sap implementation in construction organization - the traps

57
SEMINAR-II SAP Implementation in Construction Organization - the Traps Submitted By: (Hemal S Shah, CP1908) Guided By: (Mrs. Jyoti Trivedi, Lecturer) 1 | Page M.Tech Programme in Construction & Project Management CEPT University Ahmedabad-380009

Upload: hemal

Post on 18-Nov-2014

1.771 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SAP Implementation in Construction Organization - the Traps

SEMINAR-II

SAP Implementation in Construction Organization - the Traps

Submitted By:

(Hemal S Shah, CP1908)

Guided By:

(Mrs. Jyoti Trivedi, Lecturer)

1 | P a g e

M.Tech Programme in Construction & Project Management

CEPT University

Ahmedabad-380009

Page 2: SAP Implementation in Construction Organization - the Traps

Table of Contents

ACKNOWLEDGEMENT ......................................................................................... 4

CERTIFICATE .......................................................................................................... 5

CHAPTER-1 INTRODUCTION ........................................................................... 6

1.1 NEED FOR STUDY......................................................................................................................6

1.2 OBJECTIVES..............................................................................................................................6

1.4 METHODOLOGY........................................................................................................................7

1.5 RESEARCH PLAN.......................................................................................................................7

CHAPTER-2 LITERATURE REVIEW ............................................................... 8

2.1 MOST COMMON PROBLEMS IN SAP IMPLEMENTATION, [1].................................................8

2.2 TOP TEN SAP PROBLEMS, [2]................................................................................................10

2.3 PROBLEMS FROM CASE STUDY BASED ON TECHNOLOGY & ORG. STAFF FACTOR, [3]......11

2.3.1 TECHNOLOGY FACTORS.......................................................................................................................................11

2.3.2 PEOPLE FACTORS.................................................................................................................................................12

2.4 KNOWLEDGE INTEGRATION AS A KEY PROBLEM IN SAP IMPLEMENTATION, [4].............13

2.5 RESEARCH GAP.......................................................................................................................13

CHAPTER-3 DATA COLLECTION .................................................................. 14

METHODOLOGY............................................................................................................................14

3.1 SAP INTEGRATION AT AEL (ADANI ENTERPRISE PVT. LTD. )...........................................15

3.2 SAP IMPLEMENTATION REQUIREMENT................................................................................17

3.3 PROBLEMS DURING SAP IMPLEMENTATION AT ADANI.......................................................18

3.4 SAP IMPLEMENTATION RISKS...............................................................................................28

3.4.1 OPERATIONAL RISK..............................................................................................................................................29

3.4.2 ANALYTICAL RISK...............................................................................................................................................30

3.4.3 ORGANIZATIONAL RISK.......................................................................................................................................31

3.4.4 TECHNICAL RISK..................................................................................................................................................32

2 | P a g e

Page 3: SAP Implementation in Construction Organization - the Traps

CHAPTER-4 DATA ANALYSIS ......................................................................... 33

CHAPTER 5 CONCLUSION .............................................................................. 38

5.1 RECOMMENDATION................................................................................................................38

5.2 CONCLUSIONS.........................................................................................................................38

APPENDIX- A.................................................................................................................................39

REFERENCES............................................................................................................................41

List of Figures

Figure 1 Employees Technical Expertise at Various Stages of SAP Implementation..................18

Figure 2 Firms Employees Status after SAP Implementation.......................................................20

Figure 3 Port Management Information System..........................................................................22

Figure 4 Terminal Operating System...........................................................................................24

Figure 5 Budgeted vs Actual Cumulative Cost of Implementation...............................................26

List of Tables

Table 1 Top Ten SAP risks ranked by mean of likelihood............................................................34

Table 2 Top ten SAP risks ranked by mean of Impact..................................................................34

Table 3 Top 16 SAP exploitation risks..........................................................................................36

Table 4 SAP Risk Mitigation Strategies.......................................................................................37

3 | P a g e

Page 4: SAP Implementation in Construction Organization - the Traps

ACKNOWLEDGEMENT

I would like to thank Mrs. Jyoti Trivedi, Faculty of Technology, CEPT University, Ahmedabad

for her valuable guidance and continual encouragement throughout the entire duration of seminar

preparation. I am heartily thankful to her for her timely suggestions and the transparency of the

concepts of the topic that helped me a lot in concluding this study.

I would also like to thank Mr. Ashwin Oza, SAP implementation consultant, Adani,

Mr. Tarang Bhargav, as well as Mr. Keyur Shah, SR Manager, Jai Hind Projects for spending

their precious time for guiding me during my whole seminar work and make me aware of

problems occurring during SAP implementation.

4 | P a g e

Page 5: SAP Implementation in Construction Organization - the Traps

CERTIFICATE

This is to certify that the Comprehensive Report on the “SAP implementation in construction

industry-The Traps”, carried out by Hemal Shah (CP1908), towards the partial fulfillment of the

requirements for the degree of M.Tech in Construction & Project Management of CEPT

University, Ahmedabad, is the record of work carried out by him under my supervision and

guidance during III-semester (Aug-Dec’09). In my opinion, the submitted work has reached a

level required for being accepted for Seminar-II Final Jury examination.

Mrs. Jyoti Trivedi

Lecturer,

CEPT University,

Ahmedabad.

Hemal S Shah

CP1908

5 | P a g e

Page 6: SAP Implementation in Construction Organization - the Traps

Chapter-1 Introduction

SAP Systems are one of the most widely used and misunderstood IT systems that are available

today. SAP is the concept of building applications which are fully integrated, that can be used to

automate many of the routine functions of running the company. Companies typically purchase

these systems in an effort to consolidate their data and information flow into one system or

database. In an environment that is currently not running SAP systems, the data is decentralized

into many smaller subsets of system, servers and/or databases. By having everything separate, it

limits the amount of integration and collaboration that can be done. IT functions such as disaster

recover, data warehousing, backups and data updates must be done on each individual system,

rather then on one SAP System. There are many examples of successful implementations of SAP

Systems, but unfortunately, almost as many examples of unsuccessful ones. A tremendous

amount of planning needs to be done prior to bringing this type of system in house, to ensure that

it will really meet the business objectives of the company, while not forcing unwanted processes

on departments that are not inclined to change the way they do business.

1.1 Need for Study

SAP implementations are full with tales of lost millions and withdrawals after implementation.

