sample report - grocery store

37
Grocery Store #123 Sample Report Report By July 25, 2006 This is a sample report. The names and locations in the project have been changed or censored for confidentiality reasons.

Upload: construction-managers-inc

Post on 12-Nov-2014

3.236 views

Category:

Documents


7 download

DESCRIPTION

This is a sample file that offers an example of the types of reports we can generate for construction claims. Each report is customized to meet the specific needs of the construction claims case. See more at http://www.constructman.com/

TRANSCRIPT

Page 1: Sample Report - Grocery Store

Grocery Store #123

Sample Report

Report By

July 25, 2006

This is a sample report. The names and locations in the project have been changed or censored for confidentiality reasons.

Page 2: Sample Report - Grocery Store

1

Condition Assessment ReportBy Construction Managers, Inc.

Involvment

During the week of May 22, 2006, I received a phone call from the building owner Mr. John Doe with XYZ Properties requesting an evaluation of a vacant grocery market in North Carolina for mold contamination. I met Mr. Doe, we both walked through the facility. The owner conveyed that Dr. Jerry J. Tulis from Duke University Medical Center, Durham, NC was doing the mold sampling and determinations. Mr. Kyle Tomlin of BMS Catastrophe located in Fort Worth, Texas was determining the mold remediation costs. The owner then requested me and my firm, Construction Managers, Inc. to prepare a Condition Assessment Report in order to determine the

estimated costs of complete mold remediation and facility repairs. I returned the following day for additional observation before accepting the project.

Once receiving work

authorization, a detailed inspection was conducted on the building’s external and internal areas. A total of 263 exhibits of damaged electrical, plumbing, HVAC, refrigeration, wall structures and mold contamination were photographed. These exhibits provided the foundation for the Scopes of Work. Compact Discs were made and forwarded to trade contractors to assist them in preparing their proposals. The selections of trade contractors were based on their quality of

work and ability to perform necessary tasks. Locating trade contractors willing to perform this work was difficult. The trade contractors and Construction Managers, Inc. were committed to completing the project for the presented costs.

External Condition

Initially the site resembles a

vacant facility. A parking lot obviously needs resurfacing. The present parking space lines are worn and handicap parking can hardly be detected. Weeds are growing from cracks in the asphalt. A tour around the building’s exterior shows evidence of needed repairs. The only evidence that this property was a grocery market is the typical

This photo shows the extreme amount of mold growth on the floor of the grocery store. The growth of the mold is most noticeable where the shelves and freezers used to be located before demolition.

GROCERY STORE #123

Ju

ly 2

5,

2006

Photo by Construction Managers, Inc.

This is an example of a condition assessment report created by Construction Managers, Inc. The report summarizes the damages to the project and the professional recommendations to restore the building to its original condition.

Page 3: Sample Report - Grocery Store

2

building architecture.

Internal Condition

The building’s internal 45,000 square feet of floor area is contaminated with mold. There are several damaged areas to the building’s internal structure. In the absence of shelving and appliances the mold and damaged areas are clearly evident. One can see several missing plumbing, electrical, refrigeration, and mechanical components. Numerous examples of damaged electrical, plumbing, HVAC, and refrigeration structures can also be seen. Electrical outlets are smashed to the floor with exposed live wires. Copper lines for coolers and freezers are cut from the equipment leaving the lines open for contamination. Also, these lines are cut so close to the floor and walls that they are inappropriate for reuse. Many areas of the floor have open areas exposing concrete and earth. One of the worst areas of damage is under the HVAC system near the back elevation. This damage is a severe safety hazard.

There is evidence of several roof leaks and the roof inspection reveals a roof with very little maintenance. The leaks have allowed excessive moisture to enter the structure. This moisture contributes to an environmental condition resulting in an abundance of mold spores. Evidence of mold is apparent on walls and floors where coolers and freezers were once located. Mold has also spread to the HVAC ducting. Other areas such as plumbing and electrical chases and conduits are also infested with mold.

Facility Scope of Work

• Procedures for mold remediation should be per

Dr. J.J. Tulis and the New York City Department

of Health mold remediation guidlines.

• Replace all carpets.

• Replace Vinyl Composition Tile flooring.

• Verify the VCT black mastic does not contain any

asbestos.

• Replace existing roll-vinyl cove wall base.

• Replace all mold contaminated drywall.

• Electrical power will be needed for the mold

remediation process.

• Replace all contaminated cabinets.

• All surfaces will be cleaned.

• Clean all HVAC internal ducting.

NOTE: See Trade Contractors Proposals and Photo Documentation for additional Scope of Work details.

GR

OC

ER

Y S

TO

RE

#1

23

J

uly

25

th,

20

06

Left

The exterior of the store shows serious signs of neglect. Cracked sidewalks, poor parking lot and weeds can be seen sprouting everywhere.

Right

Extreme conditions of large mold growth can be found throughout the interior of the store. It has spread all over the walls and floors.

Photos by Construction Managers, Inc.

