ARENDAL SmartPlant ® Materials (SPMat) Fast Track Consulting Services Statement of Work (SOW) October 13, 2014 Document Number: PPM-14-MEX1, V1 Adrián Hernández López +52(55)55255594, x3000 [email protected]

Upload: vankhanh

Post on 11-May-2018

219 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

ARENDAL SmartPlant® Materials (SPMat) Fast Track Consulting Services

Statement of Work (SOW) October 13, 2014 Document Number: PPM-14-MEX1, V1 Adrián Hernández López +52(55)55255594, x3000 [email protected]

Page 2: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 2 of 30

Copyright

Copyright© 2004-2014 Intergraph Corporation. All Rights Reserved. Intergraph is part of Hexagon.

Notice

This Statement of Work contains confidential and proprietary information of Intergraph Corporation, Intergraph de México, and/or relevant third parties which is protected by copyright law, trade secret law, and international treaty, and may not be provided or otherwise made available without proper authorization. Said confidential and proprietary information shall not be disclosed outside ARENDAL and shall not be duplicated, used or disclosed, in whole or in part, for any purpose other than as stated in the Terms of this Statement of Work. Where disclosure of Intergraph Corporation, Intergraph de México, and/or relevant third-party confidential and proprietary information requires review by other third parties, ARENDAL shall formally request permission from an authorized legal representative of Intergraph Corporation, Process, Power & Marine Division (PP&M) to duplicate, use, or disclose in whole or in part the said confidential or proprietary information.

Trademarks

Intergraph®, the Intergraph logo®, PDS®, SmartPlant®, SmartMarine®, Intergraph Smart™, FrameWorks®, SmartSketch®, ISOGEN®, Spoolgen®, SupportManager®, SupportModeler®, TANK, I-Export, I-Route, PV-Elite®, CADWorx®, CADWorx DraftPro®, and CAESARII® are trademarks or registered trademarks of Intergraph Corporation or its subsidiaries in the United States and other countries. Microsoft®, Excel®, Access®, Active Directory®, Vista®, Windows®, Forefront®, Office 365, XP Professional, and Azure are registered trademarks or trademarks of Microsoft Corporation. Oracle® is a registered trademark of Oracle Corporation. MicroStation® is a registered trademark of Bentley Systems, Inc. SAP® and SAP NetWeaver® are registered trademarks of SAP AG in Germany and in several other countries. Other brands and product names are trademarks of their respective owners.

Revision History

Version Date Revised By Reason

1.0 10/Oct/14 AHL Initial version

1.0 AHL Legal review

Page 3: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30

Table of Contents

1 INTRODUCTION ..........................................................................................................................4

2 SCOPE OF SERVICES AND DELIVERABLES ......................................................................................4

2.1 SPMAT FAST TRACK IMPLEMENTATION........................................................................................... 4 2.2 PROJECT MANAGEMENT .................................................................................................................. 5 2.3 ASSUMPTIONS ................................................................................................................................. 5 2.4 CLARIFICATIONS, LIMITATIONS, AND EXCLUSIONS ............................................................................ 5

3 CHANGE MANAGEMENT PROCESS ..............................................................................................6

4 SCHEDULE ..................................................................................................................................6

5 COMPLETION NOTICE .................................................................................................................6

6 PRICING......................................................................................................................................7

7 INVOICING AND TERMS OF PAYMENT .........................................................................................8

8 ADDITIONAL TERMS AND CONDITIONS FOR CONSULTING SERVICES ............................................8

9 APPROVAL SIGNATURES ........................................................................................................... 11

ATTACHMENT A- WORK PACKAGES .................................................................................................. 13

Page 4: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 4 of 30

1 Introduction

Intergraph de México (hereinafter referred to as "PP&M") will provide consulting services to ARENDAL (hereinafter referred to as “Arendal”) on a fixed price basis as stated in this Statement of Work (SOW).

2 Scope of Services and Deliverables

PP&M will provide consulting services to implement out-of-the-box SmartPlant® Materials (SPMat) functionality in a pilot mode, enhance interfaces to selected applications, and roll-out SPMat with the enhanced interfaces to the Arendal Production environment.

PP&M expects to prepare a Press Release for your review and approval explaining the benefits that Arendal would have by implementing this solution.

2.1 SPMAT Fast Track Implementation

Specific activities to be performed by the Parties shall be documented and mutually agreed to in Work Packages that are specific to Arendal’s SPMat implementation. Said Work Packages are included in Attachment A for reference, but are summarized below to indicate the types of consulting services that PP&M consultants will provide to Arendal as part of the SPMat implementation.