Many of the most experienced IT organizations have failed. So what are the secrets? What are

the traps? This question could produce at least a book, and probably a sequel. Here are a few

things the Vendor is not going to tell you about. They are by no means the most important, but

they are missed in many implementations.

1.2 Objectives

1. Find out problems generated during SAP implementation in construction organization.

2. To suggest probable solution to overcome the traps of SAP.

6 | P a g e

Page 7: SAP Implementation in Construction Organization - the Traps

1.4 Methodology

(a) Literature Review:

The literature is available for past few years by eminent researchers in the area of SAP will be

reviewed from published paper of journals, codes of practice and standard books.

(b) Data collection:

Data will be collected pertaining to Problems phased by organization during SAP

implementation. For this particular one construction organization will be selected who has

implemented SAP in their organization and based on questionnaire survey data will be collected

pertaining to SAP problems.

(c) Data analysis:

Based on the collected data from case study analysis will be made to identify the traps during

SAP implementation in any construction firm.

(d) Conclusion:

Based on the analysis relevant conclusions will be made and scope for the future work will be

suggested.

(e) Scope of work:

In this seminar scope of work will be limited up to identifying problems regarding SAP

implementation in any organization.

1.5 Research Plan:

Literature Review: 17 September

Data collection & Data Analysis: 10th October

Conclusion: 25th November

7 | P a g e

Page 8: SAP Implementation in Construction Organization - the Traps

Chapter-2 Literature Review

SAP packages touch many aspects of a company’s internal and external operations.

Consequently, successful deployment and use of SAP systems are critical to organizational

performance and survival. This study presents the problems and outcomes in SAP projects. Main

question addressed here is, what problems do SAP adopters encounter as they implement and

deploy SAP and how are these problems related to outcomes? Companies experience problems

at all phases of the SAP system life cycle and many of the problems experienced in later phases

originated earlier but remained unnoticed or uncorrected. These literatures suggest that

researchers and companies will do well to adopt broad definitions and multiple measures of

success and pay particular attention to the early identification and correction of problems.

2.1 Most Common Problems in SAP Implementation, [1]

Even the most experienced organizations in information technology domain have had futile

experiences in the implementation of the SAP systems. This article highlights some of the issues

which are presumed consequential to problems at later stage, they are by no means the most

important, but they are missed in many implementations.

Change Management and Training.

This was mentioned as the major problem with implementations. Changing work practices to fit

the system is a major difficulty. Also mentioned were training across modules and starting

training sooner.

To BPR or not to BPR

It is difficult to draw the line between changing Business Processes to suit the system or

retaining Business Processes and paying the cost, in dollars and time, to change the system. As

time and cost squeeze the implementation, the usual path is to not modify the system, but to

change the way people work. This feeds back into Change Management and Training.

8 | P a g e

Page 9: SAP Implementation in Construction Organization - the Traps

Poor Planning

Planning covers several areas such as having a strong Business Case, to the availability of Users

to make decisions on configuration, to the investing in a plan that captures all the issues

associated with implementing it.

Underestimating IT skills

As most people are upgrading from old technology, the skills of the staff need to be upgraded as

well. The upgrade is also going to place significant demands on a team who are geared to

maintain an old but stable environment. Usually this effort is underestimated.

Poor Project Management

Very few organizations have the experience in house to run such acomplex project as

implementing a large-scale integrated solution. It usually requires outside contractors to come in

and manage such a major exercise. It can be a fine line between abdicating responsibility and

Sharing responsibility.

Many consulting firms do a disservice to their clients by not sharing the responsibility.

Technology Trials

The effort to build interfaces, change reports, customize the software and convert the data is

normally underestimated. To collect new data, and clean the data being converted, will also

require an effort that i s beyond what is normally expected.

Low Executive Buy-in

Implementation projects need Senior Executive involvement to ensure the right participation

mix of Business and IT, and to resolve conflicts.

Underestimating Resources

9 | P a g e

Page 10: SAP Implementation in Construction Organization - the Traps

Most common budget blow outs are change management and user training, integration testing,

process rework, report customization and consulting fees.

Insufficient Software Evaluation

This involves the surprises that come out after the software is purchased. Organizations’ usually

do not do enough to understand what, and how the product works before they sign on the bottom

line. The Bleeding Edge SAP is so massive and integrated that reporting and linking to other

systems (either your own or your customers and suppliers) can be much more difficult than you

expect. Companies looking at SAP need to examine how they accept online feeds from a

customer and examine the technological enablers as well as the implications of these

technologies inside of the Business.

2.2 Top ten SAP problems, [2]

1. Cannot receive enough technical support from system vendors.

2. SAP system is not able to seamlessly integrate with other information system.

3. Outdated and duplicated data is not properly discarded.

4. Managers cannot retrieve needed information from the system.

5. Cannot receive proper consulting advice from system consultants.

6. Ill-defined or misfit with business strategy.

7. Fail to use SAP to predict actual demands of new products.

8. Fail to use the system to generate appropriate financial budgets.

9. SAP is not properly modified to meet new business requirements.

10. Seamless integration is not achieved between modules of SAP.

10 | P a g e

Page 11: SAP Implementation in Construction Organization - the Traps

2.3 Problems from case study based on technology & Org. staff factor, [3]

2.3.1 Technology Factors

Poor selection of the Software

SAP R/3 was originally designed for manufacturing companies and not for wholesalers,

especially those doing large number of transactions. R/3 has never been used by a distributor

until that time. It lacked many requirements needed for successful wholesale distribution. SAP

R/3 was inflexible software, and any modification required time and financial investment. R/3

was unable to handle the large number of orders. FoxMeyer filled orders from thousands of

pharmacies, each of which have had hundreds of items, totaling up to 500,000 orders per day.

The legacy system handled 420,000 orders per day, but SAP only processed 10,000 orders daily

(2.4% of that of the legacy system).

No restructuring of the business process was doneSAP was not fully integrated because FoxMeyer was incapable of reengineering their business

processes in order to make the software more efficient. FoxMeyer signed a 5-year, $5 billion

contract with a new customer, University Health System Consortium in July 1994, on the

assumption that a projected US$40m in benefits from the SAP implementation would be

materialized. They placed a higher priority on meeting that customers’ need than on making the

SAP implementation success. The delivery was scheduled to start in early 1995, but FoxMeyer

pushed the implementation deadline forward 90 days to meet their customers’ needs. Thus,

FoxMeyer sacrificed the needed business reengineering processes.

