Eval 14564 Approved

Archive2 12 Fayette 7218 G40 51267 Grant Street #40 B.1 Ryan Rowles & David Anthony 9/30/2011 Bridge Replacement CE BRPA Eval 14133 Approved

Archive2 12 Greene 0 WBP 87085 Waynesburg Walk/Bike Path A.7.a, A.7.b, A.7.c Kim Ansell 1/25/2012 CE BRPA Eval 14705 Approved

Archive2 12 Greene 21 14R 87374 PA21 Gwynn Rd to Polaris A.1.a, A.1.c Kim Ansell 6/1/2011 CE BRPA Eval 12838 Approved

Archive2 12 Greene 79 13M 91138 I79 ov PA 21 Brdg Preserv A.4 Kim Ansell 4/5/2012 ED BRPA Eval 14725 Approved

Archive2 12 Greene 79 13M 91138 I79 ov PA 21 Brdg Preserv A.4 Kim Ansell 4/5/2012 ED BRPA Eval 14725 Approved

Archive2 12 Greene 79 MS1 94801 I-79 Microsurface 2012 A.1.a, A.1.c, A.1.f Kim Ansell 2/15/2012 Field viewed the project area February 15,

2012.

CE BRPA Eval 14467 Approved

Archive2 12 Washington 70 21M 90640 I-70 over SR 3024 Preserv A.4 Kim Ansell 3/27/2012 According the historic bridge survey, the

bridges are not eligible for the NRHP.

ED BRPA Eval 14668 Approved

Archive2 12 Washington 70 21M 90640 I-70 over SR 3024 Preserv A.4 Kim Ansell 3/27/2012 The bridges are not elilgible for the NRHP

according to the historic bridge survey.

ED BRPA Eval 14668 Approved

Archive2 12 Washington 79 0 94762 SR 79-17R Overlay A.1.a Kim Ansell 1/23/2012 CE BRPA Eval 14376 Approved

Archive2 12 Washington 9900 M10 47845 Mingo Creek Bridge #10 B.1 Ryan Rowles & David Anthony 3/2/2012 ED BRPA Eval 14623 Approved

Archive2 12 Westmoreland 0 --- 73372 HS West Newton Boro A.7.a, A.7.c Kim Ansell 10/25/2011 CE 1b Eval 3627 Approved

Archive2 12 Westmoreland 56 0 88080 PA 56:Valley HS - Melwood A.1.a, A.1.c Kim Ansell 5/4/2011 CE BRPA Eval 12730 Approved

Archive2 12 Westmoreland 56 0 88081 PA 56 - SR 4093 to River A.1.a, A.1.c Kim Ansell 5/4/2011 CE BRPA Eval 12729 Approved

Archive2 12 Westmoreland 119 13M 94563 Brdg Preservation 2012-1 A.4 Kim Ansell 11/23/2011 The project was field viewed by Kim Ansell

on 11-23-2011. The bridge is not listed on

the historic bridge survey.

ED BRPA Eval 13995 Approved

Archive2 12 Westmoreland 119 13M 94563 Brdg Preservation 2012-1 A.4 Kim Ansell 11/23/2011 The bridge is not listed on the historic bridge

survey. The project was field viewed by Kim

Ansell on 11-23-2011.

ED BRPA Eval 13995 Approved

Archive2 12 Westmoreland 119 13M 94563 Brdg Preservation 2012-1 A.4 Kim Ansell 11/23/2011 The bridge is not listed on the Pennsylvania

historic bridge survey. The project was field

viewed by Kim Ansell on 11-23-2011.

ED BRPA Eval 13995 Approved

Archive2 12 Westmoreland 3093 02M 89082 SR 3093 over US 119 Presv B.2 Kim Ansell 4/13/2012 ED BRPA Eval 14680 Approved

52

Appendix C CRP Findings/Postings

MPMS District County SR Section Project Name Posting Received Date Category Response

DatePHMC

Objections Contact

311 1 Crawford Smith Road Bridge (T-406) State Level Recordation 7/12/2011Mitigation: MOA/PA Commitment Coordination 7/20/2011 David Anthony

354 1 Crawford 2003 B00Mercer Pike Bridge over Conneaut Outlet Above Ground Field Assessment and Finding 6/27/2011

Determination of Effects: Above-Ground Field Assessment and Finding 6/29/2011 David Anthony

354 1 Crawford 2003 B00Mercer Pike Bridge over Conneaut Outlet Archaeological Field assessment & Finding 7/5/2011

Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

354 1 Crawford 2003 B00Mercer Pike Bridge over Conneaut Outlet Rehabilitation Feasibility Analysis-Revised 5/13/2011

Determination of Effects: Feasibility Analysis 6/2/2011 Kara Russell

354 1 Crawford 2003 B00Mercer Pike Bridge over Conneaut Outlet Letter of Agreement 7/15/2011

Resolution of Adverse Effects: Letter of Agreement 7/20/2011 Kara Russell

422 1 Crawford 1043 B00 Price Road Br SR 1043 Above Ground Field Assessment and Finding 3/19/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

422 1 Crawford 1043 B00 Price Road Br SR 1043 Archaeological Field Assessment & Finding 4/3/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

579 1 Crawford 173 B02 Cochranton Bridge Replacement Above Ground Field Assessment and Finding 2/3/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

579 1 Crawford 173 B02 Cochranton Bridge Replacement Archaeology Field Assessment & Finding 2/3/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

579 1 Crawford 173 B02 Cochranton Bridge Replacement Project Early Notification 11/10/2011Early Coordination: Advance Notification to SHPO David Anthony

70125 1 Crawford T06 Ernst Bike Trail PHMC Cover Letter & Phase I/II Management Summary 10/3/2011

Determination of Effects: Effect Determination 10/21/2011 Joe Verbka

70125 1 Crawford T06 Ernst Bike Trail Early Notification 9/8/2011Early Coordination: Advance Notification to SHPO Joe Verbka

70125 1 Crawford T06 Ernst Bike Trail PHMC Cover Letter & Phase I/II Management Summary 10/3/2011

Identification: Phase I/II Archaeological Evaluation 10/21/2011 Joe Verbka

71025 1 Crawford 0 T06 Ernst Bike Trail Ph 2 Above Ground Field Assessment and Finding 40935Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

880 1 Erie North Mill St. Bridge Above Ground Field Assessment and Finding 12/21/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

880 1 Erie North Mill St. Bridge Archaeological Field assessment & Finding 12/14/2011Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

72623 1 Erie 1008 B00 Twelve Mile Creek/SR 1008 Above Ground Field Assessment and Finding 9/8/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

72623 1 Erie 1008 B00 Twelve Mile Creek/SR 1008 Archaeology Field Assessment & Finding 10/5/2011Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

88711 1 Erie 3006 A00 SR 3006: Fry Road Determination of Effect 6/22/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

88711 1 Erie 3006 A00 SR 3006: Fry Road Determination of Effect 6/22/2011Determination of Effects: Archaeology Field Assessment and Finding David Anthony

90025 1 Erie 5 B11 PA 5 over Trib Lake Erie Above Ground Field Assessment and Finding 2/3/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

90025 1 Erie 5 B11 PA 5 over Trib Lake Erie Archaeological Field Assessment & Finding 2/14/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

92870 1 Erie T27 Corry Trail Phase 3 Archaeological Field Assessment & Finding 2/13/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

1374 1 Forest 2002 B00 SR2002 Tom's Run Above Ground Field Assessment and Finding 8/22/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

1374 1 Forest 2002 B00 SR2002 Tom's Run Archaeological Field assessment & Finding 8/9/2011Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

1374 1 Forest 2002 B00 SR2002 Tom's Run Archaeological Field assessment & Finding 8/9/2011Identification: Phase I Archaeological Survey Joe Verbka

1528 1 Mercer 1015 B00 Carlton Bridge Mitigation Proposal Letter 5/3/2012Mitigation: MOA/PA Commitment Coordination Joe Verbka

1528 1 Mercer 1015 B00 Carlton Bridge Above Ground Field Assessment and Finding 8/22/2011Determination of Effects: Above-Ground Field Assessment and Finding 9/19/2011 David Anthony

1528 1 Mercer 1015 B00 Carlton Bridge Phase I/II Archaeological Report Summary 3/12/2012Determination of Effects: Effect Determination 3/16/2012 Joe Verbka

1528 1 Mercer 1015 B00 Carlton Bridge Project Early Notification 7/26/2011Early Coordination: Advance Notification to SHPO David Anthony

1528 1 Mercer 1015 B00 Carlton Bridge Phase I/II Archaeological Report Summary 3/12/2012Identification: Phase II Archaeological Evaluation 3/16/2012 Joe Verbka

1671 1 Mercer 7303 0 Kelly Road Bridge Project Early Notification 11/16/2011Early Coordination: Advance Notification to SHPO David Anthony

1671 1 Mercer 7303 0 Kelly Road Bridge Historic Resource Boundary Clarification 10/31/2011Identification: Historic Resource Determination of Eligibility 11/22/2011 David Anthony

1671 1 Mercer 7303 0 Kelly Road Bridge Above Ground Field Assessment and Finding 5/3/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

1692 1 Mercer 740 Mill Road Bridge Replacement Archaeological Phase I/II Report 3/13/2012Determination of Effects: Effect Determination 3/16/2012 Joe Verbka

1692 1 Mercer 740 Mill Road Bridge Replacement Archaeological Phase I/II Report 3/13/2012Identification: Phase I/II Archaeological Evaluation 3/16/2012 Joe Verbka

1692 1 Mercer 740 Mill Road Bridge Replacement Project Early Notification 3/19/2012Public Involvement: Early Coordination/Advance Notification David Anthony

1738 1 Mercer 2005 B00 SR 2005/Livermore Br Above Ground Field Assessment and Finding 8/3/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

1738 1 Mercer 2005 B00 SR 2005/Livermore Br Archaeological Field Assessment & Finding 8/10/2011Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

1815 1 Mercer 19 B04 Iron Bridge Replacement Above Ground Field Assessment and Finding 6/8/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

1815 1 Mercer 19 B04 Iron Bridge Replacement US 19 over Neshannock Creek (Iron Bridge) 6/8/2011Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

1815 1 Mercer 19 B04 Iron Bridge Replacement US 19 over Neshannock Creek (Iron Bridge) 6/8/2011Identification: Phase I Archaeological Survey Joe Verbka

1827 1 Mercer 58 B05 PA 58 Br over Moury Run Above Ground Field Assessment and Finding 1/20/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

1827 1 Mercer 58 B05 PA 58 Br over Moury Run Archaeology Field Assessment & Finding 1/23/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

1923 1 Mercer 318 B00West Middlesex Bridge (SR 0318 Seg 0060) Above Ground Field Assessment and Finding 8/8/2011

Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

1923 1 Mercer 318 B00West Middlesex Bridge (SR 0318 Seg 0060) Archaeological Field Assessment & Finding 4/3/2012

Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

93071 1 Mercer T12 Indian Run Ped Bridge Above Ground Field Assessment and Finding 3/12/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

93071 1 Mercer T12 Indian Run Ped Bridge Archaeological Field Assessment & Finding 3/7/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

2254 1 Venango Cherrytree Road Bridge Above Ground Field Assessment and Finding 8/26/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

67183 1 Venango 257 A03 SR62/257 Intersection Above Ground Field Assessment and Finding 11/14/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

67183 1 Venango 257 A03 SR62/257 Intersection Above Ground Field Assessment and Finding 1/27/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

67183 1 Venango 257 A03 SR62/257 Intersection Archaeology Field Assessment & Finding 1/23/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

2933 2 Centre 2012 A06 Penns Creek Road Bridge Project Finding 6/16/2011Determination of Effects: Above-Ground Field Assessment and Finding Scott Shaffer

2933 2 Centre 2012 A06 Penns Creek Road Bridge Project Finding 6/16/2011Determination of Effects: Archaeology Field Assessment and Finding Scott Shaffer

2933 2 Centre 2012 A06 Penns Creek Road Bridge Project Finding 6/16/2011Identification: Phase I Archaeological Survey Scott Shaffer

3142 2 Centre 80 B18 Bellefonte Interchange Report Hard Copy 7/13/2011Special Processes: Submittal of Archival Paper Copy 7/15/2011 Scott Shaffer

69468 2 Centre 3006 A03 Bridge Over Buffalo Run Project Finding 3/7/2012Determination of Effects: Effect Determination Scott Shaffer

78994 2 Centre 322 N03 SR 322 Safety Improvement Project Finding 4/10/2012Determination of Effects: Effect Determination Scott Shaffer

78994 2 Centre 322 N03 SR 322 Safety Improvement Hard Copy Cover Letter 4/12/2012Special Processes: Submittal of Archival Paper Copy Scott Shaffer

78994 2 Centre 322 N03 SR 322 Safety Improvement Scoping Form 9/7/2011Scoping: Project Early Notification/ Scoping Results Scott Shaffer

85965 2 Centre 26 147 Jacksonville Rd Bettermnt Project Finding 7/12/2011Determination of Effects: Above-Ground Field Assessment and Finding 7/13/2011 Scott Shaffer

85965 2 Centre 26 147 Jacksonville Rd Bettermnt Project Finding 7/12/2011Determination of Effects: Archaeology Field Assessment and Finding 7/13/2011 Scott Shaffer

85965 2 Centre 26 147 Jacksonville Rd Bettermnt Project Finding 7/12/2011Identification: Phase I Archaeological Survey 7/13/2011 Scott Shaffer

85965 2 Centre 26 147 Jacksonville Rd Bettermnt Scoping Form 6/3/2011Scoping: Project Early Notification/ Scoping Results 6/3/2011 Scott Shaffer

3562 2 Clearfield 3007 A01 Carson Run Bridge Project Finding 10/18/2011Determination of Effects: Above-Ground Field Assessment and Finding Scott Shaffer

3562 2 Clearfield 3007 A01 Carson Run Bridge Project Finding 10/18/2011Determination of Effects: Archaeology Field Assessment and Finding Scott Shaffer

3562 2 Clearfield 3007 A01 Carson Run Bridge Project Finding 10/18/2011Identification: Phase I Archaeological Survey Scott Shaffer

3562 2 Clearfield 3007 A01 Carson Run Bridge Scoping Form 8/3/2011Scoping: Project Early Notification/ Scoping Results Scott Shaffer

3562 2 Clearfield 3007 A01 Carson Run Bridge Hard Copy Cover Letter 10/18/2011Special Processes: Submittal of Archival Paper Copy 10/28/2011 Scott Shaffer

3569 2 Clearfield 970 A01 SR 970 Shawville Bridge Project Finding 7/20/2011Determination of Effects: Above-Ground Field Assessment and Finding Scott Shaffer

3569 2 Clearfield 970 A01 SR 970 Shawville Bridge Project Finding 7/20/2011Determination of Effects: Archaeology Field Assessment and Finding Scott Shaffer

3569 2 Clearfield 970 A01 SR 970 Shawville Bridge Project Finding 7/20/2011Early Coordination: Geomorphological Testing Scott Shaffer

3569 2 Clearfield 970 A01 SR 970 Shawville Bridge Hard Copy Cover Letter 7/20/2011Special Processes: Submittal of Archival Paper Copy 7/21/2011 Scott Shaffer

92521 2 Clearfield Coalport Streetscape Project Finding 6/2/2011 BHP Enhancement: Field Concurrence 5/31/2011 Scott Shaffer

3935 2 Elk 301 Bridge Over Spring Creek MOA Consultation 10/17/2011 Resolution of Adverse Effects: MOA/PA Scott Shaffer

4718 2 Mifflin 1005 A04 Tea Creek Bridge Project Finding 1/23/2012Determination of Effects: Above-Ground Field Assessment and Finding Scott Shaffer

4718 2 Mifflin 1005 A04 Tea Creek Bridge Project Finding 1/23/2012Determination of Effects: Archaeology Field Assessment and Finding Scott Shaffer

81515 2 Mifflin 2001 A02 Jacks Creek Bridge Project Finding 6/3/2011Determination of Effects: Archaeology Field Assessment and Finding Scott Shaffer

81515 2 Mifflin 2001 A02 Jacks Creek Bridge Project Finding 6/3/2011Identification: Phase I Archaeological Survey Scott Shaffer

92530 2 Mifflin Monument Square Phase IV TE Field Assessment and Finding Form 5/13/2011 BHP Enhancement: Field Concurrence Scott Shaffer

92530 2 Mifflin Monument Square Phase IV TE Field Assessment and Finding Form 5/13/2011Determination of Effects: Effect Determination Scott Shaffer

4758 2 Potter 3013 A01 Bridge Repl. Over Allegheny River Project Finding 4/30/2012Determination of Effects: Effect Determination Scott Shaffer

4903 2 Potter 3001 A02 SR 3001 E Fork Sinnem. Ck Early Notification 6/24/2011Scoping: Project Early Notification/ Scoping Results Scott Shaffer

4903 2 Potter 3001 A02 SR 3001 E Fork Sinnem. Ck Hard Copy Cover Letter 2/1/2012Special Processes: Submittal of Archival Paper Copy 2/10/2012 Scott Shaffer

46938 2 Potter 4003 A06 SR 4003 Fishing Creek Hard Copy Cover Letter 11/22/2011Special Processes: Submittal of Archival Paper Copy 12/5/2011 Scott Shaffer

82034 2 Potter 872 A04 Bridge Replacement Over Mill Creek Project Finding 2/3/2012Determination of Effects: Above-Ground Field Assessment and Finding Scott Shaffer

82034 2 Potter 872 A04 Bridge Replacement Over Mill Creek Project Finding 2/3/2012Determination of Effects: Archaeology Field Assessment and Finding Scott Shaffer

5048 3 Bradford 414 25 SR 414 over Towanda Crk Project Finding 1/17/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

5048 3 Bradford 414 25 SR 414 over Towanda Crk Project Finding 1/17/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

5059 3 Bradford 1026 4 SR1026 ov Tb Wyalusing Cr Project Finding 3/19/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

5059 3 Bradford 1026 4 SR1026 ov Tb Wyalusing Cr Project Finding 3/19/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

5124 3 Bradford NULL BR Tomjack Cr. T-623 Project Finding 12/5/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

5124 3 Bradford NULL BR Tomjack Cr. T-623 Project Finding 12/5/2011Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

5293 3 Bradford 1026 3 SR 1026 over Gaylord Crk Project Finding 7/15/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

75698 3 Bradford 1022 9 SR 1022 Bridge Replacement Project Finding 8/17/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

75698 3 Bradford 1022 9 SR 1022 Bridge Replacement Project Finding 8/17/2011Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

87468 3 Bradford 4014 20M Buck's Creek to US 220 Project Finding 11/16/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

87468 3 Bradford 4014 20M Buck's Creek to US 220 Project Finding 11/16/2011Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

88963 3 Bradford 3035 2 SR 3035 over Sugar Creek Scoping Form 5/26/2011Scoping: Project Early Notification/ Scoping Results 5/26/2011 Scott Shaffer

92933 3 Bradford 1014 9 SR 1014 Soil Stabilzation Project Finding 6/14/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

92933 3 Bradford 1014 9 SR 1014 Soil Stabilzation Project Finding 6/14/2011Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

93804 3 Bradford 187 36 SR 187 ov Wappasening Crk Project Finding 2/8/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

93804 3 Bradford 187 36 SR 187 ov Wappasening Crk Project Finding 2/8/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

94410 3 Bradford 220 151 US 220 over Ladds Creek Project Finding 1/23/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

94410 3 Bradford 220 151 US 220 over Ladds Creek Project Finding 1/23/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

94410 3 Bradford 220 151 US 220 over Ladds Creek Scoping Form 12/9/2011Early Coordination: Notification to the SHPO 12/12/2011 Scott Shaffer

94410 3 Bradford 220 151 US 220 over Ladds Creek Hard Copy Cover Letter 1/4/2012Special Processes: Submittal of Archival Paper Copy Scott Shaffer

5555 3 Columbia 1014 8 SR1014 ov Tb Lt Briar Crk Phase I Archaeology Report 3/13/2012Identification: Consulting Party/Tribal Consultation Coordination Scott Shaffer

5555 3 Columbia 1014 8 SR1014 ov Tb Lt Briar Crk Phase I Archaeology Report 3/13/2012Identification: Phase I Archaeological Survey 3/22/2012

5555 3 Columbia 1014 8 SR1014 ov Tb Lt Briar Crk Scoping Form 11/9/2011Scoping: Project Early Notification/ Scoping Results 11/10/2011 Scott Shaffer

5555 3 Columbia 1014 8 SR1014 ov Tb Lt Briar Crk Hard Copy Cover Letter 3/13/2012Special Processes: Submittal of Archival Paper Copy 3/16/2012 Scott Shaffer

85048 3 Columbia 239 17 SR239 ovr Tb WBR West Crk Project Finding 12/20/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

85048 3 Columbia 239 17 SR239 ovr Tb WBR West Crk Project Finding 12/20/2011Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

85048 3 Columbia 239 17 SR239 ovr Tb WBR West Crk Scoping Form 12/6/2011Scoping: Project Early Notification/ Scoping Results 12/7/2011 Scott Shaffer

87988 3 Columbia 442 8 SR 442 Bridge Project Finding 1/19/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

87988 3 Columbia 442 8 SR 442 Bridge Project Finding 1/19/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

94043 3 Columbia 4013 18 SR 4013 ov Deer Lick Run Effect Finding 12/2/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

94043 3 Columbia 4013 18 SR 4013 ov Deer Lick Run Effect Finding 12/2/2011Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

5943 3 Lycoming 2069 1 Truss over Muncy Creek Early Notification 1/30/2012Early Coordination: Notification to the SHPO Matthew Hamel

6050 3 Lycoming 554 3 FRP Contract Lycoming Project Finding 1/5/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

6050 3 Lycoming 554 3 FRP Contract Lycoming Project Finding 1/5/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

6071 3 Lycoming 7219 0 Sheridan St ov Millers Rn Project Finding 3/28/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

6071 3 Lycoming 7219 0 Sheridan St ov Millers Rn Project Finding 3/28/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

76486 3 Lycoming 15 116 SR 15 Jug Handle Project Finding 10/17/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

76486 3 Lycoming 15 116 SR 15 Jug Handle Project Finding 10/17/2011Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

87887 3 Lycoming 554 2 SR 554 over Hagermans Run Project Finding 1/26/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

87887 3 Lycoming 554 2 SR 554 over Hagermans Run Project Finding 1/26/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

87915 3 Lycoming 287 132 SR 287 Bridge Project Finding 2/3/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

87915 3 Lycoming 287 132 SR 287 Bridge Project Finding 2/3/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

87919 3 Lycoming 287 133 SR 287 over Lawshe Run Project Finding 12/5/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

87919 3 Lycoming 287 133 SR 287 over Lawshe Run Project Finding 12/5/2011Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

93808 3 Lycoming 864 7 SR864 Roadway Flood Repair Project Finding 1/23/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

93808 3 Lycoming 864 7 SR864 Roadway Flood Repair Project Finding 1/23/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

94183 3 Lycoming 1006 22 SR 1006 ov Engle Run Phase I-II Archaeology Report 4/9/2012Identification: Phase I & II Archaeological Evaluation Scott Shaffer

94183 3 Lycoming 1006 22 SR 1006 ov Engle Run Hard Copy Cover Letter 4/9/2012Special Processes: Submittal of Archival Paper Copy Scott Shaffer

94183 3 Lycoming 1006 22 SR 1006 ov Engle Run Project Scoping Form 2/17/2012Scoping: Project Early Notification/ Scoping Results Scott Shaffer

6597 3 Northumberland 4022 1 SR4022 over Boiles Run Project Finding 8/24/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

6597 3 Northumberland 4022 1 SR4022 over Boiles Run Project Finding 8/24/2011Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

6729 3 Northumberland 405 73SR 405 Bridge over Norfolk Southern Railroad Project Finding 7/26/2011

Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

6729 3 Northumberland 405 73SR 405 Bridge over Norfolk Southern Railroad Project Finding 7/26/2011

Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

6729 3 Northumberland 405 73SR 405 Bridge over Norfolk Southern Railroad Project Finding 7/26/2011

Identification: Phase I Archaeological Survey Matthew Hamel

6729 3 Northumberland 405 73SR 405 Bridge over Norfolk Southern Railroad Tribal Notification 7/25/2011

