seattle university milestone schedule center for science ... › media › facilities-services ›...

1
University Community update July 1, 2019 Project Contact: Project Description: Ranleigh Starling Sr. Project Manager 206-296-6325 [email protected] -111,500 square feet -5 stories above grade -Biology/chemistry labs and classrooms -Computer Science Project Center -University Maker space -Center for Community Engagement -KXSU CSI Construction Updates for the Month of July: New Building construction site: -Skanska will continue to clear and grub the site and prepare for demolition in early July. -The existing USVC building will be demolished. -Installation of Geo Piers for ground improvement, utility vaults, storm water detention pipes, and electrical and telecommunications conduits will begin after removal of the existing building. Lower Mall and Marion Street Activities: -Saw cutting pavement on the lower mall and at Marion Street continues to create a new utility pathways between existing campus utility vaults and the new building site. Work areas are fenced. -After the utility infrastructure is in place, the paving on lower mall and Marion will be repaired, and fences removed. S Seattle University Center for Science and Innovation Milestone Schedule Month of July: -Demolish existing building -Excavate for Tower Crane Footing/Base -Install Geo Piers Month of August: -Mass excavation -Erect Tower Crane -Install Geo Piers Fun Fact: -Over 1,762,000 pounds of steel will be used at the Center for Science and Innovation, this is the equivalent to the weight of 294 African forest elephants. Thank you for your patience! The overall construction schedule is targeting completion by spring 2021. Construction camera: Here is the link for general viewing of the cameras: http://dwpwebcams.com/sucsi/slideshow.htm?station=View1 LOGIN: SUCSI PW: skanska1

Upload: others

Post on 27-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Seattle University Milestone Schedule Center for Science ... › media › facilities-services › ... · University Community update July 1, 2019 Project Contact: Project Description:

UniversityCommunity updateJuly 1, 2019

Project Contact: Project Description:Ranleigh StarlingSr. Project [email protected]

-111,500 square feet-5 stories above grade-Biology/chemistry labs and classrooms-Computer Science Project Center-University Maker space-Center for Community Engagement-KXSU

CSI Construction Updates for the Month of July:

New Building construction site:

-Skanska will continue to clear and grub the site and prepare for demolition in early July.

-The existing USVC building will be demolished.

-Installation of Geo Piers for ground improvement, utility vaults, storm water detention pipes, and electrical andtelecommunications conduits will begin after removal of the existing building.

Lower Mall and Marion Street Activities:

-Saw cutting pavement on the lower mall and at Marion Street continues to create a new utility pathways betweenexisting campus utility vaults and the new building site. Work areas are fenced.

-After the utility infrastructure is in place, the paving on lower mall and Marion will be repaired, and fences removed.

SSeattle University Center for Science and

Innovation

Milestone Schedule

Month of July:-Demolish existingbuilding-Excavate for TowerCrane Footing/Base-Install Geo Piers Month of August:-Mass excavation-Erect Tower Crane-Install Geo Piers Fun Fact: -Over 1,762,000pounds of steel will beused at the Center forScience andInnovation, this is theequivalent to theweight of 294 Africanforest elephants.

Thank you for your patience! The overall construction schedule is targeting completion by spring 2021.

Construction camera:Here is the link for general viewing of the cameras:http://dwpwebcams.com/sucsi/slideshow.htm?station=View1 LOGIN: SUCSIPW: skanska1

20190627_SU_CSI_University Newsletter (editable).pdf 1 6/27/2019 9:45:00 AM