Science Education Center Outreach Program May 18-19, 2005 PAC Meeting 1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory) LIGO-G050257-00-G

Upload: lily-rich

Post on 17-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 1

LIGO

The LIGO Science Education Center

Michael E. Zucker

(LIGO Livingston Observatory)

LIGO-G050257-00-G

Page 2: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 2

LIGO

LIGO SEC Functions

To fulfill our vision, we need to provide dedicated physical space:

• Exhibit interaction & display• Teacher and student-teacher hands-on

training • School group interactive visits• General public & adult ed interactive visits• Operations base & meeting center for this

program and other community EPO activities• LIGO science-inspired art exhibit and display

Page 3: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 3

LIGO

Constraints

• Physical footprint on existing land• Cost: $1,481k total ($135k design)• Interface and access to existing

structure• Compatibility with science operations

– HEPI greatly improves immunity to vehicle traffic (e.g. large collaboration meeting was held at LLO during S4)

Page 4: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 4

LIGOSite Plan

OUTREACHCENTER

LVEA

OSB

Existing unpaved site adjacent to LLO conference facility

Erect new building with direct access to auditorium foyer

BUS & CAR PARKINGstaging lot

Page 5: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 5

LIGO

New spaces by function•Exhibit hall

– 3,050 ft2 (approx. 50 exhibits at capacity)–Flexible utilities for new exhibits & arrangements–High ceilings, rollup forklift access–Space for BIG (immersive) exhibits

•Multipurpose Classroom– 860 ft2 to seat 30+ in close workgroup configuration (4/table)– Higher capacity in “chalk & talk” setup (A/V provisions)– Provisions for hands-on demonstrations & activity development

•Reception lobby and information area–Bookshop

•Staff operations–Manager office–Staff/docent/trainee office

Page 6: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 6

LIGO

Education Center Floorplan

QuickTime™ and aTIFF (LZW) decompressor

are needed to see this picture.

Existing auditorium

Page 7: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 7

LIGO

Sound Control

Page 8: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 8

LIGO

Sound Control

Page 9: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 9

LIGO

Lighting Control

Page 10: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 10

LIGOExterior Exhibit Concept

Kinetic wind-driven pendulum-wave sculpture covering South façade

135 magnetically-coupled 28’ masts, pivoting near C.G.

Team design on a theme by explOratorium’s Peter Richards and Thomas Humphries, inspired by LIGO physics

Page 11: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 11

LIGO

Pendulum test 3/26

Page 12: Science Education Center Outreach Program May 18-19, 2005PAC Meeting1 LIGO The LIGO Science Education Center Michael E. Zucker (LIGO Livingston Observatory)

Science Education Center Outreach ProgramScience Education Center Outreach Program

May 18-19, 2005 PAC Meeting 12

LIGO

SEC Construction Timeline

• 11/03 - Proposal Panel Review at NSF • 4/04 - NSF approves funding • 9/04 - Architects selected through two-phase competition

– Eskew + Dumez + Ripple (New Orleans, LA)– National firm with museum, nature center, education credits

• 4/05 - 50% Design Review • 6/05 - Final Design Review• 8/05 - Construction Start• 7/06 - Substantial Completion• 8/06 - Exhibit Installation • 9/06 - Public Opening!