Phase 1 – SPMAT Implementation using Fast Track

o Work Package a – Kickoff Meeting

o Work Package b – System installation

o Work Package c – SmartPlant® Reference Data (SPRD)

o Work Package d – Engineering & Procurement Integration

o Work Package e – Site Management

o Work Package f – Reports Enhancement Training

o Work Package g – Production Rollout

Phase 2 – SAP Interface

o Workshop to detail interfaces

o Create Functional Design System (FDS)

o Depending on the workshop and required interfaces, we will determine timing for the following activities:

Interface development

Interface testing

Interface deployment

Phase 3 – Support Production

o General on-site support during production

Page 5: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 5 of 30

Non-material changes in the scope of one (1) or more Work Packages will be mutually reviewed and approved by both Parties and work may proceed as scheduled; however, any material changes in the scope of one (1) or more Work Packages will be reviewed by the Parties and documented in a Change Request (CR) approved by an authorized Party representative.

Deliverables

SPMat Fast Track Implementation

SAP interface requirements (this will give us timing and activities for SAP interface deployment)

On-site support during 30 days of production

2.2 Project Management

PP&M will assign a Project Manager to oversee the completion of the consulting services and the provision of the Deliverables specified in this SOW.

2.3 Assumptions

PP&M has developed the scope and pricing for this SOW based on the following assumptions:

Arendal should have at least 3 licenses of SmartPlant Reference Data (SPRD), 5 licenses of SmartPlant Materials (SPMAT), and 1 license of SmartPlant Standard Data Base for SPRD (SDB) – Software not included in this Consulting Services Proposal

Arendal will provide all PP&M consultants working on-site with a work environment conducive to the on-going performance of their duties.

All PP&M consultants working on-site will adhere to Arendal’s standard work schedule.

Arendal will provide access to all appropriate knowledge experts as required.

The SOW’s schedule and estimate are dependent upon the timely exchange of required data as noted in this SOW.

2.4 Clarifications, Limitations, and Exclusions

Development will be performed using the latest version of SPMat. Any consulting services hours required to upgrade to a newer version of SPMat, should a new version of SPMat be released during the course of this project, are not included in this SOW.

Post-production support is outside the scope of this SOW.

Installation is limited to a single (one) environment. If requested, installation of SPMat and related software can be accommodated under a Change Order as described in Section 3, Change Management Process.

Any Intergraph Corporation proprietary information contained in a Deliverable or any source code provided by PP&M to Arendal is provided “as is” with no warranty whatsoever.

If required, PP&M resources located outside the U.S. may be utilized; thus, international travel may be necessary.

Page 6: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 6 of 30

3 Change Management Process

If either Party requests a change to this SOW, the following procedure shall be followed:

1. PP&M’s Project Manager will evaluate the change request and assess how implementing the requested change might impact the overall project price and schedule. PP&M will provide the change request impact statement to Arendal as an unsigned Change Order (CO).

2. Arendal will review the CO and evaluate its benefits and impact on other project objectives to determine if the change should be implemented. If the CO is to be implemented, PP&M will issue a signed CO to Arendal for final approval.

3. Upon issuance of the CO by PP&M, Arendal will sign the CO. In the event Arendal has previously issued a Purchase Order (PO) for the SOW, Arendal will make the appropriate change(s) in the applicable PO to reflect the agreed-upon price, schedule, and Deliverable changes as noted in the CO and deliver same to PP&M.

4. Upon receipt of the signed CO and acceptance of the updated PO from Arendal (if a PO is issued), PP&M will implement the change(s) specified in the Change Order.

PP&M may group several change requests into a single CO for Arendal’s evaluation.

No work included in a CO shall be executed until the CO is signed by both parties. CO processing delays that impact schedule and create rework may be subject to additional CO to cover the cost impacts caused by delays to the project.

4 Schedule

PP&M and Arendal will determine a mutually agreeable start date for the project.

5 Completion Notice

PP&M will provide a written Completion Notice of the SPMat Fast Track tasks and final status. Arendal will have five (5) workdays to accept or challenge the Completion Notice. If accepted, Arendal will sign the Completion Notice and promptly return a signed copy to PP&M. If Arendal wishes to challenge the Completion Notice, PP&M will evaluate and correct as necessary any agreed upon deficiencies via the SPMat Fast Track configuration files. Any issue that cannot be addressed via the SPMat Fast Track configuration files will be considered outside this SOW. Once completed, PP&M will resubmit the Completion Notice for Arendal’s signoff.

Should Arendal fail to signoff or contest the Completion Notice within the five (5) workday period, or if Arendal elects to place a deliverable into operation or production, said deliverable shall be deemed by PP&M to be accepted and the applicable payment milestone will be due and payable. PP&M has based its pricing on the review cycles described above. Delays in the review cycle, or delays for additional review iterations, may require an equitable adjustment in the pricing and schedule.

Page 7: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 7 of 30

6 Pricing

The price for the provision of the consulting services and/or deliverables per this fixed price Statement of Work is U.S. $170,560.00, excluding travel expenses (Phases 1, 2 and 3 are included as specified in this document, providing that Phase 2 will determine additional services required for SAP interface deployment).

If applicable, PP&M will charge travel time and expenses for the consulting services to Arendal at PP&M’s cost, plus ten percent (10%) for general and administrative expenses. Travel expenses may include, but are not limited to, airfare, hotel charges, car rental fees, and meals. Meals will be invoiced at current government per diem rates for the location where the services are provided. PP&M estimates that the travel expenses applicable to this SOW will be approximately U.S. $25,500.00.

