scope of work (electrical)cidco.maharashtra.etenders.in/tnduploads/cidco/tndheader/tnd...scope of...

43
CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No. SCOPE OF WORK (ELECTRICAL) GENERAL The Scope of work consists of :- 1.0 Planning, designing & execution of HT/LT Cable network as per direction of Engineer-in-Charge and as per Schedule ‘A’. 2.0 The work includes :- a) Establishment of Distribution HT/LT network in various sectors. 3.0 Providing & commissioning of : a) 11KV XLPE cable. b) L.T. Distribution network consisting of feeder pillars/minipillars (outdoor type) complete with L.T. underground XLPE armoured cable network upto consumer’s Electric meter room. c) All related allied works like trenching, earthing, safety equipments & obtaining statutory approvals. NOTE :All the equipments used shall be compatible with SCADA & the agency has to submit protocol & mapping drawings of equipments wherever applicable. All protocol shall be as per IEC Standard (e.g. for relay IEC 870-5-103) 4.0 The entire electrical works should be carried out in accordance with the specifications without any extra cost. The work shall conform to latest edition of Indian Standard Specifications & Indian Electricity Rules. 5.0 The works shall be completed as per the requirement of ISO:9002 & all required documents for the same shall be made available.

Upload: lamcong

Post on 20-Mar-2018

221 views

Category:

Documents


4 download

TRANSCRIPT

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

SCOPE OF WORK (ELECTRICAL)

GENERAL

The Scope of work consists of :-

1.0 Planning, designing & execution of HT/LT Cable network as per direction

of Engineer-in-Charge and as per Schedule ‘A’.

2.0 The work includes:-

a) Establishment of Distribution HT/LT network in various sectors.

3.0 Providing & commissioning of :

a) 11KV XLPE cable.

b) L.T. Distribution network consisting of feeder pillars/minipillars

(outdoor type) complete with L.T. underground XLPE armoured

cable network upto consumer’s Electric meter room.

c) All related allied works like trenching, earthing, safety equipments

& obtaining statutory approvals.

NOTE:All the equipments used shall be compatible with SCADA & the

agency has to submit protocol & mapping drawings of equipments

wherever applicable. All protocol shall be as per IEC Standard (e.g.

for relay IEC 870-5-103)

4.0 The entire electrical works should be carried out in accordance with the

specifications without any extra cost. The work shall conform to latest

edition of Indian Standard Specifications & Indian Electricity Rules.

5.0 The works shall be completed as per the requirement of ISO:9002 & all

required documents for the same shall be made available.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

6.0 The Technical specification of all the equipment and the quantities

required of various accessories & auxiliaries. The contractor shall also

ascertain the quantities of items such as HT/LT cables, earthing material,

supporting steel pipes etc. and procure the material as per requirement.

Excess material brought to site & not installed shall not be accepted by

CIDCO nor it will be paid for.

7.0 Inspection:

7.1 All equipment shall be offered for inspection. 7.2 The inspection shall be carried out by CIDCO representative at any stage

of manufacturing. The contractor shall give free access to the inspector at

a reasonable notice.

7.3 The equipment shall be offered for final inspection at least fifteen days in

advance to enable CIDCO to witness the acceptance tests.

7.4 No equipment shall be dispatched to site from the manufacturers work

unless dispatch clearance certificate is issued by the inspecting authority

of CIDCO.

7.5 The contractor shall arrange for the inspection of the equipment by

CIDCO representative & co-ordinate with them for timely dispatches at no

extra cost to CIDCO, including traveling & boarding expenses.

8.0 Documentation : 8.1 The contractor on receipt of LOI shall submit five sets of relevant

descriptive & illustrative literature and general arrangement, schematic

drawings, foundation plans, and any other drawings and the general

technical particulars of all the equipment to be supplied.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

8.2 On completion of the above works, and commissioning, the contractor

shall prepare a set of “as built drawings”, compile all the vendor drawings,

shop test reports, inspection reports, site test reports, operation and

maintenance literature of major equipments for handing over to CIDCO.

This shall be compiled in four sets duly bound in a neat handy book.

Separate comprehensive operation & maintenance manual should also be

submitted in four sets.

9.0 Supervision of Erection :

The contractor shall arrange for a trained supervisor of respective

equipment manufacturer during installation, testing & commissioning who

will direct the sequence of erection, make necessary adjustments/

settings, make the equipment ready for testing, certify the pre-

commissioning checks and give permission for commissioning. This shall

be arranged by the contractor at no extra cost to CIDCO.

10.0 The drawings given in the tender are indicative. The successful agency

will have to make his own assessment before execution of work.

GENERAL TECHNICAL SPECIFICATIONS

1.0 INTRODUCTION :

CIDCO is planning to provide power supply distribution infrastructure in

Kharghar node with Hi-tech equipments for reliable power supply to the

inhabitants of Kharghar node in Sector-25 to 45.

2.0 This specifications given in brief the technical requirements for the

installation, testing & commissioning of power supply distribution

infrastructure at Kharghar node in Sector-25 to 45.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

3.0 It is not the intent to specify herein all the details of design and

construction of the equipment. However the equipment offered shall

confirm in all respects to high standard of engineering design and

workmanship. The installation of the infrastructure shall be executed in a

neat manner and as per good engineering practices. The shop tests as

well as pre-commissioning tests at site shall be conducted as per relevant

IS and as per requirements of individual equipment as well as the set

norms.

4.0 The ratings, performance, testing at works, installation, testing at site,

pre-commissioning checking and commissioning of all the equipment

required shall conform to the latest revisions of all the relevant IS

specifications.

5.0 Site Conditions:

All the equipments offered shall be suitable for following site conditions:-

a) Maximum Temperature : 45 Deg. C

b) Minimum Temperature : 6 Deg. C

c) Design Ambient Temperature : 40 Deg. C

d) Maximum Humidity : 96%

e) Seismic Condition : As per IS 1893

f) Atmosphere : Corrosive as found near as sea shore.

5.1 The equipment to be supplied by the contractor shall be designed/

suitable for following supply system.

5.1.1 Voltage stepped down to 11KV

Voltage : 11 KV

Frequency : 50 Hz

Fault level : 350 MVA

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

5.1.2 415V / 240V AC supply shall have following voltage & frequency variation Voltage : + 6%

Frequency : + 3%

Fault level : 16 KA

5.2 Construction power supply is not available at the site. The contractor

shall make his own arrangement of power supply during construction

works & for equipment testing, transformer filtration etc.

5.2 Water connection is not available. The contractor shall arrange for water

at his cost. _______________________ ______________________ Stamp and signature of Contractor

Addl. Chief Engineer (II)

Date :

Date :

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

I) TECHNICAL SPECIFICATIONS FOR 11KV XLPE CABLE

1.0 SCOPE 1.1 This technical specification covers design, manufacture, testing at

manufacturer’s works, packing & delivery of High Voltage Cross linked

polyethylene insulated PVC Sheathed cables suitable for 11 KV.

