schedule gantry crane 50 ton 2

2
ID Task Name Duration Start Finish 1 FABRIKASI GANTRY CRANE 50 TON 51 days Mon 06/10/14 Mon 15/12/14 2 CIVIL WORK 25 days Mon 06/10/14 Fri 07/11/14 3 PEMBUATAN PONDASI 25 days Mon 06/10/14 Fri 07/11/14 4 PENGGESERAN KANTIN 14 days Mon 13/10/14 Thu 30/10/14 5 MECHANICAL WORK 40 days Mon 06/10/14 Fri 28/11/14 6 PEMBUATAN STRUCTURE 36 days Mon 06/10/14 Mon 24/11/14 7 PEMASANGAN RAIL 15 days Mon 10/11/14 Fri 28/11/14 8 INSTALASI WORK 15 days Tue 18/11/14 Mon 08/12/14 9 SERTIFIKASI 5 days Tue 09/12/14 Mon 15/12/14 22 29 06 13 20 27 03 10 17 24 01 08 15 22 Oct '14 Nov '14 Dec '14 Task Split Milestone Summary Project Summary External Tasks External Milestone Deadline Progress PT. BARATA INDONESIA FABRIKASI GANTRY CRANE 50 TON NOTE : DITARGETKAN SELESAI PADA DESEMBER 2014 Project: GANTRY CRANE 50 TON Date: Mon 13/10/14

Upload: fauzan-benraxid

Post on 29-Jan-2016

12 views

Category:

Documents


0 download

DESCRIPTION

schedule to finish gantry crane PIB

TRANSCRIPT

Page 1: Schedule Gantry Crane 50 Ton 2

ID Task Name Duration Start Finish

1 FABRIKASI GANTRY CRANE 50 TON 51 days Mon 06/10/14 Mon 15/12/142 CIVIL WORK 25 days Mon 06/10/14 Fri 07/11/143 PEMBUATAN PONDASI 25 days Mon 06/10/14 Fri 07/11/144 PENGGESERAN KANTIN 14 days Mon 13/10/14 Thu 30/10/145 MECHANICAL WORK 40 days Mon 06/10/14 Fri 28/11/146 PEMBUATAN STRUCTURE 36 days Mon 06/10/14 Mon 24/11/147 PEMASANGAN RAIL 15 days Mon 10/11/14 Fri 28/11/148 INSTALASI WORK 15 days Tue 18/11/14 Mon 08/12/149 SERTIFIKASI 5 days Tue 09/12/14 Mon 15/12/14

22 29 06 13 20 27 03 10 17 24 01 08 15 22Oct '14 Nov '14 Dec '14

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Progress

PT. BARATA INDONESIA

FABRIKASI GANTRY CRANE 50 TON

NOTE : DITARGETKAN SELESAI PADA DESEMBER 2014

Project: GANTRY CRANE 50 TONDate: Mon 13/10/14

Page 2: Schedule Gantry Crane 50 Ton 2

22 29 05 12 19 26 02 09 16 23 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 2Jan '15 Feb '15 Mar '15 Apr '15 May '15 Jun '15 Jul '15

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Deadline

Progress

PT. BARATA INDONESIA

FABRIKASI GANTRY CRANE 50 TON

NOTE : DITARGETKAN SELESAI PADA DESEMBER 2014

Project: GANTRY CRANE 50 TONDate: Mon 13/10/14