Proposal to Change UES Measure Status
• Residential Weatherization Manufactured Home and Single Family– Measures:
• Attic, Floor, and Wall insulation, and Window retrofits• Infiltration Reduction
– Current Status: Active
• The Issue: Infiltration Reduction measures do not account for the increased mechanical ventilation requirements required by the measure.– Savings are too high, costs are too low.
• Staff Recommendation– Change measure status to “Under Review” – RTF staff to work with subcommittee to come up with a proposal to estimate
savings and costs.
Operations Subcommittee
• Met March 5• BPA “EE Utility Summit” May 8 & 9, Portland• February 14 Minutes• Pump VFD Subcommittee• UES Measure Review Status• RTUG Protocol• End Use Business Case Kickoff• Lighting Standard Protocol Kickoff• Statements of Work
Small/Rural Subcommittee
• Eugene Rosolie and Gillian Charles Co-leads • Met on 3/8• Initial focus on RTF-specific recommendations:– developing commercial school measures,– creating a measure design checklist to ensure small/rural
consideration in the measure and specification development,– test out a few small saver measures
• Next meeting will be late March/early April– Draft the design checklist– Review progress on school measures, small savers, and GSHP.
Upcoming Subcommittee Meetings• Standard Protocol for Pump VFD– 15 March 2012 9:00 am
• Measure Life Guidelines– Tuesday March 20, 10:30-12 noon– Wednesday March 28, 1-2:30 pm
• CVR Standard Protocol– Thursday March 22, 1 – 2:30
Website UpdatesMeasure Workbooks:
• Residential | Weatherization - Manufactured Home (changed to Active status)
• Residential | Heating/Cooling - Air Source Heat Pump Upgrades MH
• Residential | Heating/Cooling - Air Source Heat Pump Upgrades SF
• Residential | Heating/Cooling - PTCS Commissioning, Controls, & Sizing MH
• Residential | Heating/Cooling - PTCS Commissioning, Controls, & Sizing SF (all revised to allow new construction applications)
• Residential | DHW - HPWH (revised to include Tier 2 interior ducted applications)
Contracts Underway• Business Case for End Use Load Study– KEMA Underway– Kickoff Meeting, 5 March 2012– Other Contractors Providing In-Kind Help
• Lighting Standard Protocol– ERS Underway– Kickoff meeting 12 March 2012
Statements of Work
• Statements of work finishing
– ELCAP Data updated to modern database– 208 RTF End Use Load Shapes to 8,760– ProCost manual and updates– UES Measure Reviews – 41 Measures