rwa, 8/12/2006 present preliminary production plan all still preliminary, as we are re-establishing...
TRANSCRIPT
Present Preliminary Production Plan
• All still preliminary, as we are re-establishing production.
• January 9th,2007:
– Delivery of 2 ring collimators.
– Installation in IR6 at beginning of February.
• January 2007:
– Delivery of another 4 ring collimators.
– Series production established.
• April 2007:
– Completion of in total 28 collimators (minimal system).
• May-November 2007:
– Production of 71 missing phase 1 collimators.
– Required rate is ~10/collimators per month challenging at CERN for final assembly on supports.
– Goal: Last phase 1 collimator is installation-ready by December 2007.
• December 2007 – February 2008:
– Production of 19 spare collimators for phase 1
Summary Production Plan Minimal System(Preliminary)
Delivery date Number of collimators (ring)
Installation readiness
Total Destination
09 Jan 2007 2 08 Feb 2007 2 6L (1), 6R (1)
16 Jan 2007 2 16 Feb 2007 4 3R (2)
24 Jan 2007 2 28 Feb 2007 6 3R (2)
06 Feb 2007 4 15 Mar 2007 10 3R (1), 3L (3)
22 Feb 2007 4 03 Apr 2007 14 3L (2), 7R (2)
21 Mar 2007 1 17 Apr 2007 15 7R (1)
28 Mar 2007 3 01 May 2007 18 7R (3)
04 Apr 2007 4 15 May 2007 22 7R (2), 7L (2)
12 Apr 2007 4 29 May 2007 26 7L (4)
20 Apr 2007 4 12 Jun 2007 30 7L (2)
Note: Significant work at CERN must be performed for delivered collimator: reception tests, mounting of motors and sensors, mounting on collimator support with correct orientation (upper quick-plugin ), final bake-out, internal transport.
Installation
• Preliminary dates for installation, as agreed with installation (Dec 7th):
LSS Number of installed collimators
Ready for installation (last collimator)
Final deadline (start bakeout)
6L 1 08/02/0708/02/07 19/02/07
6R 1 08/02/0708/02/07 19/02/07
3R 5 15/03/0715/03/07 14/04/07
3L 5 03/04/0703/04/07 20/04/07
7R 8 15/05/0715/05/07 13/06/07
7L 8 12/06/0712/06/07 25/06/07
1L 0 x 30/10/06
5L 0 x 27/11/06
5R 0 x 23/04/07
2R 0 x 21/05/07
2L 3? x 09/07/07
1R 3? x 06/08/07