Page 4: Sample Report - Grocery Store

3

Professional Evaluation

The Grocery Store #123 grocery market has 45,000 square feet of floor area. This includes the new produce area added in 1993 as shown on the right elevation. The store was originally leased and operated by “Company A”. The market was eventually closed. A probable reason for this closure is due to the fact that two other grocery markets are located on the same highway. The local town was unable to support three grocery markets belonging to the same chain in such close proximity.

The closure of Grocery Store #123 was conducted in a careless and very hazardous manner. In the absence of shelving, refrigeration lines, and appliances, needless damage and destruction are evident. It appears that there was no supervision of the equipment removal which resulted in an unprofessional job.

The following photographs and documented exhibits display numerous examples of needless damage to electrical, plumbing, HVAC, and refrigeration structures. Electrical outlets are smashed to the floor and expose live wires. Copper lines for coolers and freezers are cut from the equipment leaving the lines open for contamination. Also, these pipes are cut so close to the floor or wall that they are inappropriate for reuse. Many areas of the floor have open areas exposing concrete and earth. Existing exterior walls were removed in order to remove large equipment from the market. These walls are still not repaired. One of the worst areas of

damage is under the HVAC system near the back elevation. This damage is a safety hazard. Improper termination is evident in all of these photographs and exhibits.

In addition to improper removal of equipment, there are evidences of roof leaks. The leaks have allowed excessive moisture to enter the structure. This environmental condition resulted in an abundance of mold spores. Evidence of mold is apparent on the photographs of walls and floors where coolers and freezers were once located. Mold has also spread to the HVAC ducting. Floors,

walls, ceilings, and ducting need to be replaced and all hard surfaces need to be cleaned. Other areas with plumbing and electrical work may also be infested with mold.

Much of this damage could have

been avoided with proper supervision and professional work. The result of such improper closure now results in costly repairs.

- Sam E. Sasser

This is an example of the condition all refrigerant lines were found in the floor. The copper plumbing line were improperly cut off using torches. This line must be completely replaced before it can be used again.

GR

OC

ER

Y S

TO

RE

#1

23

J

uly

25

th,

20

06

Photo by Construction Managers, Inc.

In the business offices there are countless computer and phone wires bundled into a tangled mess.

Large holes can be found in the floor where floor refrigerators and freezers were once located. Some of these holes measure several feet in diameter and nearly a foot deep in places. You can clearly see the ground below in this photo.

Photos by Construction Managers, Inc.

Page 5: Sample Report - Grocery Store

Floor Plan

Grocery Store #123 07/25/06

The floor plan is numbered to correspond with photos. This process serves as an easy reference tool.

Page 6: Sample Report - Grocery Store

Photo #005

Seal and paint exposed concrete walls. Refrigeration copper tubing was not terminated andhas allowed internal contamination. Hole in concrete block wall for tubing was chiseled through rather than properly core drilled and sealed.

For the original report Construction Managers, Inc. took over 250 photos as evidence of damages. For the purpose of the sample report, we chose 10 photos.

Grocery Store #123 07/25/06

Page 7: Sample Report - Grocery Store

Photo #006

Replace damaged hand rails and bollard. Paint exterior concrete walls and bollard. Total area needs cleaning and weeds cut.

Grocery Store #123 07/25/06

Page 8: Sample Report - Grocery Store

Photo #021

Remediate mold. Repair damaged copper tubing and terminate. Remove damaged VCT. Replace with new VCT. Replace vinyl cove wall base. Clean walls and paint.

Grocery Store #123 07/25/06

Page 9: Sample Report - Grocery Store

Photo #065

Remediate mold. Repair damaged concrete flooring. Remove damaged VCT and replace with new VCT.

Grocery Store #123 07/25/06

Page 10: Sample Report - Grocery Store

Photo #078

Remediate mold. Remove VCT and replace with new VCT.

Grocery Store #123 07/25/06

Page 11: Sample Report - Grocery Store

Photo #079

Grocery Store #123 07/25/06

Remediate mold. Remove VCT and replace with new VCT.

Page 12: Sample Report - Grocery Store

Photo #124

Grocery Store #123 07/25/06

Replace acoustical ceiling tiles and metal grid. Replace damaged metal studs. Prepare electrical conduit per electrical code to avoid fire hazard. Replace insulation.

Page 13: Sample Report - Grocery Store

Photo #125

Grocery Store #123 07/25/06

Box cooler was removed. Walls left exposed. Replace insulation. Prepare electrical conduit per electrical code to avoid fire hazard. Replace acoustical ceiling tiles and metal grid.

Page 14: Sample Report - Grocery Store

Photo #248

Grocery Store #123 07/25/06

Electrical wiring was not properly terminated per electrical code.

Page 15: Sample Report - Grocery Store

Photo #249

Grocery Store #123 07/25/06

Major copper refrigeration lines were removed and must be replaced. Electrical wiring is not properly terminated per electrical code.