Public Involvement: Tribal Consultation Coordination Scott Shaffer

6729 3 Northumberland 405 73SR 405 Bridge over Norfolk Southern Railroad Hard Copy Cover Letter 7/27/2011

Special Processes: Submittal of Archival Paper Copy Scott Shaffer

88853 3 Northumberland 0 T608 over Warrior Run Scoping Form 5/26/2011Scoping: Project Early Notification/ Scoping Results 5/26/2011 Scott Shaffer

7588 3 Snyder 15 88Central Susquehanna Valley Transportation Report Hard Copy 7/13/2011

Special Processes: Submittal of Archival Paper Copy 7/15/2011 Scott Shaffer

47303 3 Snyder 3007 9 Truss Over Middle Creek Letter of Agreement Amendment 8/8/2011Resolution of Adverse Effects: Letter of Agreement 8/9/2011 Kara Russell

81509 3 Snyder 1023 09M From SR 11/15 to SR 61 Project Finding 2/13/2012Determination of Effects: Above-Ground Field Assessment and Finding 3/6/2012 Matthew Hamel

81509 3 Snyder 1023 09M From SR 11/15 to SR 61 Project Finding 2/13/2012Determination of Effects: Archaeology Field Assessment and Finding 3/6/2012 Matthew Hamel

81509 3 Snyder 1023 09M From SR 11/15 to SR 61 Scoping Form 12/20/2011Scoping: Project Early Notification/ Scoping Results Scott Shaffer

81509 3 Snyder 1023 09M From SR 11/15 to SR 61 Hard Copy Cover Letter 2/14/2012Special Processes: Submittal of Archival Paper Copy 2/23/2012 Scott Shaffer

88017 3 Snyder 1023 10 SR1023 ov Tb Susquehanna Project Finding 3/20/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

88017 3 Snyder 1023 10 SR1023 ov Tb Susquehanna Project Finding 3/20/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

94352 3 Sullivan 2002 18 SR 2002 over Muncy Creek Project Finding 12/2/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

94352 3 Sullivan 2002 18 SR 2002 over Muncy Creek Project Finding 12/2/2011Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

7365 3 Tioga BRG T-402 COWANESQUE RIV Feasibility Analysis 12/6/2011Determination of Effects: Feasibility Analysis Matthew Hamel

82203 3 Tioga 287 90 Marsh Creek Bridge Scoping Form 8/3/2011Scoping: Project Early Notification/ Scoping Results Scott Shaffer

82732 3 Tioga 7409 0 King St over Kelsey Creek Project Finding 1/18/2012Determination of Effects: Above-Ground Field Assessment and Finding 3/1/2012 Matthew Hamel

82732 3 Tioga 7409 0 King St over Kelsey Creek Project Finding 1/18/2012Determination of Effects: Archaeology Field Assessment and Finding 3/1/2012 Matthew Hamel

83713 3 Tioga 3001 6 SR 3001 over Buck Run Project Finding 8/19/2011Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

83713 3 Tioga 3001 6 SR 3001 over Buck Run Project Finding 8/19/2011Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

93087 3 Tioga 15 144SR 15 Section 144 Slide Remediation Project Finding Temporary Fix 12/12/2011

Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

93087 3 Tioga 15 144SR 15 Section 144 Slide Remediation Project Finding Temporary Fix 12/12/2011

Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

93087 3 Tioga 15 144SR 15 Section 144 Slide Remediation Tribal Consultation 12/20/2011

Public Involvement: Tribal Consultation Coordination Scott Shaffer

93087 3 Tioga 15 144SR 15 Section 144 Slide Remediation Hard Copy Cover Letter 3/12/2012

Special Processes: Submittal of Archival Paper Copy 3/16/2012 Scott Shaffer

7498 3 Union 309 Laurel Park Bridge over Penns Creek Feasibility Report 3/16/2012Determination of Effects: Feasibility Analysis Matthew Hamel

7500 3 Union BR County Bridge #14 Project Finding 1/18/2012Determination of Effects: Above-Ground Field Assessment and Finding Matthew Hamel

7500 3 Union BR County Bridge #14 Project Finding 1/18/2012Determination of Effects: Archaeology Field Assessment and Finding Matthew Hamel

7500 3 Union BR County Bridge #14 Hard Copy Cover Letter 1/19/2012Special Processes: Submittal of Archival Paper Copy Scott Shaffer

7838 4 Lackawanna 6011 273 Harrison Avenue Bridge Adverse Effect Determination 7/26/2011Determination of Effects: Effect Determination - non-form 7/27/2011 Kristina Thompson

7838 4 Lackawanna 6011 273 Harrison Avenue Bridge MOA Draft for Review 10/25/2011 Resolution of Adverse Effects: MOA/PA Kristina Thompson

7838 4 Lackawanna 6011 273 Harrison Avenue Bridge MOA 12/27/2011 Resolution of Adverse Effects: MOA/PA 1/17/2012 Kara Russell

7884 4 Lackawanna 438 271 Wallsville Rd Bridge Replacement Early Notification_Scoping Results 11/9/2011Early Coordination: Area of Potential Effect Kevin Mock

7913 4 Lackawanna 3021 271Stafford Avenue Bridge Replacement

Determination of Effects-Archaeology and Historic Structures 12/8/2011

Determination of Effects: Above-Ground Field Assessment and Finding Kevin Mock

7913 4 Lackawanna 3021 271Stafford Avenue Bridge Replacement

Determination of Effects-Archaeology and Historic Structures 12/8/2011

Determination of Effects: Archaeology Field Assessment and Finding Kevin Mock

7939 4 Lackawanna 3011 271 Keyser Avenue Bridge Determination of Effects 2/7/2012Determination of Effects: Effect Determination - non-form 2/7/2012 Kevin Mock

8006 4 Lackawanna 4032 250Shady Lane Bridge #2 Bridge Replacement

Determination of Effects-Historic Structures and Archaeology 7/7/2011

Determination of Effects: Above-Ground Field Assessment and Finding 7/20/2011 Kevin Mock

8006 4 Lackawanna 4032 250Shady Lane Bridge #2 Bridge Replacement

Determination of Effects-Historic Structures and Archaeology 7/7/2011

Determination of Effects: Archaeology Field Assessment and Finding 7/20/2011 Kevin Mock

8006 4 Lackawanna 4032 250Shady Lane Bridge #2 Bridge Replacement Early Notification - Scoping Results 6/27/2011

Scoping: Project Early Notification/ Scoping Results 6/27/2011 Kevin Mock

8221 4 Lackawanna 6 214 Lackawanna Trail Betterment Deferred Archaeological Testing 5/20/2011Special Processes: Deferral of Archaeological Testing Kevin Mock

8394 4 Lackawanna 347 207 Dunmore SignalsDetermination of Effects-Archaeology and Historic Structures 3/29/2012

Determination of Effects: Above-Ground Field Assessment and Finding Kevin Mock

8394 4 Lackawanna 347 207 Dunmore SignalsDetermination of Effects-Archaeology and Historic Structures 3/29/2012

Determination of Effects: Archaeology Field Assessment and Finding Kevin Mock

57706 4 Lackawanna 1012 202 Kennedy Drive & County RoadDetermination of Effects - Historic Structures and Archaeology 8/22/2011

Determination of Effects: Above-Ground Field Assessment and Finding Kevin Mock

57706 4 Lackawanna 1012 202 Kennedy Drive & County RoadDetermination of Effects - Historic Structures and Archaeology 8/22/2011

Determination of Effects: Archaeology Field Assessment and Finding Kevin Mock

67085 4 Lackawanna 7211 EMG T437 College Av Marcomis Early Notification_Scoping Results 8/15/2011Early Coordination: Notification to the SHPO Kevin Mock

67085 4 Lackawanna 7211 EMG T437 College Av Marcomis Early Notification_Scoping Results 8/15/2011Public Involvement: Early Coordination/Advance Notification Kevin Mock

68853 4 Lackawanna 4005 270 SR 4005 over D&H RR Early Notification 9/23/2011Early Coordination: Notification to the SHPO Kevin Mock

68853 4 Lackawanna 4005 270 SR 4005 over D&H RR Early Notification 9/23/2011Public Involvement: Early Coordination/Advance Notification Kevin Mock

68862 4 Lackawanna 4012 270 SR 4012 over D&H RRCombined No Adverse Effect Finding-additional scope 1/18/2012

Determination of Effects: Above-Ground Field Assessment and Finding Kristina Thompson

68862 4 Lackawanna 4012 270 SR 4012 over D&H RRCombined No Adverse Effect Finding-additional scope 3/8/2012

Determination of Effects: Above-Ground Field Assessment and Finding Kristina Thompson

68862 4 Lackawanna 4012 270 SR 4012 over D&H RRCombined No Adverse Effect Finding-additional scope 1/18/2012

Determination of Effects: Archaeology Field Assessment and Finding Kristina Thompson

68862 4 Lackawanna 4012 270 SR 4012 over D&H RRCombined No Adverse Effect Finding-additional scope 3/8/2012

Determination of Effects: Archaeology Field Assessment and Finding Kristina Thompson

68862 4 Lackawanna 4012 270 SR 4012 over D&H RRDetermination of Effects-Historic Structures and Archaeology 6/26/2011

Determination of Effects: Effect Determination 7/18/2011 Kevin Mock

68862 4 Lackawanna 4012 270 SR 4012 over D&H RREffect Response to PHMC Conditional Concurrence 9/12/2011

Determination of Effects: Effect Determination 9/21/2011 Kristina Thompson

8677 4 Luzerne 1021 370 Eighth Street Bridge Project Tribal Consultation 12/23/2011Public Involvement: Tribal Consultation Coordination Kevin Mock

8677 4 Luzerne 1021 370 Eighth Street Bridge Project Tribal Consultation 12/23/2011Public Involvement: Tribal Consultation Coordination Kevin Mock

9165 4 Luzerne 7220 BRG County Rd. 16 Bridge ReplacementNo Adverse Effect Combined Finding-Revised Scope 11/22/2011

Determination of Effects: Effect Determination - non-form 12/13/2011 Kristina Thompson

57671 4 Luzerne 1012 370 Drake's Creek Bridge Early Notification/Scoping Results 3/29/2012Scoping: Project Early Notification/ Scoping Results Kevin Mock

57728 4 Luzerne 2004 390 River Street @ King's College No Adverse Effect Combined Finding 9/12/2011Determination of Effects: Above-Ground Field Assessment and Finding 9/21/2011 Kristina Thompson

57728 4 Luzerne 2004 390 River Street @ King's College No Adverse Effect Combined Finding 9/12/2011Determination of Effects: Archaeology Field Assessment and Finding 9/21/2011 Kristina Thompson

77378 4 Luzerne White Haven Engine House ProjectDetermination of Effect-Historic Structures and Archaeology 5/10/2011 BHP Enhancement: Field Concurrence 5/27/2011 Kristina Thompson

77378 4 Luzerne White Haven Engine House ProjectDetermination of Effect-Historic Structures and Archaeology 5/10/2011

Determination of Effects: Effect Determination 5/27/2011 Kristina Thompson

87184 4 Luzerne West Side Trail Phase 1BNo Effect Finding for Transportation Enhancement Project 4/3/2012

Determination of Effects: Above-Ground Field Assessment and Finding 4/6/2012 Kristina Thompson

87184 4 Luzerne West Side Trail Phase 1BNo Effect Finding for Transportation Enhancement Project 4/3/2012

Determination of Effects: Archaeology Field Assessment and Finding 4/6/2012 Kristina Thompson

90129 4 Luzerne ENH D&L Heritage Corridor Trail ProjectDetermination of Effects-Archaeology and Historic Structures 3/16/2012

Determination of Effects: Above-Ground Field Assessment and Finding 3/22/2012 Kevin Mock

90129 4 Luzerne ENH D&L Heritage Corridor Trail ProjectDetermination of Effects-Archaeology and Historic Structures 3/16/2012

Determination of Effects: Archaeology Field Assessment and Finding 3/22/2012 Kevin Mock

9329 4 Pike 1011 470 Pond Eddy Bridge Determination of Effect 5/26/2011Determination of Effects: Effect Determination Kevin Mock

9329 4 Pike 1011 470 Pond Eddy Bridge Determination of Effects-Historic Structures 7/5/2011Determination of Effects: Effect Determination 7/5/2011 Kevin Mock

9329 4 Pike 1011 470 Pond Eddy Bridge MOA Coordination 7/5/2011Mitigation: MOA/PA Commitment Coordination Kevin Mock

9329 4 Pike 1011 470 Pond Eddy Bridge MOA Coordination 8/17/2011Mitigation: MOA/PA Commitment Coordination Kevin Mock

9329 4 Pike 1011 470 Pond Eddy Bridge Consulting Party Coordination 7/15/2011Public Involvement: Consulting Party Coordination Kevin Mock

9329 4 Pike 1011 470 Pond Eddy Bridge Public Involvement-Consulting Party Coordination 8/19/2011Public Involvement: Consulting Party Coordination Kevin Mock

9329 4 Pike 1011 470 Pond Eddy Bridge Tribal Follow-up - MOA 8/19/2011Resolution of Adverse Effects: Consulting Party/Tribal Consultation Coordination Kevin Mock

9329 4 Pike 1011 470 Pond Eddy Bridge Tribal Follow-up - MOA 8/19/2011 Resolution of Adverse Effects: MOA/PA Kevin Mock

9329 4 Pike 1011 470 Pond Eddy Bridge MOA 11/4/2011 Resolution of Adverse Effects: MOA/PA 12/6/2011 Kara Russell

9419 4 Pike 739 452SR 739 over Shohola Creek Bridge Rehab

Determination of Effects-Archaeology and Historic Structures 12/27/2011

Determination of Effects: Above-Ground Field Assessment and Finding Kevin Mock

9419 4 Pike 739 452SR 739 over Shohola Creek Bridge Rehab

Determination of Effects-Archaeology and Historic Structures 12/27/2011

Determination of Effects: Archaeology Field Assessment and Finding Kevin Mock

9580 4 Susquehanna 1016 570New Milford RR Bridge Replacement Letter of Agreement 6/27/2011

Resolution of Adverse Effects: Letter of Agreement 6/30/2011 Kara Russell

9580 4 Susquehanna 1016 570New Milford RR Bridge Replacement Final Letter of Agreement posting 7/29/2011

Resolution of Adverse Effects: Letter of Agreement 7/29/2011 Kristina Thompson

9700 4 Susquehanna 29 551PA 29 over Snake Creek Bridge #1 Replacement

Determination of Effects-Historic Structures and Archaeology 7/29/2011

Determination of Effects: Above-Ground Field Assessment and Finding Kevin Mock

9700 4 Susquehanna 29 551PA 29 over Snake Creek Bridge #1 Replacement

Determination of Effects-Historic Structures and Archaeology 7/29/2011

Determination of Effects: Archaeology Field Assessment and Finding Kevin Mock

47124 4 Susquehanna 503 Fairdale to W. Montrose Early Notification-Scoping Results 9/28/2011Early Coordination: Area of Potential Effect Kevin Mock

47124 4 Susquehanna 503 Fairdale to W. Montrose Early Notification-Scoping Results 9/28/2011Public Involvement: Early Coordination/Advance Notification Kevin Mock

47126 4 Susquehanna 505 Tiffany to US 11 Early Notification-Scoping Results 9/28/2011Early Coordination: Area of Potential Effect Kevin Mock

47126 4 Susquehanna 505 Tiffany to US 11 Early Notification-Scoping Results 9/28/2011Public Involvement: Early Coordination/Advance Notification Kevin Mock

62996 4 Susquehanna 92 502 SR 92 & 171 IntersectionAdverse Effect Determination-Above Ground Properties 5/11/2011

Determination of Effects: Above-Ground Field Assessment and Finding Kristina Thompson

62996 4 Susquehanna 92 502 SR 92 & 171 IntersectionNo Adverse Effect Finding for Above-Ground Resources-REVISED 11/22/2011

Determination of Effects: Above-Ground Field Assessment and Finding 12/13/2011 Kristina Thompson

62996 4 Susquehanna 92 502 SR 92 & 171 Intersection Effect Finding-Archaeology 6/22/2011Determination of Effects: Archaeology Field Assessment and Finding 8/3/2011 Kevin Mock

62996 4 Susquehanna 92 502 SR 92 & 171 Intersection Early Notification_Scoping Results Form 5/10/2011Early Coordination: Notification to the SHPO Kevin Mock

62996 4 Susquehanna 92 502 SR 92 & 171 Intersection Effect Finding-Archaeology 6/22/2011Identification: Phase I Archaeological Survey 8/3/2011 Kevin Mock

62996 4 Susquehanna 92 502 SR 92 & 171 Intersection Mitigation-Letter of Agreement 7/29/2011Mitigation: MOA/PA Commitment Coordination Kevin Mock

62996 4 Susquehanna 92 502 SR 92 & 171 Intersection Letter of Agreement 8/25/2011Resolution of Adverse Effects: Letter of Agreement 8/29/2011 Kara Russell

67522 4 Susquehanna 267 553Middle Wyalusing Creek Bridge Replacement

Determination of Effects - Historic Structures and Archaeology 8/25/2011

Determination of Effects: Effect Determination Kevin Mock

67522 4 Susquehanna 267 553Middle Wyalusing Creek Bridge Replacement

Determination of Effects - Historic Structures and Archaeology 8/25/2011 Special Processes: Standard Treatment Kevin Mock

67558 4 Susquehanna 1010 551SR 1010 over Salt Lick Creek Bridge Replacement

Determination of Effects-Historic Structures and Archaeology 8/5/2011

Determination of Effects: Above-Ground Field Assessment and Finding Kevin Mock

67558 4 Susquehanna 1010 551SR 1010 over Salt Lick Creek Bridge Replacement

Determination of Effects-Historic Structures and Archaeology 8/5/2011

Determination of Effects: Archaeology Field Assessment and Finding Kevin Mock

75976 4 Susquehanna 81 590I-81 Interchange Improvement at Gibson

Determination of Effects-Archaeology and Historic Structures 12/22/2011

Determination of Effects: Above-Ground Field Assessment and Finding Kevin Mock

75976 4 Susquehanna 81 590I-81 Interchange Improvement at Gibson

Determination of Effects-Archaeology and Historic Structures 12/22/2011

Determination of Effects: Archaeology Field Assessment and Finding Kevin Mock

75976 4 Susquehanna 81 590I-81 Interchange Improvement at Gibson Early Notification_Scoping Results Form 5/4/2011

Scoping: Project Early Notification/ Scoping Results Kevin Mock

88613 4 Susquehanna 858 552 SR 0858 Bridge over Summers CreekDetermination of Effects-Historic Structures and Archaeology 7/5/2011

Determination of Effects: Above-Ground Field Assessment and Finding Kevin Mock

88613 4 Susquehanna 858 552 SR 0858 Bridge over Summers CreekDetermination of Effects-Historic Structures and Archaeology 7/5/2011

Determination of Effects: Archaeology Field Assessment and Finding Kevin Mock

88613 4 Susquehanna 858 552 SR 0858 Bridge over Summers CreekDetermination of Effects-Historic Structures and Archaeology 7/5/2011 Special Processes: Standard Treatment Kevin Mock

64824 4 Wayne 7216 BRG Wangum Bridge #29 Letter of Agreement-Draft for Review 11/1/2011Resolution of Adverse Effects: Letter of Agreement Kristina Thompson

64824 4 Wayne 7216 BRG Wangum Bridge #29 Letter of Agreement- Final 3/26/2012Resolution of Adverse Effects: Letter of Agreement 4/2/2012 Kara Russell

77528 4 WayneD&H Towpath to Trail Project - Phase 3a PA Commitment Coordination 8/5/2011

Mitigation: MOA/PA Commitment Coordination Kevin Mock

77528 4 WayneD&H Towpath to Trail Project - Phase 3a Tribal Coordination 8/5/2011

Public Involvement: Consulting Party/Tribal Consultation Coordination Kevin Mock

77528 4 WayneD&H Towpath to Trail Project - Phase 3a Programmatic Agreement Coordination - ACHP 6/10/2011 Resolution of Adverse Effects: MOA/PA Kevin Mock

10113 4 Wyoming 1029 770 Tunkhannock Creek BridgeRehabilitation Feasibility Study and Consulting Party Meeting Invitation 10/13/2011

Determination of Effects: Feasibility Analysis 11/2/2011 Kristina Thompson

10113 4 Wyoming 1029 770 Tunkhannock Creek Bridge Consulting Party Coordination 4/12/2012Public Involvement: Consulting Party Coordination Kevin Mock

12647 4 Wyoming EN2 College Ave. Streetscape Phase II Determination of Effects-Historic Structures and Archaeology 9/21/2011 BHP Enhancement: Field Concurrence 9/14/2011 Kevin Mock

12647 4 Wyoming EN2 College Ave. Streetscape Phase II Determination of Effects-Historic Structures and Archaeology 9/21/2011

Determination of Effects: Effect Determination 9/14/2011 Kevin Mock

65191 4 Wyoming 6 ENH Iroquois Trail Pedestrian BridgeNo Effect Finding for Transportation Enhancement Project 8/18/2011 BHP Enhancement: Field Concurrence 8/18/2011 Kristina Thompson

10352 5 Berks 3063 A01SR 3063 Tulpehocken Bridge Replacement Determination of Effects-Archaeology 8/18/2011

Determination of Effects: Archaeology Field Assessment and Finding Kevin Mock

10352 5 Berks 3063 A01SR 3063 Tulpehocken Bridge Replacement Adverse Effect Determination-Historic Structures 12/2/2011

Determination of Effects: Effect Determination - non-form 12/19/2011 Kristina Thompson

10352 5 Berks 3063 A01SR 3063 Tulpehocken Bridge Replacement Rehabilitation Feasibility Study 9/7/2011

Determination of Effects: Feasibility Analysis 9/21/2011 Kristina Thompson

10352 5 Berks 3063 A01SR 3063 Tulpehocken Bridge Replacement Determination of Effects-Archaeology 8/18/2011

Early Coordination: Geomorphological Testing Kevin Mock

10352 5 Berks 3063 A01SR 3063 Tulpehocken Bridge Replacement Letter of Agreement-Draft for Review 1/16/2012

Resolution of Adverse Effects: Letter of Agreement 2/17/2012 Kristina Thompson

10352 5 Berks 3063 A01SR 3063 Tulpehocken Bridge Replacement Letter of Agreement-Final 3/13/2012

Resolution of Adverse Effects: Letter of Agreement 3/20/2012 Kara Russell

10380 5 Berks 3061 TLPTulpehocken Creek Bridge Replacement Form Liner Mock-Up Panel Photographs 8/26/2011

Resolution of Adverse Effects: Consulting Party/Tribal Consultation Coordination 8/29/2011 Kristina Thompson

10466 5 Berks 78 12M I-78 Improvement Project Determination of Eligibility 2/23/2012Identification: Historic Resource Determination of Eligibility 3/15/2012 Kristina Thompson

10619 5 Berks 4008 01B Little Swatara Creek Brg No Effect Project Finding 7/7/2011Determination of Effects: Above-Ground Field Assessment and Finding Kristina Thompson

10619 5 Berks 4008 01B Little Swatara Creek Brg No Effect Project Finding 7/7/2011Determination of Effects: Archaeology Field Assessment and Finding Kristina Thompson

10624 5 Berks 100 01B Passmore Bridge Replacement SHPO Consultation 11/15/2011 Other: Project Scope Change 11/15/2011 Kevin Mock

10624 5 Berks 100 01B Passmore Bridge Replacement Tribal Consultation 11/16/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Kevin Mock

10624 5 Berks 100 01B Passmore Bridge Replacement SHPO Consultation 11/15/2011 Special Processes: Standard Treatment 11/15/2011 Kevin Mock

10703 5 Berks 4026 01B Mohrsville Bridge Replacement Determination of Effects-Archaeology 7/29/2011Determination of Effects: Archaeology Field Assessment and Finding 8/26/2011 Kevin Mock

10703 5 Berks 4026 01B Mohrsville Bridge Replacement Determination of Effects-Archaeology 7/29/2011Identification: Phase I/ II Archaeological Evaluation 8/26/2011 Kevin Mock

10712 5 Berks 7215 CRB Christman Road Bridge Determination of Effects-Archaeology 9/22/2011Determination of Effects: Archaeology Field Assessment and Finding Kevin Mock