The Purchase Order should reflect both the consulting services fixed price of U.S. $170,560.00 and a travel estimate of U.S. $25,500.00 for a total of U.S. $196,060.00.

The pricing in this Statement of Work will be valid for ninety (90) days following the cover date.

Page 8: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 8 of 30

7 Invoicing and Terms of Payment

Arendal will be invoiced per payment milestone as specified in the following schedule.

Payment Milestone Payment

Percentage Payment Amount

Upon Customer approval of SOW and PP&M acceptance of Purchase Order (related to Phase 1)

28% $47,840.00

Upon acceptance of Completion Notice (termination of Phase 1) 28% $47,840.00

Upon acceptance of Completion Notice (termination of Phase 2) 14.6% $24,960.00

Upon start of Phase 3 14.7% $24,960.00

Upon acceptance of Completion Notice (termination of Phase 3) 16.7% $24,960.00

Expenses will be invoiced every two weeks

The terms of payment are net thirty (30) days from the date of invoice.

Arendal agrees to pay interest on all overdue or unpaid invoices, at the rate of one and one-half percent (1 ½%) per month, or at the maximum rate permitted by law, whichever is less. No payments may be withheld by Arendal for any reason nor may any counterclaim by Arendal be set off against any payment due hereunder, without the prior written consent of an authorized PP&M representative.

PP&M will submit invoices to Arendal at the address shown on the Purchase Order or as otherwise advised by Arendal in writing.

8 Additional Terms and Conditions for Consulting Services

1. Disclaimer – PP&M DISCLAIMS (TO THE EXTENT PERMITTED BY LAW) ALL WARRANTIES, INCLUDING THE IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS FOR PARTICULAR USE. IF UNDER THE LAW RULED APPLICABLE TO THESE TERMS ANY PART OF THE ABOVE DISCLAIMER OF EXPRESSED OR IMPLIED WARRANTIES IS INVALID, THEN PP&M DISCLAIMS EXPRESS OR IMPLIED WARRANTIES TO THE MAXIMUM EXTENT ALLOWED BY SAID LAW.

2. Limitation of Liability - IN NO EVENT WILL PP&M BE LIABLE FOR ANY DAMAGES, INCLUDING BUT NOT LIMITED TO DIRECT, INDIRECT, INCIDENTAL, CONSEQUENTIAL, PUNITIVE OR SPECIAL DAMAGES, ANY LOSS OF USE OR PRODUCTION, ANY LOSS OF REVENUE OR PROFIT, ANY LOSS OF DATA, THE USE OR INABILITY TO USE ANY DELIVERABLE, OR CLAIMS OF THIRD PARTIES, ARISING OUT OF OR IN CONNECTION WITH ANY CONSULTING SERVICES OR DELIVERABLES PROVIDED UNDER THIS SOW, EVEN IF PP&M HAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES.

UNDER NO CIRCUMSTANCES SHALL PP&M’S LIABILITY UNDER THIS SOW EXCEED THE AMOUNT THAT PP&M HAS BEEN PAID BY ARENDAL PURSUANT TO THIS SOW AT THE TIME ANY CLAIM IS MADE. EXCEPT WHERE PROHIBITED BY APPLICABLE LAW, NO CLAIM, REGARDLESS OF FORM, ARISING OUT OF OR IN CONNECTION WITH THIS SOW MAY BE BROUGHT BY Arendal MORE THAN TWO (2) YEARS AFTER THE EVENT GIVING RISE TO THE CAUSE OF ACTION HAS OCCURRED.

IF UNDER THE LAW RULED APPLICABLE TO THESE TERMS ANY PART OF THIS SECTION IS INVALID, THEN PP&M LIMITS ITS LIABILITY TO THE MAXIMUM EXTENT ALLOWED BY SAID LAW.

Page 9: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 9 of 30

3. Ownership of Intellectual Property - All PP&M Software and related deliverables (including but not limited to data, programs, or program enhancements) provided by PP&M under this SOW is owned by PP&M and shall be licensed to Arendal pursuant to PP&M’s current Software License Agreement, except as may be modified or stated herein.

Arendal understands that PP&M possesses Information and data that was developed, created, or discovered by PP&M, or that has become known to or has been conveyed to PP&M, that has commercial value in PP&M’s day-to-day business. PP&M considers such Information and/or data to be proprietary and confidential. Such Information and/or data includes, but is not limited to, trade secrets, copyrights, inventions (whether patentable or not), concepts, ideas, methods, techniques, work processes, formulae, algorithms, logic designs, screen displays, schematics, and source and object code computer programs, all of which shall hereinafter be singularly or collectively referred to as PP&M’s Intellectual Property, which is owned by PP&M.