Insufficient testing Due to the rushed schedule, some modules testing were skipped. Besides, the system was not

properly tested to identify its shortcoming in handling large amounts of orders. There was

inadequate testing and insufficient time to debug the system to ensure its functionality.

11 | P a g e

Page 12: SAP Implementation in Construction Organization - the Traps

2.3.2 People Factors

No consideration of other consultants’ adviceFoxMeyer did not listen to other consultants’ advice in the early stage of the project, A Chicago-

based consultant firm warned FoxMeyer that SAP would not be able to deliver what FoxMeyer

needed. FoxMeyer selected SAP mainly because of its reputation.

Over-ambitious project scopeThe project team members and information system staff were unfamiliar with the R/3 hardware,

systems software and application software. The project scope was enlarged with simultaneous

implementation of a $18m computerized warehouse project. Some technical problems of great

complication and were not managed well by the IS people, so additional expenditures and time

were incurred.

Dominance of IT specialists’ personal interest

Since the project was new for the wholesaling industry, the IT specialists wanted to learn the

system and secure their employment in the SAP technology business. (The SAP experience made

them more employable). They placed their personal interest of getting experience in SAP

implementation over the company¡¯s interest in getting suitable software technology. So some

system problems were hidden and not reported to management until it was too late.

Poor Management supportInitially management was supportive and committed to the project. However, once the

implementation started, management was reluctant to acknowledge the system problems.

Management failed to understand the complexity and risks in the process and agreed to have 90

days early implementation although the system was not fully tested. Management failed to

recognize the timelines and resources required in the implementation process.

Lack of end-user cooperationThe user requirements were not fully addressed and there was no training for end users.

Employees had no chance to express their priorities and business needs. Workers especially at

12 | P a g e

Page 13: SAP Implementation in Construction Organization - the Traps

the warehouses were threatened by the implementation. The automated warehouse created many

problems. Employee morale was low because of the layoffs.

They knew their jobs were soon to be eliminated. As the end users were not fully involved, they

felt they didn’t have the ownership for the project and did not work closely with the IT

specialists to solve problems.

2.4 Knowledge Integration as a Key Problem in Sap Implementation, [4]

Knowledge integration is a key problem in a SAP implementation. The need for knowledge integration continues even after implementation, if the system is to be fully appropriated. Moreover, our study finds that knowledge integration does not happen automatically as the implementation of SAP is not merely a technological task influenced by users. Perceived usefulness, but a cross-functional knowledge integration process structurally enabled by the establishment and maintenance of knowledge-based social relationships intra- and inter-organizationally. For this study, an implementation process of six months. Duration was examined to explore the impediments encountered. While the inherent limitation of a single case is noted in the study, findings show that there are significant impediments in the implementation process and that the process is strongly influenced by, the socio-technical, structural, and relational constructs foundation the organization. Managerially, the findings provide managers with possible guidelines that suggest important barriers to overcome during enterprise system implementation in various project phases. Theoretically, this paper made two contributions by offering a knowledge integration perspective that sees enterprise system implementation as a process of collective social construction (Berger and Luckmann 1967) which can be influenced by internal participants such as the implementation team, IS staff, users, and top management, as well as external participants, such as suppliers and project consultants. Secondly, the findings provide insights into the nature and dynamics of various complex impediments that underlie many SAP implementations.

2.5 Research Gap

As per the literature survey done for past 10 years, very good research have been done by various researchers in field of SAP for various industries, but very few research have been carried out regarding SAP implementation problems & their solution particularly in field of construction industry.

13 | P a g e

Page 14: SAP Implementation in Construction Organization - the Traps

Chapter-3 Data Collection

Methodology

Data collection regarding problems & probable risk occurred during SAP implementation in

construction firm is collected through discussion with Mr. Ashwin Oza, SAP consultant at

ADANI SEZ & PORT. Further, In order to achieve the research aims, the study attempted to

seek generalized statements on risks that target construction firms may experience in SAP

exploitation. Therefore, a deductive research design based on a questionnaire survey was

selected. The questionnaire design was based on a risk ontology that was created though a

process of data collected from SAP consultants at ADANI as well as critical literature review.

From this ontology it became apparent that out of the 40 predefined risks, some were related

with business aspects, while the rest focused on technical issues.

In addition, the study attempted to identify which of the 40 predefined risk events would be

perceived by respondents as risks for SAP exploitation, as well as, to assess the importance of

each identified risk according to its likelihood, impact and frequency of occurrence. In order to

achieve these objectives, each of the 40 predefined risk events was examined in the questionnaire

through four questions:

1) Whether this event could be perceived as a risk to SAP exploitation.

(1 = yes, 2= no).

2) What the probability of occurrence of this risk event could be.

(measured on a 3-point Likert scale, ranging from high [3] to low [1]).

3) What level of impact this risk could result in.

(measured on a 3-point Likert scale, ranging from high [3] to low [1]).

4) What the frequency of occurrence of this risk event could be.

(measured on a 5-point Likert scale, ranging from very often [5] to very rarely [1]).

14 | P a g e

Page 15: SAP Implementation in Construction Organization - the Traps

3.1 SAP Integration at AEL (Adani Enterprise Pvt. Ltd. )

Adani Enterprise Pvt. Ltd. (AEL) is one of the leading trading houses in India. It has been

operating for over 20 years and has the coveted “five star export house” status, which has been

granted only to a few export houses by the government of India. AEL’s business space is

inbound/outbound trade as well as domestic trade in India and it presently accounts for >1 % of

India’s imports and exports. It currently serves ~200 major clients through 17 global offices and

trades in 35 commodities. On the volumes front, its imports are >10 mnmt and exports >2 mnmt.

In FY06, it chartered ~247 ships, underscoring its size & scale of operations. It is one of the

largest players in thermal coal, iron ore, ferrous scrap and edible oils trading. For ensuring high

reliability & short turnaround time, AEL has set up dedicated logistical and handling facilities

for certain commodities like iron ore, coal, grain, fruits and vegetables, etc.

Adani Group – The Diversified Conglomerate

15 | P a g e

Page 16: SAP Implementation in Construction Organization - the Traps

Adani – FactsOrganization Adani Enterprise Pvt. Ltd.