Page 16: Sample Report - Grocery Store

Grocery Store #123

6%

34%

14%8%

22%

14%2%

OtherGeneralDemolitionRoofing/InsulationFinishesMechanicalElectrical

07/25/06

Estimate To Repair

Total Amount$1,863,902

This is an overview of the total estimated cost to repair this building.

Page 17: Sample Report - Grocery Store

Construction Managers, Inc. Estimate Report Page 1Grocery Store #123

Project name Grocery Store #123202 Main StRolesburgNC 23456

Client John Doe

Estimator Sam Sasser

Job size 45000 sf

Duration 6 mths

Report format Sorted by 'Group phase/Phase''Detail' summary

Detailed Estimate

Grocery Store #123 07/25/06

A detailed estimate of the entire project estimate breaks down the cost of labor, materials, sub-contracts, and equipment rental.

Page 18: Sample Report - Grocery Store

Detailed Estimate

Grocery Store #123 07/25/06

Construction Managers, Inc. Estimate Report Page 2Grocery Store #123

Item Description Takeoff QtyLabor

AmountMaterial

AmountSubcontract

Amount NameEquipment

AmountTotal

Amount

1000.000 GENERAL CONDITIONS

1101.000 Personnel: Supervision10 Superintendent 24.00 wk 28,800 - - 28,800

Personnel: Supervision 28,800 28,800960.00 Labor hours960.00 Equipment hours

1131.000 Personnel: Proj. Managmnt40 Project Manager 6.00 wk 18,000 - - 18,00070 CM Estimate RPT 72.00 hr 9,000 - - - 9,000

Personnel: Proj. Managmnt 27,000 27,000312.00 Labor hours240.00 Equipment hours

1511.000 Temp: Utilities1 Temp Electricity 6.00 mnth - - - - 6,000

Temp: Utilities 6,000

1521.000 Temp: Facilities05 Field Office 6.00 mnth - - - 2,850 2,850

n 10 Tool and Storage Trailors # 1 6.00 mnth - - - 1,029 1,029n 10 Tool and Storage Trailors # 2 6.00 mnth - - - 1,029 1,029

Temp: Facilities 4,907 4,9073,119.94 Equipment hours

1591.000 Office Equipment10 Job Sign 1.00 ea 81 313 - - 394

Office Equipment 81 313 3943.000 Labor hours

1592.050 Controls: Safety30 First Aid Equip 6.00 mnth - 157 - - 157

Controls: Safety 157 157

1651.000 Engineer/Architect Fees10 Electrical, HVAC, & Plumbing

Engineer's Fees- - 58,500 - 58,500

20 Reproduction - - - 2,000

Page 19: Sample Report - Grocery Store

Detailed Estimate

Grocery Store #123 07/25/06

Construction Managers, Inc. Estimate Report Page 3Grocery Store #123

Item Description Takeoff QtyLabor

AmountMaterial

AmountSubcontract

Amount NameEquipment

AmountTotal

Amount

Engineer/Architect Fees 58,500 60,500

1705.000 Clean Up10 Daily Cleanup 24.00 wk 25,920 1,377 - - 27,29755 Dumpster Rent / Haul & Dump Fee - - 10,000 - 10,00060 Final Cleanup - 34,747 - 34,747

Clean Up 25,920 1,377 44,747 72,044960.00 Labor hours

1730.000 Tools & Equipment05 Perishable Tools - 2,000 - - 2,000

Tools & Equipment 2,000 2,000

1801.000 Insurance30 Builder's Risk Insurance - - - - 3,500

Insurance 3,500

1835.000 Business License10 Dunn Business Privilege License - - - - 2520 Building Permit - - - - 7,500

Business License 7,525

1920.000 Bond10 Performance Bond - - - - 15,000

Bond 15,000

1930.000 Contract Close out20 Final Inspection & Punchlist 4,320 - - 4,320

Contract Close out 4,320 4,320

GENERAL CONDITIONS 86,121 3,847 103,247 4,907 232,1472,235.000 Labor hours4,319.940 Equipment hours

2050.000 DEMOLITION

2050.010 Demo: Subcontractors05 Sub: Mold Testing - - - 15,00006 Sub: Mold Remediation - - 284,793 - 284,79310 Sub: Asbestos Mastic Abatement - - 48,750 - 48,750

Page 20: Sample Report - Grocery Store

Detailed Estimate

Grocery Store #123 07/25/06

Construction Managers, Inc. Estimate Report Page 4Grocery Store #123

Item Description Takeoff QtyLabor

AmountMaterial

AmountSubcontract

Amount NameEquipment

AmountTotal

Amount

Demo: Subcontractors 333,543 348,543

DEMOLITION 0 0 333,543 0 348,543

2100.000 SITEWORK

2511.000 Paving: Asphalt10 Asphalt Surface Treatment 10,000.00 sy 8,700 - - 0 8,700

Paving: Asphalt 8,700 8,700322.222 Labor hours300.000 Equipment hours

2584.000 Paving: Parking Lines10 Parking & Caution Lines 0 0 2,600 - 2,600

Paving: Parking Lines 2,600 2,600

2842.000 Improvmnts: Bollard/Rails30 Pipe Bollard Steel Pipe 4.00 ea - - 2,310 - 2,31040 Guard Rail Corrugated Galvanized

