2021/05/26 Amount Item No Quantity Rate (EDDP 184/82) MAPANGULA PRIMARY SCHOOL SECTION 1 BILL NO. 1 PRELIMINARIES The JBCC Series 2000 Principal Building Agreement (JBCC Edition 4.1 March 2005 PBA and May 2005) prepared by the Joint Building Contracts Committee, shall be the agreement, amended as hereinafter described in the Notes. BUILDING AGREEMENT AND PRELIMINARIES The Preliminaries for use with the JBCC Series 2000 Principal Building Agreement (May 2005 edition) prepared by the Joint Building Contracts Committee, shall be deemed to be incorporated in these bills of quantities Contractors are referred to the above-mentioned documents for the full intent and meaning of each clause thereof These clauses are hereinafter referred to by clause number and heading only. Where standard clauses or alternatives are not entirely applicable to this contract such modifications, corrections or supplements as will apply are given under each relevant clause heading and such modifications, corrections or supplements shall take precedence notwithstanding anything contrary contained in the above-mentioned documents Where any item is not relevant to this specific contract such item is marked N/A, signifying "not applicable" Notwithstanding anything to the contrary contained in any of the contract documents including the Principal Building Agreement and the Preliminaries, the provision of the "Preliminaries" as hereinafter set forth shall prevail and shall take precedence -1- PRELIMINARIES Bill No. 1 Section No. 1 Carried Forward R

Upload: others

Post on 05-Dec-2021

15 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 1

BILL NO. 1

PRELIMINARIES

The JBCC Series 2000 Principal Building Agreement (JBCC Edition 4.1 March 2005 PBA and May 2005) prepared by the Joint Building Contracts Committee, shall be the agreement, amended as hereinafter described in the Notes.

BUILDING AGREEMENT AND PRELIMINARIES

The Preliminaries for use with the JBCC Series 2000 Principal Building Agreement (May 2005 edition) prepared by the Joint Building Contracts Committee, shall be deemed to be incorporated in these bills of quantities

Contractors are referred to the above-mentioned documents for the full intent and meaning of each clause thereof

These clauses are hereinafter referred to by clause number and heading only. Where standard clauses or alternatives are not entirely applicable to this contract such modifications, corrections or supplements as will apply are given under each relevant clause heading and such modifications, corrections or supplements shall take precedence notwithstanding anything contrary contained in the above-mentioned documents

Where any item is not relevant to this specific contract such item is marked N/A, signifying "not applicable"

Notwithstanding anything to the contrary contained in any of the contract documents including the Principal Building Agreement and the Preliminaries, the provision of the "Preliminaries" as hereinafter set forth shall prevail and shall take precedence

-1-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 2: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

The Model Preambles for Trades (1999 edition) as published by the Association of South African Quantity Surveyors shall be deemed to be incorporated in these bills of quantities and no claim arising from brevity of description of items fully described in the said Model Preambles for Trades will be entertained

PREAMBLES FOR TRADES

Supplementary preambles to the Model Preambles covering clauses of a general nature, clauses pertaining to specific materials and amendments to clauses in the Model Preambles are incorporated in these bills of quantities to satisfy the requirements of this project

The contractor's prices for all items throughout these bills of quantities must take account of and include for all of the obligations, requirements and specifications given in the Model Preambles and in any supplementary preambles

If Alternative A as set out in clause B10.3 hereinafter is to be used for the adjustment of the preliminaries each item priced is to be allocated to one or more of the three categories "F", "T" or "V" as the case may be below such item, where "F" denotes a fixed amount (amount not to be varied), "T" denotes an amount variable in proportion to time and "V" denotes an amount variable in proportion to value

GENERAL

SECTION A - PRINCIPAL BUILDING AGREEMENT

Item

Definitions and interpretation (clause 1)F:............................. V:............................ T:............................

1

Definitions (A1)

Item

Offer acceptance and performance (clause 2)F:............................. V:............................ T:............................

2

Objective and Preparation (A2 to A14)

-2-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 3: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

ItemDocuments (clause 3)F:............................. V:............................ T:............................

3

ItemDesign responsibility (clause 4)F:............................. V:............................ T:............................

4

ItemEmployer's agents (clause 5)F:............................. V:............................ T:............................

5

The principal agent shall:

- monitor and control progress and scheduling

- monitor all contract conditions, and

- coordinate the efforts of the employer's agents, the contractor and subcontractors

The powers conferred on the principal agent in terms of this clause and/or the exercising of these powers shall not be construed as removing or diminishing any of the obligations of the Contractor in terms of the Principal Building Agreement, whether financial, contractual or otherwise, nor shall the exercising of these powers create any privity of contract as between the Employer or his agents on the one part and the Contractor or subcontractors or suppliers on the other part

The principal agent reserves the right to attend and participate in all contractor/subcontractor's meetings, to invite other employer's agents to attend such meetings at his discretion and to converse and chair any such meetings if the contractor is derelict in his duty in arranging such meetings to the degree of frequency and comprehensiveness dictated in the opinion of the project manager by the circumstances and exigencies of the construction process

ItemSite representative (clause 6)F:............................. V:............................ T:............................

6

Item

Compliance with regulations (clause 7)F:............................. V:............................ T:............................

7

-3-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 4: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Item

Works risk (clause 8)

F:..................... V:............................ T:............................

8

ItemIndemnities (clause 9)F:............................. V:............................ T:............................

9

Item

Works insurances (clause 10)

F:............................. V:............................ T:............................

10

ItemLiability insurances (clause 11)F:............................. V:............................ T:............................

11

ItemEffecting insurance (clause 12)F:............................. V:............................ T:............................

12

N/ANO CLAUSE13

ItemSecurity (clause 14)F:............................. V:............................ T:............................

14

Item

Preparation for and execution of the works (clause 15)

F:............................. V:............................ T:............................

15

Execution (A15-A23)

ItemAccess to the works (clause 16)F:............................. V:............................ T:............................

16

ItemContract instructions (clause 17)F:............................. V:............................ T:............................

17

ItemSetting out of the works (clause 18)F:............................. V:............................ T:............................

18

The contractor shall notify the principal agent if any encroachments of adjoining foundations, buildings, structures, pavements, boundaries, etc exist in order that the necessary arrangements may be made for the rectification of any such encroachments

-4-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 5: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

ItemAssignment (clause 19)F:............................. V:............................ T:............................

19

The contractor shall not cede his rights or delegate his obligations in terms of this agreement unless specifically called for by the employer

Item

Nominated subcontractors (clause 20)F:............................. V:............................ T:............................

20

ItemSelected subcontractors (clause 21)F:............................. V:............................ T:............................

21

Written proof is required from subcontract tenderers at tendering that they can meet the JBCC Selected Subcontract Agreement or other tender agreements and provide security in terms of the agreement. If the above is not provided the tender may not be accepted

All amounts allowed under Provisional Amounts are intended to be awarded to Selected and Nominated Subcontractors

Item

Employer's Direct Contractors (clause 22)

F:............................. V:............................ T:............................

22

Item

Contractor's Domestic Sub-Contractors (Clause 23)

F:............................. V:............................ T:............................

23

ItemPractical completion (clause 24)F:............................. V:............................ T:............................

24

Completion (A24-A30)

ItemWorks completion (clause 25)F:............................. V:............................ T:............................

25

ItemFinal completion (clause 26)F:............................. V:............................ T:............................

26

-5-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 6: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Item

Latent defects liability period (clause 27)F:............................. V:............................ T:............................

27

ItemSectional completion (clause 28)F:............................. V:............................ T:............................

28

Item

Revision of date of practical completion (clause 29)F:............................. V:............................ T:............................

29

The removal and replacement of materials and/or workmanship that do not conform to specification or drawings shall not constitute grounds for an extension of the construction period nor for an adjustment to the contract sum (clause 29.3)

Item

Penalty for non-completion (clause 30)F:............................. V:............................ T:............................

30

Item

Interim payment to the contractor (clause 31)F:............................. V:............................ T:............................

31

Payment (A31 - A35)

Item

Adjustment to the contract value (clause 32)F:............................. V:............................ T:............................

32

Where prices are submitted by the contractor or nominated/selected subcontractors during the progress of the works in respect of contract instructions or in regard to a claim under the terms of the contract and notwithstanding the fact that such prices may be used in an interim payment certificate, there is to be no presumption of acceptance. Should the principal agent wish to accept any such prices prior to the issue of the final certificate, it will be in writing

Item

Recovery of expense and loss (clause 33)F:............................. V:............................ T:............................

33

-6-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 7: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Item

Final account and final payment (clause 34)F:............................. V:............................ T:............................

34

The employer shall not pay any interest on amounts payable to the contractor for one hundred and forty two (142) days after the date of issue of the certificate of practical completion

The employer shall, however, pay interest to the contractor at the rate stipulated in clause 34.11 on any amounts payable to the contractor more than one hundred and forty two (142) days after the date of issue of the certificate of practical completion but only for such period as the settlement of the final account is delayed by the non-performance of the principal agent or the employer or his agents. In evaluating non-performance for purposes of this clause a reasonable time shall be allowed to the employer or his agents to respond to any matter brought to his/their attention and which may affect the settlement of the final account

Item

Payment to other parties (clause 35)

F:............................. V:............................ T:............................

35

Item

Cancellation by employer - contractor's default (clause 36)F:............................. V:............................ T:............................

36

Cancellation (A36-A39)

Item

Cancellation by employer - loss and damage (clause 37)F:............................. V:............................ T:............................

37

Item

Cancellation by contractor - employer's default (clause 38)F:............................. V:............................ T:............................

38

Item

Cancellation - cessation of the works (clause 39)F:............................. V:............................ T:............................

39

-7-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 8: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Item

Dispute Settlement (clause 40)

F:............................. V:............................ T:............................

40

Dispute (A40)

Item

State clauses (Clause 41)

F:............................. V:............................ T:............................

41

Substitute Provisions (A41)

Information necessary for the completion of those clauses contained in the schedule which are necessary for tender purposes is given hereunder

Information necessary for completion of those clauses contained in the schedule which are necessary for tender purposes is given hereunder

THE SCHEDULE

Item

Pre-tender information (clause 42)

F:............................. V:............................ T:............................

42

-8-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 9: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

42.1.1Employer:

Independent Development Trust

Postal address:PO Box 55386Polokwane0700

Tel : (015) 295 0000Fax: (015) 295 6559

Physical Address:

22 Hans van Rensburg StreetPolokwane0700

42.1 CONTRACTING AND OTHER PARTIES

42.1.2 Principal Agent:

ZETHU CONSULTING SERVICES

Postal Address:Private Bag X9703Postnet Suite 90, Polokwane, 0700

Physical Address:Stand 56 Broederstroomdrift,Deerpark, Tzaneen

Tel 086 110 6521 Fax 086 605 7523Email [email protected]

-9-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 10: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

42.1.3 Architect: Phenomenal Architects

Postal Address: PO Box 68438Highveld0169

Physical Address:199 Doreen StreetColbyn

0083

Tel: 086 111 2431 Fax: 012 430 5291Email: [email protected]

42.1.4Quantity Surveyor:

ZETHU CONSULTING SERVICES

Postal Address:Private Bag X9703Postnet Suite 90, Polokwane, 0700

Physical Address:Stand 56 Broederstroomdrift,Deerpark, Tzaneen

Tel 086 110 6521 Fax 086 605 7523Email [email protected]

-10-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 11: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

42.1.5 Agents service: Civil and Structural Engineer

Consultant: AureconPostal Address:PO Box 3518Polokwane0699

Physical Address8 Watermelon StreetPlatinum Park, BendorPolokwane0699

Tel: 015 287 3802Fax: 086 604 2744Email: [email protected]

42.1.5 Agents service:

42.1.6Electrical Engineer: Estrisec (Pty) Ltd

Postal Address:

Physical Address5B Aanveil StreetTzaneen0850

Tel: 015 307 3250Fax: 086 537 9519Email: [email protected]

42.1.6 Agents service: Mechanical Engineer

N/A

-11-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 12: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

42.2.1 Works Description:

Additions and Renovations at Mapangula Primary School.

42.2 CONTRACT DETAILS

42.2.2 Site Description:

Ga Mashashane, Limpopo

29°10'56.28"E 23°51'36.36"S

42.2.3 Work or installations by direct contractors:

N/A

42.2.4 This agreement is for a government contract where there are specific options that are applicable to a State organ only

Yes

42.2.5 Date on which possession of the site is intended to be given:

To be confirmed

42.2.6 Period for the commencement of the works after the contractor takes possession of the site

10 days

42.2.7 For the works as a whole. Intended date of practical completion and the penalty per calendar day

9 months after contractual commencement date Date

Penalty Amount0,01c per R100 of Contract Amount per day

-12-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 13: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

42.2.8 For the works in sections: Intended date of practical completion and the penalty per calender day

Section 1N/A ........................................ Date

N/A ........................ Penalty Amount

42.2.9 The law applicable to this agreement shall be that of

South Africa (country)

42.3.1 Contract works insurance to be effected by:

Contractor:

For the Sum of R Contract Sum + 20%

With a deductible of - to be determined by thecontractor

42.3 INSURANCES

42.3.2 Supplementary insurance is requiredNo

42.3.3 Public liability insurance to be effected by:Contractor:

For the Sum of R10,000,000.00

With a deductible of - to be determined by the contractor

42.4.1 Waivers of contractors lien or right of continuing possession is required

No

42.4 DOCUMENTS

42.4.2 Number of construction document copies to be supplied to the contractor free of charge:

3 Number of

-13-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 14: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

42.4.3 Bills of Quantities/Lump sum document schedule of rates drawn up in accordance with:

“Standard System of Measuring Builders’ Work”

42.4.4 On acceptance of the tender the bills of quantities/lump sum document is to be submitted within working days

The priced bills of quantities must be handed in withthe tender

42.4.5 JBCC Engineering General Conditions are to be included in the contract documents:

No

42.4.6 The contract value is to be adjusted using escalation adjustment indices

YesWhere JBCC CPAP is to be used

Base Month

42.4.7 Details of changes made to the provision of JBCC standard documentation:

Refer to standard notes attached to this document in Section C1.2

SECTION B: PRELIMINARIES

Item

Definition and interpretation (B1.1 - B1.4.6)

F:............................. V:............................ T:............................

43

Definitions and interpretation (B1)

ItemChecking of documents (B2.1)F:............................. V:............................ T:............................

44

Documents (B2)

-14-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 15: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

N/AProvisional bills of quantities (B2.2)F:............................. V:............................ T:............................

45

Item

Availability of construction documentation (B2.3)

F:............................. V:............................ T:............................

46

ItemInterests of agents (B2.4)F:............................. V:............................ T:............................

47

ItemPriced documents (B2.5)F:............................. V:............................ T:............................

48

ItemTender submission (B2.6)F:............................. V:............................ T:............................

49

ItemDefined works area (B3.1)F:............................. V:............................ T:............................

50

The site (B3)

ItemGeotechnical investigation (B3.2)F:............................. V:............................ T:............................

51

ItemInspection of the site (B3.3)F:............................. V:............................ T:............................

52

Existing premises occupied (B3.4)F:............................. V:............................ T:............................

Previous work - dimensional accuracy (B3.5)F:............................. V:............................ T:............................

Previous work - defects (B3.6)F:............................. V:............................ T:............................

ItemServices - known (B3.7)F:............................. V:............................ T:............................

53

ItemServices - unknown (B3.8)F:............................. V:............................ T:............................

54

ItemProtection of trees etc (B3.9)F:............................. V:............................ T:............................

55

-15-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 16: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

ItemArticles of value (B3.10)F:............................. V:............................ T:............................

56

Item

Inspection of adjoining properties etc (B3.11)F:............................. V:............................ T:............................

57

Item

Management of the works (B4.1)

F:............................. V:............................ T: ...........

58

Management of contract (B4)

Item

Programme for the works (B4.2)

F:............................. V:............................ T:............................

59

ItemProgress meetings (B4.3)F:............................. V:............................ T:............................

60

ItemTechnical meetings (B4.4)F:............................. V:............................ T:............................

61

Item

Labour and Plant records (B4.5)

F:............................. V:............................ T:............................

62

ItemSamples of materials (B5.1)F:............................. V:............................ T:............................

63

Samples, Shop Drawings and Manufacturer's Instructions (B5)

ItemWorkmanship samples (B5.2)F:............................. V:............................ T:............................

64

Item

Shop drawings (B5.3)

F:............................. V:............................ T:............................

65

-16-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 17: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Item

Compliance with Manufacturer's Instructions (B5.4)

F:............................. V:............................ T:............................

66

ItemDeposits and fees (B6.1)F:............................. V:............................ T:............................

67

Temporary works and plant (B6)

ItemEnclosure of the works (B6.2)F:............................. V:............................ T:............................

68

ItemAdvertising (B6.3)F:............................. V:............................ T:............................

69

Item

Plant, equipment, sheds and offices (B6.4)

F: ..................... V:............................ T: ....................

70

ItemMain notice board (B6.5)F:............................. V:............................ T:............................

71

Item

Subcontractors' notice board (B6.6)

F:............................. V:............................ T:............................

72

ItemLocation (B7.1)F:............................. V:............................ T:............................

73

Temporary services (B7)

Item

Water (B7.2)Option [A] shall apply

F:............................. V:............................ T:............................

74

Item

Electricity (B7.3)Option [A] shall apply

F:............................. V:............................ T:............................

75

-17-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 18: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Item

Telecommunication facilities (B7.4)

F:............................. V:............................ T:............................

76

Item

Ablution facilities (B7.5)Option [A] shall apply

F:............................. V:............................ T:............................

77

Item

Responsibility for prime cost amounts (B8.1)F:............................. V:............................ T:............................

78

Prime cost amounts (B8)

ItemGeneral attendance (B9.1)F:............................. V:............................ T:............................

79

Attendance on N/S Subcontractors (B9)

ItemSpecial attendance (B9.2)F:............................. V:............................ T:............................

80

Item

Commissioning - Fuel, water and power (B9.3)F:............................. V:............................ T:............................

81

Item

Statutory taxes, duties and levies (B10.1)F:............................. V:............................ T:............................

Financial aspects (B10)

Item

Payment of preliminaries (B10.2)Option [B] shall apply

F:............................. V:............................ T:............................

82

Item

Adjustment of preliminaries (B10.3)Option [A] shall apply

F:............................. V:............................ T:............................

83

-18-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 19: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Item

Payment certificate cash flow (B10.4)F:............................. V:............................ T:............................

84

ItemProtection of works (B11.1)F:............................. V:............................ T:............................

85

General (B11)

N/A

Protection/isolation of existing/sectionally occupied works (B11.2)F:............................. V:............................ T:............................

86

Item

Security of the Works (B11.3)

F:............................. V:............................ T:............................

87

ItemNotice before covering work (B11.4)F:............................. V:............................ T:............................

88

Item

Disturbance (B11.5)

F:............................. V:............................ T:............................

89

Item

Environmental Disturbance (B11.6)

F:............................. V:............................ T:............................

90

Item

Works cleaning and clearing (B11.7)

F:............................. V:............................ T:............................

91

Item

Vermin (B11.8)

F:............................. V:............................ T:............................

92

Item

Overhand work (B11.9)

F:............................. V:............................ T:............................

93

-19-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 20: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Item

Instruction manuals and guarantees (B11.10)

F:............................. V:............................ T:............................

94

Item

As built information (B11.11)

F:............................. V:............................ T:............................

95

Item

Tenant Installations (B11.12)

F:............................. V:............................ T:............................

96

ItemPre-tender information (B12.1)F:............................. V:............................ T:............................

97

Schedule of variables (B12)

12.1.1 Provisional bills of quantities (B2.2)The quantities are provisional:

No

12.1.2 Availability of construction documentation (B2.3)Construction documentation is not complete

No

12.1.3 Interest of agents (B2.4)

12.1.4 Defined works area (B3.1)

12.1.5 Geotechnical investigation (B3.2)

-20-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 21: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

12.1.6 Existing premises occupied (B3.4)

The Tenderer is notified that the school will remain functional during the works. All construction activities areto be programmed around the functioning of the school, and in a manner that does not pose risks to learners, teachers and school staff.

12.1.7 Previous work - dimensional accuracy (B3.4)

12.1.8 Previous work - defects (B3.5)

12.1.9 Services - known (B3.7)

12.1.10 Protection of trees (B3.9)

All trees should be protected and only on instruction of the Principal Agent may any trees be removed

12.1.11 Inspection of adjoining properties (B3.11)

12.1.12 Enclosure of the works (B6.2)

12.1.13 Offices (B6.4.3)

An office for the clerk of works should be provided

12.1.14 Main notice board (B6.5) Yes

-21-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 22: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

12.1.15 Subcontractors notice board (B6.6)A notice board is required

No

12.1.16 Water (B7.2)Alternative Selected: A

12.1.17 Electricity (B7.3)Alternative selected: A

12.1.18 Telecommunications (B7.4)

12.1.19 Ablution facilities (B7.5)Alternative selected: A

12.1.20 Protection of existing/sectionally occupied works (B11.2)

12.1.21 Special attendance (B9.2)

Subcontractor (1) details:

N/A

12.1.22 Protection of the works (B11.1)

N/A

12.1.23 Disturbance (B11.5)

N/A

12.1.24 Environmental Disturbance (B11.6)

N/A

12.2.1 Payment of preliminariesAlternative selected: B

Post tender information (B12.2)

12.2.2 Adjustment of preliminariesAlternative selected: A

12.2.3 Additional agreed preliminaries itemsN/A

-22-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 23: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Any special items to meet the particular circumstances of a specific project are embodied in this section. Where required for an aspect of the works to be executed according to a design by a consulting engineer, a recital of the headings to the individual clauses of the JBCC Engineering General Conditions are included

SECTION C: SPECIFIC PRELIMINARIES

Item

Black economic empowerment and training

F:............................. V:............................ T:............................

98

Item

Proprietary branded products

F:............................. V:............................ T:............................

99

The contractor shall take delivery of, handle, store, use, apply and/or fix all proprietary branded products in strict accordance with the manufacturers' instructions after consultation with the manufacturer's authorised representative

Item

Contract instructions

F:............................. V:............................ T:............................

100

Contract instructions issued on site are to be recorded in triplicate in a contract instruction book which is to be supplied and maintained on site by the contractor

Item

Labour record

F:............................. V:............................ T:............................

101

-23-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 24: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

At the end of each week the contractor shall provide the principal agent with a written record, in schedule form, reflecting the number and descriptions of tradesmen and labourers employed by him and all subcontractors on the works each day of that week

Item

Plant record

F:............................. V:............................ T:............................

102

At the end of each week the contractor shall provide the principal agent with a written record, in schedule form, reflecting the number, type and capacity of all plant, excluding hand tools used on the works each day of that week

Item

Guarantees

F:.................... V:............................ T:............................

103

Where guarantees are called for, the contractor shall obtain a written guarantee, addressed to the employer, from the firm supplying the materials and/or doing the work and shall deliver same to the principal agent on the certified completion of the contract. The guarantee shall state that workmanship, materials and installation are guaranteed for a specified period from the date of certified completion of the contract, and that any defects that may arise during the specified period shall be made good at the expense of the firm supplying the materials and/or doing the work, upon written notice from the principal agent to do so. This guarantee will not be enforced if the work is damaged by defects in the construction of the building in which case the responsibility for replacement shall rest entirely with the contractor. The principal agent shall be the sole judge of the cause responsible for defects in the work and his decision shall be final and binding in terms of clause 40.2 of the agreement

Item

Overtime

F:............................. V:............................ T:............................

104

-24-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward R

Page 25: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Should overtime be required to be worked for any reason whatsoever, the costs of such overtime are to be borne by the contractor unless the principal agent has specifically authorised, in writing, prior to execution thereof, that costs for such overtime are to be borne by the employer

Item

Co-operation of contractor for cost management

F:............................. V:............................ T:............................

