rut-resistant composite · pavement, and the overall pavement performance. conclusions the...
TRANSCRIPT
Report No. COOT -DTD-R-91-4
RUT-RESISTANT COMPOSITE PAVEMENT DESIGN
Donna S. Harmelink
Colorado Department of Transportation
4201 East Arkansas Avenue Denver. Colorado 80222
Final Report
July 1991
Prepared in cooperation with the
U.S. Department of Transportation Federal Highway Administration
The contents of this report reflect the views of
the author who is responsible for the facts and
the accuracy of the data presented herein. The
contents do not necessarily reflect the official
views of the Colorado Department of Transportation
or the Federal Highway Administration. This report
does not constitute a standard, specification, or
regulation.
i
Technical Report Documentation Page
1. Report No. CDOT-DTD-R-91-4
2. Government Accession No. 3. Recipient's Catalog No.
4. Title and Subtitle Rut-Resistant Composite Pavement Design
5. Report Date July, 1991
7. Author(s) Donna S. Harmelink
9.Performing Organization Name and Address Colorado Department of Transportation 4201 E. Arkansas Avenue Denver, Colorado 80222
12. Sponsoring Agency Name and Address Colorado Department of Transportation 4201 E. Arkansas Avenue Denver, Colorado 80222
15. Supplem~ntary Notes
6. Performing Organization Code HPR A/1465A/11.065
8.Performing Organization Rpt.No. CDOH-DTD-R-91-4
10. YOik Unit No.(TRA!S)
11. Contract or Grant No.
13.Type of Rpt.and Period Covered Final Report
14. sponsoring Agency Code
Prepared in cooperation with the U.S. Department of Transportation, Federal Highway Administration
16. Abstract
The main objective of this study was to evaluate the ability of a new asphalt composite pavement design to economically reduce rutting on asphalt pavements. In addition~ the longevity of the pavement was to be assessed by determining the durability and permeability of the seal, its resistance to moisture damage in the lower layers of the pavement, and the overall pavement performance.
Conclusions The performance data does not support the use of the rut-resistant
composite pavement design. Although there were only a few failures due to stripping, the extent of the failures were significant enough to warrant discontinuing the rut-resistant composite pavement design.
The failure mechanism in the RRCP was not due to rutting or ~racking, but appears to be directly associated with stripping caused by hydrostatic pressure immediately below the PMSC layer. The conditions which are present when stripping occurs are heavy traffic, high temperatures, and the presence of moisture.
17. Key Yords Plant mixed seal coat, PMSC, Composite pavement, permeability, rut-resistant
18. Distribution Statement No Restrictions: This report is is available to the public through the National Information Service, Springfield, Virginia 22161
19. Security Classif. (of this report) 20. Security Classif.(of this page) 21. No. of Pages 115
22. Price Unclassified Unclassified
i i
TABLE OF CONTENTS
Page
section Number
I. Introduction ................................... 1
II. Objective ...................................... 2
III. site Selection ................................. 2
IV. Pre-Construction Evaluation criteria ........... 4
V. Construction -- ~eneral ........................ 5
VI. Post-Construction Evaluation -- Summaries ..... l0
VII. Conclusions ................................... 22
VIII. Implementation ................................ 23
Figure
Number
1
2
3
4
LIST OF FIGURES
Title
Page
Number
site Location Map .................. . ........... 3
Project/Environmental Information For:
C470, Between Kipling and Wadsworth ........... 19
C470, U8285 to 1-70 ........................... 20
1-70, East of Agate ........................... 21
LIST OF TABLES
Table Page
Number Number
A Rut Resistant Pavement Construction Data . .... 8-9
iii
APPENDICES
Appendix A •.•••••••• Mix Design Specifications
Appendix B •••••••••• Permeability Tests
Construction Information For:
Appendix C •••....••• C470, Between Kipling and Wadsworth
Appendix D .•.•....•. I-76, Between Tennyson and Lowell
Appendix E ..•.••••.. C470, Between US 285 and I-70
Appendix F ...•..••.. US 6, West of Holyoke
Appendix G ....•••••• SH 125, willow Creek Pass
Appendix H .......••. I-70, East of Agate
Appendix I .••••••••• US 50, East of Rocky Ford
Appendix J •••••••••• I-70, East of Debeque
Appendix K •.••...... US 40, East of Hayden
Appendix L ••.•..•... SH 172, South of Durango
iv
I. INTRODUCTION
Historically, the design of asphalt pavements has
been a balance between the needs of pavement stability and
durability. Recently, many Colorado asphalt pavements
have experienced an increase in rutting early in the life
of the pavement. Rutting is caused by a number of
factors. However, with the increase in truck loads and
higher tire pressures rutting appears to be more
prevalent. The magnitude of rutting has contributed to
the premature loss of pavement service and has shifted
design priorities to a more rut-resistant pavement.
In 1987, the Division of Highways revised its asphalt
pavement design to help reduce rutting on Colorado's
pavements. The essence of this design was a high
stability asphaltic mix in the lower layers and a durable
plant mixed seal coat (PMSC) for the top layer.
The stability in the lower layers was increased by
reducing the asphalt content of the design mix. However,
this reduction in the asphalt content was expected to
reduce the durability of the resulting pavement. A plant
mixed seal used for the top layer was expected to
compensate for the reduced durability by preventing the
intrusion of moisture and air into the lower layers.
Together these layers formed an asphalt composite pavement
that was intended to produce a high stability pavement
with a highly durable wearing surface.
1
II. OBJECTIVE
The main objective of the Rut-Resistant Composite
Pavement (RRCP) study was to evaluate the ability of the
new design to economically reduce rutting on asphalt
pavements. In addition, the longevity of the pavement was
to be assessed by determining the durability and
permeability of the seal coat, its resistance to moisture
damage in the lower layers of the pavement, and the
overall pavement performance.
III. SITE SELECTION
In 1987, the Colorado Division of Highways began
incorporating this new asphalt pavement design into all
new construction and rehabilitation projects when the item
quantity for hot bituminous pavement (HBP) was greater
than 1000 tons.
Of the 188 projects constructed with a PMSC between
July 1987 and July 1989 a total of ten sites were selected
for evaluation:
1. C470, between Kipling and Wadsworth, 2 . I-76, between Tennyson and Lowell, 3. C470, between US 285 and I-70, 4. US 6, west of Holyoke, 5. SH 125, willow Creek Pass, 6. I-70, east of Agate, 7. US 50, east of Rocky Ford, 8. I-70, east of Debeque, 9. US 40, east of Hayden, and
10. SH 172, south of Durango.
These sites were selected based on traffic volume and
the different climatic regions in Colorado. sites 1, 2
and 3 are located in Metro Denver. The location of the
sites selected for evaluation are shown in Figure 1.
2
I, I' d II i ~
il , " ; 1
Ii I
J I
M
I':LI ~ ..... ..... CJ
." H :z ~
HVJ.n
3
IE ,.. :z;
J 101 UI
>-. \01 ...,j
!!II c
! ~
~
~ ~ ai :c~ 1)". ....
i I I i i -,-.., ~
,'= i
, -'x 1101
;II
~ 101 :z;
IV. PRE-CONSTRUCTION EVALUATION CRITERIA
For all the sites, excluding new construction and the
site at Agate, pre-construction evaluations were performed
prior to paving. These evaluations included deflection
measurements (Dynaflect), rut depth measurements (six-foot
straight edge), crack mapping and visual observations.
The deflection measurements were taken every 50 feet in
the right wheel path of the driving lane. At most
locations, the rut depth measurements were taken every 50
feet in both the right and left wheel paths of the driving
and passing lanes. On most sites, crack maps were drawn
for the entire length of the test and control sections
except on severely cracked sites. At the severely cracked
sites crack maps were drawn only on the first 100 feet of
the evaluation section. The evaluation sections were 500
to 600 feet long.
The deflection measurements taken during the pre
construction evaluations were used as a baseline and
compared to subsequent evaluations.
During the pre-construction evaluation the location
of the test and control sections were established. The
test section contained the new high-stability design. The
control section contained the design mix used prior to the
incorporation of the new design with PMSC. Asphalt mix
specification for the control and test sections which were
used during the period from July 1987 through July 1989
are found in Appendix A.
Since paving with the RRCP design had begun prior to
approval of this study, two evaluation sites constructed
in the summer of 1987 did not contain control sections
(C470, between Kipling and Wadsworth and I-76, between
Tennyson and Lowell.)
4
v. CONSTRUCTION -- GENERAL
As part of the six-year study into the performance of
the department's asphalt composite pavement design, the
Research Branch developed two tests to evaluate the
permeability of the plant mixed seal coat (PMSC). The two
test methods are described in Appendix B.
During construction, permeability testing equipment
was installed at four of the ten evaluation locations.
Data acquisition equipment (Microloggers) was installed at
some of the locations to continuously record moisture
values. At the remaining locations permeability testing
was only done during the yearly evaluations.
Conventional construction techniques were used in
the placement of the rut-resistant composite pavement.
Photos 1 through 3 illustrates an asphalt paving
operation. A description of each project is found in
Appendices C through L at the back of this report. Also
included in each Appendix is a site map showing the
location of the test and control section at each location.
Table A contains the construction data for each individual
evaluation sites.
5
•
6
PHOTO 1
A paving operation
using windrow
placement.
PHOTO 2
steel-wheeled
roller used for
break down.
7
PHOTO 3
Pneumatic roller
was used prior to finish roller.
TABLE A
Rut Resistant Pavement Construction Data
TEST SECTION CONTROL SECTION
Site Construction Permeabli l ty HBP Design Actual Grade** HBP Design Actual ~ District Dates ~ Thickness %AC %AC ~ Thickness %AC roAC
6 SUllll1er 1987 No 3" 1ST 5.50 5.69 Gr E NO CONTROL SECTION FOR 3" 2nd 5.50 " THIS PROJECT 2" 3rd 5.10 5.34 " 1-1/4" 4th 5.40 5.36 " 3/4" PMSC 7.20 7.26 Type A*
2 6 SUllll1er 1987 No 3" 1st 5.20 4.63 Gr E NO CONTROL SECTION FOR 2" 2nd 5.20 4.51 " THIS PROJECT 2" 3rd 5.20 " 1-1/2" 4th 5.20 "
00 3/4" PMSC 6.60 Type B*
3 6 6/01/88 Yes 9/13/88 3-3/4" 1st 5.00 Gr E 3-3/4" 1st 5.00
3" 2nd 5.00 " 3" 2nd 5.00 2" 3rd 5.00 5.18 " 2" 3rd 5.20 4.98 1-1/4" 4th 5.00 " 1-3/4" 4th 5.20 4.75 3/4" PMSC 6.80 6.07 Type A*
4 4 7/13/88 No 1-1/4" 5.80 6.14 Gr F I 2" 5.70 6.07 3/4" PMSC 6.50 Type A*
5 3 7/25/88 Yes 1-3/4" 5.40 5.49 Gr E 2-1/4" 6.40 6.21 10/22/88 3/4" PMSC 6.30 Type B*
roAC values are unavailable * Rubberized ** Grading specifications are in Appendix A
Site
!!2..:.
6
7
8
9 I.D
10
TABLE A (Cont.)
Rut Resistant Pavement Construction Data
Construction Permeablilty District Dates Test
Summer 1989 No
2 8/15/88 Yes 10/15/88
3 Spring 1989 No
3 Summer 1989 Yes
5 Summer 1989 No
%AC values are unavailable * Rubberized
TEST SECTION
HBP Design Thickness %AC
1-1/2" 5.50 3/4" PMSC 6_20
1·1/2" 6.00 3/4" PMSC 6.00
1-3/4" 5.30 3/4" PMSC
1" 5.30 3/4" PMSC 6.00
1-1/4" 5.90 3/4" PMSC 6.10
** Gradation specifications are in Appendix A
Actual %AC
6.22
4.92
5.04 6.06
5.75 5. 49
Grade **
~
Gr C* Type B*
Gr EX Type B*
Gr E Type B*
Gr E Type B*
Gr E* Type B*
Gr E
CONTROL SECTION
HBP Thickness
2"
2-1/2"
1-3/4"
2-1/4" Northbound Lane 2-1/4" Southbound Lane
Design %AC
6.10
5.50
5.50
5.90
5.90
Actual %AC
6.32
5.51
5.06
5.85
VI. POST-CONSTRUCTION EVALUATION -- SUMMARIES
The first post-construction evaluation was made
immediately following construction. This evaluation
included deflection measurements, rut depth measurements,
core sampling, permeability tests (when applicable), and
visual observations.
