samsung quality ppt

18
Prepared By: Abdul Noushad H A PUNCH POINTS IN RFE1 SURVEY(TD LTE) Customer : Circle : KERALA

Upload: abdul-noushad-h-a

Post on 16-Jan-2017

355 views

Category:

Documents


0 download

TRANSCRIPT

Prepared By: Abdul Noushad H A

PUNCH POINTS IN

RFE1 SURVEY(TD LTE)

Customer : Circle : KERALA

CONTENTS:

1. Punch Points of GBM(Ground Base Mast) site.

2. Punch Points of RP1(shared) site.

3. Punch Points of P1(own) site.

2 RJIL-SAMSUNG Project PP of RFE1 survey

MARAD site (GBM):

1. Lightening Arrester was not properly installed.

RJIL-SAMSUNG Project PP of RFE1 survey 3

2. Ground cable not connected to TGB.

RJIL-SAMSUNG Project PP of RFE1 survey 4

3. Water logged in EB supply pipe.

RJIL-SAMSUNG Project PP of RFE1 survey 5

4.Only Non-critical MCB’s are available.

RJIL-SAMSUNG Project PP of RFE1 survey 6

5. No signage board available.

RJIL-SAMSUNG Project PP of RFE1 survey 7

6.Pole got cracked on the top of tower.

RJIL-SAMSUNG Project PP of RFE1 survey 8

7. Platform got damaged.

RJIL-SAMSUNG Project PP of RFE1 survey 9

7. Cable routing is not proper

RJIL-SAMSUNG Project PP of RFE1 survey 10

LESSI Hospital(RP1):

1. Lightning Arrestor not installed in all sectors.

RJIL-SAMSUNG Project PP of RFE1 survey 11

2. Rusted cable tray.

RJIL-SAMSUNG Project PP of RFE1 survey 12

3. No DANGER and CAUTION signage board.

RJIL-SAMSUNG Project PP of RFE1 survey 13

4. Water leakage inside the shelter.

RJIL-SAMSUNG Project PP of RFE1 survey 14

ASAD ROAD (P1):

1.No TGB installed.

RJIL-SAMSUNG Project PP of RFE1 survey 15

2. L A installed only in Alpha

sector.

RJIL-SAMSUNG Project PP of RFE1 survey 16

3. No signage board.

RJIL-SAMSUNG Project PP of RFE1 survey 17