105

It is specifically agreed that the contractor accepts the obligation of assisting the professional consultants in implementing proper cost management. The contractor will be advised by the principal agent of all cost management procedures which will be implemented to ensure that the final building cost does not exceed the budget. The quantity surveyor undertakes to make available to the contractor all budgetary allowances and cost assessments/reports to enable the proper procedures to be implemented and the contractor will attend all cost plan review and cost management meetings. The contractor undertakes to extend these procedures in regard to all subcontractors

Item

Occupational Health and Safety Specification

F:............................. V:............................ T: ..................

106

Any Principal Contractor entering into a contract with The Developer must achieve an acceptable level of Occopational Health and Safety performance. Refer to "Project Specification" and "Safety, Health and Environmental Evaluation Questionaire" The contractor to comply with all provisions of the above and to be enforced on all selected and or other sub-contractors, as no claim afterwards will be entertained

-25-

PRELIMINARIESBill No. 1Section No. 1

Carried Forward to Summary of Section No. 1 R

Page 26: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 1

BILL NO. 2

12PersonUI19 Registrations 1

OCCUPATIONAL HEALTH AND SAFETY

ItemPermit Applications with Dept. of Labor e.g. blasting (ifapplicable)

2

12No

Economics/ Health/ HygieneAssessment (Per Employee)

3

12No

Training & awareness (non accredited) per employee

4

12PersonPPE 5

12MNTHSafety Office (Per Month)6

12MNTHSHE Rep (Per Month)7

1No

Certification /Compliance (e.g. OHAS 18001)8

12MNTHInsurance Premium & Public indemnity9

ItemFines and Penalties (if applicable)10

ItemInsurance Excess (if applicable11

12PersonLegal fees (e.g. contracts12

ItemRisk Assessment (internal)13

12PersonMedical fitness surveillance14

ItemUIF 2% of salary per employee per month15

12MNTH

Welfare facilities in terms of Facilities Regulations

16

-26-

OCCUPATIONAL HEALTH AND SAFETYBill No. 2Section No. 1

Carried Forward R

Page 27: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

ItemSignage17

ItemSafety barricades18

ItemSite Hoarding & Fencing19

1NoFirst Aid Box20

12MNTHFire fighter21

12MNTHFirst Aider22

12MNTHSupervisor in terms of Electrical Installation23

-27-

OCCUPATIONAL HEALTH AND SAFETYBill No. 2Section No. 1

Carried Forward to Summary of Section No. 1 R

Page 28: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION SUMMARY - PRELIMINARIES

BillNo

PageNo

Amount

25PRELIMINARIES1

27OCCUPATIONAL HEALTH AND SAFETY2

-28-

Section No. 1

Carried to Final Summary R

Page 29: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO 1

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

The nature of the ground is assumed to be loose sandy material, therefore "earth", but possibly interspersed with "hard rock" or "soft rock".

Nature of ground

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or alternatively, from stock piles situated on the building site.

CARTING AWAY OF EXCAVATED MATERIAL

Prices for all filling and carting away of surplus material must make allowance for bulking.

PRICES

The Tenderer is referred to the relevant Clauses in the separate document Model Preambles for Trades (2008 Edition) and the Supplementary Preambles hereunder.

EARTHWORKS (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

The nature of the ground is assumed to be gravel, therefore earth, but possibly interspersed with soft rock.

Nature of ground:

-29-

EARTHWORKSBill No. 1Section No. 2

Carried Forward R

Page 30: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or, alternatively, from stock piles situated on the building site.

Carting away of excavated material:

BULK EXCAVATION, FILLING, ETC.

104m3Open face excavation.1

Open face excavation in earth over flat site:

10m3Soft rock.2

Extra over bulk excavation in earth for excavation in:

5m3Hard rock.3

FILLING

14m3Under surface beds4

Filling with approved material supplied and carted onto site by the Contractor, compacted to a density of at least 95% Mod. AASHTO maximum density:

EXCAVATION OTHER THAN BULK

15m3Trenches for strip footings5

Excavation in earth not exceeding 2m deep:

11m3Holes6

CARTING AWAY

9m3Surplus material from excavation and/or stockpile on siteto a dumping site to be allocated by the contractor.

7

Extra over all excavations for carting away:

33m2Sides of trenches not exceeding 1,5m deep.8

Risk of collapse of excavations:

-30-

EARTHWORKSBill No. 1Section No. 2

Carried Forward R

Page 31: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

33m2Sides of bulk excavations not exceeding 1,5m deep.9

ItemKeeping excavations free of all water other than subterranean water.

10

Keeping excavations free of water:

90m2

Under floors, etc. Including forming and poisoning shallow furrows against foundation walls etc., filling in furrows and ramming.

11

Soil insecticide:

33m2To bottoms and sides of trenches etc.12

CONCRETE

(CPAP FORMULA WORK GROUP NO. 110)

UNREINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

15m3Strip footings13

25MPa/19mm concrete

1.01t10mm Diameter bars.14

High tensile steel reinforcement to structural concrete work:

1.01t8mm Diameter bars.15

The Tenderer is referred to the relevant Clauses in the separate document Model Preambles for Trades (2008 Edition) and the Supplementary Preambles hereunder.

BRICKWORK IN FOUNDATIONS

6m3Piers16

Brickwork of NFX bricks (14 MPa nominal compressive strength) in Class I mortar:

57m2One brick walls17

-31-

EARTHWORKSBill No. 1Section No. 2

Carried Forward R

Page 32: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

521m150mm Wide reinforcement built in horizontally18

Brickwork reinforcement

9m2Extra over brickwork for face brickwork19

External face bricks (Prime Cost Amount R 4000.00/1000) pointed with flush horizontal and vertical joints

60mFair cutting at squint quoin or birdsmouth angle20

-32-

EARTHWORKSBill No. 1Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 33: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO. 2

CONCRETE, FORMWORK AND REINFORCEMENT

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

The contractor is refered to the Model Preambles for Trades (2008 edition) as issued the Association of South African Quantity Surveyors before pricing this bill

SUPPLEMENTARY PREAMBLES

Cost of tests

The costs of making, storing and testing of concrete test cubes as required under clause 7 "Tests" of SABS 1200 G shall include the cost of providing cube moulds necessary for the purpose, for testing costs and for submitting reports on the tests to the architect. The testing shall be undertaken by an independent firm or institution nominated by the contractor to the approval of the architect. (Test cubes are measured separately).

Formwork

Descriptions of formwork shall be deemed to include use and waste only (except where described as "left in" or "permanent"), for fitting together in the required forms, wedging, plumbing and fixing to true angles and surfaces as necessary to ensure easy release during stripping and for reconditioning as necessary before re-use.

The vertical strutting shall be carried down to such construction as is sufficiently strong to afford the required support without damage and shall remain in position until the newly constructed work is able to support itself.

-33-

CONCRETE,FORMWORK AND REINFORCEMENTBill No. 2Section No. 2

Carried Forward R

Page 34: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Formwork to soffits of solid slabs etc shall be deemed to be to slabs not exceeding 250mm thick unless otherwise described

Formwork to sides of bases, pile caps, ground beams, etc will only be measured where it is prescribed by the engineer for design reasons.

Formwork necessitated by irregularity or collapse of excavated faces will not be measured and the cost thereof shall be deemed to be included in the allowance for taking the risk of collapse of the sides of the excavations, provision for which is made in "Earthworks"

REINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

8m3Surface beds on waterproofing1

25 MPa/19mm Concrete:

3m3Slabs including beams and inverted beams2

3m3Aprons cast in panels to falls 3

21m2Aprons to falls 4

Finishing top surfaces of concrete smooth with a wood float

50m2

Forming 250mm wide segmental channel to falls in concrete including finishing smooth

5

TEST BLOCKS

6.0SetsMaking and testing set of three 150 x 150 x 150mm concrete strength test cubes.

6

Test blocks:

FINISHING TOP SURFACE OF CONCRETE

69m2Surface beds, slabs, etc.7

Finishing top surfaces of concrete smooth with a steel trowel:

-34-

CONCRETE,FORMWORK AND REINFORCEMENTBill No. 2Section No. 2

Carried Forward R

Page 35: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

ROUGH FORMWORK (DEGREE OF ACCURACY III) (CPAP Work Group No 111)

33mEdges, risers, ends and reveals not exceeding 300mm high or wide.

8

Rough Formwork to Sides:

3m2Slabs propped up exceeding 1,5m and not exceeding 3,5m high

9

MOVEMENT JOINTS, ETC.

28mNot exceeding 300mm wide.10

Two layers of 375 micron dampproof course in slip joints between horizontal concrete and brick surfaces including cement mortar bed.:

REINFORCEMENT (CPAP Work Group No 114) (MEASURED PROVISIONALLY)

60m2Type 395 fabric reinforcement in concrete surface beds, etc.

11

Fabric reinforcement:

3.51t10mm Diameter bars.12

High tensile steel reinforcement to structural concrete work:

3.96t8mm Diameter bars.13

-35-

CONCRETE,FORMWORK AND REINFORCEMENTBill No. 2Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 36: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO. 3

MASONRY

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

BRICKWORK

Where sizes in descriptions are given in brick units, "one brick" shall represent the length and "half brick" the width of a brick

Sizes in descriptions

Descriptions of hollow walls shall be deemed to include leaving every fifth perpend of the bottom course of the external skin open as a weep hole.

Hollow walls etc

Walls in two skins described as "bagged and sealed" shall be deemed to include having the outer face of the inner skin bagged with 1:6 cement and sand mixture and sealed with two coats "Brixeal" bitumen emulsion waterproofing coating.

The above preamble generally applies for works in hot and humid coastal areas

User note:

Bricks shall be ordered timeously to obtain uniformity in size and colour

Face bricks

-36-

MASONRYBill No. 3Section No. 2

Carried Forward R

Page 37: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Descriptions of recessed pointing to fair face brickwork and face brickwork shall be deemed to include square recessed, hollow recessed, weathered pointing, etc

Pointing

BLOCKWORK

Blocks are to be either solid or hollow modular dense concrete masonry units having a compressive strength of 7 MPa

Concrete masonry units

Wall ties shall be polypropylene "Permaties" complying with BS 76377. Ties for hollow walls shall be of sufficient length to allow not less than 75mm of each end to be built into the blockwork. Ties are to be spaced at intervals of not more than 1m in the horizontal direction and not more than 400mm staggered in the vertical direction except at openings, vertical joints or ends of walls where they are to be placed vertically above each other

Wall ties for blockwork

Blockwork shall comply with SABS 0145 "Concrete Masonry Construction"

Surfaces to be plastered shall have joints raked out to a depth of at least 10mm to provide a key. Cavities of hollow walls shall be kept free of mortar droppings or other undesirable matter. Every second perpend of the bottom course of the external skin of hollow walls shall be left open as a weep hole

Blockwork

Descriptions of blockwork shall be deemed to include standard complementary blocks such as corner, three-quarter, half and quarter blocks required in the construction of corners, reveals, jambs, ends, etc to solid and hollow walls and for bonding as necessary

Standard complementary blocks

-37-

MASONRYBill No. 3Section No. 2

Carried Forward R

Page 38: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Blocks shall be of approved manufacture, sound, well burnt or cured and uniform and true in size, shape and colour

DECORATIVE BLOCKS

Samples of all masonry building units, except those for walls described as "load bearing", shall consist of a minimum of 6 units. Samples of building units to be used in walls described as "load bearing" shall consist of30 units from every 30 000 units delivered to site

SAMPLES

12m2Half brick walls.1

Brickwork of NFX bricks (14 MPa nominal compressive strength) in Class I mortar:

6m2Ditto, but in beamfilling.2

12m2Ditto, but in firewall.3

21m2One brick walls.4

8m2Ditto, but in firewall.5

35m2One brick walls of two half brick skins.6

15m2One brick walls of two half brick skins in gable walls.7

6m2340mm Hollow walls of two half brick skins (no wire ties).

8

3m3Piers.9

385mClosing 120mm cavities of hollow walls horizontally with one course of brickwork.

10

BRICKWORK SUNDRIES

983m75mm Wide reinforcement built in horizontally.11

Brickwork reinforcement:

771m150mm Wide reinforcement built in horizontally.12

-38-

MASONRYBill No. 3Section No. 2

Carried Forward R

Page 39: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

6m110 x 70mm Lintels in lengths not exeeding 3m.13

Prestressed fabricated precast lintels including necessary temporary supports:

3m110 x 70mm Lintels in lengths exceeding 3m and not exeeding 4.5m.

14

24mPair of 110 x 70mm Lintels in lengths not exeeding 3m.15

4m150mm Wide turning piece to lintels etc.16

Turning pieces to lintels, etc:

4m220mm Wide turning piece to lintels etc.17

32No4mm Diameter roof tie 2m girth bent double with one end fixed to timber and other end built into brickwork.

18

Galvanised wire ties etc:

2No229 x 152mm Terracota airbricks19

Air bricks etc:

FACE BRICKWORK

33m2Extra over brickwork for face brickwork.20

Face bricks (Allow a P.C. Amount of R4 000.00 per 1 000 supplied and delivered to site) pointed with 6mm square recessed horizontal and vertical joints:

4m2Extra over brickwork for facing 220 x 220mm piers.21

9m2Extra over brickwork for facing 330 x 330mm piers.22

4m2Extra over brickwork for facing gable walls.23

3m2Extra over brickwork for facing beamfilling.24

8m230mm Wide sill set sloping and slightly projecting.25

8mFace brick-on-edge header course lintel.26

-39-

MASONRYBill No. 3Section No. 2

Carried Forward R

Page 40: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

11mExtra over brickwork for face brick-on-edge header course plinth.

27

3mCut face brick-on-edge header course lintel 110mm wide.

28

5mFair raking cutting.29

FIBRE CEMENT WINDOW CILLS

8m140mm Wide cills set flat and slightly projecting.30

15mm Thick natural grey cills in single length bedded in 4:1 sand cement mortar including metal lugs, etc:

-40-

MASONRYBill No. 3Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 41: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO 4

WATERPROOFING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

Waterproofing of roofs, basements, etc shall be laid under a ten year guarantee. Waterproofing to roofs shall be laid to even falls to outlets etc with necessary ridges, hips and valleys. Descriptions of sheet or membrane waterproofing shall be deemed to include additional labour to turn-ups and turn-downs

Waterproofing

DAMPPROOFING OF WALLS AND FLOORS

197m2In walls, under cills, etc.1

One layer of 375 micron embossed polyethylene dampproof course (SANS 952-1985 type B)

67m2Under surface beds.2

One layer of 250 micron green polyethylene waterproof sheeting (SANS 952-1985 type C) sealed at laps with PVC self-adhesive tape:

JOINT SEALANTS, ETC.

40m3 x 50mm In saw cut joints in floors.3

Two-part grey polysulphide sealing compond including backing cord, bond breaker, primer,etc.

53m15 x 10mm In isolation joints including raking out isolation joint filler.

4

-41-

WATERPROOFINGBill No. 4Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 42: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO 5

ROOF COVERINGS, ETC.

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

CORRUGATED METAL SHEETING AND ACCESSORIES

117m2Roof covering with pitch not exceeding 25 degrees.1

0,6mm IBR concealed fix Colomet finished steel sheeting and accessories fixed to timber purlins (elsewhere):

95m2Roof covering with pitch not exceeding 25 degrees.2

0.6mm Kliplok roof sheeting in cromadek finish

7mRidge capping to suit roof profile.3

0,6mm Colomet flashings:

16mHip capping to suit roof profile.4

RAINWATER DISPOSAL

13m100x 75mm Eaves gutters.5

Seamless aluminium gutters.

6NoExtra over gutter for stopped end.6

6NoExtra over gutter for angle.7

-42-

ROOF COVERINGSBill No. 5Section No. 2

Carried Forward R

Page 43: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

6NoExtra over 100 x 75mm eaves gutter for outlet for 75mm diameter pipe.

8

18m75mm Diameter rainwater pipes.9

6NoExtra over rainwater pipe for bend.10

6NoExtra over rainwater pipe for eaves offset 500mm projection.

11

ROOF INSULATION

56m2

Insulation laid taut over battens (at approximately 380mm centres) and fixed concurrent with roof covering including galvanised steel straining wires, laps, etc.

12

'Sisalation 420' or similar approved heavy industrial grade aluminium foil based insulation.:

-43-

ROOF COVERINGSBill No. 5Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 44: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO. 6

CARPENTRY AND JOINERY

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Descriptions of frames shall be deemed to include frames, transomes, mullions, rails, etc

Joinery:

Descriptions of hardwood joinery shall be deemed to include pelleting of bolt holes

-44-

CARPENTRY AND JOINERYBill No. 6Section No. 2

Carried Forward R

Page 45: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or shot pins to brickwork or concrete

Fixing

PREFABRICATED ROOF TRUSSES, ETC.

9m114 x 38mm Wall plates.1

Sawn softwood:

1NoTrusses for rectangular shaped building, size overall 13.31 x 8.48m on plan (1 Grade R).

2

Prefabricated timber roof construction complete including purlins, runners, bracing hips, valleys, cleats, purlins, etc., supplied and fixed complete:

EAVES, VERGES, ETC.

37m12 x 225mm Fascia and barge boards, including galvanised steel H-profile joiners, etc.

3

Medium density plain fibre-cement fascial and barge boards:

SKIRTINGS

65m19 x 76mm Skirtings including 19mm quadrant bead, nailed.

4

Wrought meranti:

33m19 x 50mm Cornice laid flat.5

33m16 x 150mm dado rail.6

FRAMED DOORS, ETC.

2No

40mm Framed batten door 813 x 2032mm high of top rail and stiles, middle ledge and braces and bottom rail filled in with V-jointed one side boarding.

7

Wrought meranti doors hung to steel frames:

-45-

CARPENTRY AND JOINERYBill No. 6Section No. 2

Carried Forward R

Page 46: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SOLID LAMINATED FLUSH DOORS

7No40mm Door 813 x 2032mm high.8

40mm solid laminated flush doors with hardwood veneer and two concealed edges hung to steel frames:

-46-

CARPENTRY AND JOINERYBill No. 6Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 47: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO. 7

CEILINGS, PARTITIONS AND ACCESS FLOORING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or pins or shot pinned to brickwork or concrete

Descriptions:

Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 600mm centres, and where described as "bolted" the bolts have been given elsewhere

-47-

CEILING PARTITIONS ACCESS FLOORINGBill No. 7Section No. 2

Carried Forward R

Page 48: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Electrical light fittings, diffusers, panels, etc generally are "lay in" units of the same dimensions as the suspension grid described and allowance must be made accordingly for their support inclusive of any flexibility insetting out that may be required (ceiling panels have not been deducted and pricing is to take cognisance thereof)

NAILED UP AND SCREW UP CEILINGS

124m2

Ceilings including 38 x 38mm sawn softwood brandering at 450mm centres with cross brandering at 450mm centres and at joints, ends of sheets and at light fittings, etc.

1

6,4mm Gypsum plasterboards with H-profile galvanised steel jointing strips:

2No

Extra over ceiling for 600 x 600mm hinged trap door of wrought softwood rebated framing with one sawn softwood cross brander covered with ceiling board and fitted flush in opening, including necessary trimmers all around.

2

43m2

Ceilings including 38 x 38mm sawn softwood brandering at 450mm centres with cross brandering at 450mm centres and at joints, ends of sheets and at light fittings, etc

3

6mm Fibre-cement plain ceiling boards with H-profile galvanised steel jointing strips:

2No

Extra over ceiling for 600 x 600mm hinged trap door of wrought softwood rebated framing with one sawn softwood cross brander covered with ceiling board and fitted flush in opening, including necessary trimmers all around.

4

INSULATION

124m2100mm Insulation closely fitted between tie beams and laid loose on top of brandering.

5

Non-combustible lightweight fibreglass insulation blanket:

-48-

CEILING PARTITIONS ACCESS FLOORINGBill No. 7Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 49: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO. 8

IRONMONGERY

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Where applicable finishes to ironmongery are indicated by suffixes in accordance with the following list: BS Satin bronze lacquered CH Chromium plated SC Satin chromium plated SE Silver enamelled GE Grey enamelled AS Anodised silver AB Anodised bronze AG Anodised gold ABL Anodised black PB Polished brass PL Polished and lacquered PT Epoxy coated SD Sanded

Finishes to ironmongery

"Union"

-49-

IRONMONGERYBill No. 8Section No. 2

Carried Forward R

Page 50: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

IRONMONGERY FIXED TO DOORS, ETC.

9NoWC mortice indicator bolt with emergency release.1

Bolts and latches:

9No75mm Four lever security lockset with satin chrome furniture.

2

LOCKS:

DOOR CLOSERS

2NoTS 68 door closer with parallel arm, bracket fixed to metal.

3

Dorma:

NUMERAL AND NAMEPLATES, ETC.

1NoDitto, but with letters "CLASSROOMS".4

Clear perspex name plate reverse engraved and enamelled in white lettering 25mm high to suit, twice countersunk holed for and tapscrewed to steel door frames or gate framing with chromium plated dome-headed selftapping screws:

1NoDitto, but with letters "STORE ROOM".5

2No

190 x 190 x 3mm Thick white perspex international FB2 sign plate with red fire extinguisher symbol plugged to brickwork.

6

Indicator plates countersunk holed for and screwed to door or brickwork with chromium plated dome-headed screws:

7No

75 x 150mm High aluminium toilet sign with MALE,DISABLED and/or FEMALE figure screwed to door.

7

7NoRubber tipped coathook.8

SUNDRIES

2No38mm Rubber stop plugged and srewed to wall or floor.9

-50-

IRONMONGERYBill No. 8Section No. 2

Carried Forward R

Page 51: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

3NoNickel plated steel leaf spring door holder with rubber door stop plugged and screwed to floor.

10

3No

19mm Stainless steel chromium plated towel rail, 600mm long, with end brackets plugged to plastered or tiled wall.

11

8m3 x 25mm Brass dividing strip between different floor finishes.

12

1No32mm Diameter code DL2 side grab rail, plugged.13

Chairman Industries or similar approved brushed stainless steel grab rails:

1No32mm Diameter code SL2 rear grab rail, plugged.14

BATHROOM FITTINGS

5NoLockable Stainless steel toilet roll holder plugged to wall.

15

Toilet roll holders

4NoWall mounted soap dispenser plugged.16

Soap dispensers:

PINNING BOARDS, WRITING BOARDS, PROJECTION SCREENS, ETC.

1NoPinning board size 2400 x 1200mm high plugged.17

Carpet pinning boards in aluminium frame with round plastic corners, pen tray and fixing component all fixed according to manufacturer's instruction.

1No

Chalk board size overall 1140mm high x 3600mm wide consisting of 1 x chalkboard 1800mm wide, 2 x chalkboard 900mm wide, 2 x swing type chalkboard 900mm wide.

18

Swing type green chalkboard to comply with CKS-36-1980 or equivalent code of practice, complete with chalk rail as one unit fixed to wall strictly according to manufacturers instruction:

-51-

IRONMONGERYBill No. 8Section No. 2

Carried Forward R

Page 52: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

1NoWhite board size 2 x 2400 x 1140mm high.19

White board marker board surface wall mounted complete with integrated pen tray according to manufacturers instruction:

-52-

IRONMONGERYBill No. 8Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 53: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION NO.2

BILL NO.9

STRUCTURAL STEELWORK

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions

Descriptions of L-shaped and U-shaped anchor bolts shall be deemed to include bending, threading, nuts and washers and embedding in concrete

Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

STEEL COLUMNS AND BEAMS

16No76 x 76mm x 3.0mm, 2.27m high column1

Mild steel welded columns in single lengths with flat section base, top, bearer and connection plates bolted to roof on floors and roof trusses

8m150 x 150mm x 75mm beam2

Welded beams in single lengths with flat section bearer and connection plates bolted to 76mm columns

4.00tHigh tensile bolts3

Bolts

-53-

STRUCTURAL STEELWORKBill No. 9Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 54: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO. 10

METALWORK

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions

Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

Metalwork described as"holed for bolt(s)" shall be deemed to exclude the bolts unless otherwise described

-54-

METALWORKBill No. 10Section No. 2

Carried Forward R

Page 55: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

STEEL WINDOWS, DOORS, ETC.