(No ends)24.00 lf 201 250 - - 451

Improvmnts: Bollard/Rails 201 250 2,310 2,7617.44 Labor hours

2900.010 Landscape: General20 Weed & Clean - Up - 500 - 500

Landscape: General 500 500

SITEWORK 8,901 250 5,410 0 14,561329.662 Labor hours300.000 Equipment hours

3000.000 CONCRETE

3000.010 Division 3 Subcontractors1 Patch Flatwork Concrete - - 5,400 - 5,400

Division 3 Subcontractors 5,400 5,400

CONCRETE 0 0 5,400 0 5,400

Page 21: Sample Report - Grocery Store

Detailed Estimate

Grocery Store #123 07/25/06

Construction Managers, Inc. Estimate Report Page 5Grocery Store #123

Item Description Takeoff QtyLabor

AmountMaterial

AmountSubcontract

Amount NameEquipment

AmountTotal

Amount

6000.000 WOOD & PLASTICS

6114.000 Plywood: Subfloortg30 Subfloor 3/4" T & G Plywood - 0 1,800 - 1,800

Plywood: Subfloor 1,800 1,800

WOOD & PLASTICS 0 0 1,800 0 1,800

7000.000 THERMAL & MOISTURE PROT

7000.010 Division 7 Subcontractors40 Insulation Sub (Batts & Blown) - - 18,049 - 18,04961 Roofing Sub - - 111,400 - 111,400

Division 7 Subcontractors 129,449 129,449

THERMAL & MOISTURE PROT 0 0 129,449 0 129,449

8000.000 DOORS & WINDOWS

8710.010 Hardware: Finishing11 Exterior Door Locks 0.00 ls 0 0 750 - 750

Hardware: Finishing 750 750

DOORS & WINDOWS 0 0 750 0 750

9000.000 FINISHES

9000.010 Division 9 Subcontractors20 Replace Drywall & Acoustical

Ceilings- - 101,718 - 101,718

Division 9 Subcontractors 101,718 101,718

9600.000 VCT-Flooring10 VCT-Base & Carpet tiles (Lump

Sum)- - 58,046 - 58,046

VCT-Flooring 58,046 58,046

9605.000 Carpeting

Page 22: Sample Report - Grocery Store

Detailed Estimate

Grocery Store #123 07/25/06

Construction Managers, Inc. Estimate Report Page 6Grocery Store #123

Item Description Takeoff QtyLabor

AmountMaterial

AmountSubcontract

Amount NameEquipment

AmountTotal

Amount

9605.000 Carpeting10 Carpeting - - 1,800 - 1,800

Carpeting 1,800 1,800

9615.000 Ceramic Tile10 Ceramic-Tile (Lump Sum) - - 14,740 - 14,740

Ceramic Tile 14,740 14,740

9930.010 Painting: Interior & Exte100 Painting Interior & Exterior Complete - - 57,630 - 57,630

Painting: Interior & Exte 57,630 57,630

FINISHES 0 0 233,934 0 233,934

11000.000 EQUIPMENT

11000.010 Division 11 Subcontractrs10 20 ' Lift 6.00 mnth - - - 3,450 3,450

Division 11 Subcontractrs 3,450 3,4501,039.98 Equipment hours

EQUIPMENT 0 0 0 3,450 3,4501,039.98 Equipment hours

15000.000 MECHANICAL

15000.100 Division 15 Subcontractrs5 Sprinklers - LumpSum - - 4,500 - 4,500

Division 15 Subcontractrs 4,500 4,500

15400.000 Plumbing10 Plumbing (Lump Sum) - - 20,000 - 20,000

Plumbing 20,000 20,000

15500.000 HVAC Systems10 HVAC Duct Wrap (Lump Sum) - - 65,000 - 65,000

HVAC Systems 65,000 65,000

15650.000 Refrigeration100 Refrigeration Lines (Lump Sum) - - 450,000 - 450,000

Page 23: Sample Report - Grocery Store

Detailed Estimate

Grocery Store #123 07/25/06

Construction Managers, Inc. Estimate Report Page 7Grocery Store #123

Item Description Takeoff QtyLabor

AmountMaterial

AmountSubcontract

Amount NameEquipment

AmountTotal

Amount

Refrigeration 450,000 450,000

15950.000 Controls10 Electronic Controls (Lump Sum) - - 12,000 - 12,000

Controls 12,000 12,000

MECHANICAL 0 0 551,500 0 551,500

16000.000 ELECTRICAL

16001.000 Electrical Complete10 Electrical (Lump Sum) - - 98,500 - 98,500

Electrical Complete 98,500 98,500

16502.000 Alarm System500 Fire Alarm System Service - - 750 - 750

Alarm System 750 750

ELECTRICAL 0 0 99,250 0 99,250

Page 24: Sample Report - Grocery Store

Detailed Estimate

Grocery Store #123 07/25/06

Construction Managers, Inc. Estimate Report Page 8Grocery Store #123

Estimate Totals

Description Amount Totals Hours Rate Cost Basis Cost per Unit Percent of TotalLabor 95,022 2,564.662 hrs 2.112 /sf 5.10%