Industry Diversified Conglomerate

Business Challenge

1. Do this as a single implementation yet focus on

implementation of each company as in isolation

2. Multiple Decision centers & leadership styles

3. Different Organizational objectives

4. Aligning people to a common viewpoint, highest level of

alignment

5. Different Locations

6. Multiple and Disparate legacy systems

7. Tremendous resource crunch

8. Limited experience for such a mammoth

9. Large Team management

10. Massive logistics effort

11. Finding a suitable partner

User Environment

1. 275 Users

Application Environment

SAP EC&O 6.0

1. Accounts Receivable

2. Accounts Payable

3. General Ledger

4. Fixed Assets

5. Job Cost

6. Service and Contract Billing

7. Change Management

8. HR Benefits Administration

9. Payroll

Technical Environment

1. Enterprise / Database Server(s): IBM I Series 860 12 Way

2. Deployment Server: Compaq ProLiant DL380 Dual 730 Mhz

16 | P a g e

Page 17: SAP Implementation in Construction Organization - the Traps

Intel Pentium III

3. Terminal Servers (7): HP ProLiant BL20p G2 Quad 3065

Mhz

4. Windows Terminal Servers (8): IBM eServer Blade Center.

SAP Implementation Process AT ADANI

3.2 SAP Implementation Requirement

1. Use of best practices to achieve common processes & use of ASAP methodology

2. Single SAP instance for multiple companies

3. Establishment of Central Master Data Cell

4. Integration with back-end systems (i.e. Terminal Operating systems, Port Management

system, Navis…)

5. Mapping of complete range of assets of port & railway infrastructure

6. Single Window service orientation using SAP Portal for SEZ

7. Special Process development for SEZ

8. Central Authorization management service

9. Central Expert implementation and helpdesk team

10. Solution Manager as the focal Helpdesk management tool

17 | P a g e

Page 18: SAP Implementation in Construction Organization - the Traps

11. Funds Management, Investment Management & Profitability Analysis successfully

implemented

12. Highly scalable server and network architecture setup

3.3 Problems during SAP implementation at Adani

1. Failure to Re-Design Business Processes to Fit the Software.

Avoid customization. Many companies "go to war" with the package and try to make it meet

their business process requirements, only to lead the way to huge cost overruns and project

failure in some cases. Rather than attempting to modify the software, Adani re-engineered their

business processes to be consistent with the software, and this has proved to be critical to the

project's success. It is important to re-design business processes to be consistent with system

specifications. One of the most difficult and time-consuming aspects of the project was the

creation of a "bridge" between the SAP and legacy applications, and this resulted in extensive

time and cost delays. If modifications are necessary, establish an up-front agreement between IT

and user managers with respect to what is to be modified.

2. Insufficient Training and Re-Skilling

Due to the rushed schedule, some modules testing were skipped. Besides, the system was not

properly tested to identify its shortcoming in handling large amounts of orders. There was

inadequate testing and insufficient time to debug the system to ensure its functionality.

18 | P a g e

Page 19: SAP Implementation in Construction Organization - the Traps

Adani invested heavily in training and re-skilling their developers in SAP software design and

methodology. They gave training to their employee in three stages. Cost for training of each

employee was around 2 lacs but employee were unable to grasp at their pace. Most firms

emphasized the investment in the training, re-skilling, and professional development of the IT

workforce. In the experience of various companies, training costs were higher than expected.

Figure 1 Employees Technical Expertise at Various Stages of SAP Implementation

3. Lack of Senior Management Support

Top management is expected to provide support in the areas of committing to the SAP project,

sufficient financial and human resource, and the resolution of political problems if necessary.

Limited financial support contributed to a rushed SAP implementation process, project team

members were overloaded and thus high staff turnover rate, ineffective knowledge transfer, and

political problems occurred. Insufficient commitment could lead to political problems which

hindered the implementation process (causing poor BPR, widespread user resistance to change

and low user satisfaction). Without question, top management support is critical to the success of

a project. It is important to achieve the support of senior management for accomplishing project

goals and objectives and aligning these with strategic business goals. At the time of ”Go Live”

due to cost and time over run senior management was not supporting the new system.

4. Standardization

Another "risk factor" which is closely associated with the software itself is insufficient adherence

with the standardized specifications that the software supports. Use a common data model and

common data definitions to drive common business processes.

19 | P a g e

Page 20: SAP Implementation in Construction Organization - the Traps

At Adani they have their vendor names and communication address in different style and formats

so at the time of implementation it was one of the biggest challenges which they face during

system standardization phase.

5. Lack of "Business" Analysts and Retain Qualified SAP Systems Developers

One of the critical workforce requirements for the project was the ability to obtain analysts with

both "business" and technology knowledge. Instead of 200 "programmers" with average skills,

the SAP project demanded and could be accomplished with 20 of the "best and brightest"

analysts. However, retaining these professionals was a significant problem because of their

market value.

At Adani also they face same problem, they train their employee for six months and after

training many employee ran away due to their increased market value.

Strategic Level Management Level

Knowledge Level

Operational Level

0

50

100

150

200

250

825

40

202

818

35

186

0

2813 8

Before TrainingAfter TrainingPercentage Deduction

Figure 2 Firms Employees Status after SAP Implementation

Before Training After Training Percentage DeductionStrategic Level 8 8 0.00

Management Level 25 18 28.00Knowledge Level 40 35 12.50

20 | P a g e

Page 21: SAP Implementation in Construction Organization - the Traps

Operational Level 202 186 7.92

6. Lack of Integration

In terms of factors conducive to project failure, one of the main factors associated with failure is

lack of integration. The project needs to be based on an enterprise-wide design. You can't start

with "pieces," and then try to integrate the software components later on. It is important to use a

"federal" approach; define what is needed at the enterprise-level, and then apply it to the business

unit level. A phased-in approach is superior to the "big-bang" all-at-once approach.

At Adani Enterprise Port Management system (EPMS) was used for management information

purpose but at the time of implementation problem was that implementation team face problem

during customization, they took around 8 months of time to integrate to new SAP system.

About EPMS (Enterprise Port Management System)

Enterprise Port Management System (EPMS) is an Internet (web) based end-to-end integrated

Port solution from Navayuga Infotech that handles vessel and cargo movement activities in and

out of the port. For better decision making the system provides users with real time information

about vessel arrival / departure, port facilities management, cargo & logistics information, gate

operations, etc. The objective of the application is to get the highest competitiveness by

maximizing the work efficiency, enabling effective usage of port facilities and achieving

customer satisfaction by high quality service. It also provides you with various enterprise based

functional, operational & management modules with seamless integration & interoperability.

