scaling up production - university of nottingham...–fermentation attemperation –fv crash cooling...

16
24/10/2017 1 Scaling Up Production Dick Murton www.murtonbrewing.com [email protected] Why upsize? Successful business Insufficient brewhouse capacity Mash tun too small Insufficient or no chilled liquor Insufficient HLT capacity Insufficient tank capacity FVs, CTs, BBTs Insufficient packaging capacity Paying for excessive hours for additional revenue No personal time outside work

Upload: others

Post on 04-Feb-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

  • 24/10/2017

    1

    Scaling Up Production

    Dick Murton

    www.murtonbrewing.com

    [email protected]

    Why upsize?

    • Successful business – Insufficient brewhouse capacity

    • Mash tun too small

    • Insufficient or no chilled liquor

    • Insufficient HLT capacity

    – Insufficient tank capacity • FVs, CTs, BBTs

    – Insufficient packaging capacity

    – Paying for excessive hours for additional revenue

    – No personal time outside work

    http://www.murtonbrewing.com/http://www.murtonbrewing.com/

  • 24/10/2017

    2

    Other example drivers • Need to replace equipment anyway

    – Unsafe – Poor quality or damaged equipment – Not suitable for beer / yeast types used – Cannot produce consistent quality beer

    • Lack of insulation • Cannot control liquor or beer temperatures accurately • Infection prone • Cannot pressurise tanks for carbonation

    • Poor extracts • Need to move anyway

    – lease expiring – limited space for existing capacity – limited access – permit problems

    Possible alternatives

    • Contract brew

    • Cuckoo brew

    • Double brew and rent larger FVs / CTs

    • e.g. ninkasi tank rentals

    • Use contract packager for bottles / cans

    – separate company

    – mobile packager

  • 24/10/2017

    3

    Deciding what you need

    For a given brewery size and style, the brewing recipes should be used to determine brewery design, e.g.

    • Turnaround time

    • Numbers and capacities of vessels

    • Vessel dimensions and design features

    • CIP facilities

    • Extract performance

    • Cask, keg, bottle, can storage

    – empties, secondary packaging materials

    – full packages

    Level of spec

    • Detail the required performance criteria • Will the kit you are considering achieve these? • Make sure you can safely and effectively clean &

    sanitise it

    • Automation, welded cladding will cost extra capital, but probably save revenue costs, physical effort, time

    • Will probably improve consistency & quality and possibly extract performance

  • 24/10/2017

    4

    Grist preparation

    Pre-ground malt • Convenient, but some consider it inconsistent

    Own mill • Optimised grist fractions can

    – Improve extract efficiency – reduced malt costs – Increase runoff rates / reduce set beds – Reduce debris in wort

    Grist case • Large enough for maximum grist weight • Pre-ground malt, or • Mill night before • Can also mash in directly from mill – no GC req’d

    – But max 20 minutes to mash in

  • 24/10/2017

    5

    Mash system

    • To cope with largest grist weight, e.g. – Maximum volume & normal gravity, e.g. 5% – Reduced volume at higher gravity, e.g. 10%

    • Mashing in – Manual mixing OK up to 10 brl / 400 kg – Mash mixer essential above this for most people – Mashing time – 20 mins max

    • Mashing profile – Isothermal with simple MT – Rising temperature infusion with MT – not controllable – Decoction & rising temp mashes – additional kit

    • How are you going to remove spent grains?

  • 24/10/2017

    6

  • 24/10/2017

    7

    Liquor tanks

    • Incoming water supply flow and quality

    • Break tank?

    • Chlorine removal

    • Acid treatment?

    • CLT working capacity = > 1.3 x maximum wort volume

    • HLT working capacity > 1.3 x maximum wort volume

    • Temperature and time control of HLT

    • Handling different mash and sparge temps

    Wort copper / kettle

    • Flexible heating to allow full / reduced volumes

    • Ability to vigorously boil entire contents

    • Ability to handle hop formats being used in copper – WP – pellets only

    – Hopback – whole hops only

    • Heating – Direct flame to bottom of kettle – rare

    – Electric heating elements

    – Direct gas fired – internal heating coil

    – Steam heated jackets / calandria

  • 24/10/2017

    8

  • 24/10/2017

    9

    FVs / CTs

    • Bottom / top cropping yeast ?

    • “Flat” bottom should still be sloped

    • CCVs - 60 deg internal angle

    – require extra vertical height for cone

    • Top access for top cropping

    • Lower side access for bottom cropping

    • Cooling / temperature probes for full and part brews

    • Temperature control system

  • 24/10/2017

    10

    Cooling

    • Common glycol cooling system better if =>10 brl

    • Sizing – supplier will need volumes, times, rates of

    – Fermentation attemperation

    – FV crash cooling

    – CLT cooling

    – CT / BBT cooling

    – Cold store conditions – size, temperature

    Pipework

    • Generally 10 brl (1635 litre) kit can / should use 25 mm pipe

    – Ideal flow = 2,900 –> 3,800 litres / hr

    – Mashing in 350 kg @ 3:1 = 3,150 l / hr (20 min mash)

    • Many suppliers use 1.5 inch (36 mm), but not cleanable with the pumps often supplied

  • 24/10/2017

    11

    Cleaning

    • Manual cleaning not practical for enclosed vessels – access, safety, confined working space

    • Simple CIP system particularly beneficial at 10 brl +

    • Typically single use

    • Vessels must not be continuously ponded

    • Pipe flows must be turbulent

    Packaging

    Cask / keg washing • For 10 brl kit, at least 2 head

    – More heads reduces attention required

    Bottling, canning, kegging ? • Filtered? Unfiltered? Package conditioned? • How much of each to determine size, and level of

    manual input

    Outsource • But need sensible minimum quantities - costs • Agree quality expectations

  • 24/10/2017

    12

    Other considerations

    • Filtration?

    – KG, sheet, lenticular?

    – How are you going to clean and sterilise?

    • Carbonation

    – “Natural” – krausening, primings – time required

    – “Forced” - in tank sinter

    – “Forced” - in-line

    Brewery space requirements

    • Individual pieces of kit

    • Working space for each item

    • Storage space for materials and packaged beer

    • Admin

    • Lab

    • Mess room & toilets

    • Bar / food ?

    • Off sales area

  • 24/10/2017

    13

  • 24/10/2017

    14

    The building

    • Do NOT compromise on structural safety

    – Floor and wall strengths / loadings

    • Access to get tanks in

    • Sufficient height for tank installation

    • Insulated

    • Outside space for access, parking waste storage

    10 brl FV – large brewery ratio

    3.65 metres 3.3 metres

    3.0 metres

    10 brl FV – smaller brewery ratio

    3.1 metres

  • 24/10/2017

    15

    Hygiene – non negotiable

    • You are producing food products

    • Non porous walls / ceilings – tiles / plastic / polypropylene boarding

    – impermeable paint

    • Non porous surfaces (floors and vessels) essential

    • Good falls / gullys not essential

    • Ventilation – for moisture & CO2

    • Pest control

    • Toilet / washing / personal kitchen facilities

  • 24/10/2017

    16