4. Nondisclosure - PP&M and Arendal each acknowledge that they may be furnished with, receive, or otherwise have access to information of or concerning the other Party, or relevant third party, which such Party or relevant third party considers to be confidential, proprietary, a trade secret or otherwise restricted. As used in this Agreement “Confidential Information” shall mean all information, which may include third party information, in any form, furnished or made available directly or indirectly by one Party to the other that is marked confidential, restricted, proprietary, or with a similar designation. This SOW is deemed to be Confidential Information. Confidential Information also shall include, whether or not designated “Confidential Information”, (i) all specifications, designs, documents, correspondence, software, documentation, data and other materials and work products produced by either PP&M or its subcontractors, and (ii) with respect to either Party, all information concerning the operations, financial affairs and businesses, and relations with its employees and service providers.

Each Party's Confidential Information shall remain the property of that Party, or relevant third party, except as expressly provided otherwise by the other provisions of this SOW. Arendal and PP&M shall each use at least the same degree of care, but in any event no less than a reasonable degree of care, to prevent disclosing to third parties the Confidential Information of the other as it employs to avoid unauthorized disclosure, publication or dissemination of its own information of a similar nature.

The Parties shall take reasonable steps to ensure that its employees comply with these confidentiality provisions.

This Section shall not apply to any particular information which PP&M or Arendal can demonstrate (i) was, at the time of disclosure to it, in the public domain; (ii) after disclosure to it, is published or otherwise becomes part of the public domain through no fault of the receiving Party; (iii) was in the possession of the receiving Party at the time of disclosure to it; (iv) was received after disclosure to it from a third party who had a lawful right to disclose such information to it without any obligation to restrict its further use or disclosure; or (v) was independently developed by the receiving Party without reference to Confidential Information of the furnishing Party. In addition, a Party shall not be considered to have breached its obligations by disclosing Confidential Information of the other Party as required to satisfy any legal requirement of a competent government body provided that, immediately upon receiving any such request and to the extent that it may legally do so, such Party advises the other Party promptly and prior to making such disclosure in order that the other Party may interpose an objection to such disclosure, take action to assure confidential handling of the Confidential Information, or take such other action as it deems appropriate to protect the Confidential Information.

Page 10: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 10 of 30

5. Employment – During a period from the commencement of the work described in this SOW until twelve (12) months after its completion, Arendal shall not employ or engage on any other basis or offer such employment or engagement to any of PP&M’s employees who have been associated with providing services under this SOW without the prior written approval of PP&M. Arendal agrees that if it employs or engages any PP&M employee contrary to the preceding paragraph, Arendal shall be liable to PP&M for liquidated damages in an amount equal to such employee’s salary per annum at the time of leaving the employment of PP&M.

6. Taxes - Prices are exclusive of all federal, state or local sales, use, property, gross receipts, value added or similar taxes based upon amounts payable to PP&M pursuant to this SOW (“Taxes”). Such Taxes, however do not include franchise taxes or taxes based on net income. Arendal agrees to pay PP&M any applicable Taxes or provide PP&M documentary evidence of an appropriate statutory exemption.

7. Governing Law – This SOW is governed by and shall for all purposes be construed and enforced under and in accordance with the laws of México and shall have been deemed to have been executed in México City, México. The parties agree to submit to the exclusive jurisdiction of, and agree that venue is proper in these courts in any such legal action or proceeding. The Parties waive the application of the United Nations Commission on International Trade Law and United Nations Convention on Contracts for the International Sale of Goods as to the interpretation or enforcement of this SOW.

8. Export Control – Intergraph Corporation Software and/or third-party software (which for this section also includes any Documentation or technical information pertaining thereto) provided by PP&M, its subsidiaries or distributors, is subject to the export control laws and regulations of the United States of America. For the purpose of this SOW, “Documentation” means, whether in electronic or printed form, User's Guides, Installation Guides, Reference Guides, Administrator's Guides, Customization Guides, Programmer's Guides, Configuration Guides and Help Guides delivered with Intergraph Software and/or third-party software supplied by PP&M to Arendal. Not all of the previous types of Documentation are delivered with Intergraph Software and/or third-party software supplied by PP&M. Diversion contrary to U.S. law is prohibited. Intergraph Corporation Software and/or third-party software, or the direct product(s) thereof, must not be exported or re-exported, directly or indirectly (including via remote access) under the following circumstances:

a. To Cuba, Iran, North Korea, Sudan, or Syria, or any national of these countries.

b. To any person or entity listed on any U.S. government denial list, including but not limited to, the U.S. Department of Commerce Denied Persons, Entities, and Unverified Lists, http://www.bis.doc.gov/complianceandenforcement/liststocheck.htm, the U.S. Department of Treasury Specially Designated Nationals List, www.treas.gov/offices/enforcement/ofac/, and the U.S. Department of State Debarred List, http://www.pmddtc.state.gov/compliance/debar.html

c. To any entity when Arendal knows, or has reason to know, the end use of the Intergraph Software and/or third-party software is related to the design, development, production, or use of missiles, chemical, biological, or nuclear weapons, or other un-safeguarded or sensitive nuclear uses.

d. To any entity when Arendal knows, or has reason to know, that an illegal reshipment will take place.

