2 0 1 9 - 2 0 21 W A T E R C O M M I S S I O N P R O J E C T B U D G E T
R U R A L W A T E R S U P P L YP U R P O S E F U N D I N G S U M M A R Y
Dakota Rural Water District – 2019 Expansion $461,250
McLean-Sheridan Rural Water District – 2019 Expansion $327,075
Northeast Regional Water District – Devils Lake Phase II $1,328,000
Stutsman Rural Water District – Phase 7 $1,812,000
South Central Regional Water District – North Burleigh WTP $920,000
TOTAL APPROVED $4,848,325
REMAINING BALANCE (JUNE 2019) $32,351,675
PURPOSE FUNDING TOTAL $37,200,000
ObligatedThis
Biennium
W A T E R S U P P L YP U R P O S E F U N D I N G S U M M A R Y
Mandan – Raw Water Intake $9,570,000
Bismarck – Lockport Water Pump Station $2,280,000
Mapleton – Storage Tank $840,000
Western Area Water Supply – Phase VI Pre-Construction $5,476,000
TOTAL APPROVED $18,166,000
REMAINING BALANCE (JUNE 2019) $109,834,000
PURPOSE FUNDING TOTAL $128,000,000
ObligatedThis
Biennium
2 0 1 9 - 2 0 21 W A T E R C O M M I S S I O N P R O J E C T B U D G E T
F L O O D C O N T R O LP U R P O S E F U N D I N G S U M M A R Y
Mouse River Flood Control $82,500,000
SE Cass WRD – Drain No. 40 $192,600
TOTAL APPROVED $82,692,600
REMAINING BALANCE (JUNE 2019) $113,307,400
PURPOSE FUNDING TOTAL $196,000,000
ObligatedThis
Biennium
2 0 1 9 - 2 0 21 W A T E R C O M M I S S I O N P R O J E C T B U D G E T
G E N E R A L W A T E R M A N A G E M E N TP U R P O S E F U N D I N G S U M M A R Y
Red River Basin Commission $200,000
Assiniboine River Basin Initiative $100,000
State Engineer Approvals $ --
Atmospheric Resource Operations and Research Grants $ 875,722
Aerial Imagery Project $790,000
TOTAL APPROVED $1,965,722
REMAINING BALANCE (JUNE 2019) $25,128,054
PURPOSE FUNDING TOTAL $27,093,776
ObligatedThis
Biennium
2 0 1 9 - 2 0 21 W A T E R C O M M I S S I O N P R O J E C T B U D G E T