EPMS Modules & Features

Marine & Vessel Operations System (MVOS)

1. Berth Definition and monitoring2. Vessel Documentation3. Service Request / Recording4. Marine Closure5. Vessel Dashboard

Cargo & Logistics Management System (CLMS)

1. Import / Export Documentation2. Gate Operations

3. Warehouse Operations4. Control Centre Operations5. Shipping Operations6. Jetty Operations7. Storage Planning8. Weighbridge Integration

Rail Operations Management System1. Rail Documentation2. Exchange Yard Operations3. Placement / Release of Rake4. Indent for Wagons

21 | P a g e

Page 22: SAP Implementation in Construction Organization - the Traps

1. Wagon Allotment

Human Resource Management System1. Role / Designation Configuration2. Workflow Definition

Material Management System1. Vendor Management2. Procurement Process3. Quotation System4. Purchasing & Invoicing5. Inventory & Stores6. Goods Indent / Receipt / Issue

Customs & EDI1. CHA / Importer / Exporter2. Immigration3. Navy / Coast Guard4. Data Configuration5. Data Transfer6. PCS Messaging Hub

Finance management System1. Rate Card Automation2. Customer Service Agreements3. Automated Invoicing / Billing4. Bill Adjustments5. Cash / Bank Transactions

Administration & User Customization1. Complete port administration for

Port Authorities2. Easy to use web interface3. Easily adaptable to any specific port4. User based Application & Setup

Customizations

22 | P a g e

Page 23: SAP Implementation in Construction Organization - the Traps

Figure 3 Port Management Information System

23 | P a g e

Page 24: SAP Implementation in Construction Organization - the Traps

Terminal Operating System

24 | P a g e

Page 25: SAP Implementation in Construction Organization - the Traps

Figure 4 Terminal Operating System

25 | P a g e

Page 26: SAP Implementation in Construction Organization - the Traps

7. Lack Of An Integrated Technology Strategy To Support Client-Server Implementation

The different "technology" environments at Adani delays in establishing consistency and

coordination between various company sites. There was problem regarding selection database

management system and operating system environments for the SAP application. For example,

the choice of whether to implement SAP using Unix/Oracle, operating system/database

environment or MVS/DB2 became an issue.

8. Avoid Building Bridges to Legacy Applications

Due to conglomerate business there was requirement to merge various legacy system with new

system, resulting in extensive time and cost delays. It is important to implement a total integrated

package at one time, rather than in pieces. The building of a bridge between a SAP module and a

legacy application was problematic and illustrated the complexity of building a bridge to a

legacy system.

9. Failure to Integrate Add-On Modules with the SAP System

When software does not meet requirements, most firms used bolt on's, or add-on packages which

are offered by third-party vendors. Several project managers emphasized the need to limit the

number of "bolt-on's," or "add-on's," to those which are absolutely critical to accomplishing

project activities.

10. Total Cost of Implementation

Total Cost of Ownership (TCO) of implementation of SAP includes hardware, software,

professional services, and internal staff costs, maintenance & up gradation charges. As explained

earlier at Adani due to employee failure to understand new system there was requirement to

retrain them so ultimately at the time of “Go Live” TCO was doubled then budgeted cost.

26 | P a g e

Page 27: SAP Implementation in Construction Organization - the Traps

Project Preperation

Bussiness Blue Print

Realization Final Prepera-tion

Go Live & Support

Maintanance

Bud-geted (Rs. In Cr.)

2 7 13 26 36 40

Actual (Rs. In Cr.)

2 8 15 28 42 54

5

15

25

35

45

55

Total Cost At Various StagesCo

st in

Lac

s

Figure 5 Budgeted vs Actual Cumulative Cost of Implementation

11. Operational Deficiencies

• Developing reports is difficult in SAP

• Not all required reports were available at implementation time

• Operational deficiencies that impact the accuracy and efficiency of operations and the ease of

use of the system

• SAP is not sufficiently integrated with other systems

27 | P a g e

Page 28: SAP Implementation in Construction Organization - the Traps

12. Knowledge Management

• Difficult to retain people with SAP skills due to market pressure to leave

• Insufficient resources and effort put into developing in-house knowledge

• Training provided was inadequate and did not cover the diversity of circumstances encountered

in normal daily operations

13. Organizational Context

• Differences in work ethic among project personnel

• Implementation across multiple agencies led to sub optimization of the system configuration

• Lack of leadership at senior levels

• Lack of ownership/responsibility by agency personnel at the project level

• Political issues had a negative impact on the project

• Poor communication between agencies

• Timing of implement was inappropriate because of change underway in the public sector

14. System Development

• Complexity of SAP means makes overall design decisions very difficult

• Frequency of SAP upgrades places a large burden on system maintenance

• Frequency with which requirements changed caused problems for developers

• Inadequate system testing left many errors in the implemented system

• Issues that arose during, or result from, the development phase of the SAP system

• Requested system functionality was sacrificed in order to meet implementation deadlines

• Shared knowledge among project team members was a problem - agency staff did not

understand SAP and implementation personnel did not understand agency requirements

• System documentation is inadequate, particularly with respect to system design and controls

• The project team was disbanded when the system was handed over despite many issues

remaining unresolved

• Too little effort put into redesigning the underlying business processes, resulting in a system

that represented a“technology swap” that failed to capture many of the benefits of SAP.

Now based on the above information and literature review one questionnaire has been

prepared to identify most important risk in SAP implementation.

28 | P a g e

Page 29: SAP Implementation in Construction Organization - the Traps

3.4 SAP Implementation Risks

29 | P a g e

SAP implementation

RiskOperationalRisk (OR)OR 1 In general

OR 2 Sales and marketing area

OR 3. Material & Production Area

OR 4 Financial & Accounting Area

Analytical Risk (AR)AR1. In General

AR2. Sales and marketing area

AR3. Purchase and productionarea

AR 4. Financial & Accounting Area

Organisation-Wide Risk(OWR)OWR 1. Top Management

OWR 2. SAP Planning

OWR 3. In house Expert

OWR 4. System Users

OWR 5. System Vendor & Consultant

TechnicalRisk(TR)TR 1. System Integration

TR 2. System Faults

TR 3. System Maintanance

Page 30: SAP Implementation in Construction Organization - the Traps

3.4.1 Operational Risk

30 | P a g e

OR 1 In General

OR1.1 - Operational staff are reluctant to use the

systemOR1.2- Operational staff input incorrect data to the system

OR 2 Sales & Marketing Area

OR2.1-Sales staff are not able to obtain needed data and information from the system

OR2.2-Fail to maintain up-to-date and comprehensive customer info files

OR 3Material & Production Area

OR3.1- System contains inaccurate supplier records

OR3.2- System contains inaccurate or incomplete bill of materials

OR3.3- System contains inaccurate inventory records

OR 4Financial & Accounting Area

OR4.1- Accounting staff are unwilling to release accounting responsibility and power to non-account staffs

OR4.2- Non-accounting staff are unwilling/incapable to take up accounting responsibilities.

