sanctuary canopy instructions rev d
DESCRIPTION
canopyTRANSCRIPT
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
INSTRUCTION GUIDE
SANCTUARY CANOPY
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
1.
2.
3.
Add gasket to wall plate
Drill holes in wall plate along the two rib lines
Thefirstpairofholesshouldbe25mmfromtheedgeand thenspacedevery525mmalong the length.The lastpair shouldbe25mmfromthefaredge.Theholecentrescan be adjusted to cater for obstructionson the retaining wall.
A8mmdiametermetaldrill bit shouldbeusedforthis.
Offerthewallplateuptothehostwall, mark the holes removewall plate
EXAMPLEDIMENSIONSFORTHE4250mm4PANELOPTION
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
4.
5.
Drill a 8mm diameter hole forthefixingsofthewallplateusingmasonry drill bit to a suitabledepth(110mm).
Offerwallplatetothewall,fastenthe wall plate using the throughfixingframeanchors.
6.
7.
Runabeadofsiliconealongthetopofwallplateagainst thewallto seal.
If the wall is uneaven then a secondaryflashingsuchaschased in leadorflash-bandmayberequired.
Position the locationof thePostConnectorBrackettoyoursoundconcrete floor (if the floor is notsuitablethenitmustberecasttobesuitable)andmarkthecentreholes.
Posts should never bemore than 2.75mapart,or0.25mfromtheendsofthegutter/beam.
Ensure that the holes run parallel to thehostwall,thisensuresthegutterbeamwillbe parallel
TO WALLTO P
OST
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
8.
10.
Drill the holes marked using a12mm diameter masonry drill,to at least a depth of 90mm,ensuringanydebrisisremoved.
Drill a 12mm diameter hole ineachofthe60mmx60mmposts20mm from the end and centralon the face. Ensure there aretwoholeson twoopposite facesready to the connecting bolt to passthrough.
9.
11.
Reposition the Post connector bracket and fasten to the floorusingtheshieldanchor.
Ensure the vertical flanges are at rightangles to the wall so that when the bolt connecting it to the post is inserted these are inserted parallel.
Ensuretheconnectorsareinstraightlinereadyfortheposts.TheBaseholeontheconnector is oversized to allow for someminoradjustmentstoensuretheseareinline.usedforthis.
Locate each post over the connector bracket and securethrough with the M12 x70mmstainless bolt.
Thepostsshouldnowhavea20mmgapatthebottom,thisissothatthepost/postsbeinguseasthedownpipecanexpelthewater.
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
12.
14.
13.
15.
Decide on which post / posts are goingtobeuseasdownpipeandmark the location on the insideofthegutterwithtwostraiglinesrepresenting the edges of thepost /s
ScrewtheGutterBeamEndplatesonto the section, sealing on the insideusingsiliconesealant.
Within these linesdrillanumberof holes so that the water canescape down the inside of thepost.
Use the same 12mm diameter as usedfor thepost thenyoushouldget9holes,ifusingasmallerdiameterdrillmoreholeswouldneedtobedrilled.
Drilling theholes insteadof usinga holecutter will help ensure no large debrisenterstheposttocauseablockage.
Place gutter ontop of posts.Ensuringthatitisdirectlyoppositeand inline with the wall plate.
Thepostswillsitinsidethetwoflangesonthebottomofthegutterbeamsection.
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
16. Drill 4 holes (two on each side flange)witha5mmdrillbit,evenlyspaced, (20mm fromeach edgeofthePost).
17.
18.
Securepoststothegutterbeamusingthe4.8mmblindrivets.Andsiliconesealpostifbeingusedasdownpie.
Ifspace is tightdue toobstructions, thenthe posts will have to be removed fromthe post connectors. The posts then fastenedtothegutterbeamandthenthewholeassemblyofpostsandgutterbeamsecuredbackontothepostconnectors.
The bars will span from thewallplate,acrosstothefrontbeamgutter.Ifthesystemissettothemaximum projection then thesewillnotneedtobecut.Ifthebarsdoneedtobecut,thisshouldbedonenowbeforeinstalling.