After this initial evaluation, follow-up evaluations
were made each spring and fall. Deflections, rutting,
cracking, permeability tests and visual observations were
made in the spring and the cores and additional rutting
measurements were taken in the fall. Beginning in 1990,
the fall evaluations were limited to only rutting and
visual observations. The final evaluation was made in the
spring 1991.
Deflections
Based on the analysis of the deflection data, there
is no significant difference in the load carrying capacity
of the high stability design test section as compared to
the control section. Comparison of the deflection basin
graphs for the test and control sections indicate little
change in the maximum deflections or the load transfer
properties from year to year.
Deflection basin graphs for each evaluation site can
be ' found in the Appendix for each location.
10
Rutting
To date , there is no appreciable rutting in any of
the original rut-resistant pavement design evaluation
sections. There does not appear to be any difference in
the rut measurements between the control and test section.
All the rutting measurements have been in the low severity
range (less than 0.25 of an inch).l
Individual rutting data is located in the Appendix
for each site.
The Agate site is not one of the original evaluation
sections. This site was unique from all the other sites
being evaluated under this study. This site was added
prior to the reconstruction of a RRCP paving project which
failed nine months after construction. It failed due to
severe stripping in the layer immediately below the PMSC.
Since this site was not added to this study until after
the RRCP showed signs of failure , rutting information
found at this location was not included in the rutting
evaluation. The reconstruction project was not a RRCP
design and only a 1000 foot section of the reconstructed
project contained a PMSC. The PMSC section was added for
PMSC performance evaluation purposes only. In the fall of
1990, several months after resurfacing this project for a
second time, the pavement began to show signs of stripping
immediately below the PMSC and it was milled off. The
evaluation at this location was discontinued when the PMSC
was milled off.
11
Cracking
Cracking does not appear to be a significant problem
at any of the evaluation sections. Al l of the projects
containing both a test and control section indicated that
the PMSC reduced surface cracking to some degree.
Individual cracking data summaries are located in the
Appendix for each evaluation site.
Cores
Cores were taken yearly in each evaluation section
and visually inspected for stripping.
At most of the evaluation sites the cores showed
signs of stripping progressing from year to year in the
layer immediately below the PMSC, some sites more severe
than others. A comparison of a core taken in 1990 at the
Debeque location to a core taken in 1991 at the same
location is shown in Photo 4. The core in Photo 5 was
taken from C470 in 1990.
It should be noted that all RRCP projects which have
failed due to stripping had Tensile strength Ratios (TSR)
values meeting or exceeding specifications. Lottman test
values (TSR) as determined by the Department ' s procedures
is not always a good predictor of stripping for lifts
placed immediately below a PMSC. See Appendix A for
Colorado's Lottman procedure.
Permeability Testing
During construction, wires and probes for
permeability testing were placed in both the test and
control sections on a number of selected projects. The
wires were placed between each lift to record the
difference in the moisture readings at each lift. It was
hoped the readings would help determine if moisture was
12
present and if so where it was coming from. Cores taken
at these permeability locations revealed that the PMSC was
permeable and the pavement showed early signs of stripping
in the lift immediately below the PMSC. The presence of
moisture in the cores was in agreement with the data
collected from the permeability equipment installed at the
evaluation locations. Since it had been determined PMSCs
were permeable, permeability testing was discontinued
following a study panel meeting in January 1990.
Visual Observations
Post-construction evaluations also consisted of a
visual observation of the entire project. The type of
stripping failure which this design experienced was
usually noticeable during this evaluation. Typically, the
first visual sign of failure was the appearance of rich
spots on the surface. This failure did not always show up
on the surface of the study evaluation sections. When
cores were drilled in or around these areas, stripping was
found between the PMSC layer and the layer immediately
below the PMSC. As the rich spots spread the magnitude of
stripping increased resulting in severe distress on the
roadway. If failures appeared anywhere within the
project, it was a good indication that cores taken in the
study areas would show the beginning of stripping.
Photos 6 through 10 show examples of the failures on
the C470, between US 285 and I-70 and on the I-70, east of
Agate locations. Photo 9 taken on I-70, east of Agate was
taken before this site was added to this study. Photo 10
was taken after the rehabilitation of the RRCP. This
pavement was not a high-stability (RRCP) design.
13
The final evaluation at the Debeque site showed no
signs of failure on the surface, rutting was low and
cracking was minimal. However, the cores showed signs of
stripping in the layer immediately below the PMSC as shown
in Photo 4.
Three variables which are common to the projects
which failed during this study (and other projects which
have failed around the state) are: the presence of
moisture, high temperature and heavy traffic. All the
failed projects have high rainfall (greater that 3 inches
in a month). All the projects were in high temperature
areas (above 850 F average highs). The high temperature
times usually corresponded with the high moisture times.
It appeared that the volume of traffic controls the
magnitude of stripping. As the traffic volume increases
the time to failure decreases.
Moisture, temperature, traffic and pavement
information for the projects showing failures included in
this study are shown in Figures 2 through 4.
14
15
PHOTO 4
This photo shows
how stripping
progresses. The
core on the left
taken in 1990. The
core on the right
• taken in 1991 at the Debeque
evaluation site.
Note that the top
lift of PMSC is
undisturbed.
PHOTO 5
This photo shows an
extreme case of
stripping below the PMSC. Both __ cor~e~s=-______ __
were taken out of
C470 in 1990.
16
PHOTO 6
C470, US 285 to I-70
The first sign of
the stripping
failure is the
appearance of rich
spots on the
surface. These
rich areas are
randomly spaced and
typically found in
the wheel paths.
PHOTO 7
C470, US 285 to I-70
This photo shows
areas which have
stripped under the
PMSC. Evidence of
raveling in the
right wheel path is
a result of
extensive stripping
in the RRCP layer
below the PMSC.
17
PHOTO 8
C470, US 285 to 1-70
This type of
distress was found
throughout the
project.
PHOTO 9
This photo was
taken on 1-70, east
of Agate eight
months after
construction using
the RRCP design.
This type of
distress was
typical throughout
the project .
18
PHOTO 10
This is not the
high-stability
(RRCP) design. This photo shows
stripping occurring
below the PMSC
however. The
portion stripping
is a Grading C.
This photo was
taken at the test
site on 170, east
of Agate. The
pavement had been down one year.
FIGURE 2
Project/Environmental · Information C470, Between Kipling and Wadsworth
District: 6 project: IXFU 470-1(54) Loca tion: C.4 70, Between Kipling and Wadsworth
HBP Inforr.tation P:'!SC Infor.7lation Grading: E Type: A % AC: 5. 1
* Lottmans: 104, 90, 102, 126, 108, l13~ lOOf 114. 126, 127, 117
Design Traffic ~o year ESAL IS: 1,565,000 * See Appendix A
Environmental Information
Precipitation .~lnC~h~e,~ ______ ~ ____________________ ,
~~------------~---=~------~=-~
2~----------~~--__ ~------~~~
• ~ nUl z ~ • I I r I I ~ U U t 2 ~ • I I I II 1 I. I 10 I
TIme
Temperature f.h,.." .. ~1t
ICO;":. :.;;;..:,.;~------------------------.\ .o~-------------4~-----------~~ ~~I ~ ____ ~ .. ~~~ ____ ~.
0'10 n: 1 z ~. 5 S T S' 10 11".% 1 % :s" s ~ I 18 I 8:1 I 10 I
Time
Pro;ect Status High.·~oisture, Low moisture susceptibility , moderate traffic
19
FIGURE 3
Project/Environmental Information C470, US285 tOI-70
District: 6 Prcj ect: 1XFU 470-1 (32) Location: C470, US285 to 1-70
RBP Information Grading: E
P!-!SC In fO!T.Ia ticn Type: A
% AC: 5.2% * Lottmans: 111, 101, SS, 77, 56, 61, 68, 77, 98, 96, 88, 42, 74, 56
Design Traffic 10 year ESAL IS: 1 565 000 , , Environmental Information
Precipitation Inch .. . ~----------~------------------~ 3~------------~--~~------~~~
2~----------__ ~--~~------~~~
• ~ n U 1 234 • • '7 • • ~ " ~ 1 2 ~ 4 • •
I " I " I ~ I Time
Temperature , ..... "".11
100 I 'Ol~------------~~------------~~
~~ __ ------~~~~~~~----__ ~w.
project status
O~~UL.u~ua~~~~~~~----~
'~n:' z ~ ... 5 S '7 S llOtll:1 234 $ ~ I .. I u I 110 I
Time
* See Appendix A
High .. ~oisture, high moisture susceptibility, mocerate traffic
strip~inq noticed in mid 1989 and increased in 1990.
20
District: 1
FIGURE 4
Project/Environmental Information 1-70, East of Agate
Project: IR 70-4(118) Location: 1-70, East of Agate
HBP Information Grading: C % AC: 5.3%
PMSC Information Type : B
* Lottmans: 102, 80, 92, 78, 64
Design Traffic * See Appendix A 10 year ESAL's: 3,500,000
Environmental Information
Precipitation 3~ln=Ch~e.~ __________________________ --.
~&~------------------------~~--
• I ~ n ~ 1 2 a 4 I • 7 •
.. " TIme
Temperatur-e 'OOF~.~hN~n~he~it __________________________ ~
80
Project status
811On121 88
TIme
High moisture, moderate moisture susceptibility, high traffic
Failed in 7-89
21
VII. CONCLUSIONS
The rut-resistant design, in general, has performed
well; however, because of several catastrophic failures
the use of this design was suspended. Out of the 188
projects constructed with a plant mixed seal coat, four
projects have completely failed within one year of
construction. In addition, two projects are showing signs
of failure.
Evaluations from data collected indicates the failure
mechanism is not due to rutting or cracking, but appears
to be directly associated with stripping caused by
hydrostatic pressure immediately below the PMSC layer.
Once the stripping process becomes visible on the surface
the pavement fails rapidly. The pavement fails early in
its design life before signs of rutting or cracking
appear. As the stripping becomes more severe the pavement
begins to rut and shove.
Since the rut-resistant composite pavement design was
initiated in July 1987, approximately 824 center-line
miles were paved with a plant mixed seal coat. However,
not all of these projects contained the high-stability
design in the lower lifts. Of the ten evaluation sites
selected to evaluate the rut-resistant composite pavement
design three have shown signs of stripping .
. The remaining sites have not shown signs of distress
and are performing as expected. These sites may never
fail because the condition that triggers the stripping
includes the combination of heavy traffic, high
temperatures and the presence o f moisture.
22
VIII. IMPLEMENTATION
Although there were only a few failures due to
stripping, the extent of the failures were significant
enough to warrant discontinuing the rut-resistant
composite pavement design.
In those projects without premature failures
performance data does not support the RRCP (rut-resistant
composite pavement) design as being significantly supe~ior
to the design used in the control sections.
After continued performance evaluation of the
existing PMSC projects the use of plant mixed seal coats
on new pavements was suspended entirely during the 1990
paving season.
Numerous changes to the flexible pavement design
criteria have been made since suspending the use of the
rut-resistant composite pavement design which include:
1. designs are based on optimum AC content 2. VMA requirements for the various grades 3. minimum film thickness 4. minimum 1% hydrated lime added to aggregates 5. limited natural fines in mix to 20%
Even though the design used by Colorado did not
produce the results hoped for, the use of Open Graded
Friction Courses (OGFC) have been successful in other
states. 3 The major difference between OGFCs and PMSCs is
that the PMSCs have a higher percent fines which has a
tendency to retain moisture in the pavement thus promoting
strippin.g. The concept of OGFC has merit and several
benefits such as a smoother ride, less tire noise, higher
skid resistance and better appearance can be achieved.
23
This report finalizes the formal evaluation of the
RRCP study. However, RRCP locations will be monitored
informally on individual basis to determine if future
research is needed with respect to rehabilitation,
corrective action, etc.
24
REFERENCES
1. Roadway Design Manual, Colorado Department of Highways, 1990.
2. Acceptance of Materials, FHWA Technical Advisory T 5080.11, April 6, 1989.
3. Chip Seals. Friction Courses. and Asnhalt Pavement Rutting 1990, No. 1259 Materials and Construction, Transportation Research board, National Research Council, Washington, D.C., 1990.