1.2 It is not the intent to specify completely herein all the details of design &

construction of the cables. However the cables shall conform to high

standards of engineering, design & workman ship. The equipment offered

shall be complete with all components necessary for its effective and

trouble free operation.

2.0 STANDARDS

2.1 unless otherwise specified elsewhere in its specification, the rating,

performance and testing of cables & accessories shall conform to the

latest revision of all relevant standards.

2.2 A list of such standards is enclosed at ANNEXURE – I.

3.0 PRINCIPAL PARAMETERS

The high Voltage Cables and accessories covered in this specification shall

meet the technical requirements listed at ANNEXURE – II and the

following general technical requirement.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

4.0 GENERAL TECHNICAL REQUIREMENT

4.1 Conductor

4.1.1 The conductor shall be made from electrically pure Aluminium wires. The

wires shall be stranded together and compacted.

4.1.2 The conductor shall be circular in shape.

4.2 Conductor Shielding

An extruded semi conducting compound shall be provided on the

conductor to provide a smooth surface & eliminate electrical stress

concentration.

4.3 Insulation

The core insulation shall be with Cross linked polyethylene unfilled

insulation compound. It shall be free from voids and shall withstand all

mechanical and thermal stresses under steady state & transient operating

conditions. The insulation shall be applied by triple extrusion process.

4.4 Insulation Shielding

The insulation shielding shall consist of non-metallic semi-conducting

compound in combination with non-metallic screening of copper. It shall

be possible to strip the insulation screening without applying heat. The

screen shall be capable to carry single line to ground fault current for a

duration of one second.

4.5 The conductor screen and XLPE insulation screen shall all be extruded in

one operation by extrusion to ensure perfect bonding.

4.6 Armouring

G.I. Flat street wire armouring shall be provided over the inner sheath.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

4.7 Outer Sheath

An outer sheath shall be applied on the cable by extrusion over

armouring. The outer sheath shall be of PVC compound confirming to

Type ST2. The PVC compound shall be suitable for protection against

rodent and termite attack.

4.8 In addition to the above, binder tape, filler, core identification tape shall

be provided.

ANNEXURE-I

11KV XLPE CABLE

APPLICABLE STANDARDS

The cables shall comply with the latest edition of the following standards:

Sr. No.

Indian Standard Spec. No.

Title

1. IS 7098 (Part-II) Cross-linked Polyethylene insulated PVC sheathed cables : Part II for working voltages form 3.3KV upto and including 33KV.

2. IS:8130 Conductors for insulated electric cables and flexible cords.

3. IS:5831 PVC insulation and sheath of electrical cables.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

Sr. No.

Indian Standard Spec. No.

Title

4. IS:3975 Mild steel wires, strips and tapes for armouring of cables.

5. IS:2633 Methods of testing weight, thickness and uniformity of coating on hot dipped galvanized articles.

6. IS:209 Specification for Zinc

7. IS:1753 Aluminium conductors for insulated cables.

8. IEC:502 Extruded solid dielectric insulated power cables for rated voltages form 1KV upto 30 KV.

9. IEC:540 & 540A Test methods for insulation and sheaths of electric cables and cords.

ANNEXURE-II

11KV XLPE CABLES

DESIRED TECHNICAL PARTICULARS

Sr. No.

Description Unit 11kV Particulars

1. Cable Size Core x Sq.mm. 3C x 300 sq.mm. 2. System Voltage kV 11 KV

3. Type of cable XLPE Insulated

4. Conductor material Aluminium

5. Minimum No. of strands

No. 30

6. Nominal thickness of XLPE insulation

mm 3.6

7. Minimum thickness of common covering

mm 0.7

8. Armouring 4mm x 8 mm

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

Sr. No.

Description Unit 11kV Particulars

9. Minimum thickness of outer sheath

mm 2.68

10. Approximate overall diameter

mm 81

11. Approximate net weight

kg/km 7260

12. Normal Delivery Length m 250

13. Max. DC Resistance at 20 deg C

Ohms/km 0.1

14. Approximate AC Resistance

Ohms/km 0.13

15. Approximate reactance at 50 Hz.

Ohms/km 0.095

16. Approximate Capacitance per phase

Mfd/km 0.475

17. Current rating Amps 355 (in ground) 440 (in air

18. Short time current rating

kA 28.2

19. Permissible short circuit temperature

Deg.C 250

1.1 Earthing :

1.1.1 Each Board, shall be provided with an earth busbar running along the

entire length of the board. Material and size of the earth busbar shall be

as specified. At either end of the earth bus, one (1) clamp type terminal

with nuts, bolts and earthing conductor shall be provided for bolting

Purchaser’s earthing conductor. In case the earth bus is provided near

top of the Board, one down comer at either end shall be provided for

connection to the Owner’s earthing conductor.

1.1.2 Earth busbars shall be supported at suitable intervals.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

1.1.3 Positive connection between all the frames of equipment mounted in the

switchboard and earth busbar shall be provided by using insulated

copper wires/bare busbars of cross section equal to that of the busbar.

1.1.4 All instrument and relay cases shall be connected to the earth busbar

using 1100/650V grade, 2.5 sq.mm. stranded copper earthing

conductor.

II) SPECIFICATIONS FOR EARTHING INSTALLATION

1.0 SCOPE

The intent of this specification is to define the requirements for the

supply, installation, testing and commissioning of the Earthing System.

Note : The bidder shall have to design the earthing system required for

the installation after measuring the soil resistivity & approvals.

2.0 EARTHING CONDUCTOR/ELECTRODE :

The main grid conductor shall be hot dip galvanized G.I. flat or PVC

insulated aluminium conductor/copper conductor. Sizes for main

conductors shall be marked on the drawings. Earth electrodes shall be as

per IS standard. Thickness of hot dip galvanizing shall not be less than 75

microns.

3.0 EARTHING NETWORK:

3.1 The entire earthing installation shall be done in accordance with the

earthing drawings, specifications and the standard drawings of reference

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

attached with this document. The entire earthing system shall fully

comply with the Indian Electricity Act and rules framed thereunder. The

contractor shall carry out any changes desired by the Electrical Inspector

or the owner, in order to make the installation confirm to the Indian

Electricity Rules at no extra cost. The exact location of earth conductors,

earth electrodes and earthing points on the equipment shall be

determined in field, in consultation with the Engineer-in-charge or his

authorized representative. Any changes in the methods, routing, size of

conductors etc. shall be subject to approval of the Owner/ Engineer-in-

charge before execution.

3.2 Excavation and refilling of earth, necessary for laying underground earth

bus loops shall be the responsibility of the contractor.

3.3 The resistance between the earthing system and the general mass of

earth shall be as per IS code of practice. The earth loop impendence to

any point in the electrical system shall not be in excess of 5.0 ohm, in

order to ensure satisfactory operation of protective devices.