10712 5 Berks 7215 CRB Christman Road Bridge Adverse Effect Determination-Historic Structures 11/18/2011Determination of Effects: Effect Determination - non-form 12/7/2011 Kristina Thompson

10712 5 Berks 7215 CRB Christman Road BridgeRehabilitation Feasibility Study and Consulting Party Meeting Invitation 9/13/2011

Determination of Effects: Feasibility Analysis 9/21/2011 Kristina Thompson

10712 5 Berks 7215 CRB Christman Road Bridge Letter of Agreement-Draft for Review 1/16/2012Resolution of Adverse Effects: Letter of Agreement 2/9/2012 Kristina Thompson

10712 5 Berks 7215 CRB Christman Road Bridge Letter of Agreement- Final 3/8/2012Resolution of Adverse Effects: Letter of Agreement 3/20/2012 Kara Russell

10712 5 Berks 7215 CRB Christman Road Bridge Determination of Effects-Archaeology 9/22/2011 Special Processes: Standard Treatment Kevin Mock

10713 5 Berks 7301 BUT Buttonwood Street BridgeInvitation to Consulting Party Meeting and Draft Effect Report 3/26/2012

Determination of Effects: Consulting Party/Tribal Consultation Coordination 4/9/2012 Kristina Thompson

10740 5 Berks 3422 03B Penn St Bridge Scoping Results Form/Early Notification 1/10/2012Scoping: Project Early Notification/ Scoping Results Kristina Thompson

10825 5 Berks 183 04B Schuylkill Ave Bridge_OSAInvitation to Consulting Party Meeting and Draft Effect Report 3/24/2012

Determination of Effects: Consulting Party/Tribal Consultation Coordination 4/9/2014 Kristina Thompson

10825 5 Berks 183 04B Schuylkill Ave Bridge_OSA Consulting Party Solicitation Letters 12/5/2011Public Involvement: Consulting Party Coordination Kristina Thompson

10826 5 Berks 1003 OTB Ontelaunee (Lake) Bridge Scoping Results Form/Early Notification 3/15/2012Scoping: Project Early Notification/ Scoping Results Kristina Thompson

47070 5 Berks 183 05SSR 0183/SR 0222 Intersection Reconstruction Phase III Data Recovery Report 1/11/2012

Mitigation: Phase III Archaeological Data Recovery 2/15/2012 Kevin Mock

47070 5 Berks 183 05SSR 0183/SR 0222 Intersection Reconstruction Tribal Coordination-Phase III Data Recovery 1/11/2012

Public Involvement: Tribal Consultation Coordination Kevin Mock

47070 5 Berks 183 05SSR 0183/SR 0222 Intersection Reconstruction PA Amendment to FHWA 5/16/2011 Resolution of Adverse Effects: MOA/PA 6/23/2011 Chris Kula

47070 5 Berks 183 05SSR 0183/SR 0222 Intersection Reconstruction Final Amended Programmatic Agreement 6/23/2011 Resolution of Adverse Effects: MOA/PA Kevin Mock

77027 5 Berks 222 22 222 North Corridor Phase I Eligibility Report 9/7/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Kristina Thompson

82021 5 Berks 562 02S 562_Shelbourne_Oley Int Scoping Results Form/Early Notification 9/2/2011Scoping: Project Early Notification/ Scoping Results Kristina Thompson

84648 5 Berks 61 GSE SR 61_Grand Street Ph II No Effect Project Finding 8/3/2011Determination of Effects: Above-Ground Field Assessment and Finding Kristina Thompson

84648 5 Berks 61 GSE SR 61_Grand Street Ph II No Effect Project Finding 8/3/2011Determination of Effects: Archaeology Field Assessment and Finding Kristina Thompson

84648 5 Berks 61 GSE SR 61_Grand Street Ph II Tribal Followup Notification 8/3/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Kevin Mock

86738 5 Berks 78 13M I-78 Krumsville Interchange Project Combined No Effect Finding 3/8/2012Determination of Effects: Above-Ground Field Assessment and Finding Kristina Thompson

86738 5 Berks 78 13M I-78 Krumsville Interchange Project Combined No Effect Finding 3/8/2012Determination of Effects: Archaeology Field Assessment and Finding Kristina Thompson

86738 5 Berks 78 13M I-78 Krumsville Interchange Project Scoping Results Form/Early Notification 2/8/2012Scoping: Project Early Notification/ Scoping Results Kristina Thompson

88792 5 Berks 61 16S SR 61 and Tuckerton Road Eligibility Determination 9/15/2011Identification: Historic Resource Determination of Eligibility 10/3/2011 Kristina Thompson

88792 5 Berks 61 16S SR 61 and Tuckerton Road Scoping Results Form/Early Notification 7/1/2011Scoping: Project Early Notification/ Scoping Results Kristina Thompson

90569 5 Berks 222SR 222 and Long Lane Improvements Scoping Results Form/Early Notification 3/16/2012

Scoping: Project Early Notification/ Scoping Results Kristina Thompson

92414 5 Berks 222 22S SR 222_73 & Genesis Dr Scoping Results Form/Early Notification 2/25/2012Scoping: Project Early Notification/ Scoping Results Kristina Thompson

92569 5 Berks Fleetwood_Main St WalkwayNo Adverse Effect Finding for Transportation Enhancement Project 9/13/2011 BHP Enhancement: Field Concurrence 9/13/2011 Kristina Thompson

92572 5 Berks WernersvilleTrain St Ph 3 Scoping Results Form/Early Notification 1/23/2012BHP Enhancement: Further Studies Needed Kristina Thompson

92574 5 Berks Birdsboro_Traffic CalmingNo Effect Finding for Transportation Enhancement Project 6/20/2011 BHP Enhancement: Field Concurrence 6/20/2011 Kristina Thompson

92576 5 Berks Lorane Elementary SRTS No Effect to Historic Properties Determination 6/13/2011 BHP Enhancement: Field Concurrence 6/13/2011 Kristina Thompson

92578 5 Berks Sinking Spring Penn Ave No Effect to Historic Properties Determination 6/13/2011 BHP Enhancement: Field Concurrence 6/13/2011 Kristina Thompson

11080 5 Carbon 209 10B McCall Bridge Rehab No Adverse Effect Combined Finding 9/1/2011Determination of Effects: Above-Ground Field Assessment and Finding Kristina Thompson

11080 5 Carbon 209 10B McCall Bridge Rehab No Adverse Effect Combined Finding 9/1/2011Determination of Effects: Archaeology Field Assessment and Finding Kristina Thompson

11080 5 Carbon 209 10B McCall Bridge RehabRevised Eligiblity Posting and Effect Determination 11/7/2011

Determination of Effects: Effect Determination - non-form 11/28/2011 Kristina Thompson

11080 5 Carbon 209 10B McCall Bridge Rehab Determination of No Adverse Effect-Revised 11/30/2011Determination of Effects: Effect Determination - non-form 12/15/2011 Kristina Thompson

11080 5 Carbon 209 10B McCall Bridge RehabRevised Eligiblity Posting and Effect Determination 11/7/2011

Identification: Historic Resource Determination of Eligibility 11/28/2011 Kristina Thompson

11129 5 Carbon 903 03B Jim Thorpe Bridge Replacement Letter of Agreement Draft Circulation for Review 5/9/2011Resolution of Adverse Effects: Letter of Agreement 5/23/2011 Kristina Thompson

11129 5 Carbon 903 03B Jim Thorpe Bridge Replacement Letter of Agreement execution 6/27/2011Resolution of Adverse Effects: Letter of Agreement Kara Russell

11129 5 Carbon 903 03B Jim Thorpe Bridge Replacement Final Letter of Agreement posting 7/29/2011Resolution of Adverse Effects: Letter of Agreement 7/29/2011 Kristina Thompson

77251 5 Carbon 0 0Pedestrian Bridge over Lehigh River at Jim Thorpe Scoping Results Form/Early Notification 1/3/2012

BHP Enhancement: Further Studies Needed Kristina Thompson

11498 5 Lehigh 2055 20 8th Street Bridge RehabConsulting Party Meeting Invitation and Draft Effect Report 5/3/2012

Determination of Effects: Consulting Party/Tribal Consultation Coordination Kristina Thompson

11228 5 Lehigh 4018 01B Slatedale Bridge Replacement No Effect to Above-Ground Historic Properties 5/20/2011Determination of Effects: Above-Ground Field Assessment and Finding Kristina Thompson

11384 5 Lehigh 7301 BRIUnion St Bridge Replacement over Cedar Creek New Bridge Design Consultation 3/10/2012

Determination of Effects: Consulting Party/Tribal Consultation Coordination 3/30/2012 Kristina Thompson

11384 5 Lehigh 7301 BRIUnion St Bridge Replacement over Cedar Creek New Bridge Design Consultation 3/10/2012

Public Involvement: Consulting Party Coordination 3/30/2012 Kristina Thompson

11432 5 Lehigh 3012 01B Schantz Road Bridge Phase III Archaeology_Supplemental 11/8/2011Mitigation: Phase III Archaeological Data Recovery 11/8/2011 Kevin Mock

11443 5 Lehigh 9900 PPKAmerican Parkway(Allentown Northeast Access Study)

No Adverse Effect Finding for Above-Ground Resources (revised scope) 3/17/2012

Determination of Effects: Above-Ground Field Assessment and Finding Kristina Thompson

11443 5 Lehigh 9900 PPKAmerican Parkway(Allentown Northeast Access Study) Initial Tribal Consultation 2/17/2012

Public Involvement: Consulting Party/Tribal Consultation Coordination Kevin Mock

11590 5 Lehigh 1027 01B Cold Springs Bridge Project Adverse Effect Determination-combined finding 12/12/2011Determination of Effects: Effect Determination - non-form 12/20/2011 Kristina Thompson

11590 5 Lehigh 1027 01B Cold Springs Bridge ProjectBridge Rehabilitation Feasibility Study and CP Meeting Invitation 10/12/2011

Determination of Effects: Feasibility Analysis 10/27/2011 Kristina Thompson

11590 5 Lehigh 1027 01B Cold Springs Bridge Project Letter of Agreement-Draft for Review 2/15/2012Resolution of Adverse Effects: Letter of Agreement 3/8/2012 Kristina Thompson

11610 5 Lehigh 309 07S Intersection Improvement ProjectConsultation Coordination-Replacement of Vegetation 9/20/2011

Mitigation: MOA/PA Commitment Coordination Kristina Thompson

11610 5 Lehigh 309 07S Intersection Improvement Project MOA Amendment 8/15/2011 Resolution of Adverse Effects: MOA/PA 8/25/2011 Kristina Thompson

51568 5 Lehigh 1014 0 Lehigh Street over the Lehigh River Tribal Consultation 12/16/2011Public Involvement: Tribal Consultation Coordination Kevin Mock

82992 5 Lehigh 4007 01B Schlicher's Covered Bridge RehabNo Adverse Effect Finding for Above-Ground Resources 9/26/2011

Determination of Effects: Above-Ground Field Assessment and Finding Kristina Thompson

82992 5 Lehigh 4007 01B Schlicher's Covered Bridge Rehab Determination of Effects-Archaeology 8/1/2011Determination of Effects: Archaeology Field Assessment and Finding 9/12/2011 Kevin Mock

86852 5 Lehigh 0 Old Allentown Streetscape Project No Effect Determination 5/9/2011 BHP Enhancement: Field Concurrence Kristina Thompson

91942 5 Lehigh 863 BRM LVTS Bridge Maint-Round 2 No Adverse Effect Combined Finding 11/7/2011Determination of Effects: Effect Determination - non-form Kristina Thompson

92340 5 Lehigh 7th St PedestrnLight-Ph 4No Effect Finding for Transportation Enhancement Project 8/1/2011 BHP Enhancement: Field Concurrence 8/1/2011 Kristina Thompson

92341 5 Lehigh Delaware Ave Ped AccessNo Effect Finding for Transportation Enhancement Project 10/30/2011 BHP Enhancement: Field Concurrence 10/30/2011 Kristina Thompson

79154 5 Monroe 2022 03BSR 2022 over Broadhead Ck Bridge Project Scoping Results Form/Early Notification 3/16/2012

Scoping: Project Early Notification/ Scoping Results Kristina Thompson

92776 5 Monroe 209 ENHEast Stroudsburg Pedestrian Experience, Phase II No Historic Properties Affected Finding 7/14/2011 BHP Enhancement: Field Concurrence 7/14/2011 Kristina Thompson

9050005 5 Northampton BMCSR 2003 Bridge Maintenance and Repairs No Adverse Effect Combined Finding 9/2/2011

Determination of Effects: Effect Determination - non-form 9/20/2011 Kristina Thompson

9050006 5 Northampton 611 0 Emergency SR 611 Repairs ProjectNo Adverse Effect Combined Finding-Emergency Review 10/3/2011

Determination of Effects: Above-Ground Field Assessment and Finding 10/21/2011 Kristina Thompson

t-11921 5 Northampton 611 01B Frys Run Bridge ReplacementDetermination of No Adverse Effect-Revised Scope of Work 3/20/2012

Determination of Effects: Effect Determination - non-form Kristina Thompson

t-11921 5 Northampton 611 01B Frys Run Bridge Replacement Scoping Results Form/Early Notification 2/8/2012Scoping: Project Early Notification/ Scoping Results Kristina Thompson

12665 5 Schuylkill 1002 01BPottsville St Bridge Replacement Project No Effect Project Finding 7/5/2011

Determination of Effects: Above-Ground Field Assessment and Finding Kristina Thompson

12665 5 Schuylkill 1002 01BPottsville St Bridge Replacement Project No Effect Project Finding 7/5/2011

Determination of Effects: Archaeology Field Assessment and Finding Kristina Thompson

12708 5 Schuylkill 209 07BBroad St. Bridge over Little Schuylkill R. Rehabil Combined No Adverse Effect Finding 1/23/2012

Determination of Effects: Effect Determination - non-form 2/27/2012 Kristina Thompson

12708 5 Schuylkill 209 07BBroad St. Bridge over Little Schuylkill R. Rehabil

Rehabilitation Alternatives and Consulting Party Invitation 8/1/2011

Public Involvement: Consulting Party Coordination Kristina Thompson

92364 5 SchuylkillCentral Business District Streetscape TE Project,

No Effect Finding for Transportation Enhancement Project 2/16/2012 BHP Enhancement: Field Concurrence 2/16/2012 Kristina Thompson

12931 6 Bucks BWRWorthington Mill Road over Neshaminy Creek Bridge Early Notification 3/22/2012

Early Coordination: Notification to the SHPO Catherine Spohn

13296 6 Bucks 7009 21 Rickert Road over Morris Run Rehabilitation Feasibilty Analysis 4/4/2012Determination of Effects: Feasibility Analysis Monica Harrower

13296 6 Bucks 7009 21 Rickert Road over Morris Run Invitation Letters to Potential Consulting Parties 2/9/2012Identification: Consulting Party/Tribal Consultation Coordination 2/9/2012 Monica Harrower

13296 6 Bucks 7009 21 Rickert Road over Morris Run Invitation Letters to Potential Consulting Parties 2/9/2012Identification: Consulting Party/Tribal Consultation Coordination 2/9/2012 Monica Harrower

13296 6 Bucks 7009 21 Rickert Road over Morris RunSection 106 Consulting Party Response Forms Received 3/20/2012

Identification: Consulting Party/Tribal Consultation Coordination 3/20/2012 Monica Harrower

13296 6 Bucks 7009 21 Rickert Road over Morris RunSection 106 Consulting Party Response Forms Received 3/20/2012

Identification: Consulting Party/Tribal Consultation Coordination 3/20/2012 Monica Harrower

13440 6 Bucks 663 VY2 PA 663 and Allentown RoadLetter Report on Pink Lady Site (archaeology finding) 10/4/2011 Other: Project Scope Change Catherine Spohn

13440 6 Bucks 663 VY2 PA 663 and Allentown Road Additional Work--Channel Easement 10/18/2011 Other: Project Scope Change Monica Harrower13440 6 Bucks 663 VY2 PA 663 and Allentown Road Additional Work - Channel Easement 12/20/2011 Other: Project Scope Change Catherine Spohn

13440 6 Bucks 663 VY2 PA 663 and Allentown Road Additional Work - Channel Easement Archaeology 12/20/2011 Other: Project Scope Change Catherine Spohn

13549 6 Bucks 1 03SRoute 1 Widening and Reconstruction Project

Project Scope Change Description, USGS Map and Plan 7/18/2011 Other: Project Scope Change Catherine Spohn

13573 6 Bucks 95 SFB Scudders Falls Bridge ImprovementsAddendum Report II to Phase I Archaeology Report 3/7/2012

Identification: Phase I Archaeological Survey Catherine Spohn

47392 6 Bucks 13 M04Bristol Pike: SR 413 to Levittown Parkway Wetland Mitigation Site Above-Ground Finding 12/13/2011

Determination of Effects: Effect Determination 12/13/2011 Monica Harrower

47392 6 Bucks 13 M04Bristol Pike: SR 413 to Levittown Parkway

Stormwater Management Basins Archaeology Finding 12/30/2011

Determination of Effects: Effect Determination Catherine Spohn

47392 6 Bucks 13 M04Bristol Pike: SR 413 to Levittown Parkway Stormwater Management (above-ground finding) 12/21/2011

Determination of Effects: Effect Determination - non-form 12/28/2011 Monica Harrower

47392 6 Bucks 13 M04Bristol Pike: SR 413 to Levittown Parkway Wetland Mitigation Site Above-Ground Finding 12/13/2011 Other: Project Scope Change 12/13/2011 Monica Harrower

47392 6 Bucks 13 M04Bristol Pike: SR 413 to Levittown Parkway Stormwater Management (above-ground finding) 12/21/2011 Other: Project Scope Change 12/28/2011 Monica Harrower

47392 6 Bucks 13 M04Bristol Pike: SR 413 to Levittown Parkway

Stormwater Management Basins Archaeology Finding 12/30/2011 Other: Project Scope Change Catherine Spohn

65922 6 Bucks 13 BT1 East Coast Greenway/US Route 13Additional Work--Pipe Replacement (Above-ground finding) 1/5/2012

Determination of Effects: Effect Determination 1/5/2012 Monica Harrower

65922 6 Bucks 13 BT1 East Coast Greenway/US Route 13Additional Work - Pipe Replacement (Archaeology Finding) 1/19/2012

Determination of Effects: Effect Determination Catherine Spohn

65922 6 Bucks 13 BT1 East Coast Greenway/US Route 13Additional Work - Pipe Replacement (Archaeology Finding) 1/19/2012 Other: Project Scope Change Catherine Spohn

92184 6 Bucks 13 HBJ Adj Box Beam Group (J)Horseshoe Pike over West Branch of Brandywine Creek Above-Ground Finding 10/4/2011

Determination of Effects: Above-Ground Field Assessment and Finding 10/24/2011 Monica Harrower

92184 6 Bucks 13 HBJ Adj Box Beam Group (J)Horseshoe Pike over West Branch Brandywine Creek Archaeology Finding 10/28/2011

Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

92184 6 Bucks 13 HBJ Adj Box Beam Group (J)Horseshoe Pike over West Branch of Brandywine Creek Above-Ground Finding 10/4/2011

Identification: Historic Resource Determination of Eligibility 10/24/2011 Monica Harrower

92404 6 Bucks 4051 0 Trumbauersville Gtwy PCTITransportation Enhancement Project Field Assessment & Finding 10/7/2011

BHP Enhancement: Further Studies Needed 10/11/2011 Cheryl Nagle

93439 6 Bucks Center Street over Newtown Creek Above-Ground Finding 11/16/2011Determination of Effects: Above-Ground Field Assessment and Finding 11/29/2011 Monica Harrower

93439 6 BucksBristol Road over Branch of Mill Creek Above-Ground Finding 11/30/2011

Determination of Effects: Above-Ground Field Assessment and Finding 12/20/2011 Monica Harrower

93439 6 Bucks Center Street over Newtown Creek Archaeology Field Assessment and Finding 11/23/2011Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

93439 6 BucksBristol Road over Branch of Mill Creek Archaeology Field Assessment and Finding Form 1/24/2012

Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

93439 6 Bucks Center Street over Newtown Creek Meeting Notice 2/2/2012 Other: Other Monica Harrower

94343 6 BucksBurnt House Hill Road over Watson Creek Burnt House Hill Road Above-Ground Finding 10/14/2011

Determination of Effects: Above-Ground Field Assessment and Finding 10/21/2011 Monica Harrower

94343 6 BucksBurnt House Hill Road over Watson Creek Archaeology Field Assessment and Finding 10/14/2011

Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

94343 6 BucksBurnt House Hill Road over Watson Creek Burnt House Hill Road Above-Ground Finding 10/14/2011

Identification: Historic Resource Determination of Eligibility 10/21/2011 Monica Harrower

13945 6 Chester 202 300US 202 from TR 252 to US 30 Improvements

Park and Ride Signing Plan (above-ground finding) 8/26/2011

Determination of Effects: Effect Determination 9/20/2011 Monica Harrower

13945 6 Chester 202 300US 202 from TR 252 to US 30 Improvements Additional Work--Sound Barriers 11/28/2011

Determination of Effects: Effect Determination 11/29/2011 Monica Harrower

13945 6 Chester 202 300US 202 from TR 252 to US 30 Improvements

Additional Work - SR 0202 culvert over Chester Valley Trail Lighting 12/16/2011

Determination of Effects: Effect Determination Catherine Spohn

13945 6 Chester 202 300US 202 from TR 252 to US 30 Improvements Pennsylvania Railroad Golf Club PHRS Form 10/12/2011

Identification: Historic Resource Determination of Eligibility 10/21/2011 Monica Harrower

13945 6 Chester 202 300US 202 from TR 252 to US 30 Improvements Negative Survey Form, Basin D-1 7/26/2011

Identification: Phase I Archaeological Survey 8/2/2011 Catherine Spohn

13945 6 Chester 202 300US 202 from TR 252 to US 30 Improvements

Cultural Resources Letter Report on Proposed Stormwater Basin D-7B 8/5/2011 Other: Project Scope Change Catherine Spohn

14251 6 Chester 7015 236Chandler Mill Road over W. Branch Red Clay Creek Section 106 Consulting Party Invitations 5/9/2011

Public Involvement: Consulting Party Coordination Monica Harrower

14251 6 Chester 7015 236Chandler Mill Road over W. Branch Red Clay Creek Sec. 106 Consulting Party Invitation; M.S. Boyle 5/18/2011

Public Involvement: Consulting Party Coordination Monica Harrower

14251 6 Chester 7015 236Chandler Mill Road over W. Branch Red Clay Creek

Sec. 106 Consulting Party Invitation; M. & R. St. Clair 5/20/2011

Public Involvement: Consulting Party Coordination Monica Harrower

14251 6 Chester 7015 236Chandler Mill Road over W. Branch Red Clay Creek Section 106 Consulting Party Response Forms 6/24/2011

Public Involvement: Consulting Party Coordination Monica Harrower

14261 6 Chester 7015 282 Church Road over Valley Creek Above Ground Finding 9/12/2011Determination of Effects: Above-Ground Field Assessment and Finding 9/21/2011 Monica Harrower

16738 6 Chester 422 M01Route 422 Transportation Improvement Project

Letter Report & Geomorphological Assessment of Flagg Property 6/21/2011

Early Coordination: Geomorphological Testing Catherine Spohn

16738 6 Chester 422 M01Route 422 Transportation Improvement Project

Notification to Absentee-Shawnee Tribe of Oklahoma 6/21/2011

Identification: Consulting Party/Tribal Consultation Coordination Catherine Spohn

16738 6 Chester 422 M01Route 422 Transportation Improvement Project PHRS Form - Stanley Flagg Property 8/5/2011

Identification: Historic Resource Determination of Eligibility 8/15/2011 Catherine Spohn

57659 6 Chester 0 FCP French Creek ParkwayPhila & Reading RR: Pickering Valley Branch Additional Info. 5/16/2011

Identification: Historic Resource Determination of Eligibility 5/20/2011 Monica Harrower

57659 6 Chester 0 FCP French Creek Parkway Phoenixville Historic District Boundary Decrease 9/22/2011Identification: Historic Resource Determination of Eligibility 10/11/2011 Monica Harrower