25
APPENDIX A
Mix Design Specifications
A-I
MIX DESIGN SPECIFICATIONS
Minimum Asphalt Content
With without Seal Coat Seal Coat
1" maximum size (Grading "F") 3/4" maximum size (Grading "E" and 1/2" maximum size (Grading "EX")
"C")
Air Void criteria
5.5% 6.0% 5.2% 5.5% 5.4% 5.8%
The air void criteria for all lower layers and all gradings will be 4-8%. The air void criteria for the top layer, if a seal coat is not used, is 3-4%. For Grading "F" it should be 4-8%.
Moisture Damage criteria When aspahlt film thickness is reduced, durability is also reduced. This will affect the Lottman test results, so we are lowering the Lottman criteria from 70 to 60. Use the following table for moisture damage criteria.
TABLE I
1" maximum size (Grading "F" IRS = 70
3/4" and 1/2" maximum size (Grading "E", "EX" & "C") Lottman = 60
If a seal coat is not used, the Lottman value for top layer of Grading "E", "EX" & "c" must be 70.
Type of Seal Coat
The top layer of pavement used with this design will normally be Plant Mixed Seal Coat. On low volume roads, a chip seal surface can be substituted for the PMSC. The thickness of the seal coat will normally be 3/4". Use the following table to select the proper type of PMSC.
Table II
20 Year 18K ESAL < 5,000,000 > 5,000,000
A-2
PMSC Type "A" "B"
Sieve Size of Designation
1/2" 3/8" #4 #8 #50 #200
Sieve Size of Designation
1" 3/4" 1/2 " 3/8" #4 #8 #50 #200
Gradation criteria - PMSC
Percentage by Weight Passing Square Mesh Sieves
Type A 100
90-100 32-48 8-20
3-7
Type B 100
90-100 46-62 27-39
5-17 3-7
Gradation criteria - HBP
Gr C
100 70-95 60-88 44-72 30-58
7-27 3-12
Percentage by Weight Passing Square Mesh Sieves
Gr E Gr EX Gr F 100
100 100
44-72 50-78 30-58 34-60 45-85
3-12 3-12 5-15
All mix design criteria for RRCP and standard HBP are
the same except for % asphalt content. Gr F pavements did
not utilize the low % AC mix design.
A-3
Colorado Procedure L-5109
Method of Test for
EFFECT OF WATER-RELATED CONDITIONING ON INDIRECT TENSILE PROPERTIES OF
COMPACTED BITUMINOUS MIXTURES (TSR) (Lottman)
SCOPE
1.1 This method covers measurement of the change of diametral tensile strength resulting from the effects of saturation and accelerated water conditioning of compacted bituminous mixtures. Internal water pressures in the mixtures are produced by vacuum saturation followed by a freeze and warm water soaking cycle. Numerical indices of retained indirect tensile properties are obtained by comparing the retained indirect tensile properties of saturated and accelerated water conditioned laboratory specimens wi th the similar properties of dry (unconditioned) specimens.
APPARATUS
2.1 Water baths of sufficient size to permit total immersion of the specimens, automatically controlled, and capable of accurate and uniform control of immersion temperatures of 770±1. 8 F and 1400
±1 .8 F. Baths shall be lined with non-reactive material. Water used in baths may be tap water or potable water.
2.2 Freezer, automatically controlled, capable of maintaining
A-4
temperature of 00±3. 6 F, and of sufficient size to permit total containment of specimens.
2.3 Vacuum pump with capacity to pull at least 26 inches of mercury, with accessories including vacuum jars at least 6 inches in diameter and 8 inches high; rubber gaskets, stiff metal plates greater than 6 inches by 6 inches in size, with hose fitting and suitable vacuum hose.
2.4 Testing machine capable of steady head speed of 0.2 inch per minute.
2.5 Balance having sufficient capacity, accurate to 0.1 gram, with suspension apparatus and container overflow device, similar to that specified in AASHTO T 166 for bulk specific gravity.
2.6 Plastic sheeting and heavy duty leak-proof plastic bags.
2.7 Cabinet, thermostatically controlled, capable of maintaining a temperature of 77 0±1.8 F.
COMPACTION OF TEST SPECIMENS
3.1 Make at least four specimens for each test using the same
aggregate, the same asphal t source and grade (plus additive, if specified) at optimum AC Content that are anticip,ated to be used on a specific project in the field. Specimen size is 4 inches in diameter by 2.5 inches high. Mold the specimens according to CP L-5105.
PROCEDURE
4.1 Determine bulk specific gravity of specimens according to AASHTO T 166.
4.2 Select one pair of specimens to vacuum saturate, placing the other pair in the cabinet at 77° F.
4.3 Vacuum saturate the remaining specimens as follows: Place each specimen in a vacuum jar with flat surfaces vertical. Add 77 0 F water to the jar to approximately 1 inch above the upper surface of the specimen. Dampen gasket on vacuum cover and place on top of the jar. Attach hose to vacuum pump and fitting on vacuum cover. Apply a vacuum of 26 inches of mercury to the jar for a period of 30 minutes while occasionally agi tating the jar gently. Remove vacuum and leave the specimen submerged in the jar for an additional 30 minutes.
4.4 Remove specimen from vacuum jar, and weigh submerged in room temperature water. After weighing, immediately wrap in plastic sheeting for freez ing or resubmerge the specimen for later wrapping.
4.5 Calculate the bulk density and the permeable voids as follows:
Bulk density = A/B-C Percent Permeable voids = 100 (BA)/B-C
Where: A = weight of dry specimen in air B = Weight of surface-dry (blot
ted) vacuum saturated specl men in air
C = Weight of vacuum saturated specimen in water
All weights are accurate to 0.1 grams.
ACCELERATED CONDITIONING PROCEDURE
5.1 Maintaining surface dampness and internal saturation, wrap the specimen tightly with two layers of plastic sheeting, using masking tape to secure the wrapping if necessary. Place wrapped specimen into a leak-proof plastic bag and seal the bag with a tie wire.
5.2 Place each individually wrapped and bagged specimen in a freezer for a period of 16 hours at 00±3.6 F.
5.3 Remove specimen from freezer. Carefully remove bag and wrapping and immediately immerse the specimen in the water bath at 1400±3.6 F for 24 hours.
5.4 carefully remove specimen from 1400 F bath and immerse in water bath at 77 0 +F for two hours, minimum.
A-5
DIAMETRAL TENSILE STRENGTH PROCE
DURE
6. 1 Remove a specimen from the water bath, surface dry by blotting with a towel. Place the specimen, with the flat surfaces vertical (on edge without support blocks or loading strip) under the flat head of the compression testing machine. Test one specimen at a time. Proceed with testing as rapidly as possible because the test procedure will expose the specimen to ambient air temperature which may be different than the test temperature.
6.2 Load the specimen at a steady vertical deformation rate of 0.2 inch per minute. Record the maximum compressive load. Immediately decrease the load to zero, remove specimen, and measure specimen edge on a flattened side to the nearest 0.1 inch. Accomplish this by stroking the top flattened edge (side) with a piece of chalk held lengthwise and horizontally to delineate the flattened width. Measure and average the width of both flattened edges. Record this measurement.
6.3 Repeat the procedure using the dry (unconditioned) specimens.
CALCULATIONS
7.1 Calculate specimen diametral strength as follows:
Where: St = Diametral tensile strength,
psi S10 = Maximum tensile stress, psi,
determined by calculating: S10 = 1658 - [(a + 0.7)a X 150]
Where: a = flattened width, in inches, based on a 4 inch diameter specimen loaded at 10,000 lb. per inch of thickness. P = Maximum compressive load on specimen, lbs. 10,000 = Load constant: 10,000 lb. per inch of thickness. L = Thickness of specimen, inches.
7.2 Calculate the numerical indices of the effects of vacuum saturation and accelerated conditioning as the ratios of the mechanical properties of the conditioned specimen to the mechanical properties of the unconditioned specimen as follows:
Where: TSR = Retained diametral tensile strength expressed as a percentage. StC = Diametral tensile strength of specimen conditioned by freezing. StD = Diametral tensile strength of unconditioned specimen.
7.3 Tensile Strength Rations may be interpreted as being related to long-term pavement performance (approximately eight years). Low ratios are associated with the inability of the compacted mixture to resist the effects of moisture.
A-6
APPENDIX B
Permeability Tests
B-1
As part of the six-year study into the performance of
the department's asphalt composite pavement design, the
Research Branch developed two methods of evaluating the
permeability of the plant mixed seal coats (PMSC).
The first method consisted of a two-conductor 16
gauge wire. Approximately 1/2 inch of insulation was
stripped off each conductor and the wire ends were spread
to about 1/4 inch spacing. A sponge measuring 1/2" x 3/4"
x 3/8" thick was placed on the bare wire ends. The
purpose of the sponge was twofold: it prevented the two
wire ends from touching each other and it distributed
moisture evenly around the probe ends.
During construction a groove was cut into the lower
lifts to facilitate the placement of the lead wires, as
well as the probe's end. The sponge end was placed in the
right wheel path of the driving lane under each lift. The
wire was then extended to the edge of the pavement to be
used later to measure resistance. The wire was tacked
down to prevent it from being pulled up during paving.
The procedure for measuring permeability was to
connect the probe wire to a volt-ohm-meter (VOM) which
would measure the change of resistance due to presence of
water. Water was placed on the pavement at the location
of the sensor. Traffic was allowed to travel over the
pavement to determine if water was forced into the
pavement under traffic during periods when the pavement is
wet.
Data acquisition equipment (Microloggers) was used at
some locations to record data over a period of time to
determine if the pavement was permeable and, if so, how
long the water stayed in the pavement.
B-2
The second method was a modification of a test that
has previously been used to test for water proofing of
bridge decks with membranes in Colorado.
In this' method, individual 16-gauge galvanized bare
wires were placed across the lanes beneath each lift. The
wires were tacked down at both ends and every few feet
with "U-shaped" staples to prevent damage or movement of
the wire during the paving process. Approximately one
foot of wire was left exposed at the edge of the pavement
to facilitate conduction of test equipment. The exposed
ends of the wires were buried to prevent disturbance of
the installation but were easily accessible during the
testing procedures.
To test this method, water was sprayed on the
pavement over the wire in several location across the
roadway. These locations are kept damp for approximately
20 minutes before testing. Soap is added to the water to
break down the surface tension making the penetration of
water faster. Testing was done using the bridge deck
membrane testing equipment (direct measurement of
resistance) .
B-3
TYPIC,L\L MOISTURE DETECTION INSTRUMENTATION LAYOUT
i cp o cb cp
6 (P o ,
Metho~ 1-)
? 1/ i I
2 ) A - ..
o Waier was S::Jr a'Jed ai these locations
to test the permeabl11t\:j.
Method 1: Probes extended into right
whee! path of driving lane,
Method 2 Wires extended full width. , -~- .... j -.~ ., ""'... .. . -- . ,-
....... .... .....
~-~ "J-' ¢:;~:4~~~~ _ .... '; :,- . ::~:~·:::~t;~·t~~· ......
. .-:'.: .. ;~-:-' ~.:-.,~:?'-. ~~.
......
. . . .. \-. . .
PMSC
High Stabi li t~ HBP
Existing Mat
• Genera 1 la~out used
in both methods,
Method 1 Probe placed
wi thin sponge,
Bridge Deck Membrane Testing Equipment (Used for Test Method 2)
B-4
APPENDIX C
Project Information
C470, Between Kipling and Wadsworth
C-l
C470 -- Between Kipling and Wadsworth
project No. IXFU 470-1(54), located between Wadsworth
and Ken Caryl on C470 in the southwestern part of the
city, was completed in the summer of 1987.
Since the paving process began before the study
proposal was approved a control section containing the old
mix design was not included on this project. However, a
test section was established to evaluate the new pavement
design. The test section was located between Wadsworth
and Kipling in the eastbound driving lane.
The original plans for this project required eight
inches of lime treated subgrade throughout the project.
However, on the portion between Kipling and Ken Caryl, the
subgrade contained a large quantity of rock and the lime
was deleted.
The typical section required the 9-1/2 inches of HBP
to be placed in four lifts. A 3/4 inch lift rubberized
PMSC Type A completed the paving process. The 500 foot
test section which will be evaluated during the study
period is located just east of the Kipling exit in the
eastbound lane in this portion of the project.
During construction no significant placement problems
were reported on this project.