3.4 The main earth loop shall be laid at a depth of 300 mm below grade level.

Wherever cable trenches are available, the earth lead shall be laid in the

trenches and shall be firmly cleated to the walls or run of trays when run

in concrete lines trenches. The earthing strip shall be protected against

mechanical damage.

3.5 In process unit areas, the earthing cable shall be run along cable trays

wherever specified in the layout drawings. The earthing cable shall be

suitably cleated and electrically bonded to the cable tray at regular

intervals.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

3.6 Joints and tappings in the main earth loop shall be made in such a way

that reliable and good electrical connections are permanently ensured. All

joints below grade shall be welded and suitably protected by giving two

coats of bitumen and covering with hessian tape. All joints above ground

shall be by means of connectors/lugs as far as practicable. Tee

connectors shall be used for tapping, earth leads from the main earth loop

wherever it is installed above ground. Where aluminium cable risers are

to be connected to the underground GI earth bus, the aluminium cable

riser shall be taken to the nearest earth pit and terminated through a

bolted joint. If this is not practicable then a G.I. risers shall be brought

above grade and a bolted joint shall be made between this GI riser shall

be protected applying two coats of bituminous paint/bitumen on the

exposed portion.

3.7 Conduits in which cables have been installed shall be effectively bonded

and earthed. Cable armoured shall be earthed at both ends.

4.0 EARTHING ELECTRODES:

4.1 Earth pipe electrodes shall be installed as shown in the earthing layout

drawings and in accordance with the standard drawings of reference and

IS:3043. Their location shall be marked to enable accurate location by

permanent markers.

4.2 All earth electrodes shall preferably be driven to a sufficient depth to

reach permanently moist soil. Electrodes shall preferably be situated in a

soil which has a fine texture and which is packed by watering and

ramming as lightly as possible. Wherever practicable, the soil shall be dug

up, all lumps broken and stones removed from the immediate vicinity of

the electrode.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

4.3 All earth electrodes shall be tested for earth resistance by means of

standard earth test meter. The tests shall take place in dry months,

preferably after a protracted dry spell. If necessary, a number of

electrodes shall be connected in parallel to reduce the earth resistance.

In such a case the distance between two electrodes shall not be less than

twice the length of electrode.

4.4 The electrodes shall have a clean surface, not covered by paint, enamel,

grease or other materials of poor conductivity.

4.5 The exact location and number of earth electrodes required at each

location shall be determined in the field in consultation with the

owner/Engineer-in-charge, depending on the soil strata and resistivity, to

meet the ohmic values prescribed in clause 4.3.

4.6 The disconnect facility shall be provided for the individual earth pits to

check their earth resistance periodically.

5.0 CONNECTION :

5.1 All electrical equipment is to be doubly earthed by connecting two points

on equipment to main earthing ring. The earthing ring will be connected

via links to several earth electrodes. The cable armour will be earthed

through the cable glands.

5.2 The following shall be earthed.

1. Transformer neutrals (Double Earthing).

2. Transformer Housing.

3. All switchgear and their earth buses.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

4. Motor Frames.

5. Non-current carrying metallic parts of electrical equipment such as

switchgear, switch rocks, panel boards, motor control centers,

lighting, power and instrument panels, push button stations, cable

trays, pipes conduits, terminal boxes etc.

6. All fences/enclosures housing electrical equipment.

7. All still structures, rails etc. including bonding between sections.

8. Shield Wire.

9. Structural steel Columns of building etc.

10. Loading racks.

5.3 System shall be earthed by two distint conductors directly connected to

independent earth electrodes which in turn, shall be connected to the

earth loop. The earth connection shall be properly made. A small flexible

aluminium cable loops to bridge the top cover of the transformer and the

tank shall be provided to avoid earth fault current passing through

fastening bolts when there is lightning surge, high voltage surge or failure

of the bushings.

5.4 Each Lightening Arrestor shall be connected to a separate electrode

located as close as possible to it and within he fenced area for each set of

arrestors shall be spaced such that they are all within the enclosing fence.

Each of these electrodes shall be connected to the main earth grid.

5.5 The shield wire shall be connected with the main grid solidly and net

through supporting steel structures.

5.6 All paint, scale and enamel shall be removed from the contact surface

before the earthing connections are made.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

5.7 All hardware used for earthing installation shall be hot dip galvanized for

zinc passivated. Spring washers shall be used for all earthing connections

of equipment having moving parts and for all the connections subject to

vibrations etc.

5.8 Lighting fixtures shall be earthes through the extra core provided in the

lighting cable this purpose.

6.0 TESTING

Earthing system/connections shall be tested as follows:

6.1 Resistance of individual electrodes shall be measured after disconnecting

it from the grid.

6.2 Earthing resistance of the grid shall be measured after connecting all the

electrodes to the grid and generally the test value shall conform to

IS:3043 code of practice unless otherwise specified.

6.3 The resistance to earth shall be measured at the following:

a) At each electrical system earth or system at the following.

b) At each earth provided for structure lightning protections.

c) At one point on each earthing system used to earth electrical

equipment enclosures.

d) At one point on each earthing system used to earth wiring system

enclosures such as metal conduits and cable sheaths or armour.

e) At one point on each fence enclosing electrical equipment.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

Measurement shall be made before connection is made between

the ground and the object to be grounded.

IV) TECHNICAL SPECIFICATIONS FOR L.T. XLPE POWER CABLE

1.0 GENERAL

The cables shall be suitable for laying in racks, ducts, trenched, conduits

and underground buried installation with uncontrolled back fill and

chances of flooding by water.

They shall be designed to withstand all mechanical electrical and thermal

stresses under steady state and transient operating conditions. The XLPE

cables shall withstand without damage a three-phase fault current of at

least 26.2 kA for at least 0.5 second. The armour for these power cables

shall be capable of carrying 26.2 kA for at least 0.5 second without

exceeding the maximum allowable temperature of outer sheath.

The XLPE insulated cables shall be capable of withstanding a conductor

temperature of 250 degree C during a short circuit without any damage.

The aluminium wires unsed for manufacturing the cables shall be true

circular in shape before stranding and shall be uniformly good quality, free

from defects. All aluminium used in the cables shall be of H2 grade.

The fillers and inner sheath shall be of non- hygroscopic, fire retardant

material, shall be softer then insulation and outer sheath shall be suitable

for the operating temperatures of the cable.

Progressive sequential marking of the length of cable in meters at every

one meter shall be provided on the outer sheath of all cables.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

The cable shall have outer sheath of a material with an oxygen index of

not less than 29 and a temperature index of not less than 250 degree C.

All the cables shall pass fire resistance test as per IS:1554 (part-1)

Repaired cables shall not be accepted.

Allowable tolerance on the overall diameter of the cables shall be plus or

minus 2 mm.

2.0 XLPE POWER CABLES

The XLPE insulated cables shall be of FR type, C1 category conforming to

IS:7098 (part-1) and its amendments read along with this specification.