6NoWindow type 14BH, 889 x 457mm high with one opening light.

1

Standard residential windows with steel burglar bars to fixed lights and opening sashes:

13NoWindow type 14BH, 889 x 1248mm high with one opening light.

2

PRESSED STEEL DOOR FRAMES

7NoFrame for door 914 x 2032mm high.3

1,2mm Rebated frames suitable for half brick walls:

2NoFrame for door 914 x 2032mm high.4

1,2mm Double rebated frames suitable for one brick walls:

STEEL STRONGROOM DOORS, VENTILATORS, ETC.

2NoSteel louvre unit according to NTY5

Steel Louvres

SECURITY GATES

2NoSize 925mm x 1800mm high, as per door schedule. (G12)

6

Steel security gates:

Handrail

15m60 x 60 x 4 mm Thick square hollow section handrail.7

The following in galvanized mild steel handrails framed and welded together including shopcoat as described:

4No76 x 76 x 3mm Mild steel square tubing 8

-55-

METALWORKBill No. 10Section No. 2

Carried Forward R

Page 56: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

60m25 x 25 x 5 mm Angle framing including mitred intersections.

9

4NoStop end.10

16No10 x 75 mm Expanding bolt including fixing to concrete or brickwork.

11

-56-

METALWORKBill No. 10Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 57: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO. 11

PLASTERING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

107m2

22,5mm thick sand cement screed, finished with a steel

float and prepared to receive vinyl tiles (elsewhere

measured).

1

SCREEDS

GRANOLITHIC

-57-

PLASTERINGBill No. 11Section No. 2

Carried Forward R

Page 58: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

69m235mm Thick on floors and walkways2

Untinted granolithic on concrete

INTERNAL PLASTER

175m2On walls.3

One coat cement plaster steel trowelled on brickwork.

12m2On narrow widths.4

-58-

PLASTERINGBill No. 11Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 59: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO. 12

TILING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Unless described as "fixed with adhesive to plaster (plaster elsewhere)" descriptions of tiling on brick or concrete walls, columns, etc shall be deemed to include 1:4 cement plaster backing and descriptions of tiling on concrete floors etc shall be deemed to include 1:3 plaster bedding

Descriptions

WALL TILING

-59-

TILINGBill No. 12Section No. 2

Carried Forward R

Page 60: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

19m2On walls1

200 x 200 x 6mm "Cercisa Tinte Unite" White glazed ceramic tiles fixed with adhesive to plaster (plaster elsewhere)

3m2On narrow widths2

4NoFair exposed cutting and fitting around pipe not exceeding 110mm internal diameter

3

FLOOR TILING

105m2On floors and landings4

300 x 300mm x 8mm Ceramic tiles (PC Amount R150.00/m2) fixed with adhesive to bedding (bedding elsewhere) and flush pointed with tinted waterproof jointing compound

43mSkirting 75mm high5

WALL TILING

4m2Walls in splashbacks.6

152 x 152 x 5mm Thick white glazed tiles fixed to plaster (elsewhere measured) with and approved tile adhesive to and pointed with white cement to:

-60-

TILINGBill No. 12Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 61: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO. 13

PLUMBING AND DRAINAGE (PROVISIONAL)

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Soil, waste and vent pipes and fittings shall be solvent weld jointed

uPVC pipes and fittings:

-61-

PLUMBING AND DRAINAGEBill No. 13Section No. 2

Carried Forward R

Page 62: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Pipes shall be hard drawn and half-hard pipes of the class stated. Class 0 (thin walled hard drawn) pipes shall not be bent. Class 1 (thin walled half-hard), class 2 (half-hard) and class 3 (heavy walled half-hard) pipes shall only be bent with benders with inner and outer formers. Fittings to copper waste, vent and anti-syphon pipes, capillary solder fittings and compression fittings shall be "Cobra Watertech" type. Capillary solder fittingsshall comply with ISO 2016. Only compression fittings shall be used in walls or in ground

Copper pipes:

Unless specifically otherwise stated, descriptions of pipes shall be deemed to include fixing to walls etc, casting in, building in or suspending not exceeding 1m below suspension level

Fixing of pipes

Where fittings have reducing ends or branches they are described as "reducing". In the case of pipes with diameters not exceeding 60mm only the largest end or branch size is given. Should the contractor wish to use other fittings and bushes or reducers he may do so on the understanding that no claim in this regard will be entertained. In the case of pipes with diameters exceeding 60mm all sizes are given and no claim for extra bushes, reducers, etc will be entertained

Reducing fittings

Flush pans shall have straight or side outlets and "P" or "S" traps as necessary

Flush pans

Units shall have standard aprons on all exposed edges and tiling keys against walls where applicable

Stainless steel basins, sinks, wash troughs, urinals, etc.

Descriptions of waste unions shall be deemed to include rubber or vulcanite plugs and chains fixed to fittings

Waste unions

-62-

PLUMBING AND DRAINAGEBill No. 13Section No. 2

Carried Forward R

Page 63: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SANITARY PLUMBING

27m50mm Pipes fixed to walls, etc.1

Unplasticised polyvinyl chloride (uPVC) pipes:

5m110mm Pipes fixed to walls, etc.2

9No50mm BSP Adaptor.3

Extra over uPVC pipes for:

6No110mm Straight pan connector.4

2No50mm Bend.5

1No110mm Bend.6

2No110mm Junction.7

3No50mm Access bend.8

4No110mm Access bend.9

1No50mm Access junction.10

2No110mm Access junction.11

1No110mm Access reducing junction.12

ItemAllow for testing sanitary plumbing system.13

Testing:

WATER SUPPLIES

Prices for all piping laid in ground, inspection chambers, etc. shall include for excavations, keeping free of water, distributing surplus material on site (carting away has been separately measured) and backfilling in selected material (imported fill where required will be separately measured).

Internal water supplies:

-63-

PLUMBING AND DRAINAGEBill No. 13Section No. 2

Carried Forward R

Page 64: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Holes, chases, etc., are deemed to be included in the descriptions of the pipework.

9m15mm Pipes fixed to walls, etc.14

Class O copper pipes:

2mDitto, but 22mm pipes.15

3mDitto, but 28mm pipes.16

11No15mm Pipe fittings.17

Extra over class O copper pipes for copper to copper capillary fittings:

5No22mm Pipe fittings.18

3No28mm Pipe fittings.19

5No15mm Brass pipe fittings.20

Extra over class O copper pipes for brass capillary fittings:

3No22mm Brass pipe fittings.21

3No28mm Brass pipe fittings.22

ItemAllow for testing water supply system.23

Testing:

SANITARY FITTINGS AND GEYSERS

Supply and fix the following sanitary fittings, geysers and equipment together with loose ancillary fittings supplied therewith, including unloading, storing, unpacking, hoisting or lowering as required, fixing and building into position, cutting all mortices and chases as required for fixing and building in position, cutting, brackets, clamps, etc., and connecting up pipework and handing over in perfect working order at completion:

-64-

PLUMBING AND DRAINAGEBill No. 13Section No. 2

Carried Forward R

Page 65: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

4No

"Hibiscus" Ref 7023 white vitreous china wall hung basin, size 510 x 405mm, with stopper to one taphole and fixed to wall.

24

'Vaal':

4No

"Junior" Code 751358 WC suite comprising a white vitreous china pan with trap, matching 6 litre white cistern, Code 712035 complete with lid, fitments and a junior seat fixed to wall.

25

1No

"Afsan" Code 750100 WC suite comprising a white vitreous china pan with trap, matching Aquasave low level white cistern, Code 712035 complete with lid, fitments and white matching seat fixed to wall.

26

1No

"Protea Paraplegig" Code 750246 WC suite comprising a white vitreous china pan with trap, matching 9 litre white cistern, Code 710361 complete with lid, fitments and white matching seat fixed to wall.

27

1No

"Curveline Model CVN611" drop-on single end bowl sink, size 800 x 435mm, fixed to cupboard (cupboard by others) with securing clips and sealed with sillicone adhesive along edges.

28

'Franke' - grade 304 (18/10) polished stainless steel:

ELECTRIC WATER HEATERS

1No5 Litre 'Hydroboil' 2kw underbasin electrical water heater.

29

'Kwikot':

1NoDrip tray30

TAPS, VALVES, ETC.

TANKS

2No5000 Litre jojo tank complete with lid including concrete plinth as per engineers details

31

JOJO tanks

-65-

PLUMBING AND DRAINAGEBill No. 13Section No. 2

Carried Forward R

Page 66: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

8No15mm "Cobra 108" brass hose bibtap with hose union.32

'Cobra-Watertech':

8No15mm 'Star 106-CP' bibtap.33

1No15mm 'Star 111-CP' raised nose pillartap.34

1No15mm Type '505-21 CP' elbow action pillartap.35

1No15mm 'Capstan CSS-115/044-CP' pillar tap.36

1No15mm Type '1090 Ball-o-flo' ballcock.37

1NoDitto, but 20mm ballcock.38

1NoDitto, but 25mm ballcock.39

5No15mm Type 'P-832 CP' angle regulating valve.40

5No15mm Type '350F CP' flexible connection.41

5No40mm Float valve.42

WASTE UNIONS, TRAPS, ETC.

5No

32 x 40mm 'Flexitrap' butyl rubber deep seal 'P' or 'S' trap jointed to waste outlet fitting and to PVC pipe including coupling clamps, etc.

43

'Marley':

5No

40 x 40mm 'Flexitrap' butyl rubber deep seal 'P' or 'S' trap jointed to waste outlet fitting and to PVC pipe including coupling clamps, etc.

44

5NoDitto, but combination trap.45

1No40mm Chromium plated '316CP' sink waste union complete with plug and chain.

46

'Cobra Watertech':

5No40mm 360 CP bottle trap47

-66-

PLUMBING AND DRAINAGEBill No. 13Section No. 2

Carried Forward R

Page 67: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

2No32mm Chromium plated '303-CP' slotted basin waste union complete with plug only.

48

2No

'Herbish HB 200 V (H) NW 100' stainless steel grade 304 floor drain with vertical bottom outlet size 240 x 240 x 210mm deep fitted and connected complete.

49

Floor drains, etc:

FIRE APPLIANCES, ETC.

1No

"Everyway" hose reel complete with 30m plastic hose, chromium plated stopcock, shut-off nozzle and wall bracket

50

Fire hose reels, etc.:

4No

4,5kg Dry chemical powder fire extinguisher fixed to wall with meranti backboard, size 520 x 100 x 22mm thick, plugged and screwed to wall complete with hook.

51

-67-

PLUMBING AND DRAINAGEBill No. 13Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 68: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO. 14

GLAZING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

GLAZING TO STEEL WITH PUTTY

36m2Panes exceeding 0,1m² and not exceeding 0,5m².1

4mm Clear float glass:

7m2Panes exceeding 0,1m2 and not exceeding 0,5m2.2

4mm Opaque float glass:

TOPS, SHELVES, DOORS, MIRRORS, ETC.

-68-

GLAZINGBill No. 14Section No. 2

Carried Forward R

Page 69: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

4NoMirror 450 x 600mm high with four screws.3

6mm 'GG' quality polished silvered float glass copper backed mirrors with polished edges holed for and fixed with round rose chromium plated mirrror screws with rubber buffers to plugs in brickwork or concrete:

-69-

GLAZINGBill No. 14Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 70: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 2

BILL NO. 15

PAINTWORK

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

SUPPLEMENTARY PREAMBLES

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

PREPARATORY WORK TO EXISTING WORK

Surfaces shall be thoroughly washed down and allowed to dry completely before any paint is applied. Blistered or peeling paint shall be completely removed and cracks shall be opened, filled with a suitable filler and finished smooth

Previously painted plastered surfaces

Surfaces shall be thoroughly cleaned down. Blistered or peeling paint shall be completely removed and cracks and crevices shall be primed, filled with suitable filler and finished smooth

Previously painted wood surfaces

-70-

PAINTWORKBill No. 15Section No. 2

Carried Forward R

Page 71: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Surfaces shall be thoroughly rubbed and cleaned down. Blistered or peeling paint shall be completely removed down to bare metal

Previously painted metal surfaces

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

ON FLOATED PLASTER SURFACES

175m2Interior walls.1

Prepare surfaces and remove all loose material, apply one coat alkaline resistant primer, one universal undercoat two coats eggshell enamel paint on:

175m2Interior walls.2

Prepare surfaces and remove all loose material, apply one coat alkaline resistant pure acrylic filler coat and two coats acrylic PVA paint on:

ON METAL

82m2Windows (both sides measured).3

Prepare, spot primer defects in pre-primed surfaces with red oxide primer and apply one coat synthetic metal primer, one universal undercoat and one finishing coat of high gloss enamel paint on:

9m2Door frames.4

14m2Burglar gates.5

82m2Burglar bars to windows.6

53m2Structural steel beams and columns.7

ON WOOD

-71-

PAINTWORKBill No. 15Section No. 2

Carried Forward R

Page 72: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

31m2Roof timbers at eaves and verges.8

Prepare and apply two coats carbolineum on:

12m2Wall plate.9

7m2Exterior doors.10

Stop, sand down, prepare and apply two coats polyurethane varnish on:

163mSkirtings and quadrant bead, rails, etc., not exceeding 300 mm girth.

11

23m2Interior doors.12

Prepare and apply one coat pink wood primer, stop and apply two finishing coats of non-drip semi-gloss polyurethane enamel on:

ON FIBRE-CEMENT

124m2General surfaces of ceilings.13

Prepare and apply one coat zinc chromate to nail heads and H-spline strips, one universal undercoat, stop and apply two finishing coats of eggshell enamel on:

74m2Fascias, bargeboards, etc.14

PLASTERBOARD

43m2General surfaces of ceilings.15

Prepare, prime nail heads and strips with zinc chromate primer, one universal undercoat and two finishing coats of semi-gloss PVA on:

-72-

PAINTWORKBill No. 15Section No. 2

Carried Forward to Summary of Section No. 2 R

Page 73: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION SUMMARY - NEW 1 x GRADE R

BillNo

PageNo

Amount

32EARTHWORKS1

35CONCRETE,FORMWORK AND REINFORCEMENT2

40MASONRY3

41WATERPROOFING4

43ROOF COVERINGS5

46CARPENTRY AND JOINERY6

48CEILING PARTITIONS ACCESS FLOORING7

52IRONMONGERY8

53STRUCTURAL STEELWORK9

56METALWORK10

58PLASTERING11

60TILING12

67PLUMBING AND DRAINAGE13

69GLAZING14

72PAINTWORK15

-73-

Section No. 2

Carried to Final Summary R

Page 74: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO 1

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

The nature of the ground is assumed to be loose sandy material, therefore "earth", but possibly interspersed with "hard rock" or "soft rock".

Nature of ground

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or alternatively, from stock piles situated on the building site.

CARTING AWAY OF EXCAVATED MATERIAL

Prices for all filling and carting away of surplus material must make allowance for bulking.

PRICES

The Tenderer is referred to the relevant Clauses in the separate document Model Preambles for Trades (2008 Edition) and the Supplementary Preambles hereunder.

EARTHWORKS (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

The nature of the ground is assumed to be gravel, therefore earth, but possibly interspersed with soft rock.

Nature of ground:

-74-

EARTHWORKSBill No. 1Section No. 3

Carried Forward R

Page 75: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or, alternatively, from stock piles situated on the building site.

Carting away of excavated material:

BULK EXCAVATION, FILLING, ETC.

34m3Open face excavation.1

Open face excavation in earth over flat site:

3m3Soft rock.2

Extra over bulk excavation in earth for excavation in:

2m3Hard rock.3

FILLING

201m3Under surface beds4

Filling with approved material supplied and carted onto site by the Contractor, compacted to a density of at least 95% Mod. AASHTO maximum density:

EXCAVATION OTHER THAN BULK

48m3Trenches for strip footings5

Excavation in earth not exceeding 2m deep:

3m3Holes6

CARTING AWAY

101m3Surplus material from excavation and/or stockpile on siteto a dumping site to be allocated by the contractor.

7

Extra over all excavations for carting away:

109m2Sides of trenches not exceeding 1,5m deep.8

Risk of collapse of excavations:

-75-

EARTHWORKSBill No. 1Section No. 3

Carried Forward R

Page 76: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

83m2Sides of bulk excavations not exceeding 1,5m deep.9

ItemKeeping excavations free of all water other than subterranean water.

10

Keeping excavations free of water:

288m2

Under floors, etc. Including forming and poisoning shallow furrows against foundation walls etc., filling in furrows and ramming.

11

Soil insecticide:

155m2To bottoms and sides of trenches etc.12

CONCRETE

(CPAP FORMULA WORK GROUP NO. 110)

UNREINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

22m3Strip footings13

25MPa/19mm concrete

2.34t10mm Diameter bars.14

High tensile steel reinforcement to structural concrete work:

3.58t8mm Diameter bars.15

The Tenderer is referred to the relevant Clauses in the separate document Model Preambles for Trades (2008 Edition) and the Supplementary Preambles hereunder.

BRICKWORK IN FOUNDATIONS

4m3Piers16

Brickwork of NFX bricks (14 MPa nominal compressive strength) in Class I mortar:

69m2One brick walls17

-76-

EARTHWORKSBill No. 1Section No. 3

Carried Forward R

Page 77: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

692m150mm Wide reinforcement built in horizontally18

Brickwork reinforcement

29m2Extra over brickwork for face brickwork19

External face bricks (Prime Cost Amount R 4000.00/1000) pointed with flush horizontal and vertical joints

8mFair cutting at squint quoin or birdsmouth angle20

-77-

EARTHWORKSBill No. 1Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 78: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO. 2

CONCRETE, FORMWORK AND REINFORCEMENT

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

The contractor is refered to the Model Preambles for Trades (2008 edition) as issued the Association of South African Quantity Surveyors before pricing this bill

SUPPLEMENTARY PREAMBLES

Cost of tests

The costs of making, storing and testing of concrete test cubes as required under clause 7 "Tests" of SABS 1200 G shall include the cost of providing cube moulds necessary for the purpose, for testing costs and for submitting reports on the tests to the architect. The testing shall be undertaken by an independent firm or institution nominated by the contractor to the approval of the architect. (Test cubes are measured separately).

Formwork

Descriptions of formwork shall be deemed to include use and waste only (except where described as "left in" or "permanent"), for fitting together in the required forms, wedging, plumbing and fixing to true angles and surfaces as necessary to ensure easy release during stripping and for reconditioning as necessary before re-use.

The vertical strutting shall be carried down to such construction as is sufficiently strong to afford the required support without damage and shall remain in position until the newly constructed work is able to support itself.

-78-

CONCRETE, FORMWORK AND REINFORCEMENTBill No. 2Section No. 3

Carried Forward R

Page 79: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Formwork to soffits of solid slabs etc shall be deemed to be to slabs not exceeding 250mm thick unless otherwise described

Formwork to sides of bases, pile caps, ground beams, etc will only be measured where it is prescribed by the engineer for design reasons.

Formwork necessitated by irregularity or collapse of excavated faces will not be measured and the cost thereof shall be deemed to be included in the allowance for taking the risk of collapse of the sides of the excavations, provision for which is made in "Earthworks"

REINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

43m3Surface beds on waterproofing1

25 MPa/19mm Concrete:

5m3Slabs including beams and inverted beams2

15m3Aprons cast in panels to falls 3

85m2Aprons to falls 4

Finishing top surfaces of concrete smooth with a wood float

42m2

Forming 250mm wide segmental channel to falls in concrete including finishing smooth

5

TEST BLOCKS

14.0SetsMaking and testing set of three 150 x 150 x 150mm concrete strength test cubes.

6

Test blocks:

FINISHING TOP SURFACE OF CONCRETE

287m2Surface beds, slabs, etc.7

Finishing top surfaces of concrete smooth with a steel trowel:

-79-

CONCRETE, FORMWORK AND REINFORCEMENTBill No. 2Section No. 3

Carried Forward R

Page 80: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

ROUGH FORMWORK (DEGREE OF ACCURACY III) (CPAP Work Group No 111)

119mEdges, risers, ends and reveals not exceeding 300mm high or wide.

8

Rough Formwork to Sides:

11m2Slabs propped up exceeding 1,5m and not exceeding 3,5m high

9

MOVEMENT JOINTS, ETC.

158mNot exceeding 300mm wide.10

Two layers of 375 micron dampproof course in slip joints between horizontal concrete and brick surfaces including cement mortar bed.:

REINFORCEMENT (CPAP Work Group No 114) (MEASURED PROVISIONALLY)

287m2Type 395 fabric reinforcement in concrete surface beds, etc.

11

Fabric reinforcement:

4.68t10mm Diameter bars.12

High tensile steel reinforcement to structural concrete work:

7.16t8mm Diameter bars.13

-80-

CONCRETE, FORMWORK AND REINFORCEMENTBill No. 2Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 81: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO. 3

MASONRY

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

BRICKWORK

Where sizes in descriptions are given in brick units, "one brick" shall represent the length and "half brick" the width of a brick

Sizes in descriptions

Descriptions of hollow walls shall be deemed to include leaving every fifth perpend of the bottom course of the external skin open as a weep hole.

Hollow walls etc

Walls in two skins described as "bagged and sealed" shall be deemed to include having the outer face of the inner skin bagged with 1:6 cement and sand mixture and sealed with two coats "Brixeal" bitumen emulsion waterproofing coating.

The above preamble generally applies for works in hot and humid coastal areas

User note:

Bricks shall be ordered timeously to obtain uniformity in size and colour

Face bricks

-81-

MASONRYBill No. 3Section No. 3

Carried Forward R

Page 82: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Descriptions of recessed pointing to fair face brickwork and face brickwork shall be deemed to include square recessed, hollow recessed, weathered pointing, etc

Pointing

BLOCKWORK

Blocks are to be either solid or hollow modular dense concrete masonry units having a compressive strength of 7 MPa

Concrete masonry units

Wall ties shall be polypropylene "Permaties" complying with BS 76377. Ties for hollow walls shall be of sufficient length to allow not less than 75mm of each end to be built into the blockwork. Ties are to be spaced at intervals of not more than 1m in the horizontal direction and not more than 400mm staggered in the vertical direction except at openings, vertical joints or ends of walls where they are to be placed vertically above each other

Wall ties for blockwork

Blockwork shall comply with SABS 0145 "Concrete Masonry Construction"

Surfaces to be plastered shall have joints raked out to a depth of at least 10mm to provide a key. Cavities of hollow walls shall be kept free of mortar droppings or other undesirable matter. Every second perpend of the bottom course of the external skin of hollow walls shall be left open as a weep hole

Blockwork

Descriptions of blockwork shall be deemed to include standard complementary blocks such as corner, three-quarter, half and quarter blocks required in the construction of corners, reveals, jambs, ends, etc to solid and hollow walls and for bonding as necessary

Standard complementary blocks

-82-

MASONRYBill No. 3Section No. 3

Carried Forward R

Page 83: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Blocks shall be of approved manufacture, sound, well burnt or cured and uniform and true in size, shape and colour

DECORATIVE BLOCKS

Samples of all masonry building units, except those for walls described as "load bearing", shall consist of a minimum of 6 units. Samples of building units to be used in walls described as "load bearing" shall consist of30 units from every 30 000 units delivered to site

SAMPLES

44m2Half brick walls.1

Brickwork of NFX bricks (14 MPa nominal compressive strength) in Class I mortar:

25m2Ditto, but in beamfilling.2

29m2Ditto, but in firewall.3

59m2One brick walls.4

35m2Ditto, but in firewall.5

232m2One brick walls of two half brick skins.6

19m2One brick walls of two half brick skins in gable walls.7

45m2340mm Hollow walls of two half brick skins (no wire ties).

8

6m3Piers.9

45mClosing 120mm cavities of hollow walls horizontally with one course of brickwork.