C-2
() I
w
-II--
Rut Resistant Composi te Pavement C470 be-,ween Kipling and Wadswornl
600' Core holes 2' i
shou lder s tr ip
500' -r
4' 12' -~
-.- -12' -~ 10' ~~
Evaluation Section 400'
300' Sign in Median
200' / 100' ~
- 50'
MP 13,1 Begin T e5-'- Section
w U L
~coC) W w W D- I =
TI 2i :;1 61 61 6 ""- =n (') I--- ..----< I ('J I (') I (')
PI"oject i-~pica1
T est Sec-lion
I
All lifts AC-10F except PMSC
C 470 between KIPLING and WADSWORTH RUTfiN G - TEST SECTION
0.9
0.8
""' 0.7 fII ~ ~ u c 0.6 v
~ 0.5 w 0. w
~ 0.4
w ~ 0.3
0.2
0.1
0
,,- /r--~ ~ ~ ~ ~ ~ ~~~~ ~~- j ~ i\. ~ '" / r--~ ~ X ~ ~~~~ ~ ~ ~ !\. Ix' " ~~Ix''' j 10:: r-;% 'XJ".,. /
PLjLWP PLjRWP DLjLWP DLjRWP
LANE / WHEEL PATH
~ 5/17/88 ~ 12/13/88 ~ 6/27/89 1lQ(I6/1/90 rs:sJ 9/11/90 t22l5/9/91
New Construction
5/17/88 -- first spring evaluation following construction
C-4
+-' Q) Q) 4-
~
(\) (}) c
C 470 Kip/ ing to Wadsworth Cracking Data Test Section
1000 r-----------------------------------------~
800 r-----------------------------------------~
600
400
200
0 transverse
~ 6/89 post-const
New construction
~ 6/90 post-constr
c-s
longitudinal
~ 5/91 post-constr
C 470 BETWEEN KIPLING AND WADSWORTH DEFLECTION Bt-SIN - TEST SECTION
0
10
~
20
"...... 30 .!!!. E .,.... 4-0 0
8 (I) 50
~..., ,....-!;
~ .-"
~~ ~ -~ ~ .....
z 0 F
60 hl ...J. ~ u..L
70 0.
BO
90
100 o 2 3 4
DISTANCE FROM LOAD Cft)
o 9/B7 + 5/BB ¢ 6/B9 6. 6/90 X 5/91
New construction
9/87 -- evaluation immediately following construction
C-6
APPENDIX D
Project Information
I-76, Between Tennyson and Lowell
D-1
1-76, Between Tennyson and Lowell
Project No. 1R76-1(103), located between Sheridan
Blvd and Federal Blvd on 1-76 in northwest Denver, was
completed in the summer of 1987. The section which was
chosen for evaluation was between Tennyson and Lowell in
the eastbound lane.
Since the paving process began before the study
proposal was approved, a control section containing the
old mix design could not be included in this project.
The plans for this project called for 8 inches of
lime-treated sub grade , 8-1/2 inches of HBP and 3/4 inches
of rubberized PMSC Type B. During construction
difficulties arose when placing the PMSC. During the
laydown of the 3/4 inch layer of PMSC the rubberized
asphalt became very tacky as it cooled. This made raking
the overlapping joints in tapered sections and on the
ramps difficult. By changing the asphalt cement from AC-
20R to AC-10 in the PMSC used in the tapered sections and
on the ramp, the contractor was able to create smoother
joints. On the mainline the laydown machine made a 24
foot wide pass. This wide pass in conjunction with the
quick cooling of the material required additional
attention in repairing tearing which was commonly found
behind the laydown machine.
The original evaluation section was set up in a
tapered section just west of the Federal Blvd exit.
However, after construction it was moved further west as
it was felt that a true rutting measurement could not be
made in a tapered section. The 600 foot test section is
located on the mainline in the eastbound lane between
Tennyson and Lowell.
D-2
o I
w
I
I
Rut Resis-iant Composi te Pavement I -76 bel-ween T enn\dson and Lowe 11
500' End Test
Section
- 400'
300'
<~ - 200'
-100'
50'
MP 3 Begin Test
Section
4' 12' 12' 10'
Evaluation Section
w u (J) L 2:: C)
CL ICO -('\j
~ I Q) ~ ~ Q~I ('):JJ f- ~I
w L
(')
('\)
w L
C)
('\)
w L
(')
(')
Pro jec-i t~pica 1 T est Section
All lifts AC-10F except PMSC
I 76 between TENNYSON and LOWELL RUTTIN G - TEST SECTION
0.9
0.8
,,-... 0.7 'II v ~ u c 0.6 0
~ 0.5 w Cl· w
~ 0.4
w ~ 0.3
0.2
0.1
0 PL/LWP PL/RWP DL/LWP DL/RWP
LANE / WHEEL PATH
~ 5/17/88 ~ 12/13/89 ~ 6/26/89 ~ 5/30/90 ISSJ 5/23/91
New Construction
5/17/88 -- first sprinq evaluation followinq construction
D-4
76 Tennyson to Lowell Cracking Data Test Section
1000
800 +-' ill ill 600 4-
L (IJ
400 ill c
200
0 transverse longitudinal
~ 5/88 ~ 6/89 ~ 5/90 E2Zl 5/91 post-const post-canst post-canst post-const
New Construction
5/88 -- first spring evaluation following construction
D-5
I 76 TENNYSON TO LOWELL DEFLECTION flt..SIN - TEST SECTION
0
10
20
....... 30 !!!. ~ E I!t ..- 40 0
8-III 50 z 0 F
60 ~ ...L IL... I.Ll
70 Cl
80
90
100 o 2 3
DATE
o 10/87 + 5/88 o 10/88 A 5/90 x 5/91
New Construction
10/87 -- evaluation immediately following construction
D-6
APPENDIX E
Project Information
C470, US 285 to 1-70
E-l
C470, US 285 to I-70
Paving began on this phase of C470 (Project No. IXFU
470-1(32) on June 1, 1988. The length of this project was
a little over 3 miles. The plans for this project called
for 8 inches of lime treated sub grade , 10 inches of HBP
and 3/4 inches of rubberized PMSC Type A for the entire
project except for a 1500 foot section located between
station 209+00 and 224+08 in the northbound lanes. This
section is located just north of the Morrison interchange.
This 1500 foot section consisted of 8 inches of lime
treated subgrade and 10.5 inches of HBP. This control
section did not include a PMSC and the design used for the
HBP was not intended to be the new high-stability design
mix.
The 10 inches of HBP was placed in four lifts: 3-3/4
inches, 3 inches, 2 inches and 1-1/4 inches, respectively.
The 10-1/2 inches of HBP was also placed in four lifts:
3-3/4 inches, 3 inches, 2 inches and 1-3/4 inches
respectively.
Originally, the plans called for two different AC
contents in the test and control designs. The AC content
in the control section was to be 5.2±0.3% and the
remainder of the project was to be 5.0±0.3%. However, the
district waived these requirements and allowed the
contractor to keep the AC content in the lower lifts the
same throughout the project and only increase the AC
content in the final lift on the control section. Two
lifts were placed before the research branch was notified
of the changes. At the request of the Research Branch the
AC content in the control section was returned to the
higher AC content. However, samples taken during
construction of the third lift indicated that the AC in
the driving lane of the control section was 4.98%. The AC
E-2
content in the third lift of the driving lane in the test
section was 5.18%. It was the intent of this study to
have the higher AC content in the control section.
Paving was completed on September 25, 1988. This
section of C470 was opened in November 1988.
Since construction, portions of this project have
failed due to stripping in the layer immediately below the
PMSC.
E-3
I:Ij , """
I
I
Rut Resistant Composite Pavement C470 between US 285 to 1-70
3
section
i e! Test probe area
367'
700'
Begin test section New high stabi 11 t~
design mix
End control section 120' 1-40' Test probe area
440'
Begin control section Old design mix
101 12' 121 4' ~-j- ~---I--~
~I I
Eva luation
w LlJ
L L C) C)
W W =
::::1 L L T C) C) ~
rl
.-I I 011 rll (Y)
Contr'o 1 section
-s--------Sec-rion
W W U L L (f) C)
Wi C) 2:::
<:(= W
CL T L L
T - Q)~ C) C) ~ T U.-I rl ~ :::J)
rl f--- .-I 01 (Y) rl
Project t 8pical T est section
All lifts AC--10F excep-r PMSC
C 470 between US 285 a nd I 70 New Construction
RUTIING - TEST SECTION
0.9r---------------------------------------------------------~
0.8r---------------------------------------------------------~
0.7r---------------------------------------------------------~
0.6r---------------------------------------------------------~
0.5r---------------------------------------------------------~
0.4r---------------------------------------------------------~
0.3r-----------------------------------------------~
0.2r---------~------------------------__+
0.1 1------1\
PL/LWP PL/RWP DL/LWP DL/RWP
*" LANE / WHEEL PATH
~ 6/27/89 ~ 6/1/90 ~ 5/9/91
C 470 between US 285 a nd I 70 New Construction
RUTIING - TEST SECTION
0.9 r---------------------------------------------------------~
0.8r---------------------------------------------------------~
0.71----------------------------------------------------------~
0.6 I----------------------------------------------------------~
0.51----------------------------------------------------------~
0.4r---------------------------------------------------------~
0.3 r-----------------------------------------------4
0.2r-----------------------------------__¥.
0.1 r-----4-
PL/LWP PL/RWP DL/LWP DL/RWP
*" LANE / WHEEL PATH
~ 6/27/89 ~ 6/1/90 ~ 5/9/91 ~ 6/27/89 -- first spring evaluation
following construction E-5
+-' a> (l) 4-
l0-
CI) (l) c
+-' (l) (l) 4-
l-eo (l) c
C470 Between US285 & 170 Cracking Data Test Section - Westbound Lanes
1000
800
600
400
200
o transverse
~ 6/89 post-constr
longitudinal
~ 6/90 post-constr
New Construction
6/89 -- first spring evaluation following construction
No cracking to date in test section
C470 Between US285 & 170 Cracking Data Control Section - Westbound Lanes
1000
800
600
400
200
0 transverse
E?ia 6/89 posi:-CO'lstr
New Construction
~ 6/90 post-constr
longitudinal
~ 5/91 posi:-consi:r
6/89 __ first spring evaluation following construction
E-6
C 470 BETWEEN US 285 AND I 70 New Construction
DEFLECTION B6.SIN - TEST SECTION 0
10 ,J:1
20
" :30 !!!.
---::: ~
~ ~ --~ ..... ·40 Q S. (/) 50 z 0 F
60 8 ~ ...... w.
70 0.
BO
90
100 o 2
* DISTANCE FROM LOAD Cft)
o 10/BB + 6/B9 ~ 6/90 6. 5/91
C 470 BETWEEN US 285 AND I 70 New Construction
DEFLECTION BASIN - CONTROL SECTION 0
10
""""'" 20
-" :30 !!!. ~ ~ ~ ..... 4·0 Q S. (/) 50 z 0 F
·60 8 ~ ...... w.
70 0. .
BD
90
100 o 2
#: o 10/BB
DISTANCE FROM LOAD Cft)
+ 6/B9 ~ 6/90 6. 5/91
E-7 ~lO/88 -- evaluation immediately
following construction
APPENDIX F
Project Information
US 6, West of Holyoke
F-l
US 6, West of Holyoke
Paving on Project No. FR 006-3(80) began on July 19,
1988. This project is located on SH 6 in Phillips County.
Work started on the east end of the project by paving west
in the westbound lanes. The project was nine miles long
and ran between Paoli and Holyoke. The project plans
called for 1/2 inch leveling course, 1-1/4 inches HBP and
3/4 inches rubberized PMSC Type A throughout the project
except for the 750 foot control section which did not
include the PMSC. On this section the HBP was increased
by 3/4 inch to compensate for not having a PMSC.
since the theory behind the high stability design was
to increase the stability in the lower lift, "the AC
content in the lower lifts was reduced. Typically the old
mix design would have had a higher AC content than the new
high stability design. In the design stage the AC content
for the control section was 5.9±0.3%, the AC content for
the test section was 5.8±0.3%. However the 5.9% was
adjusted to 5.7% after applying an environmental factor.
This factor was based on traffic, altitude, and the time
of year the paving is taking place. The AC content was
reduced to prevent bleeding during paving. This factor is
not applied in the new high stability design. Even though
this project did not meet the typical design criteria for
this study it is still representative of the old design
mix and the new high stability design mix.
The existing rutting on this project before paving
was very high. Rutting in the right wheel path averaged
over 1/2 inch, and in some places it was over an inch.
The leveling course was placed which removed the majority
of the ruts before the paving began.
F-2
The rolling pattern for this project began with the
steel roller. The steel roller made two to three passes,
and was followed by one pass with the rubber tire roller
and one pass with the finishing roller.