The conductor shall be stranded aluminium circular/sector shaped and

compacted. In multicore cables, the core shall be identified by red,

yellow, blue and black coloured strips or colouring of insulation. A distinct

inner sheath shall be provided in all multicore cables. For XLPE cables,

the inner sheath shall be of extruded PVC to type ST-2 of IS:5831. When

armouring is specified for single core cables, the same shall consist of

aluminium wires/strips. The outer sheath shall be extruded PVC to Type

ST-2 of IS:5831 for all XLPE cables.

3.0 CABLE DRUMS :

Cable shall be supplied non-returnable wooden or steel drums of heavy

construction. Wooden drum shall be properly seasoned, sound and free

from defects. Wood preservative shall be applied to the entire drum.

Standard lengths for each size of power and control cables shall be

500/1000 metres (LT cables). The cable length per drum shall be subject

to a tolerance of plus or minus 5% of the standard drum length. The

owner shall have the option of rejecting cable drums with shorter lengths.

However, the total quantity of cables after taking into consideration of all

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

cable drums for each size shall be within the tolerance of plus or minus

2%.

A layer of water proof paper shall be applied to the surface of the drums

and over the outermost cable layer.

A clear space of at least 40 mm shall be left between the cables and the

lagging.

Each drum shall carry the manufacturer’s name, the purchaser’s name,

address and contact number and type, size and length of the cable, net

and gross weight stenciled on the both sides of drum. A tag containing

the same information shall be attached to the leading end of the cable.

An arrow and suitable accompanying wording shall be marked on one end

of the reel indicating the direction in which is should be rolled.

Packing shall be sturdy and adequate to protect the cables, from any

injury due to mishandling or other conditions encountered during

transportation, handling and storage. Both cable ends shall be sealed

with PVC/Rubber caps so as to eliminate ingress of water during

transportation and erection.

4.0 TESTS

All cables shall conform to all type, routine and acceptance tests listed in

the relevant IS.

All power cables shall meet the requirements of the following additional

test and type test may be conducted to prove their capabilities.

1. Short time current test of conductors.

2. Short time current test on armours.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

V SPECIFICATIONS FOR CABLE LAYING

1.0 SCOPE

This is to define the requirements for the installation, testing and

commissioning of the cabling system.

2.0 CABLE SPECIFICATIONS

2.1 Power Cables

Power cables for use on 415V system shall be of 1100 Volts grade,

aluminium conductor, XLPE insulated, PVC sheathed single wire armoured

and overall PVC sheathed. Power cables for HV system shall be

aluminium conductor, XLPE insulted screened, PVC bedded galvanized

steel flat armoured and PVC sheathed cable.

All L.T. cables conform to the relevant sections of IS:1554 Part-I and H.T.

cables shall conform to IS:7098 (Part-II).

Unarmoured cables will be used wherever specified on the cable schedule.

3.0 MISCELLANEOUS MATERIALS

3.1 Connectors

Cable terminations shall be made with aluminium crimped type solderless

lugs of M/s Dowells make or approved equivalent for all aluminium

conductors and stud type terminals.

3.2 Cable Identification

Cable tags shall be of 2 mm thick aluminium strap of suitable size to

contain cable number, equipment number etc.

3.3 Ferrules

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

Ferrules shall be of self sticking type and shall be employher to designate

the various cores of control cable by the terminal numbers to which the

cores are connected for ease in identification and maintenance.

3.4 Cable Glands

Cable glands to be supplied shall be brass single/double compression type

as per the directions of Engineer-in-charge. Generally single compression

type cable glands shall be used for indoor protected locations and double

compression type shall be used for outdoor locations.

3.5 Cable Trays

Prefabricated hot dip galvanized sheet steel cable trays shall be used for

maximum support span of 2000 mm unless design is approved for larger

span. For requirements of larger than 750 mm width two trays shall be

run side by side. Cable trays shall be suitable for a cable weight of 50

kg/m running length of tray. Minimum thickness of sheet steel/galvanized

shall be 3 mm/86 micorns. Cable trays fabricated from standard rolled

sections shall used 50 x 50 x 6 /ISMC 100 sections for runners for

supporting spans limited to 2000 mm/more than 2000 mm respectively.

Cross support shall be 32 x 6 mm flat 25 x 25 x 6 mm angle for widths

upt o500 mm/ more than 500 mm respectively. If unit rate not included

in schedule of rates then cable trays if required shall be

fabricated/installed at site as per the per tonne rate for electrical

structural supports etc.

4.0 CABLE LAYING

4.1 Cable network shall include power, control lighting cables, which shall be

laid in trenches, cable trays or conduits as detailed in the relevant

drawings and cable schedules. Erection of cable trays as required shall be

the responsibility of the contractor. Cable routing shall be checked in the

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

filed to avoid interference with structures, piping or air-conditioning duct

and minor adjustments shall be done to suit the filed conditions wherever

deemed necessary without any extra cost.

4.2 High voltage, medium voltage and other control and communication

cables shall be separated from each other by adequate spacing or running

through independent pipes, trenches or cable trays, as applicable.

4.3 All cable routes shall be carefully measured and cables cut to the required

lengths, leaving sufficient lengths for the final connection of the cable to

the terminal of the equipment. The various cable lengths cut form the

cable reels shall be carefully selected to prevent undue wastage of cables.

The quantity indicated in the cable schedule is only approximate. The

contractor shall ascertain the exact requirement of cable for a particular

feeder by measuring at site and avoiding interference with structure,

foundation, pipelines or any other works.

4.4 Cables as far as possible shall be laid in complete, uncut lengths from one

termination to the other.

4.5 Cables shall be neatly arranged in the trenches/trays in such manner so

that criss-crossing is avoided and final take off to the motor/switchgear is

facilitated. Arrangement of cables within the trench/trays shall be the

responsibility of the contractor.

4.6 All cables will be identified close to their termination point by cable

numbers as per cable schedule. Cable numbers will be punched on

aluminium straps (2 mm thick) securely fastened to the cable and srapped

around it. Alternatively cable tags shall be circular in construction to

which cable numbers can be conveniently punched. Each underground

cable shall be provided with identify tags of lead securely fastened every

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

30 m of its underground length with atleast one tag at each end before

the cable enters the ground. In unpaved areas, cable trenches shall be

identified by means of markers as per standard drawing. These posts

shall be placed at location of changers in the direction of cables and at

intervals of not more than 30 m and at cable joint locations.

4.7 All temporary ends of cables must be protected against dirt and moisture

to prevent damage to the insulation. For this purpose, ends of all PVC

insulated cables shall be taped with an approved PVC or rubber insulating

tape. Use of friction type or other fabric type tape is not permitted. Lead

sheathed cables shall be plumbed with lead olloy.

4.8 RCC cable trenches with insert plates shall be provided by the contractor.

Cable shall be laid in 3 to 4 tiers in these trenches.