57659 6 Chester 0 FCP French Creek Parkway Open House Plans Display Notice 7/8/2011Public Involvement: Early Coordination/Advance Notification 7/8/2011 Monica Harrower

57683 6 Chester 7401 GAPOld Gap-Newport Pike Bridge over Valley Creek Mitigation--Stave Level Recordation 5/27/2011

Mitigation: MOA/PA Commitment Coordination 5/31/2011 Monica Harrower

64220 6 Chester 422 M03Route 422, Sec. M03 Improvement Project

Kenilworth Historic District Boundary Clarification 5/16/2011

Identification: Historic Resource Determination of Eligibility 5/16/2011 Monica Harrower

69665 6 Chester 3101 DRBCreek Road Bridge over Brandywine Creek

PHRS Form Bissell/Hill/Girt/Beverly HD Addional Info. 8/11/2011

Identification: Historic Resource Determination of Eligibility 8/15/2011 Monica Harrower

80101 6 Chester 52 JWJ SR 0052 RoundaboutAmos Harry/Eusebius Barnard House Additional Information 12/7/2011

Identification: Historic Resource Determination of Eligibility 12/16/2011 12/16/2011 Monica Harrower

80101 6 Chester 52 JWJ SR 0052 Roundabout Addendum to Phase I Archaeological Survey 4/17/2012Identification: Phase I Archaeological Survey Catherine Spohn

93440 6 Chester noneRoss Fording Road over Octoraro Creek Above-ground Finding 10/21/2011

Determination of Effects: Above-Ground Field Assessment and Finding 11/7/2011 Monica Harrower

93440 6 Chester noneRoss Fording Road over Octoraro Creek Archaeology Field Assessment and Finding 10/27/2011

Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

14747 6 Delaware 322 100US Route 322 Transportation Improvement Phase I Archaeology Survey Addendum Report 1 8/5/2011

Identification: Phase I Archaeological Survey 8/11/2011 Catherine Spohn

14891 6 Delaware 1015 RADDarby Paoli Road over Little Darby Creek & Wigwam Sec. 106 Consulting Party Invitation Letters 4/18/2012

Identification: Consulting Party/Tribal Consultation Coordination 4/18/2012 Monica Harrower

14891 6 Delaware 1015 RADDarby Paoli Road over Little Darby Creek & Wigwam Sec. 106 Consulting Party Solicitation 4/18/2012

Identification: Consulting Party/Tribal Consultation Coordination Monica Harrower

14891 6 Delaware 1015 RADDarby Paoli Road over Little Darby Creek & Wigwam Darby-Paoli Road over Wigwam Creek PHRS Form 9/28/2011

Identification: Historic Resource Determination of Eligibility 10/11/2011 Monica Harrower

14891 6 Delaware 1015 RADDarby Paoli Road over Little Darby Creek & Wigwam Rose Garland/Willows Property PHRS Form 3/8/2012

Identification: Historic Resource Determination of Eligibility 3/20/2012 Monica Harrower

14891 6 Delaware 1015 RADDarby Paoli Road over Little Darby Creek & Wigwam Ardrossan PHRS Form 3/8/2012

Identification: Historic Resource Determination of Eligibility 3/20/2012 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Ballious House and Bonaventure House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Bonsall Barn and Catherine Watson House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Desiderio House and Duffy House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Eastwick-Haugh House and Edwards House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Greene House and Habbersett House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Herrick House and Hess House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Hinkson-Warfel House and Hooper House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Joanna Greene House and Kaneda House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Kelchner House and Kruzel House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 InterchangeLima Methodist Episcopal Church and Lockee-Stone House 9/14/2011

Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange M. Grey House and Marinelli House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 InterchangeMassey House and 45 South New Middletown Road House 9/14/2011

Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange47 South New Middletown Road House and Miluski House 9/14/2011

Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Murphy House and Passmore-Clower House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Phillips House and Russel House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 InterchangeSalvadore House & 107 E. Old Baltimore Pike & 69 E. Old Baltimore Pike 9/14/2011

Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Tremblay-Victoria House 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Wolff Barn 9/14/2011Identification: Historic Resource Determination of Eligibility 9/22/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Smedley Property PHRS Form 10/17/2011Identification: Historic Resource Determination of Eligibility 11/7/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 Interchange Black Horse Acres PHRS Form 10/17/2011Identification: Historic Resource Determination of Eligibility 11/7/2011 11/7/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 InterchangePennsylvania Training School for Feeble Minded Children PHRS Form 10/17/2011

Identification: Historic Resource Determination of Eligibility 11/7/2011 Monica Harrower

15251 6 Delaware 352 US1 US 1/352 InterchangeWilliamson Free School of Mechanical Trades PHRS Form 10/17/2011

Identification: Historic Resource Determination of Eligibility 11/7/2011 Monica Harrower

15306 6 Delaware 2031 DBR Sellers Avenue Bridge over AmtrakSection 106 Consulting Party Meeting Agenda and Minutes 4/18/2012

Public Involvement: Consulting Party Coordination 4/18/2012 Monica Harrower

15306 6 Delaware 2031 DBR Sellers Avenue Bridge over Amtrak Sec. 106 Consulting Parties Response Forms 8/11/2011Public Involvement: Consulting Party Coordination Monica Harrower

15306 6 Delaware 2031 DBR Sellers Avenue Bridge over Amtrak Sec. 106 Consulting Parties Invitation List 8/11/2011Public Involvement: Consulting Party Coordination 8/11/2011 Monica Harrower

15306 6 Delaware 2031 DBR Sellers Avenue Bridge over AmtrakSection 106 Consulting Parties Meeting Invitation Letters 3/5/2012

Public Involvement: Consulting Party Coordination 3/5/2012 Monica Harrower

15477 6 Delaware 95 322I-95/US 322 Interchange Improvement Project Archaeological Memorandum 6/6/2011

Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

15477 6 Delaware 95 322I-95/US 322 Interchange Improvement Project

Updated Highland Gardens Historic District Boundary 5/24/2011

Identification: Historic Resource Determination of Eligibility 6/3/2011 Monica Harrower

15477 6 Delaware 95 322I-95/US 322 Interchange Improvement Project

Phase I Archaeological Management Summary Report & Cover Letter 10/12/2011

Identification: Phase I Archaeological Survey Catherine Spohn

15477 6 Delaware 95 322I-95/US 322 Interchange Improvement Project

Sec. 106 Consulting Parties Meeting Minutes April 28, 2011 6/22/2011

Public Involvement: Consulting Party Coordination Monica Harrower

69665 6 Delaware 3101 DRBCreek Road Bridge over Brandywine Creek

PHRS Form Bissell/Hill/Girt/Beverly HD Addional Info. 8/11/2011

Identification: Historic Resource Determination of Eligibility 8/15/2011 Monica Harrower

75800 6 Delaware 1026 CAS College Avenue over SEPTA Project Description and USGS Map 2/23/2012Early Coordination: Notification to the SHPO 2/23/2012 Monica Harrower

75800 6 Delaware 1026 CAS College Avenue over SEPTA Mahan Property PHRS Form 2/23/2012Identification: Historic Resource Determination of Eligibility 3/15/2012 Monica Harrower

75800 6 Delaware 1026 CAS College Avenue over SEPTA Millbrook Farms PHRS Form 2/23/2012Identification: Historic Resource Determination of Eligibility 3/15/2012 Monica Harrower

75800 6 Delaware 1026 CAS College Avenue over SEPTA Haverford College PHRS Form 4/13/2012Identification: Historic Resource Determination of Eligibility 5/10/2012 Monica Harrower

75800 6 Delaware 1026 CAS College Avenue over SEPTA College Avenue Culvert over Cobbs Creek 4/20/2012Identification: Historic Resource Determination of Eligibility 5/10/2012 Monica Harrower

75800 6 Delaware 1026 CAS College Avenue over SEPTA Negative Survey Form 8/15/2011Identification: Phase I Archaeological Survey Catherine Spohn

87109 6 Delaware BOS Swarthmore Boro SRSSwarthmore Borough SRS (Princeton Avenue Ped Tunnel) 1/24/2012 BHP Enhancement: Field Concurrence 1/24/2012 Cheryl Nagle

87109 6 Delaware BOS Swarthmore Boro SRSSwarthmore Borough SRS (Princeton Avenue Ped Tunnel) 1/24/2012

Determination of Effects: Effect Determination 1/24/2012 Cheryl Nagle

87109 6 Delaware BOS Swarthmore Boro SRS Project Description & USGS Map 1/23/2012Early Coordination: Advance Notification to SHPO 1/23/2012 Monica Harrower

87120 6 Delaware UDT Upper Darby Twp SRS TE Project Finding--More Information Needed 7/13/2011BHP Enhancement: Further Studies Needed 7/13/2011 Cheryl Nagle

87120 6 Delaware UDT Upper Darby Twp SRS Updated Project Description and USGS Map 8/12/2011Early Coordination: Area of Potential Effect Catherine Spohn

87120 6 Delaware UDT Upper Darby Twp SRS Pilgrim Gardens Historic District DOE 12/14/2011Identification: Historic Resource Determination of Eligibility Cheryl Nagle

87120 6 Delaware UDT Upper Darby Twp SRS Updated Project Description and USGS Map 8/12/2011 Other: Project Scope Change Catherine Spohn

93441 6 Delaware St. Davids Road over Darby Creek Above Ground Finding 11/2/2011Determination of Effects: Above-Ground Field Assessment and Finding 11/29/2011 Monica Harrower

93441 6 Delaware St. Davids Road over Darby Creek Archaeology Field Assessment and Finding 11/3/2011Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

93441 6 Delaware St. Davids Road over Darby Creek Meeting Announcement 1/25/2012Public Involvement: Consulting Party Coordination 1/25/2012 Monica Harrower

15992 6 Montgomery BRG Rockland Ave Bridge Above-Ground Finding 10/4/2011Determination of Effects: Above-Ground Field Assessment and Finding 10/24/2011 Monica Harrower

15992 6 Montgomery BRG Rockland Ave Bridge Archaeology Field Assessment and Finding 10/24/2011Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

16599 6 Montgomery 320 M07 PA Route 320 Improvements Letter to FHWA to Terminate MOA 2/7/2012 Other: Project Scope Change Catherine Spohn

16658 6 Montgomery 1006 MFB Old Forty Foot/Skippack Initial Tribal Notification Forms 12/7/2011Public Involvement: Tribal Consultation Coordination Catherine Spohn

16665 6 Montgomery 202 500 Markley Street Improvement ProjectAdditional Work--Main Street Bridge over Stony Creek 6/13/2011

Determination of Effects: Effect Determination 6/13/2011 Monica Harrower

16665 6 Montgomery 202 500 Markley Street Improvement Project ITS Devices (Above-ground properties) 9/6/2011Determination of Effects: Effect Determination 9/21/2011 Monica Harrower

16665 6 Montgomery 202 500 Markley Street Improvement Project ITS Devices 9/7/2011Determination of Effects: Effect Determination Catherine Spohn

16665 6 Montgomery 202 500 Markley Street Improvement Project Main Street Widening (Additional work) 9/27/2011Determination of Effects: Effect Determination 10/3/2011 Monica Harrower

16665 6 Montgomery 202 500 Markley Street Improvement Project Main St. Additional Work - Archaeology Finding 10/5/2011Determination of Effects: Effect Determination Catherine Spohn

16665 6 Montgomery 202 500 Markley Street Improvement ProjectAdditional Work--Main Street Bridge over Stony Creek 6/13/2011 Other: Project Scope Change 6/13/2011 Monica Harrower

16665 6 Montgomery 202 500 Markley Street Improvement Project ITS Devices 9/7/2011 Other: Project Scope Change Catherine Spohn

16665 6 Montgomery 202 500 Markley Street Improvement Project Main St. Additional Work - Archaeology Finding 10/5/2011 Other: Project Scope Change Catherine Spohn

16703 6 Montgomery 3051 C22 Old Betzwood Ped Trail Above-ground Finding 11/29/2011Determination of Effects: Above-Ground Field Assessment and Finding 12/13/2011 Monica Harrower

16703 6 Montgomery 3051 C22 Old Betzwood Ped Trail Archaeology Field Assessment and Finding 12/1/2011Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

16703 6 Montgomery 3051 C22 Old Betzwood Ped Trail Reading Railroad Main Line PHRS Form 9/22/2011Identification: Historic Resource Determination of Eligibility 10/11/2011 Monica Harrower

16726 6 MontgomeryWarminster Road over Pennypack Creek Project Description and USGS Map 12/7/2011

Early Coordination: Notification to the SHPO 12/7/2011 Monica Harrower

16726 6 MontgomeryWarminster Road over Pennypack Creek Walton/Fulmore House PHRS Form 12/7/2011

Identification: Historic Resource Determination of Eligibility 12/16/2011 Monica Harrower

16726 6 MontgomeryWarminster Road over Pennypack Creek

Walton/Fulmore House Additional Info. (Interior Photos) 1/19/2012

Identification: Historic Resource Determination of Eligibility 2/9/2012 Monica Harrower

16738 6 Montgomery 422 M01Route 422 Transportation Improvement Project

Letter Report & Geomorphological Assessment of Flagg Property 6/21/2011

Early Coordination: Geomorphological Testing Catherine Spohn

50646 6 Montgomery 63 MG1Sumneytown Pike over Unami & E. Branch Perkiomen Archaeology Field Assessment and Finding 3/30/2012

Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

50646 6 Montgomery 63 MG1Sumneytown Pike over Unami & E. Branch Perkiomen Updated Project Description and USGS Map 8/11/2011

Early Coordination: Area of Potential Effect 8/11/2011 Monica Harrower

50646 6 Montgomery 63 MG1Sumneytown Pike over Unami & E. Branch Perkiomen Bridge over Ridge Valley Creek PHRS Form 11/1/2011

Identification: Historic Resource Determination of Eligibility 11/21/2011 Monica Harrower

50646 6 Montgomery 63 MG1Sumneytown Pike over Unami & E. Branch Perkiomen

Spring House & Sumneytown Turnpike PHRS Form 11/8/2011

Identification: Historic Resource Determination of Eligibility 12/6/2011 Monica Harrower

50646 6 Montgomery 63 MG1Sumneytown Pike over Unami & E. Branch Perkiomen

Spring House & Sumneytown Turnpike Additional Information 3/28/2012

Identification: Historic Resource Determination of Eligibility 4/17/2012 Monica Harrower

50646 6 Montgomery 63 MG1Sumneytown Pike over Unami & E. Branch Perkiomen Archaeology Field Assessment and Finding 3/30/2012

Identification: Phase I Archaeological Survey Catherine Spohn

50646 6 Montgomery 63 MG1Sumneytown Pike over Unami & E. Branch Perkiomen Updated Project Description and USGS Map 8/11/2011 Other: Project Scope Change 8/11/2011 Monica Harrower

57864 6 Montgomery 1012 BCGCowpath Road/Godshall Road/Broad St. Intersection

Cover letter with updated project description, map, letter reports 8/17/2011

Determination of Effects: Effect Determination - non-form Catherine Spohn

57864 6 Montgomery 1012 BCGCowpath Road/Godshall Road/Broad St. Intersection

Cover letter with updated project description, map, letter reports 8/17/2011 Other: Project Scope Change Catherine Spohn

64798 6 Montgomery 7412 NNA N Narberth Ave O/AMTRAK Project Description and USGS Location Map 6/1/2011Early Coordination: Area of Potential Effect Monica Harrower

64798 6 Montgomery 7412 NNA N Narberth Ave O/AMTRAK Narberth Commercial Area PHRS Form 7/21/2011Identification: Historic Resource Determination of Eligibility 8/5/2011 Monica Harrower

64798 6 Montgomery 7412 NNA N Narberth Ave O/AMTRAKNarberth Southside Residential Historic District PHRS Form 7/21/2011

Identification: Historic Resource Determination of Eligibility 8/5/2011 8/5/1011 Monica Harrower

80052 6 Montgomery 7046 27Fetters Mill Road Bridge over Pennypack Creek Feasibility Analysis 11/9/2011

Determination of Effects: Feasibility Analysis 12/6/2011 Monica Harrower

80052 6 Montgomery 7046 27Fetters Mill Road Bridge over Pennypack Creek

Fetters Mill Bridge Consulting Parties Meeting Invitation Letters 2/28/2012

Public Involvement: Consulting Party Coordination 2/28/2012 Monica Harrower

80052 6 Montgomery 7046 27Fetters Mill Road Bridge over Pennypack Creek Additional Consulting Parties Response Forms 3/5/2012

Public Involvement: Consulting Party Coordination 3/5/2012 Monica Harrower

17821 6 Philadelphia 95 GIRI-95 Improvement Project Shackamaxon Street to Ann

ITS Deployment for Construction Section I-95, Sec. GR2 (Above-ground finding) 12/12/2011

Determination of Effects: Effect Determination 12/20/2011 Monica Harrower

17821 6 Philadelphia 95 GIRI-95 Improvement Project Shackamaxon Street to Ann

Phase IB/II Management Summary and Data Recovery Plan for Dyottville Site 9/30/2011

Identification: Phase I/II Archaeological Survey 10/7/2011 Catherine Spohn

17821 6 Philadelphia 95 GIRI-95 Improvement Project Shackamaxon Street to Ann Aramingo Canal Data Recovery Report 4/5/2012

Mitigation: Phase III Archaeological Data Recovery Catherine Spohn

17821 6 Philadelphia 95 GIRI-95 Improvement Project Shackamaxon Street to Ann Additional Utility Relocation Information 6/8/2011 Other: Project Scope Change Catherine Spohn

17821 6 Philadelphia 95 GIRI-95 Improvement Project Shackamaxon Street to Ann

ITS Deployment for Construction Section I-95, Sec. GR2 (Above-ground finding) 12/12/2011 Other: Project Scope Change 12/20/2011 Monica Harrower

17821 6 Philadelphia 95 GIRI-95 Improvement Project Shackamaxon Street to Ann

ITS Deployment for Construction Section I-95, Sec. GR2 (Archaeology) 12/19/2011 Other: Project Scope Change Catherine Spohn

17821 6 Philadelphia 95 GIRI-95 Improvement Project Shackamaxon Street to Ann Letter to Consulting Parties 6/7/2011

Public Involvement: Consulting Party Coordination Catherine Spohn

17821 6 Philadelphia 95 GIRI-95 Improvement Project Shackamaxon Street to Ann Project Information Forms, Dyottville Site 10/7/2011

Public Involvement: Tribal Consultation Coordination Catherine Spohn

17821 6 Philadelphia 95 GIRI-95 Improvement Project Shackamaxon Street to Ann Tribal Project Information Form, Dyottville Site 10/7/2011

Public Involvement: Tribal Consultation Coordination Catherine Spohn

17821 6 Philadelphia 95 GIRI-95 Improvement Project Shackamaxon Street to Ann

Phase IB/II Management Summary and Data Recovery Plan for Dyottville Site 9/30/2011

Resolution of Adverse Effects: Archaeological Data Recovery Workplan 10/7/2011 Catherine Spohn

47394 6 Philadelphia 95 CPR I-95: Levick Street to Bleigh Ave.Archaeological Letter Report of Wissinoming St. Phase IB Testing 5/13/2011

Identification: Phase I Archaeological Survey Catherine Spohn

61712 6 Philadelphia SC2 Kensington & Tacony Trail TE Project Field Assessment & Finding--Updated 6/15/2011 BHP Enhancement: Field Concurrence 8/12/2011 Cheryl Nagle61712 6 Philadelphia SC2 Kensington & Tacony Trail Revised Project Description & USGS Map 8/10/2011 Other: Project Scope Change Catherine Spohn

61712 6 Philadelphia SC2 Kensington & Tacony Trail TE Project Field Assessment & Finding--Updated 6/15/2011 Other: Project Scope Change 8/12/2011 Cheryl Nagle

69828 6 Philadelphia 3010 MSB Market Street Bridge Above-Ground Field Assessment and Finding 4/13/2012Determination of Effects: Above-Ground Field Assessment and Finding Monica Harrower

69828 6 Philadelphia 3010 MSB Market Street Bridge Archaeology Field Assessment and Finding 4/24/2012Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

69909 6 Philadelphia 1011 PWB Willits Road Bridge Archaeology Field Assessment and Finding 3/6/2012Determination of Effects: Archaeology Field Assessment and Finding Catherine Spohn

69909 6 Philadelphia 1011 PWB Willits Road Bridge Project Description and USGS Map 2/21/2012Early Coordination: Notification to the SHPO 2/21/2012 Monica Harrower

69909 6 Philadelphia 1011 PWB Willits Road Bridge Pennypack Park PHRS Form 2/23/2012Identification: Historic Resource Determination of Eligibility 3/16/2012 Monica Harrower

73135 6 Philadelphia 4007 GERGermantown Avenue Streetscape Improvement Project Revised Project Description and USGS map 1/24/2012 Other: Project Scope Change 1/24/2012 Monica Harrower

78764 6 Philadelphia 30 PGC Girard Avenue over CSX Project Description & USGS Map 3/30/2012Early Coordination: Notification to the SHPO 3/30/2012 Monica Harrower

78764 6 Philadelphia 30 PGC Girard Avenue over CSX Junction Railroad/Belmont Branch of CSX PHRS Form 3/30/2012

Identification: Historic Resource Determination of Eligibility 4/20/2012 Monica Harrower

78764 6 Philadelphia 30 PGC Girard Avenue over CSX Girard Avenue Passenger Railway/Route 15 Trolley Line PHRS Form 3/30/2012

Identification: Historic Resource Determination of Eligibility 4/20/2012 Monica Harrower

81584 6 PhiladelphiaSchuylkill Park Pedestrian Bridge over CSX Interpretive Signs 2/13/2012

Mitigation: MOA/PA Commitment Coordination Catherine Spohn

87937 6 Philadelphia 611 AA1 Ave of the Arts N. BroadTransportation Enhancement Project Field Assessment & Finding 2/13/2012 BHP Enhancement: Field Concurrence 2/13/2012 Monica Harrower

87937 6 Philadelphia 611 AA1 Ave of the Arts N. BroadTransportation Enhancement Project Field Assessment & Finding 2/13/2012

Determination of Effects: Above-Ground Field Assessment and Finding 2/13/2012 Monica Harrower

87937 6 Philadelphia 611 AA1 Ave of the Arts N. BroadTransportation Enhancement Project Field Assessment & Finding 2/13/2012

Determination of Effects: Effect Determination 2/13/2012 Monica Harrower

87937 6 Philadelphia 611 AA1 Ave of the Arts N. BroadProject Description, USGS Map, Lighting Plan and Mock-Up Photo 2/1/2012

Early Coordination: Area of Potential Effect 2/1/2012 Monica Harrower

92376 6 Philadelphia 4013 WLB Walnut Lane o/Wissahickon Project Description & USGS Map 3/28/2012Early Coordination: Notification to the SHPO 3/28/2012 Monica Harrower

92413 6 Philadelphia Manayunk Ped Trail PCTI Manayunk Bridge Ivy Ridge Trail TE Finding 4/26/2012 BHP Enhancement: Field Concurrence 5/1/2012 Cheryl Nagle

92413 6 Philadelphia Manayunk Ped Trail PCTI Project Description & USGS Map 7/19/2011Early Coordination: Area of Potential Effect Monica Harrower

92413 6 Philadelphia Manayunk Ped Trail PCTI

Manayunk Bridge over Schuylkill River, Schuylkill Expressway, Green Lane and Main Street PHRS Form 9/28/2011

Identification: Historic Resource Determination of Eligibility 10/20/2011 Monica Harrower

92417 6 Philadelphia Race St Connector PCTI TE Field Assessment and Finding 11/4/2011 BHP Enhancement: Field Concurrence 11/4/2011 Cheryl Nagle

92417 6 Philadelphia Race St Connector PCTI TE Field Assessment and Finding 11/4/2011BHP Enhancement: Further Studies Needed 11/4/2011 Cheryl Nagle

17938 8 Adams 3008 1Cunningham Road Bridge Rehab/Replacement Amendment to MOA 7/1/2011 Resolution of Adverse Effects: MOA/PA 7/19/2011 Kara Russell

18145 8 Adams 3001 36 Old Harrisburg Rd. Br. 1 Negative Survey Form 1/3/2012Determination of Effects: Above-Ground Field Assessment and Finding Rebecca Knapp