Thebaseofthebarwheninplaceshouldoverhang into the gutter section 30mmwhen installed.
30mm
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
19.
21.
22.
20.
Once the bars are all the correct length, the bar endcaps shouldbe installed on the end of eachbar.Thiswillthendefinetheendofthebarthatwillbehangingintothegutter.
The protective film on thesheets should be peeled backapporximatly50mmonalledgesand on both sides.
Ensuring the sheet is free fromdustmoistureandanyotherdebrithesheettapesshouldbeappliedto the two sheet ends.
IftheBarsarecuttolength,thenthesheetsshouldbecutinlengthalsotothesamesizeusingafinetoothsaw.
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
23.
24.
Thesheetenclosuresshouldbecutto1Mlengthsandpositionedover the tapes centrally.
With the sheets being approx. 1050mmwidethisleaveapprox25mmoneachsideuncovered.
Itisimportantthatontheendofthesheetintendedforthegutterthatthedripsectionfacesdownas tonot impede the flowofwater off the sheet.At the end intendedforthewallplateitisimportanttohavethedripfacinguptohelpactasawaterbufferifthereareharddrivingwinds.
Polycarbonate multiwall sheets are UVtreated,oftenthisisonlyononeside.Itisimportantthatthissideisthetopsurface.The sheet will tell you which this is butgeneralpracticeisthatthecoverfilmwiththetextonistheUVprotectedside.
It isagoodideanottoremovethecoverfilmstotallyatthisstage,becausetheywillhelpprotectthesheetsfromrubmarks,anditiseasytoforgetwhichsideshouldfaceup,andoncethecoverfilmisremoveditisnearlyimpossibletotell.
GUTTER END
WALL PLATE END
Thefirstbarshouldbepositionedflush against the gutter beamendcap,andflushwiththeendofthewallplatealso.Thebarshouldoverhang the gutter 30mm withtheendcapatthegutterend.
Ahandywayofensuring thebar is inthecorrect position and help prevent it frommovingwhen installing is toputa60mmwide block ofwood or offcut of post intothegutter.Thiswillspacethebarsothatitoverhangscorrectly.Butanysuchpackingmustberemovedafterthebarissecured.
25mm
25mm
30mm
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
25.
28.
26.
27.
From underneath two 5mmdiameter holes should be drilledthrough the underside of thewallplate and the glazing bar (along the fixing groove line).Theseshouldbe10mmfromthetwoouteredgesoftheglazingbartoallowastrongfixing.
Insert the polycarbonate sheet into the bar side, ensuring thesheet is the correctly prepared (step23)andthecorrectwayup.Ensurethesheetisfullyretainedin the bar and that the 1M sheet closures are up tight to the bar.This is important as the sheetclosureswillhelpensurethebarsare spaced correctly.
Fastenthewallplateandbarstogetherusingtwo4.8mmx12mmblindrivetsthroughthefixingholesjustcreated.
Repeatsteps25&26butonthefrontbeamnotthewallplate.
29. Insert anewbaronto the frameand engage the polycarbonate sheet so that the two long sides ofthesheetaresupported.Thesebars should now be spaced 1Mapart(1050mmbarcentres).
Remember theendcapof thebarshouldbe at the bottom (gutter) end of the roofwith the bar overhanging into the gutter30mm.
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
30.
32.
34.
Repeatsteps25to27onthenewbarjustadded.
Repeatsteps28to31untilalloftheroofisglazed.Thefinalbarshouldfinishflushwiththeendofthewallplateandbeam.
Ifthecanopyisnotgoingtobeastandardlengthandneedsshortening,thenpleaserememberthatthedimensionslistedhereallneedtobeadjustedinproportiontothereducedcanopysize.Thesheetscanbecutwithafinetoothsawandthealuminiumwithahacksaw.
31.
33.
Runasmallbeadofappropriatesiliconesealantalongthejointofthe sheet and the bar.