4.9 Directly buried cables shall be laid underground in excavated cable

trenches where specified and layout drawings. Trenches shall be of

minimum 0.9 mtr. depth and suitable width for accommodation of all

cables correctly spaced and arranged with a view of heat dissipation and

economy of design. Depth of burying shall allow minimum 900 mm soil

cover for low voltage and 1000 mm for 11KV cables.

L.T. cables shall be laid in trenches as above stated depth. Before cables

are placed, the trenches bottom shall be filled with layer of sand. This

sand shall be leveled and the cables laid over it. The cables shall be

covered with 150 mm of sand on top of the largest diameter cable and

sand shall be lightly pressed. A protective covering of 75 mm thick

second class red bricks shall then be laid flat. The remainder of the

trench shall then be back-filled with soil, rammed and leveled.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

As each row of cables is laid in place and before covering with sand every

cables shall be given an insulation test in the presence of Engineer-in-

charge/Owner. Any cable which proves defective shall be replaced before

the next group of cables are laid.

All wall openings shall be effectively sealed after installation of cables to

avoid leakage of water.

4.10 Where cables rise from trenches to motor, control, station, lighting panels

etc., they shall be taken in G.I. pipes for mechanical protection upto a

minimum of 300 mm acboe grade or as shown in the standard drawings.

Cable ends shall be carefully pulled through the conduits to prevent

damge to the cable. Where required, approved cable lubricant shall be

used for this purpose. Where cable enters conduit the cable should be

bent in large radius. Radius shall not be less than the recommended

bending radius of the cables specified by the manufacturer.

Following guide of the pipe fill shall be used for sizing the pipe size:-

a) 1 Cable in pipe : 53% full

b) 2 Cables in pipe : 31% full

c) 3 or more cables : 43% full

d) Multiple cables : 40 % full.

After the cables are installed and all testing is complete, conduit ends

above grade shall be plugged with a suitable weatherproof plastic

compound/PUTTI for sealing purpose. Alternatively G.I. Lids or PVC

bushes shall be employed for sealing purposes. The cost for the same

shall be deemed to have been included in the installation of G.I. pipe and

no separate payment shall be done.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

4.11 Where cables pass through foundation wall or other underground

structures, the necessary ducts or openings will be provided in advance

for the same. However, should it become necessary to cut holes in

existing foundations or structures the electrical contractor shall etermine

their location and obtain approval of the Engineer-in-charge before cutting

is done.

4.12 At road crossing and other places where cable enter pipe sleeves

adequate bed of sand shall be given so that the cables do not slack and

get damaged by pipe ends after back filling.

4.13 Drum number of each cable from which it is taken shall be recorded

alongwith the cable number in the cable schedule.

4.14 Cables installed above grade shall be run in trays, exposed on walls,

ceilings or structures and shall be run parallel or at right angles to beams,

walls or columns.

Cables shall be so routed that they will not be subjected to heat from

adjacent hot piping or vessels.

4.15 Individual cables or small groups which run along structures/walls etc. will

be clamped by meas of 16 SWG GI saddles on 25 x 6 mm saddle bars.

The cost of saddle and saddle bars shall be deemed to have been included

in the installation of cables and no separate payment shall be made on

this account.

They shall be rightly supported on structural steel masonry, individual or

in groups as required, if drilling of steel must be resorted to, approval

must be secured and steel must be drilled where the minimum weakening

of the structure will result.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

Cables shall be supported so as to prevent unsightly sagging, in general

distance between supports shall be approximately 300 mm for cables upto

25 mm diameter and maximum 450 mm for cables larger than 25 mm dia.

4.16 All G.I. pipes shall be laid as per site requirements. Before fabrication of

various profiles of pipe by hydraulically operated, bending machine (which

is to be arranged by the contractor), all the bars from the pipes shall be

removed. G.I. pipes buries in soil, bitumen coating shall be applied on the

buried lengths. Installation of G.I. pipes shall be undertaken well before

paving is completed and necessary co-ordination will paving agency shall

be the responsibility of Electrical contractor. The open ends of pipes shall

be suitably plugged with G.I. plugs after they are laid in final position G.I.

plugs shall be supplied by the contractor at no extra cost.

4.17 Cable laid on supporting angle in cable trenches, structures, columns and

vertical run of cable trays shall be suitably clamped by means of G.I.

saddles/clamps, whereas cable in horizontal run of cable trays shall be

tied by means of nylon cords.

4.18 Supporting steel shall be painted before laying of cables. The painting

shall be done with one coat of red lead paint and two coats of approved

bituminous alluminium paint.

5.0 TERMINATION:

5.1 All PVC cables upto 1.1KV grade shall be terminated at the equipments by

means of compression type cable lugs of aluminium. They shall have a

gland of screwed nipple with conduit electrical threads and check nut.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

5.2 Power cables shall be identified with red, yellow and blus PVC tapes.

Where copper to aluminium connections are made, necessary bimetallic

washers shall be used. For trip circuit identification additional red ferrules

shall be used only in the particular cores of control cables at the

termination points in the switchgear/control panels and control switches.

5.3 In case of control cables all cores shall be identified at both ends by their

terminal numbers by means of PVC ferrules, or self sticking cable

markers. Wire numbers shall be as per schematic/wiring/inter-connection

diagram. Bidders shall have the samples of PVC ferrules/cable markers

approved before starting the work.

5.4 Where threaded cable gland is screwed into threaded opening of different

size, suitable galvanized threaded reducing bushing shall be used of

approved type, at no extra cost.

5.5 The cable shall be through glands inside the panels or any other electrical

equipment such as motors. The individual cores shall then be dressed

and taken along the cable ways (if provided) or shall be fixed to the

panels with polyethylene straps. Only control cables of single strand and

lighting cables may be directly terminated on the terminals.

In case of termination of cables at the bottom of a panel over a cable

trench having no access from the bottom close fit hole should be drilled in

the bottom plate for all the cables in one line, then bottom plate should

be split in two parts along the center line of holes. After installation of

bottom plate and cables it should be sealed with cold setting compound.

Cables shall be clamped over the open armouring to connect it to earth

bus.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

5.6 Cable leads shall be terminated at the equipment terminals, by means of

crimped type solderless connectors as manufactured by M/s. Dowell

Electro Works or approved equivalent.

Crimping shall be done by hand crimping/hydraulically operated tool and

conducting jelly shall be applied on the conductor. Insulation of the leads

should be removed immediately before the crimping. Conductor surface

shall be cleaned and shall not be left open.

5.7 11, 6.6 and 3.3 KV cables terminations/joints shall be done byu skilled and

experienced jointers duly approved by the owner, if included in the

contract.

6.0 TESTING

6.1 Before energizing, the insulation resistance of every circuit shall be

measured from phase to phase and from phase to ground, This requires

3 measurements if one side is grounded and 6 measurements for 3 phase

circuits.