Page 31: SAP Implementation in Construction Organization - the Traps

3.4.2 Analytical Risk

31 | P a g e

AR 1 In General

AR1.1Front-line managers refuse to use the

system

AR1.2Managers cannot retrieve relevant and

needed information from the system.

AR 2 Sales & Marketing Area

AR2.1- Fail to use the system to generate accurate sales forecasts.

AR2.2- Fail to utilise the system to predict demands of new products.

AR2.3 System fails to support sales personnel to provide special sales promotion to existing customer.

AR 3Purchase & Production Area

AR3.1- System fails to generate appropriate master production Schedule

AR3.2- System fails to generate appropriate material net requirement plan.

AR 4Financial & Accounting Area

AR4.1- Fail to use the system to generate appropriate financial budgets.

Page 32: SAP Implementation in Construction Organization - the Traps

3.4.3 Organizational Risk

32 | P a g e

OWR1Top

management

OWR1.1- Top managers make important IT decisions without consulting IT experts and system users.

OWR1.2- Substantial personnel change in the top management team.

OWR1.3- Top managers do not provide sufficient support to ERP post-implementation.

OWR 2 ERP

Planning

OWR2.1- ERP development plan is missing, ill-defined or misfit with business strategy

OWR2.2- Direction for further ERP improvement and development is unclear

OWR2.3- Budget and fund assigned to ERP post implementation is in

sufficient.

OWR 3In house

Specialists

OWR3.1- Fail to form an efficient cross-functional team to continuously review the system.

OWR3.2- Lose qualified SAP experts

OWR3.3- Lose ERP-related know-how andexpertise accumulated over time

OWR 4SystemUsers

OWR4.1 Users (both staff and managers) do not receive sufficient and continuous trainingOWR4.2Users are uncomfortable to input or retrieve data from the systemOWR4.3ERP related problems are not reported promptly by system usersOWR4.4Data access right is authorised to inappropriate usersOWR4.5Confidential data is accessed by unauthorised people

OWR 5System Vendors& Consultants

OWR5.1Cannot receive sufficient technical support from system vendors

OWR5.2Cannot receive sufficient and proper consulting advice from system consultants

Page 33: SAP Implementation in Construction Organization - the Traps

3.4.4 Technical Risk

33 | P a g e

TR 1 System Integration

TR1.1 Different modules of the ERP system are

not seamlessly integrated.

TR1.2 Legacy systems are not compatible with

new ERP systems.

TR 2 System Faults

TR2.1 Invalid data is not automatically

detected when getting into the

system.

TR2.2 Hardware or software crash.

TR 3System Maintanance

TR3.1- Technical bugs of the system are not

overcome speedily.

TR3.2- Outdated and duplicated data is not

properly managed.

TR3.3- System is not properly modified to meet

new business requirements.

Page 34: SAP Implementation in Construction Organization - the Traps

Chapter-4 Data Analysis

The results of questionnaire show that all of the 40 risks, which were pre-defined in the risk

models, were confirmed by the majority of respondents as risk events to SAP implementation.

However, perceptions of impact and probability of occurrence varied somewhat.

The survey asked respondents to assess the importance of each risk from three aspects.

1. Probability of occurrence,

2. Impact and

3. Frequency of occurrence.

The mean was used in this study to provide a summary of responses associated with the

likelihood, impact and frequency of each identified risk (as presented in Appendix A). The

respondents have subsequently prioritized the 40 identified risks based on their means of

likelihood and means of impact. The top ten risks ranked by their means of likelihood are

presented in table 1. The top ten risks ranked by their means of impact are presented in table 2. A

third set of ranks based on the frequency of occurrence of each risk was neglected, because this

seemed to be less important and relatively redundant.

34 | P a g e

Page 35: SAP Implementation in Construction Organization - the Traps

Table 1 Top Ten SAP risks ranked by mean of likelihood

Rank Code Risk Item Mean Of Likelihood

(L)1 OWR 5.1 Cannot receive enough technical support from system vendors 2.0

2 TR 1.2 New system is not able to integrate with other legacy system 1.98

3 AR 1.2 Managers cannot receive needed information from system 1.95

4 TR 3.2 Outdated and duplicated data of SAP is not properly discarded 1.95

5 OWR 5.2 Cannot receive proper consulting advice from system consultants 1.95

6 OR 3.3 SAP system contains inaccurate inventory records 1.93

7 AR 2.2 Fail to use SAP to predict actual demands of new products 1.93

8 AR 4.1 Fail to use the system to generate appropriate financial budgets 1.93

9 TR 1.1 Seamless integration is not achieved between modules of SAP 1.93

10 TR 3.3 SAP is not properly modified to meet new business requirements 1.93

Table 2 Top ten SAP risks ranked by mean of Impact

Rank Code Risk Item MEAN

OF

IMPACT

(i)

1 OR 1.2 Operational staff input incorrect data into the system 2.44

2 AR 3.2 System fails to generate appropriate material net requirement plan 2.30

3 OWR 4.5 Confidential data of the system is accessed by unauthorized people 2.29

4 OR 3.2 SAP system contains inaccurate or incomplete bill of materials 2.28

5 OR 3.3 SAP system contains inaccurate inventory records 2.27

6 AR 3.1 Master production schedule generated by the SAP system is irrelevant

2.27

7 OWR 1.1 Top managers make important IT decisions without consulting IT experts

2.27

8 OWR 2.1 IS/SAP plan is missing, ill-defined or misfit with business strategy 2.18

9 AR 2.1 Sales forecast generated by SAP is inaccurate and inappropriate 2.17

10 OR 2.2 Customer info files contained in SAP are out-of-date or incomplete 2.15

35 | P a g e

Page 36: SAP Implementation in Construction Organization - the Traps

It is however apparent that the top ten risks presented in table 1 are not the same as those

presented in table 2. In other words, an identified risk that had a high mean of likelihood might

not have a high mean of impact, and vice versa. This was to be expected and shows a clear

awareness of the respondents that there was a clear difference between frequency of a risk and

critical impact of the same risk. This is a well known phenomenon in IS. In fact, from the risk

management perspective, both likelihood and impact should be considered simultaneously rather

than separately when assessing the identified risks. The highest priority should be given to risks

that have both a high likelihood and a high impact. Very often frequent risks are not critical and

therefore are considered to be acceptable risks by the organization. On the other hand, critical

risks, even if they only occur very infrequently may be considered as un-acceptable risks to take

and need a number of risk management mechanisms in place to both mitigate and resolve them.

