schedule gantry crane 50 ton 2
DESCRIPTION
schedule to finish gantry crane PIBTRANSCRIPT
ID Task Name Duration Start Finish
1 FABRIKASI GANTRY CRANE 50 TON 51 days Mon 06/10/14 Mon 15/12/142 CIVIL WORK 25 days Mon 06/10/14 Fri 07/11/143 PEMBUATAN PONDASI 25 days Mon 06/10/14 Fri 07/11/144 PENGGESERAN KANTIN 14 days Mon 13/10/14 Thu 30/10/145 MECHANICAL WORK 40 days Mon 06/10/14 Fri 28/11/146 PEMBUATAN STRUCTURE 36 days Mon 06/10/14 Mon 24/11/147 PEMASANGAN RAIL 15 days Mon 10/11/14 Fri 28/11/148 INSTALASI WORK 15 days Tue 18/11/14 Mon 08/12/149 SERTIFIKASI 5 days Tue 09/12/14 Mon 15/12/14
22 29 06 13 20 27 03 10 17 24 01 08 15 22Oct '14 Nov '14 Dec '14
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Progress
PT. BARATA INDONESIA
FABRIKASI GANTRY CRANE 50 TON
NOTE : DITARGETKAN SELESAI PADA DESEMBER 2014
Project: GANTRY CRANE 50 TONDate: Mon 13/10/14
22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 2Jan '15 Feb '15 Mar '15 Apr '15 May '15 Jun '15 Jul '15
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Progress
PT. BARATA INDONESIA
FABRIKASI GANTRY CRANE 50 TON
NOTE : DITARGETKAN SELESAI PADA DESEMBER 2014
Project: GANTRY CRANE 50 TONDate: Mon 13/10/14