10

BRICKWORK SUNDRIES

170m75mm Wide reinforcement built in horizontally.11

Brickwork reinforcement:

1 514m150mm Wide reinforcement built in horizontally.12

-83-

MASONRYBill No. 3Section No. 3

Carried Forward R

Page 84: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

52m110 x 70mm Lintels in lengths not exeeding 3m.13

Prestressed fabricated precast lintels including necessary temporary supports:

4m110 x 70mm Lintels in lengths exceeding 3m and not exeeding 4.5m.

14

4mPair of 110 x 70mm Lintels in lengths not exeeding 3m.15

39m150mm Wide turning piece to lintels etc.16

Turning pieces to lintels, etc:

34m220mm Wide turning piece to lintels etc.17

112No4mm Diameter roof tie 2m girth bent double with one end fixed to timber and other end built into brickwork.

18

Galvanised wire ties etc:

16No229 x 152mm Terracota airbricks19

Air bricks etc:

FACE BRICKWORK

377m2Extra over brickwork for face brickwork.20

Face bricks (Allow a P.C. Amount of R4 000.00 per 1 000 supplied and delivered to site) pointed with 6mm square recessed horizontal and vertical joints:

6m2Extra over brickwork for facing 220 x 220mm piers.21

22m2Extra over brickwork for facing 330 x 330mm piers.22

19m2Extra over brickwork for facing gable walls.23

18m2Extra over brickwork for facing beamfilling.24

36m230mm Wide sill set sloping and slightly projecting.25

34mFace brick-on-edge header course lintel.26

-84-

MASONRYBill No. 3Section No. 3

Carried Forward R

Page 85: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

121mExtra over brickwork for face brick-on-edge header course plinth.

27

39mCut face brick-on-edge header course lintel 110mm wide.

28

22mFair raking cutting.29

FIBRE CEMENT WINDOW CILLS

36m140mm Wide cills set flat and slightly projecting.30

15mm Thick natural grey cills in single length bedded in 4:1 sand cement mortar including metal lugs, etc:

-85-

MASONRYBill No. 3Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 86: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO 4

WATERPROOFING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

Waterproofing of roofs, basements, etc shall be laid under a ten year guarantee. Waterproofing to roofs shall be laid to even falls to outlets etc with necessary ridges, hips and valleys. Descriptions of sheet or membrane waterproofing shall be deemed to include additional labour to turn-ups and turn-downs

Waterproofing

DAMPPROOFING OF WALLS AND FLOORS

47m2In walls, under cills, etc.1

One layer of 375 micron embossed polyethylene dampproof course (SANS 952-1985 type B)

287m2Under surface beds.2

One layer of 250 micron green polyethylene waterproof sheeting (SANS 952-1985 type C) sealed at laps with PVC self-adhesive tape:

JOINT SEALANTS, ETC.

86m3 x 50mm In saw cut joints in floors.3

Two-part grey polysulphide sealing compond including backing cord, bond breaker, primer,etc.

175m15 x 10mm In isolation joints including raking out isolation joint filler.

4

-86-

WATERPROOFINGBill No. 4Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 87: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO 5

ROOF COVERINGS, ETC.

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

CORRUGATED METAL SHEETING AND ACCESSORIES

359m2Roof covering with pitch not exceeding 25 degrees.1

0,6mm IBR concealed fix Colomet finished steel sheeting and accessories fixed to timber purlins (elsewhere):

76m2Roof covering with pitch not exceeding 25 degrees.2

0.6mm Kliplok roof sheeting in cromadek finish

17mRidge capping to suit roof profile.3

0,6mm Colomet flashings:

10mHip capping to suit roof profile.4

RAINWATER DISPOSAL

120m100x 75mm Eaves gutters.5

Seamless aluminium gutters.

8NoExtra over gutter for stopped end.6

8NoExtra over gutter for angle.7

-87-

ROOF COVERINGBill No. 5Section No. 3

Carried Forward R

Page 88: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

8NoExtra over 100 x 75mm eaves gutter for outlet for 75mm diameter pipe.

8

24m75mm Diameter rainwater pipes.9

8NoExtra over rainwater pipe for bend.10

8NoExtra over rainwater pipe for eaves offset 500mm projection.

11

ROOF INSULATION

330m2

Insulation laid taut over battens (at approximately 380mm centres) and fixed concurrent with roof covering including galvanised steel straining wires, laps, etc.

12

'Sisalation 420' or similar approved heavy industrial grade aluminium foil based insulation.:

-88-

ROOF COVERINGBill No. 5Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 89: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO. 6

CARPENTRY AND JOINERY

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Descriptions of frames shall be deemed to include frames, transomes, mullions, rails, etc

Joinery:

Descriptions of hardwood joinery shall be deemed to include pelleting of bolt holes

-89-

CARPENTRY AND JOINERYBill No. 6Section No. 3

Carried Forward R

Page 90: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or shot pins to brickwork or concrete

Fixing

PREFABRICATED ROOF TRUSSES, ETC.

92m114 x 38mm Wall plates.1

Sawn softwood:

1No

Trusses for rectangular shaped building, size overall 40 x 15m on plan (4 Classroom).

2

Prefabricated timber roof construction complete including purlins, runners, bracing hips, valleys, cleats, purlins, etc., supplied and fixed complete:

EAVES, VERGES, ETC.

67m12 x 225mm Fascia and barge boards, including galvanised steel H-profile joiners, etc.

3

Medium density plain fibre-cement fascial and barge boards:

SKIRTINGS

192m19 x 76mm Skirtings including 19mm quadrant bead, nailed.

4

Wrought meranti:

192m19 x 50mm Cornice laid flat.5

106m16 x 150mm dado rail.6

FRAMED DOORS, ETC.

4No

40mm Framed batten door 813 x 2032mm high of top rail and stiles, middle ledge and braces and bottom rail filled in with V-jointed one side boarding.

7

Wrought meranti doors hung to steel frames:

-90-

CARPENTRY AND JOINERYBill No. 6Section No. 3

Carried Forward R

Page 91: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

4No44mm Door 813 x 2 032mm high8

Semi-solid flush doors with sapele veneer on both sides hung to steel frames

-91-

CARPENTRY AND JOINERYBill No. 6Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 92: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO. 7

CEILINGS, PARTITIONS AND ACCESS FLOORING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or pins or shot pinned to brickwork or concrete

Descriptions:

Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 600mm centres, and where described as "bolted" the bolts have been given elsewhere

-92-

CEILINGS, PARTITIONS AND ACCESS FLOORINGBill No. 7Section No. 3

Carried Forward R

Page 93: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Electrical light fittings, diffusers, panels, etc generally are "lay in" units of the same dimensions as the suspension grid described and allowance must be made accordingly for their support inclusive of any flexibility insetting out that may be required (ceiling panels have not been deducted and pricing is to take cognisance thereof)

NAILED UP AND SCREW UP CEILINGS

317m2

Ceilings including 38 x 38mm sawn softwood brandering at 450mm centres with cross brandering at 450mm centres and at joints, ends of sheets and at light fittings, etc.

1

6,4mm Gypsum plasterboards with H-profile galvanised steel jointing strips:

4No

Extra over ceiling for 600 x 600mm hinged trap door of wrought softwood rebated framing with one sawn softwood cross brander covered with ceiling board and fitted flush in opening, including necessary trimmers all around.

2

76m2

Ceilings including 38 x 38mm sawn softwood brandering at 450mm centres with cross brandering at 450mm centres and at joints, ends of sheets and at light fittings, etc.

3

6mm Fibre-cement plain ceiling boards with H-profile galvanised steel jointing strips:

4No

Extra over ceiling for 600 x 600mm hinged trap door of wrought softwood rebated framing with one sawn softwood cross brander covered with ceiling board and fitted flush in opening, including necessary trimmers all around.

4

INSULATION

287m2100mm Insulation closely fitted between tie beams and laid loose on top of brandering.

5

Non-combustible lightweight fibreglass insulation blanket:

-93-

CEILINGS, PARTITIONS AND ACCESS FLOORINGBill No. 7Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 94: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO. 8

IRONMONGERY

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Where applicable finishes to ironmongery are indicated by suffixes in accordance with the following list: BS Satin bronze lacquered CH Chromium plated SC Satin chromium plated SE Silver enamelled GE Grey enamelled AS Anodised silver AB Anodised bronze AG Anodised gold ABL Anodised black PB Polished brass PL Polished and lacquered PT Epoxy coated SD Sanded

Finishes to ironmongery

"Union"

-94-

IRONMONGERYBill No. 8Section No. 3

Carried Forward R

Page 95: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

IRONMONGERY FIXED TO DOORS, ETC.

8No75mm Four lever security lockset with satin chrome furniture.

1

LOCKS:

DOOR CLOSERS

4NoTS 68 door closer with parallel arm, bracket fixed to metal.

2

Dorma:

NUMERAL AND NAMEPLATES, ETC.

4NoDitto, but with letters "CLASSROOM".3

Clear perspex name plate reverse engraved and enamelled in white lettering 25mm high to suit, twice countersunk holed for and tapscrewed to steel door frames or gate framing with chromium plated dome-headed selftapping screws:

4NoDitto, but with letters "STORE ROOM".4

4No

190 x 190 x 3mm Thick white perspex international FB2 sign plate with red fire extinguisher symbol plugged to brickwork.

5

Indicator plates countersunk holed for and screwed to door or brickwork with chromium plated dome-headed screws:

4No38mm Rubber stop plugged and srewed to wall or floor.6

SUNDRIES

4NoNickel plated steel leaf spring door holder with rubber door stop plugged and screwed to floor.

7

7m3 x 25mm Brass dividing strip between different floor finishes.

8

PINNING BOARDS, WRITING BOARDS, PROJECTION SCREENS, ETC.

-95-

IRONMONGERYBill No. 8Section No. 3

Carried Forward R

Page 96: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

4NoPinning board size 2400 x 1200mm high plugged.9

Carpet pinning boards in aluminium frame with round plastic corners, pen tray and fixing component all fixed according to manufacturer's instruction.

4NoDitto, but size 4200 x 1200mm high plugged.10

4No

Chalk board size overall 1140mm high x 3600mm wide consisting of 1 x chalkboard 1800mm wide, 2 x chalkboard 900mm wide, 2 x swing type chalkboard 900mm wide.

11

Swing type green chalkboard to comply with CKS-36-1980 or equivalent code of practice, complete with chalk rail as one unit fixed to wall strictly according to manufacturers instruction:

4NoWhite board size 2 x 2400 x 1140mm high.12

White board marker board surface wall mounted complete with integrated pen tray according to manufacturers instruction:

-96-

IRONMONGERYBill No. 8Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 97: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO.9

STRUCTURAL STEELWORK

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions

Descriptions of L-shaped and U-shaped anchor bolts shall be deemed to include bending, threading, nuts and washers and embedding in concrete

Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

STEEL COLUMNS AND BEAMS

19No76 x 76mm x 3.0mm, 2.27m high column1

Mild steel welded columns in single lengths with flat section base, top, bearer and connection plates bolted to roof on floors and roof trusses

76m150 x 150mm x 75mm beam2

Welded beams in single lengths with flat section bearer and connection plates bolted to 76mm columns

5.60tHigh tensile bolts3

Bolts

-97-

STRUCTURAL STEELWORKBill No. 9Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 98: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO. 10

METALWORK

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions

Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

Metalwork described as"holed for bolt(s)" shall be deemed to exclude the bolts unless otherwise described

-98-

METALWORKBill No. 10Section No. 3

Carried Forward R

Page 99: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

STEEL WINDOWS, DOORS, ETC.

36NoWindow 01, 1143 x 1280mm high with one opening light1

Standard residential windows with steel burglar bars to fixed lights and opening sashes:

8NoWindow 02, 1143 x 854mm high with one opening light2

PRESSED STEEL DOOR FRAMES

4NoFrame for door 914 x 2032mm high.3

1,2mmSingle rebated frames suitable for one brick walls:

4NoFrame for door 914 x 2032mm high.4

1,2mm Double rebated frames suitable for one brick walls:

STEEL STRONGROOM DOORS, VENTILATORS, ETC.

8NoSteel louvre unit according to NTY5

Steel Louvres

SECURITY GATES

4NoSize 925mm x 1800mm high, as per door schedule. (G12)

6

Steel security gates:

Handrail

38m60 x 60 x 4 mm Thick square hollow section handrail.7

The following in galvanized mild steel handrails framed and welded together including shopcoat as described:

8No76 x 76 x 3mm Mild steel square tubing 8

-99-

METALWORKBill No. 10Section No. 3

Carried Forward R

Page 100: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

151m25 x 25 x 5 mm Angle framing including mitred intersections.

9

12NoStop end.10

32No10 x 75 mm Expanding bolt including fixing to concrete or brickwork.

11

-100-

METALWORKBill No. 10Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 101: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO. 11

PLASTERING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

96m2

22,5mm thick sand cement screed, finished with a steel

float and prepared to receive vinyl tiles (elsewhere

measured).

1

SCREEDS

48m2Ditto, but 32,5mm Thick.2

-101-

PLASTERINGBill No. 11Section No. 3

Carried Forward R

Page 102: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

GRANOLITHIC

48m235mm Thick on floors and walkways3

Untinted granolithic on concrete

INTERNAL PLASTER

752m2On walls.4

One coat cement plaster steel trowelled on brickwork.

5m2On narrow widths.5

-102-

PLASTERINGBill No. 11Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 103: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO. 12

TILING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Unless described as "fixed with adhesive to plaster (plaster elsewhere)" descriptions of tiling on brick or concrete walls, columns, etc shall be deemed to include 1:4 cement plaster backing and descriptions of tiling on concrete floors etc shall be deemed to include 1:3 plaster bedding

Descriptions

FLOOR TILING

-103-

TILINGBill No. 12Section No. 3

Carried Forward R

Page 104: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

318m2On floors and landings1

300 x 300mm x 8mm Ceramic tiles (PC Amount R150.00/m2) fixed with adhesive to bedding (bedding elsewhere) and flush pointed with tinted waterproof jointing compound

175mSkirting 75mm high2

-104-

TILINGBill No. 12Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 105: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO. 13

PLUMBING AND DRAINAGE (PROVISIONAL)

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

TANKS

2No5000 Litre jojo tank complete with lid including concrete plinth as per engineers details

1

JOJO tanks

FIRE APPLIANCES, ETC.

1No

"Everyway" hose reel complete with 30m plastic hose, chromium plated stopcock, shut-off nozzle and wall bracket

2

Fire hose reels, etc.:

8No

4,5kg Dry chemical powder fire extinguisher fixed to wall with meranti backboard, size 520 x 100 x 22mm thick, plugged and screwed to wall complete with hook.

3

-105-

PLUMBINGBill No. 13Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 106: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO. 14

The Tenderer is referred to the relevant clauses in the separate document Model Preambles for Trades (2008 Edition).

GLAZING

GLAZING TO STEEL WITH PUTTY

55m2Panes exceeding 0,1m² and not exceeding 0,5m².1

4mm Clear float glass:

-106-

GLAZINGBill No. 14Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 107: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 3

BILL NO. 15

PAINTWORK

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

SUPPLEMENTARY PREAMBLES

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

PREPARATORY WORK TO EXISTING WORK

Surfaces shall be thoroughly washed down and allowed to dry completely before any paint is applied. Blistered or peeling paint shall be completely removed and cracks shall be opened, filled with a suitable filler and finished smooth

Previously painted plastered surfaces

Surfaces shall be thoroughly cleaned down. Blistered or peeling paint shall be completely removed and cracks and crevices shall be primed, filled with suitable filler and finished smooth

Previously painted wood surfaces

-107-

PAINTWORKBill No. 15Section No. 3

Carried Forward R

Page 108: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Surfaces shall be thoroughly rubbed and cleaned down. Blistered or peeling paint shall be completely removed down to bare metal

Previously painted metal surfaces

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

ON FLOATED PLASTER SURFACES

752m2Interior walls.1

Prepare surfaces and remove all loose material, apply one coat alkaline resistant primer, one universal undercoat two coats eggshell enamel paint on:

ON METAL

57m2Windows (both sides measured).2

Prepare, spot primer defects in pre-primed surfaces with red oxide primer and apply one coat synthetic metal primer, one universal undercoat and one finishing coat of high gloss enamel paint on:

5m2Door frames.3

15m2Burglar gates.4

57m2Burglar bars to windows.5

55m2Structural steel beams and columns.6

ON WOOD

54m2Roof timbers at eaves and verges.7

Prepare and apply two coats carbolineum on:

40m2Wall plate.8

-108-

PAINTWORKBill No. 15Section No. 3

Carried Forward R

Page 109: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

26m2Exterior doors.9

Stop, sand down, prepare and apply two coats polyurethane varnish on:

121mSkirtings and quadrant bead, rails, etc., not exceeding 300 mm girth.

10

ON FIBRE-CEMENT

287m2General surfaces of ceilings.11

Prepare and apply one coat zinc chromate to nail heads and H-spline strips, one universal undercoat, stop and apply two finishing coats of eggshell enamel on:

45m2Fascias, bargeboards, etc.12

PLASTERBOARD

77m2General surfaces of ceilings.13

Prepare, prime nail heads and strips with zinc chromate primer, one universal undercoat and two finishing coats of semi-gloss PVA on:

-109-

PAINTWORKBill No. 15Section No. 3

Carried Forward to Summary of Section No. 3 R

Page 110: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION SUMMARY - NEW 1 x 4 CLASSROOM BLOCK

BillNo

PageNo

Amount

77EARTHWORKS1

80CONCRETE, FORMWORK AND REINFORCEMENT2

85MASONRY3

86WATERPROOFING4

88ROOF COVERING5

91CARPENTRY AND JOINERY6

93CEILINGS, PARTITIONS AND ACCESS FLOORING7

96IRONMONGERY8

97STRUCTURAL STEELWORK9

100METALWORK10

102PLASTERING11

104TILING12

105PLUMBING13

106GLAZING14

109PAINTWORK15

-110-

Section No. 3

Carried to Final Summary R

Page 111: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO 1

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

The nature of the ground is assumed to be loose sandy material, therefore "earth", but possibly interspersed with "hard rock" or "soft rock".

Nature of ground

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or alternatively, from stock piles situated on the building site.

CARTING AWAY OF EXCAVATED MATERIAL

Prices for all filling and carting away of surplus material must make allowance for bulking.

PRICES

The Tenderer is referred to the relevant Clauses in the separate document Model Preambles for Trades (2008 Edition) and the Supplementary Preambles hereunder.

EARTHWORKS (PROVISIONAL)

SUPPLEMENTARY PREAMBLES

The nature of the ground is assumed to be gravel, therefore earth, but possibly interspersed with soft rock.

Nature of ground:

-111-

EARTHWORKSBill No. 1Section No. 4

Carried Forward R

Page 112: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or, alternatively, from stock piles situated on the building site.

Carting away of excavated material:

BULK EXCAVATION, FILLING, ETC.

25m3Open face excavation.1

Open face excavation in earth over flat site:

3m3Soft rock.2

Extra over bulk excavation in earth for excavation in:

2m3Hard rock.3

FILLING

94m3Under surface beds4

Filling with approved material supplied and carted onto site by the Contractor, compacted to a density of at least 95% Mod. AASHTO maximum density:

EXCAVATION OTHER THAN BULK

90m3Trenches for strip footings5

Excavation in earth not exceeding 2m deep:

4m3Holes6

CARTING AWAY

47m3Surplus material from excavation and/or stockpile on siteto a dumping site to be allocated by the contractor.

7

Extra over all excavations for carting away:

51m2Sides of trenches not exceeding 1,5m deep.8

Risk of collapse of excavations:

-112-

EARTHWORKSBill No. 1Section No. 4

Carried Forward R

Page 113: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

16m2Sides of bulk excavations not exceeding 1,5m deep.9

ItemKeeping excavations free of all water other than subterranean water.

10

Keeping excavations free of water:

282m2

Under floors, etc. Including forming and poisoning shallow furrows against foundation walls etc., filling in furrows and ramming.

11

Soil insecticide:

64m2To bottoms and sides of trenches etc.12

CONCRETE

(CPAP FORMULA WORK GROUP NO. 110)

UNREINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

42m3Strip footings13

25MPa/19mm concrete

4.39t10mm Diameter bars.14

High tensile steel reinforcement to structural concrete work:

6.72t8mm Diameter bars.15

The Tenderer is referred to the relevant Clauses in the separate document Model Preambles for Trades (2008 Edition) and the Supplementary Preambles hereunder.

BRICKWORK IN FOUNDATIONS

4m3Piers16

Brickwork of NFX bricks (14 MPa nominal compressive strength) in Class I mortar:

130m2One brick walls17

-113-

EARTHWORKSBill No. 1Section No. 4

Carried Forward R

Page 114: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

649m150mm Wide reinforcement built in horizontally18

Brickwork reinforcement

27m2Extra over brickwork for face brickwork19

External face bricks (Prime Cost Amount R 4000.00/1000) pointed with flush horizontal and vertical joints

8mFair cutting at squint quoin or birdsmouth angle20

-114-

EARTHWORKSBill No. 1Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 115: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO. 2

CONCRETE, FORMWORK AND REINFORCEMENT

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

The contractor is refered to the Model Preambles for Trades (2008 edition) as issued the Association of South African Quantity Surveyors before pricing this bill

SUPPLEMENTARY PREAMBLES

Cost of tests

The costs of making, storing and testing of concrete test cubes as required under clause 7 "Tests" of SABS 1200 G shall include the cost of providing cube moulds necessary for the purpose, for testing costs and for submitting reports on the tests to the architect. The testing shall be undertaken by an independent firm or institution nominated by the contractor to the approval of the architect. (Test cubes are measured separately).

Formwork

Descriptions of formwork shall be deemed to include use and waste only (except where described as "left in" or "permanent"), for fitting together in the required forms, wedging, plumbing and fixing to true angles and surfaces as necessary to ensure easy release during stripping and for reconditioning as necessary before re-use.

The vertical strutting shall be carried down to such construction as is sufficiently strong to afford the required support without damage and shall remain in position until the newly constructed work is able to support itself.

-115-

CONCRETE, FORMWORK AND REINFORCEMENTBill No. 2Section No. 4

Carried Forward R

Page 116: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Formwork to soffits of solid slabs etc shall be deemed to be to slabs not exceeding 250mm thick unless otherwise described

Formwork to sides of bases, pile caps, ground beams, etc will only be measured where it is prescribed by the engineer for design reasons.

Formwork necessitated by irregularity or collapse of excavated faces will not be measured and the cost thereof shall be deemed to be included in the allowance for taking the risk of collapse of the sides of the excavations, provision for which is made in "Earthworks"

REINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

8m3Surface beds on waterproofing1

25 MPa/19mm Concrete:

2m3Slabs including beams and inverted beams2

6m3Aprons cast in panels to falls 3

63m2Aprons to falls 4

Finishing top surfaces of concrete smooth with a wood float

63m2

Forming 250mm wide segmental channel to falls in concrete including finishing smooth

5

TEST BLOCKS

5.0SetsMaking and testing set of three 150 x 150 x 150mm concrete strength test cubes.

6

Test blocks:

FINISHING TOP SURFACE OF CONCRETE

282m2Surface beds, slabs, etc.7

Finishing top surfaces of concrete smooth with a steel trowel:

-116-

CONCRETE, FORMWORK AND REINFORCEMENTBill No. 2Section No. 4

Carried Forward R

Page 117: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

ROUGH FORMWORK (DEGREE OF ACCURACY III) (CPAP Work Group No 111)

89mEdges, risers, ends and reveals not exceeding 300mm high or wide.

8

Rough Formwork to Sides:

8m2Slabs propped up exceeding 1,5m and not exceeding 3,5m high

9

MOVEMENT JOINTS, ETC.

118mNot exceeding 300mm wide.10

Two layers of 375 micron dampproof course in slip joints between horizontal concrete and brick surfaces including cement mortar bed.:

REINFORCEMENT (CPAP Work Group No 114) (MEASURED PROVISIONALLY)

282m2Type 395 fabric reinforcement in concrete surface beds, etc.

