Page 1: Scandinavian Rail Development 2013 - Martin Munk Hansen

Development plans for the National Danish Railways

16.04.2013 Scandinavian Rail Development Conference 2013

Page 2: Scandinavian Rail Development 2013 - Martin Munk Hansen

In progress

The Signalling Programme (2,5 bio. €)

Copenhagen – Ringsted new line (1,3 bio. €)

Page 3: Scandinavian Rail Development 2013 - Martin Munk Hansen

In focus for new investments

Landworks in relation to Fehmarn Belt fixed link

Freight corridor between Sweden and Germany

Electrification

”Rail fund Denmark”

Page 4: Scandinavian Rail Development 2013 - Martin Munk Hansen

Fehmarnbelt

Page 5: Scandinavian Rail Development 2013 - Martin Munk Hansen

Fehmarnbelt

Fixed link of decisive importance for railfreight

Cost: 5,4 bio. €

Expected opening year: 2021

Page 6: Scandinavian Rail Development 2013 - Martin Munk Hansen

Fehmarn landworks

- Description

- Electrification Ringsted – Rødby

- Construction of new double track Ringsted

- Rødby (except Storstrømsbridge)

- Opgrading of topspeed to 200 km/h

- Increased capacity and reduced travel

time

- Status:

- Technical design and preparatory work

- Expected opening year:

- 2021

- Cost:

- 1,2 bio. €

Page 7: Scandinavian Rail Development 2013 - Martin Munk Hansen

Storstrømsbridge

Page 8: Scandinavian Rail Development 2013 - Martin Munk Hansen

New Storstrømsbridge

Preliminary design

Cost: 0,5 bio. € Expected opening year: 2021

Page 9: Scandinavian Rail Development 2013 - Martin Munk Hansen

Øresund rail line

- Description

- Increase of capacity of Øresund rail line

by establishing a waiting track or

directional traffic near Kastrup.

- To benefit freight and passenger trains

- Status:

- Pending political decision

- Expected opening year:

- Not decided

- Cost:

- Max 70 mio €

Page 10: Scandinavian Rail Development 2013 - Martin Munk Hansen

Double track Vamdrup - Vojens

- Description

- Construction of an additional track between Vamdrup and Vojens

- Increased capacity to allow more freight trains before opening of Fehmarn link

- Reduced travel time

- Status:

- Construction works to start

- Expected opening year: - 2015

- Cost:

- 100 mio €

Page 11: Scandinavian Rail Development 2013 - Martin Munk Hansen

The Electrification Programme

There is a strong political commitment

to move forward with the

electrification

Km catenary already in commission:

– Fjernbane: 25 kV AC: 1 321 km

– S-bane: 1500 V DC: 435 km

Total: 1 756 km

Page 12: Scandinavian Rail Development 2013 - Martin Munk Hansen

Already decided projects for electrification

Km of catenary system:

– Copenhagen - Ringsted: 120 km

– Ringsted - Holeby: 258 km

– Lunderskov - Esbjerg: 114 km

– Køge Nord – Næstved: 45 km

Total volume: 537 km

Page 13: Scandinavian Rail Development 2013 - Martin Munk Hansen

Projects that still require political approval - but have a good business case

Km of catenary system:

– Roskilde – Holbæk – Kalundborg: 112 km

– Fredericia - Aarhus: 218 km

– Aarhus - Aalborg: 280 km

Total volume: 610 km

Page 14: Scandinavian Rail Development 2013 - Martin Munk Hansen

Rail fund Denmark

Project Cost

New line Funen 0,7 bio. €

Bridge Vejle fiord 0,5 bio. €

New line Eastern Jutland 0,5 bio. €

Other investments for speed upgrade Fredericia – Aarhus 0,2 bio. €

Electrification Roskilde – Kalundborg 0,2 bio. €

Electrification Fredericia – Aalborg 0,7 bio. €

Electrification Aalborg - Frederikshavn 0,1 bio. €

Electrification Vejle – Struer 0,2 bio. €

Other investments 0,7 bio. €

Total 3,7 bio. €

Page 15: Scandinavian Rail Development 2013 - Martin Munk Hansen

Electrification Projects included in the Rail fund

– Aalborg–Frederikshavn: 85 km

– Vejle-Struer: 130 km

Page 16: Scandinavian Rail Development 2013 - Martin Munk Hansen

Rail fund Denmark new lines

Page 17: Scandinavian Rail Development 2013 - Martin Munk Hansen

The 1-hour model