Scanlon Creek Operations CentreRenovation Project Update
Brian Kemp – GM, Conservation Lands
LSRCA Board of Directors
June 26, 2020
2
OVERVIEW• Project Status
• The Plan
• What Things Are Looking Like
• Questions
CurrentNature Centre
Future Home of Nature Centre
Scanlon CreekOps Centre
3
Project Status• Project was tracking well at beginning of 2020
• Shut down site due to Covid-19 restrictions - April 6th
• Commenced construction again - May 19th
• Virtual Site Meetings - every two weeks
• Constant (almost daily) communication - in-person, telephone, email, RForm
• Project Completion - targeting July 6th, 2020
4
The Plan – Upper Level
5
The Plan – Lower Level
6
What Are Things Looking Like(as of June 23rd)
Front Entrance
Reception/Foyer
7
What Are Things Looking Like(as of June 23rd)
Waiting Area
Feature Wall
8
What Are Things Looking Like(as of June 23rd)
Staff Lunchroom
Running Water!!!
9
What Are Things Looking Like(as of June 23rd)
Inclined Platform Lift
Accessible Gender-Neutral Washroom
10
What Are Things Looking Like(as of June 23rd)
Boardroom
11
What Are Things Looking Like(as of June 23rd)
Open Office Concept
12
What Are Things Looking Like(as of June 23rd)
Watershed Science Workroom
13
What Are Things Looking Like(as of June 23rd)
Manager OfficeAdministration Office
14
What Are Things Looking Like(as of June 23rd)
Storage Space – Lower Level
15