11

Fabric reinforcement:

1.75t10mm Diameter bars.12

High tensile steel reinforcement to structural concrete work:

2.99t8mm Diameter bars.13

-117-

CONCRETE, FORMWORK AND REINFORCEMENTBill No. 2Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 118: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO. 3

MASONRY

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

BRICKWORK

Where sizes in descriptions are given in brick units, "one brick" shall represent the length and "half brick" the width of a brick

Sizes in descriptions

Descriptions of hollow walls shall be deemed to include leaving every fifth perpend of the bottom course of the external skin open as a weep hole.

Hollow walls etc

Walls in two skins described as "bagged and sealed" shall be deemed to include having the outer face of the inner skin bagged with 1:6 cement and sand mixture and sealed with two coats "Brixeal" bitumen emulsion waterproofing coating.

The above preamble generally applies for works in hot and humid coastal areas

User note:

Bricks shall be ordered timeously to obtain uniformity in size and colour

Face bricks

-118-

MASONRYBill No. 3Section No. 4

Carried Forward R

Page 119: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Descriptions of recessed pointing to fair face brickwork and face brickwork shall be deemed to include square recessed, hollow recessed, weathered pointing, etc

Pointing

BLOCKWORK

Blocks are to be either solid or hollow modular dense concrete masonry units having a compressive strength of 7 MPa

Concrete masonry units

Wall ties shall be polypropylene "Permaties" complying with BS 76377. Ties for hollow walls shall be of sufficient length to allow not less than 75mm of each end to be built into the blockwork. Ties are to be spaced at intervals of not more than 1m in the horizontal direction and not more than 400mm staggered in the vertical direction except at openings, vertical joints or ends of walls where they are to be placed vertically above each other

Wall ties for blockwork

Blockwork shall comply with SABS 0145 "Concrete Masonry Construction"

Surfaces to be plastered shall have joints raked out to a depth of at least 10mm to provide a key. Cavities of hollow walls shall be kept free of mortar droppings or other undesirable matter. Every second perpend of the bottom course of the external skin of hollow walls shall be left open as a weep hole

Blockwork

Descriptions of blockwork shall be deemed to include standard complementary blocks such as corner, three-quarter, half and quarter blocks required in the construction of corners, reveals, jambs, ends, etc to solid and hollow walls and for bonding as necessary

Standard complementary blocks

-119-

MASONRYBill No. 3Section No. 4

Carried Forward R

Page 120: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Blocks shall be of approved manufacture, sound, well burnt or cured and uniform and true in size, shape and colour

DECORATIVE BLOCKS

Samples of all masonry building units, except those for walls described as "load bearing", shall consist of a minimum of 6 units. Samples of building units to be used in walls described as "load bearing" shall consist of30 units from every 30 000 units delivered to site

SAMPLES

8m2Half brick walls.1

Brickwork of NFX bricks (14 MPa nominal compressive strength) in Class I mortar:

3m2Ditto, but in beamfilling.2

6m2Ditto, but in firewall.3

28m2One brick walls.4

6m2Ditto, but in firewall.5

43m2One brick walls of two half brick skins.6

9m2One brick walls of two half brick skins in gable walls.7

21m2340mm Hollow walls of two half brick skins (no wire ties).

8

6m3Piers.9

33mClosing 120mm cavities of hollow walls horizontally with one course of brickwork.

10

BRICKWORK SUNDRIES

84m75mm Wide reinforcement built in horizontally.11

Brickwork reinforcement:

1 419m150mm Wide reinforcement built in horizontally.12

-120-

MASONRYBill No. 3Section No. 4

Carried Forward R

Page 121: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

6m110 x 70mm Lintels in lengths not exeeding 3m.13

Prestressed fabricated precast lintels including necessary temporary supports:

6m110 x 70mm Lintels in lengths exceeding 3m and not exeeding 4.5m.

14

6mPair of 110 x 70mm Lintels in lengths not exeeding 3m.15

73m150mm Wide turning piece to lintels etc.16

Turning pieces to lintels, etc:

64m220mm Wide turning piece to lintels etc.17

53No4mm Diameter roof tie 2m girth bent double with one end fixed to timber and other end built into brickwork.

18

Galvanised wire ties etc:

6No229 x 152mm Terracota airbricks19

Air bricks etc:

FACE BRICKWORK

18m2Extra over brickwork for face brickwork.20

Face bricks (Allow a P.C. Amount of R4 000.00 per 1 000 supplied and delivered to site) pointed with 6mm square recessed horizontal and vertical joints:

4m2Extra over brickwork for facing 220 x 220mm piers.21

10m2Extra over brickwork for facing 330 x 330mm piers.22

9m2Extra over brickwork for facing gable walls.23

9m2Extra over brickwork for facing beamfilling.24

18m230mm Wide sill set sloping and slightly projecting.25

18mFace brick-on-edge header course lintel.26

-121-

MASONRYBill No. 3Section No. 4

Carried Forward R

Page 122: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

23mExtra over brickwork for face brick-on-edge header course plinth.

27

18mCut face brick-on-edge header course lintel 110mm wide.

28

18mFair raking cutting.29

FIBRE CEMENT WINDOW CILLS

18m140mm Wide cills set flat and slightly projecting.30

15mm Thick natural grey cills in single length bedded in 4:1 sand cement mortar including metal lugs, etc:

-122-

MASONRYBill No. 3Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 123: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO 4

WATERPROOFING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

Waterproofing of roofs, basements, etc shall be laid under a ten year guarantee. Waterproofing to roofs shall be laid to even falls to outlets etc with necessary ridges, hips and valleys. Descriptions of sheet or membrane waterproofing shall be deemed to include additional labour to turn-ups and turn-downs

Waterproofing

DAMPPROOFING OF WALLS AND FLOORS

34m2In walls, under cills, etc.1

One layer of 375 micron embossed polyethylene dampproof course (SANS 952-1985 type B)

282m2Under surface beds.2

One layer of 250 micron green polyethylene waterproof sheeting (SANS 952-1985 type C) sealed at laps with PVC self-adhesive tape:

JOINT SEALANTS, ETC.

162m3 x 50mm In saw cut joints in floors.3

Two-part grey polysulphide sealing compond including backing cord, bond breaker, primer,etc.

328m15 x 10mm In isolation joints including raking out isolation joint filler.

4

-123-

WATERPROOFINGBill No. 4Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 124: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO 5

ROOF COVERINGS, ETC.

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

CORRUGATED METAL SHEETING AND ACCESSORIES

338m2Roof covering with pitch not exceeding 25 degrees.1

0,6mm IBR concealed fix Colomet finished steel sheeting and accessories fixed to timber purlins (elsewhere):

57m2Roof covering with pitch not exceeding 25 degrees.2

0.6mm Kliplok roof sheeting in cromadek finish

25mRidge capping to suit roof profile.3

0,6mm Colomet flashings:

8mHip capping to suit roof profile.4

RAINWATER DISPOSAL

90m100x 75mm Eaves gutters.5

Seamless aluminium gutters.

6NoExtra over gutter for stopped end.6

6NoExtra over gutter for angle.7

-124-

ROOF COVERINGBill No. 5Section No. 4

Carried Forward R

Page 125: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

6NoExtra over 100 x 75mm eaves gutter for outlet for 75mm diameter pipe.

8

16m75mm Diameter rainwater pipes.9

6NoExtra over rainwater pipe for bend.10

6NoExtra over rainwater pipe for eaves offset 500mm projection.

11

ROOF INSULATION

248m2

Insulation laid taut over battens (at approximately 380mm centres) and fixed concurrent with roof covering including galvanised steel straining wires, laps, etc.

12

'Sisalation 420' or similar approved heavy industrial grade aluminium foil based insulation.:

-125-

ROOF COVERINGBill No. 5Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 126: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO. 6

CARPENTRY AND JOINERY

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Descriptions of frames shall be deemed to include frames, transomes, mullions, rails, etc

Joinery:

Descriptions of hardwood joinery shall be deemed to include pelleting of bolt holes

-126-

CARPENTRY AND JOINERYBill No. 6Section No. 4

Carried Forward R

Page 127: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or shot pins to brickwork or concrete

Fixing

PREFABRICATED ROOF TRUSSES, ETC.

687m114 x 38mm Wall plates.1

Sawn softwood:

1No

Trusses for rectangular shaped building, size overall 28.68 x 9.86m on plan (3 Classroom).

2

Prefabricated timber roof construction complete including purlins, runners, bracing hips, valleys, cleats, purlins, etc., supplied and fixed complete:

EAVES, VERGES, ETC.

51m12 x 225mm Fascia and barge boards, including galvanised steel H-profile joiners, etc.

3

Medium density plain fibre-cement fascial and barge boards:

SKIRTINGS

148m19 x 76mm Skirtings including 19mm quadrant bead, nailed.

4

Wrought meranti:

206m19 x 50mm Cornice laid flat.5

148m16 x 150mm dado rail.6

FRAMED DOORS, ETC.

3No

40mm Framed batten door 813 x 2032mm high of top rail and stiles, middle ledge and braces and bottom rail filled in with V-jointed one side boarding.

7

Wrought meranti doors hung to steel frames:

-127-

CARPENTRY AND JOINERYBill No. 6Section No. 4

Carried Forward R

Page 128: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

3No44mm Door 813 x 2 032mm high8

Semi-solid flush doors with sapele veneer on both sides hung to steel frames

-128-

CARPENTRY AND JOINERYBill No. 6Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 129: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO. 7

CEILINGS, PARTITIONS AND ACCESS FLOORING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or pins or shot pinned to brickwork or concrete

Descriptions:

Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 600mm centres, and where described as "bolted" the bolts have been given elsewhere

-129-

CEILINGS, PARTITIONS AND ACCESS FLOORINGBill No. 7Section No. 4

Carried Forward R

Page 130: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Electrical light fittings, diffusers, panels, etc generally are "lay in" units of the same dimensions as the suspension grid described and allowance must be made accordingly for their support inclusive of any flexibility insetting out that may be required (ceiling panels have not been deducted and pricing is to take cognisance thereof)

NAILED UP AND SCREW UP CEILINGS

180m2

Ceilings including 38 x 38mm sawn softwood brandering at 450mm centres with cross brandering at 450mm centres and at joints, ends of sheets and at light fittings, etc.

1

6,4mm Gypsum plasterboards with H-profile galvanised steel jointing strips:

3No

Extra over ceiling for 600 x 600mm hinged trap door of wrought softwood rebated framing with one sawn softwood cross brander covered with ceiling board and fitted flush in opening, including necessary trimmers all around.

2

36m2

Ceilings including 38 x 38mm sawn softwood brandering at 450mm centres with cross brandering at 450mm centres and at joints, ends of sheets and at light fittings, etc.

3

6mm Fibre-cement plain ceiling boards with H-profile galvanised steel jointing strips:

3No

Extra over ceiling for 600 x 600mm hinged trap door of wrought softwood rebated framing with one sawn softwood cross brander covered with ceiling board and fitted flush in opening, including necessary trimmers all around.

4

INSULATION

318m2100mm Insulation closely fitted between tie beams and laid loose on top of brandering.

5

Non-combustible lightweight fibreglass insulation blanket:

-130-

CEILINGS, PARTITIONS AND ACCESS FLOORINGBill No. 7Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 131: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO. 8

IRONMONGERY

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Where applicable finishes to ironmongery are indicated by suffixes in accordance with the following list: BS Satin bronze lacquered CH Chromium plated SC Satin chromium plated SE Silver enamelled GE Grey enamelled AS Anodised silver AB Anodised bronze AG Anodised gold ABL Anodised black PB Polished brass PL Polished and lacquered PT Epoxy coated SD Sanded

Finishes to ironmongery

"Union"

-131-

IRONMONGERYBill No. 8Section No. 4

Carried Forward R

Page 132: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

IRONMONGERY FIXED TO DOORS, ETC.

6No75mm Four lever security lockset with satin chrome furniture.

1

LOCKS:

DOOR CLOSERS

3NoTS 68 door closer with parallel arm, bracket fixed to metal.

2

Dorma:

NUMERAL AND NAMEPLATES, ETC.

3NoDitto, but with letters "CLASSROOM".3

Clear perspex name plate reverse engraved and enamelled in white lettering 25mm high to suit, twice countersunk holed for and tapscrewed to steel door frames or gate framing with chromium plated dome-headed selftapping screws:

3NoDitto, but with letters "STORE ROOM".4

6No

190 x 190 x 3mm Thick white perspex international FB2 sign plate with red fire extinguisher symbol plugged to brickwork.

5

Indicator plates countersunk holed for and screwed to door or brickwork with chromium plated dome-headed screws:

3No38mm Rubber stop plugged and srewed to wall or floor.6

SUNDRIES

3NoNickel plated steel leaf spring door holder with rubber door stop plugged and screwed to floor.

7

6m3 x 25mm Brass dividing strip between different floor finishes.

8

PINNING BOARDS, WRITING BOARDS, PROJECTION SCREENS, ETC.

-132-

IRONMONGERYBill No. 8Section No. 4

Carried Forward R

Page 133: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

3NoPinning board size 2400 x 1200mm high plugged.9

Carpet pinning boards in aluminium frame with round plastic corners, pen tray and fixing component all fixed according to manufacturer's instruction.

3NoDitto, but size 4200 x 1200mm high plugged.10

3No

Chalk board size overall 1140mm high x 3600mm wide consisting of 1 x chalkboard 1800mm wide, 2 x chalkboard 900mm wide, 2 x swing type chalkboard 900mm wide.

11

Swing type green chalkboard to comply with CKS-36-1980 or equivalent code of practice, complete with chalk rail as one unit fixed to wall strictly according to manufacturers instruction:

3NoWhite board size 2 x 2400 x 1140mm high.12

White board marker board surface wall mounted complete with integrated pen tray according to manufacturers instruction:

-133-

IRONMONGERYBill No. 8Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 134: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO.9

STRUCTURAL STEELWORK

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

SUPPLEMENTARY PREAMBLES

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions

Descriptions of L-shaped and U-shaped anchor bolts shall be deemed to include bending, threading, nuts and washers and embedding in concrete

Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

STEEL COLUMNS AND BEAMS

18No76 x 76mm x 3.0mm, 2.27m high column1

Mild steel welded columns in single lengths with flat section base, top, bearer and connection plates bolted to roof on floors and roof trusses

57m150 x 150mm x 75mm beam2

Welded beams in single lengths with flat section bearer and connection plates bolted to 76mm columns

3.60tHigh tensile bolts3

Bolts

-134-

STRUCTURAL STEELWORKBill No. 9Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 135: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO. 10

METALWORK

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Descriptions of bolts shall be deemed to include nuts and washers

Descriptions

Descriptions of expansion anchors and bolts and chemical anchors and bolts shall be deemed to include nuts, washers and mortices in brickwork or concrete

Metalwork described as"holed for bolt(s)" shall be deemed to exclude the bolts unless otherwise described

-135-

METALWORKBill No. 10Section No. 4

Carried Forward R

Page 136: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

STEEL WINDOWS, DOORS, ETC.

27NoWindow 01, 1143 x 1280mm high with one opening light1

Standard residential windows with steel burglar bars to fixed lights and opening sashes:

3NoWindow 02, 1143 x 854mm high with one opening light2

PRESSED STEEL DOOR FRAMES

3NoFrame for door 914 x 2032mm high.3

1,2mm Single rebated frames suitable for one brick walls:

3NoFrame for door 914 x 2032mm high.4

1,2mm Double rebated frames suitable for one brick walls:

STEEL STRONGROOM DOORS, VENTILATORS, ETC.

3NoSteel louvre unit according to NTY5

Steel Louvres

SECURITY GATES

3NoSize 925mm x 1800mm high, as per door schedule. (G12)

6

Steel security gates:

Handrail

24m60 x 60 x 4 mm Thick square hollow section handrail.7

The following in galvanized mild steel handrails framed and welded together including shopcoat as described:

-136-

METALWORKBill No. 10Section No. 4

Carried Forward R

Page 137: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

6No76 x 76 x 3mm Mild steel square tubing 8

96m25 x 25 x 5 mm Angle framing including mitred intersections.

9

4NoStop end.10

24No10 x 75 mm Expanding bolt including fixing to concrete or brickwork.

11

-137-

METALWORKBill No. 10Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 138: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO. 11

PLASTERING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

216m2

22,5mm thick sand cement screed, finished with a steel

float and prepared to receive vinyl tiles (elsewhere

measured).

1

SCREEDS

GRANOLITHIC

-138-

PLASTERINGBill No. 11Section No. 4

Carried Forward R

Page 139: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

51m235mm Thick on floors and walkways2

Untinted granolithic on concrete

INTERNAL PLASTER

336m2On walls.3

One coat cement plaster steel trowelled on brickwork.

22m2On narrow widths.4

-139-

PLASTERINGBill No. 11Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 140: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO. 12

TILING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Unless described as "fixed with adhesive to plaster (plaster elsewhere)" descriptions of tiling on brick or concrete walls, columns, etc shall be deemed to include 1:4 cement plaster backing and descriptions of tiling on concrete floors etc shall be deemed to include 1:3 plaster bedding

Descriptions

FLOOR TILING

-140-

TILINGBill No. 12Section No. 4

Carried Forward R

Page 141: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

214m2On floors and landings1

300 x 300mm x 8mm Ceramic tiles (PC Amount R150.00/m2) fixed with adhesive to bedding (bedding elsewhere) and flush pointed with tinted waterproof jointing compound

138mSkirting 75mm high2

-141-

TILINGBill No. 12Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 142: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO. 13

PLUMBING AND DRAINAGE (PROVISIONAL)

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

TANKS

2No5000 Litre jojo tank complete with lid including concrete plinth as per engineers details

1

JOJO tanks

FIRE APPLIANCES, ETC.

1No

"Everyway" hose reel complete with 30m plastic hose, chromium plated stopcock, shut-off nozzle and wall bracket

2

Fire hose reels, etc.:

6No

4,5kg Dry chemical powder fire extinguisher fixed to wall with meranti backboard, size 520 x 100 x 22mm thick, plugged and screwed to wall complete with hook.

3

-142-

PLUMBING AND DRAINAGEBill No. 13Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 143: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO. 14

The Tenderer is referred to the relevant clauses in the separate document Model Preambles for Trades (2008 Edition).

GLAZING

GLAZING TO STEEL WITH PUTTY

42m2Panes exceeding 0,1m² and not exceeding 0,5m².1

4mm Clear float glass:

-143-

GLAZINGBill No. 14Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 144: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 4

BILL NO. 15

PAINTWORK

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

SUPPLEMENTARY PREAMBLES

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

PREPARATORY WORK TO EXISTING WORK

Surfaces shall be thoroughly washed down and allowed to dry completely before any paint is applied. Blistered or peeling paint shall be completely removed and cracks shall be opened, filled with a suitable filler and finished smooth

Previously painted plastered surfaces

Surfaces shall be thoroughly cleaned down. Blistered or peeling paint shall be completely removed and cracks and crevices shall be primed, filled with suitable filler and finished smooth

Previously painted wood surfaces

-144-

PAINTWORKBill No. 15Section No. 4

Carried Forward R

Page 145: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Surfaces shall be thoroughly rubbed and cleaned down. Blistered or peeling paint shall be completely removed down to bare metal

Previously painted metal surfaces

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

ON FLOATED PLASTER SURFACES

336m2Interior walls.1

Prepare surfaces and remove all loose material, apply one coat alkaline resistant primer, one universal undercoat two coats eggshell enamel paint on:

ON METAL

84m2Windows (both sides measured).2

Prepare, spot primer defects in pre-primed surfaces with red oxide primer and apply one coat synthetic metal primer, one universal undercoat and one finishing coat of high gloss enamel paint on:

7m2Door frames.3

11m2Burglar gates.4

84m2Burglar bars to windows.5

15m2Structural steel beams and columns.6

ON WOOD

82m2Roof timbers at eaves and verges.7

Prepare and apply two coats carbolineum on:

36m2Wall plate.8

-145-

PAINTWORKBill No. 15Section No. 4

Carried Forward R

Page 146: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

10m2Exterior doors.9

Stop, sand down, prepare and apply two coats polyurethane varnish on:

10m2On interior doors10

148mSkirtings and quadrant bead, rails, etc., not exceeding 300 mm girth.

11

ON FIBRE-CEMENT

180m2General surfaces of ceilings.12

Prepare and apply one coat zinc chromate to nail heads and H-spline strips, one universal undercoat, stop and apply two finishing coats of eggshell enamel on:

21m2Fascias, bargeboards, etc.13

PLASTERBOARD

36m2General surfaces of ceilings.14

Prepare, prime nail heads and strips with zinc chromate primer, one universal undercoat and two finishing coats of semi-gloss PVA on:

-146-

PAINTWORKBill No. 15Section No. 4

Carried Forward to Summary of Section No. 4 R

Page 147: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION SUMMARY - NEW 1 X 3 CLASSROOM

BillNo

PageNo

Amount

114EARTHWORKS1

117CONCRETE, FORMWORK AND REINFORCEMENT2

122MASONRY3

123WATERPROOFING4

125ROOF COVERING5

128CARPENTRY AND JOINERY6

130CEILINGS, PARTITIONS AND ACCESS FLOORING7

133IRONMONGERY8

134STRUCTURAL STEELWORK9

137METALWORK10

139PLASTERING11

141TILING12

142PLUMBING AND DRAINAGE13

143GLAZING14

146PAINTWORK15

-147-

Section No. 4

Carried to Final Summary R

Page 148: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 1

NOTE :

EARTHWORKS (PROVISIONAL)

Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 104 for CPAP formula purposes

SUPPLEMENTARY PREAMBLES

The nature of the ground is assumed to be loose sandy material, therefore "earth", but possibly interspersed with "hard rock" or "soft rock".

Nature of ground

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or alternatively, from stock piles situated on the building site.

CARTING AWAY OF EXCAVATED MATERIAL

EARTHWORKS

325m2Stripping average 150mm thick layer of top soil and stockpiling

1

Site clearance

86m3Trenches2

Excavation in earth not exceeding 2m deep

2m3Pit3

18m3Soft rock 4

Extra over trench and hole excavations in earth for excavation in

-148-

EARTHWORKSBill No. 1Section No. 5

Carried Forward R

Page 149: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

8m3Hard rock 5

288m2Sides of trench and hole excavations not exceeding 1,5m deep

6

Risk of collapse of excavations

100m3Surplus material from excavations and/or stock piles on site to a dumping site to be located by the contractor

7

Extra over all excavations for carting away

ItemKeeping excavations free of water 8

Keeping excavations free of water

50m3Trenches9

Earth filling obtained from the excavations and/or prescribed stock piles on site compacted to 93% Mod AASHTO density in 150mm layers

128m3Under surface beds10

Earth filling supplied by the contractor, compacted to 93% Mod AASHTO density with G7 material in accordance with SABS 1200DM in 150mm layers

102m2

Levelling and compaction of bottom of trench excavation in foundations, etc including scarifying for a depth of 150mm, breaking down oversize material and adding suitable material where necessary and compacting to 93% Mod AASHTO density

11

Compaction of surfaces

428m2

Levelling and compaction of ground surface under surface beds, Aprons, etc including scarifying for a depth of 150mm, breaking down oversize material and adding suitable material where necessary and compacting to 93% Mod AASHTO density

12

20No"Modified AASHTO Density" test13

Prescribed density tests on filling

SOIL POISONING

-149-

EARTHWORKSBill No. 1Section No. 5

Carried Forward R

Page 150: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

293m2

Under floors, Aprons etc including forming and poisoning shallow furrows against foundation walls etc, filling in furrows and ramming

14

Soil insecticide

217m2To bottoms and sides of trenches etc 15

-150-

EARTHWORKSBill No. 1Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 151: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 2

CONCRETE, FORMWORK AND REINFORCEMENT

For preambles see "Specifications of materials and methods to

SUPPLEMENTARY PREAMBLES

be used - PW 371"

UNREINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

6m350mm Blinding bed under Strip footings1

15MPa/12mm concrete

REINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

24m3Strip footings2

25Mpa/19mm Concrete

30m3Surface bed including thickening3

2m3Ramp4

2m3Steps5

16m3Aprons cast in panels including thickening6

CONCRETE SUNDRIES

292m2Suface beds, Apron, slabs, etc.7

Finishing top surfaces of concrete smooth with a wood float

-151-

CONCRETE FORMWORK AND REINFORCEMENTBill No. 2Section No. 5

Carried Forward R

Page 152: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

8No

Allow for preparing a set of three test cubes each size 150x150x150mm, sending them to an approved testing laboratory for testing and paying all charges in connection therewith.