18145 8 Adams 3001 36 Old Harrisburg Rd. Br. 1 Negative Survey Form 1/3/2012Determination of Effects: Archaeology Field Assessment and Finding Rebecca Knapp

18145 8 Adams 3001 36 Old Harrisburg Rd. Br. 1 Negative Survey Form 1/3/2012Identification: Phase I Archaeological Survey Rebecca Knapp

58603 8 Adams 3001 34 Old Hbg. Road Bridge 2 Negative Survey Form 1/3/2012Identification: Phase I Archaeological Survey 1/3/2012 Rebecca Knapp

68733 8 Adams 3001 37 Old Harrisburg Rd. Br. 2 Dual Finding Form 1/3/2012Determination of Effects: Above-Ground Field Assessment and Finding Jeremy Ammerman

68733 8 Adams 3001 37 Old Harrisburg Rd. Br. 2 Dual Finding Form 1/3/2012Determination of Effects: Archaeology Field Assessment and Finding Jeremy Ammerman

82983 8 Adams 30 70 East King Street Bridge Combined Field Assessment and Finding 4/3/2012Determination of Effects: Above-Ground Field Assessment and Finding Rebecca Knapp

82983 8 Adams 30 70 East King Street Bridge Combined Field Assessment and Finding 4/3/2012Determination of Effects: Archaeology Field Assessment and Finding Rebecca Knapp

82983 8 Adams 30 70 East King Street Bridge PHRS Form 1/6/2012Identification: Historic Resource Determination of Eligibility 2/13/2012 Jeremy Ammerman

82983 8 Adams 30 70 East King Street Bridge Negative Survey Form 12/15/2011Identification: Phase I Archaeological Survey Rebecca Knapp

93722 8 Adams 0 ENH Seminary Ridge Trail Scoping Form/Early Notification 3/12/2012Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

18433 8 Cumberland BR WOLF BRIDGE T-508Project Description and Consulting Party Invitations 8/3/2011

Public Involvement: Consulting Party Coordination Jerry Clouse

18433 8 Cumberland BR WOLF BRIDGE T-508 additional consulting party invitations 12/9/2011Public Involvement: Consulting Party Coordination Jerry Clouse

18433 8 Cumberland BR WOLF BRIDGE T-508 consulting party responses 12/30/2011Public Involvement: Consulting Party Coordination Jerry Clouse

18433 8 Cumberland BR WOLF BRIDGE T-508 Tribal Notification 6/30/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

18433 8 Cumberland BR WOLF BRIDGE T-508 Scoping Form 6/14/2011Scoping: Project Early Notification/ Scoping Results Jeremy Ammerman

18436 8 Cumberland 7213 BRGT-520, Craighead Bridge over Yellow Breeches Creek Feasibility Report 10/12/2011

Determination of Effects: Feasibility Analysis 10/21/2011 Jeremy Ammerman

18436 8 Cumberland 7213 BRGT-520, Craighead Bridge over Yellow Breeches Creek PHRS Form 7/26/2011

Identification: Historic Resource Determination of Eligibility Jeremy Ammerman

18436 8 Cumberland 7213 BRGT-520, Craighead Bridge over Yellow Breeches Creek Negative Survey Form 2/16/2012

Identification: Phase I Archaeological Survey Rebecca Knapp

18436 8 Cumberland 7213 BRGT-520, Craighead Bridge over Yellow Breeches Creek consulting party invitation letters 7/6/2011

Public Involvement: Consulting Party Coordination Jerry Clouse

18436 8 Cumberland 7213 BRGT-520, Craighead Bridge over Yellow Breeches Creek Consulting Party Response Forms 7/27/2011

Public Involvement: Consulting Party Coordination Jerry Clouse

70206 8 Cumberland 34 23Route 34 and Sunnyside Drive Intersection

Public Phase I Archaeology Report and Finding Form 8/2/2011

Determination of Effects: Effect Determination 8/23/2011 Rebecca Knapp

70206 8 Cumberland 34 23Route 34 and Sunnyside Drive Intersection

Public Phase I Archaeology Report and Finding Form 8/2/2011

Identification: Phase I Archaeological Survey 8/23/2011 Rebecca Knapp

18900 8 Dauphin BR Duke Street Bridge Feasibility Analysis 3/16/2012Determination of Effects: Feasibility Analysis 4/13/2012 Jeremy Ammerman

18900 8 Dauphin BR Duke Street Bridge Consulting Party Coordination 7/13/2011Public Involvement: Consulting Party Coordination Jerry Clouse

18900 8 Dauphin BR Duke Street Bridge Consulting Party Response Forms 8/10/2011Public Involvement: Consulting Party Coordination Jerry Clouse

18944 8 Dauphin 22 2 Dauphin River Route Negative Survey Form 7/1/2011Determination of Effects: Archaeology Field Assessment and Finding 7/11/2011 Rebecca Knapp

18944 8 Dauphin 22 2 Dauphin River Route Negative Survey Form 7/1/2011Identification: Phase I Archaeological Survey 7/11/2011 Rebecca Knapp

19106 8 Dauphin 2017 12 Manada Bottom Rd Br 1 Tribal Notification 7/1/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

19106 8 Dauphin 2017 12 Manada Bottom Rd Br 1 Scoping Form/Early Notification 6/6/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

65941 8 Dauphin 0 Lykens Valley Rail Trail Dual Finding Form 6/20/2011Determination of Effects: Above-Ground Field Assessment and Finding 6/22/2011 Jeremy Ammerman

65941 8 Dauphin 0 Lykens Valley Rail Trail Dual Finding Form 6/20/2011Determination of Effects: Archaeology Field Assessment and Finding 6/22/2011 Jeremy Ammerman

65941 8 Dauphin 0 Lykens Valley Rail Trail PHRS Form 5/27/2011Identification: Historic Resource Determination of Eligibility 6/8/2011 Jeremy Ammerman

65941 8 Dauphin 0 Lykens Valley Rail Trail PHRS Form Revised 6/15/2011Identification: Historic Resource Determination of Eligibility 6/22/2011 Jeremy Ammerman

74517 8 Dauphin 3018 1 Paxton Creek Bridge Scoping Form/Early Notification 6/6/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

74519 8 Dauphin 230 23 Hbg Pk Brg over Swatara Tribal Notification 6/30/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

74519 8 Dauphin 230 23 Hbg Pk Brg over Swatara Scoping Form/Early Notification 6/6/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

63180 8 Franklin 4004 0 Horse Rd SR4004 CO#116 Early Notification 11/10/2011Early Coordination: Notification to the SHPO Jeremy Ammerman

74889 8 Franklin 16 37 PA-16 Memorial Brdge Feasibility Report 2/8/2012Determination of Effects: Feasibility Analysis 2/29/2012 Jeremy Ammerman

74889 8 Franklin 16 37 PA-16 Memorial Brdge Consulting Parties 12/27/2011Public Involvement: Consulting Party Coordination Jeremy Ammerman

82979 8 Franklin 4 Orrstown Rd Bridge PHRS form addendum 8/10/2011Identification: Historic Resource Determination of Eligibility 8/26/2011 Jerry Clouse

87147 8 Franklin 30 91 US 30 Colebrook Ave Combined Field Assessment and Finding 3/5/2012Determination of Effects: Above-Ground Field Assessment and Finding Rebecca Knapp

87147 8 Franklin 30 91 US 30 Colebrook Ave Combined Field Assessment and Finding 3/5/2012Determination of Effects: Archaeology Field Assessment and Finding Rebecca Knapp

92542 8 Franklin 7202 0 Store Lane T-572 CO#54 Early Notification 11/10/2011Early Coordination: Notification to the SHPO Jeremy Ammerman

92542 8 Franklin 7202 0 Store Lane T-572 CO#54 PHRS Form 5/1/2012Identification: Historic Resource Determination of Eligibility Jeremy Ammerman

19503 8 Lancaster 1010 18 Farmersvlle Rd Bridge Consulting Party Invitation 8/5/2011Identification: Consulting Party/Tribal Consultation Coordination Jeremy Ammerman

19503 8 Lancaster 1010 18 Farmersvlle Rd Bridge PHRS Form 3/30/2012Identification: Historic Resource Determination of Eligibility 4/20/2012 Jeremy Ammerman

19503 8 Lancaster 1010 18 Farmersvlle Rd Bridge Tribal Notification 6/30/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

19503 8 Lancaster 1010 18 Farmersvlle Rd Bridge Scoping Form/Early Notification 5/20/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

19799 8 Lancaster 7213 BRG T-848 Conestoga Creek Road Bridge Archaeological Field Assessment and Finding 2/23/2012Determination of Effects: Archaeology Field Assessment and Finding Rebecca Knapp

19799 8 Lancaster 7213 BRG T-848 Conestoga Creek Road Bridge Determination of Effect Report 10/19/2011Determination of Effects: Effect Determination 9/22/2011 9/22/2011 Jerry Clouse

19799 8 Lancaster 7213 BRG T-848 Conestoga Creek Road Bridge Effects-additional information 1/24/2012Determination of Effects: Effect Determination - non-form 2/14/2012 Jerry Clouse

19799 8 Lancaster 7213 BRG T-848 Conestoga Creek Road Bridge PHRS FORMS 7/22/2011Identification: Historic Resource Determination of Eligibility 8/5/2011 Jerry Clouse

19799 8 Lancaster 7213 BRG T-848 Conestoga Creek Road Bridge Assesment of Archaeological Potential 1/6/2012Early Coordination: Geomorphological Testing 2/22/2012 Rebecca Knapp

19933 8 Lancaster 741 18 Village Road Bridge Tribal Notification 11/10/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Rebecca Knapp

19933 8 Lancaster 741 18 Village Road Bridge Scoping Form/Early Notification 10/6/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

19972 8 Lancaster 897 24 White Horse Rd Bridge Tribal Notification 6/30/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

19972 8 Lancaster 897 24 White Horse Rd Bridge Lancaster 19972 Scoping Form 6/14/2011Scoping: Project Early Notification/ Scoping Results Jeremy Ammerman

20115 8 Lancaster 896 7 PA 896 Shoulders & Rscf Combined Field Assessment and Finding 12/29/2011Determination of Effects: Above-Ground Field Assessment and Finding 2/22/2012 Rebecca Knapp

20115 8 Lancaster 896 7 PA 896 Shoulders & Rscf Combined Field Assessment and Finding 12/29/2011Determination of Effects: Archaeology Field Assessment and Finding 2/22/2012 Rebecca Knapp

20115 8 Lancaster 896 7 PA 896 Shoulders & Rscf Early Notification 10/12/2011Early Coordination: Notification to the SHPO Jeremy Ammerman

20115 8 Lancaster 896 7 PA 896 Shoulders & Rscf Phase I Archaeology Report 12/9/2011Identification: Phase I Archaeological Survey Rebecca Knapp

20115 8 Lancaster 896 7 PA 896 Shoulders & Rscf Tribal Notification 11/10/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Rebecca Knapp

63220 8 Lancaster 372 14 Christiana Pk Bridges PHRS Form 3/5/2012 Identification: Historic Resource Survey 3/26/2012 Jeremy Ammerman

63220 8 Lancaster 372 14 Christiana Pk Bridges Tribal Notification 6/20/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

63220 8 Lancaster 372 14 Christiana Pk Bridges Lancaster 63220 Scoping Form 6/14/2011Scoping: Project Early Notification/ Scoping Results Jeremy Ammerman

64827 8 Lancaster 441 12 SR 441 Relocation Phase IA Archaeology Report Addendum 7/6/2011Identification: Phase I Archaeological Survey 7/11/2011 Rebecca Knapp

64827 8 Lancaster 441 12 SR 441 Relocation PA Amendment 1/9/2012Mitigation: MOA/PA Commitment Coordination 1/31/2012 Chris Kula

64827 8 Lancaster 441 12 SR 441 Relocation Phase IA Archaeology Report Addendum 7/6/2011 Other: Project Scope Change 7/11/2011 Rebecca Knapp

64827 8 Lancaster 441 12 SR 441 RelocationDraft Amendment to the Programmatic Agreement 7/18/2011 Resolution of Adverse Effects: MOA/PA Chris Kula

64827 8 Lancaster 441 12 SR 441 Relocation PA Amendment 1/21/2012 Resolution of Adverse Effects: MOA/PA 2/1/2012 Chris Kula

64827 8 Lancaster 441 12 SR 441 Relocation Revised PA Amendment 2/14/2012 Resolution of Adverse Effects: MOA/PA 2/22/2012 Chris Kula

64827 8 Lancaster 441 12 SR 441 Relocation Revised PA Amendment 2/23/2012 Resolution of Adverse Effects: MOA/PA 3/26/2012 Chris Kula

64827 8 Lancaster 441 12 SR 441 Relocation Revised PA Amendment 3/28/2012 Resolution of Adverse Effects: MOA/PA 4/5/2012 Chris Kula

74954 8 Lancaster 4011 15 Fruitville Pike Brg Tribal Notification 6/30/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

74954 8 Lancaster 4011 15 Fruitville Pike Brg Scoping Form 6/14/2011Scoping: Project Early Notification/ Scoping Results Jeremy Ammerman

74959 8 Lancaster 1035 5 Clay Road Bridge Tribal Notification 6/30/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

74959 8 Lancaster 1035 5 Clay Road Bridge Scoping Form 6/14/2011Scoping: Project Early Notification/ Scoping Results Jeremy Ammerman

82899 8 Lancaster 743 24 Hershey Rd Bridge Tribal Notification 6/20/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

82899 8 Lancaster 743 24 Hershey Rd Bridge Scoping Form 6/14/2011Scoping: Project Early Notification/ Scoping Results Jeremy Ammerman

83168 8 Lancaster 30 69 Lincoln Hwy Corr. Imp. Response to PHMC 6/13/2011Determination of Effects: Effect Determination Jerry Clouse

83168 8 Lancaster 30 69 Lincoln Hwy Corr. Imp. Determination of Effects Addendum 1/31/2012Determination of Effects: Effect Determination 2/21/2012 Jerry Clouse

83168 8 Lancaster 30 69 Lincoln Hwy Corr. Imp. Draft Programmatic Agreement 6/23/2011 Resolution of Adverse Effects: MOA/PA 6/24/2011 Chris Kula

83168 8 Lancaster 30 69 Lincoln Hwy Corr. Imp. Deferral of Archaeological Testing 2/29/2012Special Processes: Deferral of Archaeological Testing 3/5/2012 Rebecca Knapp

85656 8 Lancaster 741 17Intersection with SR 2035, Belmont Road Supplemental Information 9/16/2011 BHP Enhancement: Field Concurrence 10/3/2011 Jeremy Ammerman

85656 8 Lancaster 741 17Intersection with SR 2035, Belmont Road Combined Field Assessment and Finding 6/6/2011

Determination of Effects: Above-Ground Field Assessment and Finding 6/17/2011 6/17/2011 Rebecca Knapp

85656 8 Lancaster 741 17Intersection with SR 2035, Belmont Road Combined Field Assessment and Finding 6/6/2011

Determination of Effects: Archaeology Field Assessment and Finding 6/17/2011 6/17/2011 Rebecca Knapp

85656 8 Lancaster 741 17Intersection with SR 2035, Belmont Road Deferral of Archaeological Testing 3/5/2012 Other: Project Scope Change 3/6/2012 Rebecca Knapp

85656 8 Lancaster 741 17Intersection with SR 2035, Belmont Road Deferral of Archaeological Testing 3/5/2012

Special Processes: Deferral of Archaeological Testing 3/6/2012 Rebecca Knapp

87710 8 Lancaster 3 Bridge over Little Cocalico Creek Combined Field Assessment and Finding 5/16/2011Determination of Effects: Above-Ground Field Assessment and Finding Rebecca Knapp

87710 8 Lancaster 3 Bridge over Little Cocalico Creek Combined Field Assessment and Finding 5/16/2011Determination of Effects: Archaeology Field Assessment and Finding Rebecca Knapp

88972 8 Lancaster 222 47 Robert Fulton Hwy Rsf Combined Field Assessment and Finding 2/23/2012Determination of Effects: Above-Ground Field Assessment and Finding Rebecca Knapp

88972 8 Lancaster 222 47 Robert Fulton Hwy Rsf Combined Field Assessment and Finding 2/23/2012Determination of Effects: Archaeology Field Assessment and Finding Rebecca Knapp

88972 8 Lancaster 222 47 Robert Fulton Hwy Rsf Early Notification Form 11/10/2011Early Coordination: Notification to the SHPO Jeremy Ammerman

88972 8 Lancaster 222 47 Robert Fulton Hwy Rsf PASS Form 2/15/2012 Other: Other 2/17/2012 Rebecca Knapp

89288 8 Lancaster 7101 BRG Rohrerstown Rd Bridge Scoping Form/Early Notification 5/1/2012Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

20400 8 Lebanon 0 BRG Bridge over Norfolk Southern PA amendment concurring party invitation letter 7/18/2011Public Involvement: Consulting Party Coordination Jerry Clouse

20400 8 Lebanon 0 BRG Bridge over Norfolk SouthernDraft Amendment to the Programmatic Agreement 6/2/2011 Resolution of Adverse Effects: MOA/PA 6/3/2011 Chris Kula

20400 8 Lebanon 0 BRG Bridge over Norfolk Southern Amendment to the Programmatic Agreement 8/25/2011 Resolution of Adverse Effects: MOA/PA 9/2/2011 Chris Kula

20400 8 Lebanon 0 BRG Bridge over Norfolk Southern Amendment to the Programmatic Agreement 9/7/2011 Resolution of Adverse Effects: MOA/PA 9/29/2011 Chris Kula

74922 8 Lebanon 443 11 Mountain Road Bridge Scoping Form/Early Notification 6/3/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

78767 8 Lebanon 1014 9 Greble Rd Bridge Tribal Notification 7/6/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

78767 8 Lebanon 1014 9 Greble Rd Bridge Scoping Form/Early Notification 6/10/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

82910 8 Lebanon 322 31 Horseshoe Pike Bridge 2 Tribal Notification 7/6/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

82910 8 Lebanon 322 31 Horseshoe Pike Bridge 2 Scoping Form/Early Notification 6/10/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

82911 8 Lebanon 341 5 Colebrook Road Bridge Tribal Notification 7/6/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

82911 8 Lebanon 341 5 Colebrook Road Bridge Scoping Form/Early Notification 6/10/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

82912 8 Lebanon 443 10 Asher Miner Rd Bridge Combined Field Assessment and Finding 6/6/2011Determination of Effects: Above-Ground Field Assessment and Finding Rebecca Knapp

82912 8 Lebanon 443 10 Asher Miner Rd Bridge Combined Field Assessment and Finding 6/6/2011Determination of Effects: Archaeology Field Assessment and Finding Rebecca Knapp

88084 8 Lebanon 72 41 Quentin Rd & Main Street PHRS Form 10/19/2011Identification: Historic Resource Determination of Eligibility 11/7/2011 Jeremy Ammerman

88084 8 Lebanon 72 41 Quentin Rd & Main Street Negative Survey Form 10/19/2011Identification: Phase I Archaeological Survey Rebecca Knapp

20531 8 Perry 4001 7Saville Covered Bridge Over Buffalo Creek Temporary Repairs 8/16/2011

Determination of Effects: Effect Determination Jeremy Ammerman

20531 8 Perry 4001 7Saville Covered Bridge Over Buffalo Creek Emergency Repairs 6/8/2011

Determination of Effects: Effect Determination - non-form 6/9/2011 Jeremy Ammerman

70206 8 Perry 34 23Route 34 and Sunnyside Drive Intersection

Public Phase I Archaeology Report and Finding Form 8/2/2011

Determination of Effects: Effect Determination 8/23/2011 Rebecca Knapp

70206 8 Perry 34 23Route 34 and Sunnyside Drive Intersection

Public Phase I Archaeology Report and Finding Form 8/2/2011

Identification: Phase I Archaeological Survey 8/23/2011 Rebecca Knapp

20979 8 York 2019 BRG Yorkana Road Bridge Rehab Combined Field Assessment and Finding 11/9/2011Determination of Effects: Above-Ground Field Assessment and Finding 12/6/2011 Rebecca Knapp

20979 8 York 2019 BRG Yorkana Road Bridge Rehab Combined Field Assessment and Finding 11/9/2011Determination of Effects: Archaeology Field Assessment and Finding 12/6/2011 Rebecca Knapp

20979 8 York 2019 BRG Yorkana Road Bridge Rehab PHRS Form 10/6/2011Identification: Historic Resource Determination of Eligibility 10/24/2011 Jeremy Ammerman

20979 8 York 2019 BRG Yorkana Road Bridge Rehab Tribal Notification 6/16/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

20979 8 York 2019 BRG Yorkana Road Bridge Rehab Scoping Form/Early Notification 5/20/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

58125 8 York 0 RWY Center Street Upgrade Combined Field Assessment and Finding 12/9/2011Determination of Effects: Above-Ground Field Assessment and Finding Rebecca Knapp

58125 8 York 0 RWY Center Street Upgrade Combined Field Assessment and Finding 12/9/2011Determination of Effects: Archaeology Field Assessment and Finding Rebecca Knapp

63097 8 York 2008 9 Libhart Mill Road Bridge Tribal Notification 11/10/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

63120 8 York 216 14 Sticks Road BridgePhase IA Archaeology/Geomorphology Report and Finding Form 7/29/2011

Determination of Effects: Above-Ground Field Assessment and Finding Rebecca Knapp

63120 8 York 216 14 Sticks Road BridgePhase IA Archaeology/Geomorphology Report and Finding Form 7/29/2011

Determination of Effects: Archaeology Field Assessment and Finding Rebecca Knapp

63120 8 York 216 14 Sticks Road BridgePhase IA Archaeology/Geomorphology Report and Finding Form 7/29/2011

Early Coordination: Geomorphological Testing Rebecca Knapp

68800 8 York 4038 1Meadowview Drive Bridge over Bermudian Creek Combined Field Assessment and Finding 3/7/2012

Determination of Effects: Above-Ground Field Assessment and Finding 4/18/2012 Rebecca Knapp

68800 8 York 4038 1Meadowview Drive Bridge over Bermudian Creek Combined Field Assessment and Finding 3/7/2012

Determination of Effects: Archaeology Field Assessment and Finding 4/18/2012 Rebecca Knapp

68800 8 York 4038 1Meadowview Drive Bridge over Bermudian Creek Feasibility Analysis Report 5/19/2011

Determination of Effects: Feasibility Analysis Jerry Clouse

68800 8 York 4038 1Meadowview Drive Bridge over Bermudian Creek

Consulting Party Invitation Letters & Response Forms 10/19/2011

Public Involvement: Consulting Party Coordination Jerry Clouse

68800 8 York 4038 1Meadowview Drive Bridge over Bermudian Creek Consulting Party Responses 8/17/2011

Public Involvement: Consulting Party Coordination Jeremy Ammerman

74945 8 York 194 18 Baltimore Pk Brg PHRS Form 3/15/2012Identification: Historic Resource Determination of Eligibility Jeremy Ammerman

74945 8 York 194 18 Baltimore Pk Brg Scoping Form/Early Notification 6/10/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

74948 8 York 3050 1 Woodberry Rd Bridge Tribal Notification 6/16/2011Early Coordination: Advance Notification to SHPO Rebecca Knapp

74948 8 York 3050 1 Woodberry Rd Bridge PHRS Form 3/23/2012Identification: Historic Resource Determination of Eligibility Jeremy Ammerman

74948 8 York 3050 1 Woodberry Rd Bridge Tribal Notification 6/16/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

74948 8 York 3050 1 Woodberry Rd Bridge Scoping Form/Early Notification 6/14/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

77327 8 York ENH Susquehanna Riverland Effects Report 4/2/2012Determination of Effects: Above-Ground Field Assessment and Finding 4/2/2012 Jeremy Ammerman

77327 8 York ENH Susquehanna Riverland Consulting Party Invitation Letter 8/5/2011Public Involvement: Consulting Party Coordination Jeremy Ammerman

77327 8 York ENH Susquehanna Riverland Tribal Notification 6/20/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

77327 8 York ENH Susquehanna Riverland Draft Programatic Agreement 3/16/2012 Resolution of Adverse Effects: MOA/PA Rebecca Knapp