Screw the wallplate endplates intoposition,andsealwithasmallbeadofsilicone.
SHORTENED LENGTH CANOPIES
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
CUSTOM CONFIGURATIONS
SANCTUARY CANOPY
-
C & A SUPPLIES LTD , BIDDER STREET, LONDON E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.CO.UK | EMAIL:[email protected]
A1
CONSTRUCTING A LENGTH OF CONNECTED CANOPIES
Cutwallplatesandgutterstosizetomakesurethatthecustomconfigurationshousethesheetingpanelscorrectly.
Thewallplatesandgutterslocatedateachendneed25mmcutofffromoneend.
Wallplatesandgutterslocatedinthemiddleofarunrequireatotalof50mmcutofffroma single end.
Retainthecut-offsasthesewillbeusedforbracingthewallplatesandgutterstogether.
DIAGRAMABOVEBASEDON4250mmWALLPLATESANDGUTTER
4225mm
4225mm
4200mm
4200mm
4200mm
4200mm
4225mm
4225mm
RETAIN THIS PIECE
-
C & A SUPPLIES LTD , BIDDER STREET, LONDON E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.CO.UK | EMAIL:[email protected]
A3
A2
Placethegutterbeamstogetherandpositioncentrallyoverthepost.Drillandfixwithrivets.Useretainedoff-cuttobrace
Movethewallplatesintopositionandsealwithabeadofsilicone
A4 Sealwithabeadofsilicone.Inthefinalstageswhenaddingthesheetsandbars,makesure that thebarssitcentrallyover theposts and joints.
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
B1
B2
CONSTRUCTING SELF SUPPORTING CANOPIES
Attach wall plates together back to back. Drill and rivet together.
Runabeadofsiliconedownthecentertofinish.
Tiebars/wiresshouldbeinstalled(notsuppliedasstandard)
-
C & A SUPPLIES LTD , BIDDER STREET, LONDON E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.CO.UK | EMAIL:[email protected]
LINE OF SELF SUPPORTING CANOPIES
C2 FollowinstructionsA1andcutappropriateamountsoffofthewallplatesandgutterbeams.Seetablebelowanddiagramoverleaf.
C1 Ifwallplatesaretospanlengthsotherthan3.2m,4.25mand5.3mitisimportantthattheback-to-backwallplatesarestaggeredtomaintainstructuralintegrityasshownintheimagebelow.
Total Span (mm) Stock lengths required (mm) Cut lengths required (mm) 3200 2x3200 nocuttingrequired
4250 2x4250 nocuttingrequired
5300 2x5300 nocuttingrequired
6350 4x3200 2x31751x31502x1600
7400 2x3200,2x4250 2x42252x3175
8450 4x4250 2x42251x42002x2125
9500 2x5300,2x4250 2x52752x4225
10550 4x5300 2x52751x52502x2650
-
C & A SUPPLIES LTD , BIDDER STREET, LONDON E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.CO.UK | EMAIL:[email protected]
4250mm
4225mm 4225mm
4225mm4225mm
4225mm
4225mm
5275mm 4225mm
4250mm
4225mm
2125mm 2125mm
5275mm
5275mm
4225mm
4200mm
5275mm4225mm
EXAMPLES
4250mm
8450mm
9500mm
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
D1
D2
CONSTRUCTING CANOPY BETWEEN 2 WALLS
Follow item2of themainSanctuarycanopy instructionsandapplyto thegutterbeam.Offer thegutterbeam to thewall, fastenusingthroughfixingframeanchors.
Decidewherethegutterpipeshouldbe.Followitems12and13ofthemainSanctuarycanopyinstructionsandapplytothegutterbeam.
-
C & A SUPPLIES LTD , BIDDEr STrEET, LonDon E16 4ST | TEL: 0845 165 165 8 | WEB: WWW.CABP.Co.UK | EMAIL:[email protected]
FURTHER OPTIONS FOR BUILDING BETWEEN 2 WALLS