8

TEST CUBES

FORMWORK

12mEdges, risers, ends and reveals not exceeding 300mm high or wide

9

Rough formwork to sides:

MOVEMENT JOINTS ETC

414m12mm Jointex expanded board not exceeding 300mm high

10

Expansion joints between vertical concrete and brick surfaces

104m5 x 20mm Saw cut joints in top of concrete11

Saw cut joints

REINFORCEMENT

2.00t8mm to 16mm Diameter bars in all class of concrete12

High tensile steel reinforcement to structural concrete work

235m2Mesh ref. No. 193 fabric reinforcement fixed horizontal in surface beds

13

Mesh Reinforcement (measure nett)

-152-

CONCRETE FORMWORK AND REINFORCEMENTBill No. 2Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 153: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 3

MASONRY

For preambles see "Specifications of materials and methods to be used - PW 371"

SUPPLEMENTARY PREAMBLES

Sizes in descriptions

BRICKWORK

Where sizes in descriptions are given in brick units, "one brick" shall represent the length and "half brick" the width of a brick

Hollow walls etc

Descriptions of hollow walls shall be deemed to include leaving every fifth perpend of the bottom course of the external skin open as a weep hole.

Walls in two skins described as "bagged and sealed" shall be deemed to include having the outer face of the inner skin bagged with 1:6 cement and sand mixture and sealed with two coats "Brixeal" bitumen emulsion waterproofing coating.

User note: The above preamble generally applies for works in hot and humid coastal areas

Face bricks

Bricks shall be ordered timeously to obtain uniformity in size and colour

Descriptions of recessed pointing to fair face brickwork and face brickwork shall be deemed to include square recessed, hollow recessed, weathered pointing, etc

Pointing

-153-

MASONRYBill No. 3Section No. 5

Carried Forward R

Page 154: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Samples of all masonry building units, except those for walls units. Samples of building units to be used in walls described as "load bearing" shall consist of 30 units from every 30 000 units delivered to site described as "load bearing", shall consist of a minimum of 6

SAMPLES

FOUNDATIONS

148m2One brick walls1

Brickwork of NFX bricks (14 MPa nominal compressive strength) in class I mortar

FACE BRICKWORK

60m2Extra over brickwork for face brickwork in foundation2

Face bricks (purchase price of R 4000.00/1000 delivered to site excluding VAT) pointed with flush horizontal and vertical joints

54mFace brick on edge3

BRICKWORK SUNDRIES

666m150mm Wide reinforcement built in horizontally4

Brick reinforcement

SUPERSTRUCTURE

74m2Half brick wall in beamfilling5

Brickwork of NFX bricks (14 MPa nominal compressive strength) in class I mortar

162m2One brick walls6

FACE BRICKWORK

174m2Extra over brickwork for face brickwork7

Face bricks (purchase price of R 4000.00/1000 delivered to site excluding VAT) pointed with flush horizontal and vertical joints

-154-

MASONRYBill No. 3Section No. 5

Carried Forward R

Page 155: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

134m2One brickwork face brick walls pointed both sides8

54mExtra over brickwork for brick-on-edge header course lintels pointed on two sides

9

Brick-on-edge header course coping, sills, etc. of face bricks (purchase price of R 3 500.00/1000 delivered to site excluding VAT) pointed with recessed joints on all exposed faces

44m

Face brick-on-edge window cill 150mm wide pointed on two side and on top and set slightly sloping and protruding.

10

26mFace brick-on-edge window cill 110mm wide pointed on side and top and set flat

11

BRICKWORK SUNDRIES

296m75mm Wide reinforcement built in horizontally12

Brick reinforcement

1 184m150mm Wide reinforcement built in horizontally13

54m220mm Wide turning piece to lintel etc14

Turning pieces

32No

Set of two 22 x 155mm high terra cotta clay vermin proof air bricks including making good reveals and gauze

15

Ventillation bricks

-155-

MASONRYBill No. 3Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 156: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 4

WATERPROOFING

For preambles see "Specifications of materials and methods to be used - PW 371"

SUPPLEMENTARY PREAMBLES

DAMP-PROOFING OF WALLS AND FLOORS

20m2In walls1

One layer 375mm micron embossed damp proof course

292m2Under surface beds2

One layer of 250 micron waterproof sheeting and sealed at overlaps with pressure sensitive tape

FLOOR AND WALLS SEALERS

150mAround steel windows and door frames.3

"Secomastic" non setting mastic sealant applied cold with a hand pressure caulking gun and leave perfectly watertight:

466m10 x 10mm sealant on top of expansion joint and in saw cut joints

4

Polyurethane Sealant

-156-

WATERPROOFINGBill No. 4Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 157: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 5

NOTE :Unless otherwise stated herein, all items in this bill shall be deemed to fall into Work Group No. 124 for CPAP formula purposes

ROOF COVERINGS ETC

PROFILED METAL SHEETING AND ACCESSORIES

54m2Roof covering with pitch not exceeding 25 degrees 1

0,6mm "IBR" Z275 spelter galvanised troughed sheet steel with "globalcoat" finish on one side in single lengths fixed to timber purlins and 0,6mm galvanised sheet steel accessories with "globalcoat"finish on one side

4mHead wall flashings 308mm girth2

4mCover flashing 154mm girth3

ROOF AND WALL INSULATION

35m2

Insulation laid taut over purlins (at approximately 1 000mm centres) and fixed concurrent with roof covering including galvanised steel straining wires

4

"Sisalation 410" housing grade glass fibre reinforced aluminium foil bonded insulation

-157-

ROOF COVERINGBill No. 5Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 158: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 6

CARPENTRY AND JOINERY

For preambles see "Specifications of materials and methods to be used - PW 371"

SUPPLEMENTARY PREAMBLES

ROOFS, ETC.

Plate nailed timber roof truss construction

28No

Gable roof timber trusses comprising of tie beam, rafters,struts overall length 10620mm x 1728mm high

1

Sawn softwood

72m38 x 114mm Wall plates in lengths exceeding 3,9m and not exceeding 6,6m

2

Sawn softwood

502m76 x 76mm Purlins in lengths exceeding 3,9m and not exceeding 6,6m

3

116m2Two coats creosote on sawn timbers4

Sundries

116No6mm Diameter galvanised wire tie 3000mm girth wrapped around rafter and purlin with ends tied together

5

448NoHurricane clips (provisional)6

EAVES, VERGES, ETC.

-158-

CARPENTRY AND JOINERYBill No. 6Section No. 5

Carried Forward R

Page 159: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

72m

12 x 225mm Fascias boards including galvanised steel H-profile jointing strips

7

Pressed fibre-cement

46m12 x 225mm barge boards including galvanised steel H-profile jointing strips

8

SKIRTINGS

116m13 x 100mm high with 19 x 19 quadrant9

Wrought meranti

DOORS, ETC.

3No

44mm thick Meranti framed, ledged, braced and battered door size 813 x 2032mm high

10

Wrought meranti doors hung to steel frames

3No

Timber framed Pin board overall size 7000 x 1200mm high in three equal section with one end rebated 19 x 75mm high meranti timber top, bottom and end rails and 19 x 75mm wide double side rebated intermediate rail with 12mm thick soft-board infill panels

11

NOTICE BOARDS, KEYBOARDS, DUCKBOARDS, ETC

5No

Fibre cement Green chalk board size 2400 x 1140mm high

12

5No

Fibre cement Green chalk board size 2400 x 1140mm high

13

-159-

CARPENTRY AND JOINERYBill No. 6Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 160: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 7

CEILINGS, PARTITIONS AND ACCESS FLOORING

SUPPLEMENTARY PREAMBLES

Items described as "nailed" shall be deemed to be fixed with hardened steel nails or pins or shot pinned to brickwork or concrete

Descriptions:

Items described as "plugged" shall be deemed to include screwing to fibre, plastic or metal plugs at not exceeding 600mm centres, and where described as "bolted" the bolts have been given elsewhere

CEILINGS ETC

197m240mm glass fibre Insulation closely fitted and laid on top of brandering between timber roof trusses etc

1

"Approved" insulation

NAILED UP CEILINGS

184m2Ceilings including 50 x 38mm sawn softwood brandering at 400mm centres

2

6,4mm "Rhino" gypsum plasterboard ceiling with H-type pressed steel jointing strips

3No

Extra over ceiling for 650 x 650mm trap door of 38 x 50mm wrought softwood rebated framing with one 38 x 50mm sawn softwood cross brander covered with ceiling board and fitted flush in opening

3

176m75mm Coved cornices4

"Rhino" gypsum plasterboard cornices

-160-

CEILINGS, PARTITIONS AND ACCESS FLOORINGBill No. 7Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 161: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 8

IRONMONGERY

For preambles see "Specifications of materials and methods to be used - PW 371"

SUPPLEMENTARY PREAMBLES

LOCKS

3No2 Lever lockset code: CZ682-24/2295-765c1

Union or Similar Approved

DOORSTOPS

3NoDoor Stop Code: AL 8730AS2

Union or Similar Approved

-161-

IRONMONGERYBill No. 8Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 162: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 9

METALWORK

For preambles see "Specifications of materials and methods to be used - PW 371"

SUPPLEMENTARY PREAMBLES

PRESSED STEEL DOOR FRAMES

3NoFrame for door 813 x 2032mm high1

1,6mm Double rebated frames suitable for one brickwalls

STEEL WINDOWS, DOORS, ETC

16NoWindow size 1616 x 1445mm high2

Standard steel window for School with burglar bars and brass fittings to opening sashes

WELDED SCREENS, GATES, ETC

3No

Purpose made security steel gate overall size 813 x 2032mm high comprising of 40 x 60 x 2mm rectangular tubing gate surround with 6 No vertical middle rails of 12mm HT steel rods at 99mm centres between steel surround and 2 No horizontal middle rails of 40 x 6mm steel flat bar at 647mm from top and bottom steel surround with and including 3 No 100mm Pin type hinged welded to pressed steel frame and 5 lever security door lock

3

Steel Gates

Handrail

-162-

METALWORKBill No. 9Section No. 5

Carried Forward R

Page 163: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

8m60 x 60 x 4 mm Thick square hollow section handrail.4

The following in galvanized mild steel handrails framed and welded together including shopcoat as described:

2No76 x 76 x 3mm Mild steel square tubing 5

32m25 x 25 x 5 mm Angle framing including mitred intersections.

6

4NoStop end.7

8No10 x 75 mm Expanding bolt including fixing to concrete or brickwork.

8

-163-

METALWORKBill No. 9Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 164: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 10

PLASTERING

For preambles see "Specifications of materials and methods to be used - PW 371"

SUPPLEMENTARY PREAMBLES

SCREEDS

184m225mm thick average on floors1

Screeds to steel trowelled, on concrete:

GRANOLITHIC

58m245mm thick average on floors2

Untinted granolithic on concrete

INTERNAL PLASTER

156m2On walls 3

Cement plaster on brickwork or blockwork

16m2On narrow width4

-164-

PLASTERINGBill No. 10Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 165: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 11

TILING

PREAMBLES

For preambles see "Model Preambles for Trades" (2008 Edition) and Supplementary preambles as specified in the Trades

Supplementary preambles are incorporated in this schedule of quantities to satisfy the requirements of this project. Such supplementary preambles shall take precedence over the provisions of the said Model Preambles

SUPPLEMENTARY PREAMBLES

The contractor's prices for all items throughout this schedule of quantities must take account of and include for all of the obligations, requirements and specifications given in the said Model Preambles and in any supplementary preambles

This bill is measured provisionally and will be subject to re-measure when the work or a portion thereof is complete. It is expected of the contractor to be able to demonstrate how he derived at the quantities and in cases where it is not possible to measure the work on completion due to cover up; the contractor must provide signed off site records proving such claims

Unless described as "fixed with adhesive to plaster (plaster elsewhere)" descriptions of tiling on brick or concrete walls, columns, etc shall be deemed to include 1:4 cement plaster backing and descriptions of tiling on concrete floors etc shall be deemed to include 1:3 plaster bedding

Descriptions

FLOOR TILING

-165-

TILINGBill No. 11Section No. 5

Carried Forward R

Page 166: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

59m2On floors and landings1

300 x 300mm x 8mm Ceramic tiles (PC Amount R150.00/m2) fixed with adhesive to bedding (bedding elsewhere) and flush pointed with tinted waterproof jointing compound

31mSkirting 75mm high2

-166-

TILINGBill No. 11Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 167: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 12

GLAZING

For preambles see "Specifications of materials and methods to be used - PW 371"

SUPPLEMENTARY PREAMBLES

GLAZING TO STEEL WITH PUTTY

50m2Panes not exceeding 0,1 m21

6.38mm Clear safety glass

-167-

GLAZINGBill No. 12Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 168: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 5

BILL NO. 13

PAINTWORK

For preambles see "Specifications of materials and methods to be used - PW 371"

SUPPLEMENTARY PREAMBLES

PAINTWORK ETC TO NEW WORK

ON FLOATED PLASTER

196m2On internal walls1

One coat alkali resistant primer and two coats acrylic PVA paint

ON PLASTER BOARD

184m2On ceiling soffit2

One coat alkali resistant primer and two coats acrylic PVA paint

54m2On fascias and barge boards3

ON FIBRE-CEMENT

ON WOOD

13m2On doors4

Three coats of Polyurethane semi gloss vanish on

116mSkirting not exceeding 100mm high5

ON METAL

-168-

PAINTWORKBill No. 13Section No. 5

Carried Forward R

Page 169: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

6m2On door frames6

One coat zinc chromate primer, I coat universal under coat and 2 coats gloss enamel on

100m2Steel windows with burglar bars (Measured over the full flat area of both sides)

7

13m2Steel doors and security gates (Measured over the full flat area of both sides)

8

13m2Steel doors and security gates (Measured over the full flat area of both sides)

9

-169-

PAINTWORKBill No. 13Section No. 5

Carried Forward to Summary of Section No. 5 R

Page 170: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION SUMMARY - NEW 1 x MULTI PURPOSE CLASSROOM

BillNo

PageNo

Amount

150EARTHWORKS1

152CONCRETE FORMWORK AND REINFORCEMENT2

155MASONRY3

156WATERPROOFING4

157ROOF COVERING5

159CARPENTRY AND JOINERY6

160CEILINGS, PARTITIONS AND ACCESS FLOORING7

161IRONMONGERY8

163METALWORK9

164PLASTERING10

166TILING11

167GLAZING12

169PAINTWORK13

-170-

Section No. 5

Carried to Final Summary R

Page 171: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 6

BILL NO. 1

ENVIRO-LOO TOILETS

For preambles refer to "General Specification of Labour and Material and Methods to be used PW371"

PREAMBLES

Where applicable the Contractor is referred to the relevant sections of SABS1200 for the full specification, meaning and implications of the work to be executed

SUPPLEMENTARY PREAMBLES

4No

Supply and install pre-cast concrete double wash-trough, complete with all necessary 19mm galvanised pipework incluading soakaway size 1000 x 1000 x 1000mm covered with bidim

1

16NoReplace cisterns and seats including all flushing mechanisms

2

SANITARY FITTINGS

BATHROOM FITTINGS

16NoLockable Stainless steel toilet roll holder plugged to wall.

3

Toilet roll holders

4NoWall mounted soap dispenser plugged.4

Soap dispensers:

4No

"Hibiscus" Ref 7023 white vitreous china wall hung basin, size 510 x 405mm, with stopper to one taphole and fixed to wall.

5

'Vaal':

PAINT ON FIBRE-CEMENT

-171-

ENVIROLOOBill No. 1Section No. 6

Carried Forward R

Page 172: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

108m2On ceilings and cornices6

Prepare and apply one coat "Plascon Merit Plaster Primer" and two coats "Plascon Super Acrylic PVA " or equal approved paint

89m2On fascias and barge boards7

PAINT ON METAL

59m2On pressed steel door frames8

Prepare, touch up primer and apply one coat "Dulux" steel primer one coat "Dulux" universal undercoat and three coats "Dulux Dura 100" high gloss enamel paint

108m2On roofs9

52m2On steel windows (both sides measured)10

397mOn eaves gutters and down pipes not exceeding 300 mm girth

11

PAINT ON WOOD

21m2On roof timbers at eaves and verges12

Two coats carbolineum wood preservative

59m2On doors13

Prepare and apply one coat "Dulux" wood primer two coats "Dulux" universal undercoat and three coats "Dulux" eggshell enamel paint

RAINWATER HARVESTING TANK AND PLINTH

24m3Excavate in earth not exceeding 2m deep for footings14

Earthworks

24m3Surplus material from excavations to a dumping site to be located by the contractor

15

72m2Risk of collapse to sides of excavations16

-172-

ENVIROLOOBill No. 1Section No. 6

Carried Forward R

Page 173: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

27m3Backfilling to trenches, holes, etc17

38m3Bases18

25MPa/20mm reinforced concrete

45m3Tank bases19

56m2Type 193 fabric reinforcement in concrete surface beds, slabs, etc

20

Fabric reinforcement

113m2One brick walls21

Loadbearing brickwork of NFX bricks (14 MPa nominal compressive strength) in class I mortar

2No

"Atlas Plastics" or equal approved rotomoulded polyethylene water tank (code: 2103AP), size 1700mm x 1500mm diameter, 2 500 litre capacity, connected to 2 x 38mm threaded inlet, outlet and overflow tank connectors including 450mm diameter manhole lid with three self tapping screws.

22

"Atlas Plastics" or other approved tanks

-173-

ENVIROLOOBill No. 1Section No. 6

Carried to Final Summary R

Page 174: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 7

BILL NO 1

For preambles see "Model Preambles for Trades (1999 Edition)" and Supplementary preambles as specified in the Trades

DEMOLITIONS

--------------

NOTE : All excavations are measured as being in "earth" and/or filling compacted to 98% modified AASHTO density

Descriptions of excavations shall be deemed to include for setting aside surplus excavated material in spoil heaps for use as filling or for depositing within 150m of the perimeter of the excavations and spreading and roughly levelling as directed, as well as for increase in bulk and multiple handling of excavated material caused by the contractor's method of operation.

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or, alternatively, from stock piles situated on the building site and for bulking.

---------------

OLD MATERIALS TO BE CARTED AWAY: Old materials from the alterations, except where described to be re-used or handed over, as well as all rubish, etc., must be regularly carted from the site and not be allowed to accumulate on or around the site.

REMOVAL OF EXISTING WORK

-174-

DEMOLITIONSBill No. 1Section No. 7

Carried Forward R

Page 175: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

OLD MATERIALS NOT TO BE RE-USED: None of the old materials are to be used for new work except where specifically described as being set aside for re-use.

1 WORKS ACTIVITY OUTLINE

1.1 Simple Demolition (single storeybuildings)

· An arrangement has been made to

develop deliver the project in phases in

order to relocate occupants to the

completed buildings. Once the

relocation is completed, demolition of

the vacated buildings will commence.

· The Tenderer shall assume

responsibility for the submission of

applications that maybe required in

order to obtain a demolitions permit.

The rates submitted are deemed to

include for this provision

The following items have been identified as

materials with salvage value and can be

sold to second-hand building materials

dealers or recycled.

· Structural steel and steel roof sheets

· Roof timbers components

· Windows and glass

· Doors and frames

· Taps, traps and sanitary fittings

· Reinforcement, cables and pipes

· Stoves, ovens, mechanical equipment

(if any) etc.

1.2 Demolition Methods

The operation can be manual or light

machinery may be used. No blasting shall

be permitted on site. If manual demolition

is preferred it needs to start from the roofs

and be carried out downwards. If light

machinery is used (e.g. bulldozers, TLB’s,

-175-

DEMOLITIONSBill No. 1Section No. 7

Carried Forward R

Page 176: SECTION 1 BILL NO. 1 PRELIMINARIES

pneumatic hammers etc.), demolition is

irregularly progressive but faster than

manual. However, this method causes

potential danger to nearby structures and

people for which due care must be taken by

the contractor.

Among other requirements spelled out in

the OHS Act (more specifically Construction

Regulation 2003), barricading (in order to

keep safe distances) and dust control (in

order not to pollute the environment and

cause explosion hazard) will be pre-

requisites. It will be up to the Contractor to

choose his demolition methods. Whatever

method is chosen it will have to comply with

the safety requirements and will have to be

reviewed and approved by the engineer.

Demolition Process Flow shall be as

follows:

· Disconnect water and electrical

supplies. Water supply isolation and

electrical lock-out must be done prior to

the commencement of the demolition.

· Loosen and take off steel roof sheets,

tiles etc, clean and straighten as

necessary, and dispose. Removal of the

asbestos roof sheeting is dealt with in

clause 4.3 of this document.

· Take down ceilings where applicable

and remove to an approved dumping

site.

· Loosen and take off roof timber

members, de-nail as necessary, and

dispose.

· Take out damaged windows and

dispose.

· Take down old damaged doors and

dispose.

· Break out old damaged door frames

and dispose.

· Take down old fittings and fixtures and

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

-176-

DEMOLITIONSBill No. 1Section No. 7

Carried Forward R

Page 177: SECTION 1 BILL NO. 1 PRELIMINARIES

dispose

· Break down ground floor walls and

remove rubble to an approved

dumping site by trucks.

· Break up ground floor slab, hard-core

filling and foundation walls to

required depth below ground level, and

remove to an approved

dumping site by trucks.

· Use remainder of the filling under

broken floors to fill and compact

portions of foundation and service

trenches opened up.

· Seal off existing water supply pipes,

electrical supply cables and

soil drains below ground level.

· Clear site of all the remaining rubble,

and leave the site clean and level.

Removal and Disconnection of Services:

· The Contractor must ensure that the

buildings and services phased for

demolition have been de-commissioned

prior to any work taking place. He must

ensure that no live electrical cabling,

active water pipe, gas or sewer lines

have been left on site after the

decommissioning procedure has been

officially completed and handed over to

him.

· All services, i.e. water, sewer, electrical

cables, mechanical etc. must be

disconnected and removed. It has been

established that there will be no impact

on the residents or local communities

due to such disconnections.

· There will be no road closures during

demolitions. Points of entrance and exit

to the demolition site must be identified

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

-177-

DEMOLITIONSBill No. 1Section No. 7

Carried Forward R

Page 178: SECTION 1 BILL NO. 1 PRELIMINARIES

upfront and clearly marked. Traffic

control and diversions shall be

monitored accordingly by the appointed

Contractor.

Health and Safety: Specialized equipment

requirement:

During the project phase, Tenderers must

provide the following to their workers to

ensure their health and safety are not

endangered:

· Proper ventilation in the workplace to

prevent settling of asbestos fibers and

dust,

· Protective outerwear, including

goggles, shoe covers, gloves, jackets

and trousers to prevent asbestos

fibers from clinging to clothing, hair and

shoes,

· Respirators that adequately cover the

nose and mouth to avoid inhalation.

The Contractor shall do the following:

· Notify the nearest Department of Labour of

the intended demolition work.

· Compile a method statement on the

procedures to be followed relating to the

demolition work.

· Appoint a competent person in writing to

supervise the demolition work.

· The appointed competent person must

check the structural integrity during the

demolition work.

2.0 NATURE OF GROUND AND SUBSOILCONDITIONS

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

-178-

DEMOLITIONSBill No. 1Section No. 7

Carried Forward R

Page 179: SECTION 1 BILL NO. 1 PRELIMINARIES

Refer to the geotechnical report included in

the tender document.