Finally, it is evident that risks that are both critical and frequent need to be addressed with the

highest priority as they often become non-manageable and therefore extremely dangerous for the

organization.

As a consequence, instead of looking at their likelihood and impact separately, this study

identifies and discuses a set of most critical risks by examining both their means of likelihood

and means of impact. In other to do so, first of all average of the means of likelihood of the 40

identified risks has been calculated: 1.83, as well as, calculated the average of their means of

impact: 2.04. The study identified that there were 16 risks, of which the means of likelihood and

the means of impact were both higher than the average level of the 40 risks. In contrast, the

remainder 24 risks had either a low mean of likelihood or a low mean of impact (i.e. lower than

the average level). It is thereby reasonable to state that, in comparison to the other 24 identified

risks, these 16 risks (as shown in table 3) seemed to be more significant and thus should receive

a higher priority. Since all of these 16 risks had a high mean of likelihood and a high mean of

impact, they should consider as risk. Therefore no further ranking was made to priorities these 16

risks.

36 | P a g e

Page 37: SAP Implementation in Construction Organization - the Traps

Table 3 Top 16 SAP exploitation risks

Rank Code Risk Mean

of (L)

Mean

of (I)

operational OR 2.2 Customer info files contained in SAP are outdated or incomplete 1.88 2.15

Risk OR 3.2 SAP system contains inaccurate or incomplete bill of materials 1.83 2.28

OR 3.3 SAP system contains inaccurate inventory records 1.93 2.27

Analytical AR 2.1 Sales forecast generated by SAP is inaccurate and inappropriate 1.85 2.17

Risk AR 2.2 Fail to use SAP to predict actual demands of new products 1.93 2.10

AR 3.1 Master production schedule generated by SAP is inappropriate 1.80 2.27

AR 3.2 System fails to generate appropriate material net requirement plan 1.85 2.30

AR 4.1 Fail to use the system to generate appropriate financial budgets 1.93 2.10

Organizational OWR 2.1 IS/SAP plan is missing, ill-defined or misfit with business strategy 1.83 2.18

RISK OWR 2.2 Direction for SAP improvement and enhancement is unclear 1.85 2.08

OWR 3.2 Lose qualified IT/SAP experts 1.83 2.05

OWR 3.3 Lose SAP-related know-how accumulated over time 1.90 2.10

OWR 5.1 Cannot receive enough technical support from system vendors 2.00 2.05

Technical TR 1.1 Seamless integration is not achieved between modules of SAP 1.93 2.05

Risk TR 1.2 SAP system is not able to seamlessly integrate with other information systems

1.98 2.04

TR 2.2 Hardware or software crashes 1.88 2.05

This means that critical risks seem to be found across the organizational processes and not

conveniently localized around one category, namely not around the technical category.

Therefore, this study seems to confirm that failure of SAP systems may not just be conveniently

related to the technical infrastructures and software packages. Actually, what this study confirms

is that it is in operational, management and strategic thinking areas that the majority of risks

were identified.

37 | P a g e

Page 38: SAP Implementation in Construction Organization - the Traps

Table 4 SAP Risk Mitigation Strategies

Risks Strategies for SAP risk managementUser

involvement

and

training

- Communicating users about project strategy and objectives

- Classifying users on the basis of their experience & skill set and assigning them

appropriate roles.

- - Effectual training strategy for different roles.

- Upgrading existing skill set to meet the requirements.

Project

managemen

t

- Strategies for recruiting and retaining technical personnel

- Model based implementation strategy.

- Check on budget and time requirements at each stage of project.

- Attain top management commitment to redesign business processes

- Defining levels and hierarchies in organization for effective decision making.

Technology

Implementa

tion

- Strategy for migration and data conversion from existing legacy system tonewly

designed system.

- Maintain log of software bugs and transaction failures.

- Simple training strategy for even very complicated modules.

System

Design

- Design should check process fragmentation.

- Strategy for migrating from existing software version to new version.

- Design should meet business plan criteria and adequately mirror required

processes.

- Use Object- and component- oriented techniques in system design.

- COM/SOM/OMA/OMG object models can be used make object definition in

dependent of programming language.

- System architecture should support partitioning of application on different

computers.

Integration

and

Technology

planning

- Carefully select operating system and network capacity keeping in mind the user

requirement and transaction loads.

- Record of technical problems with new system.

- Client-Server / Distributed Network implementation based on object

communication.

- Object communication can be implemented through CORBA or OLE.

38 | P a g e

Page 39: SAP Implementation in Construction Organization - the Traps

Chapter 5 Conclusion

5.1 Recommendation

It emanates from the above study that SAP system links together organizational strategy,

structure and business processes with the IT systems. It is important to communicate what is

happening, including the scope, objectives and activities of the SAP project. Similarly

appropriate staffing and personnel shortfalls need to be checked carefully. In case of inadequate

internal expertise, it is recommended that organization should hire consultants for technical and

procedural challenges in design and implementation of specific application modules. Instead of

large number of programmers with average skills, it would be better to have few business

consultants those who have specialized expertise in their specific domains. It is very important to

create a perfect project management plan keeping in mind the project size & structure, skill set

available, experience of the company, etc. to avoid high project cost and time over runs. System

design is highly dependent on client server/ distributed network implementation and object

oriented methodology used in various modules and components designs.

The various strategies for mitigating as well as for managing SAP risks have been listed in table.

5.2 Conclusions

To conclude the study, it may be emphasized that user involvement, user training, project

management, technology implementation, system design, integration and technology planning

are the key issues which are the critical risk factors in SAP design and implementation. A

meticulous planning of these issues would surely help in smooth and successful implementation

of SAP systems in any organization in general and in the selected organization in particular.

