scope of work
DESCRIPTION
testTRANSCRIPT
item Main equipment QTY activity1- Transformers 11kv/0.4 kv
(1,2,2.5 &3.125)MVA 28 1-ratio test
2-winding resistance3-vector group4- phase difference5-excitation
2- Transformers 11kv/6.6kv7.5MVAx4+25MVAx2
6 1- oil BDV2- oil moisture content3-oil filtration and filling4- ratio5- winding resistance6- vector group7- phase shift8- oil tanδ9-winding insulation tanδ
3- 11kv switch gear/6.6kv switchgear each switch gear has approximately 13 C.B or contactors
6 1-AC with stand2-primary injection for protection relay stability (16 loop)
4- AC UPS commissioning (60kva-100kva)including NI-CD battery capacity test
3 commissioning
5- DC 125 V commissioning including NI-CD battery capacity test
6 commissioning
6- Primary injection over load testFor 400vac C.B
40 Primary injection