3.0 ASBESTOS REMOVAL AND DISPOSAL

In an effort to protect all workers from

asbestos exposure and subsequent health

concerns, the South African Department of

Labour updated the Asbestos Health

Regulations some time ago. The aim of this

legislation was specifically to prevent the

onset of asbestos related diseases,

specifically the development of asbestos

cancer, also known as mesothelioma.

Exposure to asbestos is the only

recognized cause of mesothelioma, a fatal

type of cancer that has no cure and a

survival rate of less than one percent.

One of the regulations involves notifying the

appropriate authorities (including provincial

directors) prior to beginning any projects

where asbestos removal and disposal is

required.

The danger of exposure to asbestos fibers is now well known.safely disposed of. New legislation regarding the handlingensure the safety of workers (Regulation 155 of the OccupationalCompanies handling asbestos on a regular basis must beDepartment of Labour. Before responding to an asbestosmust be submitted to the Department of Labour for approval.with regards to the workers on site, and preventing asbestos

Upon commencement of any asbestos

related demolition and disposal the

Contractor is mandated to protect the

health of their workers by preventing any

personnel from entering areas where the

asbestos level exceeds 0.2 fibers per

millilitre of air averaged over a four-hour

period.

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

-179-

DEMOLITIONSBill No. 1Section No. 7

Carried Forward R

Page 180: SECTION 1 BILL NO. 1 PRELIMINARIES

All personnel must be notified that there

may be asbestos present in the

environment prior to beginning of work.

During the project phase, employers must

provide the following to their workers to

ensure their health and safety:

· Proper ventilation in the workplace to

prevent settling of asbestos fibers and

dust,

· Protective outerwear, including

goggles, shoe covers, gloves, jackets

and trousers to prevent asbestos

fibers from clinging to clothing, hair and

shoes,

· Respirators that adequately cover the

nose and mouth to avoid inhalation

Appropriate Safety Regulations should be

posted in the workplace to provide workers

with necessary precautionary measures.

The posting of legal required symbolic

warning signs must also be catered for.

Safety is paramount during any asbestos

removal project, but the need for safety

precautions extends above and beyond the

asbestos disposal phase. Once asbestos is

removed from a structure it poses an even

greater threat, as the asbestos fibers may

have been damaged and become friable,

and is more prone to become airborne. The

contractor must do his/her best to keep the

asbestos in a non-friable state from

demolition to disposal stage.

Upon removal, all asbestos-containing

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

-180-

DEMOLITIONSBill No. 1Section No. 7

Carried Forward R

Page 181: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

materials must be suitably isolated and

contained prior to transfer from the

workplace to an appropriate disposal area.

Containers must be marked to indicate that

they contain potentially hazardous

materials.

Asbestos waste must be disposed of in an

area that has been approved for asbestos

dumping under the stipulations of the

Environmental Conservation Act and the

National Environmental Management Act.

Any worker that is responsible for the

transfer and dumping of asbestos waste

must be provided with a respirator and

protective outerwear.

Upon disposal, transportation vehicles must

be cleaned thoroughly to prevent transfer of

any errant fibers from the approved

dumping area to a secondary location. Any

accidental spillage of asbestos waste must

be reported and cleaned immediately.

When dealing with asbestos, it is absolutely

necessary to follow all regulations in an

effort to protect the health and safety of all

individuals, as well as the environment. In

recent years the number of instances of

mesothelioma that has been a result of

second-hand asbestos exposure has

increased, furthering the need for

adherence to all regulations by all

employers and their workers.

-181-

DEMOLITIONSBill No. 1Section No. 7

Carried Forward R

Page 182: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

1No

Existing building size approximately 33.29 on plan and 3000mm high consisting of brick structure with corrugated iron roof sheeting on timber roof construction and concrete surface bed including removal of all fittings and demolish foundations where existing building is in the position of new buildings(building A)

1

Taking down and removing

1No

Existing building size approximately 301.57m2 on plan and 3000mm high consisting of brick structure with corrugated iron roof sheeting on timber roof construction and concrete surface bed including removal of all fittings and demolish foundations.

2

1No

Existing building size approximately 320m2 on plan and 3000mm high consisting of brick structure with corrugated iron roof sheeting on timber roof construction and concrete surface bed including removal of all fittings and demolish foundations.

3

1No

Existing building size approximately 16.56m2 on plan and 3000mm high consisting of brick structure with corrugated iron roof sheeting on timber roof construction and concrete surface bed including removal of all fittings and demolish foundations.

4

-182-

DEMOLITIONSBill No. 1Section No. 7

Carried Forward to Summary of Section No. 7 R

Page 183: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 7

BILL NO. 2

WATER RETICULATION (PROVISIONAL)

The contractor is refered to the Model Preambles for Trades (2008 edition) as issued the Association of South African Quantity Surveyors before pricing this bill

STANDARD PREAMBLES

WATER SUPPLIES

151m40mm Pipes laid in and including trenches not exceeding 1m deep

1

HDPE Type PE100 PN12.5 pipes to comply with SABS ISO 4427 (in minimum 12m lengths) with butt-welded joints

82m50mm Pipes laid in and including trenches not exceeding 1m deep

2

1No40 x 20mm Reducer3

Extra over HDPE pipes for butt-welded fittings

1No50 x 40mm Reducer4

8No40mm Elbow5

8No50mm Elbow6

13No40mm 90 degress bend7

10No50mm 90 degress bend8

3No40mm Tee9

3No50mm Tee10

3No40mm Adaptor coupling11

-183-

WATER RETICULATIONBill No. 2Section No. 7

Carried Forward R

Page 184: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

3No50mm Adaptor coupling12

10m110mm Pipes (no excavation)13

HDPE Type PE100 PN10 sleeve pipes to comply with SABS ISO 4427 with butt welded joints

3No40mm Elbow14

Extra over HDPE pipes for butt welded fittings

3No50mm Elbow15

1No20mm Brass garden tap with hose connection16

Taps, valves, etc

2No25mm 1001/125RB full way gate valve17

2No40mm 1001/125RB full way gate valve18

5m

25mm Pipes laid in and including trenches not exceeding exceeding 1m deep, bedding, backfilling, compaction and disposal of excavated material

19

Class 9 uPVC pressure pipes

125m

25mm Pipes laid in and including trenches exceeding 1m and not exceeding 2m deep, bedding, backfiling compaction and disposal of excavated material

20

30m

50mm Pipes laid in and including trenches exceeding 1m and not exceeding 2m deep, bedding, backfiling compaction and disposal of excavated material

21

2No25mm x 90 degrees bend22

Extra over uPVC pressure pipes for uPVC solvent welded pressure fittings

2No25mm Tee23

2No25mm Steel to HDPE adaptor24

2No25mm Copper to HDPE adaptor25

-184-

WATER RETICULATIONBill No. 2Section No. 7

Carried Forward R

Page 185: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

5m20mm Stand pipes26

Galvanized steel pipes

5m3Extra over excavation in earth for pipe trenches, chambers, etc. for excavation in "soft rock"

27

Sundries

3m3Extra over excavation in earth for pipe trenches, chambers, etc. for excavation in "hard rock"

28

2m3

Class C (15 MPa/20) concrete in thrust blocks at bends, tees, etc. including necessary extra excavation, formwork, etc

29

2No

150 x 150mm Cast iron stopcock box, including brick chamber below exceeding 500mm and not exceeding 750mm deep internally

30

2No

530 x 530mm Valve chamber exceeding 750mm and not exceeding 1000mm deep internally including cover and frame

31

ItemTesting water and fire service pipe system32

Testing

FIRE APPLIANCES, PEDESTALS, ETC.

2No80 x 65mm Brass right angle hydrant valve with cap and chain

33

Fire appliances etc

3No

25MPa/19mm Reinforced concrete hydrant pedestal 1960mm high cast around vertical pipe with bottom 1260mm below ground, 440 x 440mm square at base and tapering to octagonal shaped top 240 x 240mm overall, including necessary excavation, formwork, reinforcement and two coats of paint to exposed surfaces

34

Fire hydrant pedestals

MUNICIPAL CONNECTIONS

-185-

WATER RETICULATIONBill No. 2Section No. 7

Carried Forward R

Page 186: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

25 000.00ItemAllow the amount of R25 000 (Twenty Five Thousand Rand) for municipal connections

35

Connections

ItemAllow for Profit on above if required36

ItemAllow for Attendance on above if required37

-186-

WATER RETICULATIONBill No. 2Section No. 7

Carried Forward to Summary of Section No. 7 R

Page 187: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 7

BILL NO. 3

SEWERS

The contractor is refered to the Model Preambles for Trades (2008 edition) as issued the Association of South African Quantity Surveyors before pricing this bill

STANDARD PREAMBLES

SOIL DRAINAGE

36m

110mm Pipes laid in and including trenches not exceeding 1m deep, bedding, backfilling, compaction and disposal of excavated material

1

Heavy duty uPVC pipes

2m160mm Pipes laid in sleeve pipes (sleeve pipes elsewhere) (no excavation)

2

2m

110mm Pipes laid in and including trenches exceeding 1m and not exceeding 2m deep, bedding, backfilling, compaction and disposal of surplus excavated material

3

2m

160mm Pipes laid in and including trenches not exceeding 1m deep, bedding, backfilling, compaction and disposal of excavated material

4

5No

uPVC cleaning eye fitted to end of 110mm earthenware pipe with 300 x 300mm cast iron cover and frame placed over cleaning eye including concrete surround finished smooth

5

4m100mm uPVC pipe, raking or vertical to cleaning eye6

5No110mm Bend7

Extra over heavy duty uPVC pipes for fittings

2No110mm tee Junction8

5No110mm "Y" Junction9

-187-

SEWERBill No. 3Section No. 7

Carried Forward R

Page 188: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

1No160mm Bend10

1No160 x 110mm Reducer11

5NoExtra over 100mm uPVC pipe for 100mm juntion with I.E

12

2NoExtra over 110mm pipe for Permanent stoppers13

3No110mm Gulley "P" trap14

3No190 x 110mm Gulley head and grating15

1No110mm Rodding eye16

INSPECTION CHAMBERS

3No1830 x 1830mm Inspection chamber not exceeding 1000mm deep internally

17

Brick inspection chamber including precast concrete cover slabs (covers elsewhere) and channels in benching

1No1830 x 1830mm Inspection chamber exceeding 1000mm and not exceeding 2000mm deep internally

18

1No1830 x 1830mm Inspection chamber exceeding 2000mm and not exceeding 3000mm deep internally

19

2NoDouble seal manhole cover and frame type 2A as per SANS 1882

20

Cast iron covers, etc

1NoLifting-key for mahole cover21

3NoPrecast concrete gulley with 100mm outlet 22

Precast concrete gulleys

5No300x300x50mm Precast concrete inspection eye marker slab set in ground

23

Sundries

-188-

SEWERBill No. 3Section No. 7

Carried Forward R

Page 189: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

5No

Inspection chamber size 450 x 600 avarage 1200mm internally fitted with type 8a cast iron piece double a seal manhole cover and frame

24

5No550mm Diameter 183kg type 2b cast iron manhole cover and frame

25

ItemTesting water pipe system26

7m100mm pipes vertically or ramped to cleaning eyes (no excavation)

27

SOIL DRAINAGE (CPAP Work Group No 146) uPVC:

2m110mm cast iron `ABC` cleaning eyes28

Sundries

8m110mm Perforated pipes laid in french drain.29

SOIL DRAINAGE (CPAP Work Group No 148) upvc

16m110mm Pipes laid in and icluding trenches not exceeding 1m deep.

30

4No110mm bend 31

Etra over uPVC pipes for fittings:

-189-

SEWERBill No. 3Section No. 7

Carried Forward to Summary of Section No. 7 R

Page 190: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 7

BILL NO. 4

STORMWATER DRAINAGE (PROVISIONAL)

The contractor is refered to the Model Preambles for Trades (2008 edition) as issued the Association of South African Quantity Surveyors before pricing this bill

STANDARD PREAMBLES

Descriptions of excavations shall be deemed to include for setting aside surplus excavated material in spoil heaps for use as filling or for depositing within 150m of the perimeter of the excavations and spreading and roughly levelling as directed, as well as for increase in bulk and multiple handling of excavated material caused by the Contractor's method of operation

Descriptions of carting away of excavated material shall be deemed to include loading excavated material onto trucks directly from the excavations or, alternatively, from stock piles situated on the building site and for bulking

____________________

SUPPLEMENTARY PREAMBLES

Soil, waste and vent pipes and fittings shall be solvent weld jointed

uPVC pipes and fittings:

Unless specifically otherwise stated, descriptions of pipes shall be deemed to include fixing to walls etc, casting in, building in or suspending not exceeding 1m below suspension level

Fixing of pipes

-190-

STORMWATERBill No. 4Section No. 7

Carried Forward R

Page 191: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Where fittings have reducing ends or branches they are described as "reducing". In the case of pipes with diameters not exceeding 60mm only the largest end or branch size is given. Should the contractor wish to use other fittings and bushes or reducers he may do so on the understanding that no claim in this regard will be entertained. In the case of pipes with diameters exceeding 60mm all sizes are given and no claim for extra bushes, reducers, etc will be entertained

Reducing fittings

Exposed surfaces of concrete stormwater channels, cover slabs, inspection eye marker slabs, gulley tops, cleaning eye tops, catchpits, inspection chambers, etc shall be finished smooth with plaster

Exposed concrete surfaces

No claim for rock excavation will be entertained unless the contractor has timeously notified the quantity surveyor thereof prior to backfilling

Excavations

Pipes shall be laid and bedded and trenches shall be carefully backfilled in accordance with manufacturers' instructions

Laying, backfilling, bedding, etc. of pipes

Where no manufacturers' instructions exist, pipes shall be laid in accordance with clauses 5.1 and 5.2 of each of the following: SABS 1200 L : Medium-pressure pipelines LD : Sewers LE : Stormwater drainage

Pipe trenches etc shall be backfilled in accordance with clauses 3, 5.5, 5.6, 5.7 and 7 of SABS 1200 DB : Earthworks (Pipe trenches)

Pipes shall be bedded in accordance with clauses 3.1 to 3.4.1, 5.1 to 5.3 and 7 of SABS 1200 LB : Bedding (Pipes).

Unless otherwise described bedding of rigid pipes shall be class B bedding

-191-

STORMWATERBill No. 4Section No. 7

Carried Forward R

Page 192: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SUB-SOIL DRAINAGE

200m

110mm Slotted uPVC pipes laid in and including trenches not exceeding 1m deep, including 19mm crushed stone encasing size 300 x 300mm and Bidum Type U24 filter fabric blanket wrapped around encasing with 150mm side and 300mm end laps including stitching, complete with excavations and carting away of excavated material and backfilling of trenches with clean river sand

1

"Netlon" Slotted drainage pipes

2NoExtra over 110mm slotted uPVC pipe for end cap2

STORMWATER DRAINAGE

658m

Surface channel size 1500mm wide x average 120mm thick with 50mm deep V-shaped waterway (concrete = 0,18 m3/m)

3

25MPa/19mm unreinforced concrete with rounded salient edges and finished on exposed surfaces with 2:1 cement mortar, laid to falls in panels not exceeding 2m long with 12mm bitumen impregnated softboard movement joints with exposed edges raked out for a depth of 10mm and sealing with "Sikaflex-1a" joint sealant including all necessary formwork, excavations, compaction, etc

8NoExtra over 1200mm wide channel for closed ends, angle intersection, tee intersections, etc

4

120m

250mm Diameter uPVC stormwater pipe Class 34 laid intrenches to falls on suitable bedding material as per manufacturers instructions including all excavations, filling and compaction

5

Class 34 uPVC Stormwater Pipes

-192-

STORMWATERBill No. 4Section No. 7

Carried Forward R

Page 193: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

120m300mm Pipes laid in and including trenches not exceeding 1m deep

6

Class 75D reinforced precast concrete pipes wih ogee joints and rubber collars, etc. laid to falls in ground, on class B imported bedding including excavations, backfilling in 150mm thick layers, compaction to 95% Modified AASHTO dry density at OHC and all necessary risk of collapse, dewatering of trenches, etc.

-193-

STORMWATERBill No. 4Section No. 7

Carried Forward R

Page 194: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Catchpits, inspection chambers, etc

2NoStormwater sump exceeding 750mm and not exceeding 1000mm deep internally

7

Excavate in earth for and build stormwater catch pit internal size 500 x 500mm with one brick sides in extra hard stock bricks in (1:3) cement mortar on 150mm thick concrete class 25/19 base slab projecting 75mm all round, rendered internally in (1:3) cement plaster and including 100mm thick concrete cover slab with slight sloped top surface and with 600 x 600mm rebated opening for steel grating (elsewhere measured) formed with 50 x 50 x 6mm galvanised angle section with lugs cast into internal edge, the bottom benched up in fine mass concrete benching in bottom floated smooth with falls and finished on all exposed surfaces with 25mm thick granolithic all complete as detailed on drawing 22104-TP-02

2NoStormwater sump exceeding 1500mm and not exceeding 1750mm deep internally

8

2NoStormwater sump exceeding 2000mm and not exceeding 2250mm deep internally

9

4NoStormwater sump exceeding 1250mm and not exceeding 1500mm deep internally

10

Excavate in earth for and build stormwater catch pit internal size 700 x 700mm with one brick sides in extra hard stock bricks in (1:3) cement mortar on 150mm thick concrete class 25/19 base slab projecting 75mm all round, rendered internally in (1:3) cement plaster and including 100mm thick concrete cover slab with slight sloped top surface and with 600 x 600mm rebated opening for steel grating (elsewhere measured) formed with 50 x 50 x 6mm galvanised angle section with lugs cast into internal edge, the bottom benched up in fine mass concrete benching in bottom floated smooth with falls and finished on all exposed surfaces with 25mm thick granolithic all complete as detailed on drawing 22104-TP-02

6NoStormwater sump exceeding 1500mm and not exceeding 1750mm deep internally

11

-194-

STORMWATERBill No. 4Section No. 7

Carried Forward R

Page 195: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

2NoStormwater sump exceeding 2000mm and not exceeding 2250mm deep internally

12

4NoStormwater kerb inlet catch pit exceeding 1250mm and not exceeding 1500mm deep internally

13

Excavate in earth for and build stormwater kerb inlet catch pit (type "S2") internal size 1265 x 805mm with one brick sides in extra hard stock bricks in (1:3) cement mortar on 250mm thick concrete class 25/19mm base slab projecting 258mm all round, 100mm thick concrete class 25/19mm intermediate triangular side base slabs with 75mm thick sloping drains to form overall 1220mm wide kerb inlet rendered internally in (1:3) cement plaster and including 1200mm thick precast concrete cover slabs, supported on one precast concrete support beams in one triangular side panels and centre rectangular panel with 600mm diameter rebated opening for heavy duty precast concrete cover (elsewhere measured), the bottom benched up in fine mass concrete benching in bottom floated smooth with falls and finished on all exposed surfaces with 25mm thick granolithic all complete as detailed on drawing 22104-TP-02

2NoStormwater kerb inlet catch pit exceeding 1500mm and not exceeding 1750mm deep internally

14

-195-

STORMWATERBill No. 4Section No. 7

Carried Forward R

Page 196: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

2NoStormwater kerb inlet catch pit exceeding 1250mm and not exceeding 1500mm deep internally

15

Excavate in earth for and build stormwater kerb inlet catch pit (type "D3") internal size 1265 x 805mm with one brick sides in extra hard stock bricks in (1:3) cement mortar on 250mm thick concrete class 25/19mm base slab projecting 258mm all round, 100mm thick concrete class 25/19mm intermediate triangular side base slabs with 75mm thick sloping drains to form overall 3660mm wide kerb inlet rendered internally in (1:3) cement plaster and including 1200mm thick precast concrete cover slabs, supported on two precast concrete support beams in two triangular side panels and centre rectangular panel with 600mm diameter rebated opening for heavy duty precast concrete cover (elsewhere measured), the bottom benched up in fine mass concrete benching in bottom floated smooth with falls and finished on all exposed surfaces with 25mm thick granolithic all complete as detailed on drawing 22104-CW-10

2NoInspection chamber exceeding 1250mm and not exceeding 1500mm deep internally

16

Excavate in earth for and build stormwater inspection chamber 920 x 920mm internal size with one brick sides in extra hard stock bricks in (1:3) cement mortar on 150mm thick concrete class 25/19 base slab projecting 75mm all round, rendered internally in (1:3) cement plaster and including 100mm thick precast concrete class 30/19 cover slab bedded on brick walls with 600mm diameter rebated opening for precast concrete cover (elsewhere measured) sealed in tallow, the bottom benched up in fine mass concrete benching in bottom floated smooth with falls and finished on all exposed surfaces with 25mm thick granolithic with angles rounded including all necessary step irons, etc, all complete as detailed on drawing 22104-CW-10

2NoInspection chamber exceeding 2000mm and not exceeding 2250mm deep internally

17

-196-

STORMWATERBill No. 4Section No. 7

Carried Forward R

Page 197: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

10No

450 x 450mm x 50mm Thick heavy duty hot dipped galvanised banded Mentis Regtagrid RS40 grating with 50 x 4.5mm bearers bars (54.6kg/m²) fitted in and secure to angle section frame of rebated coverslab.

18

Covers etc

18No

600 x 600mm x 50mm Thick heavy duty hot dipped galvanised banded Mentis Regtagrid RS40 grating with 50 x 4.5mm bearers bars (54.6kg/m²) fitted in and secure to angle section frame of rebated coverslab.