There was no significant construction problems noted
during construction.
F-3
Rut Resistant Composite Pavement US 6 west of Holyoke
~ End Test Section
600'
~ MP 452.5 Begin Test Section New Design Mix
I--MP 453
228'
~~-----4-~----Begin New Design Mix
I-- End Control Section
u U)
::::: c...<
ell ~ -t"j
c... c::l
== = ~ -,....; ,....;
Test
c... c::l
= ~ -,....; ,....;
c... b() c:: ~ =: 'M
..-1 - ell N > _ell ,....; ,....;
Section
c... b()
c::l ~ =:'M
..-1 ell
N > -ell ,....; ..-1
Control Section
600'
r---Begin Control Section Old Design Mix
176'
,,~-- Bridcre
~F-4 b
US 6 west of HOLYOKE RUTTIN G - TEST SECTION
0.9
0.8
r.... 0.7 (/)
~ ..c 0 c 0.6 ;;:;-
~ 0.5 w
2 ~
~ ~
Q w
~ 0.4
w ~ 0.3
0.2
0.1
0
f--
8 ~ X
~ ~ ~ v
g ~~ ~ ~ ~~~ V '7 T
~ ~ ~ v M ~Vf--
~ ~~~ ~ ~ '/ W8/RWP W8/LWP E8/LWP E8/RWP
No pre-construction data available for ~ ;i.<.... LANE / WHEEL PATH . ~ ~~ eastbound direct~on
~ 5/12/88 ~ 8/2/88 ~ 6/8/88 5Qa 11/21/88 rs:sJ 6/12/90 rzZJ 6/27/91
~~ 8/2/88 -- evaluation immediately following construction
US 6 west of HOLYOKE RUTTING - CONTROL SECTION
0.9
0.8
r.... 0.7 (/)
~ ..c 0 c 0.6 ;;:;-
~ 0.5 w Q
w <:) 0.4 ~ w ~ 0.3
0.2
0.1
0
~ :x
f-- ~ ~
~At:=V ~ ~ v ~
~ ~~t\~ ~ ~ ~ ~ ~ ~ ~ ~X~/ ~ / W8/RWP W8/LWP E8/LWP E8/RWP
* *'1{ LANE / WHEEL PATH
~ 5/12/88 ~ 8/2/88 ~ 6/8/89 5Qa 11/21/89 rs:sJ 6/12/90 rzZJ 6/27/91
No pre-construction data available 1t" 5/12/88 -- Pre-construction
F-5 for eastbound direction evaluation
+-' ill ill 4-
'"-(\) ill C
+-' ill ill 4-
'"-(\) ill C
1500
1200
900
600
300
us 6 West of Holyoke Cracking Data Test Section
transverse transverse longitudinal longitudinal
I82Ql 5/88 ~ 6/89 ~ 6/90 E2ZJ 6/91 pre-constr post-const post-canst post-const
Pre-construction block cracking -- 1330 sq ft
US 6 West of Holyoke Cracking Data Control Section
1500 ~----------------------------------------~
1200 ~--------------------------------------~
900 ~1"V>< X x x?4-~~~~~~~~----------l
~ >< I 600 t----t'V'./'_ KX:X>(XX:><I
o tansverse transverse longitudinal longitudinal
~ 6/88 ~ 6/89 ~ 6/90 I2Zd 6/91 pre-constr post-const post-canst post-const
Pre-construction block cracking -- 4677 sq ft
F-6
0
10
20
30
40 r-. !!1. E 50
..- 60 0
8- 70 I/) z 80 0 F
90 hl ....1 lL.. 100 W Cl.
110
120
130
140
150
0
10
20
30
40 r-. !!1.
50 E ..- 60 Q 8- 70 I/) z 80 0 F
90 hl ....1 lL.. 100 W' Cl.
110
120
130
140
150
US 6 WEST OF HOLYOKE DEFLECTION E!A.SIN - TEST SECTION
-1=1
~ .......--5
------~ 7~
77 //
/# / ~§ /~
r/~/ v/ /'
o 3 4 2
DISTANCE FROM LOAD (ft) .if
5/88 --Pre-construction evaluation
* 0 5/88 + 8/88 <> 6/89 A 6/90 x 6/91
US 6 WEST OF HOLYOKE DEFLECTION BASIN - CONTROL SECTION
~.
~ ~
~~~ ~~
// ~
~/ ~// ~/ ~ ~
o 2 3 4 :eli-
~i' DISTANCE FROM LOAD (ft) 8/88 -- evaluation i=ediately
o 5/88 + 8/88 <> 6/89 A 6/90 X 6/91 following construction
F-7
APPENDIX G
Project Information
SH 125, Near willow Creek Pass
SH 125, Near willow Creek Pass
Paving on Project No. CX53-0125-04 began on July 25,
1988. The project originally began at M.P. 0.00 at the
junction of US 40 and SH 125 and continued on SH 125 to
M.P. 21.5. Before construction began the project was
extended to M.P. 33.5.
The control section was located between M.P. 0.00 and
M.P. 0.25 in both the northbound and southbound
directions. This section consisted of 2-1/4 inches of HBP
with no PMSC. The design mix AC content in this section
was 6.4±0.3%. The sample that was tested in this section
had a 6.21% AC content. During construction a 600 foot
section was established on this section in the southbound
lane to be used for further evaluations. This section
began approximately 300 feet north of M.P. 0.00.
On the remainder of the project 1-3/4 inches of HBP
was placed, covered by 3/4 inches of rubberized PMSC Type
B. The design AC content for this HBP portion of the
project was 5.4±0.3%. The sample taken during
construction had a AC content of 5.49%. A 600 foot test
section was set up in the southbound lane for evaluation
purposes. This section is located approximately 1200 feet
south of M.P. 1.00.
The plant was located just south of Rand. It was
approximately 32 miles north of M.P. 0.00. The plant
produced an average of 2500 tons per day. sixteen trucks
were in operation during the paving of the test sections.
The mix left the plant at a temperature of 285 0 F and was
placed on the site at temperature of 260oF.
The rolling process began with one pass by the
vibratory roller, followed by three passes with the. rubber
tire roller and finished with one pass with the steel
wheeled roller.
G-2
Except for the weather no delays were encountered.
During the post-construction evaluation it was
noticed that the texture of the PMSC changed as the
distance from the plant increased. The surface texture
was not as uniform and the there was more segregation in
the PMSC furthest from the plant. The longer haul and
because the PMSC was placed late in the season allowing
the mix time to cool the paver was unable to mix the PMSC
as thoroughly as it should have been.
Typically the difference in the AC content between
the control and test sections on each selected project has
been only a couple tenths of a percent; however, this
project had a difference of 1% between the control and
test sections.
paving on this project was completed on October 22,
1988.
Because of the distinct difference in the AC content
between the control and test mix designs this project is
considered a good choice for evaluating the two different
pavement designs.
G-3
Rut Resistant Composite Pavement SH 125 Willow Creek Pass
MP 1 ----
Begin Test Section
End Test Section
Moisture 77' Probes
\
New Design Mix from approximately MP 0.2 North
Begin Control Section
Moisture Probes
End Control Section
to Willow Creek Pass
30 ' SO'
300'
G-4
#1120 Test Section
c.. c:l .....
N ,.:..l ......
H Nc;i
Control Section
Old Design Mix from US 40 north to
approximately MP 0.2
Fill
SH 125 WILLOW CREEK PASS RUTTIN G - TEST SECTION
0.9
0.8
'" 0.7 (II ~ z U l:: 0.6 ;::;.
~ O.S ILl a ILl
~ 0.4-
ILl
~ 0.3
0.2
0.1
0
~
m ,.....,...., ~ N8/RWP N8/LWP S8/LWP S8/RWP
*- i<~ LANE / WHEEL PATH No pre-evaluation data available
~ 6/2/88 ~ 6/1/89 ~ 7/16/90 r2:SZ1S/21/91 for southbound direction
X 6/2/88 -- Pre-construction evaluation
SH 125 WILLOW CREEK PASS RUTTING - CONTROL SECTION
0.9
0.8
'" 0.7 (II ~ Z Q l:: 0.6 ;::;.
~ O.S ILl a ILl
~ 0.4-
ILl
~ 0.3
0.2
0.1
0
~
W
~ m N8/RWP N8!LWP S8/LWP S8/RWP
"j(. f). LANE / WHEEL PATH
~ 6/2/88 ~ 6/1/89 ~ 7/16/90 r2:SZ1S/21/91 j~
6/1/89 -- First evaluation
following construction G-5
L (tS (]) c
+-' (]) (]) 4-
SH 125 near Willow Creek Pass Crack Data Test Section
1500
1200 r-----------------------------------------~
900 r---------------------------------------~
600 r-----------------------------------------~
300 '/'///////////////////////-0
o xxx xxx
transverse
~ 6/89 post-constr
188m 7/90 post-constr
longitudinal
~ 5/91 post-constr
, No pre-construction data available for test section
SH 125 near Willow Creek Pass Crack Data Control Section
1500 ~----------------------------------------~
1200 r-----------------------------------------~
900 r-----------------------------------------~
600 r-----------------------------------------~
transverse transverse longitudinal longitudinal
~ 6/88 ~ 6/89 ~ 7/90 IZZl 5/91 p-e-constr post-const post-const post-canst
Pre-construction block cracking -- 60 sq ft
Pre-construction patching -- 142 sq ft G-6
0
10
20
30
40 ,,-... $1.
50 ~ .- 60 0
S 70 I/) z 80 0 F 90 S ....J. u... 100 w c..
110
120
130
140
150
0
10
20
30
40 ,,-... $1.
50 ~ .- 60 0
S 70 I/) z ··80 0 F 90 S ....J. u... 100 w c..
110
·120
130
140
150
SH 125 - WILLOW CREEK PASS DEFLECTION ~SIN - TEST SECTION
0 2 3 4
*'" DISTANCE FROM LOAD (ft) .» 6/88 -- Pre-construction evaluation
* 0 6/88 + 11/88 <> 6/89 t.. 7/90 X 6/91
SH 125 - WILLOW CREEK PASS DEFLECTION BASIN - CONTROL SECTION
~
~ ~
~ ~
--------~ ~ ~ L:J
o
~~
o 11/88
2
DISTANCE FROM LOAD (ft)
+ 6/89 <> 7/90
G-7
3
t.. 6/91
4 A.*-11/88 -- evaluation immediately
following construction
No pre-evaluation dynaflect data
available for the control section
APPENDIX H
Project Information
I-70, East of Agate
H-l
1-70, East of Agate
A site on 1-70 between Agate and Cedar Point was
added to the rut-resistant composite pavement study in
August 1989. This site is located in the eastbound
driving lanes and extends for 5.38 miles, between M.P.
343.26 to M.P. 348.64.
This site is unique from all the other evaluation
sites in that this project (CX1R 34-0070-03) is a
rehabilitation of the previously reconstructed rut
resistant composite pavement project (1R 70-4(118)) which
was completed in the summer of 1988.
Project No. 1R70-4(118) consisted of covering the
existing concrete pavement with one to three feet of R 70
material before placing full depth asphalt. The
contractor used locally available material (sugar sand)
for the borrow source. The full depth paving consisted of
four lifts (3/4 inches rubberized PMSC Type B wearing
surface, over 1-1/2 inches, 1-1/2 inches, and 2-3/4 inches
RBP Grading C.) The design criteria for the AC in the
PMSC was 6.0% and for the RBP Grading C it was 5.3±0.3%.
The paving was completed on July 7, 1988.
The gradation criteria for a Grading C is as follows:
Sieve Designation
3/4" 1/2" 3/8" #4 #8 #50 #200
Percent by Weight Passing Square Mesh Sieves
R-2
100 70-95 60-88 44-72 30-58
7-27 3-12
within eight months of the completion date the
pavement began showing signs of failure. The driving lane
began to rut and shove severely requiring emergency
action.
From the evaluations performed on the distressed
pavement it was determined moisture was getting into the
RBP layer directly below the PMSC and caused stripping.
Once the AC was stripped from the aggregate the pavement
began to rut. The PMSC appeared to be sealing the
moisture in and the action of traffic worked the water
into the lower lifts.
Due to the short notice for including this project in
the RRCP study a pre-evaluation was not performed in the
two sections in·the eastbound direction.
The evaluation section in the westbound direction had
already been established under a large aggregate study.