Where splices or terminations are required in circuits rated above 600

Volts, measure insulation resistance of each length of cable before splicing

and or/terminating. Repeat measurement after splices and/ or

terminations are completed.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

6.2 Measure the insulation resistance of directly buried cable circuits before

cable trenches are back-filled. Repeat measurement after back filling.

6.3 D.C. High voltage test shall be made after installation on the following:-

1) All 1000 Volts grade cables in which straight through joints have

been made.

2) All cables above 1100 V grade. For record purposes test data shall

include the measure values of leakage current verses time.

The D.C. High voltage test shall be performed as detailed below in

the presence of the Engineer-in-charge or his authorized

representative only.

Cables shall be installed in final position with all the straight

through joints complete. Terminations shall be kept unfinished so

that motors, switchgears, transformers etc. are not subjected to

test voltage.

The test voltage and duration shall be as per relevant codes and

practices of Indian Standard Institution.

7.0 H.T. CABLE LAYING 7.1 CABLES LAID IN BUILT UP TRENCHES : 7.1.1 Cables laid in the built-up trenches within the building shall be raised so

as not to lay at the trench bottom. Cables shall be either secured to the

wall by saddles or laid on angle iron brackets or cable trays, ladders,

rack, trough etc. as approved by CIDCO. Where cables are laid on cable

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

brackets, the brackets shall not be fixed more than 500 mm. apart to

avoid sag in the cables. Where cables shall be fixed with cable tie or

saddles and shall be at minimum 25 mm. away from side walls and

minimum 150 mm distance shall be observed between two adjacent

cables.

7.1.2 The dimensions of the trenches shall be determined depending upon the

maximum number of cables that is expected to be accommodated.

Wherever specified, trenches shall be filled with fine sand and covered

with RCC or steel chequered trench covers.

7.2 DUCT SYSTEM :

Wherever specified cables shall be laid in underground ducts. The duct

system shall consist of required number of reinforced hume pipes with

simplex joints. The ducts shall be properly anchored to prevent any

movement. The top surface of the cable ducts shall not be less than

100 mm below the ground level. The ducts shall be provided with

inspection manholes at all direction changes and at required regular

intervals of 50 mtr. for drawing the cables. The manholes shall be at

reinforced concrete either cast-in-situ or precast. The manhole covers

shall be RCC cover of suitable weight to withstand the load of the road

vehicle. The ducts shall be properly plugged at the ends to prevent

entry of water, rodents etc. Suitable duct markers shall be placed along

the run of the cable ducts. The duct markers shall be at least be 15

cms. square embedded in concrete, indicating the voltage, number of

ducts and direction of run of the cable be provided in the manholes for

supporting the cables. Proper identification tags shall be provided for

each cable in the manholes.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

7.3 CABLE TRENCHES (EXCAVATED):

7.3.1 The cable trenches shall be excavated 1000 mm below the finished

ground level and shall have a minimum width of 300 mm. for laying of

single cable. When more than one cables are laid in the same trench,

the width of the trench shall be increased such that the spacing

between the cables is 25 cms. and the end cables are at minimum 15

cms. from the side of the trenches. At the turning of the cable route

the trench shall be dug with radius equal to 15 times the cable

diameter.

7.3.2 The trenches shall be cut square with vertical side walls and with

uniform depth. Suitable shoring and propping may be done to avoid

caving in of trench walls. The floor of the trench shall be rammed and

leveled. The bottom of the cable trench shall be prepared with 100mm.

sand bed for laying the cables.

7.3.3 The cables shall be laid in trenches over the rollers. After the cable is

laid and straightened it shall be covered with sand, and RCC half

round/semi circular pipe of appropriate strength & size.

7.3.4 The cable trench then shall be refilled with excavated materials after

removing the stones and other sharp materials and the refilled materials

shall be compacted with light ramming.

7.3.5 Approved cable markers made of G.I. with 15 cms crown shall be

provided along the route of cables at a spacing of 40 – 50 meters and

also at both ends of road crossings or at the cable turning points. The

class, type and No. of cables shall be indicated on the markers.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

7.3.6 Cable shall be laid in hume pipes at all road crossings and in GI pipes at

the wall entries.

7.4 CABLE JOINTING :

7.4.1 Cable jointing shall be done as per the recommendations of the cable

manufacturer. Jointing shall be done by qualified cable jointer. The

location of the cable joint shall not be where the cable takes a bend also

where the soil is loose and shows signs of subsidence.

7.5 CABLE TERMINATION :

7.5.1 All cable termination shall be done in cable end box provided in RMU,

Transformer or any other H.T. equipment.

7.5.2 Cable terminations are to be made with cable heat shrinkable

termination kits of specified approved make only.

7.5.3 Every connection at a cable termination shall be mechanically and

electrically sound and protected against mechanical damage and any

vibration liable to occur shall not impose any harmful mechanical

damage to the cable conductor.

7.6 TESTING OF CABLE BEFORE LAYING AND COMMISSIONING :

7.6.1 All tests shall be carried out in accordance with relevant IS codes of

practice, IE rules.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

7.6.2 100% cable drums shall be checked for continuity and cross continuity

tests to ensure that there is no internal damage to the cable during

transportation.

7.6.3 Installation resistance shall be measured with 1000 V megger between

the cores and all the cores to earth (armour) and results shall be

recorded.

7.6.4 Before cable jointing is done, cable shall be tested for presence of

moisture by dipping a piece of insulation of cable in hot compound of

paraffin was at temperature between 120 –140 degree centigrade. The

presence of moisture is indicated by the formation of bubbles. Only a

single strip of insulation gripped by a pair of tweezers should be used.

7.6.5 After the cables are installed before commissioning it shall be tested for

high DC voltage test. The recommended volts and duration of the test

shall be as per I.E. rules & regulations. However the test voltage and

duration shall be in conformity with standards of local supply

authorities. During high voltage tests all electrical equipments related

to the cable installation must be earthed and adequate clearance shall

be maintained from the other equipments and from work to prevent

flash over.

_______________________ _______________________ Stamp and signature of Contractor

Addl. Chief Engineer (II)

Date :

Date :

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

CODES AND STANDARDS

The following codes and standards shall be applicable for continuous

performance of all electrical equipments to be supplied, delivered at site,

erected, tested and commissioning. The electrical equipments offered

shall comply to the relevant Indian Standards Specifications. Fire

Insurance Regulations, Tariff Advisory Committee Regulations, and

particular to Indian Electricity Rules in all respect with all its latest

amendments upto date.