19

SUNDRIES

2No

Subsoil drainage headwall constructed of Class 15/19 concrete wall 500 x 500 x 100mm thick with 100mm diameter outlet pipe connection flush and watertight, with 500 x 500mm stone pitching of approximately 150mm diameter river stones tightly packed in 150mm thick layer and bedded and jointed in 1:4 cement mortar and pointed with hollow recessed joints, including preparation of ground surface under, all excavations, carting away and formwork

20

Subsoil drainage outlet header walls

4No

Stormwater headwall constructed of Class 20/19 concrete base slab 150mm thick and 1800mm long overall, the slab widening from 760mm at head to 2640mm at base end and with 150 x 600mm deep toe at discharge end and five 250 x 375mm splitters blocks projecting 250mm above slab, the slab and toe reinforced with R10 mild steel reinforcing at 300mm centres in both ways, the splitter blocks reinforced with R10 mild steel reinforcing 1200mm girth four times bent to shape, the headwall 600mm long x 510mm high with 300mm diameter outlet pipe connection flush and watertight, with two sidewalls 2850mm long sloping from 510mm to 250mm high, all of one brick walls in "NFX" extra hard stock bricks in (1:3) cement mortar, all including excavations, compaction, backfilling, formwork and smooth trowelled finish to all exposed surfaces

21

Header walls

-197-

STORMWATERBill No. 4Section No. 7

Carried Forward R

Page 198: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

2No

Stormwater headwall constructed of Class 20/19 concrete base slab 150mm thick and 1800mm long overall, the slab widening from 840mm at head to 2640mm at base end and with 150 x 600mm deep toe at discharge end and five 250 x 375mm splitters blocks projecting 250mm above slab, the slab and toe reinforced with R10 mild steel reinforcing at 300mm centres in both ways, the splitter blocks reinforced with R10 mild steel reinforcing 1200mm girth four times bent to shape, the headwall 600mm long x 510mm high with 375mm diameter outlet pipe connection flush and watertight, with two sidewalls 2800mm long sloping from 510mm to 250mm high, all of one brick walls in "NFX" extra hard stock bricks in (1:3) cement mortar, all including excavations, compaction, backfilling, formwork and smooth trowelled finish to all exposed surfaces

22

2No

"Reno" matress size 3 x 2 x 0,3m of 80 x 100mm galvanised mesh with 2.75mm minimum thickness heavy duty PVC coating laid on "Bidim Grade A4" geofabric including necessary excavations, etc

23

Reno matresses

25m3Intermediate excavations24

Extra over excavations in soft material for pipe trenches, chambers, etc. for

12m3Hard rock25

320m

V-shaped channel 500mm wide x 100mm thick with rounded salient edges and finished on exposed surfaces with (2:1) cement mortar, laid to falls in panels not exceeding 1800mm long with 12mm bitumen impregnated softboard movement joints with exposed edges raked out for a depth of 10mm and filled with bituminous compound including all necessary excavation and formwork

26

Mass concrete with a coarse aggregate of 19mm anda minimum compressive strength of 15MPa at 28 days

-198-

STORMWATERBill No. 4Section No. 7

Carried Forward to Summary of Section No. 7 R

Page 199: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 7

BILL NO. 5

Refer to 'The Preambles to Trades' as issued by the Office of the Chief Director, Department of Public Works, Roads and Transport

PARKING, WALKWAYS, ETC (PROVISIONAL)

NOTE:

EPWP: All the work in this trade shall be executed in accordance with the principles of Expanded Public Works Programme, that is, labour intensive methods shall be used (www.epwp.gov.za)

PAVING

254m3Reduced levels under roads and paving1

Excavation in earth not exceeding 2m deep

254m3Surplus material from excavations and/or stock piles on site to a dumping site to be located by the Contractor

2

Extra over all excavations for carting away

ItemKeeping excavations free of water other than subterranean water

3

Keeping excavations free of water

SOIL POISONING

1 692m2Weed-killing treatment of surface under paving4

Soil Treatment

-199-

APRONS, COVERED WALKWAYS, PAVING AND BULK Bill No. 5Section No. 7

Carried Forward R

Page 200: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

1 692m2Ant poison treatment ditto5

FILLING

220m2

Rip and scarify 150mm in situ layer, wet and apply heavy rollers or rammers to achieve 93% MOD AASHTO at OMC (Optimum Moisture Content). Perform testing (DCP) to such prepared ground and further wet and compact until minimum CBR (California Bearing Ratio) of 7 is reached throughout 800mm deep soil profile. (Soil tests elsewhere measured)

6

Earth filling obtained from the excavations and/or prescribed stock piles on site including haulage approximately 150m from perimeter of excavations or stock piles

254m3Under floors etc7

Coarse river sand filling supplied by the contractor

417m3Sub-base course under paving, roads, etc.8

Imported G7 material, supplied by the contractor and brought onto site, compacted in layers not exceeding 150mm thick to 95% Mod AASHTO density (Density CBR minimun of 15% at 95% Mod AASHTO density)

417m3150mm Sub-base course under paving, roads, etc.9

Imported G5 material, supplied by the contractor and brought onto site, compacted in layers not exceeding 150mm, to 95% Mod AASHTO density (Maximum PI < 12, minimum CBR > 30 at 95% Mod AASHTO density)

29m3Under paving ,roads etc10

Earth filling of C4 material supplied by the contractor, compacted to 97% Mod AASHTO density

-200-

APRONS, COVERED WALKWAYS, PAVING AND BULK Bill No. 5Section No. 7

Carried Forward R

Page 201: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

1 692m2

Compaction of ground surface under pavings, etc including scarifying for a depth of 250mm, breaking down oversize material, adding suitable material where necessary and compacting to 93% Mod ASSHTO density

11

Compaction of surfaces

10NoModified AASHTO density test12

Prescribed density tests on filling

23m

Barrier kerb (SABS 927 fig 7) with 150 x 150 x 300mm unreinforced concrete haunching at back of each joint including excavation, backfilling, etc

13

Precast concrete, finished smooth on exposed surfaces including bedding, jointing and pointing

26m

Barrier kerb (SABS 927 fig 7) with 150 x 150 x 300mm unreinforced concrete haunching at back of each joint circular on plan not exceeding 4m radius formed with short lengths of straight kerb including excavation, backfilling, etc

14

1 692m2Paving in herringbone bond to assembly areas roads ,walkways, etc

15

60mm "Corobrick Pavers" Clay paving blocks on 25mm thick river sand bed with sand and cement mixture swept into joints and hosed down

26m

200mm Edging on and including 200 x 150mm thick unreinforced concrete bedding including excavation, formwork, etc

16

19m3Surface beds cast in panels17

20 MPa/20 mm concrete

15m2Surface beds18

Finishing top surfaces of concrete smooth with a wood float

192m2Type 193 fabric reinforcement in concrete aprons19

Fabric reinforcement

-201-

APRONS, COVERED WALKWAYS, PAVING AND BULK Bill No. 5Section No. 7

Carried Forward R

Page 202: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

96mEdges, risers, ends and reveals not exceeding 300mm high or wide

20

Smooth formwork to sides

96m12 mm Joints not exceeding 300 mm high 21

Expansion joints with bitumen impregnated softboard between vertical concrete and brick surfaces

96m12 mm Joints not exceeding 300 mm high 22

Expansion joints with bitumen impregnated softboard between vertical concrete surfaces

RAMPS

12m3Trenches and holes for thickening under surface beds, etc

23

Excavation in earth not exceeding 2m deep

7m2

Compaction of ground surface under floors etc including scarifying for a depth of 150mm, breaking down oversize material, adding suitable material where necessary and compacting to 90% Mod AASHTO density

24

Compaction of surfaces

5m3Under floors, steps, pavings, etc25

Earth filling obtained from the excavations and/or prescribed stock piles on site compacted to 93% Mod AASHTO density

5m3Under floors, steps, pavings, etc.26

Earth filling supplied by the contractor compacted to 93% Mod AASHTO density

3m3Ramps including thickenings27

25MPa/19mm concrete

-202-

APRONS, COVERED WALKWAYS, PAVING AND BULK Bill No. 5Section No. 7

Carried Forward R

Page 203: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

7m2Ramps28

Finishing top surfaces of concrete smooth with a wood float

14mEdges, risers, ends and reveals not exceeding 300mm high or wide

29

Rough form work to sides

7m2Type 193 fabric reinforcement in concrete surface beds, slabs, etc

30

Fabric reinforcement

7m2Under surface beds, ramps, etc31

One layer of 250 micron "Consol Plastics Gunplas USB Green" or other equal and approved waterproof sheeting sealed at laps with "Gunplas Pressure Sensitive Tape"

WALKWAY SLABS

115m3Reduced levels under floors32

Excavation in earth not exceeding 2m deep

97m3Trenches 33

21m3Soft rock34

Extra over trench and hole excavations in earth for excavation in

11m3Hard rock35

49m3Surplus material from excavations and/or stock piles on site to a dumping site to be located by the contractor

36

Extra over all excavations for carting away

179m2Sides of trench and hole excavations not exceeding 1,5m deep

37

Risk of collapse of excavations

-203-

APRONS, COVERED WALKWAYS, PAVING AND BULK Bill No. 5Section No. 7

Carried Forward R

Page 204: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

ItemKeeping excavations free of all water other than subterranean water

38

Keeping excavations free of water

28m3Backfilling to trenches, holes, etc39

Earth filling obtained from the excavations and/or prescribed stock piles on site compacted to 93% Mod AASHTO density

29m3Under floors, steps, pavings, etc40

Earth filling supplied by the contractor compacted to 95% Mod AASHTO density

154m2

Under floors etc including forming and poisoning shallow furrows against foundation walls etc, filling in furrows and ramming

41

Soil insectiside

104m2To bottoms and sides of trenches42

4m3Surface beds 43

20MPa/19mm concrete

20m3Strip footings44

154m2Type 193 fabric reinforcement in concrete surface beds, slabs, etc

45

Fabric reinforcement

107m2One brick walls46

Brickwork of NFX bricks (14 MPa nominal compressive strength) in class I mortar

416m150mm Wide reinforcement built in horizontally47

Brickwork reinforcement

-204-

APRONS, COVERED WALKWAYS, PAVING AND BULK Bill No. 5Section No. 7

Carried Forward R

Page 205: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

7m2Extra over brickwork for face brickwork48

External face bricks (Prime Cost Amount R 4 500.00/1000) pointed with flush horizontal and vertical joints both sides

23m220mm Wide sill set sloping and slightly projecting49

Brick-on-edge header course copings, sills, etc of external face bricks (Prime Cost Amount R 3 500.00/1000) pointed with flush joints on all exposed faces

COVERED WALKWAYS

414m3Reduced levels under floors50

Excavation in earth not exceeding 2m deep

56m3Trenches 51

47m3Soft rock52

Extra over trench and hole excavations in earth for excavation in

24m3Hard rock53

68m3Surplus material from excavations and/or stock piles on site to a dumping site to be located by the contractor

54

Extra over all excavations for carting away

282m2Sides of trench and hole excavations not exceeding 1,5m deep

55

Risk of collapse of excavations

ItemKeeping excavations free of all water other than subterranean water

56

Keeping excavations free of water

-205-

APRONS, COVERED WALKWAYS, PAVING AND BULK Bill No. 5Section No. 7

Carried Forward R

Page 206: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

42m3Backfilling to trenches, holes, etc57

Earth filling obtained from the excavations and/or prescribed stock piles on site compacted to 93% Mod AASHTO density

94m3Under floors, steps, pavings, etc58

Earth filling supplied by the contractor compacted to 95% Mod AASHTO density

94m2

Under floors etc including forming and poisoning shallow furrows against foundation walls etc, filling in furrows and ramming

59

Soil insectiside

102m2To bottoms and sides of trenches60

20m3Surface beds 61

20MPa/19mm concrete

30m3Strip footings62

93m2Type 193 fabric reinforcement in concrete surface beds, slabs, etc

63

Fabric reinforcement

112m2One brick walls64

Brickwork of NFX bricks (14 MPa nominal compressive strength) in class I mortar

564m150mm Wide reinforcement built in horizontally65

Brickwork reinforcement

56m2Extra over brickwork for face brickwork66

External face bricks (Prime Cost Amount R 4 500.00/1000) pointed with flush horizontal and vertical joints both sides

-206-

APRONS, COVERED WALKWAYS, PAVING AND BULK Bill No. 5Section No. 7

Carried Forward R

Page 207: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

187m220mm Wide sill set sloping and slightly projecting67

Brick-on-edge header course copings, sills, etc of external face bricks (Prime Cost Amount R 3 500.00/1000) pointed with flush joints on all exposed faces

187m75 x 75 x 25 x 3mm Lipped channel section purlins welded on

68

Sundry steelwork to walkways

187m150 x 75 x 20 x 3mm Lipped channel section purlins welded on cleats

69

155m75 x 75 x 3mm Hollow section coulmns 2475mm long70

187m75 x 75 x 3mm Hollow section beams and bearers etc71

136No120mm Long 75 x 75 x 5mm angle section purlin cleat welded on

72

136No100 x 100 x 3mm Thick base blate plate welded on and casted into base

73

256NoM12 x 75mm Expansion bolt74

94m2Roof covering with pitch not exceeding 25 degrees 75

0,6mm "IBR 686" Spelter galvanised ribbed sheet steel with "globalcoat" finish on one side in single lengths fixed to timber/steel purlins and 0,6mm galvanised sheet steel accessories with "globalcoat"finish on one side

684mOn rails, bars, pipes, etc not exceeding 300 mm girth76

Spot priming defects in pre primed surfaces with zinc chromate primer and applying one undercoat and two coat high gloss enamel paint on steel

-207-

APRONS, COVERED WALKWAYS, PAVING AND BULK Bill No. 5Section No. 7

Carried Forward to Summary of Section No. 7 R

Page 208: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 7

BILL NO. 6

Refer to 'The Preambles to Trades' as issued by the Office of the Chief Director, Department of Public Works, Roads and Transport

FENCING (PROVISIONAL)

NOTE:

EPWP: All the work in this trade shall be executed in accordance with the principles of Expanded Public Works Programme, that is, labour intensive methods shall be used (www.epwp.gov.za)

SUPPLEMENTARY PREAMBLES

The boundary line shall be cleared of all vegetation, trees, rocks, rubble and rubbish for a width of 500mm on each side and the same removed from site.

The one meter wide boundary line shall be graded to an even line so that the fencing mesh later described, shall have a 50mm gap at the bottom and a height of 1800mm above ground level.

Allowance shall therefore be made as required to excavate areas that are to high and to fill depressions with approved clean filling, carted on where necessary and well compacted prior to erection of posts.

Work on site

-208-

FENCING (PROVISIONAL)Bill No. 6Section No. 7

Carried Forward R

Page 209: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

Supply each gate with a suitable length of heavy duty chain and a 50mm heavy duty brass padlock with two keys

Gates shall have all joints and accessories securely welded on with all welds neatly trimmed and waterproofed, with either square and mitred corners or accurately jig-formed rounded corners with a radius not exceeding 100mm

Gates

Gates shall be hot dipped galvanised after fabrication, to conform with the requirements of SABS specification 763 - Class A _________________

4 527m2

Digging up and removing rubbish, debris, vegetation, hedges, shrubs and trees not exceeding 200mm girth, bush, etc

1

Site clearance

543mDemolish existing wire mesh fence2

EXISTING PERIMETER FENCE

EXCAVATION, FILLING, ETC

235m3Holes3

Excavation in earth not exceeding 2m deep

24m3Soft rock4

Extra over trench and hole excavations in earth for excavation in

12m3Hard rock5

141m3Surplus material from excavations and/or stock piles on site to a dumping site to be located by the contractor

6

Extra over all excavations for carting away

-209-

FENCING (PROVISIONAL)Bill No. 6Section No. 7

Carried Forward R

Page 210: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

782m2Sides of trench and hole excavations not exceeding 1,5m deep

7

Risk of collapse of excavations

ItemKeeping excavations free of all water other than subterranean water

8

Keeping excavations free of water

UNREINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

59m3In bases9

25MPa/19mm concrete

15NoMaking and testing 150 x 150 x 150mm concrete strength test cube (Provisional)

10

TEST BLOCKS

SECURITY FENCING

543m

Palisade fencing 3000mm wide x 1800mm high comprising 40 x 40 x 3mm hot rolled angle iron three prong pales at 200 centres welded to and including 38 x 76 x 2mm steel tube top and bottom rails secured to 76 x 76 x 2mm hollow section intermediate, corner and gate posts 1800mm long at 3000mm including M8 x 30 cup square with anti-vandal nuts, the posts complete with ABS vacuum formed top caps and 3mm thick bottom plates anchored to concrete (elsewhere) installed complete

11

Steel palisade fencing

Gates, screens, etc.

2NoGate 1,2 x 1,8m high including sliding lock and padlock12

Extra over palisade fencing for gates

1No

Double gate 6 x 1,8m high including heavy duty hasp and staple, padlock and two barrel bolts with two keeps in and including concrete anchor blocks

13

-210-

FENCING (PROVISIONAL)Bill No. 6Section No. 7

Carried Forward R

Page 211: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

PAINTWORK

1 631m2On steel palisade fencing including posts, etc. (both sides measured flat)

14

Prepare and apply one coat zinc chromate primer and two coats bituminous paint

-211-

FENCING (PROVISIONAL)Bill No. 6Section No. 7

Carried Forward to Summary of Section No. 7 R

Page 212: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 7

BILL NO. 7

PREAMBLESFor Preambles refer to "Standard Preambles To All Trades Rev 2 - January 2009" and "Supplementary Preambles"

CARPORTS (PROVISIONAL)

SUPPLEMENTARY PREAMBLESProprietary items or materialsProprietary items or materials where specified are to be of the brand specified - or other approved - by the Head: Works

NEW 6 BAYS COVERED AND 4 UNCOVERED BAYS

(WORK GROUP 104)

EXCAVATION, FILLING, ETC OTHER THAN BULK

15m3Holes1

Excavation in earth not exceeding 2 m deep

2m3Soft rock2

Extra over trench and hole excavations in soft material for

1m3Hard rock excavation3

6m3Surplus material from excavations and/or stock piles on site to a dumping site to be located by the contractor

4

Extra over all excavations for carting away

ItemKeeping excavations free of water5

Keeping excavations free of water

-212-

CARPORTBill No. 7Section No. 7

Carried Forward R

Page 213: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SOIL POISONING

250m2

Under floors etc including forming and poisoning shallow furrows against foundation walls etc, filling in furrows and ramming

6

Soil insecticide

(WORK GROUP 110)

CONCRETE, FORMWORK AND REINFORCEMENT

The costs of making, storing and testing of concrete test cubes as required under clause 7 "Tests" of SABS 1200 G shall include the cost of providing cube moulds necessary for the purpose, for testing costs and for submitting reports on the tests tothe architect. The testing shall be undertaken by an independent firm or institution nominated by the contractor to the approval of the architect. (Test cubes are measured separately)

General

REINFORCED CONCRETE CAST AGAINST EXCAVATED SURFACES

2m3Bases7

25MPa/19mm concrete

Item

Allow for necassary concrete test cubes size 150 x 150mm cast from batches of concrete required for the entire contract as specified, made, stored, cured and tested in accordance with SABS Method 861 and 863, including use of approved cube moulds, transporting to an approved testing laboratory for testing, paying all charges and submitting reports to the Representative/Agent

8

TEST BLOCKS

CONCRETE SUNDRIES

-213-

CARPORTBill No. 7Section No. 7

Carried Forward R

Page 214: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

250m2Surface beds, slabs, etc9

Class U2 ordinary finish to top surfaces of concrete

10NoBedding approximately 25mm thick under 200 x 200mm base plate including chamfered edges all round

10

15 MPa non-shrink grout

(WORK GROUP 124)

NOTE: The contractor is to submit a certificate signed by the merchant, stating that the roof covering supplied complies with the required thickness specified.

PROFILED METAL SHEETING AND ACCESSORIES

165m2Roof covering 11

0,55mm Chroma deck C1S IBR 686 White Lion Roof Sheets fixed to steel purlins.

(WORK GROUP 134)

STEEL COLUMNS AND BEAMS

1t100 x 100 x 3mm Hollow section columns12

Vertical hollow sections columns fixed to flat base plate welded on and bolted to concrete

1t100 x 100 x 3mm Hollow section beams welded to columns

13

Welded beams, rafter, etc in single lengths with flat section bearer and connection plates bolted to steel columns including hoisting and fixing in position 2,7m above natural ground level

90NoM12 x 75mm Expansion bolt14

Bolts to columns, etc

PURLINS, GIRTS, BRACING, ETC

-214-

CARPORTBill No. 7Section No. 7

Carried Forward R

Page 215: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

1.2t125 x 75 x 20 x 2.5 thick steel purlins15

Purlins, girts, cleats, etc. bolted to steel

(WORK GROUP 152)

PAINTWORK, ETC TO NEW WORK

PRIMING OF STRUCTURAL STEELWORK (CLASS P1)

25m2On carport steel16

Clean surfaces, bring to a bright metallic condition and paint surfaces with one coat red oxide zinc chromate metal primer on steel:

ON METAL

50m2On carport steel17

Spot priming defects in pre-primed surfaces with 'Plascon Namelcote Synthetic Metal' and apply one coat 'Plascon Merit Universal Undercoat' and two coats 'Plascon Magic Flow Eggshell Enamel' paint on steel

-215-

CARPORTBill No. 7Section No. 7

Carried Forward to Summary of Section No. 7 R

Page 216: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION SUMMARY - EXTERNAL WORKS

BillNo

PageNo

Amount

182DEMOLITIONS1

186WATER RETICULATION2

189SEWER3

198STORMWATER4

207

APRONS, COVERED WALKWAYS, PAVING AND BULK SERVICES

5

211FENCING (PROVISIONAL)6

215CARPORT7

-216-

Section No. 7

Carried to Final Summary R

Page 217: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

AmountItemNo

Quantity Rate

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

SECTION 9

BILL NO. 1

1.The following sums and amounts are NET.

PROVISIONAL SUMS

2. Under no circumstances may any Provisional Sum be extended at an amount lower than the amount given in the bill.

3. Unless a specific percentage mark-up for Attendance is indicated in a rate column, the amount priced by the Contractor for Attendance against each Provisional Sum shall be deemed to be the Lump Sum and shall not be adjusted unless the scope of the sub contract varies significantly.

4. Provisional Sums contained here-in may be omitted or reduced at the employer's sole discretion and the Contractor shall not be entitled to claim for any loss by way of reductions or omissions or any discount, or percentage relating to Provisional Sums or PC amounts or any loss of profit related thereto.

260 000.00Item

Provide the sum of R 260 000.00 (Two Hundred and Sixty Thousand Rand) for classroom furniture installed complete

1

CLASSROOM FURNITURE (To be carried out by domestic sub-contractor)

ItemProfit on above item.2

ItemAttendance on ditto.3

-217-

PROVISIONAL SUMBill No. 1Section No. 8

Carried Forward R

Page 218: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

77 900.00Item

Provide the sum of R 77 900.00 (Seventy Seven Thousand Nine Hundred Rand) for Grade R furniture installed complete

4

GRADE R FURNITURE (To be carried out by domestic sub-contractor)

ItemProfit on above item.5

ItemAttendance on ditto.6

154 000.00Item

Provide the sum of R 154 000.00 (One Hundred and Fifty Four Rand) for Multi purpose classroom furniture installed complete

7

MULTI PURPOSE CLASSROOM FURNITURE (To be carried out by domestic sub-contractor)

ItemProfit on above item.8

ItemAttendance on ditto.9

20 000.00Item

Provide the sum of R20 000.00 (Twenty Thousand Rand) for signage installed complete

10

SIGNAGE (To be carried out by domestic sub-contractor)

ItemProfit on above item11

ItemAttendance on ditto.12

-218-

PROVISIONAL SUMBill No. 1Section No. 8

Carried Forward R

Page 219: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

Brought Forward R

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

200 000.00Item

Provide the sum of R 200 000.00 (Two Hundred Thousand Rand) for borehole installed complete

13

BOREHOLE (To be carried out by domestic sub-contractor)

ItemProfit on above item.14

ItemAttendance on ditto.15

200 000.00Item

Provide the sum of R200 000.00 (Two Hundred Thousand Rand) water tank and stand complete

16

WATER TANK AND STAND COMPLETE (To be carried out by domestic sub-contractor)

ItemProfit on above item.17

ItemAttendance on ditto.18

983 021.00Item

Allow the sum of R 983 021.00 (Nine Hundred and Eighty Three Thousand Twenty One Rands) for electrical installation

19

ELECTRICAL INSTALLATION (To be carried out by domestic sub-contractor)

ItemProfit on above item20

ItemAttendance on ditto21

82 500.00Item

Allow the Budgetary Amount of R 82 500.00 (Ninety Seven Thousand Five Hundred Rand) NET for the employment of a community liaisons officer required for labour requirements by the contractor and deducted in whole part if not required.The contractor must issue copies of CLOs payslip to PA and IDT.The CLO will also report on EPWP

22

COMMUNITY LIASON OFFICER

-219-

PROVISIONAL SUMBill No. 1Section No. 8

Carried to Final Summary R

Page 220: SECTION 1 BILL NO. 1 PRELIMINARIES

2021/05/26

(EDDP 184/82)

MAPANGULA PRIMARY SCHOOL

PageNo

FINAL SUMMARY

SectionNo

Amount

28PRELIMINARIES1

73NEW 1 x GRADE R 2

110NEW 1 x 4 CLASSROOM BLOCK3

147NEW 1 X 3 CLASSROOM4

170NEW 1 x MULTI PURPOSE CLASSROOM5

173RENOVATE 4 X 4 EXISTING ENVIROLOO SEATS6

216EXTERNAL WORKS7

219PROVISIONAL SUM8

RSUB TOTAL - 1 BUILDING COSTS

Item

Provide the sum of R 594 616.20 (Five Hundred and Ninety Four Thousand Six Hundred and Sixteen Rand and Twenty Cents) for contingencies to be expended as the Client may direct or deduct

CONTINGENCY SUM

Item

Provide the amount of R 471 889.88(Four Hundred and Seventy One Thousand Eight Hundred and Eighty Nine Rand and Eighty Eight Cents) for escalation

ESCALATION

RSUB TOTAL BUILDINGS (VAT excl.)

RValue Added Tax @15%

RSub Total (VAT INCL) CARRIED TO FORM OF TENDER