77327 8 York ENH Susquehanna Riverland Final PA for Signatures 4/19/2012 Resolution of Adverse Effects: MOA/PA Rebecca Knapp

77327 8 York ENH Susquehanna Riverland Scoping Form/Early Notification 6/20/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

83420 8 York 30 84 Paradise Creek Bridge Tribal Notification 6/16/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

83420 8 York 30 84 Paradise Creek Bridge Scoping Form/Early Notification 6/14/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

83421 8 York 30 85 Lincoln Highway Bridge 1 Tribal Notification 6/16/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

83421 8 York 30 85 Lincoln Highway Bridge 1 Tribal Notification 6/16/2011Public Involvement: Tribal Consultation Coordination Rebecca Knapp

83421 8 York 30 85 Lincoln Highway Bridge 1 Scoping Form/Early Notification 6/14/2011Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

87750 8 York 7301 BRG PhiladelphiaSt Brdg/CO#77Consulting Party Invitation Letters and Project Description 7/26/2011

Public Involvement: Consulting Party Coordination Jerry Clouse

88952 8 York 7204 BRG Mill Creek Rd CO#187 Replacement Scoping Form/Early Notification 3/29/2012Scoping: Project Early Notification/ Scoping Results Rebecca Knapp

88953 8 York NULL BRG Valley St CO#114 Replace Combined Field Assessment and Finding 4/2/2012Determination of Effects: Above-Ground Field Assessment and Finding 4/30/2012 Rebecca Knapp

88953 8 York NULL BRG Valley St CO#114 Replace Combined Field Assessment and Finding 4/2/2012Determination of Effects: Archaeology Field Assessment and Finding 4/30/2012 Rebecca Knapp

21461 9 Bedford 2019 01B Lutzville Bridge Combined Field Assessments and Finding 3/27/2012Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

21461 9 Bedford 2019 01B Lutzville Bridge Combined Field Assessments and Finding 3/27/2012Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

21461 9 Bedford 2019 01B Lutzville Bridge Tribal Consultation- Inital Notification 1/5/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

21461 9 Bedford 2019 01B Lutzville Bridge Project Early Notification/Scoping Results Form 1/5/2012Scoping: Project Early Notification/ Scoping Results Susanne M. Haney

21461 9 Bedford 2019 01B Lutzville Bridge Negative Survey Form Hard CopySpecial Processes: Submittal of Archival Paper Copy Susanne M. Haney

48045 9 Bedford 56 23M N Pensyl Hollow Rd Intrsn Tribal Consultation Inital Nottification 1/4/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

48045 9 Bedford 56 23M N Pensyl Hollow Rd Intrsn Early Notification/Scoping Results Form 10/18/2011Scoping: Project Early Notification/ Scoping Results Jonathan Daily

88127 9 Bedford 2007 03B Tr W Sideling Hill Ck Brg Combined Field Assessment and Finding 8/2/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

88127 9 Bedford 2007 03B Tr W Sideling Hill Ck Brg Combined Field Assessment and Finding 8/2/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

88127 9 Bedford 2007 03B Tr W Sideling Hill Ck Brg Tribal Consultation Follow Up Notification 8/2/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

88127 9 Bedford 2007 03B Tr W Sideling Hill Ck Brg Negative Survey Form Hard Copy 8/4/2011Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

92116 9 Bedford 4010 DB3 Downtown Bedford Phase 3 Findings 12/6/2011Determination of Effects: Above-Ground Field Assessment and Finding Jonathan Daily

92116 9 Bedford 4010 DB3 Downtown Bedford Phase 3 Findings 12/6/2011Determination of Effects: Archaeology Field Assessment and Finding Jonathan Daily

21630 9 Blair 4019 4 Pinecroft Curves Early Notification/Scoping Results Form 8/18/2011Scoping: Project Early Notification/ Scoping Results Jonathan Daily

21891 9 Blair 1001 15 Little Juniata River Bridge #1 PAC Consulting Party Letter 4/17/2012Determination of Effects: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

21891 9 Blair 1001 15 Little Juniata River Bridge #1 Draft Phase III Archaeology Report FHWA 12/7/2011Mitigation: Phase III Archaeological Data Recovery 1/8/2012 Susanne M. Haney

21891 9 Blair 1001 15 Little Juniata River Bridge #1 Draft Phase III Archaeology Report PHMC 12/9/2011Mitigation: Phase III Archaeological Data Recovery 12/16/2011 Susanne M. Haney

21891 9 Blair 1001 15 Little Juniata River Bridge #1 Tribal Consultation Follow Up Information 12/7/2011Mitigation: Phase III Archaeological Data Recovery Susanne M. Haney

21891 9 Blair 1001 15 Little Juniata River Bridge #1 Hard Copy of Phase III Archaeology Report 3/12/2012Mitigation: Phase III Archaeological Data Recovery Susanne M. Haney

21891 9 Blair 1001 15 Little Juniata River Bridge #1 Phase III Redacted Archaeology Report 3/15/2012Mitigation: Phase III Archaeological Data Recovery Susanne M. Haney

21891 9 Blair 1001 15 Little Juniata River Bridge #1 PAC Consulting Party Letter 4/17/2012Public Involvement: Consulting Party Coordination Susanne M. Haney

21891 9 Blair 1001 15 Little Juniata River Bridge #1 Tribal Consultation Follow Up Information 12/7/2011Public Involvement: Tribal Consultation Coordination Susanne M. Haney

21891 9 Blair 1001 15 Little Juniata River Bridge #1 Tribal Consultation Follow Up Information 3/15/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

21891 9 Blair 1001 15 Little Juniata River Bridge #1 Hard Copy of Phase III Archaeology Report 3/12/2012Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

21895 9 Blair 4027 05B Tyrone Westvaco Bridge Above-Ground Field Assessment and Finding 10/21/2011Determination of Effects: Above-Ground Field Assessment and Finding Jonathan Daily

22027 9 Blair 2014 03B Loop Road Bridge Early Notification/Scoping Results Form 9/29/2011Scoping: Project Early Notification/ Scoping Results 10/3/2011 Susanne M. Haney

22027 9 Blair 2014 03B Loop Road Bridge Geomorphology Report 12/15/2011Special Processes: Submittal of Archival Paper Copy 1/3/2012 Susanne M. Haney

92644 9 Blair 1013 0 Sinking Run Bridge #5 Consulting party letter to Morrows 11/29/2011Public Involvement: Consulting Party Coordination 12/1/2011 Jonathan Daily

92644 9 Blair 1013 0 Sinking Run Bridge #5 Consulting Party letter 11/29/2011Public Involvement: Consulting Party Coordination 12/14/2011 Jonathan Daily

92644 9 Blair 1013 0 Sinking Run Bridge #5Consulting Party, request for comments, Form Liners

Public Involvement: Consulting Party Coordination Jonathan Daily

22406 9 Cambria 271 13 Menoher Blvd Slide Combined Field Assessments and Finding 11/8/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

22406 9 Cambria 271 13 Menoher Blvd Slide Combined Field Assessments and Finding 11/8/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

22527 9 Cambria 271 10Strank Memorial Bridge (Franklin&Conemaugh Br) Archaeology-Late Discovery Documentation 6/3/2011 Other: Other Susanne M. Haney

22527 9 Cambria 271 10Strank Memorial Bridge (Franklin&Conemaugh Br) Archaeology-Late Discovery Documentation 6/3/2011

Public Involvement: Consulting Party Coordination Susanne M. Haney

22657 9 Cambria 56 25 Strayer Street Improvements Combined Feld Assessments and Finding 11/3/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

22657 9 Cambria 56 25 Strayer Street Improvements Combined Feld Assessments and Finding 11/3/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

67166 9 Cambria 7418 1 Lilly Boro Pine Street Bridge Combined Field Assessments and Finding 7/15/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

67166 9 Cambria 7418 1 Lilly Boro Pine Street Bridge Combined Field Assessments and Finding 7/15/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

72245 9 Cambria 3024 05M Frankstown Wall and Resurfacing Tribal Consultation Follow Up Information 3/27/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

74365 9 Cambria 219 36Trib to W. Br. Susquehanna R. Culvert Combined Field Assessments and Finding 7/29/2011

Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

74365 9 Cambria 219 36Trib to W. Br. Susquehanna R. Culvert Combined Field Assessments and Finding 7/29/2011

Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

93173 9 Cambria 3030 1 SR 3030 Emg Slide Repair Combined Field Assessments and Finding 4/10/2012Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

93173 9 Cambria 3030 1 SR 3030 Emg Slide Repair Combined Field Assessments and Finding 4/10/2012Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

22782 9 Fulton 30 5 Licking Creek Bridge (Harrisonville) Combined Field Assessments and Finding 9/23/2011Determination of Effects: Above-Ground Field Assessment and Finding 10/3/2011 Susanne M. Haney

22782 9 Fulton 30 5 Licking Creek Bridge (Harrisonville) Combined Field Assessments and Finding 9/23/2011Determination of Effects: Archaeology Field Assessment and Finding 10/3/2011 Susanne M. Haney

22782 9 Fulton 30 5 Licking Creek Bridge (Harrisonville) Tribal Consultation Follow Up Information 9/23/2011Identification: Consulting Party/Tribal Consultation Coordination 11/3/2011 Susanne M. Haney

22782 9 Fulton 30 5 Licking Creek Bridge (Harrisonville) Combined Field Assessments and Finding 9/23/2011Identification: Phase I Archaeological Survey 10/3/2011 Susanne M. Haney

22782 9 Fulton 30 5 Licking Creek Bridge (Harrisonville) Combined Field Assessments and Finding 9/23/2011 Special Processes: Standard Treatment 10/3/2011 Susanne M. Haney

37266 9 Fulton 475 03S PA475 Hustontown Intrsctn Early Notfication/Scoping Results Form 1/13/2012Early Coordination: Notification to the SHPO Susanne M. Haney

37266 9 Fulton 475 03S PA475 Hustontown Intrsctn Tribal Consultation-Inital Notification 1/13/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

48015 9 Fulton 475 04S PA475 Waterfall Rd Improv Early Notification/Scoping Results Form 1/13/2012Early Coordination: Notification to the SHPO Susanne M. Haney

48015 9 Fulton 475 04S PA475 Waterfall Rd Improv Tribal Consultation-Inital Notification 1/13/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

48054 9 Fulton 522 13 PA 522 Gem Curve Combined Field Assesments and Finding 11/1/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

48054 9 Fulton 522 13 PA 522 Gem Curve Combined Field Assesments and Finding 11/1/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

48054 9 Fulton 522 13 PA 522 Gem Curve Tribal Consultation Follow Up Notification 11/2/2011Identification: Phase I Archaeological Survey Susanne M. Haney

48054 9 Fulton 522 13 PA 522 Gem Curve Tribal Consultation Follow Up Notification 11/2/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

48054 9 Fulton 522 13 PA 522 Gem Curve Tribal Consultation Initial Notification 8/9/2011Public Involvement: Tribal Consultation Coordination Susanne M. Haney

48054 9 Fulton 522 13 PA 522 Gem Curve Early Notification/Scoping Results Form 8/9/2011Scoping: Project Early Notification/ Scoping Results Susanne M. Haney

48054 9 Fulton 522 13 PA 522 Gem Curve Phase I Archaeology Report Hard Copy 11/4/2011Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

22998 9 Huntingdon 913 06B Barnettstown Bridge HRSF for PHMC committee review 6/21/2011Identification: Historic Resource Determination of Eligibility 7/6/2011 Jonathan Daily

23026 9 Huntingdon 4005 1 Neff/Juniata River Bridge #5 Construction Update 7/28/2011 Other: Other Jonathan Daily

23041 9 Huntingdon 3053 02B Robinson Run Bridge Combined Field Assessments and Finding 11/7/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

23041 9 Huntingdon 3053 02B Robinson Run Bridge Combined Field Assessments and Finding 11/7/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

23041 9 Huntingdon 3053 02B Robinson Run Bridge Tribal Consultation Inital Notification 9/30/2011Public Involvement: Tribal Consultation Coordination Susanne M. Haney

23041 9 Huntingdon 3053 02B Robinson Run Bridge Tribal Consutation Follow Up Notification 11/26/2011Public Involvement: Tribal Consultation Coordination Susanne M. Haney

23041 9 Huntingdon 3053 02B Robinson Run Bridge Early Notification/Scoping Results From 9/27/2011Scoping: Project Early Notification/ Scoping Results 9/28/2011 Susanne M. Haney

23041 9 Huntingdon 3053 02B Robinson Run Bridge Negative Survey Form Hard Copy 11/18/2011Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

74472 9 Huntingdon 3045 02B Trib Juniata Rvr Culvert Combined Field Assessments and Finding 12/7/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

74472 9 Huntingdon 3045 02B Trib Juniata Rvr Culvert Combined Field Assessments and Finding 12/7/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

74473 9 Huntingdon 3053 01B Trib Robinson Run Seg 10 Combined Field Assessments and Finding 11/7/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

74473 9 Huntingdon 3053 01B Trib Robinson Run Seg 10 Combined Field Assessments and Finding 11/7/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

74473 9 Huntingdon 3053 01B Trib Robinson Run Seg 10 Tribal Consultation Inital Notification 9/30/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

74473 9 Huntingdon 3053 01B Trib Robinson Run Seg 10 Tribal Consultation Follow Up Notification 11/29/2011Public Involvement: Tribal Consultation Coordination Susanne M. Haney

74473 9 Huntingdon 3053 01B Trib Robinson Run Seg 10 Early Notification/Scoping Results Form 9/27/2011Scoping: Project Early Notification/ Scoping Results 9/28/2011 Susanne M. Haney

74473 9 Huntingdon 3053 01B Trib Robinson Run Seg 10 Negative Survey Form Hard Copy 11/18/2011Special Processes: Submittal of Archival Paper Copy 11/18/2011 Susanne M. Haney

88096 9 Huntingdon 7208 548 T-548 Graysville Mill Brg Combined Field Assessments and Finding 1/19/2012Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

88096 9 Huntingdon 7208 548 T-548 Graysville Mill Brg Combined Field Assessments and Finding 1/19/2012Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

88096 9 Huntingdon 7208 548 T-548 Graysville Mill Brg Hard Copy Record of Disturbance Form 2/2/2012Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

92121 9 Huntingdon SMB St Marys Covered Bridge Field Assessment and Finding 2/27/2012Determination of Effects: Above-Ground Field Assessment and Finding 3/20/2012 Jonathan Daily

92121 9 Huntingdon SMB St Marys Covered Bridge Field Assessment and Finding 2/27/2012Determination of Effects: Archaeology Field Assessment and Finding 3/20/2012 Jonathan Daily

92121 9 Huntingdon SMB St Marys Covered Bridge Consulting Party Form 2/13/2012Public Involvement: Consulting Party Coordination Jonathan Daily

92121 9 Huntingdon SMB St Marys Covered Bridge Consulting Party contact 2/13/2012Public Involvement: Consulting Party Coordination Jonathan Daily

92121 9 Huntingdon SMB St Marys Covered Bridge Early Notification 2/13/2012Scoping: Project Early Notification/ Scoping Results Jonathan Daily

23057 9 Somerset 7206 353Maust Bridge (Co. Bridge 21) over Casselman River Feasibility Study review 10/27/2011

Determination of Effects: Feasibility Analysis 11/1/2011 11/1/2011 Jonathan Daily

23057 9 Somerset 7206 353Maust Bridge (Co. Bridge 21) over Casselman River Feasibility Study review 10/27/2011

Public Involvement: Consulting Party Coordination 11/1/2011 Jonathan Daily

23057 9 Somerset 7206 353Maust Bridge (Co. Bridge 21) over Casselman River Consulting Party Letter 10/25/2011

Public Involvement: Consulting Party Coordination 11/7/2011 Jonathan Daily

23057 9 Somerset 7206 353Maust Bridge (Co. Bridge 21) over Casselman River

Responses to C.Party comments on Feasibility Report 3/14/2012

Public Involvement: Consulting Party Coordination 4/13/2012 4/13/2012 Jonathan Daily

23057 9 Somerset 7206 353Maust Bridge (Co. Bridge 21) over Casselman River

Responses to PHMC comments on Feasibility Report 3/14/2012

Public Involvement: Consulting Party Coordination Jonathan Daily

23358 9 Somerset 7217 816Oldham Bridge T-816 (Co. Bridge 46) Feasibility Study review 9/20/2011

Determination of Effects: Feasibility Analysis 10/18/2011 Jonathan Daily

23358 9 Somerset 7217 816Oldham Bridge T-816 (Co. Bridge 46)

Responses to Feasibility Report comments to H.B. Foundation 3/15/2012

Public Involvement: Consulting Party Coordination Jonathan Daily

23411 9 Somerset 403 6 Kantner-Stony Creek Bridge Combined Field Assessment and Finding 8/26/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

23411 9 Somerset 403 6 Kantner-Stony Creek Bridge Combined Field Assessment and Finding 8/26/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

23411 9 Somerset 403 6 Kantner-Stony Creek Bridge Combined Field Assessment and Finding 8/26/2011Identification: Phase I Archaeological Survey Susanne M. Haney

23411 9 Somerset 403 6 Kantner-Stony Creek Bridge Tribal Consultation Follow Up Notification 8/26/2011Public Involvement: Tribal Consultation Coordination Susanne M. Haney

23411 9 Somerset 403 6 Kantner-Stony Creek Bridge Phase I Archaeology Report Hard Copy 8/26/2011Special Processes: Submittal of Archival Paper Copy 9/6/2011 Susanne M. Haney

23451 9 Somerset 669 1 Salisbury Casselman River Bridge Tribal Consultation Follow Up Information Form 9/21/2011Identification: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

23451 9 Somerset 669 1 Salisbury Casselman River BridgePhase I Letter Report and Phase II Technical Proposal 9/21/2011

Identification: Phase I Archaeological Survey 10/3/2011 Susanne M. Haney

23451 9 Somerset 669 1 Salisbury Casselman River Bridge Tribal Consultation Follow Up Information Form 9/21/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

23569 9 Somerset 1003 02B W Listie Wells Ck Culvert Combined Findings 1/4/2012Determination of Effects: Above-Ground Field Assessment and Finding Jonathan Daily

23569 9 Somerset 1003 02B W Listie Wells Ck Culvert Combined Findings 1/4/2012Determination of Effects: Archaeology Field Assessment and Finding Jonathan Daily

23574 9 Somerset 2037 02B Bigby Run Bridge Combined Finding Form 11/1/2011Determination of Effects: Above-Ground Field Assessment and Finding Jonathan Daily

23574 9 Somerset 2037 02B Bigby Run Bridge Combined Finding Form 11/1/2011Determination of Effects: Archaeology Field Assessment and Finding Jonathan Daily

23574 9 Somerset 2037 02B Bigby Run Bridge Tribal Consultation Inital Notification 8/9/2011Public Involvement: Tribal Consultation Coordination Susanne M. Haney

23574 9 Somerset 2037 02B Bigby Run Bridge Early Notification/Scoping Results Form 8/9/2011Scoping: Project Early Notification/ Scoping Results Susanne M. Haney

23620 9 Somerset 219 20 US 219 Meyersdale to SomersetAddendum Phase I/II Draft Report for Final Design Areas Tested 12/7/2011

Identification: Phase II Archaeological Evaluation 12/15/2011 Susanne M. Haney

23620 9 Somerset 219 20 US 219 Meyersdale to Somerset Hard Copy Final Phase I/II Addendum Report 2/3/2012Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

74435 9 Somerset 219 32B Somerset US 219 Culvert 1 Combined Field Assessments And Finding 12/14/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

74435 9 Somerset 219 32B Somerset US 219 Culvert 1 Combined Field Assessments And Finding 12/14/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

74435 9 Somerset 219 32B Somerset US 219 Culvert 1 Tribal Conslutation Inital Notifcation 11/3/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

74435 9 Somerset 219 32B Somerset US 219 Culvert 1 Tribal Consultation Follow Up Information 1/10/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

74435 9 Somerset 219 32B Somerset US 219 Culvert 1 Early Notification/Scoping Results Form 10/19/2011Scoping: Project Early Notification/ Scoping Results Jonathan Daily

74435 9 Somerset 219 32B Somerset US 219 Culvert 1 Negative Survey Form Hard Copy 1/5/2012Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

82399 9 Somerset 3029 2 Trent Road to 7 Springs Combined Field Assessments and Finding 9/13/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

82399 9 Somerset 3029 2 Trent Road to 7 Springs Combined Field Assessments and Finding 9/13/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

88240 9 Somerset 3015 03S Water Level Road Intersection Combined Field Assessments and Finding Form 5/5/2011Determination of Effects: Above-Ground Field Assessment and Finding 5/23/2011 Susanne M. Haney

88240 9 Somerset 3015 03S Water Level Road Intersection Combined Field Assessments and Finding Form 5/5/2011Determination of Effects: Archaeology Field Assessment and Finding 5/23/2011 Susanne M. Haney

88240 9 Somerset 3015 03S Water Level Road Intersection Phase I Abbreviated Report Hard Copy 6/3/2011Special Processes: Submittal of Archival Paper Copy 6/10/2011 Susanne M. Haney

94075 9 Somerset 219 32B Somerset US219 Culvert 2 Field Assessments and Finding 3/13/2012Determination of Effects: Above-Ground Field Assessment and Finding Jonathan Daily

94075 9 Somerset 219 32B Somerset US219 Culvert 2 Field Assessments and Finding 3/13/2012Determination of Effects: Archaeology Field Assessment and Finding Jonathan Daily

94075 9 Somerset 219 32B Somerset US219 Culvert 2 Field Assessments and Finding 3/13/2012Identification: Phase I Archaeological Survey Jonathan Daily

94075 9 Somerset 219 32B Somerset US219 Culvert 2 Early Notificaition/Scoping Results Form 2/22/2012Public Involvement: Tribal Consultation Coordination Jonathan Daily

94075 9 Somerset 219 32B Somerset US219 Culvert 2 Tribal Consultation Inital Notification 11/3/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

94075 9 Somerset 219 32B Somerset US219 Culvert 2 Tribal Consultation Follow Up Information 3/8/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

94075 9 Somerset 219 32B Somerset US219 Culvert 2 Early Notificaition/Scoping Results Form 2/22/2012Scoping: Project Early Notification/ Scoping Results Jonathan Daily

94075 9 Somerset 219 32B Somerset US219 Culvert 2 Negative Survey Form Hard Copy 4/18/2012Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

23662 10 Armstrong 422 172 Mushroom Farm Road Combined Assessments and Finding 8/24/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

23662 10 Armstrong 422 172 Mushroom Farm Road Combined Assessments and Finding 8/24/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

23813 10 Armstrong NULL 748 Lower Pine Run Bridge Feasibility Report 9/21/2011Determination of Effects: Feasibility Analysis 10/11/2011 Jonathan Daily

23813 10 Armstrong NULL 748 Lower Pine Run Bridge Feasibility Report 9/21/2011Public Involvement: Consulting Party/Tribal Consultation Coordination 10/11/2011 Jonathan Daily

23828 10 Armstrong 7202 BR T-535 McAuley Bridge PHMC Clearance Letter 7/6/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

23828 10 Armstrong 7202 BR T-535 McAuley Bridge PHMC Clearance Letter 7/6/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

24009 10 Armstrong 68 158 Brady's Bend Bridge #6 Combined Field Assessments and Finding 6/27/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

24009 10 Armstrong 68 158 Brady's Bend Bridge #6 Combined Field Assessments and Finding 6/27/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

24021 10 Armstrong 68 157 Brady's Bend Bridge #5 Combined Field Assessments and Finding 6/17/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

24021 10 Armstrong 68 157 Brady's Bend Bridge #5 Combined Field Assessments and Finding 6/17/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

24058 10 Armstrong 28 164 Slabtown Bridge No. 1 Draft Phase IB/II Report to PHMCDetermination of Effects: Archaeology Field Assessment and Finding 3/16/2012 Susanne M. Haney

24058 10 Armstrong 28 164 Slabtown Bridge No. 1 Archaeology Phase II Technical Proposal to PHMC 8/9/2011Identification: Consulting Party/Tribal Consultation Coordination 8/16/2011 Susanne M. Haney

24058 10 Armstrong 28 164 Slabtown Bridge No. 1 Tribal Consultation Follow Up, Phase IB/II Report 3/6/2012Identification: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