Page 11: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 11 of 30

Arendal should address any questions regarding export/re-export of relevant Intergraph Corporation Software and/or third-party software to Intergraph Corporation’s Export Compliance Department, Huntsville, Alabama 35894-00001, USA.

Arendal shall hold harmless and indemnify PP&M for any costs and or damages resulting to PP&M from a breach of this Article by Arendal.

THIS SECTION SHALL SURVIVE THE PERFORMANCE, EXPIRATION OR TERMINATION OF THIS AGREEMENT.

9. Place of Performance - Arendal agrees to provide appropriate work place accommodations, computer equipment, software, and necessary access for PP&M personnel.

10. Assignment - Neither PP&M nor Arendal shall assign any of its rights or delegate any of its obligations under this SOW without the prior written consent of the other Party, provided that such consent shall not be unreasonably withheld, except that PP&M may assign its rights and obligations under this SOW without the approval of Arendal to an entity which acquires all or substantially all of the assets of Intergraph Corporation or its Process, Power & Marine division, or to any subsidiary, affiliate or successor in a merger or acquisition of Intergraph Corporation or its Process, Power & Marine division.

11. Severability – Whenever possible, each provision of this SOW and each related document shall be interpreted in such a manner as to be effective and valid under applicable law. However, if any provision of this SOW shall be prohibited by or invalid under applicable law, such provision shall be ineffective only to the extent of such prohibition or invalidity without invalidating the remainder of such provision or the remaining provisions of this SOW.

12. Survival -- The Articles entitled “Disclaimer”, “Limitation of Liability”, “Ownership of Intellectual Property”, “Nondisclosure”, “Employment”, “Governing Law”, “Assignment”, and “Severability” shall survive termination or expiration of this SOW. The obligation imposed on Arendal to pay any unpaid charges which have been accrued and are due at the time of termination or expiration of this SOW, pursuant to “Terms of Payment” shall survive the expiration or termination of this SOW.

13. Entire Agreement – This SOW, and Arendal’s Purchase Order to the extent that it is not inconsistent with this SOW, constitutes the entire agreement between the Parties with respect to the subject matter hereof. All prior agreements, representations, statements, negotiations, and undertakings are superseded hereby. This SOW and Arendal’s Purchase Order shall not be amended or modified except by written agreement of the parties.

9 Approval Signatures

Signature below by an authorized PP&M representative constitutes PP&M’s release of this SOW for review by Arendal in accordance with the terms and conditions specified herein.

Page 12: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 12 of 30

Intergraph de México, Process, Power & Marine Division

Approved for Customer review by:

PP&M Contracts Administrator Date

PP&M Solutions Manager Date

Arendal and Intergraph acknowledge by their signatures below that this SOW is approved and accepted by an authorized party representative in accordance with the terms expressed herein.

ARENDAL Intergraph de México,

Process, Power & Marine Division

Approved by: Approved by:

Authorized Arendal Representative Date PP&M Contracts Administrator Date

This SOW shall only become binding and effective upon the written acceptance by PP&M and PP&M’s acceptance of Arendal’s corresponding Purchase Order or Service Order. To expedite acceptance, Arendal’s Purchase Order or Service Order should indicate that the Purchase Order or Service Order is issued in accordance with the Terms and Conditions of SOW PPM-14-MEX1, V1.

Arendal is requested to send the signed SOW, together with the corresponding Purchase Order or Services Order, to the following: [email protected], if sent electronically.

Or, if sent by FAX, express mail, or regular mail to the address and contact noted below:

Diann Copeland – Senior Contracts Administrator Intergraph Process, Power & Marine 300 Intergraph Way Building 30 – Mail Stop 135D Madison, AL 35758 Phone: (256) 730-3097 Fax: (256) 730-3300

Page 13: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 13 of 30

ATTACHMENT A- WORK PACKAGES

Optional? ID Work Package Description – Phase 1 – Fast Track Duration

(days)

N F1 Workshop to review and consolidate workflows 4

N A Kickoff Meeting 1

N B System Installation 5

N C SmartPlant Reference Data (SPRD) 5

N D Engineering & Procurement Integration 8

N E Site Management 5

Y F Reports Enhancement Training 5

N G Production Rollout 5

Optional? ID Work Package Description – Phase 2 – SAP Interface Duration

(days)

N S1 Workshop to detail interfaces 5

N S2 Create Functional Design Specification (FDS) 5

N S3 Interface development TBD

N S4 Interface testing TBD

N S5 Interface deployment TBD

Optional? ID Work Package Description – Phase 3 – Support Production Duration

(days)

N P1 General on-site support during production 20

Total for Work Packages: 68 days

Project Management (20%): 14 days

Page 14: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 14 of 30

Phase I – 1 .0, Kickoff Meeting

PP&M will discuss project implementation strategy, define communication processes, and plan with Arendal.