39 | P a g e

Page 40: SAP Implementation in Construction Organization - the Traps

Appendix- A

Means of Likelihood, Impact and Frequency of the 40 identified riskCode Risk Item Mean of

likelihoodMean of Impact

Mean of

frequency

Operational Risks

OR 1.1 Operational staff are unwilling to use the SAP system 1.45 2.03 2.03

OR 1.2 Operational staff input data into the system 1.12 2.44 1.61

OR 2.1 Sales staff are not able to obtain data and info they need from system 1.71 2.00 2.44

OR 2.2 Customer info files contained in the SAP system are out of date. 1.88 2.15 2.35

OR 3.1 SAP system contains inaccurate supplier records. 1.80 2.02 2.41

OR 3.2 SAP system contains inaccurate or incomplete bill of materials. 1.83 2.28 2.15

OR 3.3 SAP system contains inaccurate inventory records. 1.93 2.27 2.49

OR 4.1 Account staff are unwilling to release accounting response to other 1.70 1.81 2.11

OR 4.2 Non account staff are unwilling and in capable to take up response. 1.38 1.54 2.06

Analytical Risks Mean of likelihood

Mean of Impact

Mean of

frequencyAR 1.1 Front line managers refuse to use SAP system 1.35 1.85 1.75

AR 1.2 Managers cannot receive required information from system 1.95 1.98 2.48

AR 2.1 Sales forecast generated by SAP is inaccurate and inappropriate 1.85 2.17 2.29

AR 2.2 Fail to use SAP to predict actual demand of new products 1.93 2.10 2.38

AR 2.3 System fails to support sales personnel to tailor special offers 1.73 1.71 2.10

AR 3.1 Master production schedule generated by SAP is inappropriate 1.80 2.27 2.34

AR 3.2 System fail to generate appropriate material requirement plan 1.85 2.30 2.33

AR 4.1 Fail to use the system to generate appropriate financial budget 1.93 2.10 2.32

Organization Wide Risk

OWR 1.1 Top managers make imp. IT decisions without consulting IT experts. and system users.

1.46 2.27 1.90

OWR 1.2 Substantial personnel change in the top management team. 1.89 1.89 2.53

OWR 1.3 Top managers do not provide sufficient support to new system 1.60 2.05 2.12

OWR 2.1 SAP development plan is missing, ill-defined or misfit with business strategy

1.83 2.18 2.45

OWR 2.2 Direction for further SAP improvement and development is unclear 1.85 2.08 2.65

40 | P a g e

Page 41: SAP Implementation in Construction Organization - the Traps

OWR 2.3 Budget and fund assigned to SAP post implementation is in sufficient

1.55 1.93 2.43

OWR 3.1 Fail to form an efficient cross-functional team to continuously review the system.

1.85 2.03 2.59

OWR 3.2 Lose qualified SAP experts 1.83 2.05 2.57

OWR 3.3 Lose SAP-related know-how and expertise accumulated over time 1.90 2.10 2.43

OWR 4.1 Users (both staff and managers) do not receive sufficient and continuous training

1.80 1.83 2.59

OWR 4.2 Users are uncomfortable to input or retrieve data from the system 1.89 1.82 2.53

OWR 4.3 SAP related problems are not reported promptly by system users 1.83 1.98 2.50

OWR 4.4 Data access right is authorized to inappropriate users 1.24 2.12 1.76

OWR 4.5 Confidential data is accessed by unauthorized people 1.29 2.29 1.64

OWR 5.1 Cannot receive sufficient technical support from system vendors 2.00 2.05 2.59

OWR 5.2 Cannot receive sufficient and proper consulting advice from system consultants

1.95 1.98 2.46

Technical Risk Mean of likelihood

Mean of Impact

Mean of

frequency

TR 1.1 Different modules of the SAP system are not seamlessly integrated.

1.93 2.05 2.41

TR 1.2 Legacy systems are not compatible with new SAP systems. 1.98 2.04 2.48

TR 2.1 Invalid data is not automatically detected when getting into the system.

1.83 1.98 2.28

TR 2.2 Hardware or software crash. 1.88 2.05 2.33

TR 3.1 Technical bugs of the system are not overcome speedily. 1.90 1.98 2.44

TR 3.2 Outdated and duplicated data is not properly managed. 1.95 1.98 2.46

TR 3.3 System is not properly modified to meet new business requirements.

1.93 2.0 2.32

41 | P a g e

Page 42: SAP Implementation in Construction Organization - the Traps

REFERENCES

1. Mr. Jitendra Singh (2003), “SAP Implementation –Traps”,IT harmony Vol

146 ,pp.241–257

2. Guo Chao Peng, Miguel Baptista Nunes (2008), “Identification and assessment of risks to

successful exploitation of SAP systems in china.” European and Mediterranean

Conference on Information Systems 2008 (EMCIS2008)

3. Bulkeley, William M. “When things go wrong; FoxMeyer Drug took a huge high-tech

gamble; it didn't work”, The Wall Street Journal Western Edition, 1996

4. Shan L. Pan, Sue Newell, Jimmy C. Huang, Alvin Wan Kok Cheung, “Knowledge

integration as a key problem in an SAP implementation.” Twenty-Second International

Conference on Information Systems, 2001.

5. MAJED A. (2000) “EntSAPrise-Wide Information Systems: The Case of SAP R/3

Application.”, In Proceedings of the Second International Conference on Enterprise

Information Systems, pp 3-8.

6. THEMISTOCLEOUS, M., IRANI, Z., O'KEEFE, R., and PAUL, R. (2001) “SAP

Problems and Application Integration Issues: An Empirical Survey”. 34th Hawaii

International Conference on System Sciences, pp 9045-9054.

7. COTTELEER, M.J. (2002) “SAP: Payoffs and Pitfalls”. Harvard Business School

Working Knowledge.

8. Keller, G., and T. Teufel, “SAP R/3 Process Oriented Implementation”, Addison-Wesley,

New York, 1998.

9. SAP AG, ASAP Methodology for Rapid R/3 Implementation: User Manual, Walldorf,

1999.

10. El Emam, S. Quintin, N.H. Madhavji, User Participation in the Requirements engineering

Process: an Empirical Study, Requirements Engineering Journal, 1:4-26, 1996.

42 | P a g e