24058 10 Armstrong 28 164 Slabtown Bridge No. 1 Draft Phase IB/II Report to PHMCIdentification: Phase I & II Archaeological Evaluation 3/16/2012 Susanne M. Haney

24058 10 Armstrong 28 164 Slabtown Bridge No. 1 Draft Phase IB/II Report to FHWA 3/1/2012Identification: Phase I & II Archaeological Evaluation Susanne M. Haney

24058 10 Armstrong 28 164 Slabtown Bridge No. 1 Tribal Consultation Follow Up, Phase IB/II Report 3/6/2012Identification: Phase I & II Archaeological Evaluation Susanne M. Haney

24058 10 Armstrong 28 164 Slabtown Bridge No. 1 Archaeology Phase II Technical Proposal to PHMC 8/9/2011Identification: Phase I Archaeological Survey 8/16/2011 Susanne M. Haney

24058 10 Armstrong 28 164 Slabtown Bridge No. 1Consulting Party Solicitation Redacted Phase IB/II Report 3/6/2012

Public Involvement: Consulting Party Coordination Susanne M. Haney

24058 10 Armstrong 28 164 Slabtown Bridge No. 1 Programmatic Agreement to PHMC 5/16/2011 Resolution of Adverse Effects: MOA/PA 5/19/2011 Chris Kula

24058 10 Armstrong 28 164 Slabtown Bridge No. 1 Programmatic Agreement to FHWA 6/6/2011 Resolution of Adverse Effects: MOA/PA 6/7/2001 Chris Kula

77912 10 Armstrong 2025 158 Cochran's Mills No. 1 MOA Amendment 9/15/2011 Resolution of Adverse Effects: MOA/PA 9/21/2011 Kara Russell

77927 10 Armstrong 68 155 Brady's Bend Bridge #3 Combined Field Assessments and Finding Form 5/20/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

77927 10 Armstrong 68 155 Brady's Bend Bridge #3 Combined Field Assessments and Finding Form 5/20/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

77928 10 Armstrong 68 156 Brady's Bend Bridge #4 Combined Field Assessments and Finding Form 6/1/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

77928 10 Armstrong 68 156 Brady's Bend Bridge #4 Combined Field Assessments and Finding Form 6/1/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

77930 10 Armstrong 68 154 Brady's Bend Bridge #2 Combined Field Assessments and Finding 6/28/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

77930 10 Armstrong 68 154 Brady's Bend Bridge #2 Combined Field Assessments and Finding 6/28/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

89966 10 Armstrong 66 154 Spur Run Bridge Combined Field Assessments and Finding 4/3/2012Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

89966 10 Armstrong 66 154 Spur Run Bridge Combined Field Assessments and Finding 4/3/2012Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

24661 10 Butler 2004 250 Kittanning St. Bridge #2 Combined Field Assessments and Finding 6/15/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

24661 10 Butler 2004 250 Kittanning St. Bridge #2 Combined Field Assessments and Finding 6/15/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

24661 10 Butler 2004 250 Kittanning St. Bridge #2 HRSF for PHMC committee review 5/12/2011Identification: Historic Resource Determination of Eligibility Jonathan Daily

24661 10 Butler 2004 250 Kittanning St. Bridge #2 Record of Disturbance Form Hard copy 6/22/2011Special Processes: Submittal of Archival Paper Copy 6/27/2011 Susanne M. Haney

24706 10 Butler 3025 251 Little Creek Road Br #3 Combined Field Assessments and Finding 4/9/2012Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

24706 10 Butler 3025 251 Little Creek Road Br #3 Combined Field Assessments and Finding 4/9/2012Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

24706 10 Butler 3025 251 Little Creek Road Br #3 Early Notification/Scoping Results Form 11/12/2011Early Coordination: Notification to the SHPO Susanne M. Haney

24706 10 Butler 3025 251 Little Creek Road Br #3 Tribal Consultation Inital Notification 12/12/2011Public Involvement: Tribal Consultation Coordination Susanne M. Haney

24706 10 Butler 3025 251 Little Creek Road Br #3 Hard Copy Negative Survey Form 4/12/2012Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

24724 10 Butler 8 252 Adams Corner Bridge Combined Field Assessments and Finding 5/6/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

24724 10 Butler 8 252 Adams Corner Bridge Combined Field Assessments and Finding 5/6/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

24732 10 Butler 38 256 Greece City Bridge Combined Field Assessment and Finding 5/9/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

24732 10 Butler 38 256 Greece City Bridge Combined Field Assessment and Finding 5/9/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

24830 10 Butler 3017 251 Myoma Bridge #1 Field Assessment and Finding, Above-Ground 2/2/2012Determination of Effects: Above-Ground Field Assessment and Finding Jonathan Daily

24830 10 Butler 3017 251 Myoma Bridge #1 Early Notification/Scoping Results 1/25/2012Early Coordination: Notification to the SHPO Susanne M. Haney

24830 10 Butler 3017 251 Myoma Bridge #1 Tribal Consultation- Inital Notification 1/25/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

24830 10 Butler 3017 251 Myoma Bridge #1 Deferral of Archaeological Testing 2/1/2012Special Processes: Deferral of Archaeological Testing 2/22/2012 Susanne M. Haney

24861 10 Butler 7212 BR T-300 Graham Bridge Field Assessments and Finding 3/13/2012Determination of Effects: Above-Ground Field Assessment and Finding Jonathan Daily

24861 10 Butler 7212 BR T-300 Graham Bridge Field Assessments and Finding 3/13/2012Determination of Effects: Archaeology Field Assessment and Finding Jonathan Daily

24862 10 Butler 7217 BR T-325 Eidenau Bridge Combined Field Assessments and Finding 6/27/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

24862 10 Butler 7217 BR T-325 Eidenau Bridge Combined Field Assessments and Finding 6/27/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

83305 10 Butler 8 253 Harrisville Bridge Combined Field Assessments and Finding 6/22/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

83305 10 Butler 8 253 Harrisville Bridge Combined Field Assessments and Finding 6/22/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

90206 10 Butler 68 254 Muntz Run Bridge Combined Field Assessments and Finding 3/20/2012Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

90206 10 Butler 68 254 Muntz Run Bridge Combined Field Assessments and Finding 3/20/2012Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

90206 10 Butler 68 254 Muntz Run Bridge Tribal Consultation Follow Up Informaiton 3/26/2012Determination of Effects: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

90206 10 Butler 68 254 Muntz Run Bridge Tribal Consultation-Inital Notification Form 1/5/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

90206 10 Butler 68 254 Muntz Run Bridge Tribal Consultation Follow Up Information 3/15/2012Public Involvement: Tribal Consultation Coordination Susanne M. Haney

90206 10 Butler 68 254 Muntz Run Bridge Early Notification/Scoping Results Form 1/5/2012Scoping: Project Early Notification/ Scoping Results Susanne M. Haney

90206 10 Butler 68 254 Muntz Run Bridge Negative Survey Form Hard Copy 3/21/2012Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

25023 10 Clarion 7211 BR T-442 Wildcat Run Bridge Combined Field Assessemnts and Finding 12/20/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

25023 10 Clarion 7211 BR T-442 Wildcat Run Bridge Combined Field Assessemnts and Finding 12/20/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

25152 10 Clarion 208 352 South Shippenville Bridge Combined Field Assessments and Finding 7/8/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

25152 10 Clarion 208 352 South Shippenville Bridge Combined Field Assessments and Finding 7/8/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

25152 10 Clarion 208 352 South Shippenville Bridge Tribal Consultation Follow Up Notification 7/11/2011Determination of Effects: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

25152 10 Clarion 208 352 South Shippenville Bridge Combined Field Assessments and Finding 7/8/2011Identification: Phase I Archaeological Survey Susanne M. Haney

25152 10 Clarion 208 352 South Shippenville Bridge Tribal Consultation Follow Up Notification 7/11/2011Identification: Phase I Archaeological Survey Susanne M. Haney

25152 10 Clarion 208 352 South Shippenville Bridge Phase I Report Hard Copy 11/4/2011Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

46995 10 Indiana 7218 BR T-562 Dixon Run Bridge Combined Field Assessments and Finding 6/22/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

46995 10 Indiana 7218 BR T-562 Dixon Run Bridge Combined Field Assessments and Finding 6/22/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

46995 10 Indiana 7218 BR T-562 Dixon Run Bridge Tribal Consultation Follow Up Information Form 6/23/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

46995 10 Indiana 7218 BR T-562 Dixon Run Bridge Negative Survey Form Hard Copy 6/22/2011Special Processes: Submittal of Archival Paper Copy 6/27/2011 Susanne M. Haney

75924 10 Indiana 56 453South Brush Valley Bridge Replacement Combined Field Assesments and Finding 7/11/2011

Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

75924 10 Indiana 56 453South Brush Valley Bridge Replacement Combined Field Assesments and Finding 7/11/2011

Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

75924 10 Indiana 56 453South Brush Valley Bridge Replacement Tribal Consultation Follow Up Notification 7/11/2011

Determination of Effects: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

75924 10 Indiana 56 453South Brush Valley Bridge Replacement Combined Field Assesments and Finding 7/11/2011

Identification: Phase I Archaeological Survey Susanne M. Haney

75924 10 Indiana 56 453South Brush Valley Bridge Replacement Phase I Archaeology Report Hard Copy 11/4/2011

Special Processes: Submittal of Archival Paper Copy Susanne M. Haney

89918 10 Indiana 403 454 Cramer Bridge #4 Combined Field Assessments and Finding 5/1/2012Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

89918 10 Indiana 403 454 Cramer Bridge #4 Combined Field Assessments and Finding 5/1/2012Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

92374 10 Indiana 286 0 Indiana Econ. Dev. Phase1Transportation Enhancement, Field Assessment and Finding 2/2/2012 BHP Enhancement: Field Concurrence Jonathan Daily

92374 10 Indiana 286 0 Indiana Econ. Dev. Phase1Transportation Enhancement, Field Assessment and Finding 2/2/2012

Determination of Effects: Effect Determination Jonathan Daily

26019 10 Jefferson 3007 130 Summerville Bridge No. 1 Tribal Consultation Follow Up Information 3/21/2012Public Involvement: Consulting Party Coordination Susanne M. Haney

26019 10 Jefferson 3007 130 Summerville Bridge No. 1 Tribal Conslutation Inital Notification 11/15/2011Public Involvement: Tribal Consultation Coordination Susanne M. Haney

26019 10 Jefferson 3007 130 Summerville Bridge No. 1 Early Notification/Scoping Results Form 11/15/2011Scoping: Project Early Notification/ Scoping Results Susanne M. Haney

26072 10 Jefferson 949 552 Mill Creek Bridge #5 Combined Field Assessments and Findings 2/29/2012Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

26072 10 Jefferson 949 552 Mill Creek Bridge #5 Combined Field Assessments and Findings 2/29/2012Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

26143 10 Jefferson 551 Sawmill Run Bridge Above Ground Findings 6/14/2011Determination of Effects: Above-Ground Field Assessment and Finding Jonathan Daily

26143 10 Jefferson 551 Sawmill Run Bridge Archaeology Field Assessment and Finding 6/8/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

26143 10 Jefferson 551 Sawmill Run Bridge HRSF for PHMC committee review 5/11/2011Identification: Historic Resource Determination of Eligibility 5/26/2011 5/26/2011 Jonathan Daily

74325 10 Jefferson 3003 551 SR 3003 Langville Bridge Combined Field Assessments and Finding Form 5/31/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

74325 10 Jefferson 3003 551 SR 3003 Langville Bridge Combined Field Assessments and Finding Form 5/31/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

74325 10 Jefferson 3003 551 SR 3003 Langville Bridge Combined Field Assessments and Finding Form 5/31/2011Early Coordination: Geomorphological Testing Susanne M. Haney

74325 10 Jefferson 3003 551 SR 3003 Langville Bridge Hard Copy of Geomorphology Report 6/22/2011Special Processes: Submittal of Archival Paper Copy 6/27/2011 Susanne M. Haney

83298 10 Jefferson 830 552 Rockdale Bridge Early Notificiation 4/24/2012Scoping: Project Early Notification/ Scoping Results Susanne M. Haney

84830 10 Jefferson 1009 551 SR 1009 Kyle Run Combined Finding Form 10/14/2011Determination of Effects: Above-Ground Field Assessment and Finding Jonathan Daily

84830 10 Jefferson 1009 551 SR 1009 Kyle Run Combined Finding Form 10/14/2011Determination of Effects: Archaeology Field Assessment and Finding Jonathan Daily

84830 10 Jefferson 1009 551 SR 1009 Kyle Run Tribal Consultation Follow Up Notification 11/29/2011Identification: Phase I Archaeological Survey Susanne M. Haney

84830 10 Jefferson 1009 551 SR 1009 Kyle Run Tribal Consultation-Initial Notification 9/29/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Susanne M. Haney

84830 10 Jefferson 1009 551 SR 1009 Kyle Run Tribal Consultation Follow Up Notification 11/29/2011Public Involvement: Tribal Consultation Coordination Susanne M. Haney

84830 10 Jefferson 1009 551 SR 1009 Kyle Run Early Notification/Scoping Results Form 9/26/2011Scoping: Project Early Notification/ Scoping Results 9/28/2011 Susanne M. Haney

84830 10 Jefferson 1009 551 SR 1009 Kyle Run Negative Survey From Hard Copy 11/18/2011Special Processes: Submittal of Archival Paper Copy 11/18/2011 Susanne M. Haney

87571 10 Jefferson 310 0 Harmony Bridges 1 & 2 Combined Field Assesments and Finding 7/14/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

87571 10 Jefferson 310 0 Harmony Bridges 1 & 2 Combined Field Assesments and Finding 7/14/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

90503 10 Jefferson 3011 570 SR 3011 Railroad Overpass Removal Above-Ground Findings 3/22/2012Determination of Effects: Above-Ground Field Assessment and Finding Jonathan Daily

90583 10 Jefferson 28 516 Fremer Hill Cut Combined Field Assessments and Finding 8/8/2011Determination of Effects: Above-Ground Field Assessment and Finding Susanne M. Haney

90583 10 Jefferson 28 516 Fremer Hill Cut Combined Field Assessments and Finding 8/8/2011Determination of Effects: Archaeology Field Assessment and Finding Susanne M. Haney

26971 11 Allegheny 8 A12 Butler Street Bridge Above Ground Field Assessment and Finding 10/4/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

26971 11 Allegheny 8 A12 Butler Street Bridge Archaeological Field Assessment & Finding 10/19/2011Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

27134 11 Allegheny 7301 LOC South Highland Avenue Bridge Project Scope Additions 12/6/2011Determination of Effects: Effect Determination - non-form 12/28/2011 David Anthony

27134 11 Allegheny 7301 LOC South Highland Avenue BridgePost Agreement Coordination: Interpretive Panel Layout 1/31/2012

Resolution of Adverse Effects: Standard Treatment 2/15/2012 David Anthony

27179 11 Allegheny 28 A09 & A10 East Ohio Street NPDES Permit Modification 4/16/2012Determination of Effects: Effect Determination - non-form David Anthony

27179 11 Allegheny 28 A09 & A10 East Ohio StreetPost Agreement Coordination: Historic Structures Recordations 11/1/2011

Mitigation: MOA/PA Commitment Coordination 11/28/2011 David Anthony

27179 11 Allegheny 28 A09 & A10 East Ohio Street Outfall location clearance letter 3/7/2012Mitigation: MOA/PA Commitment Coordination 3/19/2012 Joe Verbka

27292 11 Allegheny 1028 A10 Culmerville Road over B&LE RR Determination of EligibilityIdentification: Historic Resource Determination of Eligibility David Anthony

27300 11 Allegheny 7301 LOCWest Ohio Street / Ridge Avenue Bridges Determination of Effect 11/16/2011

Determination of Effects: Above-Ground Field Assessment and Finding 12/14/2011 David Anthony

27300 11 Allegheny 7301 LOCWest Ohio Street / Ridge Avenue Bridges Draft Assessment of Effect Report 10/13/2011

Determination of Effects: Effect Determination David Anthony

27300 11 Allegheny 7301 LOCWest Ohio Street / Ridge Avenue Bridges Eligibility Clarification 9/27/2011

Identification: Historic Resource Determination of Eligibility 10/26/2011 David Anthony

27300 11 Allegheny 7301 LOCWest Ohio Street / Ridge Avenue Bridges Public Meeting Information 06/14/2011 6/15/2011

Public Involvement: Consulting Party Coordination David Anthony

27300 11 Allegheny 7301 LOCWest Ohio Street / Ridge Avenue Bridges

Public Meeting and Meeting Minutes Summary 06/14/2011 8/25/2011

Public Involvement: Consulting Party Coordination David Anthony

27300 11 Allegheny 7301 LOCWest Ohio Street / Ridge Avenue Bridges Draft Assessment of Effect Report 10/13/2011

Public Involvement: Consulting Party Coordination David Anthony

27300 11 Allegheny 7301 LOCWest Ohio Street / Ridge Avenue Bridges Consulting Party Meeting #3 Presentation 10/18/2011

Public Involvement: Consulting Party Coordination David Anthony

27300 11 Allegheny 7301 LOCWest Ohio Street / Ridge Avenue Bridges Determination of Effect Responses 12/21/2011

Public Involvement: Consulting Party Coordination David Anthony

27300 11 Allegheny 7301 LOCWest Ohio Street / Ridge Avenue Bridges

Determination of Effect Responses to Consulting Parties 2/23/2012

Public Involvement: Consulting Party Coordination David Anthony

27300 11 Allegheny 7301 LOCWest Ohio Street / Ridge Avenue Bridges Consulting Party Meeting #4 Minutes 4/4/2012

Public Involvement: Consulting Party Coordination David Anthony

27907 11 Allegheny 885 A35Leabanon Road Bridge over Union RR Above Ground Field Assessment and Finding 11/1/2011

Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

27907 11 Allegheny 885 A35Leabanon Road Bridge over Union RR Above Ground Field Assessment and Finding 4/6/2012

Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

27907 11 Allegheny 885 A35Leabanon Road Bridge over Union RR Archaeological Field Assessment & Finding 11/10/2011

Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

28258 11 Allegheny 7301 LOC Greenfield Avenue Bridge Above Ground Field Assessment and Finding 8/23/2011Determination of Effects: Above-Ground Field Assessment and Finding 9/21/2011 David Anthony

28258 11 Allegheny 7301 LOC Greenfield Avenue Bridge Above Ground Field Assessment and Finding 1/10/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

28258 11 Allegheny 7301 LOC Greenfield Avenue Bridge Archaeological Field Assessment & Finding 2/15/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

28258 11 Allegheny 7301 LOC Greenfield Avenue Bridge Above Ground Field Assessment and Finding 8/23/2011 Identification: Historic Resource Survey 9/21/2011 David Anthony

47019 11 Allegheny 19 A62 19/Connor - Cochran Above Ground Field Assessment and Finding 4/24/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

47019 11 Allegheny 19 A62 19/Connor - Cochran Archaeological Field Assessment & Finding 5/1/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

50958 11 Allegheny 376 A35 Squirrel Hill Tunnel Rehabiliation Squirrel Hill Tunnel Effect Finding Restatement 5/24/2011Determination of Effects: Effect Determination 5/26/2011 David Anthony

74153 11 Allegheny 3069 A14 Liberty Tunnel Rehab Ph 4 Determination of Effect 1/31/2012Determination of Effects: Above-Ground Field Assessment and Finding 2/15/2012 David Anthony

74153 11 Allegheny 3069 A14 Liberty Tunnel Rehab Ph 4 Archaeology Field Assessment & Finding 2/1/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

74153 11 Allegheny 3069 A14 Liberty Tunnel Rehab Ph 4 Determination of Effect 1/31/2012Determination of Effects: Effect Determination 2/15/2012 David Anthony

74153 11 Allegheny 3069 A14 Liberty Tunnel Rehab Ph 4 Determination of Eligibility 10/27/2011Identification: Historic Resource Determination of Eligibility 11/22/2011 David Anthony

78177 11 Allegheny 51 A75 SR 51 ov Montour Run Determination of Effect 6/22/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

78177 11 Allegheny 51 A75 SR 51 ov Montour Run Determination of Effect 6/22/2011Determination of Effects: Archaeology Field Assessment and Finding David Anthony

80025 11 Allegheny 7415 LOC CC06 Chartiers Creek Br#6 Above Ground Field Assessment and Finding 9/9/2011Determination of Effects: Above-Ground Field Assessment and Finding 9/30/2011 David Anthony

80025 11 Allegheny 7415 LOC CC06 Chartiers Creek Br#6 Archaeological Field Assessment & Finding 11/10/2011Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

80172 11 Allegheny 0 LOC GrandView Scenic Byway Above Ground Field Assessment and Finding 1/10/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

80172 11 Allegheny 0 LOC GrandView Scenic Byway Archaeology Finding Form 1/12/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

87785 11 Allegheny 376 A47 I376/Commercial St Bridge Above Ground Field Assessment and Finding 5/20/2011Determination of Effects: Above-Ground Field Assessment and Finding 5/24/2011 David Anthony

87785 11 Allegheny 376 A47 I376/Commercial St Bridge SR 376, A47 Commercial Street Rehabiliation 6/8/2011Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

88476 11 Allegheny 19 LOC 19/Cochran_Beverly Signal Above Ground Field Assessment and Finding 2/15/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

88476 11 Allegheny 19 LOC 19/Cochran_Beverly Signal Archaeological Field Assessment & Finding 2/15/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

92362 11 Allegheny 8 A55 PCTI-SR8/ Ewalt & Cook Rd Above Ground Field Assessment and Finding 10/3/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

92362 11 Allegheny 8 A55 PCTI-SR8/ Ewalt & Cook Rd Archaeology field assessment & finding 9/26/2011Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

92532 11 Allegheny 2065 A07 Thompson Run Rd Landslide Above Ground Field Assessment and Finding 3/20/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

92532 11 Allegheny 2065 A07 Thompson Run Rd Landslide Archaeological Field Assessment & Finding 3/26/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

93417 11 Allegheny 2001 0 Bunola River Road slide Above Ground Field Assessment and Finding 3/20/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

93417 11 Allegheny 2001 0 Bunola River Road slide Archaeological Field Assessment & Finding 3/26/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

93431 11 Allegheny 4063 A06 Pearce Mill Road-1 Above Ground Field Assessment and Finding 3/21/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

93431 11 Allegheny 4063 A06 Pearce Mill Road-1 Archaeological Field Assessment & Finding 3/26/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

94507 11 Allegheny NULL LOC Carrie Furnace Connector Project Early Notification 2/24/2012Early Coordination: Notification to the SHPO 2/6/2012 David Anthony

94507 11 Allegheny NULL LOC Carrie Furnace Connector Project Early Notification 2/24/2012Identification: Consulting Party/Tribal Consultation Coordination 2/6/2012 David Anthony

94885 11 Allegheny 79 0 I79 SB over Clever Road Landslide Above Ground Field Assessment and Finding 3/29/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

94885 11 Allegheny 79 0 I79 SB over Clever Road Landslide Archaeological Field Assessment & Finding 4/5/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

29138 11 Beaver 1032 B02 New York Avenue Above Ground Field Assessment and Finding 6/28/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

29138 11 Beaver 1032 B02 New York Avenue Archaeological Finding form 6/28/2011Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

93060 11 Beaver 151 B05 151/Laurel Road Slide Above Ground Field Assessment and Finding 3/15/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

93060 11 Beaver 151 B05 151/Laurel Road Slide Archaeological Field Assessment & Finding 3/15/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

29278 11 Lawrence 7301 LOC North Street Bridge #5 Above Ground Field Assessment and Finding 4/24/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

29278 11 Lawrence 7301 LOC North Street Bridge #5 Archaeological Field Assessment & Finding 4/24/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

29467 11 Lawrence 224 L05 Edinburg Overpass Bridge Project Archaeological waste area clearance letter 4/23/2012 NULL Joe Verbka

57111 11 Lawrence 7206 LOC Wampum Road Bridge No.1 Above Ground Field Assessment and Finding 3/20/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

57111 11 Lawrence 7206 LOC Wampum Road Bridge No.1 Archaeological Field Assessment & Finding 3/20/2012Determination of Effects: Archaeology Field Assessment and Finding Joe Verbka