Material 4,097 0.091 /sf 0.22%Subcontract 1,464,283 32.540 /sf 78.56%

Equipment 8,357 5,659.920 hrs 0.186 /sf 0.45%Other 49,025 1.089 /sf 2.63%

1,620,784 1,620,784 36.017 /sf 86.96 86.96%

OH & P % of Bottom Line 243,118 15.000 % T 5.403 /sf 13.04%Total 1,863,902 41.420 /sf

Page 25: Sample Report - Grocery Store

PREPARED BY

Kyle Tomlin

For

JAMES LOCKAMY

FOOD LION BUILDING

DUNN PLAZA

DUNN, NC

May 11, 2006

Grocery Store #123

A professional remediation contractor’s scope of work report was used to create the project estimate.

Page 26: Sample Report - Grocery Store

Page

2

TECHNICAL REPORT INSPECTION AND TESTING This Scope of Work is based on the inspection conducted at the Food Lion Building in Dunn Plaza located at 1727 W. Cumberland Street Dunn, NC on May 10th 2006 by Dr. J.J. Tulis of Duke University and Kyle Tomlin of BMS CAT. All remediation will be directed by this investigation and results of the visual, air and surface sampling that was performed by Dr.Tulis on this date. The onsite investigation and the conclusive test results will confirm the basis of this remediation plan of action. A limited destructive investigation will be conducted in specified areas after containment and air control has been established and approved, this will allow for a conclusive remediation protocol. DISCUSSION Specific containment and work procedures are required in the remediation of fungal contamination (viable and nonviable). BMS CAT will provide remediation services in accordance with the “ Guidelines on Assessment and Remediation of Fungi in Indoor Environments 2002, “ from the New York City Department of Health & Mental Hygiene Bureau of Environmental & Occupational Disease Epidemiology, 2002. “

SCOPE OF WORK DEFINITION OF PROCEDURES Seal & containment

6 mil fire rated poly (FR) will be used to seal porous surfaces and reduce and maintain the contaminated area. Negative air pressure

Air Filtration Devices (AFDs) will be used to maintain air control for containment and the reduction of airborne particulate before during and after remediation as required in the specified level of PPE. Sheetrock removal and disposal Removal procedure will be based on a dust reduction cutting and removal technique for the reduction of released spores. All disposals will follow provided specification.

Grocery Store #123

Page 27: Sample Report - Grocery Store

Page

3

Ceiling tile and insulation removal & disposal Ceiling tile and ceiling Insulation will be removed and bagged for disposal. Gross cleaning of all surfaces This process will take place during and at the completion of all contaminant removal. A top down cleaning procedure will be followed utilizing HEPA vacuuming and a wet wipe process for maximum efficiency of removing large debris and reducing the particulate count. Fine clean of all surfaces for pre clearance inspection A top down cleaning procedure will be followed utilizing HEPA vacuuming and a wet wipe process for maximum efficiency of removing all visual dust allowing for and pre inspection and particulate counts that substantiate clearance testing.

Containment 1. A site plan for containment has been developed during the investigation and approved

by Dr.Tulis. 2. Shut down of supply and return HVAC in all affected areas. Mechanical seal of all high

pressure system lines affecting containment area a. All supply and returns will be sealed to reduce possible cross contamination. b. At the completion of the remediation project all filters in the main unit will be

changed by Building Services or owner. 3. Set-up containment barriers and chambers.

a. The front retail areas will be separated from the rear production and storage areas.

4. Set-up of AFD’s and test for proper air control. a. Static air flow will be used during remediation. Air flow will be designed to

circulate all areas of the facility for dust reduction and air washing. b. The front retail area will be separated with an independent air flow until fine

cleaning is completed. c. The rear production storage area will be separated from the front retail with an

independent air flow system. 5. At the completion of the fine cleaning of the front retail area and the rear production

and storage area all barriers will be removed and one air flow system will be kept in place for total air washing of the facility until testing is performed.

Grocery Store #123

Page 28: Sample Report - Grocery Store

Page

4

FLOW OF WORK

• BMS sets up supply area.

• All entrance and exit activities will be at the rear of the building.

• Store front windows will be covered for privacy.

• HVAC control devices will be covered for reduction of cross contamination.

• Additional electrical power will be set up for remediation process.

• Dumpsters will be positioned at the rear of the facility.

• Gross cleaning of retail floor will be performed. ( an estimated 5 tile rows will be

removed in the area that was located under the 18 rows of stock display shelf’s )

• All drywall with visual growth patterns will be removed and disposed based on

protocol.