Scope

PP&M will provide services as specified below:

Project Implementation Introduction (Fast Track Methodology)

Review Work Package documentation and deliverables

Present Project Plan

Review Task List (activities from Work Packages)

Define communication paths

Make minor adjustments to Project Plan

Assumptions

Arendal will provide access to facilities, computers, databases, etc. for project members

Exclusions

None

Duration

1 day

Project Dependencies

Fast Track Methodology acceptance.

Client Dependencies

Project member access to required facilities/equipment/data/databases, etc.

Page 15: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 15 of 30

Activity Type

ID Description Role Dependency

Document 1 Develop Kickoff Meeting agenda Project Manager

Execute 2 Review Work Package documentation Project Manager 1

Deliver 3 Make Fast Track Project Plan adjustments Project Manager 1, 2

Document 4 Obtain Work Package acceptance and signoff Project Manager 3

Resource Name/Role Roles, Responsibilities, Remarks

Executive/Senior Consultant

Develops configuration training agenda and associated documentation, facilitates configuration training workshops, and reviews meeting minutes

Project Manager Provides management oversight, approves documentation, and oversees overall progress of this Work Package

Page 16: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 16 of 30

Phase I – 4 .0, System Installation

PP&M will install SPMat and SPRD and associated software/databases for Development/Test environment (one environment) within Arendal network located in Monterrey, N.L..

Scope

PP&M will provide services as specified below:

Install and configure SPMat Oracle® Database Server

Install and configure SPMat Oracle Web Fusion Application Server

Install and configure SPRD Plus Server

Install and Test three (3) SPRD Plus clients

Install SPMat v7.0.6 – with latest Service Pack

Install Standard Database (SDB)

Install Oracle Application Express (APEX) on Application Server (if required)

Configure and setup SPMat Catalog, Roles, Database Administrator (DBA) Settings, Project Defaults, and other elements required for use of the out-of-the-box (OOTB) functionality

Assumptions

Arendal will provide the Database Server, Web Fusion Server, and SPRD Plus Server hardware ready for installation of SPMat-related software

Arendal will provide Excel (2007/2010) on the selected Application Server

Arendal will provide all access rights for PP&M and comply with all requirements described in the installation checklist

Exclusions

Backup and restore processes are not part of the installation process

Duration

5 days

Project Dependencies

Standard product Installation Guides will be used for standard installation activities.

Client Dependencies

Installation of prerequisites will be completed by Arendal.

IIS, network, Oracle DBA, and Operating System support will be needed during Database and Application server installation

Page 17: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 17 of 30

Activity Type

ID Description Role Dependency

Document 1 Generate ‘System Configuration and Survey’ and ‘Installation Checklist’

Executive/Senior Consultant

Deliver 2 Deliver technical documentation to Arendal Project Manager

1

Deliver 3 Verify license files have been acquired and delivered to Arendal

Project Manager

Build 4 Install Development/Test SPMat Oracle Database environments at Arendal and trouble shoot any problems as needed

Senior Consultant

3

Build 5 Install Development/Test SPMat Oracle Web Fusion Application Server for SmartPlant Tools at Arendal offices and trouble shoot any problems as needed

Senior Consultant

3

Build 6 Install Development and Test SPRD Plus Server environments for SmartPlant Tools at Arendal offices and trouble shoot any problems as needed.

Senior Consultant

3

Document 7 Document As-built to describe infrastructure and topology Senior Consultant

4, 5, 6

Document 8 Obtain acceptance and signoff Project Manager

7

Resource Name/Role Role, Responsibilities, Remarks

Executive/Senior Consultant

Provides technical oversight, and reviews document design. Develops installation prerequisite check list.

Senior Consultant Installs SPMat database and provides feedback to Project Manager and Technical Lead of details not in design.

Senior Consultant Installs SPMat Application Server and SPRD Plus Server and provides feedback to Project Manager and Technical Lead of details not in design.

Project Manager Provides management oversight, approves documentation, and oversees overall progress of this Work Package.

Page 18: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 18 of 30

Phase I – 5.0, SmartPlant Reference Data

One (1) or more PP&M Executive/Senior Consultants will provide SPRD training for Arendal focused on the configuration of SPMat 7.0.6. The training sessions will be held in Monterrey, N.L..

Scope

PP&M will provide services as noted below:

Develop training agenda and associated documentation

Facilitate SPRD training session; which will cover the following topics:

Basic catalog training for all Disciplines (SPRD Classic Catalog)

Specification training for piping

Provide feedback on training meeting minutes

Assumptions

SDB will be used as reference data

Arendal will provide all training facilities

Arendal will provide resource to take all training meeting minutes

Exclusions

None

Duration

5 days

Project Dependencies

SPMat 7.0.6 has been installed within a single (one) Arendal test/training environment

Standard product documentation will be used for creating training material

Client Dependencies

Arendal will make available appropriate technical and non-technical resources for training

Page 19: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 19 of 30

Activity Type

ID Description Role Dependency

Document 1 Generate training agenda(s) and associated material Executive/Senior Consultant

Deliver 2 Deliver training documentation to Arendal Project Manager 1

Execute 3 Facilitate training sessions Executive/Senior Consultant

1, 2

Document 4 Review training meeting minutes Executive/Senior Consultant

3

Document 5 Obtain acceptance and signoff Project Manager 4

Resource Name/Role Roles, Responsibilities, Remarks

Executive/Senior Consultant

Develops configuration training agenda and associated documentation, facilitates configuration training workshops, and reviews meeting minutes.