The pre-evaluation was performed on this section on May
19, 1989. This pre~evaluation included crack mapping, rut
depth measurements, deflection measurements and visual
observations. Cracking was minimal. There was 308 linear
feet of transverse cracking and only 38 linear feet of
longitudinal cracking in the 600 foot evaluation section.
Rutting in this section averaged 0.3 inches in the right
wheel path and 0.2 inches in the left wheel path of the
driving lane. The highest measurement being 7.5 tenths of
an inch and located 400 feet into the evaluation section
in the right wheel path of the driving lane.
The test section (with PMSC) in the eastbound
direction is located between M.P. 347.30 and M.P. 347.41
(600 feet). The control section (without PMSC) in the
R-3
eastbound direction is located between M.P. 347.50 and
M.P. 347.61 (600 feet). The test section in the westbound
direction is located between M.P. 347.75 and M.P. 347.64
(600 feet).
construction Eastbound Lanes
To repair the damaged roadway the pavement was milled
26 feet wide to an average depth between 2-1/2 inches and
2-3/4 inches the entire length of the project. The 26
foot width of milling consisted of the two 12 foot driving
lanes and two feet into the outside shoulder.
The milled .section was inlaid with Grading C
rubberized. A 1-1/2 inch Grading C rubberized lift was
placed on the top of the entire roadway. The design AC
content for the Grading C was established at 5.5%±0.3%.
During construction two 600 foot sections were
established for evaluation. One section was set-up with
PMSC. The other section was established in the Grading C
section just east of the PMSC section. In addition to
these sections a third 600 foot section was established in
the westbound driving lane. The eastbound driving lanes
were rehabilitated under a contract modification order
established for the westbound project.
The milling began on Friday, August 4, 1989. On this
day 1900 tons of material were removed. On Monday, August
7, 1989, the contractor began using two milling machines
in tandem and doubled his production. The milling took
approximately three days.
The milled material from the driving lane was placed
in a windrow on the outside shoulder. This material was
later used to shoulder up. The material from the passing
lane was salvaged by state maintenance forces and
stockpiled at the east end of the job.
H-4
Due to difficulty in visually inspecting the roadway
during the milling operation some sections were not milled
deep enough to remove all the loose material.
Following the milling operations two brooms (one
rotary and one pick-up) were used in conjunction with a
small loader to clean the surface.
Each day the milled section was inlaid with Grading C
rubberized mix in order to open the roadway to traffic by
the end of the day. Once the inlay was completed the
entire project was covered with 1-1/2 inches of rubberized
Grading C. A 1000 foot section on the east end of the job
was covered with a 3/4 inch rubberized PMSC Type B in
addition to the milling and the 1-1/2 inch lift. The
design AC'criteria for the rubberized PMSC Type B was
established at 6.2%.
The top mat was paved in three passes beginning with
the inside shoulder and passing lane (16 foot), driving
lane (12 foot), and the outside shoulder (10 foot).
The drum-dryer plant was used and located at Cedar
Point which was at the easterly end of the project.
During paving there were no problems obtaining
density.
Construction Westbound Lanes
The plan typical section for the westbound lanes
consisted of 1-1/2 inches HBP Grading C without rubber in
the bottom lift. The middle lift contained 1-3/4 inches
HBP Grading C with rubber. The top layer consisted of 3/4
inches rubberized PMSC Type B. The mix design criteria
for the westbound lanes was the same as in the eastbound
lanes. A evaluation section was established for this
study in the driving lane as shown on the site map.
H-S
The PMSC sections in both the east and westbound
lanes were milled and replaced with Grading C in the fall
1990 because they were beginning to show signs of failure.
The evaluation at this location was discontinued.
H-6
·3/4" PMSC Type B
~ ~<1> 1 3/4" HEP Gr C <1> Ul Ul rt with Rubber rt eTC/) o <1> C () 1 1/2" HI3P Gr C ::I rt p., 1-'- without Rubber 0
::I
• I n 1 1/2" HBP Gr C 0 tTl::l
::r: III rt Ul 'i I rt 0
-....) eTl--' 2 174" HBP Gr C 0 c C/) ::I <1> p.,()
rt 1-'-0 ::I
~ C
tTl <1> III Ul Ul rt rt eTC/) C o <1> C () ::I rt p., 1-'-
0 ::I
C/)~ <1> <1> () Ul rtrt
3': 1-'-'"CI 0
::I U-l .j::.. -....j
0\ .j::..
I~ 0\ 0 0
-
1- g ~I F~·I· g ---I '"CI 3': - 0-----'
'"CI 3': -=<: tJ:) '"CI 3':
U-l U-l .j::.. .j::.. -....j -....j
U-l .j::..
C/)n I--' <1> 0 () ::I rtrt 1-'- 'i o 0 ::I I--'
1-'_ <1> '"CI U-l U-l
rt OQ ::r 1-':::J
i!1--' C/)o no
o
(J:l <1> () rt 1-'-o ::I
.j::.. -....j
(Jl
0
.j::.. -....j
0\ C/)~ I--' <1> <1> () Ul rtrt 1-'-0 ::I
3': '"CI
v~ .j::.. -....j
-....j (Jl
~I
2' rt
::0 <1> Ul
HI-'I Ul
-....jrt o III
::I <1> rt III Ul n rt 0
S 0>-:1 t-nO
Ul >- 1-'
OQ rt III <1> rt <1> '"CI
III < <1> S <1> ::I rt
0.9
0.8
~ 0.7 J: 0 z 0.6 .;:;;
J: Ii: 0.5 w a w 0.4 ~ 5 ~ 0.3
0.2
0.1
0
0.9
0.8
/"'. 0.7 '" 'II J::. ~ s::: 0.6 .;:;;
~ 0.5 w a w
~ 0.4
w ~ 0.3
0.2
0.1
0
70 east of AGATE RUTIIN G - TEST SECTION
~ ~ PLjLWP PLjRWP DLjLWP
"* LANE / WHEEL PATH
~ 9/19/89 ~ 5/17/90
I 70 east of AGATE RUTIING - CONTROL SECTION E8
~ PLjLWP PLjRWP DLjLWP
~ DLjRWP
No pre-construction rutting data available
~9/89 -- evaluation immediately
following construction
~ DLjRWP
* LANE / WHEEL PATH No pre-construction rutting data available ~ 9/19/89 ~ 5/17/90
H-8
I 70 east of AGATE RUTTING - CONTROL SECTION W8
0.9
0.8
-'"' 0.7 'II ~ ~ u s::: 0.6 Q
~ 0.5 w n w
~ 0.4
w ~ 0.3
0.2
0.1
0
~ r~ ~. 1 , I~
m rr77"71
[ ~I ~ Ii ~ PL/L'A'P PL/RWP DL/LWP DL/RWP
lJI.NE / WHEEL PATH
~ 5/19/89 ~ 9/19/89 ~ 5/17/90
5/19/89 -- Pre-construction evaluation
9/19/89 -- first evaluation following construction
H-9
1000
800 +-' ill ill 600 4-
L
ro 400 ill C
200
0
.;-~
1000
800 +-' ill ill 600 4-
"-ro 400 ill c
200
0
::t ~
1-70 East of Agate Cracking Data Test Section - Eastbound Lanes
transverse
9/89 post-constr ,
longitudinal
~ 5/90 post-constr
9/89 -- evaluation immediately following construction
No pre-construction cracking data available
1-70 East of Agate Cracking Data Control Section - Eastbound Lanes
transverse
9/89 post-COlstr
H-10
longitudinal
~ 5/90 post-constr
No pre-construction cracking data available
+-' (]) (]) 4-
l0-rn (]) c
1000
800
600
400
200
0
1-70 East of Agate Cracking Data Control Section - Westbound Lanes
mm transverse
~ 9/89 post-constr
longitudinal
~ 5/90 post-constr
No pre-construction cracking data available for the Agate location.
9/89 -- evaluation immediately following construction
H-ll
0
10
20
"...." 30 .!l?. E ..- 40 Q S. (I) 50 z 0 F 60 S ...J. IJ... l.aJ.
70 Q
80
90
100
0
10
20
"...." 30 .!l?. E ..- 40 q, S. (I) 50 z 0 F ·60 S ...J. IJ... l.aJ.
70 Q
.
·80
90
100
I 70 East of AGATE DEFLfCTION BASIN - EB TEST SECTION
A-
~ ~
/7 ~/
~~ ~
o 2
DISTANCE FROM LOAO (ft)
*' CI 9/89 + 5/90
I 70 East of AGATE
3
No pre-construction deflection data .. 9/89 -- evaluation immediately
following construction
DEFLECTION BASIN - EB CONTROL SECTION
----+-
~ ~ ~
// ~/ / o 2
DISTANCE FROM LOAD (ft)
CI '*9/89 + 5/90
H-12
3
No pre-construction deflection data
a
10
20
,....... 30 .!!? E ..-- 4-0 0
8-II) 50 z 0 F 60 fa ....J. L1.. u..L
70 Cl ~
80
90
100 a
I 70 East of AGATE DEFLECTION ~SIN - WB CONTROL SECTION
~
~ ~~
// // /'
2
DISTANCE FROM LOAD Cft)
[J 9/89 + 5/90
3
No pre-construction dynaflect data available
9/89 -- evaluation immediately following construction
H-13
APPENDIX I
Project Information
US 50, East of Rocky Ford
I-I
US 50, East of Rocky Ford
construction on US 50 Project No. CX(5) 09-0050-12
just east of Rocky Ford began on August 15, 1988. This
project began by heater-scarifying the top 3/4 11 to 111 of
the existing pavement on the driving and passing lanes in
both directions throughout the entire project.
The plans called for an application of 0.10 gallon
per square yard of an asphalt rejuvenator to be applied to
the heater scarified material. This amount was varied
throughout the job after the pavement showed signs of
flushing under traffic.
Following the heater scarifying process the pavement
was rolled with both the rubber tire and steel-wheeled
roller. within a couple of hours after rolling traffic
was permitted on the pavement.
Paving began in the eastbound lanes on August 25,
1988. It was done in three passes, a 16 foot, a 12 foot
and 10 foot pass, respectively, beginning with the inside
shoulder and passing lane.
The heater scarifying process continued in the
westbound lane when the paving began in the eastbound
lane.
The batch plant which was located at the Valco pit
approximately five miles from the west end of the project
produced 2000 tons a day and approximately 200 tons were
placed per hour. On the first day of paving six trucks
were in operation and little time was spent waiting on
mix. Paving began at 7:30 AM on the first day and at noon
the air temperature was in the low 90's.
The mix left the plant at 3000 F and was placed at an
average temperature of 270oF.
1-2
This project was extended 0.6 of a mile on the west
end and 0.7 of a mile on the east end. The 0.7 of a mile
on the east end was heater scarified and a 3/4" rubberized
PMSC Type B was placed to complete this section.
The depth of the lifts varied in different sections
of the project. The HBP (Gr EX) extension at the west end
was placed at a depth of 1. 5" with a 3/4" rubberized PMSC
Type B. Beginning at M.P. 370.00 to M.P. 370.19
approximately 1000 feet was designated as the control
section for this project. During the post-evaluation a
600 foot section was established in this section to be
used for the remainder of the evaluations. This section
was overlaid with 2.0 inches of HBP and was not covered
with a PMSC. The oil content in this section was to be
6.1±0.3%. Samples were taken and were sent to the lab to
determine the exact AC content. The test section used for
comparison on this project was located between M.P. 371.00
and M.P. 371.19 in the eastbound lanes. This section was
covered with a 1.5 inch HBP (Gr EX) and a 3/4 inch
rubberized PMSC .Type B. The design oil content in this
section was 6.0±0.3%.
The rolling pattern throughout the project was
different than the method usually used. A rubber tire
roller followed immediately behind the paver. It made six
to eight passes on each section of the pavement. The
steel-wheeled roller made two passes up and back with the
vibratory and one pass with the static roller after the
rubber tire completed its passes.
The job was delayed several days during the placement
of the PMSC due to the weather. The paving portion of the
job was completed on October 15, 1988.
1-3
This site is also a site for the polymerized
(rubberized) pavement study (file number 13.04). The
section used for this study sUbstituted AC-20R for AC-20
in the lower lift. A common section is used both as a
control for the polymer study and a test section for the
RRCP study.