For guidelines to the tenderers, few of the Indian Standards are indicated

below :-

1. IS:116 - Circuit breakers for AC System.

2. IS:159 - Bubars and Busbars connections.

3. IS:3043 - Code of practice of earthing.

4. IS:10116 - Code of practice for installation of switchgear.

5. IS:10116 - Code of practice for selection, installation and maintenance of fuse (upto 650 Volts.)

6. IS:3165 - Potential Transformers.

7. IS:3203 - Climate proofing of electrical equipments.

8. IS:3427 - Metal enclosed switchgear and central gear.

9. IS:3419 - Specification for fittings for rigid PVC non-metallic conduit.

10. IS:3537 - Gas separated relays.

11. IS:3639 - Fittings and accessories for power Transformer.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

12. IS:3837 - Accessories for rigid steel conduits.

13. IS:4064 - Heavy duty Air Break switches and composite. Switch fuse units for voltage and exceeding 100V.

14. IS:4064 - Switch fuse units for Industries etc.

15. IS:4237 - General requirements for switchgears not exceeding 1000 Volts.

16. IS:4615 - Switch socket outlet.

17. IS:5133 (Part-I) - Sheet steel boxed.

18. IS:3070 (Part-I) - Lighting Are stores.

19. IS:2034 - L.T. capacitors.

20. IS:192 - Electric power switchgear for indoor and outdoor installation.

21. IS:PUB 26 - Circuit Breakers.

22. IS:9535 - Specification for conduits for electrical installation.

23. IS:240 (Part-I & II) - for H.T. insulator of 33KV grade and above.

24. IS:335 - Insulating Transformer Oil.

25. IS:374 - Ceiling fans.

26. IS:375 - Marking and arrangement for switchgear boards main connections auxiliary wiring

27. IS:415 - Tungsten filament lamps. 28. IS:692 - Paper insulated cables.

29. IS:694 - PVC insulated cables and cords for

power lighting.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

30. IS:722 - Three phase watt hour meters with MDI

31. IS:732 - Electrical wiring installation (upto 650V)

32. IS:1087 - Single pole tumbler switch 5 Amps.

33. IS:1248 - Direct reading electrical indicating

instruments.

34. IS:1255 - installation and maintenance of paper insulated power cables upto 33 KV)

35. IS:1293 - 3 Pin lugs and sockets outlets.

36. IS:1554 - PVC insulated cables – heavy duty.

37. IS:1567 - Metal clad switches upto 100 Amps.

38. IS:1651 - Lead acid cell batteries.

39. IS:1653 - Rigid steel conduits for electric wiring.

40. IS:1771 - Industrial light fittings with accessories.

41. IS:6600 - Loading of oil immersed transformer.

42. IS:6946 - Reliable (flexible) non-metallic conduits for electrical.

43. IS:7098 (Part-II) - For XLPE type cables.

44. IS:5216 - Guide for safely procedure and practices in electric work.

45. IS:5578 - Guide for marking of insulated conductors.

46. IS: 5792 - 11 kv drop out fuses.

47. IS:5820 - Pre-cast concrete cables covers.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

48. IS:5908 - Method of measurement of electrical

installation in building.

49. IS:6381 - Specifications for construction and testing of electrical apparatus.

50. IS:1818 - Isolation and earthing switches.

51. IS:1886 - Code practice for installation of transformers.

52. IS:1947 - Flood lights.

53. IS:2026 - Transformers. 54. IS:9242 - Degree of protection provided for

enclosure for switchgear.

55. IS:9242 - HRS cartridge fuse units upto 650 Volts.

56. IS:2251 - Code of practice for Danger Notice Plates.

57. IS:2268 - Code bell/buzzers. 58. IS:2274 - Code of practice for wiring installation

(exceeding 650 Volts)

59. IS:3854 - Switches for domestic and similar purpose.

60. IS:2312 - Exhaust fans.

61. IS:2309 - Code of practice for lighting protection. 62. IS:2418 - Tubular fluorescent lamps for general

lighting service.

63. IS:2544 - Porcelain post top insulators for BBW Class.

64. IS:2509 - PVC electrical conduits.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

65. IS:2516 - A.C. Circuit breakers.

66. IS:2667 - Fittings for rigid steel conduits for

electrical wiring.

67. IS:2692 - 11 KV drop out fuses.

68. IS:2575 - Enclosed distribution fuse boards and cutouts for voltage upto 1000 V.

69. IS:2705 - Current transformer. 70. IS 14930 II - Double Walled Corrugated pipes of High

Density Polyethylene (HDPE) with couplings, tees, sockets for cable protection.

The entire electrical installation work shall be strictly complied with the codes,

standards, rules and regulations framed under the Indian Electricity Act. Further

it shall be strictly carried out as per the regulations and rules set out by “Tariff

Advisory Committee and/or Fire Insurance Regulations”.

Some of the rules framed under the Indian Electricity Rules, 1956 and all

amendments thereof more particularly complied to :

35, 43, 44, 44-A, 45 (Part), 50, 51, 59, 61 (a), 61 (c), 62, 63 (2), 65, 66, 67, 68,

69 and 92(2).

_______________________ _______________________ Stamp and signature of Contractor

Addl. Chief Engineer (II)

Date :

Date :

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

LIST OF APPPROVED MAKES OF ACCESSORIES FOR ELECTRICAL WORKS

Sr. No.

Particulars Makes

1. Submersible Pump /Monoblock pumps

Crompton Greaves, Aqua, Kirloskar, Mather & Platt, Modi, KSB, Kishor, Flowmore, ABS, Grundfos, Flygt Universal Engineers.

2. Ring Main Unit/HT switches & Fuseunit

MEI, Southern, Andrew Yule.

3. C.T./P.T. MSEB approved/Hupken

4. Auto Transformer starter MEI, Kilburn, JMP, Siemens, Andrew Yule, GEC, KEC

5. Trivector Meter MSEB approved

6. Measuring Instruments IMP, AE, UE, MECO, FE, Rishline (L&T), Ashida

7. Current transformer AE, Gilbert & Maxwell, IMP, Siemens SEGC (C.S), Pragati

8. PVC Conduits, PVC Pipes, DWC DHPE pipes

Garware, Pricision, Circlearc, Popular, Prince, Shaktiman, REX Polyextrusion Ltd. Premium Pipes and fittings, Madhu Plast.

9. Ceiling/Table Fans/ Air Circulators

Usha, Crompton, Bajaj, Cinni, Rallies, Orient, Polar, Almonard, Alfa.

10. G.O.D. Switches & Dropout fuse Outfit

Kiran, Pactil, Atlas, Cona Industries, Leader Electricals, Elle Electricals

11. Chain Pulley Block Elephanta, Herculas, WMI

12. Sluice Valve Kirloskar, IVC

13. Butterfly Valve Forbes, IVC

14. Lugs Dowels, Lotus, A.G. Electricals

15. C.I. Pipes Tisco, Sail, Damodar, Shivdurg.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

Sr. No.

Particulars Makes

16. Chlorinator Penwalt, Shree Mitra Purification

17. Motor Protection Relays Universal, Thresold, E.E., Minilac, Siemens, C.S. Telemechanique, Indo- Asian, L&T, Ashidha Electronics Pvt. Ltd.