Project Manager Provides management oversight, approves documentation, and oversees overall progress of this Work Package.

Page 20: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 20 of 30

Phase I – 8.0, Engineering & Procurement Integration

One (1) or more PP&M Executive/Senior Consultants will provide Engineering & Procurement Integration (E&PI) training to Arendal. The training sessions will be held in Monterrey, N.L.

Scope

PP&M will provide services as noted below:

Develop training agenda and associated documentation

Facilitate Engineering & Procurement Integration (E&PI) training session covering the following topics

Bill of Materials (BOM) Workshop (2 days)

Requisitions (2 days)

Support configuration (4 days)

Assumptions

Arendal will provide all training facilities

Arendal will provide resource to take all training meeting minutes

Training will cover only templates and processes defined in the Fast Track workflow

Exclusions

None

Duration

8 days

Project Dependencies

SPMat 7.0.6 has been installed within a single (one) Arendal test/training environment

Standard product documentation will be used for creating training material

Client Dependencies

Arendal will make available appropriate technical and non-technical resources for training

Page 21: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 21 of 30

Activity Type

ID Description Role Dependency

Document 1 Generate training agenda(s) and associated material Executive/Senior Consultant

Deliver 2 Deliver training documentation to Arendal Project Manager 1

Execute 3 Facilitate training sessions Executive/Senior Consultant

1, 2

Document 4 Review training meeting minutes Executive/Senior Consultant

3

Document 5 Obtain acceptance and signoff Project Manager 4

Resource Name/Role Roles, responsibilities, remarks

Executive/Senior Consultant

Develops configuration training agenda and associated documentation, facilitates configuration training workshops, and reviews meeting minutes.

Project Manager Provides management oversight, approves documentation, and oversees overall progress of this Work Package.

Page 22: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 22 of 30

Phase I – 10.0, Site Management

One (1) or more PP&M Executive/Senior Consultants will provide Site Management (SM) training to Arendal on the configuration of SPMat 7.0.6. The training sessions will be held in Monterrey, N.L.

Scope

PP&M will provide services as noted below:

Develop training agenda and associated documentation

Facilitate Site Management training session

Provide feedback on training meeting minutes

Support configuration

Assumptions

Arendal will provide all training facilities

Arendal will provide resource to take all training meeting minutes

Exclusions

None

Duration

5 days

Project Dependencies

SPMat 7.0.6 has been installed within a single (one) Arendal test/training environment

Standard product documentation will be used for creating training material

Client Dependencies

Arendal will make available appropriate technical and non-technical resources for training

Page 23: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 23 of 30

Activity Type

ID Description Role Dependency

Document 1 Generate training agenda(s) and associated material Executive/Senior Consultant

Deliver 2 Deliver training documentation to Arendal Project Manager 1

Execute 3 Facilitate training sessions Executive/Senior Consultant

1, 2

Document 4 Review training meeting minutes Executive/Senior Consultant

3

Document 5 Obtain acceptance and signoff Project Manager 4

Resource Name/Role Roles, Responsibilities, Remarks

Executive/Senior Consultant

Develops configuration training agenda and associated documentation, facilitates configuration training workshops, and reviews meeting minutes

Project Manager Provides management oversight, approves documentation, and oversees overall progress of this Work Package

Page 24: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 24 of 30

Phase I – 12.0, Reports Enhancement Training

One (1) or more PP&M Executive/Senior Consultants will provide Report Enhancement training to Arendal on the configuration of SPMat 7.0.6. The training sessions will be held in Monterrey, N.L.

Scope

PP&M will provide services as noted below:

Develop training agenda and associated documentation

Facilitate Report development training session

Provide feedback on training meeting minutes

Assumptions

Arendal will provide all training facilities

Arendal will provide resources with knowledge of Oracle SQL*Plus

Arendal will have Oracle Developer licenses required for training

Arendal will have required Developer Tools installed

Arendal will provide resource to take all training meeting minutes

Exclusions

Modifications to Fast Track reports, if required, will be considered as optional tasks and will be evaluated on a case-by-case basis by the Executive/Senior Consultant

Duration

5 days

Project Dependencies

SPMat 7.0.6 has been installed within a single (one) Arendal test/training environment

Standard product documentation will be used for creating training material

Client Dependencies

Arendal will make available appropriate technical and non-technical resources for training

Page 25: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 25 of 30

Activity Type

ID Description Role Dependency

Document 1 Generate training agenda(s) and associated material Executive/Senior Consultant

Deliver 2 Deliver training documentation to Arendal Project Manager 1

Execute 3 Facilitate training sessions Executive/Senior Consultant

1, 2

Document 4 Review training meeting minutes Executive/Senior Consultant

3

Document 5 Obtain acceptance and signoff Project Manager 4

Resource Name/Role Role, Responsibilities, Remarks

Executive/Senior Consultant

Develops configuration training agenda and associated documentation, facilitates configuration training workshops, and reviews meeting minutes.

