rtf staff, subcommittee and work updates march 13, 2012

8
RTF Staff, Subcommittee and Work Updates March 13, 2012

Upload: oliver-goodwin

Post on 26-Dec-2015

215 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: RTF Staff, Subcommittee and Work Updates March 13, 2012

RTF Staff, Subcommittee and Work Updates

March 13, 2012

Page 2: RTF Staff, Subcommittee and Work Updates March 13, 2012

2

Proposal to Change UES Measure Status

• Residential Weatherization Manufactured Home and Single Family– Measures:

• Attic, Floor, and Wall insulation, and Window retrofits• Infiltration Reduction

– Current Status: Active

• The Issue: Infiltration Reduction measures do not account for the increased mechanical ventilation requirements required by the measure.– Savings are too high, costs are too low.

• Staff Recommendation– Change measure status to “Under Review” – RTF staff to work with subcommittee to come up with a proposal to estimate

savings and costs.

Page 3: RTF Staff, Subcommittee and Work Updates March 13, 2012

Operations Subcommittee

• Met March 5• BPA “EE Utility Summit” May 8 & 9, Portland• February 14 Minutes• Pump VFD Subcommittee• UES Measure Review Status• RTUG Protocol• End Use Business Case Kickoff• Lighting Standard Protocol Kickoff• Statements of Work

Page 4: RTF Staff, Subcommittee and Work Updates March 13, 2012

Small/Rural Subcommittee

• Eugene Rosolie and Gillian Charles Co-leads • Met on 3/8• Initial focus on RTF-specific recommendations:– developing commercial school measures,– creating a measure design checklist to ensure small/rural

consideration in the measure and specification development,– test out a few small saver measures

• Next meeting will be late March/early April– Draft the design checklist– Review progress on school measures, small savers, and GSHP.

Page 5: RTF Staff, Subcommittee and Work Updates March 13, 2012

Upcoming Subcommittee Meetings• Standard Protocol for Pump VFD– 15 March 2012 9:00 am

• Measure Life Guidelines– Tuesday March 20, 10:30-12 noon– Wednesday March 28, 1-2:30 pm

• CVR Standard Protocol– Thursday March 22, 1 – 2:30

Page 6: RTF Staff, Subcommittee and Work Updates March 13, 2012

Website UpdatesMeasure Workbooks:

• Residential | Weatherization - Manufactured Home (changed to Active status)

• Residential | Heating/Cooling - Air Source Heat Pump Upgrades MH

• Residential | Heating/Cooling - Air Source Heat Pump Upgrades SF

• Residential | Heating/Cooling - PTCS Commissioning, Controls, & Sizing MH

• Residential | Heating/Cooling - PTCS Commissioning, Controls, & Sizing SF (all revised to allow new construction applications)

• Residential | DHW - HPWH (revised to include Tier 2 interior ducted applications)

Page 7: RTF Staff, Subcommittee and Work Updates March 13, 2012

Contracts Underway• Business Case for End Use Load Study– KEMA Underway– Kickoff Meeting, 5 March 2012– Other Contractors Providing In-Kind Help

• Lighting Standard Protocol– ERS Underway– Kickoff meeting 12 March 2012

Page 8: RTF Staff, Subcommittee and Work Updates March 13, 2012

Statements of Work

• Statements of work finishing

– ELCAP Data updated to modern database– 208 RTF End Use Load Shapes to 8,760– ProCost manual and updates– UES Measure Reviews – 41 Measures