I-4
MP 370.04
Control Section
Moisture Probes
MP 370.15
MP 370.23
Test Section Asphalt Modifier
(AC20R)
MP 370.34
MP 371. 00 600' Test Section for High Stability Design
Moisture Probes
MP 371.11
Rut Resistant Composite Pavement US 50 east of Rocky Ford
I
I f I 253'
1 I
I ... 40'
it- I i I
307' I l I
I
I
I . I
,
I
I
i
I
I
600' I
I
1 I
I
I
t I 300' 'I I
... I 40' • I
i I 260'
I
I
I
I
1-5
t;.I)
>< c CL UJ t;.I) • .-;
u ::: c >-. 22 - ;.... .'-; 4-..:.. c..:J -1->.'-; CL c:l = c;j ;....
N 0:: C1l :e C1l ........ c :=: u
"<t -N en ........ I"")
"..... 0 ~
.s::. t)
t: ;:;-
~ ILl Q
ILl
~ ILl
~
"..... 0 ~
.s::. t)
t: ;:;-
~ ILl Q
ILl
~ ILl
~
US 50 east of ROCKY FORD RUTTIN G - TEST SECTION
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
& r;r-
~ ~ ~ R5Ql I':l'7""1 / ..J7I
PLjLWP PLjRWP DLjLWP DLjRWP
"* *-!. LP.NE / WHEEL PATH ~ 5/10/88 ~ 11/3/88 ~ 5/4/89 tlC?(I9/6/89 rs:sJ 5/2/90 t:zZI 5/14/91
~5/l0/88 -- Pre-construction evaluation
US 50 east of ROCKY FORD No pre-construction data available
for passing lane R UTTIN G - CONTROL SECTION
0.9
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0
.& g
~ ~~ ~ PLjLWP PLjRWP DLjLWP DLjRWP * .-;t: LP.NE / WHEEL PATH
~ 5/10/88 ~ 11/3/88 ~ 5/4/89 tlC?(I9/6/89 rs:sJ 5/2/90 t:zZI 5/14/91
No pre-construction d?ta available for passing lane
1-6
~Jtl/3/88 -- evaluation immediately
following construction
1500
1200 +-' <l.l Q)
900 4-
L
ra 600 ill c
300
0
1500
1200 +-' (I) (I) 900 4-
l-
ra 600 (I) c
300
0
US 50 East of Rocky Ford Cracking Data Test Section
;;(- ;;(-X
t--- Xx Xx ////// x Xx ~ D<X>0C- )<l Xx ~ xxxxxx
transverse transverse longitudinal longitudinal
!22SI 5/88 ~ 5/89 ~ 5/90 r2Zl 5/9 i pre-constr post-const post-const post-const
Pre-construction block cracking -- 67 sq ft
US 50 East of Rocky Ford Cracking Data Control Section
y
~ x ~
x x x f/ / / / / /J
transverse transverse longitudinal longitudinal
~ 5/88 ~ 5/89 ~ 5/90 [22LJ 5/91 pre-constr post-const post-const post-const
Pre-construction block cracking -- 2400 sq ft
Pre-construction patching -- 3600 sq ft
I-7
0
10
20
30
40 ""' !!1.
50 E ..... 60 0 e 70 CI) Z 80 0 F
90 2 ....1 u... 100 w Cl
110
120
130
140
150
0
10
20
30
40 ""' !!1.
50 E ..... 60 0 e 70 CI) Z ···80 0 F 90 2 ....1 u... 100 w Cl
110
120
130
140
150
US 50 EAST OF ROCKY FORD DEFLECTION BASIN - TEST SECTION
~ ~ =----F"
o 2 3
*" ~* DISTANCE FROM LOAD Cft)
[J 5/88 + 11/88 ¢ 5/89 /:;. 5/90 X 5/91
US 50 EAST OF ROCKY FORD DEFLECTION BASIN - CONTROL SECTION
~ ~ ... ~
....=---./ ~
o
.If [J 5/88
2
DISTANCE FROM LOAD Cft) ff
+ 11/88 ¢ 5/89 /:;. 5/90
1-8
..;p-
3
x 5/91
..-&II
~
11/88 -- evaluation immediately
following construction
-""
Jt. 5/88 -- Pre-construction
evaluation
APPENDIX J
project Information
I-70, East of Debeque
J-l
I-70, East of Debegue
paving on Project No. IR 70-1(125) began on April 3,
1989. This project is located on Interstate 70 around the
Debeque interchange on the western slope. It begins at
M.P. 56.8 and extends for approximately 10.5 miles to M.P.
67.3. Originally paving was scheduled to begin in the
summer of 1988, however the paving was postponed until the
spring of 1989.
The plans called for 1-3/4 inches HBP Grading E in
the eastbound lanes with a 3/4 inch rubberized PMSC Type B
place on the top. The control section which was located
between Sta 950+00 in the eastbound direction, called for
2-1/2 inches HBP Grading E to be placed in one lift. This
control section which was set up by the district is
located a couple 100 feet east of where the Research
Branch did the pre-construction evaluation of the existing
pavement. The values obtained during the pre-construction
evaluation are considered to be representative of the
existing pavement for the control section set up by the
district. The remainder of the evaluation will be on the
control section set up by the district.
The minimum AC content for the test section was 5.3%,
with 4-6% voids. the minimum AC content for the control
was 5.5%, with 3-6% voids.
The 38 foot roadway was paved in two passes (outside
21 feet, inside 17 feet). The contractor arranged his
daily paving operations so that there was no exposed
longitudinal joints between the driving and passing lanes
at the end of the day.
The drum dryer plant was located off the frontage
road on the project. It operated from 8:00 A.M. to 4:00
P.M. five days a week and it produced between 2000 to 3000
tons a day. The mix was placed at 250 0 F.
J-2
The rolling pattern consisted of a vibratory steel
roller which made two passes over each section. The
rubber tire roller followed with two to three passes over
each section. The finishing roller completed the mat with
one vibrating pass and one static pass over each section.
There were no problems obtaining densities.
Due to a scheduling change in the paving,
permeability equipment was not able to be installed on
this project.
J-3
I
I 600'
600'
Rut Resistant Composite Pavement I-70 east of De8eque
MP 67.057
Control Section
MP 66.943
MP 64.109
Test Section
MP 63.995
J-4
l:Q
Q)
~ >. E-
U en :s 0-
: ~ ......... t'")
N ......... ,....,
N
UJ
!-< t.:J
o... == ~ ......... t.r:
,....,
r-.. (b
'II ~ U t:
;:;-
~ w Q w
i w ~
r-.. (b
'II ~ U t:
;:;-
~ w Q w
i w ~
70 east of DEBEQUE RUTTIN G - TEST SECTION
0.9
0.8
0.7
0.6
0.5
0.4-
0.3
:J'Q'
0.2
0.1
0
~ ~ ~g~c-ms~ ~
~ ~ ~ ~Q~ PL/LWP PL/RWP OL/LWP OL/RWP
... ~ LANE / WHEEL PATH
~ 5/19/88 ~ 8/29/89 ~ 6/4-/90 ~ 10/23/90 ISS) 5/6/91 No pre-construction data available
for passing lane ~
5/19/88 -- Pre-construction evaluation 70 east of DEBEQUE
RUTTING - CONTROL SECTION
0.9
0.8
0.7
0.6
0.5
0.4-
0.3
0.2
0.1
0
~ ~~ ~
~ ~~~Rc-~ ~ X~ .... """'"' ~ ~~ RS~~ V~ PL/LWP PL/RWP OL/LWP OL/RWP
¥ ** LANE / WHEEL PATH ~ 5/19/88 ~ 8/29/89 ~ 6/4-/90 ~ 10/23/90 ISS) 5/6/91
No pre-construction data available for passing lane
J-5
~/29/89 -- evaluation immediately
following construction
~
ro Q) c
1-70 East of DeBeque Cracking Data Test Section - Eastbound Lanes
1000 ,----------------------------------------,
800 r-----------------------------------------~ >< ~ 600 t-----------f>6<':><X> 'V"V'V 'V 'V X'
400r------------------~~~r_-------~
transverse transverse longitudinal longitudinal
~ 6/88 ~ 8/89 ~ 6/90 E7ZJ 5/91 r:;re-constr post-const post-canst post-const
Pre-construction block cracking -- 774 sq ft
1-70 East of DeBeque Cracking Data Control Section - Eastbound Lanes
1000 ~----------------------------------------~
800 ~-----------------~~~~--------~
600 r-----------------------~
transverse transverse longitudinal longitudinal
~ 6/88 m?J 8/89 ~ 6/90 rzza 5/91 pre-constr past-const post-const post-const
Pre-construction block cracking -- 220 sq ft
J-6
r.. !!!. E .... Q 9-II) z 0 F S ~ 4-ILl 0-
I 70 EAST OF DEBEOUE DEFLECTION BASIN - TEST SECTION
Or-------------------------------------------------------~
10r---------------------~::~~~~~
20 ~--------------------------~~~~--~------------------~
30 ~----------------~~~~~------------------------------~
4-0 ~----~~~~~--~~--------------------------------------~
50 ~------------~--------------------------------------------~
60 ~------~~------------------------------------------------~
70 ~--~~----------------------------------------------------~
80 ~----------------------------------------------------------~
90 ~----------------------------------------------------------~
100 ~~~----------~------------~------------~----------~--~
0
10
20
30
4-0
50
60
70
80
90
,100
o 2 3
-J,' DlSWCE FROM LOAD Cft)
D 5/88 + 8/89 ~ 6/90 A 5/91
I 70 EAST OF DEBEOUE DEFLECTION BASIN - CONTROL SECTION
4-
*'5/88 -- Pre-construction evaluation
** 8/89 -- evaluation immediately
following construction
A
~ ..lil
~ :.--: ~ ~~~
::-~~ ~/ /
o
D
2
*" DIST#tCE FROM LOAD Cft)
5/88 + 8/89 ~ 6/90
J-7
3
A 5/91
4-
* '1 t' 5/88 -- Pre-construct~on eva ua ~on
APPENDIX K
project Information
US 40, East of Hayden
K-l
US 40, East of Hayden
Paving on Project No. PR 040-2(30) began on July 6,
1989. This project is located on US 40 just east of
Hayden. It begins at M.P. 108.1 and extends in the
easterly direction approximately 8 miles to M.P. 116.3.
Construction consisted of widening the 11 foot
driving lanes to 12 feet and adding 6 foot shoulders.
This involved placing 4 inches of ABC (CI 6) covered with
1-1/2 inches of HBP on the shoulders to bring them up to
the existing roadway surface. A leveling course was
placed with a laydown machine throughout the project
except between Sta 0+00 to Sta 14+57. In this area the
overlay was placed directly on top of the old mat. A 1-
3/4 inch lift of HBP was placed in the section containing
the design mix used prior to July 1987. This included
approximately the first 2400 feet of the project. In the
high stability pavement section, 1 inch of HBP (Grading E)
was placed with a 3/4 inch rubberized PMSC Type B.
The 36 foot roadway was paved in two passes (17-1/2
foot pass eastbound lane, 18-1/2 foot pass westbound
lane). The contractor tried to arrange his daily
operation so that there were no exposed longitudinal
joints between the east and westbound lanes at the end of
the day. They were able to pave one-lane mile in each
direction per day.
The drum-dryer plant was located approximately seven
miles from the beginning of the job. The day these test
sections were paved the plant was started around 7:00 A.M.
and paving continued until 6:00 P.M .. Eight dump trucks
were used for hauling the asphalt. The placement
temperature ranged from 235 0 p to 270 0 P.
K-2
The rolling pattern consisted of one pass with the
roller in the vibratory mode and the second pass in the
static position.
behind the paver.
to eight passes.
not used.
The rolling was done as soon as possible
A rubber tire roller followed with six
On the HBP lift a finishing roller was
The minimum design ACcontent for the control was
5.5%, with 3-6% voids. The minimum design AC content for
the test section (high stability design) was 5.3% with
4-6% voids. During construction samples were taken in
both test sections and the control section.
A 3/4 inch rubberized PMSC Type B was placed over the
entire project except for the first 2400 feet. PMSC
paving began on July 19, 1989. The average placement
temperature was 295 0 F. The mix design called for 6.0±0.3%
AC in the mix.
K-3
Rut Resistant Composite Pavement to US 40 east of Hayden
S:;;~:::J \ V ~-------
\
Walker '" \ \ Ditch ~.