Project Manager Provides management oversight, approves documentation, and oversees overall progress of this Work Package.

Page 26: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 26 of 30

Phase I – 13.0, Production Rollout

The Parties will provide resources to support the migration of SPMat and associated software/databases and interfaces for Production environments within Arendal network located in Monterrey, N.L.

Scope

PP&M will provide services as specified below to assist Arendal in the installation and configuration of the specified software:

Install and configure Oracle Database Server

Install and configure Windows Application Server

Install SPMat v7.0.6

Configure and setup SPMat catalog, roles, and other elements required for use OOTB functionality

Install Standard Database (SDB)

Load base data (based on the templates)

Configure DBA settings and project defaults

Load reports

Assumptions

Arendal will provide the Database and Application Server hardware ready for installation of SPMat-related software

Arendal will have signed off on all data loading Work Packages

Exclusions

Only signed off data (based on Fast Track templates) will be loaded to Production environment

Duration

5 days

Project Dependencies

Standard product Installation Guides will be used for standard installation activities.

Client Dependencies

Training and data templates with customer data loaded

Page 27: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 27 of 30

Activity Type

ID Description Role Dependency

Document 1 Generate ‘System Configuration and Survey’ and ‘Installation Checklist’

Executive/Senior Consultant

Deliver 2 Deliver technical documentation to Arendal Project Manager 1

Deliver 3 Verify license files have been acquired and delivered to Arendal

Project Manager

Build 4 Install production SPMat Oracle Database Server and Oracle Web Fusion Application Server environments at Arendal and trouble shoot any problems as needed. Install SPRD Plus server and environment.

Senior Consultant

3

Build 5 Verify and load Arendal data Senior Consultant

4

Document 6 Document As-built to describe infrastructure and topology Senior Consultant

5

Document 7 Obtain acceptance and signoff Project Manager 6

Resource Name/Role Roles, Responsibilities, Remarks

Executive/Senior Consultant Provides technical oversight, and reviews document design. Develops installation prerequisite check list.

Senior Consultant Installs SPMat database and provides feedback to Project Manager and Technical Lead of details not in design.

Senior Consultant Installs SPMat Application Server and SPRD Plus Server and provides feedback to Project Manager and Technical Lead of details not in design.

Project Manager Provides management oversight, approves documentation, and oversees overall progress of this Work Package.

Page 28: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 28 of 30

Phase 2 – S1 .0, Workshop to detail interfaces

PP&M and Arendal will discuss data flow requirements, define communication processes, and working processes.

Scope

PP&M will provide services as specified below:

Facilitates consulting to understand existing workflows, and determine data flows

Assumptions

Arendal will provide access to facilities, computers, databases, etc. for project members

Exclusions

None

Duration

5 days

Project Dependencies

SPMAT implementation

Client Dependencies

Project member access to required facilities/equipment/data/databases, etc.

Resource Name/Role Roles, Responsibilities, Remarks

Project Manager Provides management oversight, approves documentation, and oversees overall progress of this Work Package

Page 29: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 29 of 30

Phase 2 – S2 .0, Create Functional Design Specificaction (FDS)

PP&M will discuss SAP interface development, testing and deployment plan, define communication processes, and plan with Arendal.

Scope

PP&M will provide services as specified below:

Review SAP interface development

Review testing plan

Review deployment plan

Define communication paths

Make minor adjustments to Project Plan

Assumptions

Arendal will provide access to facilities, computers, databases, etc. for project members

Exclusions

None

Duration

5 days

Project Dependencies

Fast Track Methodology acceptance.

Client Dependencies

Workshop to detail SAP interfaces

Page 30: Scope of Work Template - arendal.com.mx SmartPlants/Contrato SMP...SPMat Fast Track Consulting Services Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 3 of 30 Table of Contents

SPMat Fast Track Consulting Services

Document No: PPM-14-MEX1, V1 INTERGRAPH CONFIDENTIAL Page 30 of 30

Activity Type

ID Description Role Dependency

Document 1 Develop interface plan Project Manager

Execute 2 Review deployment documentation Project Manager 1

Deliver 3 Make SAP interface deployment Plan adjustments Project Manager 1, 2

Document 4 Obtain SAP interface acceptance and signoff Project Manager 3

Resource Name/Role Roles, Responsibilities, Remarks

Executive/Senior Consultant

Develops deployment plan and associated documentation, facilitates testing and deployment, and reviews meeting minutes

Project Manager Provides management oversight, approves documentation, and oversees overall progress of this Work Package