• All ceiling tile and ceiling insulation will be removed and disposed.

• Contaminated cabinets in expanded front office will be removed and disposed.

• All surfaces below ceiling grid will be gross cleaned.

• HVAC units and duct will be cleaned.

• All building products with visual growth patterns will be removed and disposed.

• Ceiling tile and ceiling insulation will be removed and disposed.

• All surfaces below ceiling grid will be gross cleaned.

• All surfaces below the ceiling grid in the front retail area and the rear production and

storage area will be fine cleaned.

• AFD’s will be set up for air washing of the facility until testing is to be performed ( air

washing must run no less then 7 days before testing is performed )

• Clearance testing will be performed to allow for the beginning of reconstruction.

BUILDING PRODUCTS TO BE DISPOSED

• All ceiling tile and ceiling insulation. • Carpet at front entrance. • Ceiling grid in bakery and deli prep area only. • Cabinets in expanded front office. • Limited drywall behind meat counter and seafood area. • Limited drywall behind produce counter area. • Limited drywall and plywood behind meat cooler area. • Limited drywall behind deli cooler area.

Grocery Store #123

Page 29: Sample Report - Grocery Store

Page

5

• Limited tile removal in up stares office in rear area. ( some floor sanding will be performed in the area that tiles are to be removed )

• Limited tile removal will be need in the landing next to the upstairs office in the rear area.

• The plywood deck landing under the large HVAC duct in the rear area will be removed.

• Limited insulation will be removed from the main supply duct in the rear area due to visual water damage.

SPECIAL ACKNOWLEDGMENTS

A. BMS CAT will coordinate all requests through James Lockamy (910) 890-1727 owner of property.

B. BMS CAT requests that James Lockamy provide plant services. C. BMS CAT will require an area in which a supply and equipment distribution

can be maintained.

D. BMS CAT will coordinate entrance / exit and security procedures with the appropriate contact person as needed. ( all visitors must sign in with Building Services, BMS CAT will not be responsible for PPE or required documentation from any other then BMS staff )

E. All BMS CAT non-management personnel will be uniformed or badges for

identification purposes.

F. BMS CAT will set-up restricted area noted by signage.

G. All containment and remediation procedures will be performed in PPE (Personnel Protective Equipment) specified by Dr. J.J. Tulis.

H. All dumpsters will be provided by BMS.

Pricing BMS CAT has provided a lump sum cost of $_110,358.00_ for the remediation of the Food Lion building, the cost is based on the above scope of work. Time schedule This project is schedule to take an estimated 10 days, 5 to 7 day period of air washing will be required after the completion of the remediation process before testing can be conducted. An estimated 7 day waiting period will be needed once the final test have been conducted before results will be available. This gives an estimated 22 to24 days until this property could be released for reconstruction.

Grocery Store #123

Page 30: Sample Report - Grocery Store

Page

6

. Any additional work required after the onsite investigations are completed under containment is maintained will be presented in written form to James Lockamy prior to the start of the process. Areas that are suspect to possible increases due to internal condition, and can not be seen until demolition has been performed under controlled conditions.

• The decking under the main duct supply in the rear area. • Drywall above the ceiling grid. • Decking in the upper office in the rear area. • HVAC unit and duct.

On behalf of BMS Catastrophe we wish to thank you for allowing us this opportunity to participate in the recovery of this facility. In the light of such as situation, it is our sincere desire to provide the finest in restoration and business recovery services to allow James Lockamy to return his property to a preloss condition. Respectfully Submitted, Kyle Tomlin Project Manager

CORPORATE OVERVIEW Blackmon-Mooring began business in 1948 restoring soiled and damaged furniture and carpet. Over the next 45 years, Blackmon-Mooring and affiliated companies developed unique equipment, materials, processes, and skills for cleaning and restoring structures and contents soiled and damaged by smoke, soot, water, and other contaminants generally associated with fires, floods and other disasters. In the 1960’s, Blackmon-Mooring and affiliated companies began training and licensing franchisees to serve expanding markets. The result is a network of Steamatic franchise operations that serve customers from over 200 locations in major markets nationally and internationally. In 1981, Blackmon-Mooring Steamatic Catastrophe, Inc. (BMS CAT) was formed as a special Steamatic franchisee that is directly managed and operated by members of the Blackmon and Mooring families. BMS CAT specializes in large-scale commercial and industrial remediation work following fires, floods, earthquakes, and other catastrophic losses. Their first test was the Las Vegas Hilton. While everyone else was saying six

Grocery Store #123

Page 31: Sample Report - Grocery Store

Page

7

months to get the back into operation, BMS CAT performed the project in 29 days. Since that time BMS CAT has never looked back. To be able to respond quickly to losses as they occur requires a large organization in place and an extensive inventory of equipment and chemicals for any contingency. BMS Enterprises has eight company-owned locations and over 200 franchise locations worldwide. The main BMS CAT warehouse in Texas has over 40,000 square feet and there is satellite warehouses located throughout the country. This organization and depth allow BMS CAT to take on projects that no one else can. In one particular case, BMS CAT mobilized and had over 80 supervisory personnel and 800 local workers on-site only 48 hours after the contract was signed. By recognizing the unique restoration problems associated with fires and floods, BMS CAT has been able to effectively develop methods to restore facilities and their contents. Areas of expertise are clean room prep for Certification, industrial corrosion control on machinery and electronic corrosion control on EDP equipment, data retrieval, recovery, and the restoration of documents and books. By developing these services in-house instead of relying on subcontractors, BMS CAT has been able to maintain its reputation for unmatched quality control. BMS CAT is proud of their impeccable Safety Record.