"Welcome to Hayden" sign at STA 23+80
Shelton\ Ditch
\~
5+25
End Test Section STA 34+50
600' Test Section
test section
STA 27+00
Control Section
16+50
-o
o
Glasgrid over R/R crossing at STA 15+25
Paraho Test Section
County Rd 183 Water valve 19' Rt of £ of US-40 ~ STA 0+00 ~lP 108.07
0 .. .... 'j <>
CIJ -'"' '" .. OG .... "' 0
to Hayden
\ 1 \ not drawn to scale
t 0-
== U ..... U"l :E 0- c:l 0-
~ c:l ......... t:.l Q) ..... ~ t"i "<t c..
!-< ......... >. = !-< ,....; c..:::; t"ic- .-i c..:::;
Paraho and Control Sections Test Section
K-4
'" 0 N • .-< ....
u OJ
CIJ
"0 OJ .... u ;::l
"' .... '" '" N 0 u
'" ..:
0.9
0.8
"..... 0.7 lh 'V ~ 0 s: 0.6 ;::;.
~ 0.5 w Q.
w
~ 0.4
w ~ 0.3
.0.2
0.1
0
0.9
0.8
"..... 0.7 lh 'V ~ 0 s: 0.6 ;::;.
~ 0.5 w Q.
w
~ 0.4
w ~ 0.3
0.2
0.1
0
US 40 east of HAYDEN RUTTING - TEST SECTION
~ I m ~ 9 ~~ ~ .. ~ ~ ~~
W8/RWP W8/LWP E8/LWP
¥ -'f* LANE / WHEEL PATH
~ ~
E8/RWP
"* 6/14/89 -- Pre-construction evaluation ~ 6/14/89 ~ 8/31/89 ~ 7/17/90 15Q(l5/21/91
US 40 east of HAYDEN RUTTING - CONTROL SECTION
, ""'"
m ~ ~ ~ ~ ~
~ m :6
I IS:
~ I ~ ~ ~ P;7?;I ~ ,..,....-,,-
W8/RWP W8/LWP E8/LWP E8/RWP
*" x* LANE / WHEEL PATH ~,. 8/31/89 -- evaluation immediately
~ 6/14/89 ~ 8/31/89 ~ 7/17/90 15Q(l5/21/91 following construction
K-5
+-' (]) OJ 4-
~
ill OJ c:
-+-' (l) (l) 4-
I-
m (l) c
1500
1200
900
600
300
0
US 40 East of Hayden Cracking Data Test Section
• I----
·XX x
>C :x :x :x x xx
transverse transverse longitudinal longitudinal
~ 6/89 ~ 8/89 ~ 6/90 EZZJ 5/91 p-e-constr post-const post-const post-const
Pre-construction block cracking -- 2200 sq ft
1500
1200
900
600
300
US 40 East of Hayden Cracking Data Control Section
transverse transverse longitudinal longitudinal
~ 6/89 ~ 8/89 ~ 6/90 rzza 5/91 pre-constr post-const post-const post-const
Pre-construction block cracking -- 3874 sq ft
K-6
US 40 EAST OF HAYDEN DEFLECTION BA.SIN - TEST SECTION
0
10
20
/"'. 30 .!!l E .- 40 0
B (/) 50 z 0 F
·60 fa .....l IL W
70 n
80
90
100 0 2 3 4
~
;;I: D~~NCE FROM LOAD 6/89 -- Pre-construction evaluation
0 6/89 + B/89 ~ 7/90 t.. 6/91
US 40 EAST OF HAYDEN DEFLECTION BASIN - CONTROL SECTION
0
10
20
/"'. 30 .!!l E .- 40 0
B (/) ·50 z 0 F
60 fa .....l IL W
70 n
80
90
. 100 0 2 3 4
*-DISTANCE FROM LOAD ~~89 -- evaluation immediately ~
0 6/B9 + 8/B9 ~ 7/90 t.. 6/91 following construction
K-7
APPENDIX L
Project Information
SH 172, South of Durango
L-1
SH 172, South of Durango
Paving on project No. SR 0172(12) began on July 17,
1989. This project begins at M.P. 24.5 and extends to the
south to M.P. 19.7. The original plans called for 1-1/4
inches of HBP Grading E with a 3/4 inch Type B PMSC for a
cover. The project included widening at various
locations. However, the test and control sections
established for this study did not include widening. The
pavement in the evaluation area consisted of two twelve
foot driving lanes with eight foot shoulders.
Initially, this project was designed requiring the
use of the high stability asphaltic mix in the lower layer
with a plant mixed seal coat for the top layer. However,
since that time, the design criteria for the asphalt
pavement was revised and the revisions were incorporated
into this project. These changes included raising the
asphalt content in the HBP layers to 5.9±0.3% and using
rubberized asphalt cement in the layer immediately below i
the PMSC pavement. The thirty-seven Hveem stability value
was retained, and the design voids were established at 3-
4 £,. o.
paving at the evaluation sections began on July 19,
1989. The plant was started up around 7:00 A.M. and
paving continued until 9:00 P.M .. The plant was located
approximately 5 miles west of the project. Hourly
production was 300 tons per hour but because of production
problems only 2600 tons were placed on July 17, 1989. On
July 19, nine belly dump trucks were in operation and made
one round trip per hour.
The original control section for this project was
established using an AC-10 at an asphalt content of
5.9+0.3%. The remainder of the project was to contain the
L-2
high stability mix with an AC content of 5.5±0.3%.
Because of the revisions, the 5.5% AC mix was deleted and
5.9% AC mix was used throughout the entire project. The
majority of the HBP in the southbound lanes contained
AC-10, but because of the design revisions, the northbound
lane was constructed using AC-20R.
During construction the control section in the
northbound lane was reduced from 1000 feet to 600 feet
(Sta 350+00 to Sta 356+00). This section contains 2-1/4
inches of HBP GR E AC-20R without PMSC. The test section
in the northbound lane was relocated during construction.
It is now located between Sta 357+00 and Sta 363+00. This
test section consisted of 1-1/2 inches HBP GR E AC-20R
with 3/4 inches rubberized PMSC.
Since the mix design in the southbound and northbound
lanes were different, a second 600 foot control section
(2-1/4 inches HBP GR E AC-10 without PMSC) was established
in the southbound lane opposite the control section in the
northbound lane.
Because of construction related problems effecting
performance evaluation~this site was dropped from this
study following construction.
L-3
rq ::r: OJ u Q , m
Rut Resistant Composite Pavement SH 172 South of Durango
AC-10 Control Section No PMSC
~ , -.... J:>:. ::r: OJ u Q , m
Control Section
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Q) I c
I C'U
D I c :J
I 0 ..0 .c I -<-' :J 0 I
(f)
I
I
I
I
L-4
Q) c CD
D C :J 0
.D .s '-0 Z
-, ST A 364+00
I Test Section
6001
AC-20R with PMSC
-t ST A 358+00
2001
-f
6001
AC-20R No PMSC
MP 19.7 -' ST A 350+00
n
w :r -< I:0
.)..'t: ~o
,>'
FIGURE 1
---T----·-·--··----··-··-··-··-·--i
e ),lUFFAl'
\,...~ ..
NEW
._._ ---____ ._... __ . w_. __
N
® A
~ .. @ @3
® LINCOLN
IS>
I
INGTUN
~~--, WIIA I" ..
\~AYI r YUM" i ®
lcoolII'j
~ !_. I
~i i i i 'i
~
I I: ..... _._.-.-.-.-._.- _._._._.j 1m
H
~l"_
i g--~ I : 1; :I:W:: f~! i ® !
-·-·-·-r-·---·J;;; "-;::':8--'---: i ~ ----.-,...""@
I SPRINCrlElD i ;"IIi!"'~ , i, [@ !
I--::r.:;:)=-rt., -;;:::;;:!@IJIIC'" 0: ® \ i """". I
"NIM"; @ ,..,
III -< III Z -< x
i : .--:':"'_ .. _~~ __ . __ ._ .. L.:. __ .. _ .. ___ .. _.----_ .. .1. .• -
RUT RESISTANT CrnlPOSITE PAVEMENT STUDY SITE LOCATION HAP
;';-::.
: OKLMIVM"
$
6
PHOTO 1
A paving operation
using windrow
placement.
PHOTO 2
steel-wheeled
roller used for
break down.
7
PHOTO 3
Pneumatic roller
was used prior to
firiish roller.
15
PHOTO 4
This photo shows
how stripping
progresses. The
core on the left
taken in 1990. The
core on the right
taken in 1991 at
the Debeque
evaluation site.
Note that the top
lift of PMSC is
undisturbed.
PHOTO 5
This photo shows an
extreme case of
stripping below the
PMSC. Both cores
were taken out of
C470 in 1990.
16
PHOTO 6
C470, US 285 to 1-70
The first sign of
the stripping
failure is the
appearance of rich
spots on the
surface. These
rich areas are
randomly spaced and
typically found in
the wheel paths.
PHOTO 7
C470, US 285 to 1-70
This photo shows
areas which have
stripped under the
PMSC. Evidence of
raveling in the
right wheel path is
a result of
extensive stripping
in the RRCP layer
below the PMSC.
17
PHOTO 8
C470, US 285 to 1-70
This type of
distress was found
throughout the
project.
PHOTO 9
This photo was
taken on 1-70, east
of Agate eight
months after
construction using
the RRCP design.
This type of
distress was
typical throughout
the project.
18
PHOTO 10
This is not the
high-stability
(RRCP) design.
This photo shows
stripping occurring
below the PMSC
however. The
portion stripping
is a Grading C.
This photo was
taken at the test
site on I70, east
of Agate. The
pavement had been
down one year.
FIGURE 2
Project/Environmental Information C470, Between Kipling and Wadsworth
District: 6 Project: IXFU 470-1(54) Location: C470, Between Kipling and Wadsworth
HEP Inforr:tation Grading: E % AC: 5. 1
P:'~SC In fO!::.1a tion Type: A.
* Lottmans: 104,90,102,126, 108,1131
100,114, 126,127/117
Design Traffic 1.0 year ES.AL's: 1,565,000
Environmental Infornation
Precipitation ttlche. ~~~--------~----------------------.
2~----------~~~--~--------~~~
t 1(1 11 12 1 2 :I 4 15 IS T IS i 10 11 12 1 2 :I 4 15 IS lui 8i I I<l I
TIme
Temperature F.hMlnheit
100 I eO~1 -------------4~------------~
~~~------~~~~~~~~-----&~~
o~.u~~~aJ~u.~~~~~JU~~~~
i ~ n : 1 Z :I ~ 5 S 7 S g ~ n ~ 1 : :I 4 S ~
I a8 I a~ I I<l
1"ime
* See Appendix A
Pro-;ect status High .. ·moisture, Low moisture susceptibility, moderate traffic
19
FIGURE 3
Project/Environmental Information C470, US285 to 1-70
District: 6 Project: IXFU 470-1(32) Location: C470, US285 to I-70
RBP Information Grading: E
PMSC Info~ation Type: A
% AC: 5.2% * Lott~ans: 111, 101, 88, 77, 56, 81, 68, 77, 98, 96, 88, 42, 74, 56
Design Traffic 10 year ESAL' s: 1 565 000 , ,
Environmental Information
Precipitation Inches 4r-----------~---------------------.
~~--------------~----------~~~~
• ~ n U 1 % ~ • 5 5 T 5 Q ~ n U 1 : ~ 455 I " I GIN I
TIme
Temperature Flh","l'Iifit
100 ,-, ---------------------------:
J!---------...-tl--------___ ~~I ~----~HH .. ~~----~~
o~~~~.u~u.~.u~~~~~ __ ~ __ Z ~. 4 5 e T S g 10 11 12 , 2 ~ 4 ~ S
I!~ I gO
Time
Project status
* See Append i x A
High .. moisture, high moisture susceptibility, moderate traffic
stripl?inq noticed in mid 1989 and increased in 1990.
20
FIGURE 4
Project/Environmental Information 1-70, East of Agate
District: 1 Project: IR 70-4(118) Location: I -70, East of Agate
RBP Information Grading: C % AC: 5.3%
PMSC Information Type: B
* Lottmans: 102, 80, 92, 78, 64
Design Traffic * See Appendix A 10 year ESAL's: 3,500,000
Environmental Information
Precipitation 31~n~Ch~es~ ____________________________ -.
811101112 88
23. 6 e T 8 all
TIme
Temperatur-e 100 ~F.~hre~n::.:h~ea~ __________________ 1
80
Project status
8111011 12 8S
23465 89
TIme
High moisture, moderate moisture susceptibility, high traffic
Failed in 7-89
21
"-,-~~
~
--1
..
B-4
c'--r""'i , \ ",--,"
<:'r"" ,_'L' '-----e-----e------
\./ -:.~ .~.-1 ,