57113 11 Lawrence 7206 LOC Wampum Bridge No.2Post Agreement Coordination: Historic Structures Recordation 4/9/2012

Mitigation: MOA/PA Commitment Coordination David Anthony

57113 11 Lawrence 7206 LOC Wampum Bridge No.2 LOA-DRAFT 5/5/2011Resolution of Adverse Effects: Letter of Agreement Kara Russell

57113 11 Lawrence 7206 LOC Wampum Bridge No.2 LOA-Final for execution 6/21/2011Resolution of Adverse Effects: Letter of Agreement 6/27/2011 Kara Russell

57113 11 Lawrence 7206 LOC Wampum Bridge No.2 Executed Letter of Agreement 7/12/2011 Resolution of Adverse Effects: MOA/PA David Anthony

66961 11 Lawrence 7301 LOC Mill Street Bridge Replacement Above Ground Field Assessment and Finding 2/14/2012Determination of Effects: Above-Ground Field Assessment and Finding 3/16/2012 David Anthony

29839 12 Fayette 7206 BR Weaver Mill #95Combined Finding- Archaeology and Architectural History 5/2/2012

Determination of Effects: Above-Ground Field Assessment and Finding Ryan Rowles

29839 12 Fayette 7206 BR Weaver Mill #95Combined Finding- Archaeology and Architectural History 5/2/2012

Determination of Effects: Archaeology Field Assessment and Finding Ryan Rowles

75056 12 Fayette 40 10B US 40/PA 381 IntersectionConsulting Party Letter from the National Road Heritage Corridor 6/30/2011

Public Involvement: Consulting Party Coordination Ryan Rowles

75056 12 Fayette 40 10B US 40/PA 381 Intersection Project Early Notification-Scoping Results Form 6/29/2011Scoping: Project Early Notification/ Scoping Results Ryan Rowles

93246 12 Fayette LH: Falls Visitors CenterCombined Finding- Archaeology and Architectural History 10/12/2011

Determination of Effects: Above-Ground Field Assessment and Finding 10/26/2011 Ryan Rowles

93246 12 Fayette LH: Falls Visitors CenterCombined Finding- Archaeology and Architectural History 10/12/2011

Determination of Effects: Archaeology Field Assessment and Finding 10/26/2011 Ryan Rowles

93246 12 Fayette LH: Falls Visitors CenterInitial Tribal Notification- Absentee-Shawnee Tribe of Oklahoma 9/27/2011

Identification: Consulting Party/Tribal Consultation Coordination Ryan Rowles

93246 12 Fayette LH: Falls Visitors CenterInitial Tribal Notification- Eastern Shawnee Tribe of Oklahoma 9/27/2011

Identification: Consulting Party/Tribal Consultation Coordination Ryan Rowles

93246 12 Fayette LH: Falls Visitors CenterInitial Tribal Notification- Seneca Nation of Indians 9/27/2011

Identification: Consulting Party/Tribal Consultation Coordination Ryan Rowles

93246 12 Fayette LH: Falls Visitors Center Initial Tribal Notification- Shawnee Tribe 9/27/2011Identification: Consulting Party/Tribal Consultation Coordination Ryan Rowles

93246 12 Fayette LH: Falls Visitors Center Initial Tribal Notification- Delaware Nation 9/30/2011Identification: Consulting Party/Tribal Consultation Coordination 10/6/2011 Ryan Rowles

93246 12 Fayette LH: Falls Visitors CenterInitial Tribal Notification- Seneca-Cayuga Tribe of Oklahoma

Identification: Consulting Party/Tribal Consultation Coordination Ryan Rowles

93246 12 Fayette LH: Falls Visitors CenterProject Information- Absentee-Shawnee Tribe of Oklahoma 10/13/2011

Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

93246 12 Fayette LH: Falls Visitors CenterProject Information- Eastern Shawnee Tribe of Oklahoma 10/13/2011

Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

93246 12 Fayette LH: Falls Visitors Center Project Information- Seneca Nation of Indians 10/13/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

93246 12 Fayette LH: Falls Visitors Center Project Information- Shawnee Tribe 10/13/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

93246 12 Fayette LH: Falls Visitors Center Project Information- Delaware Nation 10/18/2011Public Involvement: Consulting Party/Tribal Consultation Coordination 12/7/2011 Ryan Rowles

93246 12 Fayette LH: Falls Visitors CenterProject Information- Seneca-Cayuga Tribe of Oklahoma

Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

30170 12 Greene 18 X10 Browns Creek BridgeTribal Notifications of the Start of Bridge Construction 2/21/2012

Public Involvement: Tribal Consultation Coordination Ryan Rowles

30170 12 Greene 18 X10 Browns Creek BridgeTribal Notifications- Update of Bridge Construction Schedule 3/26/2012

Public Involvement: Tribal Consultation Coordination Ryan Rowles

76035 12 Greene 88 Q10 PA 0088 over Muddy Creek Above Ground Field Assessment and Finding 12/7/2011Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

76035 12 Greene 88 Q10 PA 0088 over Muddy Creek Archaeology Field Assessment and Finding 10/13/2011Determination of Effects: Archaeology Field Assessment and Finding 10/26/2011 Ryan Rowles

76035 12 Greene 88 Q10 PA 0088 over Muddy Creek Archaeology Field Assessment and Finding 10/13/2011Identification: Phase I Archaeological Survey 10/26/2011 Ryan Rowles

76035 12 Greene 88 Q10 PA 0088 over Muddy CreekProject Information- Absentee-Shawnee Tribe of Oklahoma 10/21/2011

Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

76035 12 Greene 88 Q10 PA 0088 over Muddy CreekProject Information- Eastern Shawnee Tribe of Oklahoma 10/21/2011

Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

76035 12 Greene 88 Q10 PA 0088 over Muddy Creek Project Information- Shawnee Tribe 10/21/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

76035 12 Greene 88 Q10 PA 0088 over Muddy Creek Project Information- Seneca Nation of Indians 10/21/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

76035 12 Greene 88 Q10 PA 0088 over Muddy Creek Project Information- Delaware Nation 10/24/2011Public Involvement: Consulting Party/Tribal Consultation Coordination 12/17/2011 Ryan Rowles

76035 12 Greene 88 Q10 PA 0088 over Muddy CreekProject Information- Seneca-Cayuga Tribe of Oklahoma

Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

84234 12 Greene 21 10D Bailey's CrossroadsCombined Finding- Archaeology and Architectural History 1/12/2012

Determination of Effects: Above-Ground Field Assessment and Finding Ryan Rowles

84234 12 Greene 21 10D Bailey's CrossroadsCombined Finding- Archaeology and Architectural History 1/12/2012

Determination of Effects: Archaeology Field Assessment and Finding Ryan Rowles

84234 12 Greene 21 10D Bailey's CrossroadsProject Information- Absentee-Shawnee Tribe of Oklahoma 1/12/2012

Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

84234 12 Greene 21 10D Bailey's CrossroadsProject Information- Eastern Shawnee Tribe of Oklahoma 1/12/2012

Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

84234 12 Greene 21 10D Bailey's Crossroads Project Information- Seneca Nation of Indians 1/12/2012Public Involvement: Tribal Consultation Coordination Ryan Rowles

84234 12 Greene 21 10D Bailey's Crossroads Project Information- Shawnee Tribe 1/12/2012Public Involvement: Tribal Consultation Coordination Ryan Rowles

84234 12 Greene 21 10D Bailey's Crossroads Project Information- Delaware Nation 1/17/2012Public Involvement: Tribal Consultation Coordination 2/23/2012 Ryan Rowles

84234 12 Greene 21 10D Bailey's CrossroadsProject Information- Seneca-Cayuga Tribe of Oklahoma 1/17/2012

Public Involvement: Tribal Consultation Coordination Ryan Rowles

30949 12 Washington 519 138 SR 0519/SR 1055 IntersectionConcurrence and DOE from SHPO on Arch Finding 5/17/2011

Determination of Effects: Effect Determination 5/17/2011 Ryan Rowles

30949 12 Washington 519 138 SR 0519/SR 1055 IntersectionProject Information- Response from Seneca Nation of Indians 5/6/2011

Public Involvement: Consulting Party/Tribal Consultation Coordination 5/6/2011 Ryan Rowles

30949 12 Washington 519 138 SR 0519/SR 1055 IntersectionProject Information- Response from Delaware Nation 5/16/2011

Public Involvement: Consulting Party/Tribal Consultation Coordination 5/11/2011 Ryan Rowles

30995 12 Washington C-61 Chartiers Creek #61Combined Finding- Archaeology and Architectural History 4/12/2012

Determination of Effects: Above-Ground Field Assessment and Finding Ryan Rowles

30995 12 Washington C-61 Chartiers Creek #61Combined Finding- Archaeology and Architectural History 4/12/2012

Determination of Effects: Archaeology Field Assessment and Finding Ryan Rowles

31067 12 Washington 136 136 Ginger Hill IntersectionCombined Finding- Archaeology and Architectural History 3/16/2012

Determination of Effects: Above-Ground Field Assessment and Finding Ryan Rowles

31067 12 Washington 136 136 Ginger Hill IntersectionCombined Finding- Archaeology and Architectural History 3/16/2012

Determination of Effects: Archaeology Field Assessment and Finding Ryan Rowles

31194 12 Washington 980 139 SR. 0980 Approach to SR. 0050 Project Early Notification 3/15/2012Early Coordination: Advance Notification to SHPO David Anthony

31194 12 Washington 980 139 SR. 0980 Approach to SR. 0050Geomorphology Report for Initial Tribal Notification 4/9/2012

Public Involvement: Tribal Consultation Coordination Ryan Rowles

47022 12 Washington 70 10JI-70 over SR. 481 Bridge Replacement

Combined Finding- Archaeology and Architectural History 3/30/2012

Determination of Effects: Above-Ground Field Assessment and Finding Ryan Rowles

47022 12 Washington 70 10JI-70 over SR. 481 Bridge Replacement

Combined Finding- Archaeology and Architectural History 3/30/2012

Determination of Effects: Archaeology Field Assessment and Finding Ryan Rowles

47022 12 Washington 70 10JI-70 over SR. 481 Bridge Replacement

Geomorphology Report for Initial Tribal Notification 3/9/2012

Public Involvement: Tribal Consultation Coordination 3/16/2012 Ryan Rowles

63590 12 Washington 1010 AHT Bebout Road Pedestrian BridgeConsultation with SHPO as per Section 2.F of MOA 5/5/2011

Mitigation: MOA/PA Commitment Coordination Ryan Rowles

63590 12 Washington 1010 AHT Bebout Road Pedestrian Bridge Concurrence from SHPO on Section 2.F of MOA 6/8/2011Mitigation: MOA/PA Commitment Coordination 6/8/2011 Ryan Rowles

70047 12 Washington 70 21H Bentleyville Interchange Above Ground Field Assessment and Finding 3/12/2012Determination of Effects: Above-Ground Field Assessment and Finding David Anthony

70047 12 Washington 70 21H Bentleyville Interchange Project Early Notification (repost) 7/5/2011Early Coordination: Advance Notification to SHPO David Anthony

70047 12 Washington 70 21H Bentleyville InterchangeConsulting Party Request Letter- Charleroi Area Historic Society 6/27/2011

Public Involvement: Consulting Party Coordination Ryan Rowles

70047 12 Washington 70 21H Bentleyville Interchange Correspondence- Charleroi Area Historic Society 6/27/2011Public Involvement: Consulting Party Coordination Ryan Rowles

70047 12 Washington 70 21H Bentleyville InterchangeAugust Correspondence- Charleroi Area Historic Society 8/18/2011

Public Involvement: Consulting Party Coordination 8/18/2011 Ryan Rowles

70047 12 Washington 70 21H Bentleyville Interchange Project Information- Delaware Nation 6/22/2011Public Involvement: Consulting Party/Tribal Consultation Coordination Ryan Rowles

70047 12 Washington 70 21H Bentleyville InterchangeProject Information- Response from Delaware Nation 8/15/2011

Public Involvement: Consulting Party/Tribal Consultation Coordination 8/10/2011 Ryan Rowles

70047 12 Washington 70 21H Bentleyville Interchange Project Early Notification (repost) 7/5/2011Public Involvement: Early Coordination/Advance Notification David Anthony

70047 12 Washington 70 21H Bentleyville Interchange Deferral of Archaeological Testing 6/13/2011Special Processes: Deferral of Archaeological Testing Ryan Rowles

75950 12 Washington 70 W31 South Junction to SR 519 Project Early Notification 3/15/2012Early Coordination: Notification to the SHPO David Anthony

87236 12 Washington 70 T20 I70: I79N to SR 136 IntchCombined Finding- Archaeology and Architectural History 9/16/2011

Determination of Effects: Above-Ground Field Assessment and Finding Ryan Rowles

87236 12 Washington 70 T20 I70: I79N to SR 136 IntchREVISED Combined Finding- Archaeology and Architectural History 10/3/2011

Determination of Effects: Above-Ground Field Assessment and Finding Ryan Rowles

87236 12 Washington 70 T20 I70: I79N to SR 136 IntchCombined Finding- Archaeology and Architectural History 9/16/2011

Determination of Effects: Archaeology Field Assessment and Finding Ryan Rowles

87236 12 Washington 70 T20 I70: I79N to SR 136 IntchREVISED Combined Finding- Archaeology and Architectural History 10/3/2011

Determination of Effects: Archaeology Field Assessment and Finding Ryan Rowles

31550 12 Westmoreland 4019 C11 Bridge over Conrail Concurrence from SHPO on LOA 5/16/2011Resolution of Adverse Effects: Letter of Agreement 5/16/2011 Ryan Rowles

31550 12 Westmoreland 4019 C11 Bridge over Conrail FINAL- FHWA Signed LOA 5/27/2011Resolution of Adverse Effects: Letter of Agreement 6/7/2011 Ryan Rowles

31550 12 Westmoreland 4019 C11 Bridge over Conrail LOA 5/6/2011Resolution of Adverse Effects: Letter of Agreement 5/16/2011 Kara Russell

32032 12 Westmoreland 70 Q10 New Stanton InterchangeProject Map and Design for Initial Tribal Notifications 3/7/2012

Public Involvement: Tribal Consultation Coordination Ryan Rowles

32079 12 Westmoreland 119 A02 SR 119/SR 819 Interchange Phase I-II Archaeological Survey Report 8/15/2011Determination of Effects: Effect Determination 9/1/2011 Ryan Rowles

32079 12 Westmoreland 119 A02 SR 119/SR 819 Interchange Phase I-II Archaeological Survey Report 8/15/2011Identification: Phase I & II Archaeological Evaluation 9/1/2011 Ryan Rowles

32079 12 Westmoreland 119 A02 SR 119/SR 819 Interchange Mitigation Letter for Commitments 1 and 2 12/15/2011Mitigation: MOA/PA Commitment Coordination 1/10/2012 Ryan Rowles

32079 12 Westmoreland 119 A02 SR 119/SR 819 Interchange Mitigation Letter for Commitment 3 12/30/2011Mitigation: MOA/PA Commitment Coordination 1/10/2012 Ryan Rowles

32079 12 Westmoreland 119 A02 SR 119/SR 819 Interchange PHMC Marker Relocation Coordination 11/4/2011Public Involvement: Consulting Party Coordination Ryan Rowles

79420 12 Westmoreland 2027 A10 Ninemile Run BridgeCombined Finding- Archaeology and Architectural History 4/4/2012

Determination of Effects: Above-Ground Field Assessment and Finding Ryan Rowles

79420 12 Westmoreland 2027 A10 Ninemile Run BridgeCombined Finding- Archaeology and Architectural History 4/4/2012

Determination of Effects: Archaeology Field Assessment and Finding Ryan Rowles

94

Appendix D SHPO Disagreements/Objections

MPMS District County SR Section Project Posting ReceivedDate PHMCObjectionsHo w Ob jec t io n was A d d res s ed

80101 6 Chester 52 JWJ SR 0052 RoundaboutAmos Harry/Eusebius Barnard House Additional

Information12/07/11 12/16/2011

PennDOT made a determination that the Amos/Eusebius Barnard

House is eligible for the NR. In the SHPO's opinon, the property is

not eligible. PennDOT accepted the SHPO's opinion.

15251 6 Delaware 352 US1 US 1/352 Interchange Black Horse Acres PHRS Form 10/17/11 11/7/2011PennDOT made a determination that Black Horse Acres Historic

District is eligible for the NR. In the SHPO's opinon, the historic

district is not eligible. PennDOT accepted the SHPO's opinion.

64798 6 Montgomery 7412 NNA N Narberth Ave O/AMTRAKNarberth Southside Residential Historic District PHRS

Form

07/21/11 8/5/2011

PennDOT made a determination thaat the Narbeth Southside

Residential Historic District is eligible for the NR. In the SHPO's

opinion, the district is not eligible. PennDOT accepted the SHPO's

opinion.

26143 10 Jefferson 551 Sawmill Run Bridge HRSF for PHMC committee review 05/11/11 5/26/2011

PennDOT made a determination that the Star Iron Works is eligible

for the NR. In the SHPO's opinon, the property is not eligible.

PennDOT accepted the SHPO's opinion for the purposes of the

project.

19799 8 Lancaster 7213 BRGT-848 Conestoga Creek Road

BridgeDetermination of Effect Report 10/19/11 10/22/2011

The Conestoga Creek Road Bridge is a 1869 girder bridge eligible

for the NR. The bridge was moved to its current location in 1920.

The Bow String Trusses are attached to the bridge as decorative

elements that were introduced in the 1950s. The trusses are one

of two extant examples in the country of Joseph Henszey's

patented design. The project will replace the bridge, but the

trusses will be relocated to a private party for reuse on another

bridge. PennDOT made a finding of No Adverse Effect. The SHPO

disagreed, stating that the relocation will have an adverse effect on

the bridge. The SHPO questioned whether the bridge was moved.

PennDOT provided additional information, whereupon the SHPO

agreed to a conditional No Adverse Effect, provided there is a

preservation covenent attached to the property transfer.

85656 8 Lancaster 741 17Intersection with SR 2035,

Belmont RoadCombined Field Assessment and Finding 06/06/11 6/17/2011

The Belmont School, an Amish schoolhouse, is a contributing

property to the Pequea South Rural Historic District. The

intersection improvement project involves the installation of a

flashing traffic beacon, lowering of the vertical curve a maximum

of 2.5 feet , cutting back the embankment on all four corners, and

set back of the Amish school fence 8 feet at the corner of the

intersection to accommodate sight distance deficiencies. PennDOT

made a finding of No Adverse Effect to which the SHPO objected.

In the SHPO's opinion, the "widening and lowering of the roadway

will affect the integrity of setting, feeling, and association of the

school to the surrounding district and its relationship to the road".

After the SHPO attended a field view and reviewed additional

information provided by PennDOT, the SHPO agreed to the finding

of No Adverse Effect.

23057 9 Somerset 7206 353Maust Bridge (Co. Bridge 21) over

Casselman RiverFeasibility Study Review 10/27/11 11/1/2011

PennDOT prepared a report on the feasibility of rehabilitating the

Maust Bridge and the evaluation of other alternatives. The SHPO

raised several concerns regarding the purpose and need for the

project and the fact that Somerset County, the owner of the bridge,

does not want to maintain the historic structure.

23057 9 Somerset 7206 353

Maust Bridge (Co. Bridge 21) over

Casselman River Responses to PHMC comments on Feasibiity Report 3/14/2012 4/13/2012

The SHPO continues to express concerns with the feasibiity

analysis. Consultation in ongoing.

96

Appendix E Concerns of the Public and Consulting Parties

District 6-0 Consulting

Party Concerns for

Historic Structures (Information provided by CRP)

Project County SR Sec MPMS Source of and Question Resolution

Rickert Road Bridge Bucks 7009 21 13296

The consulting parties (CP) disagree with the conclusion of

the bridge feasibility report, which states that the bridge

cannot be rehabilitated.

District 6-0 will schedule a CP meeting to discuss their feedback and answer their questions about the

report.

Center Avenue Bridge

RehabilitationBucks 93439

Some of the Consulting Parties object to the proposed stone

arch bridge rehabilitation. They are requesting an additional

meeting with the district.

The District is committed to holding a consutling party meeting, but a date has not been set. The project

was supposed to be let with several other bridges in a package but had to be pulled because the District

did not want to delay the other bridges that were in the package. PennDOT and FHWA are also collecting

information to address concerns and questions raised at Mary Sue Boyle’s February 29, 2012 meeting

with her clients about the project. Her clients are also Consulting Parties for the project.

Fetter’s Mill Road Bridge Montgomery 7046 27 80052

A Consulting Party meeting was held to discuss feedback that

was received from the CPs regarding the bridge feasibility

report. The report recommends that the bridge will be

rehabilitated. The CPs agree with the report but they have

concerns with some of the proposed design work, e.g. a

concrete deck is proposed but they prefer the existing open

grate deck. 

The engineers will investigate the design issues that were discussed at the CP meeting. The designs will

be brought back to the CPs at a later date. Coordination with the CPs will be on-going.

Willits Road Bridge Philadelphia 1011 PWB 69909

PennDOT evaluated Pennypack Park and determined it was

not eligible. PHMC requested additional information. The

Philadelphia Parks & Recreation Department sent PennDOT

information about the Park and why they think it is eligible.

PHMC is reviewing the additional information from PennDOT and the CPs.

Other Consulting Party

Concerns Identified in

Project PATH

Pond Eddy Bridge Pike 1011 470 9329Concerns of the public and consulting parties on the

replacement bridge. Some consulting parties continue to

oppose the replacement of the Pond Eddy Bridge.

PennDOT formed a Design Advisory Committee (DAC) to work with the consulting parties on design

features for the new bridge. Three meetings were held with the DAC.

Cold Springs Bridge Replacement Lehigh 1027 01B 11590

The Whitehall Historic Preservation Society requested that a

sign be erected along the D & L Trail with a picture and

description of the historic bridge, and that the existing

plaques located on the bridge be incorporated into the new

plaque or donated to the Whitehall Historic Preservation

Society.

The first recommendation has been incorporated into a Letter of Agreement between FHWA, PennDOT

and the SHPO.

Meadowview Drive Bridge over

Bermudian Creek

York 4038 1 68800Historic Bridge Foundation expressed concerns that bridge

rehabilitation alternatives were not adequately evaluated in

the feasibility report.

A meeting with the consulting parties was held, during which concerns were addressed to their

satisfaction.

St. Mary's Covered Bridge Huntingdon SMB 92121

The Huntingdon County Historical Society expresses concern

about a vague statement in the project description that the

integrity of the bridge will be maintained "as much as

possible". Concerned with adherence to the Secretary of

Interior Standards for Historic Preservation.

All of the activities associated with the bridge rehabilitation have been listed in the Determination of

Effect finding. The SHPO has agreed with the No Adverse Effect finding.

Maust Bridge over Casselman

River

Somerset 7206 353 23057Consulting parties expressed a number of concerns about the

conclusions reached in the Bridge Feasibility Report that the

bridge cannot be rehabilitated.

Consultation is ongoing.

Oldham Bridge Project Somerset 7217 816 23358Historic Bridge Foundation questions the need to replace the

Oldham Bridge.Consultation is ongoing.

West Ohio St./Ridge Ave. Bridges Allegheny 7301 LOC 27300

Consulting parties expressed concerns with the

Determination of Effect report and the need for the

replacement bridge to be raised over Norfolk Southern

Railroad to accommodate railcar double-stacking at the order

of the PUC. Asked to look at other alternatives such as

lowering tracks. Other concerns with visual effect to

Allegheny Commons Park and effect to trees.

The SHPO has agreed that there is an unavoidable adverse effect to the Allegheny Commons Park and

the Pennsylvania Railroad Ft. Wayne Division. Even rehab of the contributing bridges would require

replcement of 70% of its members. A meeting was held with consulting parties and the PHMC to review

comments on the Effect report. In a follow-up action, FHWA will confirm the PUC Ordrer as it relates to

the need. Mitigation options were discussed.

Bentleyville Interchange Washington 70 21H 70047

The Charleroi Area Historical Society expressed concern that

a former church building is to be removed to construct a new

intersection.

The buildling, which now functions as a restaurant, was determned not eligible for the NR before this

project was programmed. The building has undergone extensive alteration during two different

episodes that included the building of two additions.