Grocery Store #123

Page 32: Sample Report - Grocery Store

TESTING OF THE LEASED FOOD LION SUPERMARKET FACILITY FOR THE

PRESENCE OF MOLD GROWTH

Dr. J.J. Tulis, Emeritus Professor

Occupational & Environmental Medicine Community & Family Medicine

Duke University Medical Center, Durham, NC

May 16, 2006

The leased supermarket property was visited on May 10, 2006 by Dr. J.J. Tulis and Mrs. Sheryl Bowen for the purpose of inspection of the building for the presence of visible mold growth and conduct of both surface and air testing of the indicated dwelling for the presence of mold growth and indoor air quality. Dr. Tulis is Professor Emeritus at Duke University Medical Center, and Mrs. Bowen is a registered state sanitarian and environmental scientist; both individuals are experienced mold investigators. The request for investigation of the leased property, i.e., leased by Mr. James Lackamy to the Food Lion Corporation, was made by Mr. Steve Epstein of Hunton & Williams, Raleigh, NC. The subject building is located within the Dunn Plaza, Dunn, NC. With the approval of Mr. Epstein, Dr. Tulis invited Mr. Kyle Tomlin of BMS Cats, Ft. Worth, TX, a world-renowned mold remediation company, to join the investigative team comprised of Mr. Epstein, Mr. Lackamy, Dr. Tulis, Ms. Bowen, and Mr. Tomlin. Sampling of the apparent mold growth was conducted using clear cellophane tape for removal of “lift “ samples with subsequent microscopic examination. The lifted samples were affixed on glass microscope slides and placed in a transport case. For microscopic examination, lactophenol cotton blue, a mycologic stain, was placed on each lifted site, covered with a glass coverslip, and microscope fields were examined at both 100X and 400X magnification for confirmation of fungal growth and identification of fungal genera by both Dr. Tulis and Ms. Bowen. At the subject supermarket, visible mold sites were sampled in the retail area from sheetrock walls located along the east, south, and west locations and from apparent mold growth on the soiled floor tiles. Samples were also collected from the rear storage area sheetrock wall and from the office cabinets located at the eastern storefront. Results of the microscopic examinations of samples showed the presence of the following fungal genera and presumptive species of mold growth:

A professional mold evaluation report.

Grocery Store #123

Page 33: Sample Report - Grocery Store

Location Presence of Mold Growth Sheetrock wall, east retail area Dirt and debris Sheetrock wall, rear retail meat area Aspergillus versicolor, Stachybotrys Sheetrock wall, west retail area Aspergillus versicolor, Stachybotrys Floor tile, retail area Cladosporium Sheetrock wall, rear storage western area Chaetomium, Stachybotrys Eastern front office area cabinetry Aspergillus

The monitoring of the indoor air was achieved through the use of the 2-stage Andersen cascade impactor, the internationally recognized industry standard. Each stage of the impactor has 200 radially arranged holes (i.e., nozzles or jets) through which sampled air is drawn by the use of a vacuum pump, which operates at the rate of one cubic foot per minute. The principle of cascade impaction depends on the increased velocity of entrained particles due to decreases in nozzle diameters in subsequent stages of the impactor, i.e., the 200 holes in the lower stage are significantly smaller in diameter than those in the upper stage. Because of the indicated physical characteristics of the impactor, non-respirable particles (i.e., those larger than 5 micrometers or microns) are deposited on the upper stage and respirable particles (i.e., those smaller than 5 micrometers or microns) are deposited on the lower stage. Thus, the sampled air is separated into non-respirable and respirable fractions. The Andersen 2-stage impactor and associated vacuum system are calibrated with a rotameter for proper air flow. For the impaction of airborne particles containing mold spores, Malt Extract selective mycologic culture medium was used. This culture medium is the recognized industry standard for the collection of viable fungal spores. It is an aciduric medium, i.e., low in pH, that inhibits bacterial growth but does not interfere with the growth of environmental fungi. Incubation of the media was accomplished at ambient room temperature. Sampling times were determined through experience; indoor sites were sampled for both 1.0 and 2.5 minutes; the outdoor air was sampled for 2.5 minutes. An industry provided correction table was used to determine the probable number of deposited mold spores on each plate.

