Scheduled Curtailments Cancellations. Should be received at least one business day prior to start date of curtailment Resource Availability should not reflect the curtailment Day Ahead offers can be entered. Scheduled Curtailments Modifications. Modification 1: - PowerPoint PPT PresentationTRANSCRIPT
Scheduled CurtailmentsCancellations
• Should be received at least one business day prior to start date of curtailment
• Resource Availability should not reflect the curtailment
• Day Ahead offers can be entered
1
2
Scheduled CurtailmentsModifications
• Modification 1:– Delayed start date, same end date – Notice must be received at least 7 calendar days prior to changed start
date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)
Original CurtailmentStart Date End Date
Modification 1: Later Start Date
Start Date
3
Scheduled CurtailmentsModifications
• Modification 2:– Same start date, earlier end date– Notice must be received at least 7 calendar days prior to changed end
date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)
– Same requirements if curtailment extended past original end date (notice 7 / 15 calendar days prior to original end date)
Original CurtailmentStart Date End Date
Modification 2: Earlier End Date
End Date
4
Scheduled CurtailmentsCurtailment Schedule Change
• Change in Schedule:– Change to both start and end dates– Original curtailment will be cancelled, new curtailment entered– Notice must be received at least 7 calendar days prior to curtailment
start date (15 calendar days for assets with MIC or Max Net Supply >= 5 MW)
Original CurtailmentStart Date End Date
Change: Different Start and End Dates
End DateStart Date