18. 11KV cable/ 22KV cable CCI, Tropodur, Asian, Nicco, ICL, Gloster, Torrent, Polycab, HVP, Plaza

19. Feeder Pillar/ Mini pillar Popular Brass Metal works, Anil Elect. Ind. Manish, Super or any other manufacturer approved by Dept.

20. Transformer Indo Tech Transformers, Kirloskar, Emco, Bharat Bijlee, Crompton, BSES, Andrew Yule, Pactil, NGEF Delta, KEL, Sharun, Tesla, Argus., Tesla

21. PVC Insulated 1.1kV cable Plaza Cables, Havells’ India Ltd., Vardhaman Cables (Bharat Cab), R.K. Kables Ltd., Revin cable Ltd., Fixolite Wires and Cables, Macro Cables Pvt. Ltd., Dasmesh Cables, Leader Electricals (Leader Leacab), Gemscab Industries Ltd., Polycab, RPG

22. XLPE – LT cables Plaza Cables, Vardhaman Cables (Bharat Cab), Ravin cable Ltd., Macro Cables, Fixolite Wires and Cables, Dasmesh Cables, Central cable Ltd., Gemscab Industries Ltd., Polycab, RPG

23. XLPE – HT Cables Torrent Cables, Plaza Cables, Revin cable Ltd., Central Cable Ltd., Polycab, RPG

24. PVC insulated 1.1kV (HD) cable. Plaza Caes, Vardhaman Cables (Bharat Cab), Havell’s India Ltd., R.K. Kables Ltd., Macro Cables, Dasmesh Cables, Central Cable Ltd., Gemscab Industries Ltd., Polycab

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

Sr. No.

Particulars Makes

25. PVC insulated 11kV (HD) cable. Havell’s India Ltd., Central Cable Ltd.,

26. MCB, ELCB, RCCB Indo Asian Fuse Gear,Standard Electrical, Leader Electricals (Leader Aplha Brand), Esprit Switchgear Ltd, Indiana Current Co troll (Versatrip brand), Datar, L&T

27. MCCB Standard Electrical, Spaceage Switchgears, Esprit Switchgear Ltd., Datar, L&T, Indo Asian

28. Isolators/ Disconn-ectors, LV Switch gear/ Switch fuses

Standard Electrical, Kilburn

29. Distribution Board Indo Asian Switchgear, Standard Electrical, Esprit Switchgear Ltd., Indiana Current Control (Versatrip), Super

30. HRC Fuses & bases Indo Asian Switchgear, Havell’s India Ltd., R.B. Commercial Corporation

31. Compact Floures- cent Lamps Indo Asian Fuse gear

32. Alternate Circuit Breaker (acb) Spaceage Switchgears.

33.

PVC Wires, Copper Aluminium Conductor, flexible cables

Philco, Plyroflux, Paragon, Phenolex, Delta., Polyplast, Sundeep, V-Plast, Apex, Silvex, Pagoda, Sapcecab, HMT, Ralicab, Finolex.

34. Fuse switches/ SW fuse L&T, Siemens, Crompton, Telemechanique. Indo-Asian, Havells, EE, HH-ELCON, Standard, KEW, Kalki, Sentinel, Stenly., Samrat

35. Switches/Sockets Kalki, CPL, Anchor, Precission, MK, HME, EEW.

36. Cable Glands HME, EEW,

37. HC Fuse Distribution Board CPL, EE, Stenly, KEW, Kalki, EE, Standard.

38. Air/Oil Circuit Breakers (HT/LT) Kilburn, Easun, MEI, Jyoti, Andrew Yule, Siemens, L&T, GEC, Southern, BHEL, Telemechanique, Crompton.

39. Energy Meters Jaipur.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

Sr. No.

Particulars Makes

40. Capacitor GEC, Khatau-Junkar, Crompton, L&T, Madhav, Atlanta, Prabhodhan, Maladay, Aison (S+M), Samrat.

41. Steel tubular Poles Indian Electric Poles, Bombay Tubes, Nityanand, Rajan Tubes.

42. GI Octagonal Poles Zenith, Tata, Bharat, Bajaj, Saino/ Senzo Engg. Pvt. Ltd., Jenco Industrial Corpn, Shah Pylon, Philips.

43. Terminal Box, Bracket, Junction Box, control pillar.

ELM, United, DVK, Locally fabricated as per CIDCO’s approved drawing/ specifications. Abak Electricals.

44. Street light Luminaries Bajaj, Crompton, Philips, Genlec, Keselec, ELM, Mysore, Wipro, GE-Apar, Canara, Glolite, ECE, Indo-Asian. Vallient Electricals Pvt. Ltd., Fixolite Industrires.

45. Chokes/Ignitors/ Electronic Ballast

Bajaj, Crompton, Philips, Genelec, Keselac, GE-Apar, Glolite, ECE, Indo-Asian. Fixolite Industries, Madhu Gupta & Associates Pvt. Ltd.

46. Power contactors L&T, Siemens, Bharticulter, Hammer, Telemechanique, HH-ELCON, Standard, Kirloskar, Crompton, CS.

47. Lamps Bajaj, Crompton, Philips, Cema, HMT, Electron, Surya, Mysore, Sylvania-Laxman, Solarson, ECE, Indo-Asian. Solarson, ECE, Indo-Asian

48. Rotary/Select or Switches L&T, Siemens, Kaycee, EE, Bisons (ELM)

49. Post top Lantern Philips, Crompton, Glolite, Bajaj, Parimal, Tulip, Kesselec, ECE, Genelec, ELM, Wipro, Indo-Asian.

50. Street Light controller/ Timer L&T (TSQ 100) 24 Hrs. Dial, ELM.

CIDCO OF MAHARASHTRA LTD C.A.No.03/CIDCO/EE(Elect)/2011-12 Sr. Page No.

Sr. No.

Particulars Makes

51. ACSR Conductors V.K. Industries, Smita Conductors, Bombay Conductors Straight, Galada, Sterlite.

52. Alternators Kirloskar, Jyoti, NGEF, AVK-SEGC, KEL, Cater Pillar, Stmford, C.G., Newage Elect. Ltd.

53. Diesel Engines Kirloskar, Greaves Cotton, Cummins, Ashok Leyland, Cater piller.

54. Flow meters Signet, Monetek, Voryex.

55. Cable Jointing kit UNCIL SYNCHEM, Raychem, Xicon, Benson, Mahindra (Push on) M-Seal.

56. Pole paint Jehnson & Nicholson, Asian (s+M), Nerolac.

57. Flourescent Fixtures Bajaj, Crompton, Philips, GEC, Genelec, Mysore, Wipro, Glolite, Litwell, ECE, Prestolite, Indo-Asian.

58. Elevators Shindler India Ltd, Escon Elevators Ltd.

59. Energy Saver Device Prithvi Technology Pvt. Ltd.

_______________________ ________________________ Stamp and signature of Contractor

Addl. Chief Engineer (II)

Date :

Date :