Viable Airborne Fungal Spores Collected in the Leased Supermarket

Location Spores/Cubic Meter Air Rank Order of Fungal Genera

Retail area (front east) 556 AS (69%), PE (28%), CL (3%) Retail area (front west) 5600 AS (60%), PE (38%), CL (2%) Storage area (rear east) 3024 AS (75%), PE (15%), CL (10%) Storage area (rear west) 7560 AS (69%), PE (30%), CL (1%) Outdoors (front) 438 CL (90%), AS (5%), PE (5%)

AS (Aspergillus sp.), CL (Cladosporium sp.), PE (Penicillium sp.)

Grocery Store #123

Page 34: Sample Report - Grocery Store

Visual inspection of the subject facility showed the presence of apparent visibly evident mold growth throughout the building, albeit restricted to modest areas of sheetrock walls, ceiling tiles, floor tiles, and wooden cabinetry. The surface sampling of areas of presumptive mold growth revealed the presence of the fungal genera of Aspergillus, Cladosporium, Chaetomium, and Stachybotrys. Air sampling revealed the airborne presence of Aspergillus, Cladosporium, and Penicillium; Stachybotrys spores were not detected due to their inability to grow on Malt Extract culture medium. The species of Aspergillus appeared a priori to be primarily Aspergillus versicolor. Findings, both from facility inspection and quantitative and qualitative laboratory results, support the timely mold remediation of the subject facility. Because the presence of visibly evident and laboratory-documented mold growth is limited, the majority of remediation activities should be associated with aggressive housecleaning and air washing, including some removal of floor tiles and sheetrock. It would appear prudent to remove all ceiling tiles due to both mold and water damage, and all carpeting. Procedures for remediation should adhere to the well-recognized and industry-accepted NYC mold remediation guidelines.

Grocery Store #123

Page 35: Sample Report - Grocery Store

Ivey Mechanical Services 122 Drake Street

Fayetteville, North Carolina 28301

Phone: 910-483-2000

Fax: 910-483-2016 www.iveymechanical.com

August 29, 2006

Construction Managers, Inc.

P.O. Box 1138

Fremont, N.C. 27830

Re: Dunn Supermarket Refrigerate Piping.

Dear Mr. Sasser,

Thank you for giving Ivey Mechanical Company, LLC the opportunity to quote the above mentioned

project. Our scope of work will include the following:

1. Replace refrigerate copper and insulation in the back of the store.

2. Replace refrigerate copper and insulation in the bakery area located in the front of the store.

3. The refrigerate copper located under the sales floor has been severely contaminated with

concrete particles and dust. We will have to remove concrete and cut part of this copper out

to get these particles out of the lines.

4. When all the lines have been repaired and vacuumed thoroughly, we will test, cap and we

will fill each line with nitrogen.

Our budget figure for this project is $450,000.00

Our quote is valid for 30 days. Should you have any questions please feel welcome to call us at

483-2000.

Best regards,

Randall Davis

Project Manager

Ivey Mechanical Company, LLC

The last two pages are a sample of the multiple bids received from qualified trade contractors work.

Grocery Store #123

Page 36: Sample Report - Grocery Store

August 10, 2006

Construction Managers, Inc.

P. O. Box 1138 Fremont, NC 27830

Attention: Sam Sasser

Reference: Electrical Pricing for Old Winn Dixie Repairs in Dunn, NC

Mr. Sasser,

In reviewing the photos on the CD I received from you, my best guess would be around $98,500 for the

electrical work indicated in numbers 4, 28, 29, 32, 35, 41, 42, 48, 50, 53, 54, 63, 71, 77, 84, 93, 94, 95, 106, 112, 113, 115, 119, 122, 124, 125, 127, 133, 134, 135, 141, 145, 147, 149, 152, 153, 154, 157, 161,

163, 164, 182, 187, 189, 190, 195, 197, 198, 199, 201, 225, 228, 231, 232, 246, 248, 251, 255, 256, 257,

260, and 261. It is assumed that all mold remediation would be completed prior to our starting work so no

respirators would be required by our workers. (Our safety department will require this be done to let us work in the building.)

The bulk of the work as far as I can tell would consist of removing and reinstalling the indicated abandoned floor circuits, (terminating on the floor with a 6’ greenfield flex for connection to future

equipment and routed to the current equipment or location on the other end), and properly

supporting/terminating electrical items where equipment removal has created open ended circuits.

I believe if the work was done on a T & M basis the cost would be lower since I had to assume some

worst case scenarios in working up a price. It would also be helpful if there was an end result plan for the

future use of building to see if all the items coming out would actually need to go back.

Please call if you have any questions concerning this pricing. (910) 483-4193.

Sincerely,

WATSON ELECTRICAL CONSTRUCTION COMPANY LLC

Buddy Henderson

Division Manager

Fayetteville Division

Grocery Store #123

Page 37: Sample Report - Grocery Store

Grocery Store #123

Sample Report

www.constructman.com

Thank you for taking the time to review this sample report. We hope this was helpful to demonstrate how beneficial our services can be to you in your construction claims cases. Please contact us about a consultation at the address below.